    Earthwork Volume using Simpson's RuleStep by step procedure to find out the volume of earthwork using Simpson's Rule

     

    This article is about using Simpson's rule to find out the quantity of earthwork using contour maps. The procedure is explained with the help of an example. In the example given below the map is divided in to 6 horizontal and 6 vertical grids each of 5m interval. The reduced levels are given at the intersections.

     

    Suppose the final level for filling is 24.1m. Then the required depth of filling at each point is as given in the table below 

    The area on the side of each grid can be found out as follows

     

    Each side can be considered as a trapezoid. Hence the area of each side 

    eg: (0.98+0.97)/2 x 5 = 4.875

  • 8/18/2019 Earthwork Volume by Simpson's Rule - Civil Engineering Applications and Tips.pdf

    2/2

    10/1/2015 Earthwork Volume by Simpson's Rule - Civil Engineering Applications and Tips

    http://www.howtoexcel.info/Civil_Engineering/Earthwork_Volume.htm

     (0.80+0.80)/2 x 5 = 4.000

      Now the volume according to Simpson's rule is as follows 

    eg: (4.875+3.375)=8.25 4 x (4+3.75+3.925)=46.7 2 x (3.575+3.875)=21.65 Total = 76.6 

    Total earth filling volume = 373.83 x (d/3)

     =373.83 x (5/3) = 623 M3

    More Articles in Civil Engineering

    Are Contractors Entitled for Variations in Lump Sum Contracts? - Read Article

    What is Day Work in Construction Contracts? - Read Article

    How to Calculate Earthwork Volume Using Simpson's Rule? - Read Article

    What is Contingency Allowance in a Construction Contract? - Read Article

    What is Clause 14 programme? - Read Article

    What is FIDIC? - Read Article

    What is Prime Cost Sum in Construction Contracts? - Read Article

    What is Provisional Sum in Construction Contracts? - Read Article

    What is TOR Steel? - Read Article

     

    http://www.howtoexcel.info/Civil_Engineering/TOR_Steel.htmhttp://www.howtoexcel.info/Civil_Engineering/Provisional_Sum.htmhttp://www.howtoexcel.info/Civil_Engineering/Prime_Cost_Sum.htmhttp://www.howtoexcel.info/Civil_Engineering/What_is_FIDIC.htmhttp://www.howtoexcel.info/Civil_Engineering/Clause14_Programme.htmhttp://www.howtoexcel.info/Civil_Engineering/Contingency_Allowance.htmhttp://www.howtoexcel.info/Civil_Engineering/Earthwork_Volume.htmhttp://www.howtoexcel.info/Civil_Engineering/Day_Work.htmhttp://www.howtoexcel.info/Civil_Engineering/Lumpsum_Variation.htm