Effectiveness of Early Application of Penetrating Sealants
DAN VRUNO, P.E.American Engineering Testing, Inc.
St. Paul, Minnesota
Independent Variables
Three independent variables will be considered at two levels:
1. Curing time
2. Type of sealer
3. Deicer exposure
St. Paul, Minnesota
Dependent Variables
The two dependent variables (that is, responses) are scaling, which will be determined by ASTM C672, “Standard Test Method for Scaling Resistance of Concrete Surfaces Exposed to Deicing Chemicals,” and chloride ion ingress, which will be determined by performing AASHTO T260, “Sampling and Testing for Chloride Ion Content in Concrete Procedure A, Acid-Soluble Chloride Ion Content.”
St. Paul, Minnesota
Independent Variables Studied in the Laboratory Phase
Factorial Points Curing Sealer Deicer Exposure
1 4 weeks 8% siloxane CaCl2
2 4 weeks 40 % silane CaCl2
3 4 weeks None None
4 4 weeks None CaCl2
5 2 weeks 8% siloxane CaCl2
6 2 weeks 40 % silane CaCl2
7 2 weeks None CaCl2
8 2 weeks None None
9 3 weeks 8% siloxane CaCl2
10 3 weeks 40 % silane CaCl2
St. Paul, Minnesota
23 Factorial Design
St. Paul, Minnesota
Independent Variables Studied in the Laboratory Phase
Factorial Points Curing Sealer Deicer Exposure
1 4 weeks 8% siloxane CaCl2
2 4 weeks 40 % silane CaCl2
3 4 weeks None None
4 4 weeks None CaCl2
5 2 weeks 8% siloxane CaCl2
6 2 weeks 40 % silane CaCl2
7 2 weeks None CaCl2
8 2 weeks None None
9 3 weeks 8% siloxane CaCl2
10 3 weeks 40 % silane CaCl2
St. Paul, Minnesota
23 Factorial Design
St. Paul, Minnesota
Field Study Layout
St. Paul, Minnesota
6 bag 42% sand 58% rock 6.2% air w/c .43
St. Paul, Minnesota
Day of Placement – 10/31/14
St. Paul, Minnesota
Finishing Tools
St. Paul, Minnesota
Ancillary Study
St. Paul, Minnesota
Date of Placement – 11/1/14
St. Paul, Minnesota
November 2, 2014
St. Paul, Minnesota
Two Week Sealer Addition
St. Paul, Minnesota
Three Week Sealer Addition
St. Paul, Minnesota
Four Week Sealer Addition
St. Paul, Minnesota
Ancillary Popout Study
St. Paul, Minnesota
No sealer
St. Paul, Minnesota
St. Paul, Minnesota
St. Paul, Minnesota
Independent Variables Studied in the Laboratory Phase
Factorial Points Curing Sealer Deicer Exposure
1 4 weeks 8% siloxane CaCl2
2 4 weeks 40 % silane CaCl2
3 4 weeks None None
4 4 weeks None CaCl2
5 2 weeks 8% siloxane CaCl2
6 2 weeks 40 % silane CaCl2
7 2 weeks None CaCl2
8 2 weeks None None
9 3 weeks 8% siloxane CaCl2
10 3 weeks 40 % silane CaCl2
St. Paul, Minnesota
Time of Curing
4 weeks- 3 weeks- 2 weeks-
9
6
5
2
1
3
8
7
4
10
St. Paul, Minnesota
Type of Sealer Placed
8% Siloxane- 40% Silane- None-
9
6
5
2
1
3
8
7
4
10
St. Paul, Minnesota
Deicer Exposure
CaCl₂- None-
10
4
7
8
3 9
6
5
2
1
St. Paul, Minnesota
Scaling Rating
Per ASTM C672/C672M
0 – no scaling
1 – very slight scaling (3 mm depth, no coarse aggregate visible)
2 – slight to moderate scaling
3 – moderate scaling (some coarse aggregate visible)
4 – moderate to severe scaling
5 – severe scaling (coarse aggregate visible over entire surface)
St. Paul, Minnesota
0 Rating
#1 4 weeks Siloxane Deicer#2 4 weeks Silane Deicer
St. Paul, Minnesota
1 Rating
#3 4 weeks No sealer No deicer#8 2 weeks No sealer No deicer
St. Paul, Minnesota
2 Rating
#5 2 weeks Siloxane Deicer#10 3 weeks Silane Deicer
St. Paul, Minnesota
3 Rating
#4 4 weeks No sealer Deicer#6 2 weeks Silane Deicer
St. Paul, Minnesota
4 Rating
#4 4 weeks No sealer Deicer#7 2 weeks No sealer Deicer
St. Paul, Minnesota
5 Rating
#7 2 weeks No sealer Deicer
St. Paul, Minnesota
0-5 Rating
St. Paul, Minnesota
Responses of the Laboratory Phase
St. Paul, Minnesota
Factorial Points Curing Sealer Deicer Exposure Scaling Rating
1 4 weeks 8% siloxane CaCl2 0
2 4 weeks 40 % silane CaCl2 0
3 4 weeks None None 1
4 4 weeks None CaCl2 3.5
5 2 weeks 8% siloxane CaCl2 2
6 2 weeks 40 % silane CaCl2 3
7 2 weeks None CaCl2 4.5
8 2 weeks None None 1
9 3 weeks 8% siloxane CaCl2 1.5
10 3 weeks 40 % silane CaCl2 2
Curing Time
2.6
1.75
1.1
0
0.5
1
1.5
2
2.5
3
2 Weeks 3 Weeks 4 Weeks
Scal
ing
Rat
ing
St. Paul, Minnesota
Type of Sealer
2.5
1.7
1.2
0
0.5
1
1.5
2
2.5
3
No Sealer 40% Silane 8% Siloxane
Scal
ing
Rat
ing
St. Paul, Minnesota
Deicer Exposure
1
2.1
0
0.5
1
1.5
2
2.5
No Deicer CaCl2
Scal
ing
Rat
ing
St. Paul, Minnesota
Daily High and Low Temperatures10/31/14 to 4/6/15
0
0.05
0.1
0.15
0.2
0.25
-20
-10
0
10
20
30
40
50
60
70
80
10/28/2014 11/17/2014 12/7/2014 12/27/2014 1/16/2015 2/5/2015 2/25/2015 3/17/2015 4/6/2015
Pre
cip
itat
ion
Tem
pe
ratu
re, °
F
Date
High Temp
Low Temp
Precipitation
St. Paul, Minnesota
Daily High and Low Temperatures10/31/13 to 4/6/14
0
0.05
0.1
0.15
0.2
0.25
-20
-10
0
10
20
30
40
50
60
70
80
10/28/2013 11/17/2013 12/7/2013 12/27/2013 1/16/2014 2/5/2014 2/25/2014 3/17/2014 4/6/2014
Pre
cip
itat
ion
Tem
pe
ratu
re, °
F
Date
high temp
low temp
precipitation
St. Paul, Minnesota
Daily High and Low Temperatures10/31/14 to 4/6/15
0
0.05
0.1
0.15
0.2
0.25
-20
-10
0
10
20
30
40
50
60
70
80
10/28/2014 11/17/2014 12/7/2014 12/27/2014 1/16/2015 2/5/2015 2/25/2015 3/17/2015 4/6/2015
Pre
cip
itat
ion
Tem
pe
ratu
re, °
F
Date
High Temp
Low Temp
Precipitation
St. Paul, Minnesota
Average Precipitation
0
0.1
0.2
0.3
0.4
0.5
0.6
0.7
0.8
0.9
Nov Dec Jan Feb Mar April
2013
2014
2015
St. Paul, Minnesota
Now….. for the happy customer….
St. Paul, Minnesota
3 Popouts
St. Paul, Minnesota
The Dick Stehly Rule of Scaling
St. Paul, Minnesota
QUESTIONS???
THANK YOU!St. Paul, Minnesota