PROJECT NO. -1348PROPOSED OFFICE BUILDING
ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI
Page 1/1
Item BILL No. 1 - PRELIMINARIES Qnty Unit Rate Amount % CompleAmount AED
The temporary hoarding and the site office size and location shown on dwg is tentative only
authorities to accommodate all the required facilities within the allowed limits.
In case of the temporary hoarding and the site office are required to be located (partly or fully) beyond the
plot limit (i.e on adjacent neighbouring plot etc.), then it is tenderer's responsibility to obtain the consent/
permission for temporarily usage of the plot(s) for the above purpose from the owner of the said plot(s).
Setting up the Site
A Allow for providing an office compound itemand sites for workshops, plant etc.
Use and Protection of the Site
B Allow for protecting the site during the course of item
the work to the entire satisfaction of the Engr.
C Allow for keeping the site and building and any item
adjcent areas affected by the building operations
clear of debris and other rubbish and
at completion making good all disturbed works or
ground to the entire satisfaction of the Engineer
D Allow for temporary covering and barricading item
to open excavation and other hazards
E Allow for providing and maintaining warning item
signs, red warning lamps,etc. as necessary in
all such places.
F Allow for temporary traffic signs as necessary item
It is Tenderer's responsibility to confirm the location and the limits of the above with the concerned
PROJECT NO. -1348PROPOSED OFFICE BUILDING
ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI
Page 1/2
TO COLLECTION (AED)
Item BILL No. 1 - PRELIMINARIES Qnty Unit Rate Amount % CompleAmount AED
Employer's / Engineer's Facilities
[Ref. to Appendix-A to the General Spec
Section 01 'General Items]
Allow for providing the following facilities including
modifying, adapting or relocating to suit the
progress of the works and removing from site
A Offices for the sole use of the Client Rep. and Item 30,534.00 50% 15,267.00
Engineer including stationery, furniture, cleaning
maintenance, and attendance
B Telephone and facsimile for the sole use of
the Engineer including paying all charges for
installation, rental, calls (within UAE) & removal item
C Ditto - Mobile telephone for Resident Engineer item
D Surveying equipment and assistance in
checking and setting out or measuring on site item
E Provide a photocoppier machine for the sole item INCLUDED
use of the Engineer, including all paper,
toner, maintenance etc.
F Provide computers all accessories as specified item
in Appendix -A to the General specification
Section 01 (General Items), complete
G Provide equipment like camera, etc.as specified item
PROJECT NO. -1348PROPOSED OFFICE BUILDING
ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI
Page 1/3
TO COLLECTION (AED) 30,534.00 15,267.00
Item BILL No. 1 - PRELIMINARIES Qnty Unit Rate Amount % CompleAmt. AED
Contractors Facilities
Allow for providing the following facilities
including modifying, adapting or relocating to
suit the progress of the works and removing
from site
A Offices conference room, sample room, item 153,122.00 50% 76,561.00
stores, messrooms, etc.
B Sanitary facilities item
C Telephones item
D Site first aid item
E Site fire figting equipment item Included
F Site drinking water item
G Temporary hordings item
H Temporary roads, hardstandings, etc. item
Contractors Site Administration
Allow for the following:
I Site administration item 202,704.00 6% 12,162.24
J Supervision and site management item 606,768.00 6% 36,406.08
K Security item 36,800.00 6% 2,208.00
L Safety, health and welfare of workers item 129,917.00 6% 7,795.02
M Transport of workers item 128,800.00 6% 7,728.00
Plant and Equipment
Allow for providing the following:
N Small plant and tools item 522,670.00 2% 10,453.40
O Cranes and lifting equipment item 684,998.00 2% 13,699.96
P Site transport item 118,000.00 6% 7,080.00
Q Any other plant and equipment item
PROJECT NO. -1348PROPOSED OFFICE BUILDING
ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI
Page 1/4
TO COLLECTION (AED) 2,583,779.00 174,093.70
Item BILL No. 1 - PRELIMINARIES Qnty Unit Rate Amount % CompleAmount AED
Scaffolding
A Allow for providing, erecting and maintaining,
dismantling and clearing away at completion
proper and adequate scaffolding including that
required for Sub-contractors and Specialists &
Sub-contractors nominated by the Client item 144,900.00 -
Setting out and surveying
B Allow for setting out the work and preparing a
levels survey item
Existing services
C Allow for ascertaing the location of all
underground services item
D Allow for protecting all underground services
during the progress of the work item
E The Contractor shall be responsible for any
damage caused to the underground services,
for any costs of repair and for any delays
arising from such damage item
Temporary Services for the Works
Allow for providing the following services for
the works including those required by the
Sub-contractors, paying all charges and for
providing all necessary temporary
installations and removing on completion
Water for the works
F The contractor shall install a separate meter
for water on site and all charges for the
temporary connection and consumption shall
Any costs of importing water by tanker and
storing on site shall be allowed for by the
Contractor as required. item 109,779.00 6% 6,586.74
Electric lighting and power for the works.
G The contractor shall install a separate meter
for electricity on site and all charges for the
temporary connection and consumption shall
Any costs for temporary electricity
generating equipment shall be allowed for
by the contractor item 338,675.00 6% 20,320.50
be paid by the Contractor OR
paid by the Contractor OR
PROJECT NO. -1348PROPOSED OFFICE BUILDING
ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI
Page 1/5
TO COLLECTION (AED) 593,354.00 26,907.24
Item BILL No. 1 - PRELIMINARIES Qnty Unit Rate Amount % CompleAmount AED
Protection of the Works
A Allow for covering up and protecting the
works from the weather and from dammage by
the Contractors own or other workmen
performing subsequent operations including
providing all necessary dust sheets, barriers
and guard rails and clearing away same
at completion item
B Allow for carefully protecting finished work
including that of Sub-contractors item
C Allow for providing and maintaining warning
signs, red warning lamps and barrycades as
necessary in all such places item
Enclosing site etc.
D Allow for providing any temporary hoardings,
enclosures, gates, entrances, etc. for the
protection of the site, the works and materials
and for alerting and adapting the same as may
be required, removing at completion of the
works and making good all works disturbed item 31,050.00 85% 26,392.50
Local Authority Workmen
E Allow for giving access to workmen employed
by the local or other authorities and providing
them with attendance as required item
Attendance
F Allow for the general attendance of one trade
upon another item
Temporary works
G Allow for furnishing the Engineer with full
particulars, drawings, etc. of all temporary
works necessary for the execution of work item
PROJECT NO. -1348PROPOSED OFFICE BUILDING
ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI
Page 1/6
TO COLLECTION (AED) 31,050.00 26,392.50
Item BILL No. 1 - PRELIMINARIES Qnty Unit Rate Amount % CompleAmount AED
Samples, Mockups, Tests, etc.
A Allow for providing and submitting to the
Engineer, as he may require, samples of all
materials and goods which are proposed for
incorporation in the works including removal
of the same on completion of the inspection item Included
B Allow for testing materials as required by the
Specifications item 28,750.00 6% 1,725.00
C Allow for providing sample panels of materials
as required including removal of the same on
completion of the inspection item
D Allow for providing mock-ups as required
including as part of work of the same on
completion of the inspection item
As Built Drawings and Manuals
E Allow for providing the Engineer with as-built
drawings and manuals as required by the item 23,000.00 6% 1,380.00
project specifications
Progress Photographs
F Allow for providing monthly sets of
negatives, taken at relevant locations item 1,725.00
G Allow for providing prints from negatives
selected by the Engineer item -
H Allow for providing photographs of the
project at the completion stage taken by
prfessional photographer item -
Notice Boards
I Allow for providing and erecting Two Site
Notice Boards as per the details mentioned
in the project specification item 51,405.00
Clearing Away Rubbish
J Allow for clearing away rubbish at regular intervals
during the progress of works and leaving
the site and perimeter tidy at completion item 99,360.00 6% 5,961.60
PROJECT NO. -1348PROPOSED OFFICE BUILDING
ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI
Page 1/7
K Cleaning at Completion
Allow for cleaning the entire site including the
building inside and out side and leaving ready
for occupation upon completion item 34,500.00
TO COLLECTION (AED) 238,740.00 9,066.60
Item BILL No. 1 - PRELIMINARIES Qnty Unit Rate Amount % Complete Amt. AED
Condition of Contract
Allow for complying with the Conditions
of Contract as follows:
A Cost of Insurances item 109,250.00 100% 109,250.00
B Cost of Performance Bond item Excluded
C Building Permit fee item 28,750.00 100% 28,750.00
D Fluctuations in cost item -
E Compliance with Statutes, Regulations
(Refer to Conditions of Contract Part II,
Conditions of Particular Application,
page CC/2.4, Clause 26.02) item -
Sub-contractors - Nominated/ Domestic
F Allow for provision, erection, maintenance and
to the nominated and domestic sub-contractors
including provision of drainage and sewrage
connections to the sewer system/septic tank
and provision of separate line of telephone,
power, water, etc. as required for the office
accommodation, but excluding all fitting-outs of
accommodation,such as Air-conditioners,
Furniture, etc. [Also, main contractor to fully
take over all responsibilities for the nominated
and domestic Sub-contractors]
[The payment of all charges for the telephone,
water, power,etc. for the site accommodation
to be mutually agreed between the Main
Contractor, and the Sub-contractor] item Excluded
G Allow for provision, erection, maintenance and
subsequent removal (at completion of works)
of all temporary buildings, storage areas, etc.
togather with hard-standings as required for the
nominated and domestic Sub-contractors item Excluded
H Allow for lifting/lowring of all plant,
subsequent removal of free site accommodation
PROJECT NO. -1348PROPOSED OFFICE BUILDING
ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI
Page 1/8
equipment and materials as required by
all the Sub-contractors item Excluded
TO COLLECTION (AED) 138,000.00 138,000.00
Item BILL No. 1 - PRELIMINARIES Qnty Unit Rate Amount % Complete Amt. AED
Any other items
A
1. Hire plot for temporary site setup 322,546.00 6% 19,352.76
2. Site distribution gang 89,700.00 6% 5,382.00
3 -
TO COLLECTION (AED) 412,246.00 24,734.76
COLLECTION AMOUNT
Page no.
1/1 - -
1/2 30,534.00 15,267.00
1/3 2,583,779.00 174,093.70
1/4 593,354.00 26,907.24
1/5 31,050.00 26,392.50
1/6 238,740.00 9,066.60
1/7 138,000.00 138,000.00
1/8
Allow for all costs, expences, etc. details of which must be set out below and extended separately by the Contractor, incurred in carrying out the requirements of the contract and not otherwise included
PROJECT NO. -1348PROPOSED OFFICE BUILDING
ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI
Page 1/9
1/8 412,246.00 24,734.76
BILL NO.1 PRELIMINARIES
TOTAL AMOUNT CARRIED TO SUMMARY (AED) 4,027,703.00 414,461.80
Page I/S
PROJECT NO. -1348PROPOSED OFFICE BUILDING
ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI
Page 2/10
Item BILL No. 2 - SHORING Qnty Unit Rate Amount % CompleAmount AED
Shoring
A Item 23,000.00 100% 23,000.00
B Item
C Item
Permanent shoring system as shown on dwg
D Secant pile 1000mm dia. 133 m 22100 2,939,300.00 35 773,500.00
E Guniting for the secant piling. Item 387,203.00
F Item
G 122 m2 112 13,664.00
H Item 64,400.00
TO COLLECTION (AED) 3,427,567.00 796,500.00
The work in this 'Sub- structure' section is to include all items upto the ground floor level including the ground floor slab.
Allow for design, shop drawings, monitoring, etc. of the shoring system.
Allow to obtain Dubai Municipality approval of the shoring design incliding paying all fees and charges as required.
Allow for all co-ordinations with Municipality and execution of all works as per the 'Notes' stated on Shoring detail drawings.
Shoring system with Secant Piling wall including RCC coping beam with all form work and steel reinforcement, Steel section H-piles, pre-cast concrete planks,tie-back anchoring, strutting etc as required in full compliance with statutory regulations and site conditions.
Tender must provide the total quantity (in linear meter) and the unit rate (AED per lin. M) for the Shoring Works.
Stiffener column / beam including formworks, reinforcement steel, strutt, etc., complete.
200mm thick solid concrete block wall with smooth cement plaster.
Waterproofing membrane and protection board are measured elsewhere in this bill section.
Removal of the above shoring system between ground level and -2.00m level as shown on dwg including removal of the steel I-section, pre-cast concrete panels, etc.
PROJECT NO. -1348PROPOSED OFFICE BUILDING
ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI
Page 2/11
Item BILL No. 2 - SHORING Qnty Unit Rate Amount % CompleAmount AED
Earthwork
A Allow for trial pits to locate any existing services. Item 3,857.00 100% 3,857.00
BItem 8,802.00 100% 8,802.00
C
11669 m3 32 373,408.00 13% 48,543.04
D m3 N/A
E 11669 m3 13 151,697.00 13% 19,720.61
F Compact all surfaces in the bottom of excavations 1078 m2 7 7,546.00
G 188 m3 91 17,108.00
Dewatering
H Item
INCLUDED
J Item
K Item 497,703.00
Preparation of site for construction work including levelling (cutting & filling), compaction, as necessary, etc.complete.
Excavate between existing ground level and bottom of blinding for raft slab/etc( The excavated material shall be stored temporarily at near-by site as directed by the Engineer being separated as suitable material for back filling and unsuitable material for disposal)
Backfiling using the excavated suitable fill material as directed by the Engineer
Disposal of excavated surplus material to tip approved by the Authorities and the Engineer
Filling with imported material to make up levels all in accordance with drawings and specifications
Allow to obtain Dubai Municipality and all other concerned authority approval for discharging the dewatering including paying all fees and charges as required
Allow for liaison and co-ordination with Employer, Engineer and all authorities as required, for the dewatering system.
Dewatering the wole site during excavation and through construction till sufficient counter weight against buoyancy uplift is achieved ( Refer to structural drawings)
PROJECT NO. -1348PROPOSED OFFICE BUILDING
ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI
Page 2/12
TO COLLECTION (AED) 1,060,121.00 80,922.65
Item BILL No. 2 - SHORING Qnty Unit Rate Amount % CompleAmount AED
A Concrete blinding 75mm thick 1078 m2 37 39,886.00
B 50mm thick protection screed to membrane 936 m2 22 20,592.00
C Columns 54 m3 688 37,152.00
D Walls 255 m3 688 175,440.00
E Basement walls 528 m3 710 374,880.00
F Raft slab 976 m3 585 570,960.00
G Footing beam/other foundations beams m3 N / A
H Base slab of lift pit/ water tank/ etc. m3
INCLUDED
J Walls of lift pit/ water tank/ etc m3
Plain in situ concrete, grade C20 with durability requirements as in Specification Section 3
Reinforced in situ concrete, grade C60 with durability requirements as in Specifications Section 3
Reinforced in situ concrete, grade C50 with durability requirements as in Specification Section 3
PROJECT NO. -1348PROPOSED OFFICE BUILDING
ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI
Page 2/13
TO COLLECTION (AED) 1,218,910.00 -
Item BILL No. 2 - SHORING Qnty Unit Rate Amount % CompleAmount AED
A Basement- 3 - Slab & beams 76 m3 537 40,812.00
B Basement-2 - Slab & beams 137 m3 537 73,569.00
C Basement-1 - Slab & beams 137 m3 537 73,569.00
D Ground slab,beams,Ramp etc 431 m3 537 231,447.00
E Staircases 24 m3 551 13,224.00
Formwork
F To sides of columns/walls 3467 m2 131 454,177.00
G To sides of raft slab/other slabs 84 m2 56 4,704.00
H To sides of footing/other foundation beams m2 N / A
J To sides and soffits of beams/lintels/sills 402 m2 73 29,346.00
K To sides of base slabs of lift pit/water tank/etc m2 INCLUDED
L To soffit of water tank m2 INCLUDED
M To stringers and soffits of stairs 124 m2 59 7,316.00
N To sides and soffits of suspended slabs/ramps 3139 m2 73 229,147.00
P To sides of grades slab,steps,ramps,etc. 35 m2 56 1,960.00
Reinforcement
Q High tensile steel bar of various diameters 413400 kg 6.1 2,521,740.00
Reinforced in situ concrete, grade C45 with durability requirements as in Specification Section 3
PROJECT NO. -1348PROPOSED OFFICE BUILDING
ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI
Page 2/14
TO COLLECTION (AED) 3,681,011.00 -
Item BILL No. 2 - SHORING Qnty Unit Rate Amount % CompleAmount AED
Waterproofing as per drawings/specifications
A1 936 m2 51 47,736.00
A2 1523 m2 51 77,673.00
A3 Protection board 6mm thick 1523 m2 29 44,167.00
A4 127 m 29 3,683.00
A5 Waterstop/ junction hose system at all concrete joints 1202 m 49 58,898.00
A6 Allow for junction,corner,etc,details as required item 5,750.00
A7 m2 N / A
B1 120 m2 79 9,480.00
B2 Ditto - any other areas as required m2 INCLUDED
Water tank
C1 439 m2 104 45,656.00
C2 GRP ladder to underground water tanks 2 no 1725 3,450.00
C3 2 no 1035 2,070.00
Hollow Concrete Blockwork
D1 200mm thick m2
Waterproofing membrane laid on blinding below raft slab,downstand beam, etc.
Waterproofing membrane laid on vertical surface of water tank walls, holding tank walls,basement walls,footing beam,etc.
25x25mm Groove with sealant to terminate waterproofing membrane.
Reinforced fair face blockwork to receive waterproofing membrane
Waterproofing membrane and protection board over ground slab to receive interlocking tiled paving area
GRP lining to all internal surfaces of under ground water tank (slabs,walls,soffit)
Fully sealed water/ air tight cover complete to u/gwater tank
All necessary accessories like valves,fittings etc to the underground water tank are measured in bill part " Plumbing & Drainage installation"
PROJECT NO. -1348PROPOSED OFFICE BUILDING
ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI
Page 2/15
N / A
D2 100mm thick m2
TO COLLECTION (AED) 298,563.00
Item BILL No. 2 - SHORING Qnty Unit Rate Amount % CompleAmount AED
Column Protectors
A 93 No 72 6,696.00
B item 34,745.00
D 150mm high upstand kerb fixed to floor slab 39 m 73 2,847.00
E 39 m 18 702.00
F 30 m2 67 2,010.00
G 54 No 210 11,340.00
H Item 5750 5,750.00
I Item 17,250.00
High density neoprene corner protection 100mm high anchored with mechanical fasteners, complete as per as per drawing
Road marking on parking and driveway at basements, ramps and ground floor including all parking separation lines, arrows,hatching,etc, complete as shown on drawings
(External roadmarkings are measured under bill for "External Works"
Kerbing and tiling at basement and ground floor parking /driveways
Two coats of chlorinated rubber based quick drying paint in approved colours ( black/yellow/white) to upstand kerbs
60mm thick, interlocking concrete paving blocks,shape,size and colour as approved, laid in multi-colour and pattern on and including 50mm thick sand bed and sub-base
Wheel stopper 150x150x1650 long Hydraulically pressed kerb towed to RC slab.
High duty polystyrene ( Density not less than 40kg/m3) factory cut to suit filling in substation all to DEWA requirements including form trenches,chequer plate,steel joisnts as required PVC sleeves, etc.
Epoxy painted removable chequered steel plate cover plate cover along with supporting angle at substation trenches as per DEWA apecifications
PROJECT NO. -1348PROPOSED OFFICE BUILDING
ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI
Page 2/16
TO COLLECTION (AED) 74,644.00
Item BILL No. 2 - SHORING Qnty Unit Rate Amount % CompleAmount AED
Sundries
A Anti termite treatment Item 3,054.00
B 1030 m2 4 4,120.00
C Damp proof course to all block wall ( as required) 54 m2 8 432.00
D m2
E Item 2,300.00
F Allow for expansion joint including cover. Item 2,300.00
1000 Gauge Polythene water barrier membrane, one layer
Two coats of approved bituminous coating on concrete/ blockwork surfaces directly contracting with soil.
Allow for all joints of construction,control,surface,etc.as required and complete as shown on drawings.
PROJECT NO. -1348PROPOSED OFFICE BUILDING
ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI
Page 2/17
TO COLLECTION (AED) 9,152.00
Item BILL No. 2 - SHORING Qnty Unit Rate Amount % CompleAmount AED
Any other items
A
1. Circular column guard 12 no. 367 4,404.00
2. Wall guard for ramp 220 m 153 33,660.00
3 Compacted sand filling 14 m3 44 616.00
TO COLLECTION (AED) 38,680.00
COLLECTION AMOUNT AMOUNT
Page no.
2/1 3,427,567.00 796,500.00
2/2 1,060,121.00 80,922.65
2/3 1,218,910.00 -
2/4 3,681,011.00 -
2/5 298,563.00 -
2/6 74,644.00 -
2/7 9,152.00 -
Any other items not included above but considered to have a monetary value by the Contractor are to be listed and priced below :
PROJECT NO. -1348PROPOSED OFFICE BUILDING
ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI
Page 2/18
2/8 38,680.00 -
BILL NO.2 SUB-STRUCTURE
TOTAL CARRIED TO SUMMARY (AED) 9,808,648.00 877,422.65
Page - 2/S
PROJECT NO. -1348PROPOSED OFFICE BUILDING
ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI
Page 2/19
Amount AED
PROJECT NO. -1348PROPOSED OFFICE BUILDING
ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI
Page 2/20
Amount AED
PROJECT NO. -1348PROPOSED OFFICE BUILDING
ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI
Page 2/21
Amount AED
PROJECT NO. -1348PROPOSED OFFICE BUILDING
ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI
Page 2/22
Amount AED
PROJECT NO. -1348PROPOSED OFFICE BUILDING
ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI
Page 2/23
Amount AED
PROJECT NO. -1348PROPOSED OFFICE BUILDING
ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI
Page 2/24
Amount AED
PROJECT NO. -1348PROPOSED OFFICE BUILDING
ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI
Page 2/25
Amount AED
PROJECT NO. -1348PROPOSED OFFICE BUILDING
ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI
Page 2/26
Amount AED
PROJECT NO. -1348PROPOSED OFFICE BUILDING
ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI
Page 2/27 BOQ(1/8)
Item Bill No. 3 Qnty Unit Rate Amount % Complet
A Columns 184 m3 688 126592
B Walls 504 m3 688 346752
C Beams 187 m3 537 100419
D Stairs 73 m3 545 39785
E Swimming Pool base slab
F Walls for swimming pool
G Lintels / sills 9 m3 993 8937
H Suspended conventional slab (As shown in Dwgs) 1064 m3 537 571368
I Parapet walls, coping, counter, etc., 128 m3 565 72320
J 50 m3 398 19900
Formwork
K To columns 1237 m2 127 157099
L To sides and soffits of beams 1059 m2 73 77307
M To walls 3613 m2 100 361300
N To stringers and soffits of stairs 337 m2 59 19883
O To vertical sides of parapets, coping, counter etc., 1416 m2 59 83544
P To base slab / walls of swimming pool m2 0
TO COLLECTION 1,985,206.00
Reinforced in situ concrete, grade C60 with durability requirements as in Specifications Section 3
Reinforced in situ concrete, grade C45 with durability requirements as in Specification Section 3
Screed in fill to utilities, toilets & baths, etc to match adjacent raised floor area.
PROJECT NO. -1348PROPOSED OFFICE BUILDING
ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI
Page 2/28 BOQ(1/8)
BILL NO. 3
SUPERSTRUCTURE
A To sides and soffits of lintel / sill
B To horrizontal soffit of suspended slabs
C Allow for all recesses, grooves and other labours to formwork
Reinforcement
D High tensile steel bar of various diameters
Sands on roof for A/C units and water tank areincluded in builder's work for Mechanical Installation and Plumbing & Internal drainage work respectivly
E High Duty Polystyrene
(Density not less than 40kg/m3 factory cut to suit)
F Light weight screed infill (as required)
G Lintels/ sills
H Suspended conventional slab (As shown in Dwgs.)
I Parapet walls, coping, counter, etc
J
Formwork
K To columns
L To sides and soffits of beams
M To walls
N To stingers and soffits of stairs
O To vertical sides of parapets, coping, counter etc
P To base slab/ walls of swimming pool
Screed in fill to utilities, toilet & baths, etc. to match adjacent raised floor area
PROJECT NO. -1348PROPOSED OFFICE BUILDING
ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI
Page 2/29 BOQ(1/8)
A To sides and soffit of lintel/ sill 136 m2 114 15504
B To horizontal soffit of suspended slabs 4010 m2 73 292730
C item 2875
Reinforcement
D High tensile stell bar of various diameters 299100 kg 6.2 1854420
E High Duty Polystrene m2
Density not less than 40k/m3 factory cut to suit)n/a
F Light weight screed infill (as required) m3
Waterproofing
G 458 m2 30 13740
H Water proofing to airwells, balconies & planters 28 m2 30 840
J item 20636
Insulation (ref. drawing of wall sections)
K 975 m2 56 54600
L m2 included
Sundries
M item 5750
N item 5750
P Allow for expansion joint including cover item 5750
TO COLLECTION 2,272,595.00
BILL NO. 3
Allow for all recesses, grooves and other labours to formwork
Strands on roof for A/C units and water tank are included in Builder's work for Mechanical Installation and Plumbing & Internal drainage works, reqpectively
Water proofing to slabs in kitchens, toilets and bathrooms
Water proofing to external walls behind cladding & glazing
Extended polystyrene insulation to internal wall/beam/ slab soffit
50mm thick black mineral fibre insulation mechanically anchored to wall at spandrel panel
Wall ties 250mm long one end cast into concrete and other end built into joint of blockwork
Allow for wall/ slab opening for all services ducts/ pipe, etc.
PROJECT NO. -1348PROPOSED OFFICE BUILDING
ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI
Page 2/30 BOQ(1/8)
SUPERSTRUCTURES
Any Other Items
A
1
2
3
COLLECTION
Page 3/1 1,985,206.00
Page 3/2 0
Page 3/3 2,272,595.00
CARRIED TO SUMMARY 4,257,801.00
Any other items not included above but considered to have a monetary value by the Contractor are to be listed and priced below :
PROJECT NO. -1348PROPOSED OFFICE BUILDING
ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI
Page 2/31 BOQ(1/8)
BILL - Post tensioning Wroks to Concrete
Post Tensioning: Bonded type
A Item 28,750.00
B Post-tensioning works for slabs (Super-structure) Item 232,639.00
C Post-tensioning works for beams (Super-structure) Item INCLUDED
D Allow for producing as built drawings Item 5,750.00
Any Other Items
E
1
2
3
CARRIED OUT TO SUMMARY 267,139.00
Supply and install tendons with all accesoriez for installation including anchoring, stressing, grouting, supervision by specialised Engineers, design of all post-tensioned slabs, beams and associated works, submission of detailed drawings and calculation
Structural design must satisfy minimum loading criteria specified on darwings and actual loading for critical areas as well as the slab thickness and other minimum conventional reinforcement specified in the structural drawings/ specification
Submittal of shop drawings with supporting design calculations
Beamsand slabs upto and including the ground floor slab is considered under "Sub-structure" and above ground floor slab is considered under "Super-structure"
Any other items not included above but considered to have a monetary value by the Contractor are to be listed and priced below:
PROJECT NO. -1348PROPOSED OFFICE BUILDING
ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI
Page 2/32 BOQ(1/8)
Amount AED
PROJECT NO. -1348PROPOSED OFFICE BUILDING
ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI
Page 2/33 BOQ(1/8)
BILL NO. 4
BLOCKWORK
A 200mm thick 228 m2 128 29,184.00
B 250mm thick 244 m2 147 35,868.00
Light weight blockwork (Internal partitions)(Block density not exceeding 850kg/m3)
C 100mm wall 494 m2 81 40,014.00
D 200mm wall 2839 m2 88 249,832.00
E 250mm wall m2 N/A
F 100mm wall m2
G 200mm wall m2
H 100mm thick 157 m 15 2,355.00
J 200mm thick 772 m 17 13,124.00
K 250mm wall 289 m2 19 5,491.00
Sundries
L Item 2,300.00
M Item 2,300.00
N Item 2,300.00
TO COLLECTION (AED) 382,768.00
Autoclaved Aerated Concrete (AAC) light weight block work fully complied with British codes and approved by Dubai Municipality to external walls
Allow for filling hollow blockwork wall solid with concrete at vertical and horizontal abutments and around openings
12mm thick compressible joint filler between top of blockwork wall and concrete structure
Allow for forming openings for doors, windows, etc in blockwork including all details at jambs, sills and heads
Allow for forming expansion joints with Flexel board and mastic seal
Allow for the protection of all of the works in this section
PROJECT NO. -1348PROPOSED OFFICE BUILDING
ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI
Page 2/34 BOQ(1/8)
BILL NO. 4
BLOCKWORK
Any Other Items
1. 300mm thick Autoclave block 283 m2 166 46,978.00
2. 400mm thick Light weight block 11 m2 225 2,475.00
3. Dry wall partition 290 m2 230 66,700.00
4. Fire sealant 1248 m 14 17,472.00
TO COLLECTION (AED) 133,625.00
COLLECTIONPage
4/1 382,768.00
4/2 133,625.00
Any other items not included above but considered to have a monetary value by the Contractor are to be listed and priced below :
PROJECT NO. -1348PROPOSED OFFICE BUILDING
ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI
Page 2/35 BOQ(1/8)
Bill No.4 BLOCK WORKTOTAL CARRIED TO SUMMARY 516,393.00
PROJECT NO. -1348PROPOSED OFFICE BUILDING
ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI
Page 2/36 BOQ(1/8)
BILL NO. 5
ROOFING
Membrane Roofing
A m2
B m2
C m2
D m2
E m2
F m
G Dressing roofing system to rainwater outlets Item
Sundries
H Item
J Allow for protection of all the works in this section Item
BILL NO. 5
ROOFING
Any Other Items
Light weight concrete infill (density 600kg/m3) min. thick 40mm, max thick 150mm
4mm thick torch applied waterproofing membrane to roof and rainwater channel as specified in Particular Specification
50mm (minimum) thick extruded polystyrene rigid insulation density35kg/m3
Non woven fabric mesh/ building paper/ 1000 gauge polythene separation layer as approved
600x600x50mm precast plain cement concrete tiles with expansion joints at 3000mm centres both ways laid in and including 30mm thick cement sand bedding
Perimeter detail including skirting tile, flashing, mastic fill, sealant with backup rod, groove, fillet at corner, protection board, etc around parapet wall/ airwell/ services
Rain water drain system installation is measured under bill section 'Plumbing & Drainage'
Allow for all opening in roof slab and wall/ roof for services inlets and outlets
PROJECT NO. -1348PROPOSED OFFICE BUILDING
ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI
Page 2/37 BOQ(1/8)
A
1
2
3
Any other items not included above but considered to have a monetary value by the Contractor are to be listed and priced below :
PROJECT NO. -1348PROPOSED OFFICE BUILDING
ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI
Page 2/38 BOQ(1/8)
BILL NO. 6
CARPENTARY AND JOINERY
Refer to dwgs for Schedule of Doors
A1 Wooden Door - 05 (1000 x 2200mm) No
A2 Wooden Door - 06 (800 x 2200mm) No
A3 Wooden Door - 07 (900 x 2200mm) No
A4 Wooden Door - 07A (900 x 2200mm) NO
A5 Wooden Door - 08 (1100 x 2200mm) No
A6 Wooden Door - 09 (900 x 2200mm) No
Supply only hardware set
B1 Ironmongery for all doors PC supply only rate AED 350.00/door No
B2 Door closer for all doors PC supply only rate AED 350.00/door No
Note :
BILL NO. 6
CARPENTARY AND JOINERY
A1 Base Unit m
A2 Wall unit m
Door & frame sets, complete including architraves, sub-frames, fix only hardware set, all finishes, etc., as required and as shown on drawings and specification
Supply only hardware set is included as BOQ item below with PC supply rates.
Engineer may delete door closer fully or partly as per his discretion and hence, the actual quantity of the door closer used on site shall be considered and the contract sum shall be adjusted accordingly
Supply and fix Kitchen/pantry units with marble/granite worktop including 100mm high plinth
PROJECT NO. -1348PROPOSED OFFICE BUILDING
ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI
Page 2/39 BOQ(1/8)
A3
(PC supply only sink & mixer AED 650.00/set) No
A4 30mm thick marble/ granite worktop m
PC supply only rate of stone AED 450.00/m
A5
(PC supply only rate of stone AED 45.00/m) m
A6 100mm high plinth for base unit m
B For the toilets and bathrooms(PC supply only of stone AED 350.00/m2) m2
Lockers to change room
D
(TRESPA or approved equal) No
BILL NO. 6
CARPENTARY AND JOINERY
Any Other Items
Extra over item kitchen cabinet base unit for supply and fix sink, mixer, trap, other fixing accessories, etc. including connections, complete
Extra over item above for 20mm thick marble/ granite splash back
Vanity Wash Basin Marble/ Granite Counter Top
Wash basin natural stone counter top, down fascia, splash back including cutting hole for the wash basin, mastic sealing, hardwood frame, MS angle frame & supports, etc., complete
Mirrors for above vanity tops are measured under bill section 'Glazing'
3 Tier 300 x 400 x 300 deep High Pressure Laminated (HPL) lockers complete with doors, hardware, accessories, etc. for complete operations.
Any other items not included above but considered to have a monetary value by the Contractor are to be listed and priced below :
PROJECT NO. -1348PROPOSED OFFICE BUILDING
ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI
Page 2/40 BOQ(1/8)
BILL NO. 7
METAL WORK
Hollow metal (HM) doors
A1 Door no. HM-02, size 1000 x 2200mm No
A2 Door no. HM-03, size 1000 x 2200mm No
A3 Door no. HM-04, size 1000 x 2000mm No
A4 Door no. HM-05, size 1500 x 2200mm No
A5 Fire Rated Steel Door - 01 (1100 x 2200mm) No
Supply only hardware set for Steel doors
B1 No
PC supply only rate AED 350.00/doorNo
B2 Ironmongery for stairs fire escape doorsPC supply only rate AED 2,000.00/door No
Aluminium Doors and Windows(Refer drawings & specifications)
C1 GL - 01 No
C2 GL-02 No
C3 GL-03 No
C4 GL- 04 No
C5 GL-05 No
C6 GL- 06 No
C7 GL- 07 No
C8 GL- 08 No
C9 GL- 09 No
C10 GL- 10 No
C11 GL- 11 No
C12 GL- 12 No
Door & frame sets, complete inlcluding architraves, sub-frames, fixing, all finishes etc. as required and as shown on drawing and specification
Ironmongery for all Hollow metal doors except stairs fire escape doors
PROJECT NO. -1348PROPOSED OFFICE BUILDING
ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI
Page 2/41 BOQ(1/8)
BILL NO. 7
METAL WORK
Aluminium Doors and Windows [Cont'd](Refer drawings & Specifications)
A1 GL-13 No
A2 GL-14 No
A3 GL-15 No
A4 GL-16 No
A5 GL-17 No
A6 GL-18 No
A7 GL-19 No
A8 GL-20 No
A9 GL-21 No
A10 GL-22 No
A11 GL-23 No
A12 GL-24 No
A13 GL-25 No
A14 GL-26 No
A15 GL-27 No
A16 GL-28 No
A17 GL-29 No
PROJECT NO. -1348PROPOSED OFFICE BUILDING
ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI
Page 2/42 BOQ(1/8)
A18 GL-30 No
A19 GL-31 No
A20 GL-32 No
A21 GL-33 No
A22 GL-34 No
A23 GL-35 No
A24 GL-36 No
A25 GL-37 No
BILL NO. 7
METAL WORK
Aluminium Doors and Windows [Cont'd](Refer drawings & Specifications)
A1 GL-38 No
A2 GL-39 No
A3 GL-40 No
A4 GL-41 No
A5 GL-42 No
A6 GL-43 No
A7 GL-44 No
Louvers(Refer drawings & specifications)
B1 LV-01 No
B2 LV-02 No
B3 LV-03 No
B4 LV-04 No
B5 LV-05 No
B6 LV-06 No
PROJECT NO. -1348PROPOSED OFFICE BUILDING
ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI
Page 2/43 BOQ(1/8)
Curtain Walls(Refer drawings & specifications)
C1 CW-01 No
C2 CW-02 No
C3 CW-03 No
C4 CW-04 No
C5 CW-05 No
C6 CW-06 No
BILL NO. 7
METAL WORK
Cat Ladder(Refer detailed drwg. A-451)
A Cat ladder from roof to upper roof m
A2 Cat ladder from ground to first floor m
Staircase HandrailsRefer to drawing nos. A300 to A303
For staircase - 1 m
B Fixed on the wall
For staircase - 2C1 Fixed on the floor m
C2 Fixed on the wall m
For staircase - 3 m
D Fixed on the floor
(refer drwg. A-450)
E1 To Pump Room m
E2 To Commercial Area m
F m2
Super durable polyester powder coated aluminium windows, including timber sub-frames, supply and fix all associated ironmongery, weathersealing, flyscreens and fixing in position as required
50mm Powder coated stainless steel pipe handrail
100 x 20mm PESDF coated continuous aluminium box section
PROJECT NO. -1348PROPOSED OFFICE BUILDING
ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI
Page 2/44 BOQ(1/8)
Canopy/Pergola
(To be design by the Contractor)
G1 To Ground Floor Area Item
G2 To Roof Area Item
Extra over above item G1 & G2
H1 To Ground Floor Area m2
H2 To Roof Area m2
BILL NO. 7
METAL WORK
Any Other Items
A
1
2
3
Steel Canopy, complete including all supports of steel structure, etc. complete
6mm thick pre finished aluminium composite panel cladding over galvanized steel skeleton structure anchored and braced to main structure
Any other tiems not included above but considered to have a monetarey value by the Contractor are to be listed and priced below :
PROJECT NO. -1348PROPOSED OFFICE BUILDING
ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI
Page 2/45 BOQ(1/8)
BILL NO. 8
FLOOR, WALL AND CEILING FINISHES
Insitu Finishes
A 7363 m2 40 294,520.00
B Ditto to ceilings 895 m2 43 38,485.00
C 1095 m2 49 53,655.00
D Ditto to parapets, etc 437 m2 49 21,413.00
E Item
INCLUDED
F Item
TO COLLECTION (AED) 408,073.00
Cement sand plaster (1:4) 15mm thick to concrete and blockwork walls in two coat work (internally)
Cement sand plaster (1:4) 20mm thick to walls in two coat work (externally)
Allow for expanded metal lathing 300mm wide at junctions of concrete and blockwork
Allow for the provision of all grooves, rain water drips and the like as necessary, in plastering
PROJECT NO. -1348PROPOSED OFFICE BUILDING
ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI
Page 2/46 BOQ(1/8)
BILL NO. 8
FLOOR, WALL AND CEILING FINISHES
Floor FinishesA 12 m2 129 1,548.00
(PC rate for supply only Dhs. 35.00/m2)
B 11 m2 129 1,419.00
(PC rate for supply only Dhs. 35.00/m2)
C1 Raised flooring system, complete 2498 m2 173 432,154.00
(PC rate for supply only Dhs. 150/m2)
C2 Extra over ablove item C1 Carpet tile 2483 m2 104 258,232.00
F-03, with matching colour grout on raised floor
(PC rate for supply only Dhs.90.00/m2)
D 400 m2 67 26,800.00
E 127 m2 68 8,636.00
F 126 m2 55 6,930.00
G 1740 m2 68 118,320.00
Rate for Floor/ Wall/ Stair/ Step/ etc tiles shall include for jointing and pointing with an approved grout as required and bed with cement sand mortar/ cement based adhesive as approved
Contractor shall allow for plastic edge strips for all ceramic tiles external corners and horizontal edges with matching colours
F-01, 300 x 300mm Heavy duty unglazed ceramic tiles with matching colour
F-02, 200x 200 unglazed granite tiles with matching colour grout
F04, 75mm thick Sand cement screed with self leveling compound Nito Floor Top or similar equivalent approved to received finishes by Tenant.
F05, Concret slab power floated finish with hardener and sealer coat
F06, 75mm thick sand cement screed with epoxy resin based coating
F07, 100% solid epoxy flexible wear coat system, seeded into epoxy with manufacturer approved aggregate (i.e. size, washed, dried & bagged), having a minium hardness of six (6) on the Moh scale, at the recommended coverage. The system should have A-1 fire
PROJECT NO. -1348PROPOSED OFFICE BUILDING
ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI
Page 2/47 BOQ(1/8)
TO COLLECTION (AED) 854,039.00
BILL NO. 8
FLOOR, WALL AND CEILING FINISHES
Floor Fhishes (Cont'd)
A
648 m2 107 69,336.00
B 869 m2 75 65,175.00
C 104 m2 115 11,960.00
D 48 m2 96 4,608.00
E 119 m2 231 27,489.00
(PC rate for supply only Dhs. 120.00/m2)
F 139 m2 549 76,311.00
(PC rate for supply only Dhs. 350.00/m2)
G 195 m2 129 25,155.00
(PC rate for supply only Dhs. 35.00/m2)
F08, Multi-layered solvent free, rapid curing, 100% soldi flexible epoxy coating system. The system will consist of a primer coat, elastomeric tough seamless waterproofing membrane based on Du Pont Neoprene and abrasion resistance traffic bearing top coa
The system should have A-1 fire rating ASTM E86 or equivalent approved coverage
F-10, Non Slip epoxy resin coating over precast concrete steps/ landing applied to a thickness of 3mm including non slip aggregate
F11, 300 x 300mm precast white cement Terrazzo tiles with Italian chips laid on sand cement mortar bed
F-13, 60mm thick precast interlock plain cemnet concrete tiles for pedestrain paved areas
F-15, 400x 400 porcelain tiles with matching colour grout
F-19, 20mm thick granite slab cut to size with mathcing colour granite border to form pattern
F-20, 300 x 300 ceramic tiles with matching colour grout
PROJECT NO. -1348PROPOSED OFFICE BUILDING
ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI
Page 2/48 BOQ(1/8)
TO COLLECTION (AED) 280,034.00
BILL NO. 8
FLOOR, WALL AND CEILING FINISHES
Skirting Finishes
A 1398 m 39 54,522.00
(PC rate for supply only Dhs.15.00/m)
B 83 m 39 3,237.00
(PC rate for supply only Dhs. 15.00/m)
C 931 m 13 12,103.00
D 657 m 13 8,541.00
Statement Only
F14, GRP lineron floor slab of water tank Statement Only
Statement Only
S-01, 100mm high porcelain tile skirting to match the floor tiles.
S-02, 100mm high Terrazzo tiles skirting matching to floor
S-03, 100mm high epoxy resin coating - type and colour to match floor
S-04, 150mm high epoxy resin coating - type and colour to match floor
F12, 600x 600 x 50mm precast plain cement concrete tiles laid in and including cement sand bedding on roof top is measured under bill sention "Roofing"
(including wall and ceiling) is measure under bill section "Sub-structure"
Waterproof membrane laid over structural slab with protection board over & on sides is measured under bill section "Sub-structure"
PROJECT NO. -1348PROPOSED OFFICE BUILDING
ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI
Page 2/49 BOQ(1/8)
TO COLLECTION (AED) 78,403.00
BILL NO. 8
FLOOR, WALL AND CEILING FINISHES
Marble Threshold
A Width to match 100mm wide wall (PC supply only AED 100.00/m) 39 m 151 5,889.00
B Width to match 200mm wide wall (PC supply only AED 200.00/m) 20 m 278 5,560.00
Sill Cladding (Ref. Wall Sections)
C 20mm thick polished granite sill at typical floors
(PC supply only granite rate AED 200.00/m2 198 m2 381 75,438.00
-
D 56 m 23 1,288.00
E Marble cladding arround lift wall 95 m 571 54,245.00
30mm thick polished granite/ marble threshold to approval full width to all wet areas with rounded edges and anchored with stainless steel dowels
3mm thick stainless steel strip between different floor finishes as required
PROJECT NO. -1348PROPOSED OFFICE BUILDING
ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI
Page 2/50 BOQ(1/8)
TO COLLECTION (AED) 142,420.00
BILL NO. 8
FLOOR, WALL AND CEILING FINISHES
Wall Finishes
All paint finishes to wall are measured under Bill section 10
A
(PC rate for supply only Dhs. 40.00/m2) 1335 m2 97 129,495.00
B
(PC rate for supply only Dhs.600.00/m2) 767 m2 682 523,094.00
C
(Refer drawing A-310) 133 m2 748 99,484.00
W-13, 200 x 300mm glazed ceramic wall tiles with matching colour grout
W-17, 20mm thick Granite/ Marble stone cut to size anchored to wall in matching colour with stainless stell mechanical fasteners up to 100mm above the suspended ceiling.
Decorative Wooden Panel as per Engineer's approval
PROJECT NO. -1348PROPOSED OFFICE BUILDING
ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI
Page 2/51 BOQ(1/8)
TO COLLECTION (AED) 752,073.00
BILL NO. 8
FLOOR, WALL AND CEILING FINISHES
Suspended Ceilings
A 53 m2 110 5830
B 66 m2 92 6072
D m2 N/A
F 215 m2 75 16125
G 2555 m2 156 398580
Suspension systems shall be galvanised steel and cilings shall include painting where required by the Engineer
All paint finishes as required in the following suspended ceiling system are measured in the Bill section '10'
SC01, 600 x 600mm pre finished decorative perforated gypsum tiles with black acoustic backing and recessed edge suitable for black reveal Fine Line grid suspension system, all surrounded by 12.5mm thick gypsum board bulkhead (25mm lower than ceiling tiles
SC02, 6mm thick calcium silicate board ceiling painted with paint type similar to adjacent surface
SC03, 1200 x 600mm pre finished gypsum tiles with recessed exge suitable for semi concealed (recessed) suspension system all around, surrounded by 12.5mm thick gypsum board bulkhead (25mm lower than ceiling tiles) painted with paint type-3
SC04, 600 x 600mm vinyl faced moisture resistant gypsum tiles with aluminium back foil and exposed grid suspension system.
SC05, 600 x 600mm pre finished aluminium tiles with black reveal Fine Line grid suspension system
PROJECT NO. -1348PROPOSED OFFICE BUILDING
ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI
Page 2/52 BOQ(1/8)
H 343 m2 87 29841
TO COLLECTION (AED) 456,448.00
BILL NO. 8
FLOOR, WALL AND CEILING FINISHES
Sundries
A Item
INCLUDED
B Item
C Item 2,300.00
D Item INCLUDED
E Shadow gap 2203 m 14 30,842.00
F Bulk Head 628 m 87 54,636.00
SC10, 600 x 600mm pre finihsed gypsum tiles with recessed edge suitable for semi concealed (recesssed) suspension system all around, surrounded by 12mm thick gypsum board bulkhead(25mm lower than ceiling tiles) painted with paint type-3
Allow for cutting all holes for light fittings, etc. including any extra hangers, supports, and the like (ceiling)
Allow for all cutting and fitting around openings and fittings and narrow widths, etc. (flooring & wall tiling)
600 x 600mm properietary system access panel with concealed hinges/ spring latch, finish to match gypsum ceiling
Allow for protection of all of the works in this section
PROJECT NO. -1348PROPOSED OFFICE BUILDING
ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI
Page 2/53 BOQ(1/8)
TO COLLECTION (AED) 87,778.00
BILL NO. 8
FLOOR, WALL AND CEILING FINISHES
Any Other Items
A 0
1
2
3
TO COLLECTION (AED)
Page 8/9
COLLECTION
Page no.8/1
408,073.00
Any other tiems not included above but considered to have a monetarey value by the Contractor are to be listed and priced below :
PROJECT NO. -1348PROPOSED OFFICE BUILDING
ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI
Page 2/54 BOQ(1/8)
8/2 854,039.00
8/3 280,034.00
8/4 78,403.00
8/5 142,420.00
8/6 752,073.00
8/7 456,448.00
8/8 87,778.00
8/9
BILL NO. 8 FLOOR,WALL AND CEILING FINISHES
TOTAL CARRIED TO SUMMARY 3,059,268.00
PROJECT NO. -1348PROPOSED OFFICE BUILDING
ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI
Page 2/55 BOQ(1/8)
0
PROJECT NO. -1348PROPOSED OFFICE BUILDING
ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI
Page 2/56 BOQ(1/8)
BILL NO. 9
GLASS
Mirrors (Belgium glass)
A Above wash basin pedestal type No
B Above wash basin vanity type m2
C Miscellaneous glazing as required Item
D Item
Any Other Items
E
1
2
3
Note : Glazing to aluminium door and window units is included with the relevant units, Mirror size shall be 600 x 900mm high for pedestal type basin and full width x 1200mm high for vanity type basins
6mm thick polished plate glass mirrors with bevelled edges and 12mm thick marine plywood (exposed edges sealed with silicon or plastic strip colour to match with adjacent wall finish) backing plugged and screwed to walls with chromium plated dome headed m
Allow for protection of all of the works in this section
Any other tiems not included above but considered to have a monetarey value by the Contractor are to be listed and priced below :
PROJECT NO. -1348PROPOSED OFFICE BUILDING
ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI
Page 2/57 BOQ(1/8)
BILL NO. 10
PAINTING AND DECORATING
TO WALL
A m2
B m2
C m2
D m2
E m2
F m2
TO CEILING
G m2
H m2
TO FALSE CEILINGI m2
J Refer to false ceiling SC02 m2
Prepare and apply paint on smooth cemnt render, internally
W01, Acrylic base Emulsion paint (Paint Type-3) on smooth cand cement plaster
W02, Oil based /Alkyd enamel paint (Paint Type-4)on smooth cand cement plaster
W03, Semi Epoxy paint (Paint Type-2) over fair faced concrete wall
W05, Full Epoxy paint (Paint Type-1) over smooth sand cement plaster
W06, Non fungus Acrylic paint (Paint Type-5) over fair faced concrete wall
W15, Fairface concrete/flush pointed block wall wity tyrolene coat
C-04, Alkyd enamel paint over sand cement plaster
C-06, Smooth finished sand cement plaster painted with paint type-02
Refer to false ceiling SC01, SC03, SC07 & SC10 Acrylic Emulsion paint (Paint Type-3)
PROJECT NO. -1348PROPOSED OFFICE BUILDING
ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI
Page 2/58 BOQ(1/8)
BILL NO. 10
PAINTING AND DECORATING
EXTERNAL DECORATIONSRefer to elevation & section drawings
A m2
B
(PC rate for supply only of tiles Dhs.450.00/m2) m2
Sundry
C Item
BILL NO. 10
PAINTING AND DECORATING
A Any Other Items
1
Full Epoxy Paint System (Paint Type-1) rendering on sand cement plaster, colour & textured
30mm thick Natural stone cladding anchored with stainless steel fasteners as required
Allow for the protection of all the work in this section
Any other tiems not included above but considered to have a monetarey value by the Contractor are to be listed and priced below :
PROJECT NO. -1348PROPOSED OFFICE BUILDING
ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI
Page 2/59 BOQ(1/8)
2
3
BILL NO. 10A
BUILDER'S WORK
A For nominated Lift installation sub-contract works
Also include for steel supports if necessary Item
B For the installation of Signage internal & external Item
C For the installation of Cleaning cradle system Item
D For the Mechanical works Item
E For the Electrical works Item
F For the Plumbing works Item
Allow for all Builder's work in connection with the Provisional sum items including co-ordination/liasion with all concerned authorities and sub-contractors and all general and special attendance as required
Buidler's work for the installations of following works, which are neither described above nor anywhere in the BOQ, which includes the following but not limited to Excavation, Trenching, Backfilling, Compaction, Concrete blocks, Thrust block, finishes, Pr
PROJECT NO. -1348PROPOSED OFFICE BUILDING
ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI
Page 2/60 BOQ(1/8)
BILL NO. 10A
BUILDER'S WORK
A Any Other Items
1
2
3
Any other tiems not included above but considered to have a monetarey value by the Contractor are to be listed and priced below :
PROJECT NO. -1348PROPOSED OFFICE BUILDING
ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI
Page 2/61 BOQ(1/8)
BILL NO. 11
RAINWATER INSTALLATION
A No.
B No.
C m
D Item
E Item
F No.
BILL NO. 11
BASEMENT RAINWATER DRAINAGE
A Basement floor stormwater pipe line to sump Item
PLUMBING & INTERNAL DRAINAGE INSTALLATIONS
Dressing roofing system to sump/ outlet, etc, is within the scope of main contract
Roof rainwater outlet including grating, short pipes and bends through slab/ wall, connection to 100mm dia. Rainwater downpipes, etc.
Outlet in balcony for 100mm dia pipe including grating and connection to floor drain
100mm uPVC rainwater pipe including brackets and supports
Allow for cast rainwater pipe into concrete/ blockwork
Allow for bends, cleanouts, outlets, etc. to rainwater pipe
Powder coated aluminium cover to rainwater outlet
PLUMBING & INTERNAL DRAINAGE INSTALLATIONS
uPVC pipes including fittings, pipe supports, brackets, rodding eyes, pipe access, access panels and the like.
PROJECT NO. -1348PROPOSED OFFICE BUILDING
ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI
Page 2/62 BOQ(1/8)
B Catch basin No.
C At ramp m
D At Garbage room m
E No.
F Item
G Item
BILL NO. 11
SANITARY INSTALLATION
A Pedestal type wash basin + mixer No.
B Vanity type wash baisn + mixer No.
Heavy duty polymer concrete drainage channel, comprising 300x50mm thick heavy duty cast iron grating, including all necessary civil works, etc., complete including silt bucket as shown on drwgs.
Sump pit including heavy duty type cover, sand trap, etc., complete
Sump pump comrising two pumps (1D+1SB) 4.2 LPS @ 10m head including automatic switchover facility, high and low level float switches, all interconnecting pipework, valves, fittings, controls and control panel, etc. complete
Pumping main from sump pump to waste line including all bends, clean outs, fittings, etc. complete
PLUMBING & INTERNAL DRAINAGE INSTALLATIONS
(Supply of sanitary wares and accessories is included as provisional sum)
Fix only sanitary ware, taps and accessories including waste outlets, traps, connections to hot and cold water supplies and wastes, compelete
PROJECT NO. -1348PROPOSED OFFICE BUILDING
ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI
Page 2/63 BOQ(1/8)
C No.
D Urinal No.
E Item
BILL NO. 11
SANITARY INSTALLATION
Pipes and Fittings, etc
A Item
B Waste pipe with bend to wash basin/ sink No.
C Floor trap No.
D Gully trap No.
E Item
Manhole
F No.
G No.
WC seating type including low level flushing cistern, compelte
Fix only approved accessories including forming recesses and making good as required
Robe hook, Toilet roll holder, Soap holder, Towel rail, Towel ring, Tissue holder, forming recesses and making good as required
PLUMBING & INTERNAL DRAINAGE INSTALLATIONS
uPVC waste, soil and vent pipes including fittings, pipe supports, brackets, rodding eyes, access panels and the like
Allow for connections to underground drainage pipes
Pressure breaking MH with heavy duty type cover, complete
MH 600x600mm with heavy duty type cover, complete
PROJECT NO. -1348PROPOSED OFFICE BUILDING
ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI
Page 2/64 BOQ(1/8)
H No.
J Allow for connection to DM sewer system Item
HOT AND COLD WATER INSTALLATION
Equipment
K Item
L -Ditto- to roof tanks Item
BILL NO. 11
Roof mounted water tank
A No.
B Item
Ditto - (F.I.C), DI cover medium duty recess type with 6mm thick GRP push fit sealing plate
Provide all connections to concrete underground water tank to incoming and outgoing service, neck, vent, access cover and frame, etc., as required
Ladder & air-tight covers to u/g water tank are measured under bill 'Sub-structure'
PLUMBING & INTERNAL DRAINAGE INSTALLATIONS
HOT AND COLD WATER INSTALLATION (Cont'd)
Roof mounted approved cold water storage tank GRP sectional insulated panel type all connections to incoming services, interconnection, overflow, drain and supply high and low level float switches, etc
Size 2 compartments 3.0 x 10.60 x 2.5m h. with 70m3 water capacity
Transfer pump set comprising two nos. (1W+1SB), Each 250 USGPM @ 9 bar including automatic switchover facility, float switches, all interconnection pipework, valves and fittings, controls and control panel, etc,
PROJECT NO. -1348PROPOSED OFFICE BUILDING
ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI
Page 2/65 BOQ(1/8)
C Item
D Item
E Item
F Item
BILL NO. 11
Pipes, Fittings, etc.
A Item
B Item
C Item
D Allow for all other valves as required Item
Water supply booster pump set two nos. (1W+1SB) 7L/S @ 2 Bar. Each with controls and pane, 100 GPM pr. Vessel, by-pass line and aluminium enclosure including all interconnecting pipework, valves and fittings
Supply of water meter is not in the scope and part of DEWA connection. However all liasions, coordinations and all buider's works in connection with the DEWA connection are in the scope
Valve pit, valves, etc., at site entry including collect and fix water meter
Main supply from meter to underground tank and to roof tank
Collect and fix all water meter complete and valves, etc., for individual areas/ flats
PLUMBING & INTERNAL DRAINAGE INSTALLATIONS
HOT AND COLD WATER INSTALLATION (Cont'd)
CWS supply pipe to individual apartments and other areas as required
Cold/ Hot water distribution pipework with cross linked polethylene pipe & conduit sytem, all fixing accessories, etc. complete to all fittings such as sanitary wares, water heater, etc
Insulated copper hot water supply pipework including fittings, supports, brackets, etc, from water hearters to supply points
PROJECT NO. -1348PROPOSED OFFICE BUILDING
ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI
Page 2/66 BOQ(1/8)
E Bib taps No.
F Water heater, 30 litre capacity No.
G Water heater, 50 litre capacity No.
Sundries
H Allow for suitable protection to CWS pipes Item
J Item
K Item
L Item
M Item
BILL NO. 11
Any Other Items
A
1
2
3
UV protection and heat insulation for weather exposed piping
Allow for cleaning, sterilizing and disinfecting the plumbing and internal drainage installation as specified
Allow for testing and commissioning the plumbing and internal drainage installation
Allow for producing as built drawings and manuals as specified
PLUMBING & INTERNAL DRAINAGE INSTALLATIONS
Any other items not included above buty considered to have a monetary value by the Contracted are to be listed and priced below :
PROJECT NO. -1348PROPOSED OFFICE BUILDING
ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI
Page 2/67 BOQ(1/8)
BILL NO. 12
ELECTRICAL INSTALLATION
A Item
B1 L.V Panel - 1 No.
B2 L.V Panel - 2 No.
B3 Capacitor bank 350 K.V.A.R No.
LIGHTING AND POWER
C1 SMDB - ESS No.C2 SMDB - B No.C3 SMDB - COM No.C4 SMDB - CHILLERS No.C5 SMDB - CH No.C6 SMDB - LL No.
C10 SMDB - T1 No.C11 SMDB - T2 No.C12 SMDB - T3 No.C13 SMDB - T4 No.C14 SMDB - T5 No.C15 SMDB - T6 No.C16 SMDB - T7 No.
Include for the supply & complete installation as detailed in the Specifications and on the Drawings and to the complete satisfaction and approval of the Engineer and all concerned Statutory Authorities and under the following sections.
Allow for all liasions, coordinations and all builder's works in connection with the DEWA connection including collect and install KWH meter, etc.
LV panels including breakers, terminations, isolators, all necessary cabling including cable ladder,/ conduits, cleats all fittings trace and trunking supports emergency push buttons, current transformers, power factor correctors, accessories as per DEWA
Sub main distribution boards including MCCB's breakers, Terminations, isolators supports, accessories, etc., complete
PROJECT NO. -1348PROPOSED OFFICE BUILDING
ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI
Page 2/68 BOQ(1/8)
BILL NO. 12
ELECTRICAL INSTALLATION (Cont'd)
A1 DB-LL2-ESS No.A2 DB-LL1-ESS No.A3 DB-R-ESS No.A4 DB-B-ESS No.A5 DB-S/S No.A6 DB-G No.A7 DB-LL1 No.A8 DB-MAIN TELE No.A9 DB-ROOF TELE No.
A10 DB-LL2 No.A11 DB-COM-1 No.A12 DB-COM-2 No.A13 DB-B1 No.A14 DB-B2 No.A15 DB-B3 No.A16 DB-GYM No.A17 DB-PM No.A18 DB-T1-OF1 No.A19 DB-T1-OF2 No.A20 DB-T1-OF3 No.A21 DB-T2-OF1 No.A22 DB-T2-OF2 No.A23 DB-T2-OF3 No.
B Isolators including accessories Isolators Item
BILL NO. 12
ELECTRICAL INSTALLATION (Cont'd)
A Cable to all mechanical/ electrical equipments Item
Distribution boards including breakers, terminations, isolators, supports, accessories, capacitor banks, built in meters, etc., complete
PROJECT NO. -1348PROPOSED OFFICE BUILDING
ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI
Page 2/69 BOQ(1/8)
Supply & install
B Item
C From LV panels to SMDB's Item
D From SMDBs to DB's Item
Light Fittings
E Item
No.F1 Lighting point, internal No.F2 Lighting point, external No.F3 One gang one way light switch No.F4 One gang two way light switch No.F5 Two gang one way light switch No.F6 Three gang one way light switch No.F7 Four gang one way light switch No.F8 Grid switch unit No.F9 Time delay switch No.
F10 13 amp single switched socket outlet No.F11 - Ditto - weather proof No.F12 13 amp double switched socket outlet No.F13 15 amp single switched socket outlet No.F14 15 amp flex outlet No.F15 20 amp double pole switch with neon indicator No.F16 Call bell indicator No.F17 Bell push button No.F18 Floor box No.
BILL NO. 12
Lighting protection system and structural bounding complete
Cables for Sub main distribution boards and distribution boards
The supply of light fittings is included as a Provisional Sum
Fix only light fittings as specified and as shown on drawings including supports, fixings, terminations, connections, brackets, etc
Lighting/ General power installation including supply and fix switches/ sockets, wiring, ladders, ducts/conduits, cleats, trays, trunking, cable trays, fittings, accessories, connections, etc., all as necessary, compelete
PROJECT NO. -1348PROPOSED OFFICE BUILDING
ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI
Page 2/70 BOQ(1/8)
ELECTRICAL INSTALLATION
STRUCTURED CABLING SYSTEM
A1 Item
A2 Item
A3 Allow for all cable tray for Voice/ Data cables Item
A4 Allow for Voice/ Data cable trunking Item
A5 Item
A6 Item
A7 Lead-in-conduits as required Item
A8 Item
G.S.M
B1 Item
B2 Cable trays Item
B3 Allow for Earthing system, complete Item
B4 Item
Supply and installation of Structured Cabling is including as Provisional sum
Voice/ Data outlet points, junction boxes, under-ground trunking & conduits to approval
Voice/ Data conduiting from the master line jack unit to all other outlets by a tele-communication authority approved contractor as per Specification
Allow for all ducts for incoming telephone cable to Etisalat's spec. & detail
Allow for all other necessary underground ducts and conduits with draw wires
Allow for Telephone manholes and earthing complete as required
All conduits, supports, containments and Electrical works as per Tele-Communication Authority (Etisalat, etc.) requirements
Allow for connections to air conditioning, drain equipment etc.
PROJECT NO. -1348PROPOSED OFFICE BUILDING
ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI
Page 2/71 BOQ(1/8)
BILL NO. 12
ELECTRICAL INSTALLATION
CATV System
A
Item
B Item
Builder's work onlyC Item
Fuel Storage Tank and Fuel Filling SystemD Item
E Item
F Item
Containment only (including all builder's work)
Supply and install conduits/ cable trays as per drawings with draw wires, and all related civil works to CATV system
Supply and installation of MATV/SMATV system is included as Provisional sum
Containment only (including all builder's work)
Supply and install conduits with draw wires and all builder's work to MATV/SMATV system
Supply and installation including testing & commissioning of Generator is included as Provisional sum
Allow for all builder's work as required for the complete gernerator installation including its unloading, temporary stroring, placement & positioning, supply & fix of all cabling, piping, ductwork, acoutstic treatment, pedestals, etc.
Allow for supply and install Fuel Storage Tank and Fuel Filling System for the above mentioned Generator
Supply and installation of intercom system is included as Provisional sum
Containment only (including all builder's work)
Supply and install conduits with draw wires and all builder's work to the intercom sytem
Gate barriers (supply & fix is measured in Bill section 'External Works')
Containment only (including all builder's work)
Supply and install conduits with draw wires and builder's work to Gate barriers
PROJECT NO. -1348PROPOSED OFFICE BUILDING
ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI
Page 2/72 BOQ(1/8)
BILL NO. 12
ELECTRICAL INSTALLATION
Sundries
A Allow for Earthing system, complete Item
B Clean Earth Item
C Item
D Item
E Item
F Item
BILL NO. 12
ELECTRICAL INSTALLATION
Any Other Items
A
1
2
3
Allow for connections to air conditioning equipment, fans, water, heaters, etc
Allow for producing as built drawing and manuals as specified
Allow for third party testing and commissioning the electrical installation
Allow for the proctection of all the work in this section
Any other items not included above but considered to have a monetary value by the Contractor are to be listed and priced below :
PROJECT NO. -1348PROPOSED OFFICE BUILDING
ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI
Page 2/73 BOQ(1/8)
BILL NO. 13
MECHANICAL INSTALLATION
AIR-CONDITIONING & VENTILATION
Chillers
A No
B Item
C Item
Chilled Water Pressurisation Unit - 1Set
D Item
Chemical Dosing Unit
E Item
Fresh Air Supply
F Item
All external A/C units to be isolated from roof structure by approved vibration isolation material
Air-Conditioning - as specified and as shwon on drawings
Water chiller units CH! & CH2 cooling capacity 94 TR
Pumps - including all valves, pressure guage, flexible connection, etc., compelte
Primary chilled water pumps 3 nos.(2W + 1SB) capacity 226 GPM@ 100ft head (exact head to be determined by the Contractor and to Engineer's approval)
Secondary chilled water pumps 2 nos. (1W+1SB) capapcity 451GPM @ 100ft head (exact head to be determined by the Contractor and to Engineer's approval)
Automatic package unit comprising of 2 nos. feed pump ses (duty + standby), feed tank and 2 nos. expansion vessel (unit capacity to be calculated by Contractor and approved by Engineer)
Chemical dosing unit including sensors, and controllers
Fresh Air Handling Unit including run around coil heat exchanger, heat pipe, filters, all control & fire dampers, ductwork, VCD, grillers, etc., to all floors, complete (FAHU 1)
PROJECT NO. -1348PROPOSED OFFICE BUILDING
ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI
Page 2/74 BOQ(1/8)
BILL NO. 13
MECHANICAL INSTALLATION
AIR-CONDITIONING & VENTILATION
A1 Basement floor -3 Item
A2 Basement floor -2 Item
A3 Basemnet floor - 1 Item
A4 Ground floor Item
A5 Floor - 1 Item
A6 Floor - 2 Item
A7 Floor - 3 Item
A8 Floor - 4 Item
A9 Floor - 5 Item
A10 Floor - 6 Item
A11 Floor - 7 Item
A12 Roof Floor Item
Chilled water system air-conditioning including air handiling units, fan coil units, chilled water piping, all valves, all ducting, grilles, diffusers, etc., complete to the following area
PROJECT NO. -1348PROPOSED OFFICE BUILDING
ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI
Page 2/75 BOQ(1/8)
BILL NO. 13
MECHANICAL INSTALLATION
AIR-CONDITIONING & VENTILATION
A Car Park (Basement - 3) ItemUnit : EF - 1&2
B Car Park (Basement - 2) ItemUnit : EF - 1&2
C Laundry (Basement - 1) ItemUnit : EF - 1&2
D Guard Room (Ground floor) ItemUnit : EF - 1
E Garbage Room (Ground floor) ItemUnit : EF - 2
F Toilet (Ground floor) ItemUnit : EF-3
G Roof floor ItemUnit : EF-1Unit : SMK-1
Staircase Pressurisation Fans ItemH SPF - 1 & 2
BILL NO. 13
MECHANICAL INSTALLATION
Builder's Work
A
Exhaust air systems to the following including exhaust fans, all ducting, grilles, diffusers, etc., as required complete
Allow for all builders work in connection with the mechanical installation including but not limited to the following :
a) Concrete stand/ foundation for A/C units including anti-vibration pads, springs
b) Forming opening in slab for SA/RA duct/ refrigernat pipes, etc.
PROJECT NO. -1348PROPOSED OFFICE BUILDING
ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI
Page 2/76 BOQ(1/8)
d) Walkovers over pipting, ducting as required e) Inertia bases for pumpsf) Floating floor for chillers Item
Sundries
B Item
C Item
D Item
E Item
F Item
G Item
BILL NO. 13
MECHANICAL INSTALLATION
Any Other Items
A
1
2
3
c) Painting of all equipment, duct work and accessories
Allow for all control panels, thermostats, controls, etc
Allow for necessary connections, terminations control wiring, etc. complete
Allow for condensate drain pipework, fittings, insulation, 'U' traps and connections to discharge into the nearest floor trap from all A/C equipments
Allow for testing and commissioning the air conditioning & ventilation installation
Allow for protection of all of the works in this section
Allow for any acoustic treatment to chillers, surroundings, other equipment, ducts, etc.
Any other items not included above but considered to have a monetary value by the Contractor are to be listed and priced below :
PROJECT NO. -1348PROPOSED OFFICE BUILDING
ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI
Page 2/77 BOQ(1/8)
BILL NO. 14
FIRE ALARM
A Repeater panel No.
B Fire alarm control panel No.
C interfacing unit No.
D Smoke detector No.
E Heat detector No.
F Fire voice evacuation speaker No.
G Fire alarm electric sounder No.
H Fireman Telephone No.
J -Ditto- weatherproof No.
K Break glass call bell unit No.
L Item
Supply and Fix Emergency Lighting
M Emergency light fittings No.
N Emergency light fitting with EXIT sign No.
P Emergency light fitting with EXIT + arrow sign No.
Q Central emergency battery cabinet No.
R Any Other Items
1
2
3
Fire alarm installation including all wiring, conduits, connections and the like
Allow for all interconnecting wiring, conduits, etc. for the system
Any other items not included above but considered to have a monetary value by the Contractor are to be listed and priced below :
PROJECT NO. -1348PROPOSED OFFICE BUILDING
ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI
Page 2/78 BOQ(1/8)
BILL NO. 15
FIRE PROTECTION
Extinguishers
A No.
B No.
C 5.0kg automatic dry powder fire extinguisher No.
Landing valve/ FHR/ Fire extinguisher cabinet
D No.
E - Ditto - surface mounted type No.
BILL NO. 15
FIRE PROTECTION
Wet Riser/ Sprinkler
A Fire Hose reel No.
B Landing valve with hose, etc. No.
C Item
D Item
4.5kg dry powder wall mounted hand operated extinguisher
5.0kg CO2 wall mounted hand operated extinguisher
Stainless steel mirror finish recessed type cabinet for FHR, Fire extinguishers and LV
Wet riser pipework system complete including all valves, flow switches, etc., as required, completed
Sprinkler pipework system complet including all valves, flow switches, etc., as required, complete
PROJECT NO. -1348PROPOSED OFFICE BUILDING
ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI
Page 2/79 BOQ(1/8)
E Item
F Sprinkler, pendent/ upright type Item
Breeching inlets (Dry Riser)
G Item
H Item
Sundries
J Item
K Item
L Item
BILL NO. 15
FIRE PROTECTION
Any Other Items
A
1
2
3
Fire Protection pump set 3 Nos. (1 electric + 1 deisel + 1 jockey) main pump 750 GPM @ 9.6 Bar, Jockey 40 GPM @@ 9.6 Bar including fuel storage tank, pipework, valves, connections, automatic control panel, controls, cabling, pressure and flow switches, fl
Twin Inlet breaching point complte with recessed decorative mirror finish stainless steel cabinet, complete
Breeching inlet pipework system including all valves as required, complete
Allow for all builders work in connection with the Fire Proetection Installation
Allow for testing and commissioning the fire protection installation
Allow for producing as built drawings and manuals
Any other items not included above but considered to have a monetary value by the Contractor are to be listed and priced below :
PROJECT NO. -1348PROPOSED OFFICE BUILDING
ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI
Page 2/80 BOQ(1/8)
ItemBILL NO. 16
GARBAGE DISPOSAL No.
Garbage Chute/ container trolley(Refer drwg.A-345)
A
B Supply and install Garbage bin trolley,capacity 2.50m3 each
Garbage chute complete as per drawing comprising chute vent, axial blowing exhauster, access door, draft control flap, flughing spray head, loose linen intake door at each floor, Chute tube, supporting frames, automatic brushing device, etc., complete
PROJECT NO. -1348PROPOSED OFFICE BUILDING
ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI
Page 2/81 BOQ(1/8)
BILL NO. 17 m3
EXTERNAL WORKS m3
PAVING m3
A Excavate oversite to reduce levels
B Backfill with selected excavated material
C Remove surplus excavated material from site m
D m
Kerbs m
E 150 x 305mm. Upstand kerb
F 150 x 225mm, Flush kerb
G
BILL NO. 17
EXTERNAL WORKS
Footpaths
A m2
Imported fill in making up levels compacted in layers
Precast hydraulically pressed concrete kerb with foundation and haunching, mortar including all necessary excavation, disposal and backfilling
Two coats of chlorinated rubber based quick drying paint in approved colours (black/yellow/white) to upstand kerbs
150mm thick aggregate road base, compacted to minimum CBR 80%, MDD 95%
PROJECT NO. -1348PROPOSED OFFICE BUILDING
ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI
Page 2/82 BOQ(1/8)
B m2
C 50 mm thick crushed sand bed, compacted m2
D
E Item
F Item
G
General
H Item
J Item
Electricity Operated Gate Barrier
K1
K2
60mm thick, interlocking concrete paving blocks, shape, size and colour as approved, laid in multi-colour and pattern on an includin 50mm thick sand bed.
150mm thick sub base type II, compacted to minimum CBR 30%, MDD 95%
150mm thick aggregate road base, compacted to minium CBR 80%, MDD 100%
Interlocking pavers, 80mm thick laid on land including 50mm thick sand bed in multi-colour and pattern to approval
Allow to all necessary works at existing road edge including saw cutting etc., to Municipality approval, as required
Allow to match new paving upto existing and form a neat, level joint
Road marking to external parking and driveway including all parking separation lines, arrows, hatching, etc., complete as shown on drawings and specifications
Electricity operated remote controlled/ card operated barrier full width across driveway, complete as shown on dwg. (Manufacturer's details and shop drawings to approval)
Gate barrier system at the ground floor entrance to and from the basement floor parking complete
Supply of remote control handsets OR electronic cards to Engineer's approval - (Total no. of parking + extra 10nos.)
PROJECT NO. -1348PROPOSED OFFICE BUILDING
ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI
Page 2/83 BOQ(1/8)
BILL NO. 17
EXTERNAL WORKS
Any Other Items
A
1
2
3
Amount Contractor's Total(AED) Mark-up (AED)Amount (AED)
50,000.00
200,000.00
600,000.00Provisional Sums
Item 350,000.00
1 Supply only Sanitary ware, Mixers, Accessories 20,000.00
2 Supply only Light Fittings 400,000.00
3 Passenger Lifts (2nos) 250,000.00
4 Supply & install cleaning Cradle system 15,000.00
5 20,000.00
6 Supply & install Structured Cabling System 2,000,000.00
7
Any other items not included above but considered to have a monetary value by the Contractor are to be listed and priced below :
Supply & install MATV/ SMATV system with cabling
Supply, install, testing & commissioning of Generator
PROJECT NO. -1348PROPOSED OFFICE BUILDING
ON PLOT NO. 373-1136 AT AL BARSHA FIRST, DUBAI
Page 2/84 BOQ(1/8)
8 Supply & install Building Directory
9 Supply & install Internal and External Signage
10 Contingency