95
PROJECT NO. -1348 PROPOSED OFFICE BUILDING ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI Page 1/1 BILL No. 1 - PRELIMINARIES Qnty Unit Rate Amount % Comple authorities to accommodate all the required facilities within the allowed limits. Setting up the Site A Allow for providing an office compound item and sites for workshops, plant etc. Use and Protection of the Site B item C item clear of debris and other rubbish and D item to open excavation and other hazards E Allow for providing and maintaining warning item all such places. F item Item The temporary hoarding and the site office size and location shown on dwg is tentative only It is Tenderer's responsibility to confirm the location and the limits of the above In case of the temporary hoarding and the site office are required to be located (partly or fully) beyond the plot limit (i.e on adjacent neighbouring plot etc.), then it is tenderer's responsibility to permission for temporarily usage of the plot(s) for the above purpose from the owner of the Allow for protecting the site during the the work to the entire satisfaction of the Allow for keeping the site and building and adjcent areas affected by the building at completion making good all disturbed works or ground to the entire satisfaction of the Allow for temporary covering and signs, red warning lamps,etc. as necessary Allow for temporary traffic signs as

Electrical

Embed Size (px)

DESCRIPTION

Bill of quantity

Citation preview

Page 1: Electrical

PROJECT NO. -1348PROPOSED OFFICE BUILDING

ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI

Page 1/1

Item BILL No. 1 - PRELIMINARIES Qnty Unit Rate Amount % CompleAmount AED

The temporary hoarding and the site office size and location shown on dwg is tentative only

authorities to accommodate all the required facilities within the allowed limits.

In case of the temporary hoarding and the site office are required to be located (partly or fully) beyond the

plot limit (i.e on adjacent neighbouring plot etc.), then it is tenderer's responsibility to obtain the consent/

permission for temporarily usage of the plot(s) for the above purpose from the owner of the said plot(s).

Setting up the Site

A Allow for providing an office compound itemand sites for workshops, plant etc.

Use and Protection of the Site

B Allow for protecting the site during the course of item

the work to the entire satisfaction of the Engr.

C Allow for keeping the site and building and any item

adjcent areas affected by the building operations

clear of debris and other rubbish and

at completion making good all disturbed works or

ground to the entire satisfaction of the Engineer

D Allow for temporary covering and barricading item

to open excavation and other hazards

E Allow for providing and maintaining warning item

signs, red warning lamps,etc. as necessary in

all such places.

F Allow for temporary traffic signs as necessary item

It is Tenderer's responsibility to confirm the location and the limits of the above with the concerned

Page 2: Electrical

PROJECT NO. -1348PROPOSED OFFICE BUILDING

ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI

Page 1/2

TO COLLECTION (AED)

Item BILL No. 1 - PRELIMINARIES Qnty Unit Rate Amount % CompleAmount AED

Employer's / Engineer's Facilities

[Ref. to Appendix-A to the General Spec

Section 01 'General Items]

Allow for providing the following facilities including

modifying, adapting or relocating to suit the

progress of the works and removing from site

A Offices for the sole use of the Client Rep. and Item 30,534.00 50% 15,267.00

Engineer including stationery, furniture, cleaning

maintenance, and attendance

B Telephone and facsimile for the sole use of

the Engineer including paying all charges for

installation, rental, calls (within UAE) & removal item

C Ditto - Mobile telephone for Resident Engineer item

D Surveying equipment and assistance in

checking and setting out or measuring on site item

E Provide a photocoppier machine for the sole item INCLUDED

use of the Engineer, including all paper,

toner, maintenance etc.

F Provide computers all accessories as specified item

in Appendix -A to the General specification

Section 01 (General Items), complete

G Provide equipment like camera, etc.as specified item

Page 3: Electrical

PROJECT NO. -1348PROPOSED OFFICE BUILDING

ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI

Page 1/3

TO COLLECTION (AED) 30,534.00 15,267.00

Item BILL No. 1 - PRELIMINARIES Qnty Unit Rate Amount % CompleAmt. AED

Contractors Facilities

Allow for providing the following facilities

including modifying, adapting or relocating to

suit the progress of the works and removing

from site

A Offices conference room, sample room, item 153,122.00 50% 76,561.00

stores, messrooms, etc.

B Sanitary facilities item

C Telephones item

D Site first aid item

E Site fire figting equipment item Included

F Site drinking water item

G Temporary hordings item

H Temporary roads, hardstandings, etc. item

Contractors Site Administration

Allow for the following:

I Site administration item 202,704.00 6% 12,162.24

J Supervision and site management item 606,768.00 6% 36,406.08

K Security item 36,800.00 6% 2,208.00

L Safety, health and welfare of workers item 129,917.00 6% 7,795.02

M Transport of workers item 128,800.00 6% 7,728.00

Plant and Equipment

Allow for providing the following:

N Small plant and tools item 522,670.00 2% 10,453.40

O Cranes and lifting equipment item 684,998.00 2% 13,699.96

P Site transport item 118,000.00 6% 7,080.00

Q Any other plant and equipment item

Page 4: Electrical

PROJECT NO. -1348PROPOSED OFFICE BUILDING

ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI

Page 1/4

TO COLLECTION (AED) 2,583,779.00 174,093.70

Item BILL No. 1 - PRELIMINARIES Qnty Unit Rate Amount % CompleAmount AED

Scaffolding

A Allow for providing, erecting and maintaining,

dismantling and clearing away at completion

proper and adequate scaffolding including that

required for Sub-contractors and Specialists &

Sub-contractors nominated by the Client item 144,900.00 -

Setting out and surveying

B Allow for setting out the work and preparing a

levels survey item

Existing services

C Allow for ascertaing the location of all

underground services item

D Allow for protecting all underground services

during the progress of the work item

E The Contractor shall be responsible for any

damage caused to the underground services,

for any costs of repair and for any delays

arising from such damage item

Temporary Services for the Works

Allow for providing the following services for

the works including those required by the

Sub-contractors, paying all charges and for

providing all necessary temporary

installations and removing on completion

Water for the works

F The contractor shall install a separate meter

for water on site and all charges for the

temporary connection and consumption shall

Any costs of importing water by tanker and

storing on site shall be allowed for by the

Contractor as required. item 109,779.00 6% 6,586.74

Electric lighting and power for the works.

G The contractor shall install a separate meter

for electricity on site and all charges for the

temporary connection and consumption shall

Any costs for temporary electricity

generating equipment shall be allowed for

by the contractor item 338,675.00 6% 20,320.50

be paid by the Contractor OR

paid by the Contractor OR

Page 5: Electrical

PROJECT NO. -1348PROPOSED OFFICE BUILDING

ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI

Page 1/5

TO COLLECTION (AED) 593,354.00 26,907.24

Item BILL No. 1 - PRELIMINARIES Qnty Unit Rate Amount % CompleAmount AED

Protection of the Works

A Allow for covering up and protecting the

works from the weather and from dammage by

the Contractors own or other workmen

performing subsequent operations including

providing all necessary dust sheets, barriers

and guard rails and clearing away same

at completion item

B Allow for carefully protecting finished work

including that of Sub-contractors item

C Allow for providing and maintaining warning

signs, red warning lamps and barrycades as

necessary in all such places item

Enclosing site etc.

D Allow for providing any temporary hoardings,

enclosures, gates, entrances, etc. for the

protection of the site, the works and materials

and for alerting and adapting the same as may

be required, removing at completion of the

works and making good all works disturbed item 31,050.00 85% 26,392.50

Local Authority Workmen

E Allow for giving access to workmen employed

by the local or other authorities and providing

them with attendance as required item

Attendance

F Allow for the general attendance of one trade

upon another item

Temporary works

G Allow for furnishing the Engineer with full

particulars, drawings, etc. of all temporary

works necessary for the execution of work item

Page 6: Electrical

PROJECT NO. -1348PROPOSED OFFICE BUILDING

ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI

Page 1/6

TO COLLECTION (AED) 31,050.00 26,392.50

Item BILL No. 1 - PRELIMINARIES Qnty Unit Rate Amount % CompleAmount AED

Samples, Mockups, Tests, etc.

A Allow for providing and submitting to the

Engineer, as he may require, samples of all

materials and goods which are proposed for

incorporation in the works including removal

of the same on completion of the inspection item Included

B Allow for testing materials as required by the

Specifications item 28,750.00 6% 1,725.00

C Allow for providing sample panels of materials

as required including removal of the same on

completion of the inspection item

D Allow for providing mock-ups as required

including as part of work of the same on

completion of the inspection item

As Built Drawings and Manuals

E Allow for providing the Engineer with as-built

drawings and manuals as required by the item 23,000.00 6% 1,380.00

project specifications

Progress Photographs

F Allow for providing monthly sets of

negatives, taken at relevant locations item 1,725.00

G Allow for providing prints from negatives

selected by the Engineer item -

H Allow for providing photographs of the

project at the completion stage taken by

prfessional photographer item -

Notice Boards

I Allow for providing and erecting Two Site

Notice Boards as per the details mentioned

in the project specification item 51,405.00

Clearing Away Rubbish

J Allow for clearing away rubbish at regular intervals

during the progress of works and leaving

the site and perimeter tidy at completion item 99,360.00 6% 5,961.60

Page 7: Electrical

PROJECT NO. -1348PROPOSED OFFICE BUILDING

ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI

Page 1/7

K Cleaning at Completion

Allow for cleaning the entire site including the

building inside and out side and leaving ready

for occupation upon completion item 34,500.00

TO COLLECTION (AED) 238,740.00 9,066.60

Item BILL No. 1 - PRELIMINARIES Qnty Unit Rate Amount % Complete Amt. AED

Condition of Contract

Allow for complying with the Conditions

of Contract as follows:

A Cost of Insurances item 109,250.00 100% 109,250.00

B Cost of Performance Bond item Excluded

C Building Permit fee item 28,750.00 100% 28,750.00

D Fluctuations in cost item -

E Compliance with Statutes, Regulations

(Refer to Conditions of Contract Part II,

Conditions of Particular Application,

page CC/2.4, Clause 26.02) item -

Sub-contractors - Nominated/ Domestic

F Allow for provision, erection, maintenance and

to the nominated and domestic sub-contractors

including provision of drainage and sewrage

connections to the sewer system/septic tank

and provision of separate line of telephone,

power, water, etc. as required for the office

accommodation, but excluding all fitting-outs of

accommodation,such as Air-conditioners,

Furniture, etc. [Also, main contractor to fully

take over all responsibilities for the nominated

and domestic Sub-contractors]

[The payment of all charges for the telephone,

water, power,etc. for the site accommodation

to be mutually agreed between the Main

Contractor, and the Sub-contractor] item Excluded

G Allow for provision, erection, maintenance and

subsequent removal (at completion of works)

of all temporary buildings, storage areas, etc.

togather with hard-standings as required for the

nominated and domestic Sub-contractors item Excluded

H Allow for lifting/lowring of all plant,

subsequent removal of free site accommodation

Page 8: Electrical

PROJECT NO. -1348PROPOSED OFFICE BUILDING

ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI

Page 1/8

equipment and materials as required by

all the Sub-contractors item Excluded

TO COLLECTION (AED) 138,000.00 138,000.00

Item BILL No. 1 - PRELIMINARIES Qnty Unit Rate Amount % Complete Amt. AED

Any other items

A

1. Hire plot for temporary site setup 322,546.00 6% 19,352.76

2. Site distribution gang 89,700.00 6% 5,382.00

3 -

TO COLLECTION (AED) 412,246.00 24,734.76

COLLECTION AMOUNT

Page no.

1/1 - -

1/2 30,534.00 15,267.00

1/3 2,583,779.00 174,093.70

1/4 593,354.00 26,907.24

1/5 31,050.00 26,392.50

1/6 238,740.00 9,066.60

1/7 138,000.00 138,000.00

1/8

Allow for all costs, expences, etc. details of which must be set out below and extended separately by the Contractor, incurred in carrying out the requirements of the contract and not otherwise included

Page 9: Electrical

PROJECT NO. -1348PROPOSED OFFICE BUILDING

ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI

Page 1/9

1/8 412,246.00 24,734.76

BILL NO.1 PRELIMINARIES

TOTAL AMOUNT CARRIED TO SUMMARY (AED) 4,027,703.00 414,461.80

Page I/S

Page 10: Electrical

PROJECT NO. -1348PROPOSED OFFICE BUILDING

ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI

Page 2/10

Item BILL No. 2 - SHORING Qnty Unit Rate Amount % CompleAmount AED

Shoring

A Item 23,000.00 100% 23,000.00

B Item

C Item

Permanent shoring system as shown on dwg

D Secant pile 1000mm dia. 133 m 22100 2,939,300.00 35 773,500.00

E Guniting for the secant piling. Item 387,203.00

F Item

G 122 m2 112 13,664.00

H Item 64,400.00

TO COLLECTION (AED) 3,427,567.00 796,500.00

The work in this 'Sub- structure' section is to include all items upto the ground floor level including the ground floor slab.

Allow for design, shop drawings, monitoring, etc. of the shoring system.

Allow to obtain Dubai Municipality approval of the shoring design incliding paying all fees and charges as required.

Allow for all co-ordinations with Municipality and execution of all works as per the 'Notes' stated on Shoring detail drawings.

Shoring system with Secant Piling wall including RCC coping beam with all form work and steel reinforcement, Steel section H-piles, pre-cast concrete planks,tie-back anchoring, strutting etc as required in full compliance with statutory regulations and site conditions.

Tender must provide the total quantity (in linear meter) and the unit rate (AED per lin. M) for the Shoring Works.

Stiffener column / beam including formworks, reinforcement steel, strutt, etc., complete.

200mm thick solid concrete block wall with smooth cement plaster.

Waterproofing membrane and protection board are measured elsewhere in this bill section.

Removal of the above shoring system between ground level and -2.00m level as shown on dwg including removal of the steel I-section, pre-cast concrete panels, etc.

Page 11: Electrical

PROJECT NO. -1348PROPOSED OFFICE BUILDING

ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI

Page 2/11

Item BILL No. 2 - SHORING Qnty Unit Rate Amount % CompleAmount AED

Earthwork

A Allow for trial pits to locate any existing services. Item 3,857.00 100% 3,857.00

BItem 8,802.00 100% 8,802.00

C

11669 m3 32 373,408.00 13% 48,543.04

D m3 N/A

E 11669 m3 13 151,697.00 13% 19,720.61

F Compact all surfaces in the bottom of excavations 1078 m2 7 7,546.00

G 188 m3 91 17,108.00

Dewatering

H Item

INCLUDED

J Item

K Item 497,703.00

Preparation of site for construction work including levelling (cutting & filling), compaction, as necessary, etc.complete.

Excavate between existing ground level and bottom of blinding for raft slab/etc( The excavated material shall be stored temporarily at near-by site as directed by the Engineer being separated as suitable material for back filling and unsuitable material for disposal)

Backfiling using the excavated suitable fill material as directed by the Engineer

Disposal of excavated surplus material to tip approved by the Authorities and the Engineer

Filling with imported material to make up levels all in accordance with drawings and specifications

Allow to obtain Dubai Municipality and all other concerned authority approval for discharging the dewatering including paying all fees and charges as required

Allow for liaison and co-ordination with Employer, Engineer and all authorities as required, for the dewatering system.

Dewatering the wole site during excavation and through construction till sufficient counter weight against buoyancy uplift is achieved ( Refer to structural drawings)

Page 12: Electrical

PROJECT NO. -1348PROPOSED OFFICE BUILDING

ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI

Page 2/12

TO COLLECTION (AED) 1,060,121.00 80,922.65

Item BILL No. 2 - SHORING Qnty Unit Rate Amount % CompleAmount AED

A Concrete blinding 75mm thick 1078 m2 37 39,886.00

B 50mm thick protection screed to membrane 936 m2 22 20,592.00

C Columns 54 m3 688 37,152.00

D Walls 255 m3 688 175,440.00

E Basement walls 528 m3 710 374,880.00

F Raft slab 976 m3 585 570,960.00

G Footing beam/other foundations beams m3 N / A

H Base slab of lift pit/ water tank/ etc. m3

INCLUDED

J Walls of lift pit/ water tank/ etc m3

Plain in situ concrete, grade C20 with durability requirements as in Specification Section 3

Reinforced in situ concrete, grade C60 with durability requirements as in Specifications Section 3

Reinforced in situ concrete, grade C50 with durability requirements as in Specification Section 3

Page 13: Electrical

PROJECT NO. -1348PROPOSED OFFICE BUILDING

ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI

Page 2/13

TO COLLECTION (AED) 1,218,910.00 -

Item BILL No. 2 - SHORING Qnty Unit Rate Amount % CompleAmount AED

A Basement- 3 - Slab & beams 76 m3 537 40,812.00

B Basement-2 - Slab & beams 137 m3 537 73,569.00

C Basement-1 - Slab & beams 137 m3 537 73,569.00

D Ground slab,beams,Ramp etc 431 m3 537 231,447.00

E Staircases 24 m3 551 13,224.00

Formwork

F To sides of columns/walls 3467 m2 131 454,177.00

G To sides of raft slab/other slabs 84 m2 56 4,704.00

H To sides of footing/other foundation beams m2 N / A

J To sides and soffits of beams/lintels/sills 402 m2 73 29,346.00

K To sides of base slabs of lift pit/water tank/etc m2 INCLUDED

L To soffit of water tank m2 INCLUDED

M To stringers and soffits of stairs 124 m2 59 7,316.00

N To sides and soffits of suspended slabs/ramps 3139 m2 73 229,147.00

P To sides of grades slab,steps,ramps,etc. 35 m2 56 1,960.00

Reinforcement

Q High tensile steel bar of various diameters 413400 kg 6.1 2,521,740.00

Reinforced in situ concrete, grade C45 with durability requirements as in Specification Section 3

Page 14: Electrical

PROJECT NO. -1348PROPOSED OFFICE BUILDING

ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI

Page 2/14

TO COLLECTION (AED) 3,681,011.00 -

Item BILL No. 2 - SHORING Qnty Unit Rate Amount % CompleAmount AED

Waterproofing as per drawings/specifications

A1 936 m2 51 47,736.00

A2 1523 m2 51 77,673.00

A3 Protection board 6mm thick 1523 m2 29 44,167.00

A4 127 m 29 3,683.00

A5 Waterstop/ junction hose system at all concrete joints 1202 m 49 58,898.00

A6 Allow for junction,corner,etc,details as required item 5,750.00

A7 m2 N / A

B1 120 m2 79 9,480.00

B2 Ditto - any other areas as required m2 INCLUDED

Water tank

C1 439 m2 104 45,656.00

C2 GRP ladder to underground water tanks 2 no 1725 3,450.00

C3 2 no 1035 2,070.00

Hollow Concrete Blockwork

D1 200mm thick m2

Waterproofing membrane laid on blinding below raft slab,downstand beam, etc.

Waterproofing membrane laid on vertical surface of water tank walls, holding tank walls,basement walls,footing beam,etc.

25x25mm Groove with sealant to terminate waterproofing membrane.

Reinforced fair face blockwork to receive waterproofing membrane

Waterproofing membrane and protection board over ground slab to receive interlocking tiled paving area

GRP lining to all internal surfaces of under ground water tank (slabs,walls,soffit)

Fully sealed water/ air tight cover complete to u/gwater tank

All necessary accessories like valves,fittings etc to the underground water tank are measured in bill part " Plumbing & Drainage installation"

Page 15: Electrical

PROJECT NO. -1348PROPOSED OFFICE BUILDING

ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI

Page 2/15

N / A

D2 100mm thick m2

TO COLLECTION (AED) 298,563.00

Item BILL No. 2 - SHORING Qnty Unit Rate Amount % CompleAmount AED

Column Protectors

A 93 No 72 6,696.00

B item 34,745.00

D 150mm high upstand kerb fixed to floor slab 39 m 73 2,847.00

E 39 m 18 702.00

F 30 m2 67 2,010.00

G 54 No 210 11,340.00

H Item 5750 5,750.00

I Item 17,250.00

High density neoprene corner protection 100mm high anchored with mechanical fasteners, complete as per as per drawing

Road marking on parking and driveway at basements, ramps and ground floor including all parking separation lines, arrows,hatching,etc, complete as shown on drawings

(External roadmarkings are measured under bill for "External Works"

Kerbing and tiling at basement and ground floor parking /driveways

Two coats of chlorinated rubber based quick drying paint in approved colours ( black/yellow/white) to upstand kerbs

60mm thick, interlocking concrete paving blocks,shape,size and colour as approved, laid in multi-colour and pattern on and including 50mm thick sand bed and sub-base

Wheel stopper 150x150x1650 long Hydraulically pressed kerb towed to RC slab.

High duty polystyrene ( Density not less than 40kg/m3) factory cut to suit filling in substation all to DEWA requirements including form trenches,chequer plate,steel joisnts as required PVC sleeves, etc.

Epoxy painted removable chequered steel plate cover plate cover along with supporting angle at substation trenches as per DEWA apecifications

Page 16: Electrical

PROJECT NO. -1348PROPOSED OFFICE BUILDING

ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI

Page 2/16

TO COLLECTION (AED) 74,644.00

Item BILL No. 2 - SHORING Qnty Unit Rate Amount % CompleAmount AED

Sundries

A Anti termite treatment Item 3,054.00

B 1030 m2 4 4,120.00

C Damp proof course to all block wall ( as required) 54 m2 8 432.00

D m2

E Item 2,300.00

F Allow for expansion joint including cover. Item 2,300.00

1000 Gauge Polythene water barrier membrane, one layer

Two coats of approved bituminous coating on concrete/ blockwork surfaces directly contracting with soil.

Allow for all joints of construction,control,surface,etc.as required and complete as shown on drawings.

Page 17: Electrical

PROJECT NO. -1348PROPOSED OFFICE BUILDING

ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI

Page 2/17

TO COLLECTION (AED) 9,152.00

Item BILL No. 2 - SHORING Qnty Unit Rate Amount % CompleAmount AED

Any other items

A

1. Circular column guard 12 no. 367 4,404.00

2. Wall guard for ramp 220 m 153 33,660.00

3 Compacted sand filling 14 m3 44 616.00

TO COLLECTION (AED) 38,680.00

COLLECTION AMOUNT AMOUNT

Page no.

2/1 3,427,567.00 796,500.00

2/2 1,060,121.00 80,922.65

2/3 1,218,910.00 -

2/4 3,681,011.00 -

2/5 298,563.00 -

2/6 74,644.00 -

2/7 9,152.00 -

Any other items not included above but considered to have a monetary value by the Contractor are to be listed and priced below :

Page 18: Electrical

PROJECT NO. -1348PROPOSED OFFICE BUILDING

ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI

Page 2/18

2/8 38,680.00 -

BILL NO.2 SUB-STRUCTURE

TOTAL CARRIED TO SUMMARY (AED) 9,808,648.00 877,422.65

Page - 2/S

Page 19: Electrical

PROJECT NO. -1348PROPOSED OFFICE BUILDING

ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI

Page 2/19

Amount AED

Page 20: Electrical

PROJECT NO. -1348PROPOSED OFFICE BUILDING

ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI

Page 2/20

Amount AED

Page 21: Electrical

PROJECT NO. -1348PROPOSED OFFICE BUILDING

ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI

Page 2/21

Amount AED

Page 22: Electrical

PROJECT NO. -1348PROPOSED OFFICE BUILDING

ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI

Page 2/22

Amount AED

Page 23: Electrical

PROJECT NO. -1348PROPOSED OFFICE BUILDING

ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI

Page 2/23

Amount AED

Page 24: Electrical

PROJECT NO. -1348PROPOSED OFFICE BUILDING

ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI

Page 2/24

Amount AED

Page 25: Electrical

PROJECT NO. -1348PROPOSED OFFICE BUILDING

ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI

Page 2/25

Amount AED

Page 26: Electrical

PROJECT NO. -1348PROPOSED OFFICE BUILDING

ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI

Page 2/26

Amount AED

Page 27: Electrical

PROJECT NO. -1348PROPOSED OFFICE BUILDING

ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI

Page 2/27 BOQ(1/8)

Item Bill No. 3 Qnty Unit Rate Amount % Complet

A Columns 184 m3 688 126592

B Walls 504 m3 688 346752

C Beams 187 m3 537 100419

D Stairs 73 m3 545 39785

E Swimming Pool base slab

F Walls for swimming pool

G Lintels / sills 9 m3 993 8937

H Suspended conventional slab (As shown in Dwgs) 1064 m3 537 571368

I Parapet walls, coping, counter, etc., 128 m3 565 72320

J 50 m3 398 19900

Formwork

K To columns 1237 m2 127 157099

L To sides and soffits of beams 1059 m2 73 77307

M To walls 3613 m2 100 361300

N To stringers and soffits of stairs 337 m2 59 19883

O To vertical sides of parapets, coping, counter etc., 1416 m2 59 83544

P To base slab / walls of swimming pool m2 0

TO COLLECTION 1,985,206.00

Reinforced in situ concrete, grade C60 with durability requirements as in Specifications Section 3

Reinforced in situ concrete, grade C45 with durability requirements as in Specification Section 3

Screed in fill to utilities, toilets & baths, etc to match adjacent raised floor area.

Page 28: Electrical

PROJECT NO. -1348PROPOSED OFFICE BUILDING

ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI

Page 2/28 BOQ(1/8)

BILL NO. 3

SUPERSTRUCTURE

A To sides and soffits of lintel / sill

B To horrizontal soffit of suspended slabs

C Allow for all recesses, grooves and other labours to formwork

Reinforcement

D High tensile steel bar of various diameters

Sands on roof for A/C units and water tank areincluded in builder's work for Mechanical Installation and Plumbing & Internal drainage work respectivly

E High Duty Polystyrene

(Density not less than 40kg/m3 factory cut to suit)

F Light weight screed infill (as required)

G Lintels/ sills

H Suspended conventional slab (As shown in Dwgs.)

I Parapet walls, coping, counter, etc

J

Formwork

K To columns

L To sides and soffits of beams

M To walls

N To stingers and soffits of stairs

O To vertical sides of parapets, coping, counter etc

P To base slab/ walls of swimming pool

Screed in fill to utilities, toilet & baths, etc. to match adjacent raised floor area

Page 29: Electrical

PROJECT NO. -1348PROPOSED OFFICE BUILDING

ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI

Page 2/29 BOQ(1/8)

A To sides and soffit of lintel/ sill 136 m2 114 15504

B To horizontal soffit of suspended slabs 4010 m2 73 292730

C item 2875

Reinforcement

D High tensile stell bar of various diameters 299100 kg 6.2 1854420

E High Duty Polystrene m2

Density not less than 40k/m3 factory cut to suit)n/a

F Light weight screed infill (as required) m3

Waterproofing

G 458 m2 30 13740

H Water proofing to airwells, balconies & planters 28 m2 30 840

J item 20636

Insulation (ref. drawing of wall sections)

K 975 m2 56 54600

L m2 included

Sundries

M item 5750

N item 5750

P Allow for expansion joint including cover item 5750

TO COLLECTION 2,272,595.00

BILL NO. 3

Allow for all recesses, grooves and other labours to formwork

Strands on roof for A/C units and water tank are included in Builder's work for Mechanical Installation and Plumbing & Internal drainage works, reqpectively

Water proofing to slabs in kitchens, toilets and bathrooms

Water proofing to external walls behind cladding & glazing

Extended polystyrene insulation to internal wall/beam/ slab soffit

50mm thick black mineral fibre insulation mechanically anchored to wall at spandrel panel

Wall ties 250mm long one end cast into concrete and other end built into joint of blockwork

Allow for wall/ slab opening for all services ducts/ pipe, etc.

Page 30: Electrical

PROJECT NO. -1348PROPOSED OFFICE BUILDING

ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI

Page 2/30 BOQ(1/8)

SUPERSTRUCTURES

Any Other Items

A

1

2

3

COLLECTION

Page 3/1 1,985,206.00

Page 3/2 0

Page 3/3 2,272,595.00

CARRIED TO SUMMARY 4,257,801.00

Any other items not included above but considered to have a monetary value by the Contractor are to be listed and priced below :

Page 31: Electrical

PROJECT NO. -1348PROPOSED OFFICE BUILDING

ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI

Page 2/31 BOQ(1/8)

BILL - Post tensioning Wroks to Concrete

Post Tensioning: Bonded type

A Item 28,750.00

B Post-tensioning works for slabs (Super-structure) Item 232,639.00

C Post-tensioning works for beams (Super-structure) Item INCLUDED

D Allow for producing as built drawings Item 5,750.00

Any Other Items

E

1

2

3

CARRIED OUT TO SUMMARY 267,139.00

Supply and install tendons with all accesoriez for installation including anchoring, stressing, grouting, supervision by specialised Engineers, design of all post-tensioned slabs, beams and associated works, submission of detailed drawings and calculation

Structural design must satisfy minimum loading criteria specified on darwings and actual loading for critical areas as well as the slab thickness and other minimum conventional reinforcement specified in the structural drawings/ specification

Submittal of shop drawings with supporting design calculations

Beamsand slabs upto and including the ground floor slab is considered under "Sub-structure" and above ground floor slab is considered under "Super-structure"

Any other items not included above but considered to have a monetary value by the Contractor are to be listed and priced below:

Page 32: Electrical

PROJECT NO. -1348PROPOSED OFFICE BUILDING

ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI

Page 2/32 BOQ(1/8)

Amount AED

Page 33: Electrical

PROJECT NO. -1348PROPOSED OFFICE BUILDING

ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI

Page 2/33 BOQ(1/8)

BILL NO. 4

BLOCKWORK

A 200mm thick 228 m2 128 29,184.00

B 250mm thick 244 m2 147 35,868.00

Light weight blockwork (Internal partitions)(Block density not exceeding 850kg/m3)

C 100mm wall 494 m2 81 40,014.00

D 200mm wall 2839 m2 88 249,832.00

E 250mm wall m2 N/A

F 100mm wall m2

G 200mm wall m2

H 100mm thick 157 m 15 2,355.00

J 200mm thick 772 m 17 13,124.00

K 250mm wall 289 m2 19 5,491.00

Sundries

L Item 2,300.00

M Item 2,300.00

N Item 2,300.00

TO COLLECTION (AED) 382,768.00

Autoclaved Aerated Concrete (AAC) light weight block work fully complied with British codes and approved by Dubai Municipality to external walls

Allow for filling hollow blockwork wall solid with concrete at vertical and horizontal abutments and around openings

12mm thick compressible joint filler between top of blockwork wall and concrete structure

Allow for forming openings for doors, windows, etc in blockwork including all details at jambs, sills and heads

Allow for forming expansion joints with Flexel board and mastic seal

Allow for the protection of all of the works in this section

Page 34: Electrical

PROJECT NO. -1348PROPOSED OFFICE BUILDING

ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI

Page 2/34 BOQ(1/8)

BILL NO. 4

BLOCKWORK

Any Other Items

1. 300mm thick Autoclave block 283 m2 166 46,978.00

2. 400mm thick Light weight block 11 m2 225 2,475.00

3. Dry wall partition 290 m2 230 66,700.00

4. Fire sealant 1248 m 14 17,472.00

TO COLLECTION (AED) 133,625.00

COLLECTIONPage

4/1 382,768.00

4/2 133,625.00

Any other items not included above but considered to have a monetary value by the Contractor are to be listed and priced below :

Page 35: Electrical

PROJECT NO. -1348PROPOSED OFFICE BUILDING

ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI

Page 2/35 BOQ(1/8)

Bill No.4 BLOCK WORKTOTAL CARRIED TO SUMMARY 516,393.00

Page 36: Electrical

PROJECT NO. -1348PROPOSED OFFICE BUILDING

ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI

Page 2/36 BOQ(1/8)

BILL NO. 5

ROOFING

Membrane Roofing

A m2

B m2

C m2

D m2

E m2

F m

G Dressing roofing system to rainwater outlets Item

Sundries

H Item

J Allow for protection of all the works in this section Item

BILL NO. 5

ROOFING

Any Other Items

Light weight concrete infill (density 600kg/m3) min. thick 40mm, max thick 150mm

4mm thick torch applied waterproofing membrane to roof and rainwater channel as specified in Particular Specification

50mm (minimum) thick extruded polystyrene rigid insulation density35kg/m3

Non woven fabric mesh/ building paper/ 1000 gauge polythene separation layer as approved

600x600x50mm precast plain cement concrete tiles with expansion joints at 3000mm centres both ways laid in and including 30mm thick cement sand bedding

Perimeter detail including skirting tile, flashing, mastic fill, sealant with backup rod, groove, fillet at corner, protection board, etc around parapet wall/ airwell/ services

Rain water drain system installation is measured under bill section 'Plumbing & Drainage'

Allow for all opening in roof slab and wall/ roof for services inlets and outlets

Page 37: Electrical

PROJECT NO. -1348PROPOSED OFFICE BUILDING

ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI

Page 2/37 BOQ(1/8)

A

1

2

3

Any other items not included above but considered to have a monetary value by the Contractor are to be listed and priced below :

Page 38: Electrical

PROJECT NO. -1348PROPOSED OFFICE BUILDING

ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI

Page 2/38 BOQ(1/8)

BILL NO. 6

CARPENTARY AND JOINERY

Refer to dwgs for Schedule of Doors

A1 Wooden Door - 05 (1000 x 2200mm) No

A2 Wooden Door - 06 (800 x 2200mm) No

A3 Wooden Door - 07 (900 x 2200mm) No

A4 Wooden Door - 07A (900 x 2200mm) NO

A5 Wooden Door - 08 (1100 x 2200mm) No

A6 Wooden Door - 09 (900 x 2200mm) No

Supply only hardware set

B1 Ironmongery for all doors PC supply only rate AED 350.00/door No

B2 Door closer for all doors PC supply only rate AED 350.00/door No

Note :

BILL NO. 6

CARPENTARY AND JOINERY

A1 Base Unit m

A2 Wall unit m

Door & frame sets, complete including architraves, sub-frames, fix only hardware set, all finishes, etc., as required and as shown on drawings and specification

Supply only hardware set is included as BOQ item below with PC supply rates.

Engineer may delete door closer fully or partly as per his discretion and hence, the actual quantity of the door closer used on site shall be considered and the contract sum shall be adjusted accordingly

Supply and fix Kitchen/pantry units with marble/granite worktop including 100mm high plinth

Page 39: Electrical

PROJECT NO. -1348PROPOSED OFFICE BUILDING

ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI

Page 2/39 BOQ(1/8)

A3

(PC supply only sink & mixer AED 650.00/set) No

A4 30mm thick marble/ granite worktop m

PC supply only rate of stone AED 450.00/m

A5

(PC supply only rate of stone AED 45.00/m) m

A6 100mm high plinth for base unit m

B For the toilets and bathrooms(PC supply only of stone AED 350.00/m2) m2

Lockers to change room

D

(TRESPA or approved equal) No

BILL NO. 6

CARPENTARY AND JOINERY

Any Other Items

Extra over item kitchen cabinet base unit for supply and fix sink, mixer, trap, other fixing accessories, etc. including connections, complete

Extra over item above for 20mm thick marble/ granite splash back

Vanity Wash Basin Marble/ Granite Counter Top

Wash basin natural stone counter top, down fascia, splash back including cutting hole for the wash basin, mastic sealing, hardwood frame, MS angle frame & supports, etc., complete

Mirrors for above vanity tops are measured under bill section 'Glazing'

3 Tier 300 x 400 x 300 deep High Pressure Laminated (HPL) lockers complete with doors, hardware, accessories, etc. for complete operations.

Any other items not included above but considered to have a monetary value by the Contractor are to be listed and priced below :

Page 40: Electrical

PROJECT NO. -1348PROPOSED OFFICE BUILDING

ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI

Page 2/40 BOQ(1/8)

BILL NO. 7

METAL WORK

Hollow metal (HM) doors

A1 Door no. HM-02, size 1000 x 2200mm No

A2 Door no. HM-03, size 1000 x 2200mm No

A3 Door no. HM-04, size 1000 x 2000mm No

A4 Door no. HM-05, size 1500 x 2200mm No

A5 Fire Rated Steel Door - 01 (1100 x 2200mm) No

Supply only hardware set for Steel doors

B1 No

PC supply only rate AED 350.00/doorNo

B2 Ironmongery for stairs fire escape doorsPC supply only rate AED 2,000.00/door No

Aluminium Doors and Windows(Refer drawings & specifications)

C1 GL - 01 No

C2 GL-02 No

C3 GL-03 No

C4 GL- 04 No

C5 GL-05 No

C6 GL- 06 No

C7 GL- 07 No

C8 GL- 08 No

C9 GL- 09 No

C10 GL- 10 No

C11 GL- 11 No

C12 GL- 12 No

Door & frame sets, complete inlcluding architraves, sub-frames, fixing, all finishes etc. as required and as shown on drawing and specification

Ironmongery for all Hollow metal doors except stairs fire escape doors

Page 41: Electrical

PROJECT NO. -1348PROPOSED OFFICE BUILDING

ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI

Page 2/41 BOQ(1/8)

BILL NO. 7

METAL WORK

Aluminium Doors and Windows [Cont'd](Refer drawings & Specifications)

A1 GL-13 No

A2 GL-14 No

A3 GL-15 No

A4 GL-16 No

A5 GL-17 No

A6 GL-18 No

A7 GL-19 No

A8 GL-20 No

A9 GL-21 No

A10 GL-22 No

A11 GL-23 No

A12 GL-24 No

A13 GL-25 No

A14 GL-26 No

A15 GL-27 No

A16 GL-28 No

A17 GL-29 No

Page 42: Electrical

PROJECT NO. -1348PROPOSED OFFICE BUILDING

ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI

Page 2/42 BOQ(1/8)

A18 GL-30 No

A19 GL-31 No

A20 GL-32 No

A21 GL-33 No

A22 GL-34 No

A23 GL-35 No

A24 GL-36 No

A25 GL-37 No

BILL NO. 7

METAL WORK

Aluminium Doors and Windows [Cont'd](Refer drawings & Specifications)

A1 GL-38 No

A2 GL-39 No

A3 GL-40 No

A4 GL-41 No

A5 GL-42 No

A6 GL-43 No

A7 GL-44 No

Louvers(Refer drawings & specifications)

B1 LV-01 No

B2 LV-02 No

B3 LV-03 No

B4 LV-04 No

B5 LV-05 No

B6 LV-06 No

Page 43: Electrical

PROJECT NO. -1348PROPOSED OFFICE BUILDING

ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI

Page 2/43 BOQ(1/8)

Curtain Walls(Refer drawings & specifications)

C1 CW-01 No

C2 CW-02 No

C3 CW-03 No

C4 CW-04 No

C5 CW-05 No

C6 CW-06 No

BILL NO. 7

METAL WORK

Cat Ladder(Refer detailed drwg. A-451)

A Cat ladder from roof to upper roof m

A2 Cat ladder from ground to first floor m

Staircase HandrailsRefer to drawing nos. A300 to A303

For staircase - 1 m

B Fixed on the wall

For staircase - 2C1 Fixed on the floor m

C2 Fixed on the wall m

For staircase - 3 m

D Fixed on the floor

(refer drwg. A-450)

E1 To Pump Room m

E2 To Commercial Area m

F m2

Super durable polyester powder coated aluminium windows, including timber sub-frames, supply and fix all associated ironmongery, weathersealing, flyscreens and fixing in position as required

50mm Powder coated stainless steel pipe handrail

100 x 20mm PESDF coated continuous aluminium box section

Page 44: Electrical

PROJECT NO. -1348PROPOSED OFFICE BUILDING

ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI

Page 2/44 BOQ(1/8)

Canopy/Pergola

(To be design by the Contractor)

G1 To Ground Floor Area Item

G2 To Roof Area Item

Extra over above item G1 & G2

H1 To Ground Floor Area m2

H2 To Roof Area m2

BILL NO. 7

METAL WORK

Any Other Items

A

1

2

3

Steel Canopy, complete including all supports of steel structure, etc. complete

6mm thick pre finished aluminium composite panel cladding over galvanized steel skeleton structure anchored and braced to main structure

Any other tiems not included above but considered to have a monetarey value by the Contractor are to be listed and priced below :

Page 45: Electrical

PROJECT NO. -1348PROPOSED OFFICE BUILDING

ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI

Page 2/45 BOQ(1/8)

BILL NO. 8

FLOOR, WALL AND CEILING FINISHES

Insitu Finishes

A 7363 m2 40 294,520.00

B Ditto to ceilings 895 m2 43 38,485.00

C 1095 m2 49 53,655.00

D Ditto to parapets, etc 437 m2 49 21,413.00

E Item

INCLUDED

F Item

TO COLLECTION (AED) 408,073.00

Cement sand plaster (1:4) 15mm thick to concrete and blockwork walls in two coat work (internally)

Cement sand plaster (1:4) 20mm thick to walls in two coat work (externally)

Allow for expanded metal lathing 300mm wide at junctions of concrete and blockwork

Allow for the provision of all grooves, rain water drips and the like as necessary, in plastering

Page 46: Electrical

PROJECT NO. -1348PROPOSED OFFICE BUILDING

ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI

Page 2/46 BOQ(1/8)

BILL NO. 8

FLOOR, WALL AND CEILING FINISHES

Floor FinishesA 12 m2 129 1,548.00

(PC rate for supply only Dhs. 35.00/m2)

B 11 m2 129 1,419.00

(PC rate for supply only Dhs. 35.00/m2)

C1 Raised flooring system, complete 2498 m2 173 432,154.00

(PC rate for supply only Dhs. 150/m2)

C2 Extra over ablove item C1 Carpet tile 2483 m2 104 258,232.00

F-03, with matching colour grout on raised floor

(PC rate for supply only Dhs.90.00/m2)

D 400 m2 67 26,800.00

E 127 m2 68 8,636.00

F 126 m2 55 6,930.00

G 1740 m2 68 118,320.00

Rate for Floor/ Wall/ Stair/ Step/ etc tiles shall include for jointing and pointing with an approved grout as required and bed with cement sand mortar/ cement based adhesive as approved

Contractor shall allow for plastic edge strips for all ceramic tiles external corners and horizontal edges with matching colours

F-01, 300 x 300mm Heavy duty unglazed ceramic tiles with matching colour

F-02, 200x 200 unglazed granite tiles with matching colour grout

F04, 75mm thick Sand cement screed with self leveling compound Nito Floor Top or similar equivalent approved to received finishes by Tenant.

F05, Concret slab power floated finish with hardener and sealer coat

F06, 75mm thick sand cement screed with epoxy resin based coating

F07, 100% solid epoxy flexible wear coat system, seeded into epoxy with manufacturer approved aggregate (i.e. size, washed, dried & bagged), having a minium hardness of six (6) on the Moh scale, at the recommended coverage. The system should have A-1 fire

Page 47: Electrical

PROJECT NO. -1348PROPOSED OFFICE BUILDING

ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI

Page 2/47 BOQ(1/8)

TO COLLECTION (AED) 854,039.00

BILL NO. 8

FLOOR, WALL AND CEILING FINISHES

Floor Fhishes (Cont'd)

A

648 m2 107 69,336.00

B 869 m2 75 65,175.00

C 104 m2 115 11,960.00

D 48 m2 96 4,608.00

E 119 m2 231 27,489.00

(PC rate for supply only Dhs. 120.00/m2)

F 139 m2 549 76,311.00

(PC rate for supply only Dhs. 350.00/m2)

G 195 m2 129 25,155.00

(PC rate for supply only Dhs. 35.00/m2)

F08, Multi-layered solvent free, rapid curing, 100% soldi flexible epoxy coating system. The system will consist of a primer coat, elastomeric tough seamless waterproofing membrane based on Du Pont Neoprene and abrasion resistance traffic bearing top coa

The system should have A-1 fire rating ASTM E86 or equivalent approved coverage

F-10, Non Slip epoxy resin coating over precast concrete steps/ landing applied to a thickness of 3mm including non slip aggregate

F11, 300 x 300mm precast white cement Terrazzo tiles with Italian chips laid on sand cement mortar bed

F-13, 60mm thick precast interlock plain cemnet concrete tiles for pedestrain paved areas

F-15, 400x 400 porcelain tiles with matching colour grout

F-19, 20mm thick granite slab cut to size with mathcing colour granite border to form pattern

F-20, 300 x 300 ceramic tiles with matching colour grout

Page 48: Electrical

PROJECT NO. -1348PROPOSED OFFICE BUILDING

ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI

Page 2/48 BOQ(1/8)

TO COLLECTION (AED) 280,034.00

BILL NO. 8

FLOOR, WALL AND CEILING FINISHES

Skirting Finishes

A 1398 m 39 54,522.00

(PC rate for supply only Dhs.15.00/m)

B 83 m 39 3,237.00

(PC rate for supply only Dhs. 15.00/m)

C 931 m 13 12,103.00

D 657 m 13 8,541.00

Statement Only

F14, GRP lineron floor slab of water tank Statement Only

Statement Only

S-01, 100mm high porcelain tile skirting to match the floor tiles.

S-02, 100mm high Terrazzo tiles skirting matching to floor

S-03, 100mm high epoxy resin coating - type and colour to match floor

S-04, 150mm high epoxy resin coating - type and colour to match floor

F12, 600x 600 x 50mm precast plain cement concrete tiles laid in and including cement sand bedding on roof top is measured under bill sention "Roofing"

(including wall and ceiling) is measure under bill section "Sub-structure"

Waterproof membrane laid over structural slab with protection board over & on sides is measured under bill section "Sub-structure"

Page 49: Electrical

PROJECT NO. -1348PROPOSED OFFICE BUILDING

ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI

Page 2/49 BOQ(1/8)

TO COLLECTION (AED) 78,403.00

BILL NO. 8

FLOOR, WALL AND CEILING FINISHES

Marble Threshold

A Width to match 100mm wide wall (PC supply only AED 100.00/m) 39 m 151 5,889.00

B Width to match 200mm wide wall (PC supply only AED 200.00/m) 20 m 278 5,560.00

Sill Cladding (Ref. Wall Sections)

C 20mm thick polished granite sill at typical floors

(PC supply only granite rate AED 200.00/m2 198 m2 381 75,438.00

-

D 56 m 23 1,288.00

E Marble cladding arround lift wall 95 m 571 54,245.00

30mm thick polished granite/ marble threshold to approval full width to all wet areas with rounded edges and anchored with stainless steel dowels

3mm thick stainless steel strip between different floor finishes as required

Page 50: Electrical

PROJECT NO. -1348PROPOSED OFFICE BUILDING

ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI

Page 2/50 BOQ(1/8)

TO COLLECTION (AED) 142,420.00

BILL NO. 8

FLOOR, WALL AND CEILING FINISHES

Wall Finishes

All paint finishes to wall are measured under Bill section 10

A

(PC rate for supply only Dhs. 40.00/m2) 1335 m2 97 129,495.00

B

(PC rate for supply only Dhs.600.00/m2) 767 m2 682 523,094.00

C

(Refer drawing A-310) 133 m2 748 99,484.00

W-13, 200 x 300mm glazed ceramic wall tiles with matching colour grout

W-17, 20mm thick Granite/ Marble stone cut to size anchored to wall in matching colour with stainless stell mechanical fasteners up to 100mm above the suspended ceiling.

Decorative Wooden Panel as per Engineer's approval

Page 51: Electrical

PROJECT NO. -1348PROPOSED OFFICE BUILDING

ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI

Page 2/51 BOQ(1/8)

TO COLLECTION (AED) 752,073.00

BILL NO. 8

FLOOR, WALL AND CEILING FINISHES

Suspended Ceilings

A 53 m2 110 5830

B 66 m2 92 6072

D m2 N/A

F 215 m2 75 16125

G 2555 m2 156 398580

Suspension systems shall be galvanised steel and cilings shall include painting where required by the Engineer

All paint finishes as required in the following suspended ceiling system are measured in the Bill section '10'

SC01, 600 x 600mm pre finished decorative perforated gypsum tiles with black acoustic backing and recessed edge suitable for black reveal Fine Line grid suspension system, all surrounded by 12.5mm thick gypsum board bulkhead (25mm lower than ceiling tiles

SC02, 6mm thick calcium silicate board ceiling painted with paint type similar to adjacent surface

SC03, 1200 x 600mm pre finished gypsum tiles with recessed exge suitable for semi concealed (recessed) suspension system all around, surrounded by 12.5mm thick gypsum board bulkhead (25mm lower than ceiling tiles) painted with paint type-3

SC04, 600 x 600mm vinyl faced moisture resistant gypsum tiles with aluminium back foil and exposed grid suspension system.

SC05, 600 x 600mm pre finished aluminium tiles with black reveal Fine Line grid suspension system

Page 52: Electrical

PROJECT NO. -1348PROPOSED OFFICE BUILDING

ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI

Page 2/52 BOQ(1/8)

H 343 m2 87 29841

TO COLLECTION (AED) 456,448.00

BILL NO. 8

FLOOR, WALL AND CEILING FINISHES

Sundries

A Item

INCLUDED

B Item

C Item 2,300.00

D Item INCLUDED

E Shadow gap 2203 m 14 30,842.00

F Bulk Head 628 m 87 54,636.00

SC10, 600 x 600mm pre finihsed gypsum tiles with recessed edge suitable for semi concealed (recesssed) suspension system all around, surrounded by 12mm thick gypsum board bulkhead(25mm lower than ceiling tiles) painted with paint type-3

Allow for cutting all holes for light fittings, etc. including any extra hangers, supports, and the like (ceiling)

Allow for all cutting and fitting around openings and fittings and narrow widths, etc. (flooring & wall tiling)

600 x 600mm properietary system access panel with concealed hinges/ spring latch, finish to match gypsum ceiling

Allow for protection of all of the works in this section

Page 53: Electrical

PROJECT NO. -1348PROPOSED OFFICE BUILDING

ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI

Page 2/53 BOQ(1/8)

TO COLLECTION (AED) 87,778.00

BILL NO. 8

FLOOR, WALL AND CEILING FINISHES

Any Other Items

A 0

1

2

3

TO COLLECTION (AED)

Page 8/9

COLLECTION

Page no.8/1

408,073.00

Any other tiems not included above but considered to have a monetarey value by the Contractor are to be listed and priced below :

Page 54: Electrical

PROJECT NO. -1348PROPOSED OFFICE BUILDING

ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI

Page 2/54 BOQ(1/8)

8/2 854,039.00

8/3 280,034.00

8/4 78,403.00

8/5 142,420.00

8/6 752,073.00

8/7 456,448.00

8/8 87,778.00

8/9

BILL NO. 8 FLOOR,WALL AND CEILING FINISHES

TOTAL CARRIED TO SUMMARY 3,059,268.00

Page 55: Electrical

PROJECT NO. -1348PROPOSED OFFICE BUILDING

ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI

Page 2/55 BOQ(1/8)

0

Page 56: Electrical

PROJECT NO. -1348PROPOSED OFFICE BUILDING

ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI

Page 2/56 BOQ(1/8)

BILL NO. 9

GLASS

Mirrors (Belgium glass)

A Above wash basin pedestal type No

B Above wash basin vanity type m2

C Miscellaneous glazing as required Item

D Item

Any Other Items

E

1

2

3

Note : Glazing to aluminium door and window units is included with the relevant units, Mirror size shall be 600 x 900mm high for pedestal type basin and full width x 1200mm high for vanity type basins

6mm thick polished plate glass mirrors with bevelled edges and 12mm thick marine plywood (exposed edges sealed with silicon or plastic strip colour to match with adjacent wall finish) backing plugged and screwed to walls with chromium plated dome headed m

Allow for protection of all of the works in this section

Any other tiems not included above but considered to have a monetarey value by the Contractor are to be listed and priced below :

Page 57: Electrical

PROJECT NO. -1348PROPOSED OFFICE BUILDING

ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI

Page 2/57 BOQ(1/8)

BILL NO. 10

PAINTING AND DECORATING

TO WALL

A m2

B m2

C m2

D m2

E m2

F m2

TO CEILING

G m2

H m2

TO FALSE CEILINGI m2

J Refer to false ceiling SC02 m2

Prepare and apply paint on smooth cemnt render, internally

W01, Acrylic base Emulsion paint (Paint Type-3) on smooth cand cement plaster

W02, Oil based /Alkyd enamel paint (Paint Type-4)on smooth cand cement plaster

W03, Semi Epoxy paint (Paint Type-2) over fair faced concrete wall

W05, Full Epoxy paint (Paint Type-1) over smooth sand cement plaster

W06, Non fungus Acrylic paint (Paint Type-5) over fair faced concrete wall

W15, Fairface concrete/flush pointed block wall wity tyrolene coat

C-04, Alkyd enamel paint over sand cement plaster

C-06, Smooth finished sand cement plaster painted with paint type-02

Refer to false ceiling SC01, SC03, SC07 & SC10 Acrylic Emulsion paint (Paint Type-3)

Page 58: Electrical

PROJECT NO. -1348PROPOSED OFFICE BUILDING

ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI

Page 2/58 BOQ(1/8)

BILL NO. 10

PAINTING AND DECORATING

EXTERNAL DECORATIONSRefer to elevation & section drawings

A m2

B

(PC rate for supply only of tiles Dhs.450.00/m2) m2

Sundry

C Item

BILL NO. 10

PAINTING AND DECORATING

A Any Other Items

1

Full Epoxy Paint System (Paint Type-1) rendering on sand cement plaster, colour & textured

30mm thick Natural stone cladding anchored with stainless steel fasteners as required

Allow for the protection of all the work in this section

Any other tiems not included above but considered to have a monetarey value by the Contractor are to be listed and priced below :

Page 59: Electrical

PROJECT NO. -1348PROPOSED OFFICE BUILDING

ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI

Page 2/59 BOQ(1/8)

2

3

BILL NO. 10A

BUILDER'S WORK

A For nominated Lift installation sub-contract works

Also include for steel supports if necessary Item

B For the installation of Signage internal & external Item

C For the installation of Cleaning cradle system Item

D For the Mechanical works Item

E For the Electrical works Item

F For the Plumbing works Item

Allow for all Builder's work in connection with the Provisional sum items including co-ordination/liasion with all concerned authorities and sub-contractors and all general and special attendance as required

Buidler's work for the installations of following works, which are neither described above nor anywhere in the BOQ, which includes the following but not limited to Excavation, Trenching, Backfilling, Compaction, Concrete blocks, Thrust block, finishes, Pr

Page 60: Electrical

PROJECT NO. -1348PROPOSED OFFICE BUILDING

ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI

Page 2/60 BOQ(1/8)

BILL NO. 10A

BUILDER'S WORK

A Any Other Items

1

2

3

Any other tiems not included above but considered to have a monetarey value by the Contractor are to be listed and priced below :

Page 61: Electrical

PROJECT NO. -1348PROPOSED OFFICE BUILDING

ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI

Page 2/61 BOQ(1/8)

BILL NO. 11

RAINWATER INSTALLATION

A No.

B No.

C m

D Item

E Item

F No.

BILL NO. 11

BASEMENT RAINWATER DRAINAGE

A Basement floor stormwater pipe line to sump Item

PLUMBING & INTERNAL DRAINAGE INSTALLATIONS

Dressing roofing system to sump/ outlet, etc, is within the scope of main contract

Roof rainwater outlet including grating, short pipes and bends through slab/ wall, connection to 100mm dia. Rainwater downpipes, etc.

Outlet in balcony for 100mm dia pipe including grating and connection to floor drain

100mm uPVC rainwater pipe including brackets and supports

Allow for cast rainwater pipe into concrete/ blockwork

Allow for bends, cleanouts, outlets, etc. to rainwater pipe

Powder coated aluminium cover to rainwater outlet

PLUMBING & INTERNAL DRAINAGE INSTALLATIONS

uPVC pipes including fittings, pipe supports, brackets, rodding eyes, pipe access, access panels and the like.

Page 62: Electrical

PROJECT NO. -1348PROPOSED OFFICE BUILDING

ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI

Page 2/62 BOQ(1/8)

B Catch basin No.

C At ramp m

D At Garbage room m

E No.

F Item

G Item

BILL NO. 11

SANITARY INSTALLATION

A Pedestal type wash basin + mixer No.

B Vanity type wash baisn + mixer No.

Heavy duty polymer concrete drainage channel, comprising 300x50mm thick heavy duty cast iron grating, including all necessary civil works, etc., complete including silt bucket as shown on drwgs.

Sump pit including heavy duty type cover, sand trap, etc., complete

Sump pump comrising two pumps (1D+1SB) 4.2 LPS @ 10m head including automatic switchover facility, high and low level float switches, all interconnecting pipework, valves, fittings, controls and control panel, etc. complete

Pumping main from sump pump to waste line including all bends, clean outs, fittings, etc. complete

PLUMBING & INTERNAL DRAINAGE INSTALLATIONS

(Supply of sanitary wares and accessories is included as provisional sum)

Fix only sanitary ware, taps and accessories including waste outlets, traps, connections to hot and cold water supplies and wastes, compelete

Page 63: Electrical

PROJECT NO. -1348PROPOSED OFFICE BUILDING

ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI

Page 2/63 BOQ(1/8)

C No.

D Urinal No.

E Item

BILL NO. 11

SANITARY INSTALLATION

Pipes and Fittings, etc

A Item

B Waste pipe with bend to wash basin/ sink No.

C Floor trap No.

D Gully trap No.

E Item

Manhole

F No.

G No.

WC seating type including low level flushing cistern, compelte

Fix only approved accessories including forming recesses and making good as required

Robe hook, Toilet roll holder, Soap holder, Towel rail, Towel ring, Tissue holder, forming recesses and making good as required

PLUMBING & INTERNAL DRAINAGE INSTALLATIONS

uPVC waste, soil and vent pipes including fittings, pipe supports, brackets, rodding eyes, access panels and the like

Allow for connections to underground drainage pipes

Pressure breaking MH with heavy duty type cover, complete

MH 600x600mm with heavy duty type cover, complete

Page 64: Electrical

PROJECT NO. -1348PROPOSED OFFICE BUILDING

ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI

Page 2/64 BOQ(1/8)

H No.

J Allow for connection to DM sewer system Item

HOT AND COLD WATER INSTALLATION

Equipment

K Item

L -Ditto- to roof tanks Item

BILL NO. 11

Roof mounted water tank

A No.

B Item

Ditto - (F.I.C), DI cover medium duty recess type with 6mm thick GRP push fit sealing plate

Provide all connections to concrete underground water tank to incoming and outgoing service, neck, vent, access cover and frame, etc., as required

Ladder & air-tight covers to u/g water tank are measured under bill 'Sub-structure'

PLUMBING & INTERNAL DRAINAGE INSTALLATIONS

HOT AND COLD WATER INSTALLATION (Cont'd)

Roof mounted approved cold water storage tank GRP sectional insulated panel type all connections to incoming services, interconnection, overflow, drain and supply high and low level float switches, etc

Size 2 compartments 3.0 x 10.60 x 2.5m h. with 70m3 water capacity

Transfer pump set comprising two nos. (1W+1SB), Each 250 USGPM @ 9 bar including automatic switchover facility, float switches, all interconnection pipework, valves and fittings, controls and control panel, etc,

Page 65: Electrical

PROJECT NO. -1348PROPOSED OFFICE BUILDING

ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI

Page 2/65 BOQ(1/8)

C Item

D Item

E Item

F Item

BILL NO. 11

Pipes, Fittings, etc.

A Item

B Item

C Item

D Allow for all other valves as required Item

Water supply booster pump set two nos. (1W+1SB) 7L/S @ 2 Bar. Each with controls and pane, 100 GPM pr. Vessel, by-pass line and aluminium enclosure including all interconnecting pipework, valves and fittings

Supply of water meter is not in the scope and part of DEWA connection. However all liasions, coordinations and all buider's works in connection with the DEWA connection are in the scope

Valve pit, valves, etc., at site entry including collect and fix water meter

Main supply from meter to underground tank and to roof tank

Collect and fix all water meter complete and valves, etc., for individual areas/ flats

PLUMBING & INTERNAL DRAINAGE INSTALLATIONS

HOT AND COLD WATER INSTALLATION (Cont'd)

CWS supply pipe to individual apartments and other areas as required

Cold/ Hot water distribution pipework with cross linked polethylene pipe & conduit sytem, all fixing accessories, etc. complete to all fittings such as sanitary wares, water heater, etc

Insulated copper hot water supply pipework including fittings, supports, brackets, etc, from water hearters to supply points

Page 66: Electrical

PROJECT NO. -1348PROPOSED OFFICE BUILDING

ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI

Page 2/66 BOQ(1/8)

E Bib taps No.

F Water heater, 30 litre capacity No.

G Water heater, 50 litre capacity No.

Sundries

H Allow for suitable protection to CWS pipes Item

J Item

K Item

L Item

M Item

BILL NO. 11

Any Other Items

A

1

2

3

UV protection and heat insulation for weather exposed piping

Allow for cleaning, sterilizing and disinfecting the plumbing and internal drainage installation as specified

Allow for testing and commissioning the plumbing and internal drainage installation

Allow for producing as built drawings and manuals as specified

PLUMBING & INTERNAL DRAINAGE INSTALLATIONS

Any other items not included above buty considered to have a monetary value by the Contracted are to be listed and priced below :

Page 67: Electrical

PROJECT NO. -1348PROPOSED OFFICE BUILDING

ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI

Page 2/67 BOQ(1/8)

BILL NO. 12

ELECTRICAL INSTALLATION

A Item

B1 L.V Panel - 1 No.

B2 L.V Panel - 2 No.

B3 Capacitor bank 350 K.V.A.R No.

LIGHTING AND POWER

C1 SMDB - ESS No.C2 SMDB - B No.C3 SMDB - COM No.C4 SMDB - CHILLERS No.C5 SMDB - CH No.C6 SMDB - LL No.

C10 SMDB - T1 No.C11 SMDB - T2 No.C12 SMDB - T3 No.C13 SMDB - T4 No.C14 SMDB - T5 No.C15 SMDB - T6 No.C16 SMDB - T7 No.

Include for the supply & complete installation as detailed in the Specifications and on the Drawings and to the complete satisfaction and approval of the Engineer and all concerned Statutory Authorities and under the following sections.

Allow for all liasions, coordinations and all builder's works in connection with the DEWA connection including collect and install KWH meter, etc.

LV panels including breakers, terminations, isolators, all necessary cabling including cable ladder,/ conduits, cleats all fittings trace and trunking supports emergency push buttons, current transformers, power factor correctors, accessories as per DEWA

Sub main distribution boards including MCCB's breakers, Terminations, isolators supports, accessories, etc., complete

Page 68: Electrical

PROJECT NO. -1348PROPOSED OFFICE BUILDING

ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI

Page 2/68 BOQ(1/8)

BILL NO. 12

ELECTRICAL INSTALLATION (Cont'd)

A1 DB-LL2-ESS No.A2 DB-LL1-ESS No.A3 DB-R-ESS No.A4 DB-B-ESS No.A5 DB-S/S No.A6 DB-G No.A7 DB-LL1 No.A8 DB-MAIN TELE No.A9 DB-ROOF TELE No.

A10 DB-LL2 No.A11 DB-COM-1 No.A12 DB-COM-2 No.A13 DB-B1 No.A14 DB-B2 No.A15 DB-B3 No.A16 DB-GYM No.A17 DB-PM No.A18 DB-T1-OF1 No.A19 DB-T1-OF2 No.A20 DB-T1-OF3 No.A21 DB-T2-OF1 No.A22 DB-T2-OF2 No.A23 DB-T2-OF3 No.

B Isolators including accessories Isolators Item

BILL NO. 12

ELECTRICAL INSTALLATION (Cont'd)

A Cable to all mechanical/ electrical equipments Item

Distribution boards including breakers, terminations, isolators, supports, accessories, capacitor banks, built in meters, etc., complete

Page 69: Electrical

PROJECT NO. -1348PROPOSED OFFICE BUILDING

ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI

Page 2/69 BOQ(1/8)

Supply & install

B Item

C From LV panels to SMDB's Item

D From SMDBs to DB's Item

Light Fittings

E Item

No.F1 Lighting point, internal No.F2 Lighting point, external No.F3 One gang one way light switch No.F4 One gang two way light switch No.F5 Two gang one way light switch No.F6 Three gang one way light switch No.F7 Four gang one way light switch No.F8 Grid switch unit No.F9 Time delay switch No.

F10 13 amp single switched socket outlet No.F11 - Ditto - weather proof No.F12 13 amp double switched socket outlet No.F13 15 amp single switched socket outlet No.F14 15 amp flex outlet No.F15 20 amp double pole switch with neon indicator No.F16 Call bell indicator No.F17 Bell push button No.F18 Floor box No.

BILL NO. 12

Lighting protection system and structural bounding complete

Cables for Sub main distribution boards and distribution boards

The supply of light fittings is included as a Provisional Sum

Fix only light fittings as specified and as shown on drawings including supports, fixings, terminations, connections, brackets, etc

Lighting/ General power installation including supply and fix switches/ sockets, wiring, ladders, ducts/conduits, cleats, trays, trunking, cable trays, fittings, accessories, connections, etc., all as necessary, compelete

Page 70: Electrical

PROJECT NO. -1348PROPOSED OFFICE BUILDING

ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI

Page 2/70 BOQ(1/8)

ELECTRICAL INSTALLATION

STRUCTURED CABLING SYSTEM

A1 Item

A2 Item

A3 Allow for all cable tray for Voice/ Data cables Item

A4 Allow for Voice/ Data cable trunking Item

A5 Item

A6 Item

A7 Lead-in-conduits as required Item

A8 Item

G.S.M

B1 Item

B2 Cable trays Item

B3 Allow for Earthing system, complete Item

B4 Item

Supply and installation of Structured Cabling is including as Provisional sum

Voice/ Data outlet points, junction boxes, under-ground trunking & conduits to approval

Voice/ Data conduiting from the master line jack unit to all other outlets by a tele-communication authority approved contractor as per Specification

Allow for all ducts for incoming telephone cable to Etisalat's spec. & detail

Allow for all other necessary underground ducts and conduits with draw wires

Allow for Telephone manholes and earthing complete as required

All conduits, supports, containments and Electrical works as per Tele-Communication Authority (Etisalat, etc.) requirements

Allow for connections to air conditioning, drain equipment etc.

Page 71: Electrical

PROJECT NO. -1348PROPOSED OFFICE BUILDING

ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI

Page 2/71 BOQ(1/8)

BILL NO. 12

ELECTRICAL INSTALLATION

CATV System

A

Item

B Item

Builder's work onlyC Item

Fuel Storage Tank and Fuel Filling SystemD Item

E Item

F Item

Containment only (including all builder's work)

Supply and install conduits/ cable trays as per drawings with draw wires, and all related civil works to CATV system

Supply and installation of MATV/SMATV system is included as Provisional sum

Containment only (including all builder's work)

Supply and install conduits with draw wires and all builder's work to MATV/SMATV system

Supply and installation including testing & commissioning of Generator is included as Provisional sum

Allow for all builder's work as required for the complete gernerator installation including its unloading, temporary stroring, placement & positioning, supply & fix of all cabling, piping, ductwork, acoutstic treatment, pedestals, etc.

Allow for supply and install Fuel Storage Tank and Fuel Filling System for the above mentioned Generator

Supply and installation of intercom system is included as Provisional sum

Containment only (including all builder's work)

Supply and install conduits with draw wires and all builder's work to the intercom sytem

Gate barriers (supply & fix is measured in Bill section 'External Works')

Containment only (including all builder's work)

Supply and install conduits with draw wires and builder's work to Gate barriers

Page 72: Electrical

PROJECT NO. -1348PROPOSED OFFICE BUILDING

ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI

Page 2/72 BOQ(1/8)

BILL NO. 12

ELECTRICAL INSTALLATION

Sundries

A Allow for Earthing system, complete Item

B Clean Earth Item

C Item

D Item

E Item

F Item

BILL NO. 12

ELECTRICAL INSTALLATION

Any Other Items

A

1

2

3

Allow for connections to air conditioning equipment, fans, water, heaters, etc

Allow for producing as built drawing and manuals as specified

Allow for third party testing and commissioning the electrical installation

Allow for the proctection of all the work in this section

Any other items not included above but considered to have a monetary value by the Contractor are to be listed and priced below :

Page 73: Electrical

PROJECT NO. -1348PROPOSED OFFICE BUILDING

ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI

Page 2/73 BOQ(1/8)

BILL NO. 13

MECHANICAL INSTALLATION

AIR-CONDITIONING & VENTILATION

Chillers

A No

B Item

C Item

Chilled Water Pressurisation Unit - 1Set

D Item

Chemical Dosing Unit

E Item

Fresh Air Supply

F Item

All external A/C units to be isolated from roof structure by approved vibration isolation material

Air-Conditioning - as specified and as shwon on drawings

Water chiller units CH! & CH2 cooling capacity 94 TR

Pumps - including all valves, pressure guage, flexible connection, etc., compelte

Primary chilled water pumps 3 nos.(2W + 1SB) capacity 226 GPM@ 100ft head (exact head to be determined by the Contractor and to Engineer's approval)

Secondary chilled water pumps 2 nos. (1W+1SB) capapcity 451GPM @ 100ft head (exact head to be determined by the Contractor and to Engineer's approval)

Automatic package unit comprising of 2 nos. feed pump ses (duty + standby), feed tank and 2 nos. expansion vessel (unit capacity to be calculated by Contractor and approved by Engineer)

Chemical dosing unit including sensors, and controllers

Fresh Air Handling Unit including run around coil heat exchanger, heat pipe, filters, all control & fire dampers, ductwork, VCD, grillers, etc., to all floors, complete (FAHU 1)

Page 74: Electrical

PROJECT NO. -1348PROPOSED OFFICE BUILDING

ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI

Page 2/74 BOQ(1/8)

BILL NO. 13

MECHANICAL INSTALLATION

AIR-CONDITIONING & VENTILATION

A1 Basement floor -3 Item

A2 Basement floor -2 Item

A3 Basemnet floor - 1 Item

A4 Ground floor Item

A5 Floor - 1 Item

A6 Floor - 2 Item

A7 Floor - 3 Item

A8 Floor - 4 Item

A9 Floor - 5 Item

A10 Floor - 6 Item

A11 Floor - 7 Item

A12 Roof Floor Item

Chilled water system air-conditioning including air handiling units, fan coil units, chilled water piping, all valves, all ducting, grilles, diffusers, etc., complete to the following area

Page 75: Electrical

PROJECT NO. -1348PROPOSED OFFICE BUILDING

ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI

Page 2/75 BOQ(1/8)

BILL NO. 13

MECHANICAL INSTALLATION

AIR-CONDITIONING & VENTILATION

A Car Park (Basement - 3) ItemUnit : EF - 1&2

B Car Park (Basement - 2) ItemUnit : EF - 1&2

C Laundry (Basement - 1) ItemUnit : EF - 1&2

D Guard Room (Ground floor) ItemUnit : EF - 1

E Garbage Room (Ground floor) ItemUnit : EF - 2

F Toilet (Ground floor) ItemUnit : EF-3

G Roof floor ItemUnit : EF-1Unit : SMK-1

Staircase Pressurisation Fans ItemH SPF - 1 & 2

BILL NO. 13

MECHANICAL INSTALLATION

Builder's Work

A

Exhaust air systems to the following including exhaust fans, all ducting, grilles, diffusers, etc., as required complete

Allow for all builders work in connection with the mechanical installation including but not limited to the following :

a) Concrete stand/ foundation for A/C units including anti-vibration pads, springs

b) Forming opening in slab for SA/RA duct/ refrigernat pipes, etc.

Page 76: Electrical

PROJECT NO. -1348PROPOSED OFFICE BUILDING

ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI

Page 2/76 BOQ(1/8)

d) Walkovers over pipting, ducting as required e) Inertia bases for pumpsf) Floating floor for chillers Item

Sundries

B Item

C Item

D Item

E Item

F Item

G Item

BILL NO. 13

MECHANICAL INSTALLATION

Any Other Items

A

1

2

3

c) Painting of all equipment, duct work and accessories

Allow for all control panels, thermostats, controls, etc

Allow for necessary connections, terminations control wiring, etc. complete

Allow for condensate drain pipework, fittings, insulation, 'U' traps and connections to discharge into the nearest floor trap from all A/C equipments

Allow for testing and commissioning the air conditioning & ventilation installation

Allow for protection of all of the works in this section

Allow for any acoustic treatment to chillers, surroundings, other equipment, ducts, etc.

Any other items not included above but considered to have a monetary value by the Contractor are to be listed and priced below :

Page 77: Electrical

PROJECT NO. -1348PROPOSED OFFICE BUILDING

ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI

Page 2/77 BOQ(1/8)

BILL NO. 14

FIRE ALARM

A Repeater panel No.

B Fire alarm control panel No.

C interfacing unit No.

D Smoke detector No.

E Heat detector No.

F Fire voice evacuation speaker No.

G Fire alarm electric sounder No.

H Fireman Telephone No.

J -Ditto- weatherproof No.

K Break glass call bell unit No.

L Item

Supply and Fix Emergency Lighting

M Emergency light fittings No.

N Emergency light fitting with EXIT sign No.

P Emergency light fitting with EXIT + arrow sign No.

Q Central emergency battery cabinet No.

R Any Other Items

1

2

3

Fire alarm installation including all wiring, conduits, connections and the like

Allow for all interconnecting wiring, conduits, etc. for the system

Any other items not included above but considered to have a monetary value by the Contractor are to be listed and priced below :

Page 78: Electrical

PROJECT NO. -1348PROPOSED OFFICE BUILDING

ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI

Page 2/78 BOQ(1/8)

BILL NO. 15

FIRE PROTECTION

Extinguishers

A No.

B No.

C 5.0kg automatic dry powder fire extinguisher No.

Landing valve/ FHR/ Fire extinguisher cabinet

D No.

E - Ditto - surface mounted type No.

BILL NO. 15

FIRE PROTECTION

Wet Riser/ Sprinkler

A Fire Hose reel No.

B Landing valve with hose, etc. No.

C Item

D Item

4.5kg dry powder wall mounted hand operated extinguisher

5.0kg CO2 wall mounted hand operated extinguisher

Stainless steel mirror finish recessed type cabinet for FHR, Fire extinguishers and LV

Wet riser pipework system complete including all valves, flow switches, etc., as required, completed

Sprinkler pipework system complet including all valves, flow switches, etc., as required, complete

Page 79: Electrical

PROJECT NO. -1348PROPOSED OFFICE BUILDING

ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI

Page 2/79 BOQ(1/8)

E Item

F Sprinkler, pendent/ upright type Item

Breeching inlets (Dry Riser)

G Item

H Item

Sundries

J Item

K Item

L Item

BILL NO. 15

FIRE PROTECTION

Any Other Items

A

1

2

3

Fire Protection pump set 3 Nos. (1 electric + 1 deisel + 1 jockey) main pump 750 GPM @ 9.6 Bar, Jockey 40 GPM @@ 9.6 Bar including fuel storage tank, pipework, valves, connections, automatic control panel, controls, cabling, pressure and flow switches, fl

Twin Inlet breaching point complte with recessed decorative mirror finish stainless steel cabinet, complete

Breeching inlet pipework system including all valves as required, complete

Allow for all builders work in connection with the Fire Proetection Installation

Allow for testing and commissioning the fire protection installation

Allow for producing as built drawings and manuals

Any other items not included above but considered to have a monetary value by the Contractor are to be listed and priced below :

Page 80: Electrical

PROJECT NO. -1348PROPOSED OFFICE BUILDING

ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI

Page 2/80 BOQ(1/8)

ItemBILL NO. 16

GARBAGE DISPOSAL No.

Garbage Chute/ container trolley(Refer drwg.A-345)

A

B Supply and install Garbage bin trolley,capacity 2.50m3 each

Garbage chute complete as per drawing comprising chute vent, axial blowing exhauster, access door, draft control flap, flughing spray head, loose linen intake door at each floor, Chute tube, supporting frames, automatic brushing device, etc., complete

Page 81: Electrical

PROJECT NO. -1348PROPOSED OFFICE BUILDING

ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI

Page 2/81 BOQ(1/8)

BILL NO. 17 m3

EXTERNAL WORKS m3

PAVING m3

A Excavate oversite to reduce levels

B Backfill with selected excavated material

C Remove surplus excavated material from site m

D m

Kerbs m

E 150 x 305mm. Upstand kerb

F 150 x 225mm, Flush kerb

G

BILL NO. 17

EXTERNAL WORKS

Footpaths

A m2

Imported fill in making up levels compacted in layers

Precast hydraulically pressed concrete kerb with foundation and haunching, mortar including all necessary excavation, disposal and backfilling

Two coats of chlorinated rubber based quick drying paint in approved colours (black/yellow/white) to upstand kerbs

150mm thick aggregate road base, compacted to minimum CBR 80%, MDD 95%

Page 82: Electrical

PROJECT NO. -1348PROPOSED OFFICE BUILDING

ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI

Page 2/82 BOQ(1/8)

B m2

C 50 mm thick crushed sand bed, compacted m2

D

E Item

F Item

G

General

H Item

J Item

Electricity Operated Gate Barrier

K1

K2

60mm thick, interlocking concrete paving blocks, shape, size and colour as approved, laid in multi-colour and pattern on an includin 50mm thick sand bed.

150mm thick sub base type II, compacted to minimum CBR 30%, MDD 95%

150mm thick aggregate road base, compacted to minium CBR 80%, MDD 100%

Interlocking pavers, 80mm thick laid on land including 50mm thick sand bed in multi-colour and pattern to approval

Allow to all necessary works at existing road edge including saw cutting etc., to Municipality approval, as required

Allow to match new paving upto existing and form a neat, level joint

Road marking to external parking and driveway including all parking separation lines, arrows, hatching, etc., complete as shown on drawings and specifications

Electricity operated remote controlled/ card operated barrier full width across driveway, complete as shown on dwg. (Manufacturer's details and shop drawings to approval)

Gate barrier system at the ground floor entrance to and from the basement floor parking complete

Supply of remote control handsets OR electronic cards to Engineer's approval - (Total no. of parking + extra 10nos.)

Page 83: Electrical

PROJECT NO. -1348PROPOSED OFFICE BUILDING

ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI

Page 2/83 BOQ(1/8)

BILL NO. 17

EXTERNAL WORKS

Any Other Items

A

1

2

3

Amount Contractor's Total(AED) Mark-up (AED)Amount (AED)

50,000.00

200,000.00

600,000.00Provisional Sums

Item 350,000.00

1 Supply only Sanitary ware, Mixers, Accessories 20,000.00

2 Supply only Light Fittings 400,000.00

3 Passenger Lifts (2nos) 250,000.00

4 Supply & install cleaning Cradle system 15,000.00

5 20,000.00

6 Supply & install Structured Cabling System 2,000,000.00

7

Any other items not included above but considered to have a monetary value by the Contractor are to be listed and priced below :

Supply & install MATV/ SMATV system with cabling

Supply, install, testing & commissioning of Generator

Page 84: Electrical

PROJECT NO. -1348PROPOSED OFFICE BUILDING

ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI

Page 2/84 BOQ(1/8)

8 Supply & install Building Directory

9 Supply & install Internal and External Signage

10 Contingency