Upload
kakalakas
View
227
Download
4
Tags:
Embed Size (px)
DESCRIPTION
Ecra Activities Report 2011
Citation preview
Activities & Achievements of the Authorityin 2011
June 2012
2 ECRA
Our Mission .................................................................................................................
To insure that supplies of electricity and desalinated water products provided to consumers in the Kingdom are: • Adequate• Reliable• Of high quality, and• Fairly priced
.................................................................................................................
12011 Activities & Achievements
2 ECRA
32011 Activities & Achievements
4 ECRA
Contents
52011 Activities & Achievements
6 ECRA
Subject Page
Summary of the Report 11
Part IGeneral Background on
the Electricity and Water Desalination Sector, and the Authority15
The Electricity and Water Desalination Sector 16
Overview of the Authority 17
Part IIActivities and Achievements of the Authority in 2011
23
Consumer Care and Service Providers Affairs 24
1- Electricity Outages 24
a) Statistical Study of Causes of Electricity Outages 24
b) Mahayil-Asir Electricity Network Study 25
2- Review of SEC’s Safety Procedures 26
3- Electricity Industry Accidents Reporting Procedures 27
a) Workshops 27
b) Second Edition of the Procedures 27
c) Administering the Procedures 27
4- Regulating the Consumer-Service Provider Relationship 27
a) Agreement for Service Connection at the Distribution Voltage 28
b) Consumer Agreement 28
c) Rules for Electricity Service Disconnection 28
5- Rules for Relocation of Overhead Electricity Networks 28
6- Electricity Service to Consumers with Special Needs 28
72011 Activities & Achievements
Subject Page
7- Rules and Procedures for Consumer Care and Service Providers Affairs 29
8- Consumer Complaints 30
a) Management of Complaints System 30
b) Complaints Regarding SEC 30
9- Electricity Connection to Farms, Villages, Hamlets, and Settlements 33
Tariffs 34
1- Service Connection to the Distribution Network - Setting Charges According to Breaker Capacity
34
2- Time-of-Use Tariff for Non-Residential Consumers 35
3- Electricity Industry Data and Tariff Computations Program 35
4-ClassificationofSaudiAramcoElectricityMeters 36
Codes and Regulations 37
1- Saudi Electricity Transmission Code 37
2- Seawater Desalination Code 37
3- Charges for Use of Transmission System 37
4- Supervision of Codes and Regulations 38
a) Saudi Electricity Transmission Code Supervisory Committee 38
b) Saudi Electricity Distribution Code Supervisory Committee 38
Licensing 39
1- Authorizations 39
2- Licenses 40
3- Exemptions from Licensing 40
4- License Forms 40
8 ECRA
Subject Page
Electricity and Desalinated Water Industry Plans 41
1- Electricity Industry Restructuring Plan 41
2- Long Range Plan for Electricity 43
3- Development of Long Range Plan for Water Desalination 44
4- Electricity and Water Desalination Industry Data 44
Standards, Quality of Service, and Performance Monitoring 45
1- Licensees’ KPIs 45
2- Financial and Accounting KPIs for SEC 47
3- Development of Electricity Demand-Side Management Program 47
4- Standardization of Distribution Voltage 49
Electronic Management and IT 50
1- E-Management 50
2- ECRA’s Website 50
3- Oracle Program 50
Other Activities 51
1-ElectricityBillPaymentAssistancetoRecipientsofSocialSecurityBenefits 51
2- GCC Electricity Interconnection 51
3- Saudi Arabia-Egypt Electricity Interconnection 52
4- The Annual Electricity Statistical Booklet 52
Human Resources and Finances 53
1-Human Resources 53
2-Training and Manpower Development 53
3-Financial Data 54
92011 Activities & Achievements
Subject Page
Part IIIReport of the Electricity Industry Dispute Resolution Committee
59
Introduction 60
Composition of the Committee 60
Charges of the Committee 60
Modus Operandi of the Committee 61
Activities of the Committee 61
Part IVThe Electricity and Water Desalination Industry in the Year 2011
65
The Electricity Industry in 2011 66
The Electricity Tariff in the Kingdom 74
Water Desalination in 2011 84
Participation of the Private Sector in the Electricity and Water Desalination Industry 90
The Appendices 93
Appendix (1): Authorizations, Licenses, and Exemptions from Licensing 94
Appendix (2): Documents and Information available on ECRA’s Website 99
The Board of DirectorsManagement of the Authority
105
10 ECRA
Summary of the Report
112011 Activities & Achievements
12 ECRA
This report consists of four parts.
***
Part I contains a general background of the
electricity and water desalination sector in Saudi
Arabia, and a brief overview of the Electricity &
Cogeneration* Regulatory Authority (ECRA).
***
Part 2 aims to give a complete picture of the
Authority’s activities and achievements in 2011
which included the following accomplishments in
the areas within ECRA’s purview:
Consumer Care
• Continuation of monitoring power interruptions
and studying their causes.
• Investigation of the condition of the Mahayil-
Asir electrical network.
• Organization of several workshops on the procedures
for reporting electricity industry accidents.
• Completing preparation of agreement for
service connection to the distribution network,
consumer agreement, and rules for service
disconnection.
• Completing drafting the rules and procedures
for providing electricity services to persons with
special needs.
• Preparing a draft of the rules for relocation of
overhead electricity network segments.
• Issuing the second edition of the “Rules and
Procedures for Reporting Electricity Industry
Accidents”.
* Cogeneration: The simultaneous production of electricity and desalinated water (or steam) used in other production processes.
• Commencing preparation of the database for
electricity industry accidents.
• Preparation of the terms of reference for the
project to draft the rules, regulations and
procedures for Consumer Care and Service
Providers’ Affairs.
• Commencement of work on creating a system to
handle consumer complaints.
• Resolution of some 88% of the 447 consumer
complaints received by the Authority concerning
electricity services.
• Continuation of ECRA’s participation in the
activities of the committee for electricity
connection to farms and villages plan.
Tariffs
• Setting charges for service connection to the
distribution network based on breaker capacity.
• Completingreviewofthefinalresultsofthe
pilot project conducted by the Saudi Electricity
Company (SEC) to improve consumers power
factor.
• Continuing actual implementation of the
automated system for management of the
electricity industry information database.
• ClassificationofSaudiAramcoelectricity
meters.
Codes and Regulations
• Enactment of the Seawater Desalination Code.
• IssuanceofcertainmodificationstotheSaudi
Transmission Code.
• Commencement of work on developing
regulations for use of the transmission system.
132011 Activities & Achievements
Licensing
• By the end of the reporting year, the following
authorizations, licenses, and exemptions were issued:
- Nine authorizations to commence studies to
undertake projects in electricity generation,
cogeneration, and water desalination.
- Thirtyfivelicensesforelectricitygeneration,
transmission, trading, distribution,
cogeneration and water desalination.
- Twelve exemptions from licensing for
electricity generation, cogeneration and
water desalination plants.
• Completingthedraftofthefinalformofthe
Energy Principal Buyer license, and the license
for mobile electricity generation units.
Electricity and Water Desalination Industry Plans
• Following up of implementation of the
electricity industry restructuring plan.
• Preparation of terms of reference for a study to
develop a fuel plan for electricity generation
and water desalination.
Standards, Quality of Service, and Performance
Monitoring
• Measurement of KPIs of service providers for the
firsttimeintheKingdom.
• ImplementationofSEC’sfinancialand
accounting KPIs.
• Completion of the study on development of
electric energy demand-side management
programs.
Other Activities
Continuing implementation of the program for
electricitybillpaymentassistancetobeneficiaries
of social security in association with the Ministry of
SocialAffairs.Thenumberofbeneficiariesin2011
reached 241,000.
The Authority continued the process of building
its internal infrastructure, streamlining its business
operations, and making further strides in its move
towards E-management.
***
Part III of the report outlines the activities of the
Electricity Industry Dispute Resolution Committee *
showing that the committee’s docket during the year
had 126 cases, of which 64 were adjudicated by the
committee.
***
Part IV of the report contains a description of the
state of the electricity and water desalination
industry** in the Year 2011 and other issues related
to this industry.
* Electricity Industry Dispute Resolution Committee: A committee, independent of the Authority, formed by a Council of Ministers decision
** The electricity and water desalination industry: Electricity services that Persons undertake or intend to undertake, which include electricity generation, cogeneration, transmission of electricity, its distribution, supply and trading; water desalination, its transportation to points of distribution, and trading in desalinated water.
14 ECRA
Part IGeneral Backgroundof the Electricity and
Water Desalination Sector,and the Authority
152011 Activities & Achievements
16 ECRA
The Electricity and Water Desalination Sector
Components of the Sector
The electricity and water desalination sector is composed
of the following elements:
The Ministry of Water and Electricity: which is
responsible for establishing overall policies, plans, and
strategies for the Electricity and Water Desalination
Industry.
The Electricity & Cogeneration Regulatory Authority
(ECRA): which is responsible for regulating the Electricity
and Water Desalination Industry and issuing licenses
to any person engaged in any of its activities. Details of
the goals, objectives, and responsibilities of ECRA are
contained in the following section of this report.
The Electricity and Water Desalination Industry: which
consists of entities licensed by ECRA, such as the Saudi
Electricity Company (SEC), Saline Water Conversion
Corporation (SWCC), and others as listed later in this
report. These entities generate electricity, produce
desalinated water (with or without simultaneous
production of electricity) or steam (with simultaneous
production of electricity), transmit or transport these
products, distribute them to consumers, or trade in them.
The Consumers: who purchase the products of the
electricity and water desalination industry for their own
use.
The electricity and water desalination industry, in turn,
consists of two components:
• The Electricity Industry: SEC is the dominant player
in this industry as explained later in this report. It
is a joint stock company whose shares are traded
publicly in the Saudi Capital Market. Over 81% of
the company’s shares are owned by the Government
and Saudi Aramco. The company performs the
functions of electricity generation, transmission*,
anddistribution.SWCCgeneratesasignificant
share of the electricity sold by SEC. A few producers
supply electricity to captive customers. Several
Independent Power Projects (IPPs) and Independent
Water and Power Projects (IWPPs) are currently in
operation and some are under construction or in
advanced stages of bidding.
ECRA’s Board has approved plans for restructuring the
electricity industry** by unbundling its main activities
of generation, transmission and distribution. The aim of
the unbundling is to create an environment conducive
to competition wherever possible. It is clear that
competition will be easiest in generation, but eventually
competition will be introduced in the retail business
(non-wire related) of distribution and services.
• The Water Desalination Industry: At the present
timeSWCCistheonlysignificantplayerinthe
water desalination arena. SWCC is currently a
government agency but has over the past few
years worked diligently on plans to privatize all its
operations. These plans have received government
approval, and SWCC management is working
on implementation of the approved plans. It is
anticipated that the outcome of the privatization
process will be introduction of real competition in
this industry which hitherto has been absent. Several
IWPPs are in operation and more projects are under
construction or in the process of bidding and when
completed and operational, these plants will supply
a major portion of the desalinated water requirement
in the Kingdom.
* The Saudi Electricity Transmission Company (SETC) was recently established. It is a joint stock company, wholly owned by SEC. SETC is responsible for transmitting electricity from the generation plants to the distribution network system.
** See page 41 (The Electricity Industry Restructuring Plan).
172011 Activities & Achievements
Overview of the Authority
Introduction
The Electricity & Cogeneration Regulatory Authority
(ECRA) was established in 1422* AH (2001) with the
aim of insuring that consumers in the Kingdom obtain
electricity supplies; and products of cogeneration and
water desalination that are adequate, reliable, of high
quality, and at reasonable prices.
To carry out this objective the Authority monitors the
performance of service providers, within a regulatory
framework that is consistent with the government’s laws,
its decisions and policies, and the applicable standards
in the Kingdom as well as international best practices.
The main goals of the Authority are:
• Protection of the public interest and the rights of
consumers.
• Promotion of consumer oriented electricity, water
desalination, and cogeneration services that protect
the consumer’s right of choice among competing
service providers.
• Encouragement of private sector investors to
participate and invest in the development of the
Saudi electricity and water desalination industry,
protecting their interests, and enabling them to
realize fair economic returns on their investments.
• Formation of a clear, transparent, stable, and
non-discriminatory regulatory framework for the
electricity and water desalination industry.
• Creation of a favorable environment that encourages
legitimate and fair competition among providers and
suppliers of electricity and in the water desalination
industry.
The Electricity Law and the Authority’s Charter delineate
the responsibilities entrusted to ECRA by the government
inorderforittoachieveitsobjectives.Specifically,these
responsibilities cover four areas as follows:
• Supply Matters - issuing licenses for generation,
transmission, distribution, retailing, and trading
of electricity and cogeneration services as well
as production, trading, and transportation of
desalinated water; monitoring licensees’ compliance
with their license requirements and conditions;
developmentofunifiedregulatoryaccountingand
reporting procedures for electricity, cogeneration,
and desalination providers; coordination of
the infrastructure of the electricity and water
desalination industry, and development of the
expansion plans of these industries.
* The Authority was established by Council of Ministers Decision Number 236 issued on 27/8/1422AH (13 November 2001). On 17/5/1425AH (5 July 2004) the Council of Ministers, by Decision Number 163, assigned to the Authority the additional responsibility of regulating the cogeneration industry. Consequently, the Authority’s name was revised to the current appelation of “ Electricity & Cogeneration Regulatory Authority” (ECRA). On 4/5/1428AH (21/5/2007) the Council of Ministers enacted a new charter for the Authority through the Council’s Decision Number 154 that included addition of the regulation of production and transportation of desalinated water to the existing ECRA remit.
18 ECRA
• Consumer Issues - assessment of tariffs charged
for supply of electricity, cogeneration, and water
desalination services, periodic review of these tariffs,
proposing (as needed) new tariffs to the government,
protecting interests of stakeholders in the industry,
investigating and resolving complaints by involved
parties, and improving industry performance.
• Technical Issues - developing and issuing best
practice codes and standards, insuring adequacy
of the R&D activities of the electricity and
water desalination industry, promoting energy
conservation measures in coordination with the
Ministry of Water and Electricity (MoWE), and
handling other relevant technical matters.
• Organizational and Administrative Tasks -
definingpublicinterestwithregardtothe
electricity and water desalination industry,
development of regulations for expansion of
the infrastructure of the industry, encouraging
private sector participation and investments,
and issuing periodic reports to the Council
of Ministers on costs and tariffs of electricity,
cogeneration, and desalination services.
Organizational Structure
ECRAisafinanciallyandadministratively
autonomous organization, supervised by a board
of directors chaired by the Minister of Water and
Electricity, with the Governor of the Authority as
deputy chair, six members from senior government
officialsrepresentingtheministriesofWaterand
Electricity, Finance, Petroleum & Mineral Resources,
Commerce & Industry, Economy & Planning,
andSWCC;andfivemembersselectedontheir
own merits. The section entitled “The Board and
Management of the Authority” (page 105) shows
the composition of the Board in 2011.
The board is the ultimate authority to supervise
ECRA’s affairs, adopt policies and plans for its
operations, pursue implementation of laws and
regulations, and issue directives related to public
policies and approved plans of the electricity
industry.
The Authority is headed by the Governor who is
appointed by a Royal Order at the ministerial rank
of “Distinguished Grade”. He is the chief executive
andoperatingofficeroftheAuthority.
192011 Activities & Achievements
The Governor is assisted by three vice-governors,
and a number of permanent and temporary advisors
and consultants. The information technology, the
public relations departments, and the internal
auditing unit report directly to the Governor.
Each vice-governor heads a sector of ECRA’s
operations as follows:
1- Vice-Governor for Consumers and Service
Providers Affairs
Supervises the following two departments:
Consumer Care: handles documentation of
consumers’ rights and responsibilities, investigates
their complaints and claims of violations by
service providers, prepares cases for referral to the
Electricity Industry Dispute Resolution Committee,
and periodically reviews causes of consumers’
complaints and disputes in order to suggest
appropriate rules and procedures to eliminate them.
Service Providers Affairs: handles documentation
of service providers’ rights and obligations, reviews
disputes and claims of violations by a service
provider against another or against the Authority,
prepares cases for referral to the Electricity Industry
Dispute Resolution Committee, and periodically
reviews causes of service providers’ complaints and
disputes in order to suggest appropriate rules and
procedures to eliminate them.
2- Vice-Governor for Regulatory Affairs
Oversees the following departments:
Technical Affairs: prepares technical studies dealing
with regulating the electricity and water desalination
industry, develops rules to insure provision of
reliableandefficientservices,preparesstandards
of performance for licensees, and oversees their
compliance with these standards.
Legal and Licensing Affairs: receives applications
for authorizations, licenses, and exemptions from
licensing; oversees compliance of licensees with
the requirements and conditions of the Law and
their licenses; prepares contracts and agreements;
drafts and reviews proposed rules, procedures,
regulations, and forms used for the industry; and
represents the Authority and defends it in litigations
and courts.
20 ECRA
Economics and Tariff Affairs: conducts studies on the
economics of the electricity and water desalination
industry; prepares studies for tariff reviews; develops
indicators and incentives for consumers and service
providers to encourage conservation and improve
performance; and maintains the Electricity National
Register and updates its contents periodically.
3- Vice-Governor for Support Services
Oversees the following departments which deal with
theAuthority’sinternalandback-officeoperations:
Financial Affairs: includes accounting, purchasing,
and storehouse.
Human Resources: handles personnel affairs,
employment, training, health insurance, travel, and
personnel services.
Administrative Support: includes mail services,
reproduction, photocopying and binding, document
scanning,transportation,centralarchives,andoffice
refreshment services.
PropertyManagementOffice:Overseesoffice
furniture and equipment, space utilization, building
maintenance, janitorial services, and building security.
212011 Activities & Achievements
Figure (1): Organization chart of the Authority
Board of Directors
Governor
Governor’sOffice
Information Technology
Public RelationsExternal Auditor
ServiceProviders
Affairs
ConsumerCare
Legal &Licensing Affairs
TechnicalAffairs
HumanResources
Economics &Tariff Affairs
Internal Auditing
Advisors
Vice-Governor,Support Services
Vice-Governor,Regulatory Affairs
Vice-Governor, Consumers& Service Providers Affairs
FinancialAffairs
The organization chart of the Authority is shown in Figure (1).
PropertyManagement
AdministrativeSupport
22 ECRA
Part II
232011 Activities & Achievements
Activities & Achievements of the Authority in 2011
24 ECRA
Consumer Care and Service Providers Affairs
Figure (2): SEC’s operating districts
The consumer is the main focus of ECRA’s interests.
The Authority thus created a department of
Consumer Care to cater for his needs and foster
his rights and interests. The department performs
its duties within the regulatory framework of the
Electricity Law and its Implementing Regulations
that prescribe the principle of fair treatment and
availability of choices in selecting the means
of dealing with disputes that arise between the
consumers and the service providers.
ECRA’s activities in the area of consumer care during
2011 included the following:
1- Electricity Outages
a) Statistical Study of Causes of Electricity Outages
During the year under consideration ECRA
continued requesting periodically from SEC reports
and data regarding power outages (particularly for
outages affecting 100 or more consumers and lasting
30 minutes or more) for the purpose of studying
these cases, analyzing them and investigating their
causes in order to follow up on implementation of
mitigation techniques to minimize their recurrence.
ECRA analyzed the outages in each of the SEC’s
districts of operations (Figure 2), the number of
affected consumers, and the duration and causes
of the outages. The Authority concentrated on the
causes of the outages, and it worked with the service
providertofindsolutionstolimittheirrecurrence
and minimize their impact on the consumers.
Comparisons were made periodically to gauge
improvements made, the level of decrease of
outages, and their frequency.
In general, the principal causes of outages were:
• Cable damages which accounted for 38% of all
outages.
• Weather conditions which were responsible for
23% of outages.
• Transmission network failures which were the
cause of 11% of the outages.
In2011ECRAnotedasignificantdecreaseinthe
outages caused by load shedding compared to the
previous year. This improvement in performance is
attributable to SEC’s efforts to increase generation
capacity through its projects of building new
generation plants and improving the network in
various locations.
District
Eastern District
Southern District
Central
District
252011 Activities & Achievements
Figure (3):Percentage Distribution of Causes of
Electricity Outages in 2011
Figure (4):Distribution of complaints by
SEC operating district
34%Western
OperatingDistrict
31%Central
OperatingDistrict
16%Eastern
OperatingDistrict
19%SouthernOperating
District
38%Cable Damages
24%Other Causes2%
Failures of IsolatedGeneration Units
2%Failures of MainGeneration Units 23%
WeatherConditions, Failuresof Overhead Lines
Failures of Transmission
Networks
11%
Figure 3 shows the percentage distribution of
the causes of electricity outages throughout the
Kingdom in 2011,
while Figure 4 shows the percentage distribution of
the power outages in SEC’s operations districts.
ECRA is working closely with SEC to continually
increase the capacity of the overall electricity
network to meet the ever-increasing demand,
while at the same time insuring maintenance of a
reasonable level of reliability in accordance with
international standards, as well as updating the
networks and increasing the generation capacities
in the various locations in order to minimize power
outages as much as possible and reduce their
impact on consumers. Implementation of projects
to achieve these objectives undoubtedly requires
huge investments and continuous supervision of the
network throughout the Kingdom.
b) Mahayil-Asir Electricity Network Study
Seeing a surge in the frequency of power outages
and their duration in certain parts of the Kingdom, as
well as what KPIs measurements indicated regarding
the rather low level of service quality in some parts
ofthecountry,ECRAdecidedtoundertakeafield
studytofindoutthecausesoftheseproblemsand
devise remedies to improve the situation. Mahayil-
Asir, in the Southern Operating District was selected
as the site for this study which was to be considered
as a representative sample for all other similar areas.
The study was undertaken by a team from ECRA,
SECandaninternationalconsultingfirm.Thestudy
resulted in a comprehensive report that outlined the
main underlying causes for interruption including
administrative, operational, and planning issues
aswellasdeficienciesintheoriginaldesignand
construction of the overhead networks. The report
contained the following recommendations:
26 ECRA
Firstly: Developing a Plan to Improve Administrative
and Operational Procedures: To be implemented
immediately and for the short term. The objective
oftheplanistoovercomedeficienciesinthe
administrative and operational procedures that do not
requirelargefinancialexpenditures.Itconcentrates
on evaluating physical and manpower resources,
surveying the electricity networks, and performing the
required maintenance works.
Secondly: Developing a Comprehensive Plan to
Improve the Electricity Network Performance:
A long term plan to remedy the conditions and
weaknesses of the electricity network. The plan seeks
to improve and enhance the distribution networks
by upgrading or replacing the overhead power lines
with other types, and installing power restoration and
partitioning equipment. These measures contribute
to bolstering reliability of the network and expediting
restoration of power.
ECRA sent the report to SEC and charged the
company with implementing its recommendations,
and submitting periodic reports on the progress of
implementation as well as reporting any achievements
in network performance improvements. ECRA also
charged the company to undertake a comprehensive
study in the other areas for which measurements of
the KPIs showed failure to meet the required levels
of performance, and submit proposed remedies with
timetables for execution.
2- Review of SEC’s Safety Procedures
Due to the occurrence of several safety-related
incidents in the operations of SEC during 2011,
ECRA undertook a detailed review of the SEC safety
procedures. A comprehensive report was prepared
containing general notes regarding common
instructions the company must observe, as well as
specificinstructionsandproceduresitmustadd
272011 Activities & Achievements
to its existing system. The report raised questions
regarding the company’s ability to follow through on
implementation of its safety procedures. At the end
of 2011 ECRA was still discussing with SEC the steps
that must be taken in the short and the long terms
to alleviate the dangerous conditions that lead to
accidents.
3- Electricity Industry Accidents Reporting Procedures
a) Workshops
In 2011 ECRA continued organization of workshops
in several cities in the Kingdom that were started in
the previous year. The theme of these workshops was
“Electricity Industry Accidents Reporting Procedures”.
Staff members from SEC and other licensees
participated in these workshops which were held to
familiarize them with the procedures, and insure that
they understand them and apply them properly.
The workshops consisted of an explanation of the
procedures that covered how to report incidents
to the Authority, how to prepare reports of major
electricity industry accidents such in the areas of
generation, transmission, or distribution, health and
safety accidents, or accidents that have environmental
impact. The workshops also served to answer queries
from the participants regarding various aspects of the
procedures and to clarify them, as well as present
an evaluation of the experience of application of
the procedures for the period since their adoption in
2009.
b) Second Edition of the Procedures
In response to comments received by ECRA either
directly from the licensees or through the workshops
held in the past two years regarding the electricity
industry accidents reporting procedures, the Authority
in 2011 updated these procedures and issued the
second edition.
c) Administering the Procedures
In 2011 the Authority commenced development of
a preliminary concept for building a database of
electricity industry accidents by utilizing an electronic
system, which it already owns, for management of the
electricity industry database and information. Building
of the database is expected to be completed in 2012.
The database will facilitate collecting information
aboutaccidentsforpurposesofclassificationand
analysis. It will also serve as a channel for the
licensees to report accidents to the Authority, thus
insuring that accident reports are submitted in a
timely manner as required by the procedures.
4- Regulating the Consumer-Service Provider
Relationship
During the report year the Authority completed drafts
of two agreements covering the consumer-service
provider relationship, as well as a draft of the rules
regarding service disconnection. After a series of
meetings between the Authority and the service
providerstheagreementsreachedtheirfinalstagesof
development. They were published in newspapers to
solicit public comments on them.
The documents are aimed at regulating the consumer-
service provider relationship by outlining the rights
and responsibilities of each party. The documents also
serve as a legal reference in any dispute that may arise
between the parties.
Following is a description of these documents:
28 ECRA
a) Agreement for Service Connection at the Distribution
Voltage
This is an agreement signed between the service
provider and the person requesting the service
delineating the rules and conditions under which
the service is provided. It includes the rights and
responsibilities of each party, the application form
for requesting the service, and all the basic data and
documents that are required for service connection or
that might be required while the agreement is still in
force.
b) Consumer Agreement
This is an agreement between the service provider and
the consumer which covers the conditions for providing
the service. It includes the conditions and rules that
each party must abide by, the application form for
opening a consumer account with the company, and
all the basic data and documents that are required for
consuming electricity or that might be required while
the agreement is still in force.
c) Rules for Electricity Service Disconnection
Theserulesdefinetheconditionsunderwhichthe
electricity service to a consumer may be disconnected.
They include the steps that the service provider must
undertake (including giving warning notices through
several means to the consumer in a set period of
time prior to the action) before he can disconnect
the service. The rules also include the conditions and
procedures for resuming the service after the conditions
for disconnection have been eliminated.
5- Rules for Relocation of Overhead Electricity
Networks
ECRA’s experience in the past few years has indicated
that a substantial number of consumers complaints
concern requests to relocate overhead electricity lines
that cross their properties. In 2011 the Authority drafted
“Rules for Relocating Overhead Electricity Networks”
toserveasbasisforresolvingthisissue.Therulesdefine
the responsibilities of the service providers and the
property owners and outline the conditions that govern
requests for relocation. Final draft and adoption of the
rules is expected in 2012.
6- Electricity Service to Consumers with Special Needs
Thefinaldraftoftherulesandprocedurestohandle
requests for service from consumers with special
needs has been completed by the Authority in
2011. The objective of this document is to set a
comprehensivedefinitionofpersonswithspecial
needs, and establish mechanisms and special
procedures for handling their needs. In 2012 the
Authority will continue consultations with the
service providers prior to adoption of these rules and
procedures.
292011 Activities & Achievements
7- Rules and Procedures for Consumer Care and
Service Providers Affairs
The responsibilities assigned to ECRA by the
Electricity Law include enhancing the electricity
services and bolstering the rights of consumers and
service providers. In pursuit of this responsibility
ECRA issued in 2011 a Request For Proposals (RFP)
invitingqualifiedconsultantstosubmitbidsfor
preparation of several regulatory systems dealing
with the relationship between the Authority, the
consumers and the service providers. The systems
aim to protect the rights of all parties. They are
to be designed in line with the best international
practices, while at the same time taking into
consideration the present and future conditions of
the Saudi electricity industry. The scope of work
consisted of the following:
• Reviewing existing regulations in the Kingdom
and other countries for consumer services and
service providers’ affairs.
• Comparingandanalyzingdeficienciesinthe
existing regulations.
• Determining the elements of consumer
protection which include:
- Electricity meter rules.
- Management of consumer relations by the
service providers.
- Consumer complaints procedures.
- Practices for defending and protecting
consumer rights.
- Electricity service quality standards.
- Measurement of consumer satisfaction.
- Information and services offered to
consumers, including informational
campaigns about their rights and
responsibilities.
The scope of work also included development of
comprehensive regulations for service providers’
affairs, their rights, regulations for realizing fair
return on their investments, the practices of
defending and protecting their rights, procedures to
enhance the Authority’s ability to expedite dispute
resolutions, and regulations and codes regarding
competition among service providers.
30 ECRA
8- Consumer Complaints
a) Management of Complaints System
In 2011 ECRA signed a contract with a consulting
firmtodevelopasystemtohandleconsumer
complaints and enhance the services of the
consumer care department and increase its
efficiency.Thesystemaimstoachievethefollowing
objectives:
• Automate the consumer care department
procedures.
• Receive consumer complaints either
electronically though ECRA’s website or in
personatitsheadoffice.
• Process the complaint electronically within
ECRA
• Notify consumers of the progress of their
complaints by SMS messages.
• Provide a portal in the Authority’s website where
the consumer can follow the progress of his
complaint, and obtain information regarding
any recommendation or decision made by the
Authority with respect to his complaint.
• Provide various types of reports such as the
percentage of resolved complaints, types and
sources of complaints, and the service provider
district from which the complaint originated.
The work under this project is expected to be
completed in 2012.
b) Complaints Regarding SEC
The Authority deals with consumer complaints
associated with electricity, cogeneration, and water
desalination covering areas such as application of
tariffs, quality of supply, quality of service, billing,
and other matters through mediation*. The same
method of mediation is also used to resolve disputes
that arise between the industry participants. Among
the cases in which this method was employed were
the following examples:
• A number of consumer complaints involving
requests for service connection and billing.
• A request by the Ministry of Health to
transfer responsibility for the operation and
maintenance of the proposed Najran hospital
switching station to SEC.
• A request by SWCC to review its proposed
agreement with the Saudi Electricity
Transmission Company to provide electricity
service for the pumping stations of the Shuqaiq
Water Desalination System (Phase II).
The Authority works diligently to treat all players
fairly whether they are consumers, service providers,
investors, traders or any other participant in the
electricity and water desalination industry. It is also
keen on protecting all players’ interests vis-à-vis
third parties. In the event that mediation fails, the
Authority may issue a ruling on the dispute or refer
it to the Electricity Industry Dispute Resolution
Committee. The Authority’s ruling may also be
referred to the Committee if one of the parties does
not accept it. The Committee’s decisions may be
appealed to the Kingdom’s Court of Grievances.
During the report year, the total number of
complaints received by ECRA regarding SEC services
was447.TheyareshowninTable(1)classifiedby
* Mediation: a process in which a representative of the Authority conducts discussions among the parties to a dispute designed to enable them to reach a mutually acceptable agreement.
312011 Activities & Achievements
type and by the SEC operating district from which
they originated. The Authority successfully resolved
some 88% of these complaints while the remaining
ones are still under its active consideration.
It should be noted that the number of complaints
in 2011 has decreased by 38% from the number in
the previous year. The decrease is attributed to the
following:
• Resolving the issue of service connection to
residential units for which the owners do not yet
possess titles. The resolution was made through
application of the procedures mandated by the
Council of Ministers Decision (CMD) Number
136* issued on 15/5/1429AH (19/5/2008).
In 2011 complaints arising out of this issue
decreased by 71% compared to the previous
year.
• Resolving complaints regarding service
connection tariff. This problem was resolved by
applying the rules and regulations in this regard
contained in the Service Provision Manual.
In 2011 complaints arising from this issue
decreased by 67% compared to 2010.
* The CMD 136 included several items among which: requiring the Ministry of Rural and Municipal Affairs to expedite surveying all residential units for which the owners do not yet possess titles in accordance with the requirements of CMD Number 115 issued on 7/5/1424AH (7/7/2003), and allowing a grace period of two years starting from the date of issuance of CMD 136 to submit requests to connect electricity service to existing housing units constructed in areas that already had the service, provided they were constructed prior to the date of CMD 115 issued on 7/5/1424AH ( 7/7/2003).
Complaint typeSEC Operating District
Eastern Central Western Southern
Service connection 3 15 23 16
Billing and tariff 8 22 15 8
Removal of overhead lines and compensation requests
3 6 6 37
Removal of substations and transformers
4 6 7 2
Power interruption 12 92 45 66
Others 5 16 14 16
Total complaints by operating district 35 157 110 145
Total district-specific complaints 447
Table (1): Electricity consumer complaints in 2011
by type and SEC operating district
32 ECRA
Figure (5): Distribution of the precentage of complaints by type
Figure (6): Distribution of complaints by SEC operating district
4%Removal
of Substationsand Transformers
Billing & Tariff14%
11%Removal
of overheadlines and
compensation requests
47%Power
Interruptions
13%Connections
32%Southern
25%Western
35%Central
8%Eastern
OtherComplaints
11%
• Efforts by SEC to resolve issues regarding transfer
of overhead lines from private properties.
Complaints arising from this issue decreased in
2011 by 56% compared to the previous year.
• The positive results of application of regulatory
instruments, such as the Service Provision Manual,
adopted by ECRA to protect consumers and
service providers. This process provided better
control of complaints and enhanced SEC’s ability
to resolve them in accordance with the provisions
of the Manual, thus reducing complaints regarding
billings and electricity meters malfunctioning.
The category of complaints shown as “Others”
in Table (1) includes requests to establish
emergency centers in various locations, requests for
compensations for damages or injuries resulting from
electrical shocks, complaints of trenching in the
vicinity of a residence, requests to transfer electricity
service from one location to another, and various
other sundry issues.
Figure (5) shows distribution of the percentage of
complaints by type. Complaints regarding service
interruptions and service connections represent
around 50% of the complaints received by ECRA
during the year.
LookingatcomplaintsclassifiedbySECoperating
district (Figure 6), it is noted that most of the
complaints came from the Central Operating District
(35% of all complaints) and the Southern Operating
District (32%). Most of the complaints from the
Central Operating District can be attributed to power
interruptions arising out of two causes:
332011 Activities & Achievements
• Cable ruptures in Hayil and some areas in
Riyadh.
• Weather conditions which damaged overhead
lines in some of the counties of the Riyadh
Province.
The complaints in the Southern Operating District
are attributable to a number of causes, chief among
which are:
• Power disruptions in Jazan Province, and in
Mahayil-Asir and Bisha Counties.
• Requests for service connection, removal of
overhead lines, and compensations. These
requests still represent a substantial element of
complaints.
In the Western Operating District most complaints
were caused by power disruptions in the Ola,
Tarabah, and Raniyah Counties, as well as some
parts of Makkah and Madinah Provinces. They also
included complaints regarding service connections
by owners of residential units who do not hold titles
to them.
9- Electricity Connection to Farms, Villages,
Hamlets, and Settlements
In previous years a committee was formed with
members from the Ministry of Water and Electricity,
ECRA, and SEC to update the implementation plan
of extending the electricity service to all approved
farms, villages, hamlets and settlements throughout
the Kingdom. The implementation is to be carried
outwithintheabilityofSECforself-financing.
The Committee adopted certain rules to govern
preparation of the plan for the connection process.
During the report year the committee continued
updating of the plan in accordance with the rules
which it had established.
34 ECRA
Tariffs
Among ECRA’s primary concerns are that tariffs
mustbecostreflective,fairandaffordableto
end-users; that their structure must be easy to
implement, and that income collected by the
electricity industry in accordance with these tariffs
must meet its’ revenue requirements. In order to
achieve these objectives ECRA’s responsibilities
include the following:
• Developing a methodology for tariff setting and
for periodic review of the adopted tariffs.
• Designing and preparing a tariff structure.
• Developing an overall tariff policy statement for
the Kingdom.
• Developing a comprehensive system to collect
financialandoperationaldatafromallservice
providers in the Kingdom.
• Developing a comprehensive cost accounting
system in order to assess service providers
costs which ultimately affect the tariff paid by
consumers.
Ontheotherhand,theefficientuseoftheavailable
energy sources, depletion of resources and
protection of the environment, as well as economic
factors require that all countries must embrace
policies which are sustainable for the future. Thus,
ECRA is keen that the tariffs in the Kingdom must
reflectthoseconcernsbyprovidingconsumers
with incentives to improve their utilization of the
electricity system, and apply conservation measures
that reduce their costs while at the same time they
improvetheefficiencyofthepowersystem.
ECRA’s tariff activities in 2011 were as follows:
1- Service Connection to the Distribution Network
- Setting Charges According to Breaker Capacity
On 20/9/1431AH (30/8/2010) the Council of
Ministers issued CMD 324 which mandated
standardization of the distribution voltage in the
Kingdom to be in line with the international voltage
standard of (230/400V). Within the framework of
ECRA’s regulatory responsibilities as assigned to
it by CMD 324, the Authority adopted a decision
to set the service connection charges to be based
352011 Activities & Achievements
on the breaker capacity in kVA instead of the
previously applied system which was based
on breaker size measured in Amps. Thus the
decision binds the connection tariff to the user
requirements for installed capacity and not to the
breaker current carrying capacity (in Amps) which
permits constructing the tariff on a fair basis among
consumers. This also allows the service providers
to vary breaker capacities based on their Ampere
ratings and supply them in accordance with the
consumers’ requirements.
An important consequence of this decision has been
reducing the costs of connection at the new voltage
of (230/400 V) by about 9% for most consumers.
2- Time-of-Use Tariff for Non-Residential
Consumers
One of the important uses of the tariff is to serve as
an instrument to support stability of the electricity
service, supplying it to consumers with high quality
and reliability, and encouraging savings and load
management. This is achieved by designing the tariff
so that it includes incentives for load management
and load shifting through the use of a tariff which
changes with the time of use (either peak demand
time during the day, or according to the season of
the year). It also includes mechanisms to incentivize
the consumer for proactive interaction with the
serviceproviderfortheirmutualbenefits.
The tariff can also serve as an instrument to increase
efficiencyofutilizationoftheelectricalsystem
by giving consumers incentives to improve their
power factor. Such incentives encourage consumers
to produce reactive power locally at their sites,
reducing the current transmitted through the
network. The reduction in the current transmitted
leads to savings in network capacity and reduces
the need for expansions of generation capacities,
switching equipment, and transmission and
distribution lines. This approach is used in most
countries.
In this connection, SEC completed in 2011 a
pilot project designed to test application of rules
to govern improvement of the power factor for
non-residential consumption (i.e., government,
commercial, and industrial consumptions). The
Authorityreviewedthefinalresultsoftheproject,
and at the end of 2011 was considering applying
the rules on an experimental basis for a year so that
consumers can evaluate the effects of these rules
on their consumption and thus take appropriate
measures if necessary to improve the power factor.
ThereaftertheAuthoritywillmakeafinalassessment
of the results of the project and prepare a tariff to be
implemented by the service provider.
3- Electricity Industry Data and Tariff
Computations Program
The program enables the Authority to obtain data
electronically from the licensees which is accurate
and up-to-date. This permits interested parties in the
electricity industry (including investors, researchers
and consumers) to obtain the data they need.
The program was built of independent modular units
for each electricity industry activity, i.e., generation,
transmission, or distribution. Each unit is capable of
being developed further and updated at any time by
adding new elements or eliminating older elements
36 ECRA
ifneeded,andtoinsurethecollectionandflowof
data on a regular basis. Authorized personnel from the
licensees can access the system and update data related
to their business either monthly or annually, depending
onthenatureofthedata(eithertechnicalorfinancial).
Theprogramperformsinitialdataverification.The
Authoritystaffundertakesfinalreviewofthedata,after
which it becomes available for analysis, writing reports,
and making charts and graphs according to the required
classification.Theprogramcanproducevariousreports
for the interested parties. The Authority, however, retains
therighttowithholdanyconfidentialdatathatmayhave
an impact on competitiveness.
At the end of 2010 the Authority commenced actual
implementation of the program. In 2011 it continued
receiving data regularly from the licensees, reviewing
and verifying it, and subsequently adding it to the
database. By the end of 2011 about 70% of the basic
data and about 50% of the operations data were entered
into the database. The Authority is working in earnest
with the licensees to complete all data entries by the end
ofthefirstquarterof2012.
Tomaximizebenefitsderivedfromthedatabase
program, and expand the user base to include various
government agencies ECRA signed during the year a
Memorandum of Understanding (MoU) with the Ministry
of Water and Electricity covering exchange of electricity
industry data available from the program.
4- Classification of Saudi Aramco Electricity Meters
Formanyyearsclassificationoftheelectricitymeters
was a subject of contention between Saudi Aramco and
SEC. Saudi Aramco maintained that all of its electricity
consumption falls under the “industrial consumption”
tariff category, while SEC’s position was that not all of
Saudi Aramco’s consumption falls under that class, and
that in fact for tariff purposes the consumption falls
into three categories: “industrial”, “residential”, and
“commercial”.
CMD 114 issued on 10/4/1430AH (6/4/2009) dictated
treatment of Aramco loads in accordance with the
nature of consumption. The CMD assigned to ECRA
the responsibility to determine; 1) the Saudi Aramco
facilities that are of a residential or commercial nature,
and thus do not qualify for the industrial consumption
tariff, and 2) which entity is responsible for the
construction and maintenance of the distribution
network serving Saudi Aramco’s facilities. The decision
thus set the mechanism for settlement with SEC of
payment shortfalls incurred by Saudi Aramco throughout
the years of the dispute.
Pursuant to this responsibility the Authority, during
the reporting year, formed a working group from the
two organizations to list electricity meters in all Saudi
Aramco sites and classify them according to the type
of consumption. The team listed 680 meters. The two
partiesagreedontheclassificationof422ofthese
meters.
After reviewing reports of the working group, the
Authoritymadearulingregardingclassificationofthe
remaining meters in conformity with the rules and
regulations governing electricity consumption tariff and
the aforementioned CMD 114.
372011 Activities & Achievements
Codes and Regulations
During the report year the Authority continued work
on a number of codes and regulations as follows:
1- Saudi Electricity Transmission Code
In 2007 ECRA issued the “Saudi Transmission Code”
which outlines the responsibilities of all users and
licensees of the electricity transmission system.
The code prescribes the methods of operation and
maintenance of the transmission system including
the main technical components and equipment
related to metering and connection to the system. It
alsospecifiestheplanningrequirements.
In 2011 certain articles of the code were amended,
anditstitlewasmodifiedtothe“SaudiElectricity
Transmission Code”.
2- Seawater Desalination Code
In its effort to establish the legal framework for
the water desalination industry and issue the set
of codes, rules, and regulations that are required
to regulate this industry; the Authority signed a
contract with a specialized international consulting
firmtodraftaseawaterdesalinationcode.Thecode
was aimed at covering all aspects of the industry,
including production, dispatch, and transportation.
ECRA reviewed all the legal and technical aspects of
thedraftcode,preparedbytheconsultingfirm,with
all relevant participants in the industry. After review,
the code was approved by ECRA’s Board of Directors
in 2011.
The Seawater Desalination Code provides clear
guidelines which all concerned parties must adhere
to in order to achieve the following:
• Increase reliability of desalinated water supplies.
• Compliance of produced desalinated water with
the approved standards.
• Highoperationalefficiency.
• Fair competition that attracts investments in this
industry.
• Low cost of desalinated water production.
3- Charges for Use of Transmission System
Charges for use of the transmission system represent
the price charged by the owner of the transmission
system from its users in order to permit them to
transmit electricity from the generation plants to the
distribution system. During the report year ECRA
signed a contract with an experienced international
consultingfirmtodesignastructuretodetermine
charges for use of the transmission network. Design
of the structure was completed in 2011. During the
coming two years (2012-2013) ECRA intends to
start using it on experimental basis and insure the
readiness of all requirements for deployment such as
installationofdigitalmeters,andmodificationofthe
billing system, to be followed by full deployment in
2014.
38 ECRA
4- Supervision of Codes and Regulations:
a) Saudi Electricity Transmission Code Supervisory
Committee
The supervisory committee for the transmission code
consists of members from several relevant parties. It
holds its meetings on a quarterly basis. In the four
meetings of the report year the committee completed
the following tasks:
• Formed two subcommittees: one for exemption
of generation activity of SEC, and the other to
review the degree of licensees’ compliance with
the code.
• Received 118 requests from code users for
exemption from some of the provisions or for
theirmodification.TheCommitteereviewedthe
requests and submitted its recommendations to
ECRA.
• Developed and updated its website which
includes minutes of its meetings, its decisions,
ECRA’s actions on these decisions, and the
committee’s annual reports.
b) Saudi Electricity Distribution Code Supervisory
Committee
The supervisory committee for the distribution code
consists of members from several relevant parties. It
holds its meetings on a quarterly basis. In the four
meetings of the report year the committee completed
the following tasks:
• Prepared the committee’s manual.
• Developedrequestformsformodificationsor
exemptions.
• Held three workshops to introduce the code to
workersinthefield.
• Received 16 requests from code users for
exemptions from some of its provisions or for
theirmodification.TheCommitteereviewedthe
requests and submitted its recommendations to
ECRA.
392011 Activities & Achievements
Licensing
The Electricity Law and the Charter of the Authority
require that any person engaged in any of the
following activities has a valid license issued by the
Authority in order to legally conduct his activities in
Saudi Arabia:
• Generation, transmission, distribution, trading,
retail, export or import of electricity;
• Cogeneration or trading in cogeneration
products; and
• Water desalination, its transportation to the
points of distribution, or trading in desalinated
water.
The objectives of the licensing process are to
streamline the development of the electricity
and water desalination industry and monitor the
quality and reliability of the services which are of
paramount importance to the consumers as well as
to the national economy as a whole.
The Authority issues licenses and monitors licensees’
performance, and takes appropriate measures to
enforce the provisions of the Electricity Law on
violators of the license conditions and requirements
to protect public interest.
The Authority also requires licensees to comply
with technical, legal, and environmental protection
requirements.
The licensing framework covers requirements and
conditions for each type of license, details of rights,
duties and obligations of licensees, and details
of monitoring procedures. The Electricity Law
and its Implementing Regulations require that all
procedures and the basis of monetary charges be as
transparent as possible.
ECRA’s website contains forms to request
authorizations and licenses for activities in electricity
generation, transmission, retailing, trading and
distribution; as well as activities in cogeneration
and water desalination and its transportation to
the distribution points. The website also includes
a listing of all licenses issued by the Authority, and
the rules adopted by ECRA’s Board of Directors for
calculating license fees.
In 2011 the Authority completed the following tasks
in the area of licensing:
1- Authorizations
In pursuit of its objectives to encourage investment
in the electricity and water desalination industry, the
Authority issues authorizations permits to interested
parties to allow them to commence preliminary
preparation work (including feasibility studies,
planning, and technical investigations) before they
start actual activities.
In 2011 the Authority issued nine permits distributed
as follows (Table A1-1, Page 94):
- Eight authorizations for electricity cogeneration.
- One authorization for electricity generation
from mobile units.
These permits were issued to nine entities.
40 ECRA
2- Licenses
Licenses are issued at least 30 days before
construction commences. In 2011 the Authority
issued, or reissued (renewed) 35 licenses (Table A1-
2, Page 95) as follows:
• eleven licenses for electricity generation.
• two licenses for electricity transmission.
• one license to own an electricity transmission
network.
• two licenses for electricity distribution and
retailing.
• nine licenses for cogeneration.
• four licenses for water desalination.
• two licenses for trading in electricity.
• three licenses for trading in desalinated water.
• one license for transportation of desalinated
water.
These licenses were issued to 27 entities.
3- Exemptions from Licensing
TheElectricityLawspecifiesthatnopersonmay
undertake any electricity activity without a valid
license from the Authority. The Implementing
Regulations of the Law allow for exempting a
licensee from the licensing requirement if the
generation plant is not connected to a transmission
network or a distribution network and all its output
is exclusively used by the owner of the plant. The
exemption also applies to a transmission network
and a distribution network under similar conditions.
By the end of 2011 ECRA issued, or renewed 12
exemptions from licensing (Table A1-3, Page 98) as
follows:
• nine exemptions for generation plants.
• one exemption for a desalination plant.
• two exemptions for cogeneration plants.
These exemptions were issued to twelve entities.
4- License Forms
In2011thefinalversionofthePrincipalBuyer
license was completed. It will be submitted to
ECRA’s Board in 2012 for approval. The Authority
also completed in 2011 preparation of the permit to
study construction of mobile electricity generation
units.
412011 Activities & Achievements
Electricity and Desalinated Water Industry Plans
Saudi Electricity Company (SEC)
Generation(SEC)
Transmission
Distribution
Consumers
Generation(SWCC)
Generation(Other Entities)
Figure (7):Current organizational structure of the electricity
industry in the Kingdom.
During 2011 ECRA’s activities included
work on the following plans for the
electricity and water desalination industry.
1- Electricity Industry
Restructuring Plan
The electricity industry restructuring plan
approved by ECRA’s Board outlines the major
steps for unbundling the main activities of the
industry (i.e., generation, transmission, and
distribution) and moving it from the current
vertically integrated structure (Figure 7) into an
environment of competitiveness on an economic
basis through the following steps:
• Creation of an independent transmission
company that maintains an open and unbiased
policy of access to the transmission system
for use by all producers and large consumers
without discrimination.
• Creating a special entity known as the “Principal
Buyer”, to manage the electricity industry
income, and enter into clear and transparent
contracts with all service providers (in the areas
of generation, transmission, and distribution),
which are reviewed and approved by ECRA. The
Principal Buyer is responsible for overseeing that
all parties abide by the contracts.
• Design a clear, transparent, and fair electricity
“wheeling” tariff for the transmission system.
• Creation of several competing entities in the
fieldofgeneration.
• Introducing competition in wholesale electricity
services to the distribution companies and large
consumers.
• In the long run, introduce competition in the
fieldofdistributionandservicetoconsumers.
Figure (8): shows the organization structure of the
industryinthefirstphaseofimplementationofthe
plan.
In 2011 ECRA continued discussion with SEC
regarding the plan’s implementation timetable. The
following milestones were achieved:
• The process of establishing the National
Electricity Transmission Company (NETC), a
limited joint stock company wholly owned by
SEC (the Holding Company), continued. NETC
pursued building its organizational infrastructure
in preparation for commencing its activities at
the start of 2012.
42 ECRA
Figure (8):Structure of the electricity industry after completion of Phase I of the restructuring plan
Consumers ConsumersConsumers
IndependentGeneration
IndependentGeneration
IndependentGeneration
IndependentGeneration
GenerationCompany
GenerationCompany
Transmission
GenerationCompany
IndependentGeneration
Cogeneration Cogeneration
Cogeneration
Cogeneration
Cogeneration
DistributionCompany
DistributionCompany
DistributionCompany
• SEC pledged to establish a special unit within the
holding company to undertake the responsibility
of the Principal Buyer. This unit is expected to start
its activities in 2012.
• The Authority and SEC agreed on the
establishment, during 2012, of several generation
companies, wholly owned by SEC. These
companies are expected to commence operations
before the end of 2013.
• SEC has also pledged to establish during 2012
a distribution company that will go into actual
operation at the beginning of 2013.
• The Authority has formulated a structure for the
charges to use the transmission system which will
be tested in the coming two years (2012-2013).
Ultimately after the restructuring plan is fully
implemented there will be several companies
competing in generation, and several distributors
and service providers (Figure 9). There will also
be a spot market for electricity trading as well as
a parallel market for bilateral supply and trading
in electrical energy. It is hoped that successful
execution of all elements of the plan will lead
to creation of a competitive market for electrical
services where selling and buying are governed by
the free market rules of supply and demand.
SEC
432011 Activities & Achievements
SEC
Cogeneration
DistributionCompany
ServiceProvider
ServiceProvider
ServiceProvider
ServiceProvider
ConsumersConsumersConsumersConsumersConsumers
DistributionCompany
DistributionCompany
Principal Buyer
Transmission
SEC
GenerationCompany
GenerationCompany
GenerationCompany
IndependentGeneration
IndependentGeneration
IndependentGeneration
IndependentGeneration
IndependentGeneration
Cogeneration Cogeneration Cogeneration
Figure (9):Electricity industry structure after full implementation of the plan
ConsumersConsumers
2- Long Range Plan for Electricity
This plan was prepared by the Research Institute
of King Fahd University of Petroleum & Minerals
(KFUPM-RI), together with an international
consultant.
The plan took into account the restructuring plan
underway, and grid interconnection with the GCC
countries, as well as the available types of fuel for
electricity generation.
In predicting demand; minimum, maximum, and
likely growth in demand, population increases,
economic growth, and the weightings of industrial,
commercial and residential consumptions were
considered.
Development of the plan was based on the
development plans for expansion of the generation
plants in SEC’s Eastern, Central, Western, and
Southern Operations Districts. Plans were also
developed for the isolated areas. Standards were
formulated for generation that include expansion,
type and availability of fuel, type and size of
generation units, technical and operational
specifications,andexpectedlifetimeoftheexisting
and proposed units.
Based on the generation plan, the transmission
system plan was developed. Capacities of the
transmission networks were determined to deliver
energy from the generation plants to the distribution
centers. The plan also included a schedule to
synchronize expansion of transmission with
44 ECRA
expansion in generation along with investment
requirements to meet demand for electricity
throughout the plan years.
3- Development of Long Range Plan for Water
Desalination
Reports for the past three years have indicated
that concurrent with signing of the contract for the
electricity generation plan, a contract was signed
with the King Abdullah Research Institute of King
Saud University, in association with a specialized
firm,todeveloptheplanforwaterdesalination.
During 2011 work on the study continued.
The study involves projection forecasts for the
needed desalinated water in the Kingdom over the
next 25 years. It will include an estimate of the split
between desalination and aquifer production.
With respect to desalination, the plan will
determine the amount of desalinated water
produced by cogeneration as well as other methods,
primarily reverse osmosis (RO).
It will also include determination of the amount
of electricity produced in the cogeneration plants
so as to include this contribution in the long range
plan for electricity generation and transmission.
Furthermore, the study will take into consideration
economic parameters, population distribution,
location of plants, aquifer data, and other factors.
The study is being carried out with the collaboration
of MoWE, ECRA, SWCC, and SEC.
4- Electricity and Water Desalination Industry Data
TheAuthorityistheofficialcustodianandlocusof
the National Electricity Register which contains all
data related to the electricity and water desalination
industry. The Register contains full text of licenses,
decisions, laws, codes, standards, generation
capacities, installed capacities, electricity and water
desalination plans, demand forecasts, and other
data.
As part of its services, ECRA offers access to the
information available in the register to members
of the general public, government and private
organizations, service providers, investors, and
other parties interested in this industry.
In this connection, during the report year the
Authority provided information to several
government agencies. The Ministry of Petroleum and
Mineral Resources was provided with information
regarding heat radiation by the electrical network
for a study being undertaken by the ministry; while
the King Abdullah City for Atomic and Renewable
Energy (KACARE) received information regarding
development of renewable energy strategy.
452011 Activities & Achievements
Standards, Quality of Service, and Performance Monitoring
One of ECRA’s main responsibilities is monitoring
the performance of licensees to insure achieving the
following objectives:
• Adequacy of supply of electricity and desalinated
water.
• Reliability and quality of services.
• Compliance with the electricity law, and conditions
and requirements of the licenses to protect the
public interest.
• Responding in a reasonable time span to consumers’
complaints.
• Reducing the number and extent of service
interruptions.
• Expeditious restoration of service when interruptions
do occur, and
• Continual investment to provide service to new
customers.
In order to achieve these goals the Authority prepares
key performance indicators (KPIs) and standards for
every electricity activity which all service providers must
meet at a minimum. Financial incentives are provided
to service providers whose performance exceeds the set
standards,whilefinancialpenaltiesareassessedfrom
those who underperform them.
The Authority, in consultation with the licensees,
issues codes for connections and codes for use of the
transmission and distribution networks. These codes,
which all users of the networks must comply with,
containspecificandclearrulesandproceduresderived
from technical and operational requirements of the
networks to insure their safety, integrity, and protection.
In 2011 the Authority’s performed the following
activities in the area of standards, quality of service, and
performance monitoring:
1- Licensees’ KPIs
KPIs enable the Authority to monitor performance of the
entities working in the areas of electricity generation,
transmission, distribution and consumer services as
well as to determine the performance level that must
be achieved by the electricity industry in future to reach
standards comparable to those of the industrialized
nations. Twenty six KPIs were selected for the various
activities of the electricity industry (i.e., generation,
transmission, distribution, and consumer services).
In 2011 the Authority adopted the “KPIs Manual for the
ElectricityIndustryMarket“,andthe“DataVerification
Manual”. In the same year the Authority also audited
performanceKPIsatthebranchleveloffivelicensees,
visited 24 sites (Table 2), and prepared reports of the
audits which were sent to the licensees and published in
the ECRA website.
The auditing results varied between the licensees.
Some of the KPIs were of good and acceptable quality,
and some showed that they would require further
improvements. Still some of the KPIs were incorrect
due to being misunderstood by some of the licensees,
or due to lack of data records to refer to, or some other
hindrances.
Table (3) shows some KPIs for the various activities of
the electricity industry. In the auditing reports sent to
the licensees, they were apprised of recommendations
made to improve the KPIs measurement process. In the
coming years, ECRA will review compliance with these
recommendations and insure implementation during the
annual auditing stage.
46 ECRA
The KPI calculations also showed a great deal of
variation of the level of service between the regions.
While certain levels for some KPIs were achieved
in a region, in other regions the same KPIs came
below the desired levels. SEC was duly informed of
these results and was requested to submit proposed
measures to improve the KPIs in the regions with
substandard levels.
* Availability: Percentage of time when the unit is available for service.
Table (2): Sites where KPIs were audited
Serial Licensee – ActivityNumberof Sites
1Saudi Electricity Company (SEC) –
Generation4
2Saudi Electricity Company (SEC) –
Transmission2
3Saudi Electricity Company (SEC) –
Distribution4
4Saudi Electricity Company (SEC) –
Subscribers Services4
5 Marafiq–Generation 1
6 Marafiq–Transmission 1
7 Marafiq–Distribution 1
8 Marafiq–SubscribersServices 1
9 Saudi Aramco 2
10Saline Water Conversion Corporation
(SWCC)2
11 Water & Electricity Company (WEC) 2
Total 24
Table (3): Some KPIs for the various activities
ActivityKPI
LicenseeName of KPI Level Targeted Level Achieved
Generation Availability* 85%
92% Saudi Aramco (Qatif Plant)
98% Saudi Aramco
86.9% Jubail Power & Water Company
97.5%Rabigh Water & Electricity
Company94.8% WEC – Shuaibah Plant
86% SEC – Quraiyah Plant
83%SEC – Rabigh (Steam generation
units)
92%SEC – Rabigh (Combined cycle
units)
TransmissionCoefficientofpower
unavailability0,0008
0.0022 SEC
0.0079 Marafiq
Distribution
Average time of power disruption per customer
per year150 minutes
196.9 minutes SEC
170.9 minutes Marafiq
Average number of power disruptions per customer
per year2
5.21 SEC
1.8 Marafiq
472011 Activities & Achievements
2- Financial and Accounting KPIs for SEC
One of ECRA’s responsibilities is to enable the
licenseestooperateefficientlyinordertorecover
their expenses and realize reasonable returns on the
invested capital in the regulated activities. Based
on this charge ECRA developed a mathematical
modeltocalculatethelicenseesfinancialKPIsthat
should be monitored. Chief among these KPIs are
the following:
• Profitabilitymeasures.
• Abilitytosecurefinancing.
• Average loan expense coverage.
• Measures of debt collection.
The objective of measurement of the licensees’
financialperformanceistoparticipateindeveloping
toolstofacilitatecomparingtheirfinancial
performance with that achieved by regional and
international entities that work in comparable
environments. The measurement also aims at
proposing suitable remedial measures that the
licensees must undertake to minimize their costs
and increase the quality of their services to the
consumerswithoutdegradingtheirfinancial
positions or affecting their fair returns.
During the year under consideration ECRA pursued
with SEC implementation of the requirements
ofthemathematicalmodelandsetthefinancial
performance KPIs for the company.
3- Development of Electricity Demand-Side
Management Program
In the past few years electrical peak loads in the
Kingdom grew at a rate of 8% per annum. This rapid
growth rate is attributed to several factors:
• Growth of the population and the economy.
• Growth of per capita consumption of electricity.
• Lack of use of thermal insulation in buildings.
• Lowefficiencyofelectricalequipmentused
in the Kingdom, especially air-conditioning
equipment which represents the largest
component of electricity consumption.
The load growth presents a challenge to the
Kingdom’s electricity industry to raise huge amounts
of capital, ranging between SR20 billion and SR40
billion annually in order to build the generation
capacities, and the transmission and distribution
networks that are required to meet this growth.
The Kingdom’s electricity system can meet the
growth of electricity loads in one of two ways:
• Expansion of the system by building new
generation plants, and new transmission and
distribution networks, or
• Reduce demand for electric power, and
minimizewasteduetoinefficientuseof
electricity. This approach is known as “Demand-
Side Management” (DSM).
Studies by the Authority indicated that DSM
programs are the least expensive and most
economical approach compared to the costs of
expansion.
In 2011 the Authority prepared a feasibility study
on DSM which showed that this approach depends
on two main components: “load shifting at times of
peakdemand”programs,and“energyefficiency”
programs.
48 ECRA
The load shifting programs seek to reduce the electricity
loads at the time of peak demand which require
generation capacities that run less than 10% of the
time per year. If these loads are shifted to a non-
peak demand time this action will lead to increased
utilization of the installed generation units thus
reducing the costs to the service providers and the
consumers.
The DSM study included recommendations to
implement two groups of programs:
1- The “Electrical Load Shifting” programs group:
The electrical load shifting group consists of three
programs:
• Direct control of air-conditioning units (load
curtailment).
• Incentive tariff to reduce loads.
• Interruptible loads tariff.
2- The “Energy Efficiency” programs group:
Theenergyefficiencygroupconsistsoftwoprograms:
• Increasingefficiencyoftheair-conditioning
equipment.
• Implementingthebuildingefficiencystandards(i.e.,
usingthermalinsulation,andusinghighefficiency
air-conditioning and other electrical equipment).
The study showed that by implementing these programs
more than 2,200MW of installed generation capacity
can be saved during the next ten years, thus leading to
huge savings of more than SR76 billion. The savings
result from the following:
• SR14.3 billion which would have been spent to
build new generation plants.
• SR46.3 billion the additional cost of fuels,
calculated at international market prices, which
those plants would have used.
• SR10.8 billion the costs of operation and
maintenance of those plants plus the cost of their
fuels calculated at the subsidized price.
• SR5 billion the costs of the transmission and
distribution networks which those plants would
have required.
On the other hand the costs of implementing the load
managementandenergyefficiencyprogramsare
estimated to be around SR27 billion. Figure 10 shows
comparison between the costs of implementing the
electricity demand-side management programs and the
savings that can be realized from this action over a ten
year timespan.
492011 Activities & Achievements
0
10
60
20
70
30
80
40
90
50
Additional incomeresulting from selling fuel at
international prices
Transmission and Distribution network costs
Generation costs
Fuel costs (subsidized) + Operation and Maintenance costs
4- Standardization of Distribution Voltage
From the very beginning of the introduction of electricity
services in the Kingdom, the distribution voltage varied
between the various regions of the country. In some
regions a 110/220V system was used, and in other
regions the 220/400V system was used, while in some
other regions both systems were used. This situation
undoubtedly posed danger to the consumers, and may
havecausedfiresanddamagestoelectricalinstruments
and equipment.
On 20/9/1431AH (30/8/2010) CMD Number 324 was
issued which mandated that a uniform distribution voltage
of 230/400V shall be used throughout the country.
The CMD included a timetable for implementation
which stipulated that connection of electricity to
new constructions at the new voltage shall be made
immediately, while existing structures will have a grace
periodoftenyears,afterwhichretrofittingtothenew
system will be achieved gradually so that the entire
country will have a uniform distribution voltage by the end
ofafifteenyearperiodfromthestartoftheprogram.SEC
willundertaketheretrofittingatnocosttotheconsumers.
The change to a uniform distribution voltage system
undoubtedly will lead to the following enhancements of
the electrical services:
• Improvetheefficiencyofequipment.
• Decrease the distribution network losses.
• Increase the number of customers that can be served
from a distribution station.
• Improve safety.
• Support local industry as it will not be forced to
produce equipment that works on two voltage
systems, or have two production lines: one for
equipment using 110V and the other for equipment
using 230V.
During the report year the Authority participated
in the work of the committee formed by the
Ministry of Water and Electricity to oversee a public
relations campaign to disseminate information to
the Kingdom’s population about the importance of
the voltage change, the reasons for making it, the
mechanism of its implementation, and the timetable
for achieving it.
Figure (10): Comparison of the expected savings over a ten year period as a result of implementing the “Electricity Load Shifting” and the “Energy Efficiency” programs with their costs
Costs of Load Shifting
Costs Savings
Costs of implementingenergy efficiency
Programs
Am
ount
s(B
illio
n SR
)
50 ECRA
Electronic Management and IT
ECRA’s activities in the area of electronic management
and IT in 2011 were as follows:
1- E-Management
During 2011 ECRA continued development of IT
applications needed by its administrative support
operationssuchasfinancialaffairs,purchasing,
personnel, licensing, and administrative communications.
During the year it also:
• started actual utilization of the Electricity Industry
Data Program*,
• signed a contract with an international consulting
firmtobuildaspecialprogramdedicatedto
consumer care**,
• connected to the government GSN channel
operated by the e-Government transactions and
services program (Yesser) in order to authenticate
the identities of complainers prior to processing their
complaints,
• communicated with the National Center for Digital
Certificationinordertobelicensedasaproviderof
governmentdigitalcertificationservices,andstarted
preparations of the prerequisites for this process.
According to Yesser, ECRA achieved a level of 72.89%
transformation in electronic transactions during the
year, and a cumulative index of 54.15% in the overall
transformation process.
2- ECRA’s Website
In 2011 ECRA continued development of its
website***and updating its data. The development
included the following:
• Establishing a link to the database which contains
the data of the entities that are licensed, the entities
that obtained permits to study projects which they
contemplate undertaking in the areas of electricity
and water desalination, or the entities exempted
from licensing.
• Development of forms to update company data
through the website.
• Creating a webpage to seek views of the general
public on subjects under consideration by ECRA.
• Connecting the National Electricity Register on the
website with the database management system of
ECRA in order to automatically update the Register.
Appendix (2) contains a listing of documents and
information available on ECRA’s website that may be of
interest to consumers, investors, and anyone interested in
the electricity and water desalination industry.
3- Oracle Program
During the year the Authority offered a training program
to its entire staff on the purchasing module of the Oracle
program so that an employee can prepare a purchase
order without assistance from the staff of the purchasing
unit. It has also started a training program for the IT staff
on support for the Oracle program which is the backbone
oftheHR,payroll,finance,purchasing,consumercare,
and licensing systems.
* See page 35 “Electricity Industry Data and Tariff Computations Program”
** See page 30 “Management of Complaints System”
*** www.ecra.gov.sa
512011 Activities & Achievements
Other Activities
In addition to activities in its main areas of responsibility,
ECRA performed the following tasks in 2011:
1- Electricity Bill Payment Assistance to Recipients of
Social Security Benefits *
Electricity service is considered one of the basic services
for a society. Governments in many countries provide
support for persons of limited income through programs
that supply them with electricity at subsidized prices
which insures continuity of the service.
As part of the Government efforts to enhance quality-of-
life for Saudis, while at the same time encourage prudent
energy use to insure sustainability of the electricity
services, the Authority continued in 2011 to implement
its agreement of cooperation with the Ministry of Social
Affairs to build a database that ties names of recipients
ofsocialsecuritybenefitswiththeirelectricitybills,and
their national ID numbers. This information facilitates the
process of providing the needy with partial assistance for
payment of the electricity bill. The amount of assistance
given, and the method of giving it were designed on
ascientificandsystematicbasis.Indeterminingthe
amount of assistance several elements were taken
into consideration including: estimate of the monthly
electricity consumption for each family based on the
number of its members, the location of their residence,
and differences in climatic conditions between the
various regions of the Kingdom. Suitable values were
selected based on accurate data which were used to set
these values. The program also included development of
amediacampaigntoeducaterecipientsofthebenefits
about means of energy conservation so that the assistance
given to them does not lead to energy waste and become
a burden on the government or the service provider.
From the date the program was launched on July 23,
2009 till the end of 2011 the number of recipients has
reached241,000beneficiaries.Itisexpectedthatthis
number will eventually reach 500,000.
2- GCC Electricity Interconnection
The GCC ** states established an organization to build
and operate an electricity interconnection system to
enableeachstatetoincreasetheefficiencyofoperation
and the security of supply of its system, reduce costs that
arise from the ability to share in operational reserves and
production capacities, and facilitate inter-states free trade
of excess capacity.
In 2011 connections between Kuwait, Saudi Arabia,
Bahrain, Qatar, and United Arab Emirates were
completed. ECRA continued during the year its
participation in the advisory and regulatory committee of
the Gulf Interconnection Authority which manages the
system.
* RecipientsofthesocialsecuritysystembenefitsintheKingdomarethelowincomefamiliesandincludeorphans,widowedor divorced women, families of persons in the penal system, and those without a provider. At the time of the report this group numbered around 700,000 recipients, representing about 13% of residential electricity consumers.
** The members of the Arabian Gulf Cooperation Council (GCC) are: the United Arab Emirates, the Kingdom of Bahrain, the Kingdom of Saudi Arabia, the Sultanate of Oman, the State of Qatar, and the State of Kuwait.
52 ECRA
3- Saudi Arabia-Egypt Electricity Interconnection
The Kingdom of Saudi Arabia and the Arab
Republic of Egypt started several years ago a
study and preparation for the interconnection of
their electricity networks. Over two years ago the
feasibility study of the project was completed. A
marine survey of the proposed route in the Gulf of
Aqaba was completed recently.
The two countries formed a team to work, in
participation with specialized international
consultingfirms,onthedraftandreviewoflegal,
commercial, and technical agreements for the
interconnection. ECRA is a member of this work
team.
4- The Annual Electricity Statistical Booklet
In 2011 ECRA issued the third edition of the Annual
Electricity Industry Statistical booklet. The booklet
contains data and statistical indicators for the
electricity and water desalination industry for the
year 2010 including comparisons with previous
years. These data and indicators make it possible
for all local, regional, and international parties
concerned to obtain accurate and updated data
about the electricity and water desalination industry
and its development in the Kingdom.
532011 Activities & Achievements
Human Resources and Finances
1- Human Resources
By its very nature, the Authority is a very small
organization. For that reason it has adopted a policy
of running its business with a set of human resources
consisting of the following:
• A nucleus of highly specialized and highly
educated individuals with a wide experience
and thorough knowledge of the electricity
industry and regulatory affairs.
• A cadre of administrative and technical staff to
support the expert group.
• A continually changing group of consultants
(both individuals and organizations) determined
by the nature of the task under consideration.
This arrangement insures that in every case the
Authority receives the best available expertise,
whenever it is needed, at the lowest overall cost,
as payment for the expertise is limited to the
time of need without the necessity of permanent
employment.
Table (4) shows the distribution of the staff in 2011
according to their specialties. They are all Saudi
nationals.
2- Training and Manpower Development
ECRA is particularly conscious of human resource
development and is proactive in providing
development opportunities for employees. On
joining the organization, all employees undergo a
one week training/induction course. An important
resource in this context is the ECRA “Employee
Manual” which contains all the important elements
of ECRA operations and practices. Selection of
the training program depends on the nature of
the employee’s job, and the program is executed
according to a systematic plan that indicates his
actual training needs.
During 2011, 32 employees participated in 37 short
training courses in the Kingdom and abroad. Seven
training programs were held on ECRA’s premises
and were attended by 52 employees. Two additional
employees were sent abroad for training programs
of long duration to bring their total number to
seven. The Authority also offered scholarships to
27 employees to pursue high school education,
undergraduate studies at Saudi universities, and
graduate studies leading to master’s degrees at Saudi
and foreign universities. Table (4): Distribution of employees in
2011 by job specialty
Specialty Number
Technical 16
Administrative and Clerical 66
Support 10
Engineering 10
Legal 7
Financial 7
Economics 2
Total 118
54 ECRA
3- Financial Data
ThefinancialresourcesoftheAuthorityconsistof
the licensing remuneration, payments received for
services rendered to service providers and others,
andfinesleviedfromviolators.
The licensing remuneration is set by rules adopted
by the Board of the Authority.
The rules were established on the basis of collecting
sufficientfundstocovertheannualfinancialneeds
of the Authority.
They take into consideration the nature of work of
the licensee (cogeneration, generation of electricity,
its transmission, distribution, or trading; and water
desalination, its transportation, or trading), the
relativecontributionofeachactivitytothefinancing
of the Authority, and the size of the licensee’s
activity.
Table (5) shows comparisons of the Authority’s
income in 2011 with those of the previous year
while Table (6) shows the comparisons of its
expenditures.
552011 Activities & Achievements
Table (5): Revenue comparison for 2011 with the previous year(Amounts in thousands of Saudi Riyals)
Source 2011 2010
Saudi Electricity Co. 80,489 82,152
Saline Water Conversion Corp. 9,666 10,444
Tihamah Energy Generation Ltd. Co. 760 856
Saudi Aramco 715 809
Rabigh Arabian Water & Electricity Co. 686 117
Jubail Power Co. 169 191
MarafiqElectricityandWaterCo. 816 943
Shuaibah Water and Electricity Co. 2,108 2,531
Shuqaiq Water and Electricity Co. 1,552 -
Jubail Water and Electricity Co. 4,515 2,048
Saudi Cement Co. 160 197
Bawarej International Water Desalination Ltd. Co. 75 93
Power Energy Equipment Rentals 12 -
Shuaibah Expansion Project Co. 225 278
Water and Electricity Ltd. Co. 562 307
Water and Electricity Supply Co. 646 740
Rakaa Energy and Water Co. Ltd. 2 2
General Contracting Co. (Al-Olayyan) 105 85
Abdul Aziz and Abdullah Kanoo Co. 56 20
Taqa Environment and Electrical Energy System Ltd. Co. 60 48
Total 103,380 101,864
56 ECRA
* Data taken from a report of the International Energy Regulators Network (www.iern.net) entitled:
“IERN 1ST DRAFT OF THE REPORT ON THE POWERS AND COMPETENCIES OF REGULATORY AUTHORITIES”.
2011 2010
Approved Actually Spent Approved Actually Spent
Salaries,wagesandbenefits 33,815 33,680 31,798 31,601
Social security 2,630 2,520 2,543 2,505
End of service remuneration 5,180 5,110 2,150 2,148
Health insurance 3,090 2,984 2,594 2,577
Training and scholarships 3,355 3,329 2,660 2,635
Studies and consultations 10,600 10,345 12,653 12,372
Operational expenses 20,510 19,740 22,145 21,564
Capital Expenses 4,200 3,153 25,321 24,131
Allocation for Permanent Headquarters Building
20,000 20,000 - -
Total expenses 103,380 100,861 101,864 99,533
Figure (11) represents a chart that shows comparisons of per capita budget for regulatory authorities in many
countries around the world*. It is obvious from this chart that in Saudi Arabia the per capita share in ECRA’s
budget is among the lowest in the world
Table (6): Comparison of approved budget allocations with
actual expenditures for 2011 with the previous year
(Amounts in thousands of Saudi Riyals)
572011 Activities & Achievements
FIGURE (11): Comparison per capita budget of regulatory authorities of
several countries around the world
The Authority’s charter permits it to retain a reserve equal to twice its expenditures for the preceding year. At
the end of 2011 the accumulated value of the cash reserve held by ECRA reached SR 68,250,299.00.
5 10
Regulatory Authority Budget (€/capita)
15 20
0.945 EURO
2.388 EURO
58 ECRA
Part IIIReport of
The Electricity Industry Dispute Resolution Committee
592011 Activities & Achievements
60 ECRA
Introduction
Dispute resolution is one of the important
responsibilities of ECRA. Disputes include consumer
complaints against service providers as well as
disputes among licensees. In all cases the policy of
ECRA is to resolve the dispute through negotiation
and mediation between the parties. If the mediation
effort does not lead to satisfactory resolution, the
dispute is referred to the Electricity Industry Dispute
Resolution Committee.
In accordance with the Electricity Law, the
Electricity Industry Dispute Resolution Committee
is an entity independent of ECRA, formed by the
Council of Ministers. It consists of six members:
three legal experts, two experts in the electricity
industry,andafinancialexpert.Membershipinthe
committee is for three years, renewable.
Composition of the Committee
On 18/8/1427AH (9/11/2006) the committee was
constituted by CMD 211 as follows:
Dr. Mohammad A. M. Marzoogi Chairman
Dr Samir A. H. Al-Baiyat Member
Mr. Youssef M. A. Al-Mubarak Member
Dr. Anwar H. A. Mufti Member
Mr. Fahad M. S. Al-Issa Member
Dr. Ayoub M. A. Al-Jarbou Member
On 23/5/1430 AH (18/5/2009) the Council of
Ministers by Decision Number 169 renewed
the terms of service for the committee chair
and members for another three years starting on
18/8/1430 AH (9/8/2009).
Charges of the Committee
ArticleThirteenoftheElectricityLawspecifiesthe
charges of the committee to rule on the following:
• Disputes, complaints, and violations arising in
the electricity industry.
• Disputes among and between licensees.
• Disputes between a licensee and one or more
consumers.
• Any violation of the Electricity Law, its
Implementing Regulations, or the Charter of the
Authority.
The committee exercises its charges without
prejudice to any other means of dispute resolution
indicated by the agreements in force between the
parties to the dispute.
It should be noted that although the committee’s
jurisdiction includes ruling on disputes between
ECRA and licensees, the Electricity Law allows for
settling such disputes through arbitration.
Article Fifteen of the Law outlines the penalties
that may be imposed on violators of its Articles,
its Implementing Regulations, or the Charter of
the Authority. Article Fifteen also gives ECRA the
authority to place the activities of any violator under
guardianship, but such action must be submitted
urgently to the committee within a period not
exceeding thirty days.
612011 Activities & Achievements
Modus Operandi of the Committee
The Electricity Law covers certain important aspects
of the modus operandi of the committee. Article
Thirteen states that decisions are taken by a majority
of votes, and in the case of a tie the side with which
the chair votes carries. The article also mandates that
the reasoning for all decisions must be stated, that
decisions must be read in public sessions, that the
committee shall not refrain from making a ruling on
grounds of the absence of textual statements under
the Law covering the dispute at hand, but must in
such cases refer to the common law of the Kingdom.
The Law subjects decisions of the committee to
review by the Court of Grievances. Anyone subject
to a ruling by the committee may appeal the ruling
to the Court of Grievances within sixty days of
thedateheisnotifiedoftheruling.Ifhedoes
notappealwithinthespecifiedperiod,theruling
becomesfinal.
The Law states that the bylaws of the committee
are to be issued by ECRA’s Board. They were
indeed issued as Appendix (1) to the Implementing
Regulations of the Electricity Law pertaining to the
Duties of the Authority by Board Decision Number
3/11/27 on 15/4/1427AH (13/5/2006).
Activities of the Committee
1- Cases Received by the Committee
The Committee considered the cases received
during 2011 as well as cases pending from
the previous year, a total of 126. It decided to
follow a written memorandum form of litigation
whereby each party is provided with copies of
the memoranda and documents submitted by the
other party, and he is then requested to submit his
response prior to the committee session in which
the case is to be considered. During the session
all outstanding issues are addressed and closing
arguments are made.
The cases considered in 2011 were as follows:
a) Cases Pending from 2010
Forty-six cases were pending from 2010. The
committee ruled on all of them except for six
cases which were still under consideration
pending submittal of some documents and other
requirements which had not been met at the end of
the year.
b) Cases Received in 2011
In 2011 the committee received 80 cases. It issued
rulings in 24 of those cases, while some of the
remaining are in advanced stages of adjudication
pending issuance of rulings, and the remaining
group will require some time to complete submittal
of documents and hearing arguments of litigants in
order to reach rulings.
Table (7) shows the status of the cases considered by
the committee in 2011.
62 ECRA
2- Comparison of the Number of Cases Received
by the Committee and the Number of Cases it
Finalized in 2011 with the Previous Year
Table (8) shows a comparison of the number of cases
received by the committee and the number of cases
itfinalizedin2011withthepreviousyear.
Categorization of Cases According to the Requests
they Contained
By analyzing the cases received by the committee in
2010 and 2011 it becomes clear that most involve
requeststhatcanbeclassifiedasshowninTable(9).
Table (7): Cases on the docket of the Committee in 2011
CategoryNumber of Cases
Under review In chamber Closed Total
Violation Related to the Electricity Industry 1 - - 1
Disputes Related to the Electricity Industry 43 18 64 125
Total 44 18 64 126
Table (8): Number of cases received by the
Committee and the number of cases it finalized:
Comparison of 2011 with the previous year
YearNumber of Cases
ReceivedNumber of Cases
Finalized
2010 64 50
2011 80 64
Increase 25% 28%
Table (9): Categorization of cases according to the requests they contained
Type of Request 2010 2011 TOTAL
Payment of rent for using real estate property for electrical equipment 29 26 55
Transfer of a transmission line 19 12 31
Compensation for damages resulting from electrical equipment 10 7 17
Compensation for mental anguish, and physical damages 4 12 16
Compensation for lands allocated by eminent domain action as right of way or paths for electrical equipment
7 4 11
Compensation for disconnection of electrical services and the damages resulting from the disconnection
5 4 9
Refund of amounts paid to licensee 3 6 9
Removal of a distribution line 0 9 9
632011 Activities & Achievements
It should be noted that some of the cases included more than one request. There were also some consequent requests not related to the electricity industry, such as requests for payment of suing expenses which were not included in the table.
Table (9 continued): Categorization of cases according to the requests they contained
Type of Request 2010 2011 TOTAL
Removal of a transformer/electricity box 4 2 6
Relocation of a transformer station 4 2 6
Service connection 3 2 5
Determination of costs of service connection according to the old rule (i.e, rule used before 6/3/2010)
4 0 4
Removal of an electrical room 2 2 4
Enforcement of an eminent domain action 2 1 3
Compensation for drop in real estate property value due to presence of electrical equipment on the premises
1 2 3
Compensationformateriallossesresultingfromafireinanelectricitymeteror a transformer
1 2 3
Non-enforcement of payment for electricity bills of prior periods 1 1 2
Recalculation of the amount of electricity bills 1 1 2
Objection to the requirement to provide a site for the electrical equipment 1 1 2
Expropriation of the remainder of a property that was subject to an eminent domain action because the remainder became useless
1 1 2
Compensation for failure to connect the service 0 2 2
Imposing a penalty on a licensee for committing a violation 1 1 2
Imposing a penalty on a licensee for procrastination in implementing a decision by the Authority
1 1 2
Compensation for injuries caused by electrical current 0 1 1
Abrogation of an executive order for expropriation ofproperty for eminent domain
0 1 1
Forgive payment of penalty for tampering with the electricity meter 0 1 1
Paying the licensee for supplying electrical equipment 0 1 1
Failure to connect electrical service to others 0 1 1
Rescind surcharges on the electricity bill 0 1 1
Relocate buried electricity cable 0 1 1
Grant an additional electricity meter 0 1 1
Reconnect electricity service 1 0 1
Reissue electricity bills in the name of the previous consumer 1 0 1
64 ECRA
Part IVThe Electricity and Water Desalination
Industry in the Year 2011
652011 Activities & Achievements
66 ECRA
The Electricity Industry in 2011
The Saudi electricity system is the largest in the Arab
world, where peak load in 2011 reached 48,267
MW. The following is a brief description of this
system.
Generation
Generation capacity in the Kingdom in 2011
reached 57,432 MW*. Of this total capacity SEC
owned 75%, SWCC 9%, and ownership of the
remainder was distributed among several producers
as shown in Table (10) and Figure (12).
Table (10): Runtime capacities of generation units of licensed entities
Producing entity No. of plants Capacity (MW)
Saudi Electricity Co. (SEC) 48** 43,006
Saline Water Conversion Corporation (SWCC) 6*** 5,120
Jubail Water and Electricity Co. 1 2,942
Shuaibah Water and Electricity Co. 1 1,191
Tihamah Power Generation Co. 4 1,083
Marafiq(Yanbu) 1 1,038
Shuqaiq Water and Electricity Co. 1 1,020
Saudi Aramco 6 1,018
Arabian Rabigh Water and Electricity Co. 1 481
Saudi Cement Company 2 266
Jubail Power Co. 1 250
Aman Modern Energy Co. 3 18
Total 75 57,433****
All data appearing in this section of the report has been obtained from SEC, excepting data for generation where the
data was obtained from the licensees.
Rented units are not included.
Cogeneration plants only.
This total represents the installed capacities; the total of the available capacities was 51,148MW.
*
*****
****
672011 Activities & Achievements
16%
75%
9%
Other Producers
Saudi Electricity Company
Desalination
Figure (13) shows distribution of generation
capacities in the four operating districts of SEC*.
ofYanbuIndustrialCitywhereMarafiqisresponsible
for transmission). During 2011 the National
Electricity Transmission Company (NETC) was
established. NETC is expected to commence actual
operations in 2012 which include planning, building
and operating all components of the transmission
systems for voltages of 110kV and higher.
Transmission from the generation plants to the
consumption areas is carried through high voltage
overhead lines that have a total length of 45,442 km
and underground lines that have a total length of
4,232 km.
The national transmission network consists of
transformer stations, connection and disconnection
stations, transmission lines at the high voltages of
110, 115, and 132kV, and transmission lines at the
very high voltages of 230 and 380kV.
TheSouthernSECOperatingDistrictwasfinally
connected to the Western Operating District with
the completion of the transmission line which
connects the Shuqaiq generation station in the Jazan
Province with the Shuaibah generation station in the
Makkah Province in 2010. The Western Operating
District was also connected to the Central Operating
District through completion of the transmission line
connecting Qaseem to Al-Madinah Al-Munawarah.
SEC is currently carrying out preliminary studies
to build a 500 kV DC line connecting Riyadh
with Jeddah. The completion of this line will thus
completetheconstructionofaunifiednational
network. In the meantime construction is underway
of a national control center for the electricity system
which will enhance the capabilities of the National
Electricity Transmission Company to manage the
Transmission
At present SEC has a monopoly on transmission of
electric power in the Kingdom (with the exception
Figure (12): Distribution of generationcapacities among producers
Figure (13): Distribution of electricity generation capacities in the SEC operating districts
* SEC’s operating districts are shown in Figure (2) page 24.
8%Southern
34%Western
37% 21%Eastern
Central
68 ECRA
National system from east to west and from north to
south, and coordinate the activities of the regional
control centers that are operating currently in the
SEC eastern, central, western and southern operating
districts.
Distribution
Currently SEC has a monopoly also of electricity
distribution to consumers in the Kingdom (with the
exceptionoftwoareasoperatedbyMarafiqinJubail
and Yanbu). In 2011 SEC delivered a total of 219,662
GWh of energy, an increase of 3.5% over the
previous year. The number of customers increased
over the same period by 5.7% to 6,341,025. Table
(11)showsthedistributionofcustomersclassified
by consumption type. As evident from Figure (14),
the residential sector consumes half of the total
electricity sold, of which 70% is attributed to air-
conditioning.
The distribution network consists of 213,608 km
of overhead lines and 195,681 km of underground
buried lines.
Consumption is about equal at slightly over 30% in
each of the Eastern, Central, and Western Operating
Districts while consumption in the Southern
Operating District amounts to about a quarter of the
quantity consumed in the other districts (Figure 15).
The distribution of consumption among the various
categories shows a marked regional variation. While
industrial consumption dominates in the Eastern
Operating District (Figure 16), in the other operating
districts residential consumption
is dominant. It is more than 55%
in the Central Operating District
(Figure 17), around 60% in the
Western Operating District
Figure (14): Distribution of consumptionby class-kingdom-wise
4%Others
19%
15%
50%
12%
Industrial
Commercial
Residential
Government
Table (11): Distribution of consumers based ontype of consumption in 2011
TypeNumber
of subscribers
Consumption Percent of total consumption(GWh)
Residential 5,023,038 109,262 49.7%
Commercial 1,030,963 32,511 14.8%
Government 204,451 27,528 12.5%
Industrial 7,646 42,128 19.2%
Others 74,927 8,233 3.7%
Total 6,341,025 219,662
692011 Activities & Achievements
(Figure 18), and reaches a maximum of 67% of the
total consumption in the Southern Operating District
(Figure 19).
The distribution of residential and commercial
consumption in 2011 in the operating districts
(Figure20)reflectstherelativepopulation
densities in these districts. The larger government
consumption in the Central Operating District is
attributed to the location of the Kingdom’s capital in
that area. The presence of the two major industrial
giants, Saudi Aramco and SABIC, in the Eastern
Operating District explains the high industrial
consumption of this district.
Figure (15): Distribution of consumptionamong the Operating Districts
Figure (17): Distribution of consumptionin the Central Operating District
Figure (16): Distribution of consumptionin the Eastern Operating District
Figure (18): Distribution of consumptionin the Western Operating District
4%Other
8%
31%32%
9%
9%
46%
Southern
Eastern
Residentials
Commercial
Government
Industrial
31%Western
30%Central
5%Other
2%Other
7%
12%
19%60%
Industrial
Government
Commercial
Residential
7%Industrial
16%Government
17%
55%
Commercial
Residential
70 ECRA
Figures for electricity generation from various
sources, total quantity of electricity sold by SEC, and
total energy loss of the entire SEC system are shown
in Table (12).
Figure (19): Distribution of consumptionin the Southern Operating District
4%Others
13%
15%67%
Government
Commercial
Residential
1%Industrial
80
70
60
50
40
30
20
10
0
32
9 94
46
17 16
57
1912
27
15 13
1
5560
67
Figure (20): Comparison of consumptionpatterns in the operating districts
Eastern Central Western Southern
Residential Commercial Government Industrial Others
Perc
ent
Consumption Type
4
712011 Activities & Achievements
Consumer Service Connections
Attheendof2010,SEChad53,092unfulfilled
requests from consumers for service connections.
During 2011, the company received 155,318 new
requests. Of the total new and old requests, the
company was able to satisfy 136,320, a response
rate of 65%.
Growth Trends in the Past Decade
During the past decade (2002-2011) the number
of consumers increased from 4,029,319 in 2002 to
6,341,025 in 2011(Figure 21), an increase of 57.5 %.
Energy sales during the same period increased by
70.8% from 128,629 GWh in 2002 to 219,662
GWh in 2011 (Figure 22), while peak demand
increased by 102.1% from 23.938 GW in 2002 to
48.367 GW in 2011 (Figure 23).
Table (12): Electricity production, sale, and losses
Quantity of electric energy(GWh)
20102011
189,415193,952Electricity generated at SEC plants
183,721187,824Electricity sent from SEC plants
16,00015,037Electricity imported from SWCC
34,47641,080Electricity imported from other producers
234,197243,941Total electricity carried by the transmission system
212,263219,662Total electricity sold
2010201121,93524,279Total electricity loss in the transmission and
distribution systems
3.01%3.16%Percent of electricity consumed in SEC Plants
9.37%9.95%Loss in the entire SEC system
72 ECRA
220
200
180
160
140
120
6.5
6.0
5.5
5.0
4.5
4.0
Year
2011
2006
2010
2005
2009
2004
2008
2003
2007
2002
Figure (21): Growth of the number of consumers (2002-2011)
Figure (22): Growth of energy sales (2002-2011)
2011
2006
2010
2005
2009
2004
2008
2003
2007
2002
Year
Num
ber
of c
onsu
mer
s
(in m
illio
ns)
Ener
gy S
ales
(in 1
000
GW
h)
732011 Activities & Achievements
50
45
40
35
30
25
20
Fuel Types Used in Energy Production
Natural gas and crude oil were used as fuels to
produce some 74% of the energy in 2011 (Figure
24). The other fuels used were diesel, and heavy fuel
oil (HFO).
Figure (24): Fuel types used in electricity
production in 2011
Figure (23): Growth of peak demand (2002-2011)
5%
21%
Heavy Fuel Oils
Diesel
37%Natural gas
37%Crude Oil
Peak
Dem
and
(GW
h)
Year
2011
2006
2010
2005
2009
2004
2008
2003
2007
2002
74 ECRA
Electricity Tariff in the Kingdom
Introduction
One of the most important concerns of ECRA is that
tariffsaredesignedsothattheyarecostreflective,
fair and affordable to end-users, their structure is
easy to implement, and that income collected by
the industry in accordance with these tariffs meets
its revenue requirements.
In order to achieve these aims ECRA’s concerns
include:
• Developing a methodology for tariff setting and
for periodic review of the adopted tariffs.
• Designing and preparing a tariff structure.
• Developing an overall tariff policy statement for
the Kingdom.
• Preparingastandardizedfinancialreporting
system to be utilized by all licensed service
providers.
• Developing a comprehensive system to collect
financialandoperationaldatafromallservice
providers in the Kingdom.
• Developing a comprehensive cost accounting
system in order to assess service providers’
costs which ultimately affect the tariff paid by
consumers.
ECRAisalsokeenthattariffsreflectthegovernment
concernswithregardtotheefficientuseofavailable
energy sources, and depletion of resources and
protection of the environment, as well as economic
factors. Thus, ECRA strives to insure that tariffs in
theKingdomreflectthoseconcernsbyproviding
consumers with incentives to improve their
utilization of the electricity system, and apply
conservation measures that reduce their costs while
atthesametimetheyimprovetheefficiencyofthe
power system.
A Brief History of Electricity Tariffs in the Kingdom
In the early years of introduction of electricity
services in the Kingdom, prices of these services
varied from one producer to another, depending
on his cost of production. In 1954 the government
Table (13) Electricity Prices in Major Cities per CMD 174 of 1959
City
All Consumers, Except Mosques( in SR/kWh)
Mosques(SR/kWh)
First 100 kWhMore than 100
kWhFirst four hours
after sunset
More than four hours after
sunset
Jeddah 0.24 0.21 0.24 0.18 0.18
Makkah 0.30 0.25 0.30 0.17 0.15
Madinah 0.30 0.25 0.30 0.18 0.15
Khobar 0.30 0.25 0.26 0.17 0.15
Dammam 0.30 0.25 0.26 0.17 0.15
752011 Activities & Achievements
decided to set electricity prices to
be affordable to consumers. For
example, the price in Jeddah was
thus reduced from SR 0.55 per kWh
to SR 0.325 per kWh. Prices were
also set in Makkah and Taif at levels
that guaranteed reasonable returns
to the private owners of the utilities.
In 1959 a new electricity tariff
was issued by Council of Ministers
Decision (CMD) 174 which set the
prices as shown in Table (13),
Beginning on 1/7/1383 AH (18/11/1963) the tariff prices
werereducedandunifiedthroughouttheKingdomby
CMD 421 on 4/6/1383 AH (22/10/1963). The reductions
were 12% percent for Jeddah, 30% for Makkah, and
40% for Taif. Concomitant with these reductions, the
Government guaranteed the private utilities subsidies
that covered their operating costs and a reasonable
marginofprofit.FurtherreductionsinJeddahweremade
in 1389 AH (1969) by the Saudi National Electric Power
Company, the utility operator in the city, which reduced
the rate from SR 0.24 to SR 0.20 per kWh.
On 30/11/1391 AH (17/1/1972) the tariff saw further
reductions via CMD 1099. The prices were as shown in
Table 14.
The CMD included two provisions:
- abolishingthe“meterrent”andchargingafixed
monthly service fee of SR 5.00 for non-industrial
consumers and SR 20.00 for industrial consumers.
- providing annual subsidies to the utility companies
iftheyfailedtomakeprofits.Thesubsidieswere
designedtoguaranteethecompaniesaprofit
margin of 7%.
On 1/7/1393 AH (31/7/1973) the government decreed
reduction of the tariff by 50-60% in 16 smaller towns
intheKingdomthatfixedtherateatSR0.18perkWh
for industrial consumption and SR 0.20 per kWh for
all other consumption. The subsidies for companies
operatinginthesetownsweresettoallowforaprofit
margin of 10% to encourage investment in electricity
services in these regions.
On 20/7/1394 AH (9/8/1974) CMD 1020 set the tariff
for industrial consumption at SR 0.05 per kWh, and SR
0.07 per kWh for all other consumption. The CMD also
raisedtheguaranteedprofitmarginto15%andprovided
for credit facilities and loans through the Saudi Industrial
Development Fund to electricity operating companies.
On 1/3/1405 AH (23/11/1984), the Government
adopted a graduated tariff that increased with each
increasing “bracket” of consumption. The prices were as
shown in Table (15).
Non-industrial consumption (SR/kWh)
Industrial consumption(SR/kWh)
Jeddah 0.14 0.13
Makkah 0.20 0.18
Taif 0.20 0.18
Madinah 0.20 0.18
Yanbu 0.25 0.20
Dammam 0.14 0.10
Table (14): Electricity prices in various cities as per CMD 1099 of 30/11/1391 AH (17/1/1972)
76 ECRA
Inthefollowingfifteenyears1405-1420AH
(1985-2000)twomodificationsweremade
to this tariff that included enlargement of
the «brackets», expansion of the classes
ofbeneficiaries,andreductionofthe
tariffs. A fee of SR0.05/kWh was added to
consumption above 2000 kWh to establish
a fund for electricity projects needed on an
urgent or emergency basis.
The Current Tariff
In 1415 AH (1995) the
Ministry of Industry and
Electricity undertook a
comprehensive study
of the electricity sector
in the Kingdom that
culminated in the
Council of Ministers
Decision 169 which
mandated total overhaul
and restructuring of the
entire sector. The decision also included approval
of a new tariff (Table 16) starting on 1/1/1421 AH
(6/4/2000).
ThetariffwaslatermodifiedbyCMD170on
12/7/1421 AH (9/10/2000) to the current tariff
shown in Table (17) which became effective from
1/8/1421 AH (28/10/2000).
This tariff remained in effect for approximately
ten years. On 19/7/1431 AH (1/7/2010), ECRA’s
Board, utilizing the authority* delegated to it by the
Council of Ministers in 1431AH (2010), approved a
new tariff for the non-residential (i.e., government,
commercial, and industrial) consumption tariff
while the residential consumption tariff remained
unchanged. Thus the current tariff became as shown
in Tables (18-A, 18-B, and 18-C).
Table (15) Electricity tariff adopted on1/3/1405 AH (23/11/1984)
Monthly Consumption
“Bracket”(kWh)
Non-industrial consumption
(SR/kWh)
Industrial consumption
(SR/kWh)
0-1000 0.07
0.051001-2000 0.10
> 2000 0.15
Table (16): Tariff as of 1/1/1421 AH (6/4/2000)
Monthly Consumption(kWh)
Residential, Commercial, Government
(SR/kWh)
Agricultural, Charitable Societies(SR/kWh)
Industrial(SR/kWh)
1-2,000 0.05
0.10
0.12
2,001-4,000 0.10
4,001-5,000 0.13
0.12
5,001-6,000 0.18
6,001-7,000 0.23
7,001-8,000 0.28
8,001-9,000 0.32
9,001-10,000 0.36
>10,000 0.38
* The Council of Ministers Decision granted ECRA the authority to set the non-residential tariff with a ceiling of SR0.26/kWh.
772011 Activities & Achievements
Table (17): Tariff approved by CMD 170 as of 1/8/1421 AH (28/10/2000)
Table (18-A): Current Tariff - Non-industrial Consumption
Monthly Consumption
(kWh)
Residential, Commercial, Government
(SR/kWh)
Agricultural, Mosques, Charitable Societies
(SR/kWh)
Industrial, Medical Facilities, Private Educational Institutions
(SR/kWh)
1-2,000 0.05 0.05
0.12
2,001-4,000 0.100.10
4,001-5,0000.12
5,001-6000
0.12
6,001-7,000 0.15
7,001-8,000 0.20
8,001-9,000 0.22
9,001-10,000 0.24
>10,000 0.26
Monthly Consumption(kWh)
Type of Consumption
Residential(Halalah/kWh)
Agricultural, Mosques, Charitable
Organizations(Halalah/kWh)
Commercial(Halalah/kWh)
Government(Halalah/kWh)
Unchanged, as per CMD 170 As of 19/7/1431 AH (1/7/2010)
1-2,000 5 512
26
2,001-4,000 1010
4,001-5,00012
205,001-6,000
12
6,001-7,000 15
7,001-8,000 20
8,001-9,000 22
269,001-10,000 24
More than 10,000 26
78 ECRA
Table (18-B): Current Tariff – Industrial Tariff* for Small Industries(Industrial Plants With Contracted Loads not Exceeding 1,000kVA)
Variable Tariff(for plants with digital meters)
Seasonal Tariff(for plants with electro-
mechanical meters)Season
Tariff(Halalah/
kWh)Time of Use
Tariff(Halalah/
kWh)Time of Use
12 All times 12 All times 1 October-30 April
10
Off-peak hours Saturday-Thursday: 00:00-8:00.Friday: 00:00-9:00,21:00-00:00
15 All times 1 May – 30 September
26Peak timeSaturday-Thursday: 12:00-15:00.
15 All other times
Table (18-C): Current Tariff – Industrial Tariff* for Large Industries(Industrial Plants With Contracted Loads Exceeding 1,000kVA)
Variable Tariff(for plants with digital meters)
Seasonal Tariff(for plants with electro-
mechanical meters)Season
Tariff(Halalah/
kWh)Time of Use
Tariff(Halalah/
kWh)Time of Use
14 All times 14 All times 1 October-30 April
10
Off-peak hours Saturday-Thursday: 00:00-8:00.
Friday: 00:00-9:00,21:00-00:00
15 All times 1 May – 30 September
26Peak time
Saturday-Thursday: 12:00-15:00.
15 All other times
Applicable Since 19/7/1431 AH (1/7/2010)*
792011 Activities & Achievements
250
200
150
100
50
0
In general, the electricity tariff in the Kingdom is
one of the least expensive in the world as seen
in Figure 25 which shows a comparison of the
average electricity tariff in the Kingdom with
severalcountries.Thedatainthisfigureisthelatest
available in the internet**. All tariffs are for 2011.
Figure (25): Comparison of average electricity tariff in the Kingdom with several countries
Data were taken from the following site: http://en.wikipedia.org/wiki/electricity_tariff**
Tong
a
Den
mar
k
Ger
man
y
Bra
zil
Bel
gium
Net
herl
and
Italy
Irel
and
Swed
en
Spai
n
Port
ugal
Hun
gary
Chi
le
Sing
apor
e
UK
Finl
and
Fran
ce
Chi
na
Latv
ia
Turk
ey
Hon
g Ko
ng
USA
Mol
dova
Can
ada
Rus
sia
Dub
ai
Uzb
ekis
tan
Icel
and
Kin
gdom
of S
audi
Ara
bia
Hal
alah
/ K
Wh
80 ECRA
60
50
40
30
20
10
0
To give an idea of the progression of tariffs in
the Kingdom since 1370 AH (1950) Figure (26)
illustratestheprogressionofthetariffforthefirst
100 kWh of residential consumption in the City of
Jeddah as an example.
Monthly Bill for Residential Consumption
Total residential consumption of electric energy
in 2011 was 109,261 GWh, which represents
49.7 % of total electric energy consumption in the
Kingdom.
By studying monthly residential consumption bills
issued in 2011, the following becomes apparent
(Figure 27):
• 61.4% of the bills were valued at SR100 or less
each.
• 25.6% of the bills ranged in value between
SR101.00 and SR200.00 each.
• 7.3% of the bills ranged in value between
SR201.00 and SR500.00 each.
• Only 5.9% of the bills had a value exceeding
SR500.00 each.
From the preceding data it is clear that more than
94% of the monthly residential consumers bills
issued in 2011 did not exceed SR500.00 each
(Figure 25).
Figure (26): Change of tariff per kWh of the first 100 kWh of
residential consumption in the city of Jeddah from 1950 to the present
1950
1960
1970
1980
1990
2000
2010
Year
Tari
ff
(Hal
alah
/kw
h)
812011 Activities & Achievements
Figure (27): Percentage distribution of monthly bills 2011
Value of the monthly bill
70%
60%
50%
40%
30%
20%
10%
0%
1.74.2 2.9 4.4
9.2
16.2
61.2
more than SR
1000.00
SR501.00 - SR
1000.00
SR401.00 - SR
500.00
SR301.00- SR
400.00
SR201.00 - SR
300.00
SR101.00 - SR
200.00
SR100.00 or less
82 ECRA
100%
90%
80%
70%
60%
50%
94.191.1
77.5
61.4
86.7
Undoubtedly, the monthly bill will vary greatly from
one month to another according to season. The bill
amountincreasessignificantlyinthesummerand
decreases in the winter for most parts of the country.
Cost of Unit of Electricity and Average Sale Price
In 2011, the average cost of a unit of electricity (kWh)
in the Kingdom was about 14.9 Halalah/kWh. This
figurecoversthecostsofgeneration,transmission,
and distribution. It accounts for operational and
capital expenditures, fuel, purchased electricity, and
depreciation (Figure 29). The average price collected
from consumers by SEC was 14.1 Halalah/kWh.
Figure (28): Cumulative percentage of monthly bill issued in 2011
Cum
ulat
ive
perc
enta
ge
Not exceeding SR
500.00
Not exceeding SR
400.00
Not exceeding SR
300.00
Not exceeding SR
200.00
Not exceeding SR
100.00
Value of the monthly bill
832011 Activities & Achievements
Figure (29): Distribution of cost of electricity unit
27%
30%
18%
12%
13%
OperationalExpenses
Depreciation
Fuels
CapitalExpenses
PurchasedElectricity
84 ECRA
Water Desalination in 2011
Saudi Arabia is considered the largest producer
of desalinated water in the world. The following
sections contain a description of the water
desalination system in the Kingdom.
Production of Desalinated Water
The Saline Water Conversion Corporation (SWCC) is
the principal entity for desalinated water production
in the Kingdom. Its share of total production is
about 58%. Table 19 shows the capacities of entities
working in desalinated water production and
cogeneration, while Figure 30 shows the percentage
of desalinated water produced by each licensee.
The quantity of desalinated water produced by
SWCC in 2011 increased by 5.5% compared to
the previous year (Table 20) to reach 933 million
cubic meters. Figure 31 shows the percentage
share of each SWCC plant in the total corporation
production.
Table (19): Desalinated Water and Steam Productions of
Entities Licensed to Operate in the Desalinated Water and Cogeneration Fields
LicenseeNumber of Plants
Desalinated Water Production Capacity
(M3/Day)
Steam Production Capacity
(Ton/Hour)
SWCC 17 3,363,731 30,689
Jubail Water & Electricity Co. 1 805,464 5,170
Shuaibah Water & Electricity Co. 1 880,000 6,048
Tihamah Power Generation 4 0 4,405
Marafiq(Yanbu) 1 95,760 0
Shuqaiq Water & Electricity Co. 1 216,000 0
Saudi Aramco 6 0 2,514
Rabigh Arabian Water & Electricity Co. 1 196,728 4,295
Jubail Power Co. 1 0 510
Shuaibah Expansion Project 1 150,000 0
Bawarej International Co. 2 52,000 0
Total 36 5,759,683 53,631
852011 Activities & Achievements
Figure (30): Percentage Distribution of Production
Capacities Among the Licensees
Table(20): Desalinated Water Produced in
Each SWCC Plant
Transportation of Desalinated Water
SWCC is responsible for transportation of the
desalinated water from the production plants to the
major reservoirs of the Potable and Sanitary Water
Departments in the various cities and towns. These
departments, which come under the purview of the
Ministry of Water and Electricity, along with the
National Water Company (NWC) are responsible
for water distribution to the ultimate consumers.
Figure (32) shows locations throughout the Kingdom
of SWCC’s water desalination plants as well as the
major water transportation pipelines.
58.4%
12.3%
15.3%
14%
SWCC
OtherProducers
Shuaibah Water& Electricity
Jubail Water& Electricity
Figure (31): Percentage share of
each SWCC plant in the corporation’s total
desalinated water production
Production Quantity(Million Cubic Meter)
PlantYear
2011 2010
Jubail 375.9 334.4
Al-Khobar 141.9 152.1
Khafji 7.8 7.8
Jeddah 136.2 132.7
Shuaibah 131.7 100.2
Yanbu 113.2 118.4
Shuqaiq 2.2 15.0
Small Plants 23.8 23.0
Total Production 932.7 883.6
40.3%
15.8%
14.6%
15.2%
14.1%
Jubail
The Other Plants
Jeddah
Al-Khobar
Shuaibah
86 ECRA
3.13.02.92.82.72.62.52.42.3
Figure (32): Desalination plants and major desalinated
water transportation lines in the Kingdom
SWCC’s Annual Production Capacity of Desalinated Water
Figure (33) shows SWCC’s production capacity of desalinated water over the past ten years.
Figure (33): Production capacity of desalinated water in the past ten years
Prod
ucti
on C
apac
ity
(Tho
usan
d cu
bic
met
ers)
2002 20062004 2008 20102003 20072005 2009 2011
Desalination Plants
City
Pipelines
Future pipelines
Haql
TabukDuba
Wajh
Omloj
Yanbu
KhafjiHafar Al-BatinRass alzor
NeairiahZulfi
GatHasaa
ShaqraRiyadh Hufuf
Majma’ah
BuraydahJubayl
DammamKhobar
Jeddah
Barakk
Shuqaq
Farasan Jazan
Madinah
RabighMakkah
TaifShuaiba
Baha
Ahd Almasareha
Khamis MushaytAhadRafidah
872011 Activities & Achievements
Production Capacity Factor
The production capacity factor expresses the
ratio of actual production to design capacity. The
overall average production capacity factor for the
entire corporation decreased from 84.2% in 2010
to 83.1% in 2011. The decrease is due to several
causes. They include ceasing production of some
of the units in the Shuaibah and Shuqaiq plants in
order to accommodate about 403 Million cubic
meters of water received from private producers
through SWCC pipelines, as well as maintenance
work and rehabilitation program in some of the
plants.
Electricity Generation in SWCC
Most water desalination plants owned by SWCC are
of the cogeneration type, where desalinated water
is produced simultaneously with electricity. SWCC
sells most of its electricity production to SEC.
In 2011 SWCC generated 24.1 GWh of electricity.
The West Coast Plants contributed 9.1 GWh (37.8%
of the total generation production) while the East
Coast Plants produced 15.0 GWh (62.2% of the
total production).
SWCC Plants Costs of Production
The average costs of desalinated water and
electricity production as well as the average
cost of transportation of desalinated water to the
major reservoirs of the potable and sanitary water
departments are shown in Table (21). It is clear
from the table that production of desalinated water
in small plants, which are located in remote areas
and serve very small communities, is extremely
expensive.
Table (21): SWCC average costs of production of desalinated water
and electricity, and average cost of transportation of desalinated water
Average Cost
Cos
t of
w
ater
pr
oduc
tion
East Coast 2.18 SR/m3
West Coast 3.05 SR/m3
Small Plants 11.37 SR/m3
Cost of water transportation 1.12 SR/m3
Cost of electricity generation 0.07 SR/kWh
88 ECRA
SWCC Restructuring Plan
In conformity with the policy adopted by the
government to privatize a certain number of
economic activities, and the decisions of the
Council of Ministers and Supreme Economic
Council to implement privatization in the area
of water desalination, SWCC had undertaken in
the past few years tremendous efforts to study
restructuring of its activities and modifying its
charter in order to foster private sector participation
and investment in the construction and operation of
new desalination plants. The studies concentrated
particularly on privatization alternatives of
SWCC. These efforts were concluded in late
2008 with adoption of transforming SWCC into a
holding company (Figure 34) with wholly owned
subsidiaries. This approach permits participation of
the private sector in the production companies (in a
fashion similar to the IWPPs), and allows the private
sector to participate at a later stage in the ownership
of the holding company through public share
offering. The private sector share in the ownership
of the subsidiary production companies will depend
on the investment attractiveness of each plant,
but will not be less than 60% of each subsidiary
production company.
Figure (34): Final structure of SWCC after implementation of the restructuring plan
The Holding Company
Full Ownership Partial Ownership
(Subsidiares)
ResearchInstitute &
DesalinationTechnologies
OtherProduction
Plants
Trans-porta-tion
Khafji
Al-Khobar
SmallPlants
Shuqaiq
Ras Al-Khair
Shuaibah
Jubail
Yanbu
892011 Activities & Achievements
Since the privatization model was adopted, SWCC
concentrated its efforts on preparation of its incorporation
documents, submitting them to the Supreme Economic
Council, preparing the commercial agreements, working
out details of the organizational structure, streamlining
human resources, reengineering operations, developing
IT strategies and applications, working on change
management,definingtheassetsanddetermining
their valuation, and other processes and procedures.
SWCC is currently undergoing actual application of
restructuring and transformation into a commercial mode
of operation.
At the present time SWCC is awaiting promulgation
of the order to form the holding company. It will
then undertake transforming the plants targeted for
privatization into production companies, and thereafter
prepare RFBs to privatize these companies.
In order to privatize the holding company, the private
sector will be allowed in the short to medium-term (i.e.,
aperiodnotexceedingfiveyearsafterestablishingthe
holding company) to share in its operations through a
management contract (or contracts).
In the long run the possibility of transforming the strategic
transportation unit into a production company will be
considered. The private sector may then participate
through a public share offering or as a strategic partner.
Table (22) lists the desalination plants targeted to be
transformed into production companies with private
sector participation.
Table (22): SWCC desalination plants targeted for privatization as production companies
Production Company Plants that it will own
Yanbu Yanbu Plants 1,2, 3, RO Plant
Small Plants Group 1 Dhuba 3, Umloj 3, Wajh 3, 4
Small Plants Group 2 Leith 1, Gunfuthah 1, Farasan 2, Rabigh 2
Shuaibah Shuaibah 1, 2, 3
Shuqaiq Shuqaiq 1, 3
Al-Khobar Al-Khobar 3, 4
Jubail Jubail 4, RO Plant
90 ECRA
Participation of the Private Sectorin the Electricity and Water Desalination Industry
Electricity Industry
ECRA considers private sector participation in the
electricity and water desalination industry essential
for the development and sustainability of this
industry in the Kingdom. The Authority has thus
placed this matter as one of its highest priorities.
As shown in Table (10) page 66, the private sector
alreadyparticipatessignificantlyingeneration.
According to a study undertaken to estimate
the funding needs of the electricity services for
the period 2009-2020, the amount required for
electricity generation, transmission and distribution
was estimated at SR526 billion distributed as shown
in Table (23).
The estimates of Table (23) are based on the
assumptions that by the year 2020 the peak load
will be 71,940 MW and the generation reserve will
be 15%.
Undoubtedly, the amount of work required by the
electricity industry and the volume of investments
needed represent attractive opportunities for the
private sector to participate in the execution of the
industry projects and in its growth and development.
The investment opportunities for private sector
participation in the industry include:
• Developing Independent Power Projects (IPPs),
and Independent Water and Power Projects
(IWPPs).
• Building, leasing, and/or operating transmission
lines and pipelines.
• Forming power generation and desalination
production companies.
• Obtaining concessions or leases for existing
generation and water production facilities.
• Obtaining facility management contracts.
• Direct purchase of selected existing power and
water desalination assets.
• Undertakingelectricitydistributioninspecific
areas.
• Providing services to consumers.
Table (23): Estimated funding required for implementing electricity
projects through the Year 2020.
ActivityRequired Funding
(in billion SR)
Percentage of total funding required
Generation 335 63.7%
Transmission 121 23%
Distribution 70 13.3%
Total 526
912011 Activities & Achievements
Water Desalination Industry
The large economic development that the Kingdom
is currently undergoing has led to an increase in
demand for desalinated water, and consequently
the need to execute many projects that require large
financialinvestments.Studieshaveshownthatthe
Kingdom will need to invest around SR300 billion
on water desalination in the coming twenty years.
The studies have shown that, in the medium term,
the estimated costs for implementing projects
for water desalination, cogeneration, and water
transportation up to the year 2020 will be SR91
billion (Figure 35). The estimates were made on
the basis that by 2020 SWCC will be producing 6
million cubic meters of desalinated water daily.
As with the electricity industry, undoubtedly, the volume
of work required by the desalination industry, and the
size of investment it needs present attractive opportunities
for participation of the private sector in carrying out the
water desalination industry projects, and share in its
growth and development. The opportunities available to
the private sector to participate in this industry include
the following:
• Executing the projects that are let out for bidding
by SWCC, through the system known as EPC
(engineering, procurement, and construction).
• Building independent projects for water desalination after
the holding company and its subsidiaries are established.
• Building pipelines.
• Supplying and manufacturing spare parts for the
desalination plants.
• Carrying out many of the operation and maintenance
contracts for the production plants and the pipelines.
Figure (35): Desalinated water industry financing
requirements for capital andoperational expenses to
the year 2020
(amounts in SR Billion)
65.4
Capital Expenses Operational Expenses
25.5Electricityand
Water43.7
Water9
Transportation8.8
Transportation
21.7
Electricity7.7
***ECRA will be working in coordination with the
Ministry of Water & Electricity (MoWE), SEC, SWCC,
investors from the private sector, and all other
interested parties to select the options most suitable
andbeneficialtoSaudiArabia.
92 ECRA
The Appendices
932011 Activities & Achievements
94 ECRA
Appendix (1)Authorizations, Licenses, and Exemptions from Licensing
Table (A1-1): Permits Issued by the Authority
(By the end of 2011)
Activity OrganizationProject
LocationProduction Capacity
Cog
ener
atio
n
1 Rayet Al-Hijaz Trading Est. RabighElectricity: 5,000 MW
Desalinated water: 150,000 M3 /day
2Rabigh International Power & Water Co.
RabighElectricity: 1,200 MW
Desalinated water: 450,000 M3 /day
3Misha’al Atiyah Al-Malki
Est.Rabigh
Electricity: 1,400 MW Desalinated water: 1,000,000 M3 /day
4 Itlal Al-Ghad Group RabighElectricity: 1,000 MW
Desalinated water: 500 M3 /day
5National Tri-Production
Energy Co.Jeddah
Electricity: 1,000 MW Desalinated water: 100,000 M3 /day
Steam: 100,000 Ton/hour
6 Arabian Paper Co. DammamElectricity: 50 MW
Steam: 250 Ton/hour
7District Cooling Systems
Co.Taif
Electricity: 600 MW Desalinated water: Not determined yet.
Steam: Not determined yet.
8Mabaher Al-Jazeerah
Strategic Power & WaterRabigh
Electricity: 2,060 MW Desalinated water: 1,500 M3 /day
Elec
tric
ity
Gen
erat
ion
9Electrical Energy
and Communication Technology Co.
Various sites Electricity: 1,000 MW
952011 Activities & Achievements
Table (A1-2): List of organizations holding licenses
(By the end of 2011)
Activity Organization Project Location Production Capacity
Elec
tric
ity g
ener
atio
n
1 Saudi Electricity Co.Throughout the
Kingdom48,777 MW
2General Contracting Co.
(Alolayan Group).Mobile units in several parts of the Kingdom
618.4 MW
3 Saudi Cement Co. Ein Dar, Hafouf 246 MW
4Taqah for Environmental and Electric Energy Systems Ltd.
Mobile units in several parts of the Kingdom
353.2 MW
5 Energy Equipment Rental Co.Mobile units in several parts of the Kingdom
331.34 MW
6 Rabigh Electricity Co. Rabigh 1,320 MW
7Abduallah & Abdul Aziz
Kanoo Co.Mobile units in several parts of the Kingdom
119 MW
8 Dhurma Electricity Co. Riyadh 1,756 MW
9 Twairqi Power Co. Dammam 126 MW
10 Nour Power Co.Mobile units in several parts of the Kingdom
23 MW
11 Hajar Electricity Co. Gurayyah 4,098 MW
Elec
tric
ity tr
ansm
issi
on 12 Saudi Electricity Co.Throughout the
Kingdom
13Power and Water Utility
Company for Jubail and Yanbu (Marafiq)
Jubail and Yanbu
Ow
ners
hip
of a
tr
ansm
issi
on n
etw
ork
14 Saudi Arabian Mining Co.
(Ma’aden)Ras Al-Khair
Overhead line: 122 km Max. load: 2300 kVA
Voltage: 380 kV
96 ECRA
Activity Organization Project Location Production Capacity
Elec
tric
ity d
istr
ibut
ion
and
reta
il
15 Saudi Electricity Co.Throughout the
Kingdom
16Power and Water Utility
Company for Jubail and Yanbu (Marafiq)
Jubail and Yanbu
Cog
ener
atio
n
17Saline Water Conversion
Corporation (SWCC)Throughout the
Kingdom
Electricity: 5,017.6 MW Desalinated water:2,923,387 M3 /day
Steam: 28,692 ton/hour
18 Jubail Power Co. Jubail Industrial CityElectricity: 250 MW Steam: 510 ton/hour
19Tihama Power Generation Ltd.
(Saudi Aramco Independent Projects)
Juaimah, Othmaniah, Shedgum, andRas Tannourah
Electricity: 1,083 MW Steam: 4,405 ton/hour
20Shuaibah National Water &
Electricity Co.Shuaibah
Electricity: 1,191 MW Desalinated water:888,000 M3 /day
Steam: 6,053 ton/hour
21Shuqaiq Water & Electricity
Co.Shuqaiq
Electricity: 1,020 MW Desalinated water:212,000 M3 /day
22 Jubail Water & Electricity Co. JubailElectricity: 2,875 MW
Desalinated water:805,464 M3 /day
23Rabigh Arabian Water &
Electricity Rabigh
Electricity: 120 MW Desalinated water:
12,000 M3 /day Steam: 470 tons/hour
24 Saudi AramcoRiyadh, Buqaiq, Qatif, Kharasaniyah, Barri,
Yanbu
Electricity: 1,051 MW Desalinated water:
2,514 M3 /day
25Power and Water Utility
Company for Jubail and Yanbu (Marafiq)
YanbuElectricity: 1,533 MW
Desalinated water:95,760 M3 /day
Table (A1-2 continued): List of organizations holding licenses
(By the end of 2011)
972011 Activities & Achievements
Activity Organization Project Location Production Capacity
Wat
er d
esal
inat
ion 26 Shuaibah Expansion IWPP Co. Shuaibah
Desalinated water:150,000 M3 /day
27 National Tri-production Co. JeddahDesalinated water:
80,000 M3 /day
28Bawarij Water Desalination
International, Ltd. Shuaibah
Desalinated water:50,000 M3 /day
29Saline Water Conversion
Corporation (SWCC)Several locations in the
KingdomDesalinated water:440,299 M3 /day
Elec
tric
ity
Trad
ing 30 Water & Electricity Co. 1,750 MW
31 Marafiq(Tawreed)Co. 2,744 MW
Des
alin
ated
Wat
er
Trad
ing
32 Water & Electricity Co. 1,242,000 M3/day
33 Marafiq(Tawreed)Co. 800,000 M3/day
34 Rakaa for Energy & Water Co. 50,000 M3/day
Tran
spor
tatio
n of
D
esal
inat
ed W
ater
35Saline Water Conversion
Corporation (SWCC)Throughout the
Kingdom---
Table (A1-2 continued): List of organizations holding licenses
(By the end of 2011)
98 ECRA
Activity Organization Project locationProduction
capacity
Elec
tric
ity g
ener
atio
n
1 Yanbu Cement Company Yanbu 100 MW
2Yamama Saudi Cement
Company Ltd. Riyadh 158 MW
3 City Cement Company Marat Center Riyadh 46 MW
4 Al-Tuwairqi EnergySecond Industrial Estate,
Dammam450 MW
5 Saudi Arabian Mining Co. (Ma’aden)
Hazm Al-Jalameed 50 MW
6Nation Agricultural
Development Co. (Nadec)Haradh
28 MW
7 Tabuk Cement Co. Dhuba 46MW
8 Najran Cement Co. Najran 56 MW
9 Middle East Chemicals Ltd.Al-Ajemi Industrial City,
Riyadh8 MW
Cog
ener
atio
n
10 National Shrimp Co. Al-Leith
Electricity: 25MW Desalinated water:
420 M³/day Steam: 4.5 ton/hour
11 Saudi Paper Co.Second Industrial Estate,
DammamElectricity: 15 MW Steam: 25 ton/hour
Wat
er d
esal
inat
ion
12 Tabuk Cement Co. DhubaDesalinated water:
1,500 M³/day
Table (A1-3): List of entities with exemptions from licensing*
(At the end of 2011)
* Under the Implementing Regulations an exemption from licensing is given to a generation station if it is not connected to the transmission or distribution systems (other than those also exempted), and the electricity service is restricted to use by the owner of the generation station. An exemption is also given to a transmission and/or distribution system in an analogous manner.
992011 Activities & Achievements
Appendix (2)Documents and Information Available on ECRA’s Website
ECRA’s website on the internet (www.ecra.gov.sa) contains a large number of documents and useful
information for consumers, investors, and anyone interested in the electricity and water desalination industry.
These documents and information include the
following:
Rules and Regulations
• Electricity Law
• ECRA’s Charter
• Implementing Regulations for the Electricity Law
Covering ECRA’s Responsibilities
• Implementing Regulations for ECRA’s Charter
• Codes and regulations
• Circulars and decisions concerning the
electricity industry
• Council of Ministers Decision Number 169
issued on 11/8/1419AH (1/12/1998) dealing
with restructuring of the electricity sector
• Council of Ministers Decision Number 170
issued on 12/7/1421AH (9/11/2000) modifying
the electricity tariff which was included in
CMD Number 169 issued on 11/8/1419AH
(1/12/1998)
• Current electricity Tariff.
• Electricity Service Connection to Buildings
Bylaw
• Buildings Electrical Wiring Bylaw
• Standby Electric Energy Generation Bylaw
• Safety Rules Bylaw
• Saudi Electricity Transmission Code
• Saudi Electricity Distribution Code
• Water Desalination Code
• Rules and Procedures for Reporting and
Investigating Electricity Industry Accidents
• Development of Mechanism for Design of Tariff
Structure, and System for its Review
National Electricity Register
• A brief about the Register
• Historical data
• Licenses
• Record of Decisions
• Codes and Standards
• Unifiedoffers
• License remuneration calculation
• Station capacities
• Capacities of transmission and distribution
networks
• Electricity network expansion plans
• Other information
1. Number of subscribers and energy sold
(2005-2009)
2. Energy loss in the network
3. Annual peak load in the Kingdom
4. Detailed peak load for the Kingdom
5. Electricity Industry Statistical Yearbook 2008
6. Electricity Industry Statistical Yearbook 2009
100 ECRA
7. Electricity Industry Statistical Yearbook 2010
8. Special requests/suggestions
Consumer Care
• Service Provision Manual
• Procedure for handling consumer complaints
• Consumer complaints for the past years
• Form for consumer complaint against SEC
• ECRA’s role in serving the consumer
• Rights of consumer vis-à-vis the service provider
• The consumer responsibilities
• The booklet “ECRA…at the Service of the
Consumer” (in Arabic)
Investor Services
• License rules and procedures
- Authorization Requests
• Request to undertake electricity generation
or cogeneration activity
• Request to undertake water desalination
activity
- License Requests
• Request to obtain a license to undertake any
of the following activities of the electricity
and water desalination industry:
• Generation
• Trading
• Transmission
1012011 Activities & Achievements
• Distribution
• Desalination
• Cogeneration
• Water transportation
- License Forms
• Electricity distribution and retailing license
• Electricity generation license
• Cogeneration license
• Electricity transmission license
• Electricity retailing license
• Trading license
- Waiver Forms
• Waiver from electricity license form
• Temporary waiver from water desalination
license form
Annual Reports
• ECRA’s Activities and Accomplishments 2011
• ECRA’s Activities and Accomplishments 2010
(Arabic only)
• ECRA’s Activities and Accomplishments 2009
• ECRA’s Activities and Accomplishments 2008
• ECRA’s Activities and Accomplishments 2007
• Annual Report for the period 2002-2006
Studies
• Summary of the Long Range Plan for Electricity
Generation and Transmission.
• A synopsis of the Desalination Code in the
Kingdom.
102 ECRA
• Development of the program for electricity
demand-side management in Saudi Arabia.
• Development of the electricity industry major
performance KPIs: determination of the targets
and incentives.
• Development of the electricity industry major
performance KPIs: the targets and incentives
report.
• Development of the electricity industry major
performance KPIs: major performance KPIs
report.
Papers of Activities Undertaken by ECRA
The following papers represent activities undertaken
by ECRA:
• ECRA’s participation in the Energy Conservation
EfficiencyForumandExhibition.
• The meeting of the Demand-Side Load
Management in Saudi Arabia project.
• ECRA’s participation in the IEE Energy
Conference.
• Workshop on Development of the system of
Electricity Load Management in Saudi Arabia.
• Second Workshop to Bolster Renewable Energy
in Saudi Arabia.
1032011 Activities & Achievements
• Development of a National Policy to Bolster
Renewable Energy in Saudi Arabia.
• Presentations of The First Assembly of the GCC
Electricity Sector Regulators.
• Presentations of the Workshop on Structuring
and Development of the Electricity Industry in
Saudi Arabia.
• Symposium of Electricity Terminology.
• Workshop to present the performance KPIs
project.
Conservation
• How to reduce electricity consumption of
electrical equipment?
• The Consumer Guide to Conserving Electrical
Energy Consumption and Load Shifting.
• Add to Your Knowledge: Energy Posters.
104 ECRA
Board of Directors
Management of the Authority
1052011 Activities & Achievements
106 ECRA
Board of Directors
H.E. Adullah A. Al-HuseyenMinister of Water & Electricity
Chairman of the Board
H.E. Dr. Abdullah M. Al-ShehriGovernor
Electricity & Cogeneration Regulatory Authority
Deputy Chairman of the Board
Mr. Hassan F. AqeelDeputy Minister for Internal Trade
Ministry of Commerce & Industry
Mr. Abdullah I. Al-HubayibChairman of the Board,
Saudi ABB Co.
Dr. Abdullah A. Al-AlsheikhVice-Governor for Planning & Development
Saline Water Conversion Corporation
Prof. Fahad H. DakhilExecutive Director,
Educational & IT Projects Co.
Mr. Abdul Aziz O. Al-OmairAsst. Deputy Minister for
Financial and Accounting Affairs
Ministry of Finance
Mr. Safar M. DhofayerExecutive Manager
Southern Cement Co.
Dr. Ahmed S. Al-KhalifaAssistant Deputy Minister for Electricity Affairs
Ministry of Water & Electricity
Dr. Khalid H. BayyariSenior Vice-President and General Manager
Advanced Electronics Co.
Mr. Abdullah A. Al-JarbouHead, Municipalities & Housing Sector
Ministry of Economy & Planning
Dr. Fahd Saleh Al-SultanSecretary General
Council of Saudi Chambers
Mr. Khalid H. Al-SenaniDirector, Gas Supplies and Pricing Department
Ministry of Petroleum & Mineral Resources
1072011 Activities & Achievements
Management of the Authority
VICE-GOVERNORS
Dr. Saleh A. BakhrebahVice-Governor,
Support ServicesTel: (01) 201-9104Fax: (01) 201-9105
Email: [email protected]
Mr. Nasser H. QahtaniVice-Governor,
Regulatory Affairs Tel: (01) 201-9034Fax: (01) 201-9035
Email: [email protected]
Dr. Abdulrahman Al-Ibrahim*Vice-Governor ,
Consumers & Service Providers Affairs
Tel: (01) 201-9172Fax: (01) 201-9173
Email: [email protected]
ADVISORS
Dr. Mohammed A. Abul HamayelAdvisor, and Supervisor of Information Technology
Tel: (01) 201-9200Fax: (01) 201-9203
Email: [email protected]
Mr. Khalid M. MaziedLegal Advisor/ Board Secretary
Tel: (01) 201-9117Fax: (01) 201-9296
Email: [email protected]
Department Heads
Mr. Mohammad Al-HusseiniDirector,Governor’sOffice
Tel: (01) 201-9007Fax: (01) 201-9012
Email:[email protected]
Mr. Nuais Al-HwaidyDirector, Public Relations
Tel: (01) 201-9045Fax: (01) 201-9044
Email: [email protected]
Prince Saud A. Al-MugrenDirector, Consumer Affairs
Tel: (01) 201-9220Fax: (01) 201-9227
Email: [email protected]
(To be appointed)Director, Service Providers Affairs
Tel: (01) 201-9160Fax: (01) 201-9162
Email: [email protected]
Mr. Abdul Rahman Al-MohaiziDirector General, Legal &
Licensing AffairsTel: (01) 201-9131Fax: (01) 201-9132
Email: [email protected]
Mr. Fayez G. Al-JabriDirector General, Technical Affairs
Tel: (01 201-9111Fax: (01) 201-9113
Email: [email protected]
Mr. Mansour H. Al-AnaziDirector General, Economic Affairs
Tel: (01) 201-9120Fax: (01) 201-9123
Email: [email protected]
Mr. Ibrahim A. Al-GaraawiDirector, Finance
Tel: (01) 201-9280Fax: (01) 201-9287
Email:[email protected]
Mr. Fahd M. Al-HassaniDirector, PersonnelTel: (01) 201-9263Fax: (01) 201-9265
Email: [email protected]
Mr. Hamid k. Al-MalkyDirector, Administrative Support
Tel: (01) 2019-9109 Fax: (01) 201-3211
Email: [email protected]
Mr. Saleh A. Al-TurabiDirector, Property Management
Tel: (01) 201-9020Fax: (01) 201-9025
Email: [email protected]
GOVERNORH.E. Dr. Abdullah M. Al-Shehri
Tel: (01) 201-9009 Fax: (01) 201-9012 Email: [email protected]
* On18/1/1433AH(13/12/2011)hewasappointedbyaRoyalOrderasGovernorofSWCC.Thus,theofficeofVice-GovernorforConsumer and Service Providers Affairs became vacant as of that date.
108 ECRA
ECRA Headquarters Building
Ministry of the Interior
Al-Khaleej OverpassCairo SquareKhurais Road
Takhassusi St.
King Fahad R
oad
to Dammam
IntercontinentalHotel
Council ofSaudi Chambers
Location Map of the ECRA Headquarters
to Makkah Al-Mukarammah
1092011 Activities & Achievements
Electricity & Cogeneration Regulatory Authority
King Fahd National Library Catalog
REDMEC Number: 1658-3523
Deposition Number: 1428-2329
ww
w.dakkin.com
For further information onthe Authority please contact
The Public Relations Department
Public Relations Telephone: (01) 201-9045 | Public Relations Fax: (01) 201-904ECRA Operator: (01) 201-9000 | ECRA Toll Free: (800) 125-9000
Or please visit our site on the internetwww.ecra.gov.sa