46
PILOT Presentation This presentation applies only to the Electric Utility 1

Electric PILOT Workshop February 2013

Embed Size (px)

Citation preview

Page 1: Electric PILOT Workshop February 2013

PILOT Presentation

This presentation applies only to the Electric Utility

1

Page 2: Electric PILOT Workshop February 2013

Application of Cash Criteria

1. Keep the rates stable

2. Increase the transfer to the City, however, it should not be at the expense of existing Capital Expenditure Programming

3. Reduce Industrial Rates—number 1 above should take care of number 3, since no rate increase for a long time is the same as a rate decrease.

2

Page 3: Electric PILOT Workshop February 2013

Operating Expenses—numbers from 2011 Audit

$18,858,445.00

$6,053,688.00

$883,761.00

2011--Operating Expenses

Power Supply Expenses

Other Expenses

PILOT

•Approximately 70% of all electric utility expenditures are power supply expenses. •Other expenses will increase due primarily large increases in Transmission Expense. •Focus on reducing power supply expenses.

3

Page 4: Electric PILOT Workshop February 2013

Power Supply Planning

The following items are included in this study, some have already been implemented, while others will likely be implemented in the future.

1. Rate stabilization fund is used—this was implemented in 2006. 2. Statistical Model being used by system control to dispatch generating units—implemented in

2012. 3. Base load supply was reduced from 30 MW to 25 MW—this was implemented on January 1,

2013. This supply comes from Missouri River Energy Services. 4. Unit 8 has a scheduled run in January, June, July and August—this has been implemented, and

functions as a hedge against the market. 5. Installation of new Wartsila 9.5 MW generating unit—Unit will go on-line in February 2013. Unit

will be used as a hedge against the real-time market. 6. Change air permit for units 3 and 4. Each of these units are 4 MW dual fuel units. Late spring

2013 we will identify what needs to be done (if anything), to gain added operating hours for both units. Anticipate this will be complete in 2014. Units will be used as a hedge against the real-time market.

7. Purchase and install a 2nd Wartsila 9.5 MW generating unit—we would like to see this unit go on-line in 2015/2016 time frame. This unit will be used as a hedge against the real-time market.

4

Page 5: Electric PILOT Workshop February 2013

Power Supply agreement with Missouri River Energy Services

• Missouri River Energy Services(MRES) is a Joint Action Agency. HUC has a membership agreement with MRES. HUC’s electrical bill from MRES is based on a rate. All members of MRES have the same rate structure.

• MRES rate structure is seasonal, following is a breakdown of that rate structure: – Dec-Feb.—$53.1/MWHR – March-May--$44.1/MWHR – June-Aug.—$58.3/MWHR – Sep.-Nov--$44.2/MWHR

• Approximately 70 % of Hutchinson’s electrical energy supply comes from MRES. The other 30 % comes from market purchases or is generated using HUC’s power plants.

• Much emphasis has been placed on mitigating market risk as it relates to the 30 % that HUC provides Hutchinson. Market years 2006, 2007, 2008, 2009, 2010, 2011 and 2012 have all been treated as test years to determine the proper amount of generation that need to be installed at plant 1 to mitigate market risk.

• The following slides are a representation of the level of effectiveness of HUC’s strategies for the additional 30 % using a combination of market purchases and HUC’s electrical generation.

5

Page 6: Electric PILOT Workshop February 2013

Example of July 20, 2011—25 MW Base Load, Unit 3, 4, 8 New Unit 5

0

10

20

30

40

50

60

70

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

Load

Base Load + Unit 8 + Other Gen.

July 20, 2011

Unit 8 scheduled start

Units 3, 4, 5 start Market > Gen Cost

Purchase off market Market < Gen Cost

Unit 8 scheduled stop

Units 3, 4, 5 stop Market < Gen Cost

Not enough generation at Plant 1 to cover load

Time—24 Hours/day

Blue Line is HUC Electric Load

Red Line is Electric Supply MRES Base Load Supply

6

MWHR’s

Page 7: Electric PILOT Workshop February 2013

Example of July 20, 2011—25 MW Base Load, Unit 3, 4, 8, New Units 5 & 6

0

10

20

30

40

50

60

70

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

Load

Base Load + Unit 8 + Other Gen.

July 20, 2011

MRES Base Load Supply

Unit 8 scheduled start

Units 3, 4, 5, 6 start Market price > Gen Cost

Plant 1 now has enough Generation to take care of HUC load. HUC will realize a small op. income from electric supply sold into market. The Op. Income received is subtracted from Wholesale rates charged to HUC retail customers.

Time—24 Hours/Day

Blue Line is HUC Electric Load

7

Red Line is Electric Supply

MWHR’s

Page 8: Electric PILOT Workshop February 2013

Example July 2011 July 2011

$/MWHR MWHR Total Cost

Base Load $ 58.02 18,600 $ 1,079,172.00

Market Purchases $ 29.11 7,824 $ 227,755.95

Cost of Unit 8 Scheduled Gen. $ 36.60 2,400 $ 87,840.00

Hedged Gen.--units 3, 4, 5, 6 $ 47.49 3,109 $ 147,649.33

Additional Market Purch. After gen. $ 140.21 17 $ 2,383.62

Total HUC Load and Cost w/o bundling $ 34.88 13,350 $ 465,628.90

Bundled Gen.Revenue $ 67.54 1,751 $ 118,260.86

Bundled Gen Expense $ 47.24 1,751 $ 82,725.00

Bundled Gen Op Income $ 35,535.86

Total HUC Cost less bundling op. income $ 32.22 13,350 $ 430,093.04

Blended Cost for July $ 47.24 31,950 $ 1,509,265.04

MWHR's % Provided

Provided from MRES Base Load Supply 18600 58.22% $ 58.02

Combination of Market & Generation Supply 13350 41.78% $ 32.22

Total HUC retail supply 31950

8

Page 9: Electric PILOT Workshop February 2013

Monthly Supply from MRES and Market/Generation for 2011

Monthly 2011

% MRES Supply

Agreement % from Market/Generation

January 72% 28%

February 72% 28%

March 74% 26%

April 77% 23%

May 74% 26%

June 67% 33%

July 58% 42%

August 62% 38%

September 74% 26%

October 80% 20%

November 83% 17%

December 81% 19%

2011 Annual Supply % Supplied

% MRES Supply Agreement 72%

% from Market/Generation 28%

Note: This reflects the 25 MW base load power supply agreement with MRES. Please note that anywhere from 60% to 80% of HUC average monthly energy purchases are provided via MRES base load supply agreement. 9

Page 10: Electric PILOT Workshop February 2013

HUC 2011—Market $/MWHR

$-

$5.00

$10.00

$15.00

$20.00

$25.00

$30.00

$35.00

$40.00

$45.00

$50.00

Market

Statistical Model+Unit 6

Average Market Price

Average + Unit 6

Market Mitigation 2011

Average price using a combination of market purchases and HUC generation at plant 1

Average price if all extra needs purchased off market

10

Page 11: Electric PILOT Workshop February 2013

2011 Blended

$-

$10.00

$20.00

$30.00

$40.00

$50.00

$60.00

2011 Actual

Statistical Model+Unit 6

2011 Average

Avg + Unit 6

2011 Base Load Contract reduction, Unit 8 scheduled run, Statistical Model being used, Installation of New Unit 5 Unit 3 and 4 added Op. hours Installation of New Unit 6

Note: Does not include transmission expense.

11

Page 12: Electric PILOT Workshop February 2013

Annual % Supply From MRES and Market/Generation

% Annual Supply

Year

% MRES

Supply

Agreement

% from Market

and/or

Generation

Total HUC

Load

(MWHR's)

2006 69% 31% 319069

2007 67% 33% 328647

2008 69% 31% 318496

2009 76% 24% 288620

2010 72% 28% 305777

2011 72% 28% 302775

2012 75% 25% 291957

Note: The MRES base load power supply agreement accounts for approximately 70% of HUC annual energy needs. 12

Page 13: Electric PILOT Workshop February 2013

$/MWHR savings by project and Benchmarking Study

2006 2007 2008 2009 2010 2011 2012

Actual Average $54.06 $53.77 $57.47 $54.10 $52.78 $53.51 $52.35

25 MW Base Load and Market Purch. $50.68 $53.22 $52.47 $45.38 $45.59 $45.87 $46.01

+ Unit 8 $49.71 $52.54 $51.52 $45.64 $45.33 $45.66 $45.94

Statistical Model + Unit 5 $47.78 $49.85 $49.96 $45.01 $44.59 $44.71 $44.76

Statistical Model + Units 3, 4 $46.16 $47.59 $48.64 $44.49 $43.97 $43.90 $43.77

Statistical Model+Unit 6 $44.23 $44.91 $47.08 $43.86 $43.23 $42.94 $42.59

APPA Benchmark--10% to 50 % Generation(median) $46.00 $58.00 $47.00

APPA Benchmark--North Central/Plains(median) $49.00 $59.00 $60.00

APPA Benchamrk--50% to 100% Generation(median) $34.00 $46.00 $43.00

13

Page 14: Electric PILOT Workshop February 2013

Per Unit and Extended Savings

Per Unit($/MWHR) Savings by project 2006 2007 2008 2009 2010 2011 2012

25 MW Base Load and Market $3.38 $0.55 $5.00 $8.72 $7.19 $7.64 $6.35

+ Unit 8 $0.97 $0.68 $0.95 ($0.26) $0.26 $0.21 $0.07

Statistical Model + Unit 5 $1.93 $2.68 $1.56 $0.63 $0.74 $0.96 $1.18

Statistical Model + Units 3, 4 $1.62 $2.26 $1.31 $0.53 $0.62 $0.81 $0.99

Statistical Model + Unit 6 $1.93 $2.68 $1.56 $0.63 $0.74 $0.96 $1.18

Electric Sales (MWHR's) 319,069 328,647 318,496 288,620 305,777 302,775 291,957

Extended Savings 2006 2007 2008 2009 2010 2011 2012

25 MW Base Load and Market $1,078,771 $180,675 $1,592,879 $2,516,080 $2,198,758 $2,312,946 $1,852,610

+ Unit 8 $309,172 $224,629 $304,073 ($74,937) $80,785 $62,353 $20,350

Statistical Model + Unit 5 $615,954 $882,118 $496,845 $180,551 $225,721 $289,806 $344,275

Statistical Model + Units 3, 4 $518,163 $742,836 $418,396 $152,043 $190,081 $244,047 $289,916

Statistical Model + Unit 6 $615,319 $882,118 $496,845 $180,551 $225,721 $289,806 $344,275

Total Savings $3,137,378 $2,912,375 $3,309,037 $2,954,288 $2,921,065 $3,198,957 $2,851,426

Note: Red = Market Hedge and Bundling

14

Page 15: Electric PILOT Workshop February 2013

Bundling and Market Prices

2007 2008 2009 2010 2011

Annual LMP(Market)

Prices $51.26 $48.08 $24.61 $29.01 $27.76

$-

$500,000.00

$1,000,000.00

$1,500,000.00

$2,000,000.00

$2,500,000.00

$3,000,000.00

$3,500,000.00

2006 2007 2008 2009 2010 2011 2012

Bundled Revenue

Bundled Income

Bundled Expense

Effects on bundling as it relates to LMP or Market Prices--HUC generates more MWHR’s during higher market year prices. In addition, Operating Revenue and Operating Income both increase substantially. The graph only reflects plant 1 generation.

15

Page 16: Electric PILOT Workshop February 2013

Bundling and Market Prices

2007 2008 2009 2010 2011

Annual LMP (Market) Prices $51.26 $48.08 $24.61 $29.01 $27.76

0

5000

10000

15000

20000

25000

30000

2006 2007 2008 2009 2010 2011 2012

Bundled Generation

Bundled Generation

MWHRS

HUC generates more MWHR’s during higher market year prices. The graph only reflects plant 1 generation.

16

Page 17: Electric PILOT Workshop February 2013

Market Purchases, Hedged Generation and LMP (Market) Prices

2007 2008 2009 2010 2011

Annual LMP (Market) Prices $51.26 $48.08 $24.61 $29.01 $27.76

0

20000

40000

60000

80000

100000

120000

2006 2007 2008 2009 2010 2011 2012

Hedge

Market Purchases

Market Purchases and Hedged Generation--HUC generates more MWHR’s during higher market year prices. The graph only reflects plant 1 generation.

MWHR

17

Page 18: Electric PILOT Workshop February 2013

Savings due to changing Base Load and Market Purchases—January 2013

$0

$500,000

$1,000,000

$1,500,000

$2,000,000

$2,500,000

$3,000,000

2006 2007 2008 2009 2010 2011 2012

25 MW Base Load

18

Page 19: Electric PILOT Workshop February 2013

Savings due to Unit 8 Scheduled Hedge and Bundling—January 2013

($500,000)

$0

$500,000

$1,000,000

$1,500,000

$2,000,000

$2,500,000

$3,000,000

2006 2007 2008 2009 2010 2011 2012

+ Unit 8

25 MW Base Load

Note: Red = Market Hedge and Bundling 19

Page 20: Electric PILOT Workshop February 2013

Savings due to adding Unit 5 Hedge and Bundling—February 2013

($500,000)

$0

$500,000

$1,000,000

$1,500,000

$2,000,000

$2,500,000

$3,000,000

2006 2007 2008 2009 2010 2011 2012

Statistical Model + Unit 5

+ Unit 8

25 MW Base Load

Note: Red = Market Hedge and Bundling. Years 2006, 2007 and 2008 are higher market years, please note effectiveness of HUC generation during those years.

20

Page 21: Electric PILOT Workshop February 2013

Savings due to Additional Operating Hours Units 3 and 4 Hedge and

Bundling--2014

($500,000)

$0

$500,000

$1,000,000

$1,500,000

$2,000,000

$2,500,000

$3,000,000

$3,500,000

2006 2007 2008 2009 2010 2011 2012

Statistical Model + Units 3, 4

Statistical Model + Unit 5

+ Unit 8

25 MW Base Load

Note: Red = Market Hedge and Bundling. Years 2006, 2007 and 2008 are higher market years, please note effectiveness of HUC generation during those years.

21

Page 22: Electric PILOT Workshop February 2013

Savings due to adding Unit 6 Hedge and Bundling —2015/16

($500,000)

$0

$500,000

$1,000,000

$1,500,000

$2,000,000

$2,500,000

$3,000,000

$3,500,000

2006 2007 2008 2009 2010 2011 2012

Statistical Model+Unit 6

Statistical Model + Units 3, 4

Statistical Model + Unit 5

+ Unit 8

25 MW Base Load

Savings by Market Year with Respect to Integrated Resources Plan and Other Strategies

Note: Red = Market Hedge and Bundling. Years 2006, 2007 and 2008 are higher market years, please note effectiveness of HUC generation during those years.

22

Page 23: Electric PILOT Workshop February 2013

Summary of Savings 2006 2007 2008 2009 2010 2011 2012

25 MW Base Load and Market Purchases $1,078,771 $180,675 $1,592,879 $2,516,080 $2,198,758 $2,312,946 $1,852,610

Savings due to gen. hedge & bundling $2,058,608 $2,731,700 $1,716,158 $438,208 $722,307 $886,011 $998,815

$3,137,378 $2,912,375 $3,309,037 $2,954,288 $2,921,065 $3,198,957 $2,851,426

$0

$500,000

$1,000,000

$1,500,000

$2,000,000

$2,500,000

$3,000,000

$3,500,000

2006 2007 2008 2009 2010 2011 2012

Savings due to gen. hedge & bundling

25 MW Base Load and Market Purchases

Summary--note effectiveness of plant 1 generation hedge and bundling during higher electric market years (years 2006, 2007, and 2008).

23

Page 24: Electric PILOT Workshop February 2013

Question on Power Supply Planning?

24

Page 25: Electric PILOT Workshop February 2013

Problems with PILOT Formula

1. Bundling at Plant 1

2. Bundling at Plant 2

3. Capacity Sales

4. Base Load--Point to Point Energy Sales(Steam Turbine at Plant 2)

5. Roadway Lighting

25

Page 26: Electric PILOT Workshop February 2013

Example July 2011—Bundling Plant 1 July 2011

$/MWHR MWHR Total Cost

Base Load $ 58.02 18,600 $ 1,079,172.00

Market Purchases $ 29.11 7,824 $ 227,755.95

Cost of Unit 8 Scheduled Gen. $ 36.60 2,400 $ 87,840.00

Hedged Gen.--units 3, 4, 5, 6 $ 47.49 3,109 $ 147,649.33

Additional Market Purch. After gen. $ 140.21 17 $ 2,383.62

Total HUC Load and Cost w/o bundling $ 34.88 13,350 $ 465,628.90

Bundled Gen.Revenue $ 67.54 1,751 $ 118,260.86

Bundled Gen Expense $ 47.24 1,751 $ 82,725.00

Bundled Gen Op Income $ 35,535.86

Total HUC Cost less bundling op. income $ 32.22 13,350 $ 430,093.04

Blended Cost for July $ 47.24 31,950 $ 1,509,265.04

MWHR's % Provided

Provided from MRES Base Load Supply 18600 58.22% $ 58.02

Combination of Market & Generation Supply 13350 41.78% $ 32.22

Total HUC retail supply 31950

Note: Red Text is what is affected by any changes made in the PILOT. 26

Page 27: Electric PILOT Workshop February 2013

Bundling Plant 1(Cont’d.) Plant 1 2006 2007 2008 2009 2010 2011 2012

Bundled Revenue $2,256,291 $2,913,863 $2,334,374 $979,575 $1,064,214 $1,154,797 $1,228,410 Bundled Expense $1,464,621 $1,897,578 $1,626,986 $672,975 $718,402 $714,042 $675,311 Bundled Income $791,670 $1,016,285 $707,387 $306,600 $345,812 $440,755 $553,099

Less 5% PILOT $112,815 $145,693 $116,719 $48,979 $53,211 $57,740 $61,420

Applied to stabilize rates $678,856 $870,592 $590,669 $257,621 $292,601 $383,015 $491,679

•During times when HUC needs bundling most are the years HUC is transferring the largest amount to City in the form of PILOT. This reduces the effectiveness of bundling.

27

Page 28: Electric PILOT Workshop February 2013

Bundling Plant 2—Real Time Market Unit 1--Plant 2 2007 2008 2009 2010

Op Revenue $5,977,170 $1,316,210 $1,012,561 $1,304,767

Op Expense $3,579,503 $1,108,139 $632,072 $780,645

Op. Income $2,397,667 $208,071 $380,489 $524,122

Less 5% PILOT $298,859 $65,811 $50,628 $65,238

Applied to Stabilize Rates $2,098,809 $142,261 $329,860 $458,883

•During times when HUC needs bundling most are the years HUC is transferring the largest amount to City in the form of PILOT. This reduces the effectiveness of bundling. •In the above examples, the statistical model for systems control was used. It should be noted the statistical model does not work as effectively on combustion turbines. The model was designed to work for reciprocating engines like those found at plant 1.

28

Page 29: Electric PILOT Workshop February 2013

Bundling Plant 1 + Plant 2 Plant 1 2007 2008 2009 2010 Bundled Revenue $2,913,863 $2,334,374 $979,575 $1,064,214 Bundled Expense $1,897,578 $1,626,986 $672,975 $718,402 Bundled Income $1,016,285 $707,387 $306,600 $345,812

Unit 1--Plant 2 2007 2008 2009 2010 Op Revenue $5,977,170 $1,316,210 $1,012,561 $1,304,767 Op Expense $3,579,503 $1,108,139 $632,072 $780,645 Op. Income $2,397,667 $208,071 $380,489 $524,122

Plant 1 + Plant 2 2007 2008 2009 2010 Op Revenue $8,891,033 $3,650,584 $1,992,136 $2,368,981 Op Expense $5,477,081 $2,735,126 $1,305,047 $1,499,047 Op. Income $3,413,952 $915,459 $687,088 $869,934

Less 5% PILOT $444,552 $182,529 $99,607 $118,449

Applied to Stabilize Rates(Bundling) $2,969,400.66 $732,929.33 $587,481.54 $751,484.76

•Transfer is unstable—a range of approximately $100,000 to $450,000

•The years where HUC needs to apply Op. Income the most to stabilize rates corresponds with the years where HUC is transferring the most. In particular, high market year in 2007, and low market year in 2009.

29

Page 30: Electric PILOT Workshop February 2013

Capacity Sales 2013 2014 2015 2016 2017 2018

Potential Capacity Sales(Op. Revenue) $112,000 $332,000 $572,000 $812,000 $1,052,000 $480,000

Less Transfer to City $5,600 $16,600 $28,600 $40,600 $52,600 $24,000

HUC additional cash flow $106,400 $315,400 $543,400 $771,400 $999,400 $456,000

•City will receive 5% of Operating Revenue, and HUC will realize a significant increase in cash flow. This added cash flow is not applied to further stabilize rates.

•A capacity contract is a wholesale sale with another electric utility, and could be viewed as an option on a plant to produce electrical energy for another electric utility.

30

Page 31: Electric PILOT Workshop February 2013

Base Load--Point to Point Energy Sales(Steam Turbine at Plant 2)

Cost of Electric Production from Unit 1 (Combined Cycle) Plant 2 = Heat Rate x Price of N. Gas + Fixed Cost + Pilot % = 8.84 x 5 + 6.67 + 5%

Heat Rate(Combined Cycle) 8.84

Price of N. Gas--$/MCF 5

Plus Fixed Cost in $/MWHR $6.67

Expense per MWHR $50.87

Add-in 5% transfer $2.54

Total Expense per MWHR $53.41

MRES Agreement as a reference--annualized $/MWHR $49.94

Combined Cycle(MW) 52

Number of Hours per year 8760

Total MWHR's generated annually 455520

•HUC does not have a 5% margin on this type of a transaction. Every one dollar represents $455,520 of annual income. With a 5% transfer, the transfer would be approximately $1,150,000. •With a 5% transfer, it is unlikely that HUC would be able to do this type of a transaction. Consequently, the steam turbine at Plant 2 may become useless to HUC.

31

Page 32: Electric PILOT Workshop February 2013

Roadway Lighting

• Presently HUC provides roadway lighting for

Free to the City. HUC charges the City for roadway lighting, and follows it up with an additional transfer. This is considered Operating Revenue, consequently HUC would pay 5% of something that it is providing for free.

32

Page 33: Electric PILOT Workshop February 2013

Recommendations for Electric Utility

• Change the transfer percentage to 5% of retail operating revenue(metered sales on electric distribution system), do not include wholesale sales (sales for resale). Additionally, do not include roadway lighting.

• The 5% of retail operating revenue will include the electric utility expenses as it relates to Legal, HR, IT, and Roadway Lighting.

• HUC should break out its cost of goods sold(not counting transmission expense?), or power supply expenses into a separate business unit. This would include Sales for Resale—Capacity Sales and also Hedged, and Bundled Electrical Energy Sales.

• A dividend payment based off of Net Income would be made to the City from the new business unit.

• Look into creating an added line item in the budget for all of the other shared services found on the shared service list, and place this under “Other contributions” in the budget. No money would be exchanged, instead this line item would reflect labor, materials, equipment useage, etc. for other items contributed to the City’s operations. At this point, I am not sure how difficult it would be to do this, however, this is certainly something we could explore.

33

Page 34: Electric PILOT Workshop February 2013

Supporting Documents

34

Page 35: Electric PILOT Workshop February 2013

HUC 2006—Market

$/MWHR

$-

$10.00

$20.00

$30.00

$40.00

$50.00

$60.00

$70.00

$80.00

$90.00

Market

Statistical Model+Unit 6

Market Average

Average + Unit 6

Market Risk Mitigation 2006

Average price using a combination of market purchases and HUC generation at plant 1

Average price if all extra needs purchased off market

35

Page 36: Electric PILOT Workshop February 2013

2006 Blended

$-

$10.00

$20.00

$30.00

$40.00

$50.00

$60.00

$70.00

2006 Actual

Statistical Model+Unit 6

2006 Actual Average

Avg + Unit 6

2006 Base Load Contract reduction, Unit 8 scheduled run, Statistical Model being used, Installation of New Unit 5 Unit 3 and 4 added Op. hours Installation of New Unit 6

Note: Prices do not include Transmission expense.

36

Page 37: Electric PILOT Workshop February 2013

HUC 2007—Market

$/MWHR

$-

$10.00

$20.00

$30.00

$40.00

$50.00

$60.00

$70.00

$80.00

$90.00

Market

Statistical Model+Unit 6

Average Market Price

Average + Unit 6

Market Risk Mitigation 2007

Average price if all extra needs purchased off market

Average price using a combination of market purchases and HUC generation at plant 1

37

Page 38: Electric PILOT Workshop February 2013

2007 Blended

$-

$10.00

$20.00

$30.00

$40.00

$50.00

$60.00

$70.00

2007 Actual

Statistical Model+Unit 6

2007 Average

Avg + Unit 6

2007 Base Load Contract reduction, Unit 8 scheduled run, Statistical Model being used, Installation of New Unit 5 Unit 3 and 4 added Op. hours Installation of New Unit 6

Note: Prices do not include transmission expense

38

Page 39: Electric PILOT Workshop February 2013

HUC 2008—Market

$/MWHR

$-

$10.00

$20.00

$30.00

$40.00

$50.00

$60.00

$70.00

$80.00

$90.00

Market

Statistical Model+Unit 6

Average Market Price

Average + Unit 6

Market Mitigation 2008

Average price if all extra needs purchased off market

Average price using a combination of market purchases and HUC generation at plant 1

39

Page 40: Electric PILOT Workshop February 2013

2008 Blended

$-

$10.00

$20.00

$30.00

$40.00

$50.00

$60.00

$70.00

$80.00

2008 Actual

Statistical Model+Unit 6

2008 Average

Avg + Unit 6

2008 Base Load Contract reduction, Unit 8 scheduled run, Statistical Model being used, Installation of New Unit 5 Unit 3 and 4 added Op. hours Installation of New Unit 6

Note: Prices do not include

40

Page 41: Electric PILOT Workshop February 2013

HUC 2009—Market

$-

$5.00

$10.00

$15.00

$20.00

$25.00

$30.00

$35.00

$40.00

$45.00

$50.00

Market

Statistical Model+Unit 6

Average Market Price

Average + Unit 6

Market Mitigation 2009

41

Page 42: Electric PILOT Workshop February 2013

2009 Blended

$-

$10.00

$20.00

$30.00

$40.00

$50.00

$60.00

$70.00

2009 Actual

Statistical Model+Unit 6

2009 Average

Avg + Unit 6

2009 Base Load Contract reduction, Unit 8 scheduled run, Statistical Model being used, Installation of New Unit 5 Unit 3 and 4 added Op. hours Installation of New Unit 6

Note: Prices do not include transmission expense.

42

Page 43: Electric PILOT Workshop February 2013

HUC 2010—Market $/MWHR

$-

$5.00

$10.00

$15.00

$20.00

$25.00

$30.00

$35.00

$40.00

$45.00

Market

Statistical Model+Unit 6

Average Market Price

Average + Unit 6

Market Risk Mitigation 2010 Average price if all extra needs purchased off market

Average price using a combination of market purchases and HUC generation at plant 1

43

Page 44: Electric PILOT Workshop February 2013

2010 Blended

$-

$10.00

$20.00

$30.00

$40.00

$50.00

$60.00

2010 Actual

Statistical Model+Unit 6

2010 Average

Avg + Unit 6

2010 Base Load Contract reduction, Unit 8 scheduled run, Statistical Model being used, Installation of New Unit 5 Unit 3 and 4 added Op. hours Installation of New Unit 6

Note: Prices do not Include transmission

44

Page 45: Electric PILOT Workshop February 2013

HUC 2012—Market

$/MWHR

$-

$5.00

$10.00

$15.00

$20.00

$25.00

$30.00

$35.00

$40.00

$45.00

$50.00

Market

Statistical Model+Unit 6

Average Market Price

Average + Unit 6

Market Mitigation 2012

Average price if all extra needs purchased off market

Average price using a combination of market purchases and HUC generation at plant 1

45

Page 46: Electric PILOT Workshop February 2013

2012 Blended

$-

$10.00

$20.00

$30.00

$40.00

$50.00

$60.00

2012 Actual

Statistical Model+Unit 6

2012 Average

Avg + Unit 6

2012 Base Load Contract reduction, Unit 8 scheduled run, Statistical Model being used, Installation of New Unit 5 Unit 3 and 4 added Op. hours Installation of New Unit 6

Note: Prices do not include transmission expense

46