    Jakarta , 17 July 2012

    Readiness of PLN to Utilize Renewable Energy (Capacity,

    Bankable Power Purchase Agreement and Feasibility Study,

    Pricing)

    PT PLN (Persero)

    PT PLN ( Persero )

    EBTKE CONEX 2012

  • PLN has been ready since quite long time. PLN has a long history in using greenenergy for its electricity generation especially as PLN project.

    How about IPPs Project? Great opportunity for private to make a PPA with PLN in IPP Schemes, RE or

    Non RE Data said that very low success ratio of IPPs project compared to PLN project

    and the problem is not the readiness o PLN Readiness of PLN in not necessary for questioned and has been realised by:

    o Stated on RUPTL (RE is priority nor leas cost)o Consistenly support the goverment policieso Support the IPP project : entertaint the IPP developer when required

    for continuation the project

    Utilizing RE for Electricity, is PLN ready?

  • Gas

    Geothermal

    LNG

    HSD MFO

    Coal

    IPPs project, front (study) to end (electricity delivered)

    Study (Preliminary, Pra FS, FS) : dev. responsibility technical (duration & quality) andfinancial

    Permits : government (local, forestry, MeMR) permits and approval

    Procurement : Pricing and PPA

    Financial Closing : equity and loan

    Construction : developer responsibility technical (duration and quality) and financial

    Operation : developer responsibility technical (O/M) and financial

    PLN has an intensive involvement only in procurement (pricing and PPA)

    PLN concern to capacity, energy production, energy price, availability and continuity

    Pricing for RE, PLN implements the government regulation (FIT or B 2 B) and PPA is negotionable

    Pricing and PPA are not main problem, main constraint generally due to permits and internaldeveloper (capability in technical and financial)

    Are the PPA and Pricing as the main problem?

    2

  • Gas

    Geothermal

    LNG

    HSD MFO

    Coal

    IPP for MHEPP status

    3

    Number Installed Capacity (kW) Number Installed Capacity (kW)

    Indonesia Barat 67 398,731

    Operasi 7 21,095 7 21,095

    Konstruksi 10 71,868 17 92,963

    PPA 19 137,900 36 230,863

    Ijin ESDM 15 68,210 51 299,073

    Proposal 16 99,658 67 398,731

    Indonesia Timur 48 162,770

    Operasi 8 26,340 8 26,340

    Konstruksi 19 62,600 27 88,940

    PPA 5 12,550 32 101,490

    Ijin ESDM 12 49,980 44 151,470

    Proposal 4 11,300 48 162,770

    Jawa Bali 68 214,119

    Operasi 8 2,055 8 2,055

    Konstruksi 12 26,210 20 28,265

    PPA 10 38,570 30 66,835

    Ijin ESDM 27 109,434 57 176,269

    Proposal 11 37,850 68 214,119

    Total Indonesia 183 775,620

    Total Operasi 23 49,490 23 49,490

    Total Konstruksi 41 160,678 64 210,168

    Total PPA 34 189,020 98 399,188

    Total Ijin ESDM 54 227,624 152 626,812

    Total Proposal 31 148,808 183 775,620

    IPP CumulativeRegion

    REKAPITULASI STATUS PLTM IPP

    12 Juli 2012

    IPP for MHEPP

    Total PPA : 98

    Construction/FC : 41

    Operated : 23

    F/C problem : 11

    Construction problem : 14

  • Gas

    Geothermal

    LNG

    HSD MFO

    Coal

    IPP Geothermal status

    4

    MODEL PENGEMBANGAN

    SESUAI PERMEN ESDM 01/2012

    PIC PROBLEMSJUMLAH PROYEK

    TOTAL KAPASITAS

    (MW)

    PLTP PLN (EKSPLORASI DAN PENDANAAN) 1 20 PLN TULEHU

    PLTP PLN (HILIR)-PGE (HULU) 4 300 PLN, PGEHULULAIS, S. PENUH, KOTAMOBAGU(TEHNICAL AND PERMITS PROBLEM)

    PLTP IPP - KONTRUKSI / FC SELESAI 2 170 DEVELOPER PATUHA UNIT 1, ULUBELU 3 & 4

    PLTP EKSTENSION/WKP EXISTING SIAP IMPLEMENTASI

    8 1115DEVELOPER

    , PLN

    LUMUT BALAI, LAHENDONG 5 & 6, KARAHA BODAS 1, KAMOJANG 5 (F/C DELAY)

    W. WINDU (PERMITS, TECHNICAL AND PRICING)

    SARULLA I (JOC)

    DIENG 2&3 (PRICING)

    PATUHA 2 & 3 (TECHNICAL)

    CIBUNI (LEGAL INTERNAL DEV)

    PLTP WKP EXISTING MENUNGGU PROPOSAL / BELUM EKSPLORASI

    3 395 DEVELOPER

    KARAHA BODAS 2&3, KAMOJANG 6 (PERMITS)

    T. PERAHU II (TECHNICAL AND PRICING)

    I.ARGOPURO (PERMITS AND TECHNICAL)

    SARULLA II (TECHNICAL)

  • Gas

    Geothermal

    LNG

    HSD MFO

    Coal

    IPP Geothermal status

    5

    MODEL

    SESUAI PERMEN ESDM 01/2012

    PIC PROBLEMSJUMLAH PROYEK

    TOTAL KAPASITAS

    (MW)

    PLTP WKP BARU ESC/PPA SELESAI 3 445 DEVELOPERATADEI, MUARALABOH, RAJABASA(EXPLORASI, F/C)

    PLTP WKP BARU (SURAT PENUGASAN SDH TERBIT DALAM PROSES/NEGOSIASI ESC/PPA)

    13 1515DEVELOPER

    , PLN

    SOKORIA, T.PERAHU I, C.CISUKARAME, TAMPOMAS (PRICING)

    GUCI, R.DADAP, BATURADEN, NGEBEL, R.DANO, UNGARAN, SUOH SEKINCAU, S.MERAPI, JABOI (PPA PROCESS)

    PLTP WKP BARU (PROSES PENERBITAN SURAT PENUGASAN)

    3 140 KESDM JAILOLO, HUU, IJEN

    PLTP WKP BARU (IUP BELUM TERBIT/TENDER PEMDA BELUM SELESAI)

    14 825 PEMDA

    S.AGAM, D.RANAU, BONJOL, SIPOHOLON, S.SAMOSIR, WAY RATAI, GN. ENDUT, U.TELOMOYO, GN. CEREMAI, SEMBALUN, BORA, S. WAYAUA, MERANA/MASAINGI, MATALOKO

    TOTAL 51 4925

    From total of 51 projects :

    Pricing problem faced by only 7 projects

    PPA process : 9 project

  • Gas

    Geothermal

    LNG

    HSD MFO

    Coal

    PLN has entertaint IPP projects, which had faced financial problem due to problems ofdevelopers scope. Renegociate the increasing price :

    2009 2011 : 25 IPP and 15 have been ammended

    2011 2012 : 6 IPP and 2 have been ammended

    Preliminary evaluation : after ammended with better price less than 50% of IPP terkendademonstrate promising progress.

    Lesson :

    Price is not main problem

    Higher price does not guarantee the successful of the project

    Higher price in some cases invite other stakeholder (brokers etc.), the incentives do not go tothe right stake holder (profesional developers)

    Unsuccess story on IPP terkendala

    6

  • Government (central and local) support required: Establish clear and harmonic regulation Commit to proceed issues regarding permission certainly and progresively Sinergic relationship between central and local government Controling (monitor and supervise) the progress of RE development Facilitating to enhance technical, financial and social aspect

    Private Iniciatives required: Preparing internal capability (technical & financial) seriously Commit to undertake each steps of development inline / meet the

    regulation and PPA including procedure, cost, schedule and quality Profesional communication with other stake holder especially government

    and buyer/PLN

    Government Support and Private Iniciative

  • Thank you

    8

    http://www.flickr.com/photos/valanne/432271395/

  • Gas

    Geothermal

    LNG

    HSD MFO

    Coal

    IPP Geothermal status

    9

    MODEL

    SESUAI PERMEN ESDM 01/2012

    PIC PROBLEMSJUMLAH PROYEK

    TOTAL KAPASITAS

    (MW)

    PLTP WKP BARU ESC/PPA SELESAI 3 445 DEVELOPERATADEI, MUARALABOH, RAJABASA(EXPLORASI, PERMITS, F/C)

    PLTP WKP BARU (SURAT PENUGASAN SDH TERBIT DALAM PROSES/NEGOSIASI ESC/PPA)

    13 1515DEVELOPER

    , PLN

    SOKORIA, T.PERAHU I, C.CISUKARAME, TAMPOMAS (PRICING)

    GUCI, R.DADAP, BATURADEN, NGEBEL, R.DANO, UNGARAN, SUOH SEKINCAU, S.MERAPI, JABOI

    PLTP WKP BARU (PROSES PENERBITAN SURAT PENUGASAN)

    3 140 KESDM JAILOLO, HUU, IJEN

    PLTP WKP BARU (IUP BELUM TERBIT/TENDER PEMDA BELUM SELESAI)

    14 825 PEMDA

    S.AGAM, D.RANAU, BONJOL, SIPOHOLON, S.SAMOSIR, WAY RATAI, GN. ENDUT, U.TELOMOYO, GN. CEREMAI, SEMBALUN, BORA, S. WAYAUA, MERANA/MASAINGI, MATALOKO

    TOTAL 51 4925

  • Existing Total Capacity 34,928 MW

    Generation Capacity (type and ownership) 2011

    2.756

    2.871

    8.112

    12.170

    3.503

    440

    130

    477

    285

    3.142

    347

    695

    0 2.000 4.000 6.000 8.000 10.000 12.000 14.000

    Diesel PP

    GTPP

    CCPP

    Coal STPP

    HEPP

    Geothermal

    IPP (MW) PLN (MW)

  • Share of RE in National Installed Capacity and Electricity Produced

    Fuel oil, 23.%

    Hydro, 7%

    Nat.Gas, 21%

    Coal, 44%

    Geothermal and other, 5.%

    National (PLN+ IPP) installed

    capacity power plant (RE 14%)

    Electricity generated based on

    primary energy (RE 12%)

  • Fuel Mix Projection 2011-2020 (in percentages)

    Gas

    Geothermal

    Hydro

    LNGHSD

    MFO

    Coal

    Share of RE plan to increase from 11 % (2011) to 18 % ( 2020 )

    6% 6% 6% 5% 5% 6% 6% 6% 6% 6%

    5% 4% 4% 5%8% 8%

    10% 11% 12% 12%

    50% 54%

    61% 63%63%

    64%64%

    65% 64% 64%

    17%

    21%

    21%19% 17%

    15% 12% 8% 8% 8%

    0%

    4%

    3%5% 6% 5% 7% 9%

    9% 8%

    5%

    2%

    1.1%0% 0% 0% 0% 0% 0% 0%

    16.12%

    8.57%3.93%

    1.81% 0.99% 0.88% 0.77% 0.70% 0.70% 0.71%

    0%

    10%

    20%

    30%

    40%

    50%

    60%

    70%

    80%

    90%

    100%

    2011 2012 2013 2014 2015 2016 2017 2018 2019 2020

    Impor Biomass Surya/Hybrid HSD MFO LNG Gas Batubara Geothermal Hydro

    -

    50,000

    100,000

    150,000

    200,000

    250,000

    300,000

    350,000

    400,000

    2011 2012 2013 2014 2015 2016 2017 2018 2019 2020

    GW

    h

    Impor Biomass Surya/Hybrid HSD MFO LNG Gas Batubara Geothermal Hydro

  • MW

    1313

    4,477

    5,372

    4,283

    2,357 2,254 1,992 1,780 1,718

    3,019

    4,102

    1,106

    1,505

    688

    1,917

    3,690

    5,172

    4,656

    2,463

    2,015

    780

    -

    1,000

    2,000

    3,000

    4,000

    5,000

    6,000

    7,000

    2011 2012 2013 2014 2015 2016 2017 2018 2019 2020

    IPP

    PLN

    Total : 55,345 MW ( 31.353 MW of PLN and

    23,993 MW of IPP)

    About 5.500 MW/year additional capacity

    5,583

    6,877

    4,971

    4,271

    5,941

    7,164

    6,436

    4,181

    5,034 4,882

    -

    1,000

    2,000

    3,000

    4,000

    5,000

    6,000

    7,000

    8,000

    2011 2012 2013 2014 2015 2016 2017 2018 2019 2020

    PLTU PLTA PLTP PLTGU PLTG PLT Lain Total

    Power Plant Capacity Development Plan (2011-2020)

    CFPP : 35,573 MW

    M/HPP : 5,723 MW

    GPP : 6,247 MW

    CCPP : 3,263 MW

    GTPP : 4,093 MW

    Others : 441 MW

    Total : 55,345 MW

    MW

  • 14

    RE Potential and Development Plan

    NORENEWABLE

    TYPEPOTENCY

    INSTALLED

    CAPACITY

    ADDITIONAL CAPACITY PROGRAM(2011-2020)

    1 Hydro power 75.670 MW 5.705 MW 5222 MW

    2 Geothermal 29.038 MW 1.209 MW 6247 MW

    3 Mini/Micro Hydro 769 MW 218 MW 501 MW

    4 Biomass 49.810 MW 61 MW 374 MW

    5 Solar power 4,80 kWh/m2/day 13,5 MW 592 MW

    6 Wind power3 6 m/s (9.290

    MW)1,87 MW 140 MW

    Source : RIPEBAT 2010-2025 updated from multiple sources and RUPTL 2011-2020