Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
1 | P a g e
EE 456 Design Project December 7, 2011
Project Members: Eurydice B Ulysses
Yanyi He
Ayoub Ali
2 | P a g e
Table of Contents
Transmission Map……………………………………………………………………………………….3
One-Line Diagram……………………………………………………………………………………….4
Introduction ……………………………………………………………………………………………….5
Section 1 Base Case ………..........................................................................................................................................5
Base Case Bus Voltages and Angles.............................................................................................................6
Real and Reactive Power Flow at all Lines...................................................................................................6
Generator Real and Reactive Power Outputs ...............................................................................................7
Voltage Ratings Violation for Base Case......................................................................................................8
Contingency Analysis of the Base Case........................................................................................................8
Generator Outage Data...................................................................................................................................9
Full Contingency Assessment of Base case...................................................................................................9
Cost of Resolving Base Case Issues............................................................................................................10
Section 2
Modified Power System for New Needs…….. ...........................................................................................11
Normal Operating Conditions Voltage Ratings Violations….....................................................................11
Contingency Analysis of Modified Power System......................................................................................12
Generator Outage Data………………………….........................................................................................12
Full Contingency Assessment of the New Design………...........................................................................12
Cost of the New System……...………………............................................................................................14
Validation of Minimal Cost………………….............................................................................................14
Conclusion……..………………………………………………………………………………………….14
References……..………………………………………………………………………………………….15
3 | P a g e
Transmission Map
Figure 1: A transmission map of the system with modifications showing the line routes and voltages
4 | P a g e
One-Line Diagram
Figure 2: A one-line diagram of the system showing bus, line, transformer, and load connections
5 | P a g e
Introduction
A power system is an energy system consisting of loads, supplies, transformers, transmission
lines, etc. The transmission lines provide paths from supplies to distanced loads. The
transformer is a facility to coordinate system operation at different voltage levels. The
coordination of all the proper power system infrastructures ensures reliable operations. A well-
designed power system is not vulnerable to rational changes of systems or even contingencies.
We call it a reliable power system. The reliability standards are referred to criteria of North
America Electric Reliability Corporation (NERC) [1].
In this project, we were initially given a reliable system. However, the system may not have been
reliable when considering NERC reliability criteria. Firstly, we proposed some investments and
upgrading strategies to modify the exercise system. Secondly, the system was subject to changes.
The changes partially contained load growth, additional infrastructures, and potential
contingency events. Our group aimed to find one of the most economic ways to modify the
previous reliable power system that was still valid under changes according to NERC standards.
The new power system could also satisfy and serve new needs. All the numerical results were
obtained from PSSE.
The report is organized as follows: Section 2 is introduction of our existing power system.
Section 3 is the primarily modified power system with additional infrastructures for load growth.
We will give our economic design in Section 4. Contingencies study is in Section 5.
Section 1
Base Case
The base case was composed of 10 real and reactive loads, 3 generators, 2 transformers, and 20
transmission lines located at 17 buses. Tables I to IV are data of loads, generators, transformers,
and transmission lines respectively. The tables also show the operation results of the base case.
We had 4 voltage violations of base case at buses 10, 13, 16, and 17 under normal conditions. All
4 violations were due to low voltage. Therefore, the most economical way to increase the voltage
was to install fixed shunt capacitors at the violating buses. The capacities of fixed shunt had to be
within a certain range. A small shunt would not be enough to cause any leverage, and a large
shunt would cost more and cause excessive voltage. The 4 violated buses were all 69 kV buses.
In order to avoid recurrent violation, we picked buses 10, 11, 13, and 16 to install the fixed
shunt. We noted that when bus 11 was not picked, it showed violation in contingency analysis
frequently. Although bus 17 was neglected in the selection, capacitors at bused 10, 13, and 16
helped balance the voltage output at bus 17. After careful consideration, 15 MVAR fixed shunts
were installed at buses 10, 11, and 13, and 5 MVAR was added to bus 16.
6 | P a g e
Table I: Bus Voltages and Angles
Bus number Bus name Bus voltage (pu) Angle (degrees)
1 OWL 1.0 0
2 SWIFT 1.0 -1.58
3 PARROT 1.0 -3.08
4 LARK 0.9620 -6.57
5 JAY 0.9630 -6.79
6 RAVEN 0.9670 -6.76
7 WREN 0.9612 -7.15
8 ROBIN 0.9687 -6.32
9 SISKIN 0.9704 -4.22
10 JUNCO 0.9036 -10.02
11 QUAIL 0.9761 -4.60
12 HERON 0.9840 -4.19
13 EGRET 0.8955 -11.59
14 GULL 0.9926 -2.68
15 CROW 0.9691 -6.26
16 YANYI 0.9532 -7.92
17 EURY 0.9528 -6.39
Table II: Real and Reactive Power Flow and Currents at all Lines
From
Bus Name
To
Bus
Name
Real
Power
Flow
(MW)
Reactive
Power
Flow
(MVAR)
Current
(Amps)
1 Owl 9 Siskin 111.0 26.4 409
11 Quail 78.2 9.7 282
14 Gull 5.9 -1.2 21
2 Swift 11 Quail 89.6 24.3 333
12 Heron 81.2 13.9 295
14 Gull 29.2 4.2 106
3 Parrot 6 Raven 68.1 28.0 322
12 Heron 17.1 13.9 110
15 Crow 64.9 31.8 333
4 Lark 5 Jay 35.8 -7.6 55
9 Siskin -65.8 -2.4 271
5 Jay 4 Lark -12.7 6.5 53
6 Raven -4.3 -12.1 48
7 Wren 34.2 1.4 127
7 | P a g e
8 Robin -27.2 -11.6 110
11 Quail -90.0 -14.3 340
6 Raven 3 Parrot -84.3 -25.7 327
5 Jay 4.3 10.7 43
7 Wren 5 Jay -34.2 -2.0 128
15 Crow -55.8 -18.0 219
8 Robin 5 Jay 27.2 10.4 108
12 Heron -67.2 -15.4 255
9 Siskin 1 Owl -109.4 -21.1 412
4 Lark 73.2 2.8 271
17 Siskin 26.2 13.3 109
10 Junco 13 Egret 10.6 .3 98
17 Siskin -25.6 -10.3 255
11 Quial 1 Owl -77.0 -8.7 285
2 Swift -88.7 -22.3 336
5 Jay 90.7 15.9 338
12 Heron 2 Swift -80.5 -13.0 297
3 Parrot -27.3 -17.3 118
8 Robin 67.7 15.3 253
13 Egret 10 Junco -10.5 -.3 98
16 Crow -19.5 -9.7 204
14 Gull 1 Owl -5.9 -2.8 23
2 Swift -29.1 -7.2 108
15 Crow 3 Parrot -86.1 -29.5 337
7 Wren 56.0 17.6 217
16 Crow 20.1 11.9 86
16 Crow 13 Egret 20.1 11.1 202
15 Crow -20.1 -11.1 202
17 Siskin 9 Siskin -26.2 -12.1 254
10 Junco 26.2 12.1 254
Table III: Generator Real and Reactive Power Outputs
Generator Name
Real
Power
Output
(MW)
Reactive
Power Output
(MVAR)
1 Owl 195.0274 34.9193
2 Swift 200 42.4533
3 Parrot 200 73.6848
8 | P a g e
Table IV: Voltage Ratings Violation for Base Case on Line 5-11
Bus Number Bus name Bus Voltage Min Voltage Allowed Difference
Current
Violation
10 Junco 0.9036 0.96 0.054 No
13 Egret 0.8955 0.96 0.0645 No
16 Crow 0.9532 0.96 0.0068 No
17 Siskin 0.9528 0.96 0.0071 No
Under normal operations, the voltage stayed between 0.96 and 1.0 per unit. Under emergency,
the voltage was allowed to range from 0.90 to 1.05 per unit. The reactive generation capacity
was 490 MW, and the reactive generation capacity is from -100 MVAR to 250 MVAR. We
almost evenly distribute 1/3 of real power to each generator. P2 and P3 were set to 200 MW in
the baseline system.
From the results, we observed that the entire voltage amount stayed within the limits. Except bus
13, all other bus angles were below 10 degrees. The loss in the system was (200 + 200 + 194.3
585 =) 9.3 MW. The efficiency of the system was 98.4%. With regards to the current, the
currents were all below 50% of the rating. The system state could be considered to be close to
perfect.
Contingency Analysis of Base Case
We evaluated our system based on NERC criteria. Performance A is essentially our normal
operations, which was discussed above. Performance B is basically the N-1 contingency
analysis. We considered generator outage, transmission line outages, and transformer outages.
When we simulated generator outages, we almost evenly distribute the generation from the
outage generator to other generators in service.
Among all the contingencies, the only violation that was observed was under Line 2-14. When
Line 2-14 was taken off from the system, we could see the bus 14’s voltage would drop from
0.9926 to 0.8651 p.u. Generally, although the systems were under contingency simulation, the
system voltage was not dropped a lot. Most voltages were higher than 0.95 p.u. The currents
were within the rating. Moreover, it was counterintuitive to see that transmission line outages
would better off the system’s efficiencies. Because when we removed a line, we could avoid the
power loss in the removed one as well. The loads at 69 kV buses were rural loads and small,
thus transformer contingencies would not affect the whole system much as long as there was
one transformer to connect to generator to the load.
9 | P a g e
Table V: Generator Outage Data for Base Case
Generator Outage Name Bus Number
Bus
Name Bus Voltage Difference
Current
Violation
1 Owl 13 Egret 0.8936 0.0033 No
2 Swift
10
13
Junco
Egret
0.8946
0.8863
0.0054
0.0137
No
3 Parrot
10
13
Junco
Egret
0.8656
0.8512
0.0244
0.0488
No
Table VI: Full Contingency Assessment for Base Case
From Bus
number
From bus
name
To bus
number
To bus
name
Voltage
Violation
Current
Violation
1 Owl 9 Siskin
Egret (0.8658)
Junko (0.8669) No
1 Owl 11 Quail
Junco(0.8968)
Egret (0.8893) No
1 Owl 14 Gull Egret (0.8955) No
2 Swift 11 Quail
Junco(0.8987)
Egret (0.8902) No
2 Swift 12 Heron Egret (0.8922) No
2 Swift 14 Gull
Egret (0.8958)
Gull (0.8656) No
3 Parrot 6 Raven
Junco (0.8947)
Egret (0.8860) No
3 Parrot 12 Heron Junco(0.8911) No
3 Parrot 15 Crow
Egret (0.8680)
Junko (0.8821) No
4 Lark 5 Jay Egret(0.8942) No
4 Lark 9 Siskin Egret(0.8956) No
5 Jay 6 Raven Egret(0.8932) No
5 Jay 7 Wren
Junco (0.8988)
No
5 Jay 8 Robin
Junco (0.8986) No
5 Jay 11 Quail
Junco (0.8855) No
7 Wren 15 Crow None No
10 | P a g e
8 Robin 12 Heron
Egret (0.8895)
Junco (0.8979) No
10 Junco 13 Egret
Egret (0.8712)
No
10 Junco 17 Eury
Junco (0.6822)
Egret (0.7679) No
13 Egret 16 Yanyi
Junco (0.7809)
Egret (0.7211) No
Cost of Resolving Base Case Issues
We added fixed shunt at bus 14 to resolve the problem. However, under normal conditions, the
fixed shunt would cause excessive voltage. If we added a fixed shunt at bus 14 to avoid voltage
drop under contingency, we needed to add breaker to the shunt as well. The fixed shunt would
not be applied unless contingency happens.
Adding 4 Capacitor banks at the buses 4, 11, 13 and 16 resolved all these voltage violations and
satisfied the NERC criteria, and the capacities were 15, 15, 15 and 5 MVAR respectively.
We added 4 capacitor banks at the cost = 3000*50 = $0.150 million
Installation and associated equipment cost = 4*$60,000 = $0.240 million
Total cost = $0.39 million
11 | P a g e
Section 2 Modified Power System for New Needs Figure 1 is the new power system network. We have additional load at additional bus 18. Two
new transmission lines connect bus 18 with bus 14 and bus 2. Although Line 2-18 is enough to
serve the steel mill under normal conditions, but considering the contingency of Line 2-18, it
would not serve the steel mill, therefore, we invested in two new lines connecting the steel mill.
In the new system, we also assumed that all the loads were increased by 30% without changing
the power factors. Similar to before, we almost evenly distributed the generation to 3 generators.
P2 and P3 were 270 MW.
Under normal conditions (after modification), the maximal current was from Line 4-9, 52% of
the rating. The voltages now were certainly with assigned ranges. However, the voltage angles
were not as small as the baseline case. Buses 10 and 13’s angles were around 14 degrees and 16
degrees respectively. The systems current efficiency was (585*1.3+40)/(270*2+278) = 97.8 %.
The efficiency decreased by 0.7 % compared to baseline system. This was due to additional
losses in the new line.
Table VIII: Normal Operating Conditions Voltage Ratings Violation
Bus
Number
Bus name Bus
Voltage
Min
Voltage
Allowed
Difference Current
Violation
4 Lark 0.9461 0.96 0.0139 No
5 Jay 0.9479 0.96 0.0121 No
6 Raven 0.9537 0.96 0.0063 No
7 Wren 0.9455 0.96 0.0145 No
8 'ROBIN' 0.9559 0.96 0.0041 No
9 'SISKIN' 0.9568 0.96 0.0032 No
10 'JUNKO' 0.8623 0.96 0.0977 No
13 'EGRET' 0.8515 0.96 0.1085 No
15 GROW 0.9561 0.96 0.0039 No
12 | P a g e
Contingency Analysis of Modified Power System
When generator 1 or 3 was under outage, we could not simply assign half loads to the other 2
generators, because the currents would violate the rating. Thus, when generator 1 was under
outage, we re-dispatched the generation to be 373.53A and 450A for generators 1 and 3
respectively. When generator 3 was under outage, we re-dispatched the generation to be
347.5815A and 485A for generators 2 and 3 respectively. The line currents would come below
the rating limits again. However, we needed to add some costs of the re-dispatch since the local
marginal prices varied across locations.
Table IX: Generator Outage
Generator Outage Name Bus Number
Bus
Name Bus Voltage Difference
Current
Violation
1 Owl
10
13
Junko
Egret
0.8360
0.8288
0.0640
0.0712
No
2 Swift
10
13
Junco
Egret
0.8486
0.8366
0.0514
0.0634
No
3 Parrot
3
4
5
6
7
8
10
13
15
16
17
Parrot
Lark
Jay
Raven
Wren
Robin
Junko
Egret
Grow
Yanyi
Eury
0.8926
0.8922
0.8871
0.8781
0.8765
0.8975
0.7979
0.7776
0.8768
0.8539
0.8854
0.0674
0.0678
0.0729
0.0819
0.0835
0.0625
0.1621
0.1824
0.0832
0.1061
0.0746
No
Table X: Full Contingency Assessment of the New Design
From Bus
number
From bus
name
To bus
number
To bus
name Voltage Violation
Current
Violation
1 Owl 9 Siskin
Egret (0.8278)
Junco(0.8373) No
1 Owl 11 Quail
Egret (0.8514)
Junco(0.8623) No
1 Owl 14 Gull
Egret (0.8461)
Junco(0.8567) No
2 Swift 11 Quail
Egret (0.8434)
Junco(0.8550) No
13 | P a g e
2 Swift 12 Heron
Egret (0.8461)
Junco (0.8567) No
2 Swift 14 Gull
Egret (0.8493)
Junco(0.8605) No
2 Swift 18 Steel Mill
Egret(0.8086)
Junco(0.8280)
Yanyi (.8818) No
3 Parrot 6 Raven
Egret (0.8492)
Junco (0.8589) No
3 Parrot 12 Heron
Egret(0.8493)
Junco(0.8638) No
3 Parrot 15 Crow
Egret (0.8453)
Junko (0.8610) No
4 Lark 5 Jay
Egret(0.8414)
Junco(0.8540) No
4 Lark 9 Siskin
Egret(0.8413)
Junco(0.8539) No
5 Jay 6 Raven
Egret(0.8213)
Junco(0.8322) No
5 Jay 7 Wren
Egret (0.8534)
Junco (0.8539)
Jay (.8977)
Wren (.8869) No
5 Jay 8 Robin
Egret (0.8578)
Junco (0.8606)
Wren (.8992) No
5 Jay 11 Quail
Egret (0.7998)
Junco (0.8785) No
7 Wren 15 Crow
Junco (0.8702)
Egret(0.8655) No
8 Robin 12 Heron
Junco (0.8533)
Egret(0.8419) No
10 Junco 13 Egret
Junco (0.8864)
Egret(0.8115) No
10 Junco 17 Eury
Junco( 0.4892)
Egret (0.5569)
Yanyi (0.8340 ) No)
13 Egret 16 Yanyi
Junco (0.6238)
Egret ( 0.5267 )
Eury ( 0.8337 ) No
14 Gull 18 Steel Mill
Junco(0.8622 )
Egret(0.8514 ) No
14 | P a g e
Cost of the New System
Transmission Line 2-18: 161kV, line length 16.00 miles
Transmission Line 14-18: 161kV, line length 18.00 miles
Line breaker cost is $95,000 for one.
Cost per miles: 0.106 million $ / mile
Conductor: Dove
Fixed shunt: total shunt: 25+20+25+17=87 MVAR
Transmission Line 2-18: 161kV 34*0.106= 3.6040 million $
Transmission Line 14-18: 161kV
Line Breaker cost 0.38 million $
Fixed shunts at buses 4*0.06+0.003*87= 0.501 million $
Site cost 0.3 million $
Total Cost 4.785 million $
Validation of Minimal Cost
Process on searching the optimal investment decisions:
i) In order to serve the steel mill, we had to connect the steel mill to the system, but the
system had to be valid under contingency, hence we had to add at least two lines. Since
the cost was in positive correlation to the distance, we preferred a shorter line. Thus,
Line 2-18 and Line 14-18 were the best choice. Since bus 2 and 14 were both 161kV,
bus 18 was assigned to be 161kV as well, as otherwise we would have to pay additional
transformer cost.
ii) As for the transmission line conductor, the contingency analysis results told us that Dove
was enough to serve the system, which was the cheapest type at a 161 kV level.
iii) Under contingency analysis, voltage violation was our only concern, because there was
no current violation. The cheapest way we could choose to resolve voltage violation was
by adding fixed shunt capacitors. We recorded buses that violated the voltage limit.
Adding one shunt would cause voltage change on other buses as well. After
experimenting, we picked buses 4, 10, 13, and 16 and added 25, 20, 25 and 15 MVAR
fixed shunts.
Conclusion
We designed a new system to meet with load growth and new needs from a steel mill. After full
contingency analysis of the new system, we found solutions to help the system to meet the
NERC reliability standards by adding fixed shunts. Our solution was an approximate optimal
solution of cost minimization. The final system satisfied NERC performance A and B criteria.
15 | P a g e
References
[1] North American Electric Reliability Corporation Standard TPL-001-0.1 – System
Performance under Normal Conditions