E04-018 status report

Alexandre Camsonne

Hall A Jefferson Laboratory

Hall A collaboration meeting

December 13th 2007

Page 2: E04-018 status report Alexandre Camsonne Hall A Jefferson Laboratory Hall A collaboration meeting December 13 th 2007

Hall A collaboration meetingApril 10, 2023

2

Outline

• He form factors

• Expected results

• Experimental setup He3/He4

• Update

• Conclusion

Page 3: E04-018 status report Alexandre Camsonne Hall A Jefferson Laboratory Hall A collaboration meeting December 13 th 2007

Hall A collaboration meetingApril 10, 2023

3

Few body form factors

dd

Z 2 2 E

4E 3 sin4 / 2 A Q2 cos2 / 2 B Q2 sin2 / 2

A Q2 FC2 Q2 FM

2 Q2 1

B Q2 22FM2 Q2

Q2 4E E sin2 / 2 =Q2 / 4M 2

dd

Z 2 2 E cos2 / 2

4E 3 sin4 / 2 FC2 Q2

•He3 Form Factors

•He4 Form Factors

Page 4: E04-018 status report Alexandre Camsonne Hall A Jefferson Laboratory Hall A collaboration meeting December 13 th 2007

Hall A collaboration meetingApril 10, 2023

4

He3 form factor expected results

Page 5: E04-018 status report Alexandre Camsonne Hall A Jefferson Laboratory Hall A collaboration meeting December 13 th 2007

Hall A collaboration meetingApril 10, 2023

5

He3 Form Factor expected results

Page 6: E04-018 status report Alexandre Camsonne Hall A Jefferson Laboratory Hall A collaboration meeting December 13 th 2007

Hall A collaboration meetingApril 10, 2023

6

He4 Form Factor expected results

Page 7: E04-018 status report Alexandre Camsonne Hall A Jefferson Laboratory Hall A collaboration meeting December 13 th 2007

Hall A collaboration meetingApril 10, 2023

7

Hall A E04018

• Forward and backward measurement to separate the two form factors for He3

• High luminosity

• He3 and He4 measurement

• Use both HRS in coincidence to get elastic signal out of background background

– Time of flight

– Energy loss in scintillator

– Kinematical correlation

• Experiment complete on July 2007

• Analysis on going…

Page 8: E04-018 status report Alexandre Camsonne Hall A Jefferson Laboratory Hall A collaboration meeting December 13 th 2007

Experimental Details

• 20 cm long targets operated at 8K

• Beam current of up to 100 µA, corresponding to luminosity of 2.1038 nuclei/cm2/s

• Allowing cross section to be measured as small as 2.10-41 cm2/sr

• Beam energy from 0.7 to 4.4 GeV, covering Q2 from 1.5 (0.6) to 4 (5) GeV2 for 3He (4He) with 3 angle settings for Rosenbluth separation on 3He

• Scattered electron and recoiling nucleus detected in coincidence

Page 9: E04-018 status report Alexandre Camsonne Hall A Jefferson Laboratory Hall A collaboration meeting December 13 th 2007

Work in progress

Next projects

•TOF Corrections•Calorimeter Calibration•3-D VDC/Detector Track/Event Display•Monte Carlo Improvements•Computer Upgrade

•Cherenkov Gain Equalization corrections

•Detectors efficiencies

Page 10: E04-018 status report Alexandre Camsonne Hall A Jefferson Laboratory Hall A collaboration meeting December 13 th 2007

Hall A collaboration meetingApril 10, 2023

10

Page 11: E04-018 status report Alexandre Camsonne Hall A Jefferson Laboratory Hall A collaboration meeting December 13 th 2007

Hall A collaboration meetingApril 10, 2023

11

Raw time of flight

Page 12: E04-018 status report Alexandre Camsonne Hall A Jefferson Laboratory Hall A collaboration meeting December 13 th 2007

Hall A collaboration meetingApril 10, 2023

12

Corrected time of flight

Page 13: E04-018 status report Alexandre Camsonne Hall A Jefferson Laboratory Hall A collaboration meeting December 13 th 2007

Hall A collaboration meetingApril 10, 2023

13

Corrected time of flight

Page 14: E04-018 status report Alexandre Camsonne Hall A Jefferson Laboratory Hall A collaboration meeting December 13 th 2007

Hall A collaboration meetingApril 10, 2023

14

Conclusion

•Still setting up for full analysis

•New computers ordered

•Full production by January 2008

•Preliminary results expected for summer 2008