DESCRIPTION
E S C L E uropean Society of Construction Law Introduction The Microsoft Case (still pending) Conclusion of contract (Vista / Office 2007 / Support) Publication of direct award (after conclusion) OSS firms challenge the award Court: prohibition of any procurement which is not absolutely necessary Court later: prohibition reversed, but reservation of further measures
Citation preview
E S C LEuropean Society ofConstruction Law
How to challenge a public contract award – and what about damages?The Swiss regulations
www.unifr.ch/baurecht
Martin Beyeler
Dr. iur., Fürsprecher (Attorney-at-law / Zurich)
Institute for Swiss and International Construction LawUniversity of Freiburg Switzerland
E S C LEuropean Society ofConstruction Law
E S C LEuropean Society ofConstruction Law
Overview
1. Challenging Contract Awards under Swiss Lawa) Complaint procedureb) Court‘s decision
2. Challenging Contracts under Swiss Law?
3. Observation on the Cases
E S C LEuropean Society ofConstruction Law
IntroductionThe Microsoft Case (still pending)
• Conclusion of contract (Vista / Office 2007 / Support)
• Publication of direct award (after conclusion)
• OSS firms challenge the award
• Court: prohibition of any procurementwhich is not absolutely necessary
• Court later: prohibition reversed, butreservation of further measures
E S C LEuropean Society ofConstruction Law
Challenging Awards IThe Legal Framework
• EC Directives not applicable
• GPA / Bilateral Agreement
• GPA XX
• Provisional measures
• Annulment / Compensation
E S C LEuropean Society ofConstruction Law
Challenging Awards IIFrom the award to the contract
(AwardDecision)
AwardPublication 10 / 20 days Conclusion
of Contract Execution
E S C LEuropean Society ofConstruction Law
Standstill
Challenging Awards IIIAnnulment of Award
AwardPublication 10 / 20 days
Compla
int!
Provisionalmeasures?
No!
Conclusionof Contract
Annulmentof Award
Yes!
StandstillConfirmation
of Award
Standstill
E S C LEuropean Society ofConstruction Law
Challenging Awards IVDeclaration of unlawfulness
Provisionalmeasures?
No!
Conclusionof ContractStandstill Execution
Complaint founded?
Yes!
No!
Declaration ofunlawfulness
Action for damages
E S C LEuropean Society ofConstruction Law
Challenging Awards V„Effective Procedures“ (GPA XX:2)
• ‚Most important of all decisions‘
• Prognosis / Balance of interests
• Some courts write more, some less
• 70-90 % of all cases: no provisional measures
• No provisional measures: 95 % of withdrawals
effectiverelief
urgencyof conclusion
E S C LEuropean Society ofConstruction Law
Challenging Contracts?Different Situations
What if the contract is concluded ...
• ... too early (during standstill)?
• ... without an award publication?
• ... with wrong contents or terms?
• ... for a too long period?
• ... with the wrong partner?
E S C LEuropean Society ofConstruction Law
?Challenging Contracts?Various Solutions for one problem
• No consequences, no sanctions. – (No problem?)
• Per se-nullity or per se-ineffectiveness of contract.
• Contracting Authority is not entiteled to conclude.
• Courts can give orders with regard to the contract.
• Courts can annul the contract.
vs.
E S C LEuropean Society ofConstruction Law
Observations on Case 1The Floors
• Award to the cheapest tender: standardized goods?
• Two prices, but only one blank space: formalism.
• No surface indicated: bidder questions.
• Price confirmation by Tenderer 2: equal treatment?
• Loss-reduction commitment applies!
• No compensation for loss of profit!
E S C LEuropean Society ofConstruction Law
Observations on Case 2The Waterfront
• Rules on reservations
• Winter measures
• Always higher coststhan offered?
• If minor: legal award?
• If major: illegal award!
• (no loss of profit)
E S C LEuropean Society ofConstruction Law
Observations on Case 3The Carpets
• ‚Overall estimate of the tender‘
• Rules on forfeiture of reprovals
• Minor disregard of specifications
• Alternative tenders
• Too few employees?
• Complaint unfounded
E S C LEuropean Society ofConstruction Law
Observations on Case 4The Cleaning
• ‚Unreasonably low bid‘
• Rules on annulment
• Challenging an annulment
• Legal annulment
• Legal, but mala fide annulment: only damages
• Abusive annulment: correction (if possible)
E S C LEuropean Society ofConstruction Law
The End
Thank you very muchfor your attention!