EHV TRANShlISSION LINE DESIGN Oppurtunities of Cost Reduction

Embed Size (px)

Citation preview

  • 8/16/2019 EHV TRANShlISSION LINE DESIGN Oppurtunities of Cost Reduction

    1/8

    IEEETransactions

    on

    Power Delivery,

    Vol.

    5 N O . 2 April 1990

    EHV TRANShlISSION

    L I N E

    DESIGN

    OPPORTUNITIES FOR COST REDUCTION

    Richard

    E.

    Kennon, Senior Member

    Electric Power Research Institute

    Palo Alto, CA

    KEYWORDS

    EHV, Transmission, Line, Design, Economics, Optimization,

    Standardization, Conductor, Terrain

    ABSTRACT

    The design of transmission lines is often limited to

    a

    few

    standard conductors and structures in order to minimize the

    costs of engineering, construction, inventory, and speed of

    damage restoration. Certain design factors, such as unloaded

    conductor tensions, maximum allowable conductor temperatures,

    and phase spacing to avoid ice galloping induced flashovers,

    are also fixed. Limiting the designer's choices can be economic

    in certain situations but not in others. What makes economic

    sense in flat terrain

    o r

    with a lightly loaded line may not be

    economic in hilly terrain or with a line whose electric load

    is consistently high.

    This paper considers a range of line optimization

    techniques which can be applied to decide whether standard

    o r

    optimized line designs

    are

    appropriate. It is found that even

    simple methods of optimization can help the designer keep his

    costs to a minimum.

    The effects of electrical losses, structure family and

    heights, conductor design limits on temperature and tension

    are determined in flat and hilly terrain for a 500 kV example

    case. In the example, in flat terrain, the selection of an

    optimum design in place of the standard, results in savings

    of from 8 to 15% in the total present worth of revenue

    required for construction and losses over the life of the line.

    In a specific section of hilly terrain, the example shows that

    the use of optimization methods results in savings of from 15

    to 19%. Th e costs

    of

    redesigning structures, using non-standard

    conductors and investigating the proposed changes in design

    limits must be measured against such potential savings.

    1.0 BACKGR OUND INTRODUCTION

    Many utilities in the United States and in Europe, utilize

    standard transmission line structures in order to minimize the

    costs of engineering, simplify construction, minimize inventory

    and ease restora tion problems in case of damage. Since

    structure loads are primarily determined by conductor loadings,

    a

    standard single

    o r

    bundled conductor corresponds to each

    standard set

    of

    structures.

    39 TD 435 2 PWRD 4 paper recommended and approved

    by the IEEE Transro iss ion and 3 i s t r i bu t io n Commi tt ee

    of

    t h e

    I E E E

    Power Engineer ing 3ociety for p r e s e n t a t i o n

    a t t he I EEE /PES

    1989

    Transmiss ion

    an3

    D i s t r i b u t i o n

    Conference, New O r l e a n s , L o u i s i a n a , 4 p r i l

    2 -

    7 , 1989.

    Yanuscr ip t submi t t ed October

    7 ,

    1983; made avai l a5 l e

    f o r p r i n t i n g Y ar ch

    8 ,

    1989.

    Dale A. Dou glas, Senior Member

    Power Technologies, Inc.

    New

    York N Y

    1145

    Those who use standardized structure/conductor designs

    do so for all but the largest line projects contending that the

    engineering and test costs exceed the potential savings in line

    losses and capital costs resulting from a full engineering line

    design study. If a single structure/conductor combination is

    used

    for

    a

    particular voltage class, the only variables

    considered in the line design process are route selection,

    tangent structure heights, and structure spotting

    of

    the standard

    structure family along the route.

    Even in those cases where one attempts to optimize the

    design of a particular line, the range of certain design factors

    may be limited.

    For

    example, the minimum size of conductor

    may be strongly influenced by radio noise limits, such limits

    being fixed by regulation. Similarly, the cost of right-of-way

    is a major factor in line cost but the cost of purchasing and

    clearing the land is beyond the control of the designer.

    Other design factors, however, that

    within the control

    of

    the designer may be kept at traditional levels because of

    a lack of technical data

    -

    for example, it may be

    m o r e

    economic

    to install conductors to a higher unloaded tension than is done

    in normal practice but the lack of field results on the

    use

    of

    higher tensions prevents it

    - or

    simply because using traditional

    values avoids th e need for eng ineering analysis.

    A previous paper

    [ I ]

    described how line optimization

    studies allow one to evaluate the potential savings offered by

    conductor material and design innovations. Cost reductions

    resulting from changes in conductor properties were determined

    'for single and double circuit

    345

    kV lines in flat terrain.

    Changes in conductor design leading to reduced aeolian

    vibration and ice galloping and changes in conductor thermal

    elongation coefficient, conductivity and the use of trapezoidal

    rather than round strands were evaluated. The conclusions

    of that paper were that the greatest opportunities for cost

    reduction lay in increased everyday conductor tension, conductor

    compaction, and reduced thermal elongation.

    Using the optimization methods described herein, the utility

    line designer may estimate the potential savings involved in

    various changes in his standard design without needing to

    develop detailed structure designs. This calculated savings can

    then be compared to the costs of the designing and testing

    structures, the additional cost of inventory/restoration and the

    detailed engineering costs that would be required to build the

    optimized line.

    2.0 LINE DESIGN CHOICES

    There is no unique process by which all transmission lines

    are designed. There

    are,

    however, certain elements to any

    line design that are common to all, The largest difference

    between the design process at one utility and another is

    determined by the degree to which the line design is

    standardized or optimized. That is, the extent to which the

    engineer is free to select the structures and conductor, and

    to alter certain design parameters to obtain the optimum line

    design solution in a particular design situation.

    2.1 ODtimization Versus Standa rdizatio n

    In a fully standardized design, the engineer essentially

    fits a limited family of standard structures supporting the

    corresponding standard conductor to the selected route. He

    attempts, while doing this, to minimize both the number of

    structures per mile and the use of expensive anglehtrain

    structures whenever possible.

    O55j-S950/9O/0jOO-l145 OlOO

    990

    EEE

  • 8/16/2019 EHV TRANShlISSION LINE DESIGN Oppurtunities of Cost Reduction

    2/8

    1146

    In flat terrain, structures are spotted at or near their

    maximum allowable wind span and angle/strain structures are

    only required for failure containment and at points where the

    line changes direction. In hilly

    or

    mountainous terrain,

    anglehtrain structures may be required to handle sharp changes

    in elevation and the full utilization of tangent structure

    capabilities is less likely.

    In a fully optimized design, the use of any available

    structure and/or conductor is possible

    so

    long

    as

    it can be

    shown to be economic and reliable. Design limits are

    questioned and studied. In flat terrain the wind/weight spans

    are varied searching for the lowest cost for each potential size

    and type of phase conductor. in hilly or mountainous terrain,

    unloaded conductor tensions, structure wind/weight spans, H/V

    ratios, and the available range of structure heights and types

    are varied seeking to find the minimum cost support structure

    for each potential phase conductor size and type.

    2.2 St ructure Choices

    Some of the major structure design parameters that may

    be varied in a process of line optimization are:

    o Structure type (steel lattice, guyed V , etc.)

    o Structure mechanical characteristics (wind span,

    weight span, H/V ratio)

    o

    Available structure family (tangent, Oo 15O

    suspension, etc.)

    o Available structure heights (range and

    interval)

    Admittedly, the designer may not be free to vary

    ll

    these

    design parameters because of regulatory or aesthetic restraints,

    but, unless completely restricted as to structure, available design

    possibilities should be studied in a systematic manner.

    2.3 Conductor Choices

    Conductor design parameters (not all of which are

    independent) that may be varied in a process of line

    optimization are:

    o

    o

    subconductor diameter

    o

    conductor strength weight

    o

    conductor resistance

    o

    coefficient of thermal elongation

    o conductor weight per unit length

    number of conductors per phase

    2.4 D esign Limits

    Design limits can result from safety, reliability or economic

    considerations. They can be based on detailed engineering

    studies or on simple tradition. Safety considerations determine

    minimum ground clearance, structural safety factors and

    maximum ice and wind loadings that the line must survive.

    Reliability determines that the mid-span phase-to-phase spacing

    must be adequate to avoid flashovers during occurrences of

    ice galloping. Environmental limits may dictate the minimum

    diameter subconductor in a particular bundle configuration.

    3.0 ALTERN ATIVE DESIGN OPTIMIZATION APPROACHES

    If the designer is limited to the use of a few standard

    structu res (single tangent struc ture, 15O strain and a dead-end

    structure) all designed for a particular conductor, then the

    optimization of this line is limited to the minimum cost

    placement of these structures on the chosen right-of-way.

    This may be done by an experienced hand or by numerical

    methods. This particular form of optimization is well understood

    and is a standard part of every line design. The greatest

    opportunities for minimizing cost in the process of spotting

    towers is in uneven terrain[2].

    This study assumes that the process of line design using

    standard structures and conductor includes the optimum or near

    optimum cost placement of available structures on the right-

    of-way either by means of an experienced tower spotting

    engineer or by means of a numerical program.

    3.1 Con ductor ODtimization

    The type and size of phase conductor are varied.

    Standard

    structures are not varied. The minimum allowable conductor

    diameter is set by the minimum required thermal capacity for

    low voltage lines and by radio noise, audible noise and corona

    requirements for higher voltage bundled lines. The maximum

    practical conductor diameter is determined by the load limits

    of the standard structures (the larger the conductor diameter,

    the shorter the wind and weight spans - the stronger the

    conductor, the smaller the maximum line angle of angle

    structures).

    Within these constraints on conductor size, the

    subconductor diameter is selected such that the sum of total

    present worth of revenue required (PWRR) for electrical losses

    over the life of the line and the levelized costs of construction

    and maintenance, are a minimum [3],[4].

    3.2 Conductor and Structure Ootimization

    Variations in both the conductor and the structure are

    considered. The lower limit on conductor diameter is still set

    by either thermal or environmental design limits but larger

    conductors can be accommodated by strengthening structures.

    Conductors and structures having certain novel characteristics

    are considered. Since the range of choices is large, the task

    of design becomes both more complex and, potentially at least,

    more rewarding.

    For each type of structure investigated, the structure cost

    varies with crossarm height, phase spacing, conductor diameter,

    tension and span length.

    A mathematical relationship between

    structure cost and these variables must be determined before

    this optimization approach can be undertaken. The resulting

    optimal conductor and structures will involve the costs of

    detailed structure design and perhaps some test work.

    Design limits

    -

    unloaded conductor tension limits,

    maximum conductor temperature, phase spacing, etc.

    -

    are

    unchanged.

    3.3 Condu ctor. Structur e and Design Limit ODtimization

    The evaluation of certain innovations in conductor and

    structure materials and/or design may require a re-evaluation

    of conductor, structures and even design limits, limited only

    by the need for safety and reliability at minimum cost. For

    example, a new conductor design such as SDC[S], can be

    installed at higher than standard unloaded tensions and offers

    reduced structure wind loading due to the use of trapezoidal

    rather than round strands. The resulting savings in structure

    height and/or number of tangent structures per mile must be

    compared to the increased costs from more heavily loaded angle

    structures and possibly higher construction loads. The

    advantages and disadvantages of such innovations require a

    rather thorough rethinking of all the standard design

    components and assumptions. Even with the use of standard

    conductors, the consideration of non-standard design limits such

    as reduced or increased tension[6] and reduced o r increased

    maximum temperature[7] may offer significant savings in certain

    types of terrain or may provide the justification for necessary

    research concerning the use of nonstandard design limits.

    4.0 OPTIMIZATION

    OF

    A STANDARD

    500

    KV DESIGN

    In order to demonstrate the preceding optimization

    alternatives, the design of a 500kV transmission line using a

    standard conductor and limited family of standard structure

    designs will be compared to various optimized alternatives.

    The example designs are kept relatively simple but are sufficient

    to illustrate the concepts clearly.

  • 8/16/2019 EHV TRANShlISSION LINE DESIGN Oppurtunities of Cost Reduction

    3/8

    1147

    'ooor------

    6

    I \

    4 0 0 -

    l

    Certain major line costs (such as right-of-way purchase

    and clearing and shield wire material and labor) and certain

    minor line costs (such as insulators, spacers and hardware) are

    insensitive to changes in the design of the standard steel lattice

    structure . These costs essentially remain constant regardless

    of optimization efforts regarding structures and conductor.

    4.1 Standardized Design

    It is assumed that the example line is to be built in a

    National Electric Safety Code (NESC) Heavy loading area;

    that the standard design consists of

    a

    3-conductor bundle

    of

    Rail ACSR; and that only single circuit, self-supporting steel

    lattice structures are used either for standard or non-standard

    structures. Th e standard structure family consists of a tangent

    tower that can be used at line angles of up to 2 degrees, and

    a 60° dead-end strain tower. The standard tangent structures

    are available in three heights and the strain structure in only

    one height. Minimum ground clearance at the maximum

    conductor temperature of IOOC is 27 feet.

    The standardized line design process as defined here,

    allows one to minimize the line cost by selecting the least

    expensive combination of structure heights and types from

    those available but does not allow variation of the mechanical

    characteristics of the various standard structure types nor the

    available range of heights. The standard structure family is

    described in Tables 1 and

    2.

    The mechanical capabilities

    (maximum line angle, wind spans, weight spans, maximum wind

    to weight span ratio) are listed for the suspension and the

    strain structure. Structure costs include structure and

    foundation material, labor and hauling, insulators, conductor

    hardware, and conductor clipping costs.

    MA X

    MAX WIND SPAN

    MA X I MU M MA X

    ANGLE ANG.

    ANG. LOADED BARE

    RATIO

    TY PE LI N E @ M A X

    @

    Oo WEIGHT SPAN H/V

    P E G ) FT) n)

    FT)

    IW

    T A N G E N T

    SUSPENSION 2 1000

    1000

    1245 2000 1.4

    A N G LE

    STRAIN 60 1000

    5000

    2000 3 ~

    TABLE la.

    -

    Mechanical Capabilities

    of

    Standard Structure

    Family with Standard 3-Conductor Bundle

    Rail ACSR

    Structure AlTACHM ENT COST OF

    Type X A R MH T H EIG H T STR U CTU R E

    m

    FT)

    W 1s K)

    TA N G EN T 73 60

    21.9

    SUSPENSION

    83

    70 24.0

    9 3

    80 26.1

    A N G LE

    STRAIN

    60

    60

    63.1

    TABLE Ib - Costs

    for

    Standard Structure Family.

    Note

    that costs include m aterial, erection. hardware insulators

    and clipping.

    Note that the maximum allowable wind/weight spans and

    H/V

    ratios

    of

    the standard structure family members, apply

    to the standard phase conductor (a bundle of 3 Rail ACSR

    conductors) installed to the standard design conditions

    (15

    final unloaded tension at 60F,

    70

    maximum loaded tension)

    with NESC Heavy loading.

    In flat terrain, a single tangent structure (crossarm) height

    In hilly terrain, the standard tangent tower

    f 93 feet is used.

    is available in crossarm heights of 73, 83 and 93 feet.

    The standard conductor and structure design meets the

    environmental requirements -

  • 8/16/2019 EHV TRANShlISSION LINE DESIGN Oppurtunities of Cost Reduction

    4/8

    1148

    4 .2 Ootimized Conductor Selection

    In this simplest optimization study, the standard

    transmission line structures remain unchanged both in cost and

    mechanical capability. Th e search for alternate conductors

    is restricted to those that meet the environmental

    requirements, and can be installed using the standard structure

    family with the same design restrictions on unloaded tension

    and maximum conductor temperature.

    Consider the two possible electrical loading situations as

    described in section

    4.1

    -

    259/0

    LF

    and 75%

    LF.

    Given the

    restrictions on changing the standard structures and the

    environmental limits, the conductor selection study is limited

    to other sizes of 45/7, low steel ACSR or mechanically

    equivalent conductors in 2 and 3-conductor bundles. Only ACSR

    conductors are considered here.

    The use of larger 45/7 ACSR conductors in a 3-conductor

    bundle meets the environmental restrictions but would require

    redesign of the strain structures because of increased tension

    loads. Two-cond uctor bundles with conduc tor diameters of less

    than 1.7 inches do not meet the environmental requirements.

    A two-conductor bundle of 2156 kcmil, 84/19 Bluebird, however,

    presents approximately the same mechanical ice and wind

    structure loads, only slightly higher RI and AN levels, and

    nearly the same maximum sags as the standard 3-conductor

    bundle of Rail ACSR.

    Table 3 compares RI/AN levels, direct and present worth

    material and labor costs, and present worth of electrical losses

    over the

    35

    year life of the line for

    Loss

    Factors of

    25

    and

    75%, for both the standard 3-conductor Rail and the alternate

    2-conductor Bluebird bundle. Since the conductors have

    approximately the same sag and utilize the standard structures,

    the structure costs are approximately the same both in flat

    and hilly terrain. For either

    Loss

    Factor, the Bluebird alternate

    yields a lower net PW cost, however, the PW savings at the

    higher loss factor is approximately three times as large.

    From Table 3 , it can be se en that in creasing th e PW of

    construction costs by $38K/mile to install the Bluebird

    conductor, reduces the PW of electrical losses by $66K/mile

    and $118K/mile for loss factors of 25 and 75%, respectively.

    The corresponding net PW savings are $28K/mile and $SOK/mile.

    3 RAIL 2. BLUEBIRD

    ENVIRONMENTAL

    EFFECTS

    RI @ Edge of ROW (dB) 44 45

    AN

    @

    Edge

    of

    ROW (dB(A) 47 51

    CONDUCTOR MATERIAL LABOR

    DIRECT COST ($K/MILE)

    PW COST (SK/MILE)

    PW OF BLEC LOSSES (SK/MILE )

    LF

    25%

    LF 75%

    61

    100

    84

    138

    236 I70

    42 303

    PW NE T SAVlN GS ($K/MILE)

    LF 25% 28

    LF 75%

    80

    TABLE 3 - Comparison of Present Worth

    of

    Conductor

    Material & Labor and Electrical Losses

    or

    Standard

    3*RAIL ACSR Bundle and Alternate 2.Bluebird Bundle

    at Loss Factors (LF)

    of

    25% and 75%. Table data applies

    to both flat and hilly terrain.

    4.3 Optimized Conductor and Structure

    In this example, it is assumed that either the standard

    conductor and/or the standard structure family can be altered

    if

    R

    lower cost design solution is found but that the standard

    design limits (maximum conductor unloaded tension,

    environmental effects, etc.) remain the same. The savings

    indicated by this study of conductor and structure alternatives

    must be compared to any design and testing costs that would

    be required to implement the new design.

    In order to evaluate possible cost reductions through

    changes in the standard structure family, one must be able to

    estimate structure cost as a function of conductor loadings

    and tower dimensions. While it is possible to recalculate the

    structure cost by means of a detailed analysis for each

    combination of wind/weight span, conductor, tower height and

    phase arrangement, section 4.3.1 discusses a simpler and quicker

    method of estimating structure cost by means of a linear

    regression equation.

    4.3.1 Regression Cost Eauation s

    -

    Structure and foundation

    cost depends upon conductor loading (maximum wind/weight

    spans), phaseishield wire attachment points (phase-phase spacing

    and height to bottom phase) and, for angle structures, on the

    conductor tension and line angle. For the purposes of

    optimization studies, structure and foundation costs under

    different loading conditions may be estimated based upon a

    limited number of structure designs through the development

    of a linear regression structure cost equation.

    While it is understood by the authors that structure and

    foundation costs are not linearly dependent on loading and

    geometry, experience has shown that a linear regression model

    is adequate for optimization studies performed early in the line

    optimization process. Once a combina tion of conduct or and

    structure family is tentatively selected, the designer may want

    to replace the approximate structure costs with more precise

    values based upon detailed design studies. These improved

    models could then be used in the final tower spotting process

    in fine tuning the conductor tension and tower locations.

    As an example of how such regression equations are

    developed, steel lattice structure weights were calculated for

    sixteen different combinations of conductor, crossarm height,

    and with conductor loadings typical of an NESC area for single

    circuit steel lattice structures, using a finite element design

    program called SCTDES written by Dr. Alain Peyrot of the

    University of Wisconsin although one could equally well obtain

    such data from other design methods.

    The resulting structure

    weights for the eight cases are listed in column 1 of Table

    4. The transverse (T), vertical (V),longitudinal

    (L)

    broken wire

    loads and the crossarm height above earth are also shown in

    the Table.

    ACTUAL

    ESTIMATED

    T L V H t

    WEIGHT

    WEIGHT LOAD LOAD LOAD HT

    TWR TWR ACT-EST TRNS LONG VERT XARM

    9901.52 9910.56

    -0.1

    19.40 12.39 33.71 66.50

    19098.86 19200.28 -0.5 33.95 9.18 59.00 109.20

    9824.24 9560.86 2.7 15.55 11.92 30.48 67.10

    18046.21 18195.65

    -0.8

    27.22 10.49 53.35 107.80

    10172.73 10183.58

    -0.1

    19.77 12.51 35.47

    66.90

    19443.56 19255.46 1.0 34.60 10.76 62.08 107.10

    1011S.15 9750.80 3.6 16.32 13.07 32.07 67.20

    18648.11 1 8584.47 0.3 28.57 11.43 56.12 108.20

    9865.15 9933.53 -0.7 19.21 30.50 32.05 71.40

    24078.41 23800.07 1.2 33.62 6.66 56.09 144.50

    9434.85 9415.91 0.2 15.07 38.28 28.59 72.50

    20106.44 19973.30 0.7 26.38 19.84 50.03 125.30

    9965.15 10070.33 1 . 1 19.57 35.10 33.61 71.80

    23097.35 23262.15 -0.7 34.25 9.15 58.82 138.60

    10056.06 10513.09 -4.5 16.53 8.60 31.36 72.50

    20655.30 20899.06 -1.2 28.93 7.84 54.88 125.30

    TABLE 4

    -

    Actual Structure Weights Compared

    to

    Estimated Weights

    Based on the Following Regression.

    Equation: SW - 3386 + 12.6.T -24.9 L + 122.6'V

    +

    138.8. Ht

    Based on the design weights and the conductor loadings

    and crossarm height, a linear regression equation, which is also

    shown in Table 4, was determined. The primary independent

    regression variables are transverse load and crossarm height,

    but the fit is improved by including vertical and longitudinal

    loading as well. The second and third columns of the Table

    show the structure weights calculated on the basis of the

    regression equation and the percent difference from the design

  • 8/16/2019 EHV TRANShlISSION LINE DESIGN Oppurtunities of Cost Reduction

    5/8

    1149

    weights, respectively. Clearly, the linear regression equation

    yields excellent estimates of structure weight over the range

    of loading and structure heights indicated in the Table.

    A similar analysis of foundation costs and strain tower

    weights lead to corresponding linear regression equations for

    foundation cost and strain structure weight. The optimization

    studies in the balance of this paper utilize such equations in

    order to estimate the cost of structure and foundation for

    various conductors, heights and spans.

    4.3.2 ODtimum Conductor

    &

    Structure in Flat Terrain-

    In section 4.2, a 2-conductor bundle of Bluebird ACSR was

    shown to be less expensive than th e standa rd 3- conductor

    bundle of Rail ACSR yet gave roughly the same RI and Audible

    noise and the same structural loads. In this section, the

    possibility of using a wider range of conductor types and sizes,

    while adjusting the structure cost to reflect the conductor load

    in each case, is considered. Also, the wind/weight span of

    the tangent structure is varied for each candidate conductor

    in searching for the minimum cost design. Design limits-

    conductor unloaded tension in %RBS, maximum conductor

    temperature, broken wire load assumptions, RI limits, etc.-

    remain constant for each conductor and structure.

    In flat terrain, angle towers are used wherever there is

    a change in line direction. Thus the number of such towers

    is constant no matter how the conductor and structure

    wind/weight sp ans vary. The cost of each angle structure,

    however, changes with the conductor tension and the

    transverse load. Tangent towers are largely insensitive to

    conductor tension, but increase in cost primarily with

    transverse load.

    Starting with the standard win d span of 1000 feet, the

    total present worth of revenue required (PWRR) for electrical

    losses and construction cost is plotted against conductor

    diameter. Figures 2a and 2b are for loss factors of 25% and

    75%, respectively. 3-conductor bundles of all-aluminum

    conductor (AAC); 45/7 ACSR; and 54/19 ACSR were studied.

    The subconductor diameter yielding minimum total present worth

    of revenue required (PWRR) for construction and losses is not

    sensitive to the conductor type, however, it sensitive to loss

    factor. The largest diameter subconductors of each type - 1590

    kcmil Coreopsis AAC, 1590 kcmil Lapwing, a nd 1590 kcmil

    Falcon - offer savings at either

    loss

    factor over the standard

    design.

    TOTAL

    PWR R (SKIMILEI

    i

    I

    20

    1

    CONDUCTOR

    DIAMETER

    (IN)

    Figure 2a - Total PWRR versus Subconductor

    Diameter for 3 Conductor Bundles. Wind Span

    is 1000 ft. Loss Factor is 25%. All Tangent

    Structures in Flat Terrain.

    TOTAL PWR R ( K/MILE)

    I\

    75

    -

    7

    65 1

    CONDUCTOR DIAMETER (IN)

    Figure 2b

    -

    Total PWRR versus Subconductor

    Diameter fo r 2 Conductor Bundles. Wind Span

    1000 ft.

    Loss

    Factor is 75%. All Tangent

    Structures in Flat Terrain.

    Total PWRR depends slightly on the tangent tower wind

    span for the three 1590 kcmil conductors. In this case, the

    minimum total PWRR occurs for the standard wind span of 1000

    feet.

    With a 3-conductor bundle of Lapwing ACSR, with loss

    factors (L F) of 25% and 75%, and a peak normal load of 1000

    MVA, the net savings in comparison to the standard 3-conductor

    Rail bundle is $39K/mile and $108K/mile, respectively.

    4.3.3 ODtimum Conductor Structure in Hillv Terrain-

    The effect of altering the standard range of tower heights

    and the wind span of standard tangent structures will be studied

    for the Lapwing conductor selected in section 4.3.2. The

    standard structure/conduc tor family has tangent tower

    attachment heights of 60 to 80 feet available for hilly terrain.

    Table shows the effect of varying the wind span and the

    range of structure heights.

    RANGE OF MAX NO.

    OF

    COST OF

    AlT AC H WIND STRUCTURES STRUCTURES

    CASE HEIGHTS SPAN TANGENTtDE-TOTAL TANGENTtDE-TOTAL

    FILE (FT)

    FT)

    (SUMILE)

    3D

    70 800 16 +

    I 1

    - 27 I l l + 224 335

    121

    +

    162

    =

    2820

    1000

    I6

    8 -

    24

    139 +

    101

    -

    240

    200

    17

    +

    5 22

    0

    IO8

    + 183 = 292

    E 60-80 800 17 + 9 = 26

    60-80

    1000

    20

    + 5

    25 142 +

    101 -

    243

    1 3 9 + 8 0 - 2 1 9

    0-80

    I200 18 + 4

    22

    3F 60-120

    1200

    17 +

    3 -

    20 I44 + 60

    -

    204

    60-120 I400 I S

    +

    2

    =

    17 145 + 41

    =

    I86

    TABLE

    5 -

    Variation in Direct Structure Cost (for 3 L apwing B undle )

    with Maximum Wind Span and Structure

    Heights

    in Hilly Terrain.

    In this hilly terrain, the

    use

    of stronger tangent

    structures (i.e. a 1200 foot wind span instead of the standard

    1000 feet ) increases the cost of tangent structure but

    reduces the QQ structurc cost from $243K/mile to $219K/mile

    by reducing the numbei of tangent structures from 20 to 18

    and the strain structures from to 4.

    Also, referring again to Table 5 increasing the range

    of

    structure attachment heights from 60-80 feet up to 60-120 feet

    further reduces the total structure cost for a 1200 foot tangent

    wind span fro m $219K/mile t o $204K/mile. If the tangent wind

    span is further increased to 1400 ft., the total structure cost

    is reduced to $186K/mile.

    By increasing the range of available tower heights and

    using stronger tangent strudtures, the structure cost associated

    with the 3-conductor Lapwing ACSR conductor can be reduced

    by $57K/mile.

  • 8/16/2019 EHV TRANShlISSION LINE DESIGN Oppurtunities of Cost Reduction

    6/8

    1150

    When the optimized 3-conductor Lapwing design is

    compared to the standard 3-conductor Rail design, net savings

    of $86K and $155K/mile in total PWRR for losses and

    construction are found for LF's of 25% and 75 , respectively.

    4.4 Ootimization Studv of Design Limits

    In this section, the value of changes in two standard

    design limits will be considered - maximum allowable conductor

    temperature and maximum final unloaded design tension

    expressed as a percent of rated strength. First the sensitivity

    to these design limits will be investigated for the standard

    conductor and structures, then the broader impact on the use

    of alternative conductors and structures will be considered.

    4.4.1 - Changing Maximum Conductor TemDerature - The

    maximum allowable conductor temperature determines the

    maximum sag in EHV lines. Thus it seems apparent that any

    decrease in this design limit will result in shorter structures

    and less construction cost. Yet the maximum allowable

    temperature also determines the thermal rating of the line.

    The higher the maximum allowable temperature of the conductor,

    the higher the thermal rating of the line. In low voltage lines,

    thermal ratings can be of primary concern and insufficient

    thermal capacity under emergency conditions may force

    expensive reconductoring of lines.

    In EHV lines, the environmental limits usually require the

    use of relatively large bundled conductors whose thermal

    capacity, even for moderate temperature limits is more than

    sufficient over the life of the line. The line cost data in Table

    6, shows the sensitivity to maximum allowable conductor

    temperature both for flat and hilly terrain. If the maximum

    conductor design temperature is reduced to 5OoC from 100°C,

    with the standard conductor/structure in flat terrain, the

    difference in direct construction cost of tangent structures

    is $5K/mile. The savings is virtually the same whether the

    terrain is flat or hilly. If it can be determined that the thermal

    capacity of the line is sufficient for a 5OoC maximum conductor

    temperature, then the savings is easily obtained.

    SAG AT TOTAL

    MAXIMUM MAXIMUM TANGENT

    ALLOWABLE TEMP FOR TOWER

    TERRAIN CONDUCTOR 1200

    FT.

    COST

    __ TEMP (CC1 RULING

    SPAN

    @./MILE1

    F L AT 100

    60.0

    151

    F L AT 50 55.0 146

    HILLY'

    100 60.0 124

    HILLY' so

    55.0

    120

    *Structure Heights of 60 to 120

    f t .

    Wind Span 1200 ft.

    TABLE

    6

    - Effect of Maximum Allowable Conductor Temperature

    Upon Line Cost for

    3

    x Lapwing Conductor Bundle.

    4.4.2 Effe cts of Maximum Unloaded Conductor Tension

    -

    If

    the standard design limit on maximum unloaded conductor

    tension is increased, the level of aeolian vibration will also

    increase. This may require the use of vibration dampers.

    Increasing conductor tension also affects structure cost in three

    ways - the number of tangent structures per mile tends to go

    down since the conductor sag is less for a given span; the

    tension load on angle structures goes up requiring them to be

    stronger and therefore more expensive; and strain structures,

    the use of weights, or the redesign of suspension structures

    may be required in order to deal with uplift problems in uneven

    terrain.

    Figure 3  shows curves of structure cost versus final

    unloaded tension (expressed as a pelcent of rated breaking

    strength) for a line in flat ierrain where there are only

    tangent structures, and a line where there are assumed to be

    4 angle structures within the 3.6 mile section. In the latter

    case, the decrease in the number of tangent towers required

    is offset by the increased cost of the four angle structures.

    In the former case, the total PWRR of the line decreases by

    $22K/mile as the tension is increased from

    15

    to 21%.

    TOTAL PWRR (8KIMI)

    I

    7

     WIT H AN GLES

    66 k I

    I

    21

    6

    15

    18

    UNLOADED FINAL TENSION @60F

    RES)

    Figure 3 - Total PWRR versus Unloaded Final

    Conductor Tension @ 60F for Flat Terrain

    with and without Angle/Strain Towers.

    Figure 4 shows the impact of conductor tension limit

    changes on the line costs for the standard structure/conductor

    combination in the hilly terrain shown in Figure 1.  It is

    assumed that there are no line angles between the strain towers

    at each end of the section. Note that the tension (in YoRBS)

    which yields the minimum total PWRR is different for each

    of the three conductors considered. Above a certain value

    of unloaded conductor design tension, the number of strain

    structures required increases as does the total structure cost.

    Clearly, in hilly terrain, even without line angles, the use of

    higher conductor tensions is not always an advantage.

    TOTAL

    PWRR ( KIMI)

    8

    LAPWINO

    COREOPSIS

    7 8 0 .

    FALCON

    780

    WIND SPAN

    7

    FINAL UNLOADED TENSION C60F ( RBS)

    Figure 4 - Total PWRR versus Unloaded Final

    Conductor Tension

    @

    60F for Hilly Terrain. Wind

    Span of Tangent Towers is 1200 ft. and 1400 ft.

    4.5 Comoarison of Standard and Ootimized Line Designs

    In the preceding sections of this paper, the possibility

    of reducing the costs of construction and electrical losses by

    varying different line design factors has been evaluated for

    a particular

    500

    kV line design situation. Clearly, the savings

    due to each variable while not precisely additive, may

    accumulate. Thus it is of interest to consider the possible

    savings that could accrue if the standard line design is

    optimized with respect to conductor size, type, maximum

    allowable temperature, an d unloaded tension, and where the

    structures are optimized with respect to wind span and, in hilly

    terrain, with the range of available heights.

  • 8/16/2019 EHV TRANShlISSION LINE DESIGN Oppurtunities of Cost Reduction

    7/8

    1151

    Table 7a compares the standard line design (1000 foot

    wind span, 3-conductor Rail ACSR bundle, 100°C maximum

    allowable conductor temperature, 15% final unloaded tension,

    etc.) with an optimized design in flat terrain with all tangent

    structures. The net total present worth savings on the cost

    of structure, conductor and electrical losses are $44K/mile and

    $1 13K/mile f or loss factors of 25% and 75%, respectively. These

    savings must be compared with the added costs of tower

    redesign and the need for additional inventory

    of

    conductor

    hardware, etc.

    STANDARD OPTIMUM

    Conductor

    3

    Rail 3 Lapwing

    Max Wind Span

    1000 1000

    Tension (%RBS),T

    15 .

    IOOOC

    21 . SOT

    Direct Construction

    Cost (SK/Mile) 191 219

    Total PWRR (SK/Mile)

    75

    LF 734

    621

    25 LF 549 505

    TABLE 7a

    -

    Comparison of Standard and Optimized Standard and

    Optimized 500

    kV

    Conductor and Structure in Flat Terrain.

    Table 7b compares the standard line design to that

    of

    the optimum in hilly terrain. As in the preceding, the net total

    PW savings are $102K/mile and $168K/mile for 25% and 75%

    LF's. These potential savings must be compared with the added

    costs of tower redesign and the need for additional inventory

    of conductor hardware, etc.

    STANDARD OPTIMUM

    Conductor 3. Rail

    3.

    Coreopsis

    Max. Wind Span 1000 1400

    Tension

    (%R BS). OC

    15,

    100 21, so

    Direct Cost of

    Conductor & Structures

    (SK/Mile) 275 265

    Total PWRR (%/Mile)

    75 871 703

    25 686 584

    TABLE 7b - Comparison of Standard and Optimized 500 kV

    Conductor and Structure in Hilly Terrain

    (3.6

    miles

    wi t hou t line angles).

    5.0

    CONCLUSIONS

    Clearly, the indicated savings through line optimization

    is not a net savings at all. The cost of implementing these

    various changes in structure and conductor design and use will

    clearly cost money as well as save it. The point is, that the

    methods outlined in this paper point in the direction of

    potential cost savings in EHV lines. The degree to which they

    are actually implemented by the utility designer depends upon

    the costs associated with the changes as well as upon the

    savings indicated here.

    Nevertheless, one may draw several conclusions from the

    preceding examples of optimization:

    (1)

    The use of standardized conductor and structure designs

    is not necessarily uneconomic. In many cases, the size

    of conductor at EHV voltages, as determined by

    environmental needs, requires a conductor larger than

    is economic. In such cases, the use of a standard

    conductor and corresponding structure designs minimizes

    the engineering costs and eases inventory/restoration repair

    problems.

    (2) If the standard conductor design, which meets the

    environmental and thermal needs of the line, is smaller

    than the economic conductor size, then the savings in

    present worth of electrical losses over the life of the

    line can be significant. This is particularly true on long

    lines where the use

    of

    a non-standard conductor is not

    an inventory or restoration problem.

    The potential savings from a line optimization study

    increase with the number of factors considered. For

    example, a study that considers redesigning the structures

    as well as the conductor allows potentially higher savings

    than a study of conductor alone.

    Line design factors considered in this paper were conductor

    size, conductor type, structure wind/weight span, structure

    height range, unloaded conductor tension, and maximum

    allowable conductor temperature. All appear to be

    potential sources of significant savings.

    The potential savings from optimization studies is difficult

    to predict without actually performing the studies. With

    the availability of increasingly sophisticated numerical

    line design methods, the engineering time required for

    such studies (and thus the cost) has decreased dramatically.

    Even if standard conductor and structure designs are

    retained after concluding an optimization study, the

    designer has a solid basis for retaining standard designs.

    ACKNOWLEDGMENT

    The authors acknowledge the contribution of Messrs. H.

    Bryan White and John Bates to the sections of this study

    concerning structure optimization with regard to terrain. The

    algorithm used in studying tower placement in hilly terrain

    was developed by them.

    In

    addition, the authors wish to thank

    the Electric Power Research Institute which sponsored the

    studies from which this paper was excerpted and who also

    sponsored the development of the Transmission Line Optimization

    Program with Terrain (TLOPWT) which was used to perform

    all the optimization calculations.

    1.

    2.

    3

    4.

    5

    6.

    7.

    6.0 REFERENCES

    Dou gla s, D.A., Economic Measures of Bare Overhead

    Conductor Characteristics, IEEE Transactions on

    Power Delivery, Vol. 3, No. 2, April, 1988, pp 754-

    761.

    Bates, J. and White, H.B., Micro-based Program

    Refines Transmission Design, Transmission

    Distribution Magazine, April; 1987, pp 40-49.

    Grant,

    IS.

    and Clayton, R.E., Transmission Line

    Optimization, IEEE Transactions on Power Delivery,

    Vol. PWRD-2, No. 2, April, 1987, pp 520-526.

    Grant, I.S. and Longo, V.J. Economic Incentives for

    Larger Transmission Conductors, IEEE PES Paper

    81 WM 208-8 presented at the IEEE PES Winter

    Meeting 1980.

    Kirkpatrick, L.A., McCulloch, A.R. and Pue-Gilchrist,

    A.C., Ten Years of Progress with Self-Damping

    Conductor, Paper No. F79 736-0, presented at the

    IEEE PES Summer Meeting, 1979.

    Fritz, E., The Effe ct of Tighter Conductor Tensions

    on Transmission Line Costs, IEEE Transactions

    Paper, Vol. PAS-79, 1960, pp 513-527.

    Day, P., Gaylard, B., et al, Influence of Conductor

    Designs and Operating Temperature on the Economics

    of Overhead Lines,

    Proc.

    IEEE, Vol. 118, No. 3/4,

    March/April, 1971.

    ,

  • 8/16/2019 EHV TRANShlISSION LINE DESIGN Oppurtunities of Cost Reduction

    8/8

    1152

    APPENDIX

    Economic Data

    -

    Base Case Values

    Cost of conductor steel

    Cost of 1350 aluminum

    Cost of tower erection

    Cost

    of

    tower material

    Period of analysis

    Discount Rate

    Line fixed charge rate

    Demand charge

    Demand fixed charge rate

    Demand reserve

    Demand charge escalation rate

    Energy charge

    Energy charge escalation rate

    0.40

    $/lb

    1.00 $/lb

    1.00 $/lb

    1.00 $/lb

    35 years

    12.00%

    20.00

    550.00 $/kW

    20.00%

    20.00%

    3.50%

    0.020 $/kWh

    7.00%

    Dale A. Douglass is a Senior Member of the IEEE. Born in

    Cleveland, Ohio in 1941, he received a BSME in 1963, and an

    MSEE and PhDEE in 1964 and 1967, respectively, from Carnegie

    Mellon University.

    After working as a member of technical staff with Bell

    Laboratories and as a product design engineer with Kaiser

    Aluminum, Dr. Douglass joined the staff of Power Technologies,

    Inc. in 1978 as a Senior Enginee r. He is presently Manager

    of the Overhea d Transmission Systems Unit.

    He

    has been

    involved in many aspects of overhead transmission design

    including wind-induced motions of conductor, optimal economic

    transmission design, and dynamic thermal rating techniques.

    He is a member of Tau Beta Pi and Pi Tau Sigma and is a

    member of the working groups on Overhead Conductor

    Temperature and Vibration and Galloping under the Towers,

    Poles, and Conductors subcommittee of the IEEE.

    He

    has

    chaired task forces on transient thermal ratings, AC resistance

    of

    bare overhead conductors, and safe design tensions for

    conductor.

    Mr. Richard E. Kennon is a graduate of the California Institute

    of Technology with a B.S. degree in Electrical Engineering

    obtained in 1952.

    He

    received a Masters degree in Business

    Administration from Indiana University in 1972. A senior

    member of the Institute of Electrical and Electronic Engineers,

    Kennon holds six

    U.S.

    patents and has written several articles

    and papers on the subject of overhead transmission lines.

    He

    is also an individual member of CIGRE.

    Before moving to EPRI, Kennon was Manager, Capacitor

    Equipment Engineering with the Westinghouse Electric

    Corporation in Bloomington, Indiana. In that position, he had

    responsibility for design of series capacitor protection, capacitor

    banks and capacitor fuses.

    He

    also held the positions of

    Supervising Engineer and Senior Engineer where he was

    responsible for design of station class surge arresters and

    development of ceramic bonded silicon carbide arrester blocks.

    He was formerly a Sales Engineer with Westinghouse in Los

    Angeles.

    Kennon is the Manager of the Overhead Transmission Lines

    Program, Electrical Systems Division, at the Electric Power

    Research Institute (EPRI) in Palo Alto, CA. Kennon joined

    the Institute in 1975 as a Project Manager in the Substations

    Program. Moving to his presen t position in 1978, he became

    responsible for research at two transmission research facilities

    and for development of EPRI’s TLWorkstation.