Earthmoving Materials Operations

Embed Size (px)

DESCRIPTION

Tema saipal besplatno bersiw

Citation preview

  • 1Lecture 02ECE 404: Construction Technologies & Processes 1

    AUGUST 26, 2015

    CHANG-SEON SHON, PH.D., ASSISTANT PROFESSOR

    DEPARTMENT OF CIVIL ENGINEERING

    NAZARBAYEV UNIVERSITY

    LECTURE 2EARTHMOVING MATERIALS &

    OPERATIONS

    Lecture 02ECE 404: Construction Technologies & Processes 2

    EARTHMOVING IS THE PROCESS OF MOVING SOIL OR ROCKFROM ONE LOCATION TO ANOTHER AND PROCESSING IT SO

    THAT IT MEETS CONSTRUCTION REQUIREMENTS OF LOCATION, ELEVATION, DENSITY, MOISTURE CONTENT, AND SO ON

    EARTHMOVING ACTIVITIES

    Excavating / loading / hauling / placing (dumping and spreading) / compacting / grading / finishing

    FOR EFFICIENT EARTHMOVING PROCESS,

    Accurate estimating of work quantities and job conditions

    Proper selection of equipment

    Competent job management

    EARTHMOVING PROCESS

  • 2Lecture 02ECE 404: Construction Technologies & Processes 3

    CHOICE OF EQUIPMENT INFLUENCES ON THE EFFICIENCY & PROFITABILITY OF THE CONSTRUCTION OPERATION

    FACTORS THAT SHOULD BE CONSIDERED IN SELECTINGEQUIPMENT FOR A PROJECT

    The ability of the equipment to perform the required work

    Maximize the profit produced by the equipment

    Achieve the lowest cost per unit of production

    Possible future use of the equipment

    Availability of parts and service

    Effect of equipment downtime on other construction equipment and operations

    EQUIPMENT SELECTION

    Lecture 02ECE 404: Construction Technologies & Processes 4

    BASIC RELATIONSHIP FOR ESTIMATING THE PRODUCTION OF ALLEARTHMOVING EQUIPMENT

    =

    =

    Where,Vol. percycle averagevol. ofmaterialmovedperequipmentCyclesperhour thenumberofcyclesactuallyachieved expected perhour

    PRODUCTION OF EARTHMOVINGEQUIPMENT

  • 3Lecture 02ECE 404: Construction Technologies & Processes 5

    (From TM 5-331B, U.S. Department of the Army)

    JOB EFFICIENCY FACTORS FOR EARTHMOVING OPERATIONS

    PRODUCTION OF EARTHMOVINGEQUIPMENT (CONTD)

    Lecture 02ECE 404: Construction Technologies & Processes 6

    TRAFFICABILITY

    Ability of a soil to support the weight of vehicles under repeated traffic

    Function of soil type and moisture conditions

    Factors impacting soil trafficability

    Soil strength / Slipperiness / Stickiness / Slope / Stoniness

    Drainage, stabilization of haul routes, or the use of low-ground pressure construction equipment may be required when poor trafficability conditions exist

    EARTHMOVING MATERIALS: GENERAL SOIL CHARACTERISTICS

  • 4Lecture 02ECE 404: Construction Technologies & Processes 7

    LOADABILITY

    Measure of the difficulty in excavating and loading a soil

    E.g. Loose granular soils vs. compacted cohesive soils and rock

    UNIT SOIL WEIGHT (LBS/YD3 OR KG/M3)

    Used as measure of compaction

    Factor in determining the capacity of a haul

    Depend on soil type, moisture content, and degree of compaction

    MOISTURE CONTENT

    GENERAL SOIL CHARACTERISTICS(CONTD)

    =

    100

    Lecture 02ECE 404: Construction Technologies & Processes 8

    SOIL IDENTIFICATION ANDCLASSIFICATION

    SOIL

    Consist of gravel, sand, silt, clay, and organic materials

    2m

    m

  • 5Lecture 02ECE 404: Construction Technologies & Processes 9

    SOIL CLASSIFICATION

    SOIL CLASSIFICATION SYSTEMS

    Two principal soil classification systems are used for design and construction in the United States

    Unified System

    AASHTO System (American Association of State Highway and Transportation Officials)

    In both systems, soil particles 3 in. or larger in diameter are removed before performing classification tests.

    Lecture 02ECE 404: Construction Technologies & Processes 10

    SOIL CLASSIFICATION: UNIFIED SOIL CLASSIFICATION SYSTEM (USCS)

    STEP 1. DETERMINE ATTERBERG LIMITS

    Plasticity index (PL) = Liquid limit (LL) - Plastic limit (PL)

  • 6Lecture 02ECE 404: Construction Technologies & Processes 11

    STEP 2. CONDUCT SIEVE ANALYSIS AND DETERMINE SOIL GROUPON THE BASIS OF PI AND R200

    SOIL CLASSIFICATION: USCS (CONTD)

    Lecture 02ECE 404: Construction Technologies & Processes 12

    STEPS 3-6. DETERMINE R4 CONTENT AND GET RATIO OFR4/R200. THEN, DETERMINE SOIL TYPE USING THE FOLLOWINGTABLES.

    SOIL CLASSIFICATION: USCS (CONTD)

  • 7Lecture 02ECE 404: Construction Technologies & Processes 13

    SOIL CLASSIFICATION: AASHTO SYSTEM

    AASHTO SYSTEM OF SOIL CLASSIFICATION

    Courtesy of BOMAC Americas

    Lecture 02ECE 404: Construction Technologies & Processes 14

    SOIL CLASSIFICATION: GRADATION CURVE

    Typical gradation curves for coarse-grained soils. (U.S. Army Engineer School)

  • 8Lecture 02ECE 404: Construction Technologies & Processes 15

    SOIL CLASSIFICATION: FIELD IDENTIFICATION

    UNIFIED SYSTEM OF SOIL CLASSIFICATION : FIELD IDENTIFICATION

    Weight passing

    in. (6mm) passing materials : < 50% : gravel

    50% : sand

    No.200 (75m) passing materials

    < 10% : well or poorly graded

    10% : High or low plasticity

    Lecture 02ECE 404: Construction Technologies & Processes 16

    SOIL CLASSIFICATION: FIELD IDENTIFICATION (CONTD)

    DRY STRENGTH TEST AND PLASTICITY

  • 9Lecture 02ECE 404: Construction Technologies & Processes 17

    SOIL SHAKING TEST

    Place soil in palm of hand

    Add water gradually and knead the soil until it begins to get sticky

    Form a ball about in. (19mm) in diameter

    Hold the ball in one hand and tap the back of the hand with the other

    If the ball becomes wet and shiny, it is mostly fine sand or silt

    No reaction suggests clay

    SOIL CLASSIFICATION: FIELD IDENTIFICATION (CONTD)

    Lecture 02ECE 404: Construction Technologies & Processes 18

    CONSTRUCTION CHARACTERISTICSOF SOILS

  • 10

    Lecture 02ECE 404: Construction Technologies & Processes 19

    BASIC RULE OF EARTHWORKS OPERATION

    Cut for the high

    Fill for the low

    EARTHWORK OPERATION

    Lecture 02ECE 404: Construction Technologies & Processes 20

    EARTHWORK OPERATION : FILL & CUT

  • 11

    Lecture 02ECE 404: Construction Technologies & Processes 21

    SOIL VOLUME-CHANGECHARACTERISTICS

    TYPICAL SOIL VOLUME CHANGE DURING EARTHMOVING

    Most excavated materials are found to increase in volume after excavation (bulking or loosing)

    When compacted in the in-situ volume, soils occupy less volume (shrinkage)

    Lecture 02ECE 404: Construction Technologies & Processes 22

    SOIL CONDITIONS

    Bank: Material in its natural state before disturbance. Often referred to as in-place or in-situ. A unit volume is identified as a bank cubic yard (BCY) or a bank cubic meter (BCM).

    Loose: Material that has been excavated or loaded. A unit volume is identified as a loose cubic yard (LCY) or loose cubic meter (LCM).

    Compacted: Material after compaction. A unit volume is identified as a compacted cubic yard (CCY) or compacted cubic meter (CCM).

    SOIL VOLUME-CHANGECHARACTERISTICS (CONTD)

  • 12

    Lecture 02ECE 404: Construction Technologies & Processes 23

    SWELL

    SOIL VOLUME-CHANGECHARACTERISTICS (CONTD)

    % =()

    () 1 100

    EXAMPLE

    Find the swell of a soil that weight 1661 kg/m3 in its natural state and 1186 kg/m3 after excavation.

    Lecture 02ECE 404: Construction Technologies & Processes 24

    SHRINKAGE

    SOIL VOLUME-CHANGECHARACTERISTICS (CONTD)

    % = 1 ()

    () 100

    EXAMPLE

    Find the shrinkage of a soil that weight 1661 kg/m3 in its natural state and 2077 kg/m3 after compaction

  • 13

    Lecture 02ECE 404: Construction Technologies & Processes 25

    LOAD FACTORS

    SHRINKAGE FACTOR (COMPACTION FACTOR)

    SOIL VOLUME-CHANGECHARACTERISTICS (CONTD)

    =()

    ()or

    =1

    1 +

    =()

    ()or

    = 1

    Lecture 02ECE 404: Construction Technologies & Processes 26

    LOAD AND SHRINKAGE FACTORS

    EXAMPLE

    A soil weighs 1163 kg/LCM, 1661 kg/BCM, and 2077 kg/CCM

    Find the load factor and shrinkage factor for the soil

    How many bank cubic meters (BCM) and compacted cubic meters (CCM) are contained in 593330 loose cubic meters of this soil?

    SOIL VOLUME-CHANGECHARACTERISTICS (CONTD)

  • 14

    Lecture 02ECE 404: Construction Technologies & Processes 27

    SOIL VOLUME-CHANGECHARACTERISTICS (CONTD)

    TYPICAL SOIL WEIGHT AND VOLUME CHANGE CHARACTERISTICS*

    Lecture 02ECE 404: Construction Technologies & Processes 28

    WHEN PLANNING AND ESTIMATING EARTHWORK, IT ISFREQUENTLY NECESSARY TO DETERMINE THE SIZE OF THE PILE OF

    MATERIAL THAT WILL BE CREATED BY THE MATERIAL REMOVED

    FROM THE EXCAVATION

    If the pile of material is long in relation to its width, it is referred to as a spoil bank.

    SPOIL BANKS OR PILES

  • 15

    Lecture 02ECE 404: Construction Technologies & Processes 29

    DETERMINE THE DIMENSIONS OF SPOIL BANKS OR PILES

    Convert the volume of excavation from in-place condition (BCY or BCM) to loose conditions (LCY or LCM)

    TRIANGULAR SPOIL BANK

    SPOIL BANKS OR PILES (CONTD)

    Lecture 02ECE 404: Construction Technologies & Processes 30

    CONICAL SPOIL PILE

    SPOIL BANKS OR PILES (CONTD)

  • 16

    Lecture 02ECE 404: Construction Technologies & Processes 31

    TYPICAL VALUES OF ANGLE OF REPOSE OF EXCAVATED SOIL

    SPOIL BANKS OR PILES (CONTD)

    Lecture 02ECE 404: Construction Technologies & Processes 32

    EXAMPLE 1

    Find the base width and height of a triangular spoil bank containing 76.5 BCM if the pile length is 9.14 m, the soil's angle of repose is 37, and its swell is 25%.

    SPOIL BANKS OR PILES (CONTD)

  • 17

    Lecture 02ECE 404: Construction Technologies & Processes 33

    EXAMPLE 2

    Find the base diameter and height of a conical spoil pile that will contain 76.5 BCM of excavation if the soil's angle of repose is 32and its swell is 12%.

    SPOIL BANKS OR PILES (CONTD)

    Lecture 02ECE 404: Construction Technologies & Processes 34

    WHEN PLANNING OR ESTIMATING AN EARTHMOVING PROJECT, IT IS OFTEN NECESSARY TO ESTIMATE THE VOLUME OF MATERIAL

    TO BE EXCAVATED OR PLACED AS FILL

    THE PROCEDURES TO BE FOLLOWED CAN BE DIVIDED INTOTHREE PRINCIPAL CATEGORIES:

    Pit excavations (small, relatively deep excavations such as those required for basements and foundations)

    Trench excavation for utility lines

    Excavating or grading relatively large areas

    PROCEDURES SUGGESTED FOR EACH OF THESE THREE CASES AREDESCRIBED IN THE FOLLOWING SECTIONS.

    ESTIMATING EARTHWORK VOLUME

  • 18

    Lecture 02ECE 404: Construction Technologies & Processes 35

    SMALL, RELATIVELY DEEP EXCAVATIONS SUCH AS THOSEREQUIRE FOR BASEMENTS AND FOUNDATION

    Divide the horizontal area into a convenient set of rectangles, triangles, or circular segments

    Calculate total area (the sum of the segment areas)

    Calculate the average depth

    Calculate volume

    ESTIMATING EARTHWORK VOLUME: PIT EXCAVATIONS

    =

    Lecture 02ECE 404: Construction Technologies & Processes 36

    EXAMPLE

    Estimate the volume of excavation required (bank measure) for the basement shown. Values shown at each corner are depths of excavation. All values are in meter.

    ESTIMATING EARTHWORK VOLUME: PIT EXCAVATIONS (CONTD)

  • 19

    Lecture 02ECE 404: Construction Technologies & Processes 37

    TRENCH EXCAVATION FOR UTILITY LINES

    Calculate the trench cross-section area

    Measure the linear distance along the trench line

    Calculate volume

    ESTIMATING EARTHWORK VOLUME: TRENCH EXCAVATIONS

    =

    Lecture 02ECE 404: Construction Technologies & Processes 38

    CROSS-SECTIONAL AVERAGE METHOD

    ESTIMATING EARTHWORK VOLUME: TRENCH EXCAVATIONS (CONTD)

    = +

    2

    =1

    2

    + 2

    +

    2

    =1

    6 + 4 +

    : ,

  • 20

    Lecture 02ECE 404: Construction Technologies & Processes 39

    EXAMPLE

    Find the volume (bank measure) of excavation required for a trench 0.92 m wide, 1.83 m deep, and 152 m long. Assume that the trench sides will be approximately vertical.

    ESTIMATING EARTHWORK VOLUME: TRENCH EXCAVATIONS (CONTD)

    Lecture 02ECE 404: Construction Technologies & Processes 40

    EXCAVATING OR GRADING RELATIVELY LARGE & COMPLEX AREAS

    Divide the area into a grid indicating the depth of excavation or fill at each grid intersection

    Assign the depth at each comer or segment intersection a weight according to its location (number of segment lines intersecting at the point)

    Interior points : a weight of four

    Exterior points : a weight of two

    Corner points : a weight of one

    ESTIMATING EARTHWORK VOLUME: LARGE AREAS

    =

  • 21

    Lecture 02ECE 404: Construction Technologies & Processes 41

    EXAMPLE

    ESTIMATING EARTHWORK VOLUME: LARGE AREAS (CONTD)

    Lecture 02ECE 404: Construction Technologies & Processes 42

    ESTIMATING EARTHWORK VOLUME: LARGE AREAS (CONTD)

    1 4 3 4

    1 1 2 2 4

    2 2 2 3 4

    5 1 2 3 4

    1 2 3 4

    4

    4

    4

    4

    2 3 44

    abV y y y y

    abV h h h h

    abV h h h h

    abV h h h h

    abV h h h h

    SQUARE PILLAR

  • 22

    Lecture 02ECE 404: Construction Technologies & Processes 43

    ESTIMATING EARTHWORK VOLUME: LARGE AREAS (CONTD)

    1 4 3

    1 1 4 4

    2 3 4 4

    6 1 2 4

    1 2 3 8

    6

    6

    6

    6

    2 3 86

    abV y y y

    abV h h h

    abV h h h

    abV h h h

    abV h h h h

    PRISM

    Lecture 02ECE 404: Construction Technologies & Processes 44

    EXAMPLE

    Find the volume of excavation required for the area shown in Figure. The figure at each grid intersection represents the depth of cut at that location.

    ESTIMATING EARTHWORK VOLUME: LARGE AREAS (CONTD)

  • 23

    Lecture 02ECE 404: Construction Technologies & Processes 45

    EARTHWORK CALCULATION SHEET(TABLE)

    Area (m2)

    *Average

    Area

    (m2)

    **Vol. of

    soil

    (m3)

    Area

    (m2)

    Average

    Area

    (m2)

    Vol. of

    soil

    (m3)

    Compaction

    factor

    (C)

    1Revised

    Vol.

    (m3)

    11 21.6 8.3 963.3

    12 20 29.4 25.5 510.0 1.3 4.8 96.0 0.9 106.7 403.3 1366.6 106.7

    13 12.5

    14 7.5

    15 20

    16 20

    Total

    * Average area is the average of previously and currently measured areas

    **Volume of soil = Average area x distance1Revised vol. of soil = vol. of soil / compaction factor2"+" means cutting of soil while "-" imply filling of soil3Cumulative vol. of soil4At the same station no, select small vol. of soil betwwen cutting and filling of soil

    Cutting of soil (Used in fiiling) Filling of soil 2Calculated

    Soil (m3)

    Excess (+)

    Short (-)

    3Cumulative

    Vol.

    (m3)

    4Vol. (m3)

    horizontal

    direction

    Station No. Distance

    EARTHWORK CALCULATE SHEET (TABLE) IS REQUIRED TO DRAWMASS DIAGRAM

    Lecture 02ECE 404: Construction Technologies & Processes 46

    EARTHWORK CALCULATION TABLE: HIGHWAY CONSTRUCTION

  • 24

    Lecture 02ECE 404: Construction Technologies & Processes 47

    IN ORDER TO MINIMIZE MATERIAL WASTE OR BORROW, IT ISNECESSARY TO PRODUCE WHAT IS CALLED A MASS HAULDIAGRAM

    A PLOT OF CUMULATIVE VOLUME OF SOIL AGAINST DISTANCEALONG THE ROAD

    CUT VOLUMES ARE TAKEN TO BE POSITIVE AND FILL VOLUMESTO BE NEGATIVE

    COMMON IN ROADWAY OR AIRFIELD

    PREPARED BY HIGHWAY AND AIRFIELD DESIGNERS TO ASSIST INSELECTING AN ALIGNMENT

    MASS (HAUL) DIAGRAM

    Lecture 02ECE 404: Construction Technologies & Processes 48

    MASS (HAUL) DIAGRAM (CONTD)

  • 25

    Lecture 02ECE 404: Construction Technologies & Processes 49

    THE VERTICAL COORDINATE OF THE MASS DIAGRAM CORRESPONDING TOANY LOCATION ON THE ROADWAY PROFILE REPRESENTS THE CUMULATIVE

    EARTHWORK VOLUME FROM THE ORIGIN TO THAT POINT

    WITHIN A CUT, THE CURVE RISES FROM LEFT TO RIGHT

    WITHIN A FILL, THE CURVE FALLS FROM LEFT TO RIGHT

    A PEAK ON THE CURVE REPRESENTS A POINT WHERE THE EARTHWORKCHANGES FROM CUT TO FILL

    A VALLEY (LOW POINT) ON THE CURVE REPRESENTS A POINT WHERE THEEARTHWORK CHANGES FROM FILL TO CUT

    WHEN A HORIZONTAL LINE INTERSECTS THE CURVE AT TWO OR MOREPOINTS, THE ACCUMULATED VOLUMES AT THESE POINTS ARE EQUAL. THUS, SUCH A LINE REPRESENTS A BALANCE LINE ON THE DIAGRAM.

    MASS (HAUL) DIAGRAM (CONTD)

    Lecture 02ECE 404: Construction Technologies & Processes 50

    CONSTRUCTION USE OF THE MASSDIAGRAM (CONTD)

    USING THE MASS DIAGRAM

    The length and direction of haul within a balanced section

    The average length of haul for a balanced section

    The location and amount of borrow (material hauled in from a borrow pit) and waste (material hauled away to a waste area) for the project

    Selection of type of equipment for accomplishing the work

    Selection of construction method

  • 26

    Lecture 02ECE 404: Construction Technologies & Processes 51

    CONSTRUCTION USE OF THE MASSDIAGRAM (CONTD)

    EXAMPLE

    Figure 1 shows the mass diagram of earthwork.

    (1) What is the total amount of soil (m3) between A and B?

    (2) What is the average distance (m) between A and B? Figure 1. Mass diagram