E000000073.2621.Frost & Sullivan CII Karnataka Event WP

Embed Size (px)

Citation preview

  • 7/31/2019 E000000073.2621.Frost & Sullivan CII Karnataka Event WP

    1/33

    A Whitepaper by

  • 7/31/2019 E000000073.2621.Frost & Sullivan CII Karnataka Event WP

    2/33

    A Whitepaper by

    CONTENTS

    1. INDIA POWER SECTOR OVERVIEW - Page 3

    2. KARNATAKA POWER SECTOR SCENARIO Page 7

    3. CONVENTIONAL POWER GENERATION IN KARNATAKA Page 17

    4. RENEWABLE ENERYG DEVELOPMENT IN KARNATAKA Page 23

    5. POWER TRANSMISSION & DISTRIBUTION

    INFRASTRUCTURE IN KARNATAKA Page 29

  • 7/31/2019 E000000073.2621.Frost & Sullivan CII Karnataka Event WP

    3/33

    A Whitepaper by

    CHAPTER 1: INDIA POWER SECTOR OVERVIEW

    India is today the 2nd fastest growing economy globally. Powering the economic growth requires

    tremendous amount of support from a countrys basic infrastructure Roads, Ports, Electricity, Water,

    Electricity / Power are key elements supporting the nations infrastructure growth.

    India with an installed capacity of 169.7 GW (as on December 2010) was ranked 6thglobally in terms of

    power generation installed capacity. As on June 2011, Indias power generation installed capacity has

    increased to ~177 GW. In the 11th five year plan (FY2007-FY2012), India to-date has added ~44.7 GW of

    capacity, which is almost double the capacity added during the 10th five year plan (FY2002-FY2007).

    Government of India in Y2002 had set a target of adding almost 100 GW of capacity over a 10 year

    period between FY2002 and FY2012, with the objective of Power for All by 2012. Chart 1.1 below

    indicates the growth of power generation capacity over the past few years.

    Chart 1.1 - India Power Generation Capacity-Cumulative (Figs in GW)

    Source: Central Electricity Authority, Ministry of Power

  • 7/31/2019 E000000073.2621.Frost & Sullivan CII Karnataka Event WP

    4/33

    A Whitepaper by

    In spite of the Govt.s aggressive target of power generation capacity addition, the actual capacity

    addition has not been able to meet planned targets due to various reasons, including:

    Constrained main plant equipment (boiler, turbine, and generator) manufacturing capacity, etc.

    Delayed clearances environmental, forest etc.

    Land acquisition issues

    Poor financial condition of State Electricity Boards (SEBs)

    Shortage of BOP suppliers

    Chart 1.2 - India Power Generation Capacity, Planned vis--vis actual Capacity Addition

    (Figs in GW)

    Source: Central Electricity Authority, Ministry of Power

    Power sector has not been able to keep pace with the rapid increase of Energy Demand. Although

    Indias Power Transmission & Distribution (T&D) infrastructure ranks 5th globally, with the backdrop of

    missing power generation capacity addition, rampant power theft, dismal condition and inappropriate

    maintenance of the equipment/infrastructure has resulted into huge T&D losses, thereby leading to

    power demand-supply gap scenario.

  • 7/31/2019 E000000073.2621.Frost & Sullivan CII Karnataka Event WP

    5/33

    A Whitepaper by

    Chart 1.3 - India Power Generation Capacity, Planned vis--vis actual Capacity Addition

    (Figs in GW)

    Source : CEA, Ministry of Power

    With heavy dependence on fossil fuel imports, India is becoming vulnerable to price volatility. With the

    increasing demand for hydrocarbon resources and the limited global growth in their supply, an increase

    in the price of conventional fuels is inevitable. Globally-increasing coal prices, besides the domestic coal

    supply shortage, have made it imperative for India to diversify its energy sources.

    With this background of power demand-supply gap and the long-term strategy for establishing energy

    security and reducing the carbon footprint, the countrys power generation scenario calls for rapid

    capacity addition from all possible sources. India has voluntarily committed to reduce carbon emissions,

    despite its per capita carbon emission being less than a fifth of the global average. As part of Indias

    strategy to lower the carbon emission intensity, increasing the contribution of Renewable Energy (RE),

    an emission-free and clean fuel source, as a dependable source of energy is one of the key aspects.

    Aggressive plans to increase the countrys power generation capacity requires large tracts of land and

    equivalent amount of investment in laying the power T&D infrastructure. With approximately 40

    percent of the population in India without access to electricity, and hurdles with respect to Right-Of-

    Way, expanding the T&D infrastructure is beset with its own set of challenges. In such a scenario ,

    renewable RE is an excellent energy source in meeting localized power requirements through

    distributed generation applications, thereby reducing the burden of laying additional T&D infrastructure.

  • 7/31/2019 E000000073.2621.Frost & Sullivan CII Karnataka Event WP

    6/33

    A Whitepaper by

    INCREASING FOCUS ON RENEWABLE ENERGY IN INDIA

    The share of RE, as one of the countrys sources of energy, has been steadily increasing over the past

    few years, almost 5.7 times in comparison to 1.5 times of thermal power (in absolute terms), over a

    period of last 9 years (end-March 2002 to end-March 2011). Contribution of renewable energy to Indias

    power generation mix stood at 11.4 percent (March 2011), steadily increasing from a share of 3.3

    percent (March 2002). These facts indicate the growing importance of RE in the countrys power

    generation mix.

    Chart 1.4 - India Power Generation Mix by Fuel Source (percentage)

    Note: Figures indicated in chart are as at the end of March for each year

    Source: CEA, Ministry of Power, MNRE

    Small hydropower, biomass, wind, solar, etc. are some sources of RE in India. Wind energy dominates

    Indias RE basket with a share of 70.9 percent. In fact, growth in wind energy capacity within the country

    has been a major driving factor for the increasing share of RE in the countrys energy mix.

  • 7/31/2019 E000000073.2621.Frost & Sullivan CII Karnataka Event WP

    7/33

    A Whitepaper by

    CHAPTER 2 : KARNATAKA POWER SCENARIO

    KARNATAKA STATE - ECONOMIC OVERVIEW

    Chart 1.4 - Karnataka State Gross Domestic Product (GDP), (000 crores)

    Source : Karnataka Economic Survey, Government of Karnataka

    Karnatakas economy has been growing at a rapid pace, faster than the overall economic growth of the

    country. At the end of FY2010-11, Karnatakas GDP reached 397.9 thousand crores. Over the past 5

    year period the CAGR of the GDP has been 15.2 %.

    From the GDP composition stand-point, an interesting fact emerges. As compared to Agriculture, and

    industry sector, the share of the services sector in Karnatakas GDP has been increasing at a much faster

    rate. At the end of 10th five year Plan (FY2006-07), the services sector contributed 50.9% of GDP, which

    has now increased to 54.9%. This growth of Service sector has been at the cost of the Industry sector,

    which is reflected in the below chart

  • 7/31/2019 E000000073.2621.Frost & Sullivan CII Karnataka Event WP

    8/33

    A Whitepaper by

    Chart 1.5 - Karnataka GDP composition by Sector (Percentage share)

    Source: Karnataka Economic Survey, Government of Karnataka

    KARNATAKA POWER SECTOR STRUCTURE

    At present, power sector generation in Karnataka is spear headed by the Karnataka Power Corporation

    Limited (KPCL). The State Electricity Board dealing with the transmission and distribution of electricity --

    the Karnataka Electricity Board (KEB) -- was unbundled and corporatized in 1999.

    This resulted in the formation of Karnataka Power Transmission Corporation Ltd. (KPTCL) which retained

    charge of T&D, while a small generation company, Visveswaraya Vidyut Nigama Limited (VVNL), was

    given control of the few generation stations earlier controlled by the Board.

    KPTCL a 100% Government of Karnataka (GoK) entity, transmission utility unbundled from the erstwhile

    Karnataka Electricity Board (KEB), as a part of power sector reform in Karnataka. KPTCL in turn was

    unbundled in June 2002, with the distribution segment split between the existing five main geographical

    zones. Karnataka Power Transmission Corporation Limited (KPTCL) is the sole transmission utility which

    handles power from the grid to the distribution level. Power is then distributed to the customers

    through five Distribution Companies

  • 7/31/2019 E000000073.2621.Frost & Sullivan CII Karnataka Event WP

    9/33

    A Whitepaper by

    Chart 1.6 Karnataka Power Distribution

    Source: KERC, KPCL, KPTCL

    KARNATAKA POWER GENERATION SCENARIO

    The State of Karnataka with an installed power generation capacity of 11.5 GW (as end March 2011),

    contributed 6.6% of Indias total power generation installed capacity. Installed Power Generation

    capacity in Karnataka has witnessed a CAGR of 9.5% for the period FY2006-07 to FY2010-11.

    As depicted in Chart 1.6 below,

    Thermal power dominates the Power Generation mix with a share of 44% as at end of March

    2011 (FY2010-11). The main sources of thermal power in Karnataka are the two main power

    plants at Raichur and Bellary.

    Hydel power projects on the rivers of Sharavathi, Kalinadi, Varahi, Ghataprabha, Almatti and

    Shivanasamudram form the second most important source, contributing 31 % to the total power

    generation capacity of the State. Karnataka state has a long and enviable history in power

    generation as Asias first major hydro-electric generating station was set up at Sivasamudram as

    early as 1902 for commercial operation, at a time when technology was still in its infancy, even

    in the advanced countries

    Hydel power source dominated Karnatakas power generation mix until FY2006-07. From

    thereon, thermal power capacity has been steadily increasing. In contrast Hydel power capacity

    growth has stagnated

    Karnataka

    Power

    Transmission

    Corporation

    Limited

    KPTCL

    BESCOM,

    Bangalore

    Electricity

    Supply

    Company

    MESCOM,

    Mangalore

    Electricity

    Supply

    Company

    HESCOM,

    Hubli

    Electricity

    Supply

    Company

    GESCOM,

    Gulbarga

    Electricity

    Supply

    Company

    CESCOM,

    Chamundeshw

    ari Electricity

    Supply

    Company

  • 7/31/2019 E000000073.2621.Frost & Sullivan CII Karnataka Event WP

    10/33

    A Whitepaper by

    Kaiga Generating Station in Uttar Kannada district is one of Indias six atomic power plants; in

    operation since 2000. This plant has four units and in November 2009, approval was granted by

    National Power Corporation for expansion in the Second Phase that will generate 1400 MW of

    power when completed.

    Chart 1.6 Karnataka Power Generation Capacity Addition, by fuel source (Figs in GW)

    Source : CEA, Ministry of Power

    Chart 1.7 - Karnataka Power Generation Capacity ,by fuel source (Figs in GW)

    Source : CEA, Ministry of Power

  • 7/31/2019 E000000073.2621.Frost & Sullivan CII Karnataka Event WP

    11/33

    A Whitepaper by

    KARNATAKA POWER DEMAND-SUPPLY SCENARIO

    As is the case at the pan-India level, State of Karnataka suffers from power shortage, as well. With an

    annual energy requirement of ~50,500 Million units (MUs) in FY2010-11, the energy availability was to

    the tune of ~46,600 MUs only, resulting in a deficit of 7.6%.

    The figures below highlight the fact that electricity imports reached a peak in the years 2004-05 due to

    inadequate addition to the generation capacity (hence relatively lower Electricity Generation). In recent

    years the import of electricity is starting to decline, however to make the state self-reliant, a long way

    has to be treaded. It will require substantial generation capacity augmentation ( Year on Year), plant

    load factor improvements ( from an average of mid 60s to the mid 80s in percentage points), energy

    efficiency measures etc. in the years to come.

    Source : Economic Survey of Karnataka, 2010-2011

    Chart 1.8 Generation vs Imports in Karnataka ( 2002-2011)

    0

    5000

    10000

    15000

    20000

    25000

    30000

    35000

    2002-03 2003-04 2004-05 2005-06 2006-07 2007-082008-09(RE)

    2009-10 ( P)

    2010-11(A)

    Million Units

    Electricity Generation ( Million Units) Imports( Million Units)

  • 7/31/2019 E000000073.2621.Frost & Sullivan CII Karnataka Event WP

    12/33

    A Whitepaper by

    The T&D losses in the state have been gradually decreasing as depicted in Chart below, decreasing from

    a value of 29.7% in FY2006-07 to 20.6% in FY2010-11. The fluctuating trend of power shortage with the

    decreasing trend of T&D losses, clearly indicates the increasing demand for power within the state, and

    the inability of the state to increase power generation capacity in line with the requirements

    The deficit crisis across the state has affected every sector of the industry. This scenario has essentially

    manifested in unscheduled load-shedding scenario. The government has resorted to unscheduled

    loadshedding for five to six hours during the day in Bangalore, while other cities and rural areas have

    plunged into a virtual darkness, affecting industrial, commercial as well as residential customers

    Chart 1.9 - Karnataka Power T&D losses, and Power Deficit (Figs in %)

    Source : Economic Survey of Karnataka, CEA, Ministry of Power

    Note : T&D loss figures for FY2008-09, FY2009-10 and FY2010-11 are revised estimates / provisional.

  • 7/31/2019 E000000073.2621.Frost & Sullivan CII Karnataka Event WP

    13/33

    A Whitepaper by

    ELECTRICITY PRICES IN KARNATAKA

    Electricity prices in Karnataka have been on an rise. Karnataka is amongst the leading states in

    terms of higher electricity prices

    Chart 2.0 - Electricity Prices Comparison (Figs in Rs / Kwh for Domestic consumer with 4KW

    connected load and consuming on an avg. of 400Kwh/month )

    Source India Economic Survey FY2010-11

    Chart 2.1 - Electricity Prices Comparison (Figs in Rs / Kwh for Large Industry 1000KW 60%

    L.F.(438000 KWh/ Month)

    Source : India Economic Survey, FY2010-11. Note figures have been rounded off

  • 7/31/2019 E000000073.2621.Frost & Sullivan CII Karnataka Event WP

    14/33

    A Whitepaper by

    ELECTRICTY END USERS

    The four major groups of power consumers are:

    Irrigation pump (IP) sets

    Domestic lighting & All Electric Homes(AEHs)

    Industries

    Commercial lighting.

    These four groups together accounted for about 87% of the total power consumption in 2009-10 and

    almost 88% in the first half of 2010-11. The irrigation pump sets alone consumed more than 1/3 of the

    total power consumption in the State.

    Table 1.1 - Electricity Consumption

    Electricity Consumption (MUs)

    Consumer Groups 2008-09 2009-10

    2010-11

    (up to Dec.

    2010)

    Average rate

    (paise / kwhs)

    (2009-10)

    1 Industries 5693 5932 4958 495

    2 I.P.Sets 11217 11772 8733 102

    3 Domestic Lighting & AEH 6710 7360 6060 343

    4LT Industries & Water

    Works1519 2366 1878 412

    5Public Water Works and

    sewerage pumping1779 1044 803 354

    6 Commercial Lighting 4010 4350 3636 644

    7 Public Lighting 493 690 542 311

    8 Others 599 177 135 1013Total 32020 33690 26745 333

    Source : Economic Survey of Karnataka, 2010-2011

    Irrigation Pump Sets consume around 1/3 of the total electricty consumption in Karnataka, which

    further implies that the agriculture segment creates the maximum demand for power. Domestic

    lighting & AEH is the second largest consumer of electricty followed closely by the Industrial sector

    (majority services sector).

  • 7/31/2019 E000000073.2621.Frost & Sullivan CII Karnataka Event WP

    15/33

    A Whitepaper by

    Source : Economic Survey of Karnataka, 2010-2011

    FORMATION OF POWER COMPANY OF KARNATAKA LIMITED (PCKL) A SPECIAL PURPOSE

    VEHICLE (SPV)

    In order to bridge the Gap between availability and Demand, capacity addition in generation was felt

    necessary. With this background and to supplement the efforts of KPCL, GOK accorded approval for

    constitution of SPV viz., PCKL on 12-07-2007 in order to facilitate private investment in development of

    conventional energy resources,

    PCKL facilitates the entry of private players in power projects in the state and also takes up

    energy trading on behalf of all distribution companies

    PCKL makes arrangements with other states for exchange of power to balance the demand

    during monsoon and summer seasons. PCKL invites bids for sale and purchase of short term

    power.

    PCKL is exploring the opportunities for equity participation and joint venture with the States

    who are establishing pit head power plants and with neighbouring states where activities on

    projects have been initiated.

    Chart 2.2 - Pattern of Power Consumption & Power Tariffs in Karnataka (2009-10)

    18.5

    32.722.7

    7.0

    3.0

    13.6

    2.0

    0.5Industries

    I.P.Sets

    Domestic Lighting & AEH

    LT Industries & Water Works

    Public Water Works andsewerage pumpingCommercial Lighting

    Public Lighting

    Others

  • 7/31/2019 E000000073.2621.Frost & Sullivan CII Karnataka Event WP

    16/33

    A Whitepaper by

    PCKL on behalf of all ESCOMs has registered itself with Indian Energy Exchange limited for

    carrying out the transactions of energy on day ahead basis.

    MAJOR POWER PLANT PROJECTS INITIATED BY PCKL

    PCKL, is carrying out bid processing activities for capacity addition by establishing 3 coal based

    thermal power projects

    1. 1000 MW at Chamalapura in Mysore District,2. 1320 MW power plant at Ghataprabha in Belgaum District through private investment,

    for which Govt. land has been allotted

    3. Approval for 1320 MW plant at Jewargi in Gulbarga District on long term basis throughtariff based competitive bidding process and process of land acquisition has began.

    PCKL has envisaged establishment of distributed generation for which tenders have been

    floated for establishment of 5 MW and part thereof capacity power plants at Taluka level in the

    state of Karnataka.

    PCKL invited bids for procurement of 2000 MW of power on long term basis through

    competitive bidding route (Case-I) under merchant Power Plants

  • 7/31/2019 E000000073.2621.Frost & Sullivan CII Karnataka Event WP

    17/33

    A Whitepaper by

    CHAPTER 3 : CONVENTIONAL POWER GENERATION IN KARNATAKA

    Hydel power plant which forms a sizeable chunk of the fuel mix in Karnataka depends on the vagaries

    of nature. Thermal power plants along with renewable energy are most suited for Karnataka.However, with the non-availability of pit-head coal, the state has urged the Centre to allocate captive

    coal blocks to the power projects of the State and increase Karnataka's share in Central Power

    generation.

    COAL BASED POWER PLANT EXPANSION IN KARNATAKA - CHALLENGES

    Distance from the coal mines:

    The major coal mines are located in the Eastern and North-Eastern parts of India. So, it takes a

    huge shipment cost to transport coal from these coal mines to Thermal power plants in

    Karnataka.

    Coal theft during shipment:

    The coal is shipped in the hopper wagons which are open & hence it is very much vulnerable to

    coal theft during the shipment.

    Increased amount of water/moisture in the coal:

    As the coal is shipped in the hopper wagons, it soaks huge amount of moisture and also gets

    affected by the rain. So, when it is used in the plant it affects the equipments adversely due to

    the increased amount of water in it.

    Ash disposal:

    After burning the coal a huge amount of ash remains. Disposal of this ash posing as a problem in

    the coal based thermal power plants.

    Hot corrosion and erosion:

    Hot corrosion and erosion are recognized as serious problems in coal based power generation

    plants in India. The coal used in Indian power stations has large amounts of ash (about 50%)

    which contain abrasive mineral species such as hard quartz (up to 15%) which increase the

    erosion propensity of coal. Hot corrosion and erosion in boilers and related components are

    responsible for huge losses, both direct and indirect, in power generation.

    Environmental issues:

  • 7/31/2019 E000000073.2621.Frost & Sullivan CII Karnataka Event WP

    18/33

    A Whitepaper by

    Poor quality of coal used in the coal based thermal power plants in India is causing the

    environmental degradation through gaseous emission, particulate matters, fly ash and bottom

    ash.

    KARNATAKA COAL REQUIREMENT FOR THERMAL POWER PLANTS:

    Coal received for Karnataka in 2009-10 for Power Generation is estimated at appx 10.7 MMT as against

    11.1 MMT in 2008-09. Coal availability and transportation is a major challenge for coal based power

    plants.

    Table 1.2 Coal receipt for Power Generation in Karnataka in Y 2009-10:

    Collieries Coal Receipt in MMT- 2009-10

    South Central Coal Fields 2.2

    Western Coal Fields 2.2

    Mahanadi Coal Fields 3.5

    Imports 0.9

    KEMTA 2.0

    TOTAL 10.7

    Source: Karnataka Power Corporation Ltd, Directors Report-2011

    Karnataka has plans adding 4,700 MW of coal based power plants over the next 5 years. Coal

    requirement for the upcoming power plants is estimated at 32.2 MMTPA, which is quite substantial

    compared to present consumption.

    The state government has applied for coal allocation with ministry of coal (Govt of India). However its

    to be noted that Coal India has not been able to supply additional coal requirements in the country for

    the last two years. Since the state does not have sizable coal mines it had to depend on other states &

    imports for sustaining its coal based power plant. Karnataka took initiative to build power plant in

    Chattisgarh (Godhna Power Plant- 1600 MW) close to coal pit. This is to bypass issues & cost for coaltransportation (coal linkages) incase the Power Plant is situated in Karnataka.

  • 7/31/2019 E000000073.2621.Frost & Sullivan CII Karnataka Event WP

    19/33

    A Whitepaper by

    KARNATAKA GAS BASED POWER PLANT:

    The state government has plans for establishment of the Tadadi Combine Cycle Power Plant (2100 MW).

    Gas Linkage for the power plant is still to be decided. Feasibility for linkages from LNG Terminal is under

    review.

    It is to be noted that cost of power generation from Gas Based Power Plants is dictated by gas prices.

    The below chart depicts cost of power generation with in Coal & Gas based power plants under different

    conditions:

    Chart 2.3 - Cost per unit comparison between coal and gas based power plants

    Source: CEA, May 2010

    From the above diagram, it can be deduced that gas prices in excess of $8/mmbtu makes power

    generation from gas based plants expensive.

    NTPC currently enjoys advantage of low gas prices due to its earlier agreement with GAIL for gas supply.

    However at present, spot gas prices are hovering around $15/mmtbu hurting gas based power plants in

    the country. Each $ increase in LNG prices increase power generation cost on an average of 35 paisa.

    Gas Based power plants are best suited for peak power supply at premium cost. With introduction of

    smart grid and metering system, variable electricity cost may become a reality.

    Karnataka Agriculture Pump Efficiency Improvement:

    Several states like Maharashtra, Punjab, Gujarat have launched pump efficiency improvement projects

    for municipal & agricultural/irrigation pump segment.

    1.47 1.47 1.470.99 0.99 0.99 0.99 0.99 0.99

    11.9 1.98

    2.03 2.372.71 3.01

    3.51 4.012.47

    3.37 3.453.02

    3.363.70

    4.004.50

    5.00

    0.0

    1.0

    2.0

    3.0

    4.0

    5.0

    6.0

    PitheadCoal

    Station

    CoalStation

    (1000km

    from

    Mine)

    ImportedCoal

    -Coastal

    NaturalGas

    @$6/mmbtu

    NaturalGas

    @$7/mmbtu

    NaturalGas

    @$8/mmbtu

    NaturalGas

    @$9/mmbtu

    NaturalGas

    @$11

    .5/mmbtu

    NaturalGas

    @$12/mmbtu

    F ixed Va ria bl e T ot a lCoal Based Power Plants

    INR/KWHr

  • 7/31/2019 E000000073.2621.Frost & Sullivan CII Karnataka Event WP

    20/33

    A Whitepaper by

    It is estimated that for transportation of 1 kilo litre of water to Bangalore the cost is between Rs 16-20.

    This is a cost and energy efficiency issue and is coined as energy-water-nexus. Irrigation pumps used in

    agriculture accounts for appx 25% energy consumption in India. However for Karnataka the

    consumption is estimated at 42.3% of the power generation in the state. With electricity being

    subsidized for agricultural use, increase consumption of power by agricultural pumps affects the health

    of the Power Distribution Utilities in the state.

    Below chart depicts the percentage sales Vs revenue from agricultural consumer for selected states in

    India

    The above chart indicates the need to increase efficiency of agricultural pumps in State of Karnataka.

    Increase energy efficiency would help in lowering electricity subsidy to rural/agricultural segment which

    helps in addressing state finances better.

    Karnataka is already engaged in increasing pump efficiency and notable power saving (up to 50%) has

    been achieved.

    Y : Sales in MKwhr (%) to Total Sales

    Gujarat

    West Bengal

    Maharashtra

    UP

    Karnataka

    Punjab

    AP

    Haryana

    Note: Values in X & Y Axis are in Percentage

    Source Bureau of Energy Efficiency, India

    Chart 2.4 - Percentage Electricity Sales Vs Revenue from Agricultural Consumer for

    Different States

    X : Sales in

    Rs Crore(%)

    to Total

    Sales

  • 7/31/2019 E000000073.2621.Frost & Sullivan CII Karnataka Event WP

    21/33

    A Whitepaper by

    Table 1.3 - Upcoming Thermal Power Plants In Karnataka:

    Project Promoter Location Capacity

    Karnataka Power Corporation Yeramarus,Vadaloor 1200 MW

    Shri Siddheshwar Sugars Telgi, Bijapur District 14 MW

    Karnataka Power Corporation Raichur 600 MW

    NTPC/BHEL North Karnataka 6900 MW

    NTPC Kuldigi,Bijapur District 4000 MW

    Karnataka Power Corporation Kudithini,Bellary District 500 MW

    Power Company of Karnataka Ltd. Jewrgi,Gulabarga District 1320 MW

    Ind-Bharat Power (Karwar) Ltd.Hankon,Uttara Kannada

    District300 MW

    Mukund Ltd. Ginigera, Koppal 15 MW

    Karnataka Power Corporation Edlapura,Raichur District 600 MW

    Hassan Thermal Power Hassan 1000 MW

    Surana Power Raichur 400 MW

    Reliance Industries Bidar 800 MW

    Atlas Power Gulbarga Not Specified

    Karnataka Power Corporation Bidadi 1400 MW

    Coastal Karnataka Power Tadri 4000 MW

    Table 1.4 - Ultra Megawatt Power Plant (Umpp) In Karnataka:

    Name of

    DeveloperLocation

    Power in

    MWUnits

    Capital

    Involved

    Expected Year of

    Commissioning

    NTPCKudgi in BijapurDistrict of North

    Karnataka.

    4000 MW 800*5Rs. 24,000

    Crore

    Dec 2014 ( First

    2400 MW)

    Power Finance

    Corporation (PFC)

    Coastal

    Karnataka4000 MW --

    Rs. 15000,

    Crore

    Under

    Construction

  • 7/31/2019 E000000073.2621.Frost & Sullivan CII Karnataka Event WP

    22/33

    A Whitepaper by

    PROPOSED NATURAL GAS PLANTS IN KARNATAKA:

    The Karnataka government is planning to build three gas-based power plants under Public Private

    Partnership (PPP) with an investment of around Rs 10,000-Rs 13,000 crore. Gas for these projects is to

    be supplied by the Gas Authority of India (GAIL) from Dabhol in Ratnagiri district in Maharashtra toBangalore in Karnataka. The proposed gas based plants with a capacity of 700 MW each are to be setup

    at Belgaum, Davangere and Tumkur, which fall under the proposed gas pipeline route of 850 km length.

    GAIL has committed to supply gas by FY2012-13, and the pipeline on this route would be designed to

    carry 16 million metric square cubic metres per day (MMSCD) of gas.

    These projects would be setup under Public Private Partnership (PPP) model, and the Karnataka Govt. Is

    likely to award the project to private companies by the end of Y2011 enabling the investing

    company to complete it by the end of 2013.

    Besides KPCL is also planning to setup a 2100 MW gas based plant at Tadadi, Uttar Kannada

    district. Imported natural gas is proposed to be used for this plant.

    Table 1.5 - Proposed Natural Gas Plants In Karnataka

    Name of Plant/

    DeveloperLocation

    Power in

    MWUnits

    Capital

    Involved

    Expected Year of

    Commissioning

    Bidadi Combined

    Cycle Power Plant Bidadi 1400 MW 350*4Rs. 3750

    Crores 2014

    RGPPL, KPCL

    Belgaum,

    Davangere and

    Tumkur

    2100 MW 700*3Rs. 13000

    Crore

    KPCLTadadi, Uttara

    Kannada district2100 MW 700*3 -

    CHALLENGES FOR SETTING UP GAS BASED POWER PLANTS -

    The obstacles to realize the full potential of gas-fired generation: The two major obstacles against

    realizing the full potential of gas-fired power generation in India are gas price sensitivity and availability

    of gas.

    India is facing three major challenges on its way to become a well-functioning gas market:

    (i) Lack of sufficient transmission infrastructure,(ii) Lack of a coherent legal and regulatory framework for the sector; and(iii) Continuous questions about the affordability of gas.

  • 7/31/2019 E000000073.2621.Frost & Sullivan CII Karnataka Event WP

    23/33

    A Whitepaper by

    CHAPTER 4 : RENEWABLE ENERGY DEVELOPMENT IN KARNATAKA

    Given the inherent advantage of Renewable energy, the fast depleting fossil fuel sources & its hazardous

    environmental impact, the Karnataka Govt recognized the need to develop renewable energy based

    capacity in the State. The Renewable Energy policy 2009-14 was framed in 2009, to regulate and ensure

    speedy development of renewable energy capacity build-up within the State

    As per this policy capacity addition targets through various renewable sources were set with a total

    planned capacity addition of 4200 MW, with a planned outlay of INR 22,000 Crores

    Table 1.6 - Karnataka Renewable Energy policy 2009-14 (capacity addition plan, in MW)

    Year wise proposed capacity additionRE Source Target MW

    09-10 10-11 11-12 12-13 13-14

    Wind Power2969 630 680 530 530 599

    Mini and Small

    Hydro600 100 100 150 150 100

    Cogeneration in

    Sugar Industry281 56 56 56 56 57

    Biomass / Bio Gas300 60 60 60 60 60

    Waste to Energy50 10 10 10 10 10

    Total4200 856 906 806 806 826

    Source : KREDL

  • 7/31/2019 E000000073.2621.Frost & Sullivan CII Karnataka Event WP

    24/33

    A Whitepaper by

    Chart 2.5 - Karnataka Renewable Energy Capacity Increase, Cumulative (Figures in MW)

    Source : KREDL

    Strategy for Wind project

    KPCL is the Karnataka public sector undertaking is the premier Power Generating Company in the State.

    A priprerancial allotment of Wind Power Projects above 500 MW and Solar Power Projects above 100

    MW will be considered.

    The followings geographical regions in Karnataka State are reserved for allotment of Wind Power

    Projects to Karnataka Power Corporation Limited.

    50 MW at Kappadagudda Extension

    270 MW at Hill ranges of Guledagudda Gudur.

    Hill ranges of Sureban, Yere Kittur, Kallur, Mallur and Basidoni.

    Hill ranges of Halolli to Katkol (Godachi, Khanpet, Torgal)

    Hill ranges of Halagatti, Mudakavi, Tadasi, Vasan, Govinakoppa.

    Hill ranges of Soudatti to Ugargol.

    Hill ranges of Hanumana Hatti to Kakti.

    Zalki of Indi Taluk.

  • 7/31/2019 E000000073.2621.Frost & Sullivan CII Karnataka Event WP

    25/33

    A Whitepaper by

    Strategy for Small Hydro Projects:

    KREDL will take steps to identify the potential sites watershed basin wise including canal based projects

    and offer the identified sites for development on Public Private Partnership/Build Operate Own Transfer

    mode. The Mini Hydro Project proposals which do not involve diversion of the water flow resulting indrying up the stream/river stretch will be considered for development.

    Keeping in view the environmental issues, the Mini Hydro projects in the Western Ghats

    Districts/Forest areas will be restricted to maximum 5.00 MW and preferably Run of the River (ROR)

    projects encouraged. To facilitate successful expeditious commissioning of the targeted hydro projects

    the various statutory clearances will be facilitated through single window mechanism.

    Strategy for Biomass projects:

    Karnataka has 10.5 million Hectors of arable land which generates around 15 million metric tons of

    agricultural/agro-processing unit residues. The state with 3 million hectors of forest land offers forest

    residues plus dry bamboo biomass sources, targeted to harness 300 MW of power through biomass

    projects based on Rankine Cycle/Biomass Boiler and Otto Cycle/ Biogas Plant or Biomass Gasifier. The

    Biomass plants will be linked to organic fertilizer production units with key input being the waste coming

    from the Biomass power plant. To offset the negative factors the biomass projects will be encouraged by

    extending enabling Tariff atmosphere. The government waste lands will be identified and offered to set

    up Biomass Projects.

    Table 1.7 - Comparison of Renewable Energy capacity Addition Plan vs. Actual Addition across

    various sources in Karnataka State (Figures in MW)

    RE sourcePlanned Capacity

    Addition (MW)

    Actual Capacity

    Addition (MW)

    Difference/Target

    Variation (%)

    FY2009-10 FY2010-11 FY2009-10 FY2010-11 FY2009-10 FY2010-11

    Wind 630.0 680.0 146.0 254.1 -76.8% -62.6%Small Hydro 100.0 100.0 154.4 36.5 54.4% -63.5%

    Co-generation 56.0 56.0 147.3 108.5 163.0% 93.8%

    Bio-mass 60.0 60.0 6.0 0.0 -90.0% -100.0%

    waste 10.0 10.0 0.0 0.0 -100.0% -100.0%

    Source KREDL Annual Reports

  • 7/31/2019 E000000073.2621.Frost & Sullivan CII Karnataka Event WP

    26/33

    A Whitepaper by

    Present and Future Investment Scenario in Renewable Energy Sector:

    Private Sector Investment:

    During the (2007-2009) three years of Renewable Energy development, in the state, on an

    average annually about 300 MW Renewable Energy capacity additions brought in about Rs

    1,800 crores investment by the private sector.

    It is expected that the new Renewable policy initiative may bring in an additional investment of

    Rs 1,600 crores annually by the private sector. With this the private sector investment would

    amount to Rs 17,000 crores during the policy period.(2009-2014)

    Companies like Soham are presently operating small hydro plants in the state with a 22 MW

    plant and 5 other small scale hydro plants.

    The Government of India, the World Bank and the Global Environmental Facility (GEF) are

    supporting private investors in renewable energy development project with the aim of

    improving commercial markets and financing for wind, mini-hydro, and solar PV technologies.

    Various projects, along with Danish and other assistance and a strengthened India Renewable

    Energy Development Agency (IREDA) are promoting and financing private-sector renewable

    energy investments.

    Public Sector Investment:

    The profit making Central and State Public Sector Undertakings may also invest in the

    Renewable Energy projects and may bring in Rs 5,000 crores.

    Akshaya Shakthi Nidhi (Green Energy Fund):

    In order to facilitate Renewable Energy project financing and Energy conservation and Efficiency

    measures Green Energy Fund ''Akshaya Shakthi Nidhi'' will be established. "Green Energy Cess"

    of Rs 0.05 (five paise) per unit would be levied on the electricity supplied to commercial and

    industrial consumers.

    It is estimated to generate about Rs 55 crores annually. Out of the Rs 55 crores, 10 % of this

    fund to the tune of Rs 5 crores will be set apart as contribution to Energy Conservation Fund for

    Energy Conservation activities.

  • 7/31/2019 E000000073.2621.Frost & Sullivan CII Karnataka Event WP

    27/33

    A Whitepaper by

    The balance Rs 50 crores will be set apart for Renewable Energy project financing. The Akshaya

    Shakthi Nidhi will be administered by KREDL for promotion of Renewable Energy particularly in

    Public Private Participation (PPP) mode, decentralized generation and distribution Renewable

    Energy projects for the benefit of rural sector.

    The funds may also be utilized for land acquisition and land development activity for Renewable

    Energy projects including Net Present Value and compensatory Afforestation, soil moisture

    conservation etc for forest land clearance.

    KARNATAKA SOLAR POLICY 2011-2016

    Karnataka State Govt recently announced its new Solar Policy 2011-2016. This policy is applicable with

    effect from 1-July-2011, and shall remain in force up to 31-Mar-2016 or until any changes are made bythe State Govt., as deemed fit

    Some of the key highlights of the updated Solar policy 2011-12016 are

    1. A total of 350 MW of solar energy is targeted to be added by 2016. Split of 350 MW is indicated

    in the chart below

    2. The current tariff for solar power plants set by the state electricity regulator is 14.50 rupees per

    kilowatt-hour for photovoltaic plants and11.35 rupees per kilowatt-hour for solar thermal

    plants, according to a tariff order on the website of the Karnataka Electricity Regulatory

    Commission

    3. Renewable Purchase Obligation (RPO), of 0.25% to ESCOMs of the total power consumed. In

    circumstances of short-fall of solar energy procurement by ESCOMs, the short-fall can be

    compensated by purchase of solar specific REC

  • 7/31/2019 E000000073.2621.Frost & Sullivan CII Karnataka Event WP

    28/33

    A Whitepaper by

    Chart 2.6 - Karnataka Solar Policy 2011-2016 plan for building up solar energy capacity within

    the State through various routes

    Source: Government of Karnataka, Karnataka Renewable Energy Development Ltd.

    350 MW Solar power

    for the period 2011-

    12 to 2015-16

  • 7/31/2019 E000000073.2621.Frost & Sullivan CII Karnataka Event WP

    29/33

    A Whitepaper by

    CHAPTER 5 : POWER TRANSMISSION & DISTRIBUTION INFRASTRUCTURE IN

    KARNATAKA

    In its Policy Statement on restructuring and privatization [GOK, 2001(b)], the Government of Karnataka

    had specifically mentioned three priorities:

    1. Ensuring that the people of Karnataka have equitable access to basic and reasonably

    priced electricity services, with all households electrified by the year 2010

    2. Providing adequate electricity to industry and commerce to achieve economic growth

    3. Promoting the kind of energy use that will not damage the environment

    As can be seen from the figure below, the power generation demand gap is increasing since the year

    2007-2008, primarily due to an increase in the demand for power in the state. The direct consequence

    of this increasing demand is the increasing import of electricity from neighboring states (as has been

    discussed in Section on KARNATAKA POWER GENERATION SCENARIO).

    Source : Economic Survey of Karnataka, 2010-2011

    Chart 2.7 - Electricity Demand vs Generation ( 2002 -2011)

    0

    5000

    10000

    15000

    20000

    25000

    30000

    35000

    40000

    2002-03 2003-04 2004-05 2005-06 2006-07 2007-082008-09(RE) 2009-10 ( P) 2010-11(A)

    Electricity Generation ( Million Units) Power Consumption ( Million Units)

  • 7/31/2019 E000000073.2621.Frost & Sullivan CII Karnataka Event WP

    30/33

    A Whitepaper by

    Table 1.8 - Transmission line ( CKM) and substations across various voltage levels as on 31st

    July 2011

    A couple of other reasons of this demand- supply gap are the relatively slower pace of power capacity

    augmentation (Both Generation and T&D) in the state and the high AT&C losses. Apart from having

    adequate generation capacity, it is also important to have an efficient Transmission & Distribution

    network which can provide electricity even to the most remote places at the same time ensuring that

    the power losses are minimized and the power quality is maintained across the network

    Key recommendations:

    Need to Scrutinize Every Segment of the Value Chain.

    From generation to transmission to distribution to the end user every component must be observed

    thoroughly to understand the shortcomings.

    Equitable investment in the T&D sector to ensure it does not lag behind power generation sector

    and there is adequate infrastructure for evacuation of power.

    To reduce losses being incurred, every executive at every organization must be made accountable.

    The flow of energy from Power Generation to Power T&D to End user and the reverse flow ofmoney must be ensured for smooth operation.

    Replicating Successful Models Implemented Elsewhere

    Two cases highlighted for bench-marking:

    Development of national highways in China and;

    Voltage Level (kV) Substations Transmission Line in ckm

    400 4 1978

    220 88 9372

    110 319 8840

    66 535 9569

    33 370 8494

    1316 38254

  • 7/31/2019 E000000073.2621.Frost & Sullivan CII Karnataka Event WP

    31/33

    A Whitepaper by

    Distributed franchisee model for bill collection that has improved collection

    efficiency in certain villages in Gujarat.

    Distributed Power Generation with Solar Energy with Smart Equipments in West

    Bengal : As part of the initiative to promote solar and smart solutions, WBGEDC is in

    process to implement and install solar panels in various school and education

    institutes with smart equipments. This initiative is aimed at introducing self power-

    reliant schooling concept in West Bengal. Success of this initiative can also ensure

    extra power to the grid in future.

    Distributed Power Generation

    Decentralized and renewable energy technologies are expected to have a big impact

    on the way the power sector develops in the coming years. Distributed power can reduce line losses although presently, capital cost of

    technologies like solar is prohibitive.

    Private participation should be encouraged for the development of Micro-grids.

    Availability vs. Reliability

    The per capita consumption of energy in India stands at around 700 kWh today. The

    government has set a target of 1000 kWh for the per capita consumption. In view of this

    target, power needs to be made available to those who have no access to it.

    Solutions such as Energy Management Software and Asset Management Systems although

    important, are secondary to the primary issue of power availability.

    Exploring Indian Power T&D Models

    Private-Public Partnership (PPP) model, which has been successful in other sectors, must be

    explored in depth in the power sector.

    This opens the forum for devising new transmission and distribution models that could beperceived in future to achieve a network which is transparent with minimum AT&C/ T&D

    losses.

  • 7/31/2019 E000000073.2621.Frost & Sullivan CII Karnataka Event WP

    32/33

    A Whitepaper by

    The Need for Evolution in Substation Technology:

    The future outlook on GIS (Gas Insulated Substations) against the current trend of EHV

    (Electrical High Voltage) substations.

    GI Substations have advantages like reduced space, less maintenance and highly reliable, in

    comparison to EHV substations; but at the same time GI Substations are expensive by nearly

    40% compared to EHV substations.

    Indian utility majors are required to perceive at this technology challenge for future

    expansions and refurbishments. Almost 80% of the substations in China are GIS.

    High T&D Equipment Demand:

    In regards to the plans from various government T&D regulatory authorities like PGCIL and Powergrid,

    regarding installation of ultra-high voltage (UHV) electrical transmission network and consequent T&Dequipment demand estimated under the 11th and 12th Five-year plans, some of the challenges that

    present themselves in front of equipment manufacturers are:

    Sourcing upgraded Technology for UHV transmission (765 KV to 1200 KV), as globally very

    few equipment manufacturers have the capability in this range.

    Meeting the equipment demand, with an optimized cost structure.

    High cost competition from Chinese equipment manufacturers in the T&D space.

    DSM (Demand Side Management):

    Introduction and implementation of DSM (Demand Side Management) systems, providing

    real-time information regarding electricity consumption pattern to the consumers.

    This system shall ensure higher satisfaction among consumers, transparency in metering

    measures from various T&D authorities and also provide scope for new smart metering

    technology.

    Need for Proficient Remote Electrification/ MICRO-GRIDS: This concept in India is currently in a nascentstage. Current long network transmission is aggregated by very high T&D loss. These losses can be

    overcome through some of the measures as under, which present themselves as a challenge on this

    front:

    Privatization of T&D infrastructure providers

    Micro-Generation (Micro-Grids) Measures in far flung cities, to reduce T&D losses.

  • 7/31/2019 E000000073.2621.Frost & Sullivan CII Karnataka Event WP

    33/33

    Localization of T&D (through training)

    HOT SPOT Management Technologies:

    There is a need for SCADA and PLC Based smart metering technology for efficient Asset Monitoring,

    Asset Management and Protection to ensure reliable power in India in a long term perspective.