Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
http://www.iaeme.com/IJCIET/index.
International Journal of Civil Engineering and Technology (IJCIET)Volume 9, Issue 13, December 2018, pp.
Available online at http://www.iaeme.com/ijciet/issues.asp?JType=IJCIET&VType=9&IType=13
ISSN Print: 0976-6308 and ISSN Online: 0976
©IAEME Publication
EFFECTIVE CONSTRUCTI
DESIGN-BUILD VS. DESIGN
METHODS; 5-
DRAWINGS-CALENDAR
Construction Management Program, Department of Engineering Management,
College of Eng., Prince Sultan University, Riyadh, Saudi Arabia
Department of
Royal U
ABSTRACT
Design and construction are measured as
project, which fundamentally starts with the engineering design and closes with
construction. The achievement of the complete set is subject to how
project achieved its main objectives: highest quality, least
These objectives are significantly affected by the connection’s strength amongst the
two stages of the set: design and construction. It’s monitored that most of
difficulties facing the proper implementation of those objectives
weak connection between the two main stages of the project. Since then, this research
paper decided to investigate the main influences assoc
between both stages through applying the lean construction concepts.
seeks the feasible actions that could support this relationship as an approach to
enhance the project objectives, which are definitively dedicated to the building
construction product at the end results. Focusing more, this research compare
evaluates two selected key factors that believed to affect the connection of both design
and construction stages: The Design
methods/contracts. For more concentration, an appraisal is applied throughout a
selected group of (5) principal factors: design time, construction drawings,
construction calendar, communication channels, and change orders. This is
considered as a partial study, which could be expanded later throughout more factors.
Finally, results and concl
on the performed statistical analysis.
IJCIET/index.asp 918 [email protected]
International Journal of Civil Engineering and Technology (IJCIET) 2018, pp.918–931, Article ID: IJCIET_09_13_092
http://www.iaeme.com/ijciet/issues.asp?JType=IJCIET&VType=9&IType=13
6308 and ISSN Online: 0976-6316
Scopus Indexed
EFFECTIVE CONSTRUCTION UTILIZING
BUILD VS. DESIGN-BID-BUILD
-FEATURE APPRAISAL (T
CALENDAR-COMMUNICATION
CHANGES)
Ihab M. Katar
Construction Management Program, Department of Engineering Management,
College of Eng., Prince Sultan University, Riyadh, Saudi Arabia
Dina R. Howeidy
Department of Interior Design, College of Art & Design,
Royal University for Women, Bahrain
Design and construction are measured as the main stages of the construction
project, which fundamentally starts with the engineering design and closes with
construction. The achievement of the complete set is subject to how
project achieved its main objectives: highest quality, least cost, and
These objectives are significantly affected by the connection’s strength amongst the
two stages of the set: design and construction. It’s monitored that most of
difficulties facing the proper implementation of those objectives are related to the
weak connection between the two main stages of the project. Since then, this research
paper decided to investigate the main influences associated with
between both stages through applying the lean construction concepts.
seeks the feasible actions that could support this relationship as an approach to
enhance the project objectives, which are definitively dedicated to the building
construction product at the end results. Focusing more, this research compare
evaluates two selected key factors that believed to affect the connection of both design
and construction stages: The Design-Build (DB) and the Design-Bid
methods/contracts. For more concentration, an appraisal is applied throughout a
d group of (5) principal factors: design time, construction drawings,
construction calendar, communication channels, and change orders. This is
considered as a partial study, which could be expanded later throughout more factors.
Finally, results and conclusion are presented to propose the recommendation based
on the performed statistical analysis.
92
http://www.iaeme.com/ijciet/issues.asp?JType=IJCIET&VType=9&IType=13
ON UTILIZING
BUILD
FEATURE APPRAISAL (TIME-
COMMUNICATION-
Construction Management Program, Department of Engineering Management,
College of Eng., Prince Sultan University, Riyadh, Saudi Arabia
Art & Design,
main stages of the construction
project, which fundamentally starts with the engineering design and closes with
construction. The achievement of the complete set is subject to how to further the
cost, and the least time.
These objectives are significantly affected by the connection’s strength amongst the
two stages of the set: design and construction. It’s monitored that most of the
are related to the
weak connection between the two main stages of the project. Since then, this research
the correlation
between both stages through applying the lean construction concepts. Furthermore, it
seeks the feasible actions that could support this relationship as an approach to
enhance the project objectives, which are definitively dedicated to the building
construction product at the end results. Focusing more, this research compares
evaluates two selected key factors that believed to affect the connection of both design
Bid-Build (DBB)
methods/contracts. For more concentration, an appraisal is applied throughout a
d group of (5) principal factors: design time, construction drawings,
construction calendar, communication channels, and change orders. This is
considered as a partial study, which could be expanded later throughout more factors.
usion are presented to propose the recommendation based
Ihab M. Katar and Dina R. Howeidy
http://www.iaeme.com/IJCIET/index.asp 919 [email protected]
Keywords: Lean construction - Project design - construction project-design
objectives-Design-Build (DB) -Design-Bid-Build (DBB).
Cite this Article: Ihab M. Katar and Dina R. Howeidy, Effective Construction
Utilizing Design-Build Vs. Design-Bid-Build Methods; 5-Feature Appraisal (Time-
Drawings-Calendar-Communication-Changes), International Journal of Civil
Engineering and Technology (IJCIET) 9(13), 2018, pp. 918–931.
http://www.iaeme.com/ijciet/issues.asp?JType=IJCIET&VType=9&IType=13
1. INTRODUCTION
For discussing the possible factors that might affect the connection between the two stages of
a construction project, it worth having more information concerning both Design and
Construction. The information will help in enhancing the destined connection, which would
be returned to the objectives of construction project. In this regard, the study will highlight
both stages independently, and then show the main factors that affect the connection strength
amongst them, which are the DB and the DBB methods/contracts.
1.1. Design Process
In the design process, three “roles” are played as the design discloses: There is a client, who is
a person or group or firm that desires design concepts; There is also a user to operate or utilize
what is designed; and there is a designer whose job is to solve the client’s problem (set the
design) in a way that meets the user’s requirements [1].
The designs are almost physical objects. Also, e-versions such as drawings, computer
software, or their “paper” products, plans, articles, and books are objects in this logic. Here,
it’s crucial to highlight the importance of owning the needed knowledge prior starting a new
design throughout searching and reading; “reading is not only crucial for a person's self-
cultivation, but also an important way for people to mould themselves, perfect their
characters, elevate their minds, and gain wisdom” [2]. Reaching a proper design approach by
thorough readings and researches within the first steps of its complete process, leads to
accomplish the economic aspect in this important stage; many construction cost and project
management practices already use ‘target costing’ terminology or repeat target value design
(TVD) in some part of the process[3].
1.2. Construction
Go into the field where you can see the machines and methods at work that make the modern
buildings, or stay in construction direct and simple until you can work naturally into building-
design from the nature of construction [4].
The architect should have construction at least as much at his fingers’ ends as a thinker his
grammar [5].
There is an underlying assertion that improving construction performance need not be the
outcome of primarily pursuing procurement solutions [6].
For any but the smallest buildings, the next step for the owner of the prospective building
is to engage, either directly or through a hired construction manager, the services of building
design professionals. Here, the owner should recognize that being competent is not the same
as being strong in relation to the competition [7], [8], and [9].
Although a building begins as a concept, it is built in a world of material actualities. The
building designers, architects and engineers work constantly from an awareness of what is
possible and what isn’t. They are able to employ an apparently limitless list of building
materials and a number of structural systems to produce a building of any desired form and
Effective Construction Utilizing Design-Build Vs. Design-Bid-Build Methods; 5-Feature Appraisal
(Time-Drawings-Calendar-Communication-Changes)
http://www.iaeme.com/IJCIET/index.asp 920 [email protected]
texture; Leading to wide-use of new construction materials that fix current concerns about the
conventional ones [10], in this stage, designers should consider specifying such kinds of
materials.
However, this research is concerned primarily with the options of construction; what
process will be followed in terms of contracting sequence, demonstrating the effects of each
on the design objectives. These should be studied, however, with reference to many other
factors that bear on design of buildings, some of which require explanation here.
1.3. Lean Construction
Lean management system success is largely and directly attributed to their sole approach of
cutting waste and added value [11]. Lean Construction’s (LC) growing popularity is even
acknowledged by those who question the applicability of lean to the construction sector [12].
Green also draws our attention to his critical definition of LC as a “complex cocktail of ideas”
[13]. Moreover, most construction managers agree that the industry is susceptible to multiple
wastes, overruns, delays, errors, and inefficiency. As a result, construction projects seldom
finish on time, within budget, and at a quality level accepted by the customer [14]. Thus,
several project management approaches have emerged to improve construction performance
including lean construction, lean project management, and value-engineering [15].
Recent years have seen a growing international academic interest in lean construction
[16], [17], and [18]. On the other hand, some other researches gave alerts when dealing with
this concept; “Rather than providing a step forward to the future, the concept of lean
construction may well provide a step backwards to the past [19]. However, the majority
confirmed that it is a combination of operational research and practical development in design
and construction with an adaption of its principles and practices to the end-to-end design and
construction process. Dissimilar to manufacturing, construction is a project-based production
process. Lean construction – a term by the International Group for Lean Construction in 1993
[20], was highlighted recently few years back. This refers to the application of lean
production principles and practices in design-construction processes to maximize value and to
reduce waste [16], [17], [21], and [22]. Lean is valued for its ability to identify waste [23] and
[24]. Together, Lean and Green have the ability to identify waste and evaluate its
environmental impact, but they often do not provide an actual method to reduce waste [25].
Also, the benefits in a certain study were identified, analysed and the outcomes suggest that
there is a direct linkage between sustainability and lean Construction [26]. Many papers
before, were working on extending the simulation approaches by employing the lean
construction concepts, such as IKEA model, and others [27]. In Europe, the idea of improving
value is leading to an exploration of how Lean construction might deliver some improvement
at least within the European Construction Institute (ECI) and its members [28]. Last but not
least, Lean principles in general and lean construction in particular are approaches developed
to improve the productivity of the construction industry and its projects [29]. This approach
tries to manage and improve construction processes with minimum cost and maximum value
by considering the client’s needs.
1.4. Construction Methods
This research figures out the main possible factors that might contribute significantly to the
relationship of both stages: design and construction. It aims to enhance their connection to
become stronger, which will be reflected to the project and design objectives.
Aiming more concentration, the study chose different contracts/methods used worldwide
in implementing the construction projects: DBB, DB, and others. Following, are the main
Ihab M. Katar and Dina R. Howeidy
http://www.iaeme.com/IJCIET/index.asp 921 [email protected]
ideas of these methods, which should be subject to the appraisal, in order to gain the needed
results that will recommend the best.
1.5. Construction Project Delivery Methods
Construction projects have different delivery methods in terms of contractual arrangements.
It’s important to investigate how companies in the construction sector deal with the
phenomenon of ‘quality’ and develop quality management approaches [30], as quality is a
core management factor while dealing with the project delivery method.
1.5.1. DBB Method/Contract
In typical DBB project structure (Figure 2), the owner hires first a team of architects and
engineers to offer design services, which lead to develop drawings and technical
specifications referred to construction documents that describe the facility to be built.
Afterwards, construction firms are invited to bid on the project. Each bidding firm reviews
the construction documents and then proposes a cost to construct this project. The owner then
evaluates the submitted offers and awards the construction contract to the bidder believed
most suitable. This selection may be based on bid price only, or sometimes other factors
related to bidders’ qualifications may also be considered. Next, the construction documents
become a part of the construction contract, and the selected firm proceeds with the work. On
all except small projects, the winner firm acts as the GC, coordinating and managing the
overall construction process. However, it may be relying on smaller, more specialized
subcontractors to perform significant parts or even all of the construction work. During
construction, the design team keeps on providing services to the owner, serving to ensure that
the project is adhering to the requirements of the documents, as well as answering queries
related to the design, payments to the contractor, changes to the work, and similar issues.
Amongst the advantages of DBB, project structure is easy-to-understanding, well-
established legal practices, and easy to be managed. The direct relationship between the
owner and the design team ensures that the owner preserves control over the design and
delivers a healthy set of checks and balances during the construction process. Moreover, with
design work completed prior the project is bid, owner starts construction with a fixed cost and
a high degree of confidence regarding the final cost of the project.
Finally, in DBB project structure, the owner contracts with two entities, in which both
design and construction responsibilities remain divided among them during the project.
1.5.2. DB Method/Contract
In DB project structure, one entity ultimately undertakes responsibility for both design and
construction (Figure-2). A DB project initiates with the owner developing a conceptual design
that describes the functional or performance requirements of the proposed project but doesn’t
detail its form or how it would be constructed. Following, using this conceptual information, a
DB firm is selected to complete all remaining parts of the project including different project
activities like planning and scheduling. Also, it is obvious that the activities at site is
influenced at a higher order by the planning and scheduling of activities in order to achieve
smooth workflow throughout the project[31].
Selection of the DB may be based on a competitive bid process similar to that described
above for DBB projects, on negotiation and evaluation of a firm’s qualifications for the
projected work, or on some combination of both. DB companies themselves can take a variety
of forms: a single firm incorporating both design and construction expertise, a joint venture
(JV) between two firms, one is specialized in construction and the other in design, or a
Effective Construction Utilizing Design-Build Vs. Design-Bid-Build Methods; 5-Feature Appraisal
(Time-Drawings-Calendar-Communication-Changes)
http://www.iaeme.com/IJCIET/index.asp 922 [email protected]
construction management firm that subcontracts with a separate design firm to provide those
services.
Regardless of the internal structure of the DB firm, the owner contracts with a single
entity through the rest of the project, which shoulders responsibility for all remaining design
and construction services. DB project structure offers the owner a single source of
accountability for all aspects of the project. It also places the designers and constructors in a
collaborative correlation, introducing construction know-how into the design phases of a
project and allowing the earliest possible consideration of constructability, cost control,
scheduling, and similar issues. This structured method also accommodates fast-track
construction, a scheduling technique for reducing construction time. Managing an increasing
complexity of construction delivery requires a myriad of collective activities of a group of
people than individual could accomplish separately [32]. In the same line, project delivery
followed a design-and-build (D&B) approach, with a guaranteed maximum price (GMP) and
fixed dates for the handover of the building to the tenants, and here, a penalty could be agreed
between the investor and the main contractor in case of missing the due dates [33].
Figure 2.DBB vs. DB Construction Structures [34].
1.5.3. Different Methods/Contracts
There is a possibility for other delivery methods: the owner may sign separate contracts with a
design team and a construction manager. As in DB construction, the construction manager
contributes to the project earlier to the start of construction, conducting construction
knowledge during the design stage. Construction management project delivery could take
several forms and is frequently associated with especially sizeable or complex projects
(Figure-3).
In turnkey construction, an owner contracts with a single entity that provides financing for
the project and not only design and construction services. In other practices, design and
construction could be undertaken by a single-purpose entity, in which the owner, architect,
and contractor are all joint members. Moreover, other project delivery methods could also be
combined; permitting several possible organizational schemes offering design and
construction services that suit a diversity of owner desires and project conditions.
Figure 3. Construction management project delivery forms [34].
Ihab M. Katar and Dina R. Howeidy
http://www.iaeme.com/IJCIET/index.asp 923 [email protected]
Regardless variances in these production environments, construction industry is watching
lessons learned in factory production for approaches to enhance the quality and efficiency of
its own processes. These concepts and alike are called lean construction methods (as
mentioned earlier in this research), that attempt to:
• Remove any wasteful activities
• Structure the procedures of production and the supply chain of materials and products in order
to achieve the fastest and most reliable workflow
• Decentralize the information and decision making in to pass the control of construction
processes to the hands of those most familiar with the work and most capable of refining it
Present estimates of labour inefficiency in building construction run as high as 35 - 40%,
and estimates of materials waste are 20% or so [35]. Also, it’s found that job rotation, job
enrichment, planning cultural activities for the employees and the labours can enhance the
efficiency [36].
The challenge of lean construction is to reorganize the way in which construction
materials and components of the building are manufactured, delivered, and assembled in a
way to reduce these inefficiencies and expand the quality of the delivered product.
2. RESEARCH PROBLEM
Repeated problems are taking place when the awarded consultant of supervision starts their
tasks. Most of the time, this consultant is referring any weaknesses in the project to the
consultant of design. It’s a common practice that may occur between any entities of the same
area of specialization. This attitude is resulting in misleading to the project objectives due to
the weakness in performance of the supervision consultant, which is most probably justified
by having incomplete or faulty outputs from the design consultant. Moreover, several factors
need to be revisited within the project cycle, as they influence its main objectives that touch
all of the construction time, cost, and quality. For more concentration, part of these factors is
discussed in this study by measuring their impact on the given objectives. The chosen factors
are: design time, construction drawings, construction calendar, communication channels, and
change orders.
3. OBJECTIVE
Figure out the best construction delivery method by applying the concepts of lean
construction, which is believed to improve the project’s main objectives.
4. HYPOTHESES
Collecting both project delivery stages: design and construction, in one place under the
responsibility of a singular entity (DB) will contribute to accomplish the concepts of lean
construction, and thus, the main construction project objectives will be achieved properly as
planned. This approach is also ideal for solving most of the project delivery issues that used to
take place by distributing the tasks of design and construction among different entities
considering the weak communications.
5. RESEARCH APPROACH
While stages, design and construction are the main contractual components of a construction
project, and are also sequential, so it’s wise to have a strong connection amongst them. By
experience, and due to contractual reasons, a kind of weakness shows up due to the lack of
coordination between both stages. The source of this weakness is believed to be caused by
first: the two consultants (of design and supervision) that are not working for the same entity.
Effective Construction Utilizing Design-Build Vs. Design-Bid-Build Methods; 5-Feature Appraisal
(Time-Drawings-Calendar-Communication-Changes)
http://www.iaeme.com/IJCIET/index.asp 924 [email protected]
Second: the collaborative work between the engineer (design consultant) and constructor
(contractor) is somehow weak as they are also working for separate entities and places. Third:
the coordination between the engineer (supervision consultant) and the constructor
(contractor) carries some negative signs even if they are working in the same place, as each of
them has an individual contract with the owner, which make the consultant, by role nature,
working “against” the contractor to get the owner’s confidence.
The approach depends on measuring the difference between two cases:
• The consultant of design and the consultant of supervision are different, and both are not
belonging to the contractor entity (the common practice) represented in the DBB contract
type.
• The consultant of design and of supervision and the contractor are all represented in one entity
(less likely practice) represented in the DB contract type.
Since the second case above is not the common practice, the research will show and
measure the positive/negative reflections of using it to the project objectives throughout an
appraisal of certain features’ group.
Furthermore, the quality management approaches has been previously shown[30] to
provide rich data relating to the views and actions of stakeholders involved in a real ‘live’
project in respect of Lean [37]. Case-based research is also appropriate where there is little
prior empirical evidence about a phenomenon [38]. The study here followed the approach in
which participant observations, archival records, which provided information on performance,
and semi structured interviews, were used to obtain qualitative data [39] and [40]. Therefore,
an investigation will be the action that suits this case, and to make it applicable, the study
sample was selected carefully from the same area: construction project main players (owners,
consultants of design/construction, and contractors). It will state the impact of including both
stages in one entity: design and construction (DB method/contract), then compare its results
with the other method: separate design and construction stages with different consultants of
design and supervision (DBB method/contract).
To apply the approach’s concept above, a group of (5) features was selected carefully to
measure the differences between both methods/contracts. The following design of question
structure was distributed to the population chosen (mentioned below) to collect their
feedbacks:
“For each of the following features, score both of project construction contracts (1-5). The
scoring is based on thorough investigations for each type of contracts, and therefore, each
feature scores should be supported by accepted information through a clear argument. As a
result, after filling the table, there should be arguments for each feature.
1. Design time (less)
2. Construction drawings (simplicity)
3. Construction calendar (less)
4. Communication channels (less)
5. Change orders (less)
Score scale : 1 is the lowest and 5 is the highest”
The last questions were organized and tabulated for the purpose of collecting back the
average scores (Table-1).
Ihab M. Katar and Dina R. Howeidy
http://www.iaeme.com/IJCIET/index.asp 925 [email protected]
Table 1. the attached table within the survey distributed among the population Data Collection.
Name: No.:
S Features
(more score for description between parentheses)
Construction Contract
Design-Build Design-Bid-
Build
1 Design time (less)
2 Construction drawings (simplicity)
3 Construction calendar (less)
4 Communication channels (less)
5 Change orders (less)
Total Scores
Rank
Through unstructured interviews with design and construction players: owners,
consultants (of design and supervision), and contractors, the data were collected by filling the
given forms (appendix-1). They were asked to give their feedbacks regarding the (5) chosen
factors among the two delivery methods: DB & DBB. The interviewees were asked to
elaborate about their scoring justifying them.
6. RESULTS AND DISCUSSION
The results obtained from the feedbacks of the interviewees (appendix-1) were as follows:
Feedbacks were collected, tabulated, and classified to give the needed statistics for
analysing the results. Table-2 below, shows the feedbacks for the DB contract, which overall
scored it 21.00 / 25.00 among the “five” features’ evaluations.
Table 2. Feedbacks collected for DB Contracts
Likewise, table-3 below, shows the feedbacks for the DBB contract, which overall scored
it 12.96 / 25.00 among the “five” features’ evaluations.
Table 3. Feedbacks collected for DBB Contracts
Design Time (less: DB = 4.38, DBB = 2.50), Figure-4
With reference to the time required for design stage, DB had the upper hand mainly as a result
of incorporating both design and construction in one entity. The existence of the design team
nearby the construction team had a great gain. There is no need to prepare the full-set of
design drawings, BOQs, and specifications as supposed to do in DBB. In this case, and while
the construction begins, any missed or ambiguous information could be gathered effortlessly
from the design team, because they are working together, which is considered a harsh mission
S. Features \ Feedbacks 1 2 3 4 5 6 7 8 9 10 11 12 13 Average Round
1 Design time (less) 4 4 5 4 5 4 5 4 4 4 4 5 5 4.384615 4.38
2 Construction drawings (simplicity) 5 3 1 4 2 5 4 2 4 4 3 2 4 3.307692 3.31
3 Construction calendar (less) 4 4 4 4 4 5 5 4 5 4 4 5 5 4.384615 4.38
4 Communication channels (less) 5 4 5 4.5 5 4 5 5 4 4.5 4.5 5 5 4.653846 4.65
5 Change orders (less) 5 3 5 4 5 5 4 4 4 4.5 4 4 4 4.269231 4.27
23 18 20 20.5 21 23 23 19 21 21 19.5 21 23 ######## 21.00Total Scores
S. Features \ Feedbacks 1 2 3 4 5 6 7 8 9 10 11 12 13 Average Round
1 Design time (less) 2 2 3 3 1 3 3 2 2 3 3.5 3 2 2.5 2.5
2 Construction drawings (simplicity) 4 4 5 3 4 4 3 5 3 3 2.5 4 3 3.653846 3.65
3 Construction calendar (less) 1 2 2 2.5 2 3 3 2 2 3.5 3.5 3 1 2.346154 2.35
4 Communication channels (less) 2 3 3 2.5 1 2 2 3 2 3 3 3 2 2.423077 2.42
5 Change orders (less) 1 2 2 2 1 3 3 2 1 3 3.5 2 1 2.038462 2.04
10 13 15 13 9 15 14 14 10 15.5 16 15 9 12.96154 12.96Total Scores
Effective Construction Utilizing Design-Build Vs. Design-Bid-Build Methods; 5-Feature Appraisal
(Time-Drawings-Calendar-Communication-Changes)
http://www.iaeme.com/IJCIET/index.asp 926 [email protected]
in DBB. On the other hand, in DBB the complete design documents should be completed
entirely and neatly prior proceeding to the construction stage. One more add; switching to the
construction stage desires an intermediate stage: bidding, which demands an extra time added
to the project schedule.
Figure 4. Design time of DB vs. DBB Charts
Construction Drawings (simplicity: DB = 3.31, DBB = 3.65), Figure-5
As mentioned in (1) above, the simplicity of the design drawings needed for construction
(part of the design documents), goes for DB. However, and as watched from the overall
scoring of this feature, the feedbacks went to DBB. By screening amongst the (13) evaluators,
it’s clear that most of them (8/13) scored DB over DBB, which is supports the logic. On the
contrary, a less number (5/13) scored DBB over DB, which contradicts the logic. It was an
essential action to contact (personally) those evaluators who went for DBB to have more
information about their feedbacks. All of the collected answers from this group underlined a
misunderstanding of this feature; they didn’t consider the word “simplicity” and thought that
they would score the amount and completeness of the drawings, so they scored the opposite
trend. However, the overall scoring didn’t award this feature a big difference towards DBB,
and there was also an option to rescore these feedbacks, but the research went for the current
scoring to achieve transparency, besides having a margin of mistakes. Finally, the trend was
clear in spite of these issues.
Figure 5.Construction Drawings of DB vs. DBB Charts
Construction Calendar (less: DB = 4.38, DBB = 2.35), Figure-6
It’s an interpretation of the time needed for construction stage. Like the time needed for
design, discussed in (1) above, almost the same sense goes for construction as it’s one of the
two stages of a project completion. The collaborative work of both stages; design and
construction in DB, is a witness of acquiring less time when estimating the construction
calendar. Evaluators’ scoring went also in this feature to award DB higher, which defends
also the appropriateness of depending on DBregarding this feature.
Ihab M. Katar and Dina R. Howeidy
http://www.iaeme.com/IJCIET/index.asp 927 [email protected]
Figure 6. Construction Calendar of DB vs. DBB Charts
Communication Channels (less: DB = 4.65, DBB = 2.42), Figure-7
Clear difference is evident between both contracts considering this feature. It doesn’t need a
detailed description to figure out the complexity of communication channels required in DBB
amongst both teams; design and construction, as they are located in different establishments.
Consequently, DB was scored higher according to the evaluators’ feedbacks.
Figure 7. Communication Channels of DB vs. DBB Charts
Change Orders (less: DB = 4.27, DBB = 2.04), Figure-8
Any modification could take place during the construction stage from the original design
documents (design, materials, quantities… etc.) requires a “change order” to become
applicable. In practice, projects usually have change orders in their records. The less quantity
of such changes reflects either the project studies’ neatness during the design stage including
the completeness and accuracy of design documents, or the strong connection between both
teams, design and construction. Since the first case is less likely to be accomplished due to
several causes, but the second one is a direct outcome of comprising both teams under one
entity. Hence, DB has the higher score in this feature.
Figure 8. Change Orders of DB vs. DBB Charts
Effective Construction Utilizing Design-Build Vs. Design-Bid-Build Methods; 5-Feature Appraisal
(Time-Drawings-Calendar-Communication-Changes)
http://www.iaeme.com/IJCIET/index.asp 928 [email protected]
With the same line of the hypothesis, DB got the higher scores amongst the population
feedbacks. It was a general result, even with regard to each evaluator, that the DB contract
was a clear and direct winner in this comparison; please refer to the above results in tables 2
& 3 (the total scores) against each evaluator, who were numbered 1-13 respectively, and
Figure-9 below.
Figure 9. Total Scores of DB vs. DBB Charts
Furthermore, in spite of the minor differences between items to be scored, but the average
went for the concept of integrating both design and construction in a singular entity DB
instead of separating them as followed in the DBB method/contract (Table-4).
Table 4. Average scores obtained from the collected population feedbacks
Name: Average No.: 1-13
S Features
(more score for description between parentheses)
Construction Contract
Design-Build Design-Bid-
Build
1 Design time (less) 4.38 2.50
2 Construction drawings (simplicity) 3.31 3.65
3 Construction calendar (less) 4.38 2.35
4 Communication channels (less) 4.65 2.42
5 Change orders (less) 4.27 2.04
Total Scores 21.00 12.96
Rank 1 2
7. CONCLUSION
Throughout the results and discussion, the research hypothesis was confirmed. The DB
method/contract works on enhancing the link strength among the project stages: design and
construction. In the same time, this method provides an ideal connection between both stages,
and also applies the concepts of lean construction to minimize the waste in all of time, cost,
and quality of the final product “the project”.
As mentioned earlier, the DB method/contract in the construction market is a witness of
escalating trend:” between 1980 and 2005 the share of private, non-residential construction
work performed as DB construction increased from about 5% of the total market to an
estimated 30 - 40%” [41]. This indicator supports the results of this research; in 2018, which
leads to the recommendation of expanding the use scale of DB in the same market.
Ihab M. Katar and Dina R. Howeidy
http://www.iaeme.com/IJCIET/index.asp 929 [email protected]
REFERENCES
[1] Edward CLD., Patrick L., Engineering Design: A Project-Based Introduction, Fourth
Edition, Wiley, 2013.
[2] Katar I. M. (2016). Reading Activity impact on the Engineering Management Learners’
Efficiency in Research Presentation, KICEM Journal of Construction Engineering and
Project Management, Online ISSN 2233-9582, Vol.6, No.3 / Sep 2016, p. 8-13.
[3] Daria Zimina , Glenn Ballard & Christine Pasquire (2012) Target value design: using
collaboration and a lean approach to reduce construction cost, Construction Management
and Economics, 30:5, 383-398, DOI: 10.1080/01446193.2012.676658.
[4] Frank Lloyd Write (1931), Architectural Forum, (Published monthly by National Trade
Journals, Inc. New York).
[5] Le Corbusier (1927), Towards a New Architecture, Dover Publication Inc., New York.
[6] Hedley Smyth (2004) Competencies for Improving Construction Performance: Theories
and Practice for Developing Capacity, International Journal of Construction Management,
4:1, 41-56, DOI: 10.1080/15623599.2004.10773050.
[7] Barney, J. B. and Hansen, M. (1995). “Trustworthiness as a Source of Competitive
Advantage”, Paper given at the Australian Graduate School of Management, University of
South Wales, Sydney.
[8] Hamel, G. and Prahalad, C.K. (1994). Competing for the future, Harvard Business Books,
Boston, MA.
[9] Smyth, H. J. (2000). Marketing and selling construction services, Blackwell Science,
Oxford.
[10] Katar I. M. (2017). Evaluate State-of-the-Art Carbon Fibers’ Composites (CFC) as
Finishing Materials in Building Construction, International Journal of Applied
Engineering Research, ISSN 0973-4562, Volume 12, Number 23, p. 13826-13833.
[11] Kamarudin S. K.; Nakanishi H. (2017). Lean Construction Management: a Toyota Way
for Organisational Learning and Participation. Malysian Construction Research Journal
(MCRJ), Special Issue eISSN 2590-4140, Vol. 1. No.1, p. 40-52.
[12] Green, S. D., Harty, C., Elmualim, A. A., Larsen, G. D., and Kao, C. C. (2008). On the
discourse of construction competitiveness. Building Research & Information, 36(5),
pp.426-435.
[13] Green, S. D. (2002). The human resource management implications of Lean construction:
Critical perspectives and conceptual chasms. Journal of Construction Research, 3(01),
pp.147-165.
[14] FMI/CMAA Sixth Annual Survey of Owners (2005). Available at:
http://www.cmaafoundation.org/files/surveys/2005-survey.pdf.
[15] Al-Aomar, Raid (2012) Analysis of lean construction practices at Abu Dhabi construction
industry. Lean Construction Journal 2012 pp 105-121.
[16] Alarcon, L. ed. (1997). Lean Construction. A.A. Balkema Publishers, Rotterdam, The
Netherlands. (Proc. first three annual conf. of the Int’l. Group for Lean Construction).
[17] Howell, G. and Ballard, G. (1998). Implementing lean construction: understanding and
action. Proceedings Sixth Annual Conference of the International Group for Lean
Construction. Guaruja, Sao Paulo, Brazil.
[18] Koskela, L. (1992) Application of the New Production Philosophy to Construction,
Technical Report No. 72, Center for Integrated Facility Engineering, Stanford University,
CA.
[19] S. D. GREEN (1999) The missing arguments of lean construction, Construction
Management & Economics, 17:2, 133-137, DOI: 10.1080/014461999371637.
Effective Construction Utilizing Design-Build Vs. Design-Bid-Build Methods; 5-Feature Appraisal
(Time-Drawings-Calendar-Communication-Changes)
http://www.iaeme.com/IJCIET/index.asp 930 [email protected]
[20] Gleeson, F. and Townend J. (2007). Lean construction in the corporate world of the U.K.
construction industry. University of Manchester, School of Mechanical, Aerospace, Civil
and Construction Engineering.
[21] Koskela, L. (1997). Lean production in construction. In L. Alarcon (Ed), Lean
Construction (pp. 1-9). Rotterdam: Balkema.
[22] Koskela, L. (2003). Is structural change the primary solution to the problems of
construction? Building Research & Information, 31(2), 89-96.
[23] Klotz L, Horman M, Bodenschatz M. 2007. A lean modeling protocol for evaluating green
project delivery. Lean Construction J. 3:1–18.
[24] Lapinski A, Horman M, Riley D. 2006. Lean processes for sustainable project delivery. J
Constr. Eng. Manage. 132:1083–1091.
[25] Abdulaziz Banawi& Melissa M. Bilec (2014) A framework to improve construction
processes: Integrating Lean, Green and Six Sigma, International Journal of Construction
Management, 14:1, 45-55, DOI: 10.1080/15623599.2013.875266.
[26] Saurav Dixit, Satya N Mandal, Anil Sawhney, Subhav Singh, Area of Linkage Between
Lean Construction and Sustainability in Indian Construction Industry. International
Journal of Civil Engineering and Technology, 8(8), 2017, pp. 623–636.
[27] Heng Li, H L Guo, Yan Li & Martin Skitmore (2012) From IKEA Model to the Lean
Construction Concept: A Solution to Implementation, International Journal of
Construction Management, 12:4, 47-63, DOI: 10.1080/15623599.2012.10773200.
[28] Christine Pasquire (2012) Positioning Lean within an exploration of engineering
construction, Construction Management and Economics, 30:8, 673-685, DOI:
10.1080/01446193.2012.689431.
[29] Andersen, Belay, Amdahl Seim (2012) Lean construction practices and its effects: A case
study at St Olav’s Integrated Hospital, Norway. Lean Construction Journal 2012 pp 122-
149.
[30] Delgado-Hernandez, D.J. and Aspinwall, E. (2008) Quality management case studies in
the UK construction industry. Total Quality Management, 19(9), 919–38.
[31] M.Indira and M. VenkataJyothsna An Approach to Effective Construction Management
Based on Lean Construction Techniques, International Journal of Civil Engineering and
Technology, 8(4), 2017, pp. 1954-1959.
[32] Tey, K. H.; Chai, C. S.; Olanrewaju, A. L.; Aminah, M. Y. (2018). Conceptualising 4Cs in
Construction Project Team Integration. Malysian Construction Research Journal (MCRJ),
ISSN No.: 1985-3807, Vol. 24. No.1, p. 83-96.
[33] David James Bryde& Ralf Schulmeister (2012) Applying Lean principles to a building
refurbishment project: experiences of key stakeholders, Construction Management and
Economics, 30:9, 777-794, DOI: 10.1080/01446193.2012.700405.
[34] Edward A., Joseph I., Fundamentals of Building Construction; Materials & Methods, Fifth
Edition, Wiley, 2013.
[35] RM Senthamarai; P Devadas M; D Gobinath, Concrete made from ceramic industry
waste: Durability properties, Construction and Building Materials, Volume 25, issue 5,
May 2011, p. 2413-2419.
[36] K. Shyam Chamberlin, SS. Asadi and D. Sai Chaitanya, Evaluation of Latest Trends and
Developments in Lean Construction in India: A Model Study. International Journal of
Civil Engineering and Technology, 8(10), 2017, pp. 461–471.
[37] McIvor, R., Humphreys, P., McKittrick, A. and Wall, T. (2009) Performance management
and the outsourcing process: lessons from a financial services organisation. International
Journal of Operations & Production Management, 29(10), 1025–48.
[38] Barrett, M. and Barrett, R. (2011) Exploring internal and external supply chain linkages:
evidence from the field. Journal of Operations Management, 29(5), 514–28.
Ihab M. Katar and Dina R. Howeidy
http://www.iaeme.com/IJCIET/index.asp 931 [email protected]
[39] Yin, R.K. (2003) Applications of Case Study Research, Sage, Thousand Oaks, CA.
[40] Yin, R.K. (2003) Case Study Research: Design and Methods, Sage, Thousand Oaks, CA.
[41] Perry John Forsythe (2007) A conceptual framework for studying customer satisfaction in
residential construction, Construction Management and Economics, 25:2, 171-182, DOI:
10.1080/01446190600771439.
APPENDIX-1: A Survey sample collected from the population feedbacks