Upload
others
View
10
Download
0
Embed Size (px)
Citation preview
Electrical Distribution System Installation Connection and Inspection
T HR EL 17001 ST
Standard
Version 1.0
Issued Date: 12 February 2015
Important Warning This document is one of a set of standards developed solely and specifically for use on public transport assets which are vested in or owned, managed, controlled, commissioned or funded by the NSW Government, a NSW Government agency or a Transport Agency (as defined in the Asset Standards Authority Charter). It is not suitable for any other purpose. You must not use or adapt it or rely upon it in any way unless you are authorised in writing to do so by a relevant NSW Government agency. If this document forms part of a contract with, or is a condition of approval by a NSW Government agency, use of the document is subject to the terms of the contract or approval. This document may not be current. Current standards are available for download from the Asset Standards Authority website at www.asa.transport.nsw.gov.au.
© State of NSW through Transport for NSW
T HR EL 17001 ST Electrical Distribution System Installation Connection and Inspection
Version 1.0 Issued Date: 12 February 2015
Standard governance
Owner: Lead Electrical Engineer, Asset Standards Authority
Authoriser: Chief Engineer Rail, Asset Standards Authority
Approver: Director, Asset Standards Authority on behalf of ASA Configuration Control Board
Document history
Version Summary of change
1.0 First issue as T HR EL 17001 ST superseding TS: 11000 Updated details of forms in Section 13.
For queries regarding this document, please email the ASA at [email protected] or visit www.asa.transport.nsw.gov.au
© State of NSW through Transport for NSW
T HR EL 17001 ST Electrical Distribution System Installation Connection and Inspection
Version 1.0 Issued Date: 12 February 2015
Preface The Asset Standards Authority (ASA) is an independent unit within Transport for NSW (TfNSW)
and is the network design and standards authority for defined NSW transport assets.
The ASA is responsible for developing engineering governance frameworks to support industry
delivery in the assurance of design, safety, integrity, construction, and commissioning of
transport assets for the whole asset life cycle. In order to achieve this, the ASA effectively
discharges obligations as the authority for various technical, process, and planning matters
across the asset life cycle.
The ASA collaborates with industry using stakeholder engagement activities to assist in
achieving its mission. These activities help align the ASA to broader government expectations of
making it clearer, simpler, and more attractive to do business within the NSW transport industry,
allowing the supply chain to deliver safe, efficient, and competent transport services.
The ASA develops, maintains, controls, and publishes a suite of standards and other
documentation for transport assets of TfNSW. Further, the ASA ensures that these standards
are performance based to create opportunities for innovation and improve access to a broader
competitive supply chain.
This document has been developed by the Chief Engineer Rail section of the Asset Standards
Authority, reviewed by a committee of TfNSW cluster representatives, and approved by the
Asset Standards Authority Configuration Control Board.
This document details the requirements for connection of installations, or installations proposed
to be connected to the RailCorp distribution system.
The document complies with the requirements of the Electricity Supply (Safety and Network
Management) Regulation 2008 and the Service and Installation Rules for NSW August 2012.
This document replaces TS 11000 Electrical Distribution System Installation Connection and
Inspection that superseded RailCorp standard EP 17 00 00 06 SP Installation Inspections.
This document is to be read in conjunction with chapter 2, Customer Installation Safety of
EP 95 00 30 03 SP RailCorp Network Management Plan and T HR EL 17000 ST Demarcation
of RailCorp Low Voltage Distribution System Version 1.0.
The significant changes to TS 11000 include update to forms referenced in Section 13.
© State of NSW through Transport for NSW Page 3 of 29
T HR EL 17001 ST Electrical Distribution System Installation Connection and Inspection
Version 1.0 Issued Date: 12 February 2015
Foreword Sections relating to internal procedures and forms associated with the distribution network
service provider (DNSP) have been carried forward from the previous RailCorp standard, while
developing this standard.
The document includes those internal procedures and forms and is published on behalf of the
DNSP on the ASA website. This has been done to ensure that relevant requirements are not
lost. In future editions it is envisaged that some or all of these will be incorporated into internal
DNSP documents.
© State of NSW through Transport for NSW Page 4 of 29
T HR EL 17001 ST Electrical Distribution System Installation Connection and Inspection
Version 1.0 Issued Date: 12 February 2015
Table of contents 1. Introduction ............................................................................................................................................ 6 2. Purpose ................................................................................................................................................... 6 2.1. Scope ..................................................................................................................................................................... 6 2.2. Application ............................................................................................................................................................. 6 3. Reference documents ........................................................................................................................... 7 4. Terms and definitions ........................................................................................................................... 8 5. Organisational responsibilities .......................................................................................................... 10 6. Electricity supplies .............................................................................................................................. 10 6.1. Relationship of this document to legislation and the customer installation safety plan .............................. 11 6.2. Accredited service providers ............................................................................................................................. 11 7. Installation owner or custodian responsibilities .............................................................................. 11 7.1. Safety of installation ........................................................................................................................................... 11 7.2. Qualified electricians .......................................................................................................................................... 11 8. Distribution network service provider responsibilities ................................................................... 12 9. Applying for connection of a new installation or an alteration to an existing installation .......... 12 9.1. Process ................................................................................................................................................................ 12 9.2. Small scale renewable energy micro generation systems .............................................................................. 13 10. Notification of electrical works ........................................................................................................... 13 10.1. Local DNSP connection ...................................................................................................................................... 14 10.2. Tests required...................................................................................................................................................... 14 10.3. Installations not to be connected ...................................................................................................................... 15 11. Inspections ........................................................................................................................................... 15 11.1. Work requiring inspection .................................................................................................................................. 15 11.2. Electrical testing methodology .......................................................................................................................... 17 11.3. Defects ................................................................................................................................................................. 17 11.4. Inspection reports ............................................................................................................................................... 18 11.5. Disciplinary action .............................................................................................................................................. 18 11.6. Qualifications of installation inspectors ........................................................................................................... 19 12. Audit inspections ................................................................................................................................. 20 13. Forms .................................................................................................................................................... 20 Appendix A - Discretionary inspections flowchart ..................................................................................... 21 A.1 Preliminary assessment stage ........................................................................................................... 21 A.2 Assessed contractor stage ................................................................................................................. 21 A.3 Defects .................................................................................................................................................. 22 Appendix B - Installation inspection flowchart ........................................................................................... 23 Appendix C - Visual inspection checklist .................................................................................................... 24 Appendix D - Guidelines for completing defect forms ............................................................................... 27
© State of NSW through Transport for NSW Page 5 of 29
T HR EL 17001 ST Electrical Distribution System Installation Connection and Inspection
Version 1.0 Issued Date: 12 February 2015
1. Introduction Each distribution network service provider (DNSP) has a legislative responsibility to ensure that
installations connected to its distribution system are safe and do not pose a risk to life, health, or
property. This is to protect the consumer and also to protect the DNSP so that its system
reliability is not jeopardised by unauthorised or faulty installations.
2. Purpose This document details the requirements for connection of installations, or installations proposed
to be connected to the RailCorp distribution system.
2.1. Scope This standard provides the requirements for the following aspects of installations and
inspections:
• the application process for connection of a new installation or alteration to an existing
installation; commonly called the 'Application for Connection'
• the notification process for the self test regime of electrical works; commonly called the
'Certificate of Compliance - Electrical Works'
• the distribution network service provider inspection and testing regime
2.2. Application This document applies to the following:
• all installations connected or proposed to be connected to the RailCorp distribution system
• all installations connected or proposed to be connected to the local distribution network
service provider system via an isolating transformer
This document does not apply to high voltage installations, the 1500 V dc railway traction
system or the railway signalling system.
This document applies to all installation owners or custodians and their electrical contractors, all
Transport for NSW, Sydney Trains, NSW Trains or other rail transport entity employees.
© State of NSW through Transport for NSW Page 6 of 29
T HR EL 17001 ST Electrical Distribution System Installation Connection and Inspection
Version 1.0 Issued Date: 12 February 2015
3. Reference documents Australian standards
AS/NZS 2381 Electrical equipment for explosive gas atmospheres - Selection, installation and
maintenance Set
AS/NZS 3000 Wiring Rules
AS/NZS 3017 Electrical Installations – Testing and Inspection Guidelines
AS/NZS 4777 Grid connection of energy systems via inverters
Transport for NSW standards
EP 12 00 00 02 SP Low Voltage Distribution and Installations Earthing References and
Definitions
EP 12 10 00 10 SP System Substation Earthing
EP 12 10 00 11 SP Distribution Substation Earthing
EP 12 10 00 20 SP Low Voltage Distribution Earthing
EP 12 10 00 21 SP Low Voltage Installations Earthing
T HR EL 17000 ST Demarcation of RailCorp Low Voltage Distribution System
EP 95 00 30 03 SP RailCorp Network Management Plan Chapter 2 - Customer Installation
Safety
ESB E001 Low Voltage Electrical Standards
T HR EL 17001 F1 Information regarding applications for connection
T HR EL 17001 F2 Application for Connection
T HR EL 17001 F3 Application for Temporary Connection
Legislation
NSW Electricity Supply Act 1995
Electricity Supply (General) Regulation 2001
Electricity Supply (Safety and Network Management) Regulation 2008
Electricity (Consumer Safety) Act 2004
Electricity (Consumer Safety) Regulation 2006
Home Building Act, 1989
© State of NSW through Transport for NSW Page 7 of 29
T HR EL 17001 ST Electrical Distribution System Installation Connection and Inspection
Version 1.0 Issued Date: 12 February 2015
Other references
Service and Installation Rules of New South Wales 2012
Code of Practice (Electricity) - Service and Installation Rules of New South Wales 2007
Code of Practice – Distribution Risk Management 1998
NSW Department of Energy and Water Code of Practice – Installation Safety Management
1997, Appendix 2
Electricity Association of NSW Guide to the Training of Personnel Working on or Near Electricity
Works 1999
Certificate of compliance – Electrical Work (Office of Fair Trading)
4. Terms and definitions The following terms and definitions apply in this document:
application for connection a document submitted to the DNSP requesting approval to connect
a new installation or change the loading of an existing installation
authorised electrician a person who is authorised under the Home Building Act 1989 to do
electrical wiring work
CCEW Certificate of Compliance - Electrical Work
custodian the person that has responsibility for an installation
DNSP distribution network service provider a person who owns or controls a distribution
system
distribution system the electricity power lines and associated equipment and electricity
structures that are used to convey and control the conveyance of electricity:
(a) to the premises of wholesale and retail customers, up to the point of supply in relation to the
premises (which may or may not be situated on the building or land comprising the premises),
or
(a1) from the premises of regulated offer customers that have a complying generator installed
and connected from the point of supply to the premises, or
(b) to, from and along the rail network electricity system,
but does not include a transmission system or any lines, equipment and structures prescribed
by the regulations.
EDU electrical distribution unit the name of the business unit accountable for the rail
transport DNSP responsibilities. The EDU currently resides in Sydney Trains.
© State of NSW through Transport for NSW Page 8 of 29
T HR EL 17001 ST Electrical Distribution System Installation Connection and Inspection
Version 1.0 Issued Date: 12 February 2015
electrical installation as defined by the Electricity (Consumer Safety) Act 2004: any fixed
appliances, wires, fittings, apparatus or other electrical equipment used for (or purposes
incidental to) the conveyance, control and use of electricity in a particular place, but does not
include any of the following:
(a) Any electrical equipment used, or intended for use, in the generation, transmission or
distribution of electricity that is:
(i) Owned or used by an electricity supply authority, or
(ii) Located in a place that is owned or occupied by such an authority.
(b) Any electrical article connected to, and extending or situated beyond, any electrical outlet
socket.
(c) Any electrical equipment in or about a mine.
(d) Any electrical equipment operating at not more than 50 volts alternating current or 120 volts
ripple-free direct current.
(e) Any other electrical equipment, or class of electrical equipment, prescribed by the
regulations.
electrical installation work means the work of installing, adding to, altering, disconnecting,
reconnecting or replacing an electrical installation
LDNSP local distribution network service provider an organisation which owns and controls
the principal distribution system in the geographical distribution area in which the installation is
located
The geographical areas of the LDNSP's are defined in the Service and Installation Rules of
NSW.
LV low voltage exceeding 50 V ac or 120 V ripple-free dc but not exceeding 1000 V ac or
1500 V dc
HV high voltage a voltage exceeding 1000 V ac or 1500 V dc
isolating transformer a transformer with protective separation between the input and output
windings. It is used to separate the earthing systems between the RailCorp distribution system
and the LDNSP.
qualified electrician see authorised electrician
switchboard an assembly of circuit protective devices, with or without switchgear, instruments
or connecting devices, suitably arranged and mounted for distribution to, and protection of, one
or more submains or final subcircuits or a combination of both.
switchboard, main a switchboard from which the supply to the whole electrical installation can
be controlled
© State of NSW through Transport for NSW Page 9 of 29
T HR EL 17001 ST Electrical Distribution System Installation Connection and Inspection
Version 1.0 Issued Date: 12 February 2015
Sydney Metropolitan Rail Area area bounded by Newcastle (in the north), Richmond (in the
northwest), Bowenfels (in the west), Macarthur (in the southwest) and Bomaderry (in the south),
and all connection lines and sidings within these areas, but excluding private sidings
5. Organisational responsibilities Rail Corporation New South Wales (RailCorp) is the holding and property management
company for major rail and rail property assets in the Sydney Metropolitan Rail Area. The
railway electrical distribution system is the 'RailCorp Distribution System'.
The RailCorp distribution system is generally located within the Sydney Metropolitan Rail Area,
bounded by the geographical extremities as follows:
• Hamilton in the North
• Kiama in the South
• Wallerawang in the West (Bowenfels is the extent of the 1500 V dc system)
• Glenlee (Campbelltown) in the South West
Electrical distribution unit (EDU) within Sydney Trains is the distribution network service provider
(DNSP) for all installations covered by the application of this standard within the Sydney
Metropolitan Rail Area.
The Service and Installation Rules of NSW nominate RailCorp as the DNSP and will
be updated to Sydney Trains with the next edition.
The Asset Standards Authority (ASA) publishes the standards applicable to the RailCorp
distribution system including installations.
The local distribution network service providers (LDNSPs) are Ausgrid, Endeavour Energy and
Essential Energy.
6. Electricity supplies Electricity supplies to installations within the Sydney Metropolitan Rail Area are either derived
directly from the RailCorp high voltage (HV) distribution network or from the local distribution
network service provider via an isolating transformer. This isolating transformer forms part of the
RailCorp low voltage (LV) distribution network. In these situations the EDU becomes the DNSP
from the secondary terminals of the isolating transformer.
The demarcation of supplies is documented in T HR EL 17000 ST Demarcation of RailCorp Low
Voltage Distribution System.
© State of NSW through Transport for NSW Page 10 of 29
T HR EL 17001 ST Electrical Distribution System Installation Connection and Inspection
Version 1.0 Issued Date: 12 February 2015
6.1. Relationship of this document to legislation and the customer installation safety plan The Electricity Supply (Safety and Network Management) Regulation requires DNSPs to have
plans in place to manage specific aspects of their distribution systems. One of the requirements
is the management of customer installation safety.
The customer installation safety plan is provided in chapter 2 of EP 95 00 30 03 SP RailCorp
Network Management Plan and governs all installations within the electrified rail corridor. This
plan addresses the specific rail requirements associated with installations, including
requirements detailed in the Service and Installation Rules of NSW.
6.2. Accredited service providers The customer installation safety plan does not include an accreditation system for contestable
works on the RailCorp distribution system.
Connections to the network can only be carried out either by or under the direction of
DNSP-authorised staff.
7. Installation owner or custodian responsibilities Installation owners or custodians are responsible for the following:
• safety of installations
• ensuring that electrical works are performed by qualified electricians
7.1. Safety of installation Installation owners or custodians are responsible for the maintenance of their installations to
ensure the safety of persons and property and the prevention of bushfires.
7.2. Qualified electricians To carry out electrical works on installations, electrical contractors shall be fully licensed in
accordance with the Home Building Act, 1989.
The licenses are administered by the Office of Fair Trading NSW.
Installation owners or custodians are responsible for ensuring that any contractor or trades
person they engage to carry out electrical works are appropriately licensed. In the case of
project works the custodian is deemed to be the project manager.
© State of NSW through Transport for NSW Page 11 of 29
T HR EL 17001 ST Electrical Distribution System Installation Connection and Inspection
Version 1.0 Issued Date: 12 February 2015
8. Distribution network service provider responsibilities The DNSP is responsible for the following:
• managing applications for connections and associated network loadings
• monitoring the standard of electrical work
• confirming that appropriate testing procedures have been implemented by the installing
electrical contractor
To achieve its responsibilities, the DNSP has an inspection program to monitor the performance
of electrical contractors.
9. Applying for connection of a new installation or an alteration to an existing installation Submitting a completed Application for Connection form is a mandatory requirement for all new
connections or connection alterations. The electrical contractors or installers acting on behalf of
the installation owner or custodian behalf shall complete the standard Application for
Connection form. For project work this may be done by the AEO designer as part of the design
deliverables.
Where a temporary connection is required for a short time and at the conclusion of that time no
connection will be needed. For example, for construction of a bridge, then the Application for a
Temporary Connection form shall be used.
Refer to Section 13 for the list of forms available.
9.1. Process Applications are to be submitted in accordance with the details embedded on the Application for
Connection form.
The relevant installation inspector, or their representative, will determine if the associated
substation and the supply main switchboard have the capacity to supply any additional load
required.
For alterations to existing installations, the installing electrical contractor or AEO designer is
responsible to determine if the installation has the capacity to accept additional load and to
design the installation accordingly. The installation owner or custodian shall be consulted to
approve any increased electrical load.
For services originating from a LDNSP, the Application for Connection form shall be submitted
to the LDNSP with a copy to the DNSP.
© State of NSW through Transport for NSW Page 12 of 29
T HR EL 17001 ST Electrical Distribution System Installation Connection and Inspection
Version 1.0 Issued Date: 12 February 2015
9.2. Small scale renewable energy micro generation systems Small scale renewable energy micro generation systems include solar, wind and biomass.
These systems shall only be connected to the network via an inverter that complies with
AS4777 and has a capacity no more than 10 kW for single phase connections or 30 kW for
three phase connections.
The installing electrical contractor or AEO designer shall demonstrate that the design satisfies
the criteria as specified in Clause 8.6.3 of Service and Installation Rules of NSW prior to
approval.
10. Notification of electrical works All electrical installation work shall be tested to verify compliance with AS/NZS 3000, the
Service and Installation Rules of NSW, and relevant standards, before being permanently
connected to the supply.
Compliance is the responsibility of the installing electrical contractor.
The current Office of Fair Trading NSW Certificate of Compliance Electrical Work (CCEW) form
shall be used by electrical contractors for notifying the DNSP of electrical installation work as
required by the Electricity (Consumer Safety) Regulation 2006. Supplies of compliance
certificates can be obtained from electrical wholesalers.
The NSW Electricity (Consumer Safety) Regulation obligates electrical contractors to provide a
completed CCEW form to installation owners or custodians and the DNSP covering the details
of their electrical installation work, the required test results, and who carried out the work.
The CCEW is to be submitted to the DNSP for all electrical work carried out on an
installation contrary to note 1 in the Guide to the Testing, Connection and Notification
Requirements for different types of electrical installation work section of Certificate of
Compliance Electrical Work.
A CCEW form shall be submitted to the DNSP within 14 days after the completion of any safety
and compliance tests.
A separate CCEW is required to be submitted to the DNSP after correcting any notified defect in
an installation.
All CCEW forms shall be completed in full, with particular attention to the following details:
• clear identification of the customer’s address and contact number
• clear identification of the repairs carried out or load to be connected
© State of NSW through Transport for NSW Page 13 of 29
T HR EL 17001 ST Electrical Distribution System Installation Connection and Inspection
Version 1.0 Issued Date: 12 February 2015
• actual test values for the earthing system integrity and insulation resistance for the 'Test
Report' section
• legible signature and license details entered by the electrical contractor for the certification
section
If the CCEW form has not been clearly or correctly completed then the installation inspector will
return the form to the person submitting it, advising that a new or suitably corrected CCEW form
shall be resubmitted within five working days. Failure to comply with these requirements shall
initiate disciplinary action.
In the case of work that is discovered other than by way of a CCEW form, the installation
inspector shall inform the installation owner or custodian that the work has not been notified and
that a CCEW shall be submitted.
In the event of the installation being a RailCorp asset then the installation inspector is to report
to the line manager responsible for the premises or their representatives, in accordance with the
DNSP safety management process.
10.1. Local DNSP connection For new connections to a LDNSP a Certificate of Compliance - Electrical Work (CCEW) shall be
submitted to the LDNSP concerning the connection to their network at the completion of the
works. Simultaneously, the CCEW concerning the installation connected to the isolating
transformer shall be submitted to the DNSP.
For alterations or additions to existing connections the CCEW shall be submitted to the DNSP.
10.2. Tests required All electrical installation work shall be tested to verify compliance with AS/NZS 3000, the
Service and Installation Rules of NSW and relevant standards, before permanently connected to
the supply.
The minimum inspection shall include testing the work in accordance with the requirements of
the NSW Department of Energy and Water Code of Practice – Installation Safety Management,
Appendix 2.
The test methods shall adhere to the Electrical Installation Testing Guidelines offered in
AS/NZS 3017, and use calibrated instruments which are periodically checked to ensure they
remain operational and safe.
Test results shall ensure all the outcomes specified in Clause 1.8 of AS/NZS 3000 are
established.
© State of NSW through Transport for NSW Page 14 of 29
T HR EL 17001 ST Electrical Distribution System Installation Connection and Inspection
Version 1.0 Issued Date: 12 February 2015
10.3. Installations not to be connected Installation work can only be connected to the electricity supply once testing and inspection
activities prove compliance with the following standards and codes of practice:
• AS/NZS 3000 and supporting standards
• Service and Installation Rules of NSW
• Transport for NSW Standards
For the following installation work, connection to the electricity supply can only be carried out by
an individual who has been, or is supervised by a person, appropriately authorised by the DNSP
and possesses formal training with respect to the task undertaken:
• consumers mains and main switchboard
• installations in environments classified as hazardous areas by relevant Australian
Standards including AS/NZS 2381 Section 1
11. Inspections The Distribution Network Service Provider (DNSP) shall carry out inspections of selected new
installations, additions and alterations to existing installations for compliance with the relevant
codes, regulations and standards.
The inspection shall consist of a visual examination to check compliance with the rules, the level
of technical expertise for finish of the work, and includes sufficient testing to verify that the
electrical contractor has performed the appropriate tests.
The inspection shall include a thorough visual check of the earthing system to ensure that it
meets dc traction system special requirements.
All inspections will be carried out within three months of receipt of notification of electrical works.
11.1. Work requiring inspection New installations, additions and alterations to installations shall be subject to mandatory and
discretionary inspections.
The inspection of additions and alterations is limited to that portion of the installation set out in
the Certificate of Compliance Electrical - Work, unless during the installation it is obvious that
portions of the existing installation are defective and immediately dangerous.
Installations requiring a mandatory inspection shall not be placed in service until a complete
installation inspection has been performed.
© State of NSW through Transport for NSW Page 15 of 29
T HR EL 17001 ST Electrical Distribution System Installation Connection and Inspection
Version 1.0 Issued Date: 12 February 2015
Where an installation is found to have been energised by an unauthorised contractor prior to
inspection, it shall be inspected and the matter referred to the Manager, EDU.
If the installation is found to be immediately dangerous, the defective portion is to be
disconnected from the supply and danger tagged out of service. A defect notice is then to be
issued.
All work that has been found to be defective shall be reinspected.
Installation inspections are separate to the 'self test' which are to be carried out after
every job in accordance with Clause 33 of the Electricity (Consumer Safety)
Regulation 2006.
11.1.1. Mandatory inspections
Clause 3.8 of the NSW Department of Water & Energy Code of Practice – Installation Safety
Management states the following installation work, as applicable to this standard, shall be
inspected:
• consumers mains and main switchboards
• installations in environments classified as hazardous areas by AS/NZS 2381 Section 1
All other installation work shall be inspected on a discretionary basis.
11.1.2. Discretionary inspections The DNSP will carry out discretionary inspections of selected installations based upon the
following broad criteria:
• the type of installation work involved
• whether the work is major or minor job
• location whether the works are accessible to the public
• risk profile
• the electrician’s previous performance in that particular type of work
Inspection requirements, in terms of percentage of work to be inspected, will be periodically
reviewed as the familiarity of installing contractors in the market changes, in particular with
demonstrated knowledge of Transport for NSW standards.
11.1.3. Progress inspections Where any part of the electrical installation will be concealed such as underground or behind a
lined wall, then it may be appropriate for progress inspections to be carried out during the
© State of NSW through Transport for NSW Page 16 of 29
T HR EL 17001 ST Electrical Distribution System Installation Connection and Inspection
Version 1.0 Issued Date: 12 February 2015
installation. Such inspections may be initiated locally and without receipt of formal notification
from the electrical contractor.
11.2. Electrical testing methodology AS/NZS 3017:2007 and AS/NZS 3000:2007 section 6, provides guidelines for testing of
electrical installations.
The procedures for carrying out the electrical tests that form part of an installation inspection are
set out in the DNSP procedures.
11.3. Defects Work that does not comply with AS/NZS 3000, Service and Installation Rules of NSW and
Transport for NSW Standards shall be considered to be defective.
All defective work shall be notified to the customer and to the installing contractor. Three copies
of any notification shall be produced:
• customer's copy
• installing contractor's copy
• DNSP copy, which is held by the DNSP installation inspector
Each notification is to be uniquely numbered.
All defect correction work is required to be reinspected.
11.3.1. Major defects Major defects are those considered to present a high risk safety hazard to life, health or
property. Electrical installation work containing major defects shall not be connected to the
network. Major defects are listed in the NSW Department of Water and Energy Code of Practice
- Installation Safety Management, Appendix 3.
If major defects are encountered during an inspection, the installation inspector shall isolate the
section of the installation containing the major defect if possible. If this is not possible the entire
electricity supply to the installation may need to be disconnected.
If any part of the electrical installation is disconnected it shall be suitably tagged with a warning
not to connect and the nature of the defect.
If the disconnection of a defective installation results in subsequent hazards or the installation is
considered system critical then the defect shall be rectified immediately. For example, station
lighting defects or the Rail Management Centre. The installation owner or custodian is also to be
notified immediately.
© State of NSW through Transport for NSW Page 17 of 29
T HR EL 17001 ST Electrical Distribution System Installation Connection and Inspection
Version 1.0 Issued Date: 12 February 2015
11.3.2. Minor defects Minor defects are defects that are not considered to be major defects.
For minor defects, a period of 21 days grace is allowed for the defects to be rectified. If it is not
rectified within this period a 'final notice' is to be forwarded to the installation owner or custodian.
If it is still not rectified within 14 days of the date of the final notice then the matter is to be
discussed with the installation owner or custodian before disconnecting supply.
11.3.3. Reinspection Work will not to be reinspected until a notification that the work is ready for reinspection has
been received by the DNSP. Notification is via a new CCEW form.
The DNSP will have a follow up system to ensure CCEW forms for reinspection are received.
Costs associated with reinspection will be charged to the installing electrical contractor.
11.3.4. Defects in other parts of the installation If during an inspection of a consumers’ installation other parts of the installation not indicated on
the CCEW form is found to be dangerous, or is likely to become dangerous, then the installation
inspector is to report the defect in accordance with the DNSP procedures.
The inspector shall list the identified defects and address a hazard report to the installation
owner or custodian responsible for the premises, or their representative, in accordance with the
DNSP safety action management process.
If the supply to the installation is not disconnected at the time of inspection, then the hazard
report shall include the period within which the installation is to be made safe or otherwise
supply will be disconnected.
The installation shall be reinspected after that period has expired to ensure that the installation
has been made safe.
11.4. Inspection reports Results of inspections shall be recorded.
Inspections records shall be maintained for a minimum of seven years.
11.5. Disciplinary action If a person breaches any law applicable to the provision of electricity supply, electrical safety or
electrical installation work, the DNSP may report that person to the appropriate authority or take
legal action itself. The action taken will depend on the seriousness of the breach, or the
frequency of breaches. The DNSP may also disconnect the installation from the network.
© State of NSW through Transport for NSW Page 18 of 29
T HR EL 17001 ST Electrical Distribution System Installation Connection and Inspection
Version 1.0 Issued Date: 12 February 2015
Breaches occur where a person or contractor undertakes one of the following activities:
• carries out installation work that is defective or unsafe
• fails to carry out the required tests
• fails to notify the DNSP after carrying out electrical installation work
• deceives or attempts to deceive any of the DNSP employees as to any fact, matter or thing
relating to an electrical installation
• makes a representation in any document in relation to any electrical installation, which they
have supplied, that is false or misleading
• connects an electrical installation to the RailCorp network without the DNSP approval
• fails to rectify defects when notified
Disciplinary action may include the following:
• issuing a verbal or written warning
• issuing a formal interview or counselling
• referring an electrical contractor to the Office of Fair Trading
• referring to the Commercial Tribunal
11.6. Qualifications of installation inspectors DNSP personnel that assume an installation inspector role as part of their daily activities shall
be qualified according to the type of installation. Types of installations include the following:
• low voltage installations
• consumers' aerial lines
11.6.1. Low voltage installations Inspectors of low voltage installations shall meet the following requirements:
• hold a supervisor certificate (electrician) or a contractor licence (electrical) issued by the
Office of Fair Trading or approved equivalent which entitles them to work without
supervision
• have demonstrated the necessary knowledge of TfNSW Standards and testing
requirements
• hold a current Rail Industry Safety Induction card
• have a minimum of five years experience working as a qualified electrician
© State of NSW through Transport for NSW Page 19 of 29
T HR EL 17001 ST Electrical Distribution System Installation Connection and Inspection
Version 1.0 Issued Date: 12 February 2015
11.6.2. Consumer aerial line Inspectors of consumer aerial line installations shall meet the following requirements:
• be qualified and have met the requirements of the Electricity Association of NSW Guide to
The Training of Personnel Working on or Near Electricity Works to inspect and test
overhead lines
• have the necessary knowledge and experience, in particular to TfNSW Standards, to
undertake the inspection of the particular type of work to be inspected
11.6.3. Installations located within hazardous areas inspector qualifications For installations located within hazardous areas installation inspectors shall be appropriately
trained and qualified to carry out hazardous area inspections.
12. Audit inspections Audit inspections will be carried out to observe that legislative requirements have been met with
regard to electrical installations, installing contractors and the inspection and testing function to
measure the effectiveness of the installation inspection program.
The frequency of the audits will be at a level which contributes to maintaining or exceeding
existing minimum safety outcomes.
Audit inspections will be coordinated by the Manager EDU, Sydney Trains.
13. Forms The following forms are available on the ASA website and are used when implementing this
standard:
• T HR EL 17001 F1 Information regarding applications for connection
• T HR EL 17001 F2 Application for Connection
• T HR EL 17001 F3 Application for Temporary Connection
© State of NSW through Transport for NSW Page 20 of 29
T HR EL 17001 ST Electrical Distribution System Installation Connection and Inspection
Version 1.0 Issued Date: 12 February 2015
Appendix A - Discretionary inspections flowchart Discretionary inspections follow a process that includes the following stages:
• preliminary assessment stage
• assessed contractor stage
• defect identification
Figure 1 shows the discretionary inspections process.
Figure 1 Discretionary inspections
A.1 Preliminary assessment stage The first three Certificate of Compliance Electrical Work (CCEW) jobs received from each
electrical contractor are to be assigned for an inspection.
If there are no major defects in three consecutive jobs, then the contractor's jobs move to the
'Assessed Contractor' stage.
A.2 Assessed contractor stage Additional jobs received from an electrical contractor will be inspected depending on the risk
profile.
If access is not available, another job may be assigned for inspection or access to the job
arranged for a later date at the discretion of the inspector.
If no major defects are detected during the inspection, the 'Assessed Contractor' stage
continued as more jobs are notified.
© State of NSW through Transport for NSW Page 21 of 29
T HR EL 17001 ST Electrical Distribution System Installation Connection and Inspection
Version 1.0 Issued Date: 12 February 2015
A.3 Defects If a major defect is detected during an inspection, the contractor is moved back to the
'Preliminary inspection' stage.
Major defect details for the jobs are to be recorded in the inspector's database for each
contractor.
© State of NSW through Transport for NSW Page 22 of 29
T HR EL 17001 ST Electrical Distribution System Installation Connection and Inspection
Version 1.0 Issued Date: 12 February 2015
Appendix B - Installation inspection flowchart Figure 2 shows the installation inspection process.
Figure 2 Installation inspection flowchart
© State of NSW through Transport for NSW Page 23 of 29
T HR EL 17001 ST Electrical Distribution System Installation Connection and Inspection
Version 1.0 Issued Date: 12 February 2015
Appendix C - Visual inspection checklist The visual inspection checklists for the following categories are provided in Table 1 through
Table 6:
• general
• consumer mains
• switchboards
• wiring systems
• electrical equipment
• earthing
Table 1 - Visual inspection checklist for general category
Inspection aspect Comments / Example Protection against direct contact with live parts
Insulation, enclosure
Protection against indirect contact with exposed conductive parts
Double insulation or isolating transformers
Protection against hazardous parts Enclosure, guarding or screening of flammable materials, hot surfaces and parts that may cause physical injury
Protection against spread of fire Penetration of fire barriers General condition of the electrical equipment
Signs of damage that could impair safe operation, disconnection of unused electrical equipment
All wiring and equipment which could be susceptible to mechanical damage is adequately protected
-
Insulated joints in any continuous earthed metallic structure
Fencing, water pipes
Table 2 – Visual inspection checklist for consumer mains
Inspection aspect Comments / Example Sufficient current carrying capacity - Voltage drop with allowable limits - Installation conditions Enclosure, depth of burial, mechanical protection
and other conditions affecting the de-rating of any cabling
Aerial installation conditions - Connection of wiring - Protection against external influences -
© State of NSW through Transport for NSW Page 24 of 29
T HR EL 17001 ST Electrical Distribution System Installation Connection and Inspection
Version 1.0 Issued Date: 12 February 2015
Table 3 – Visual inspection checklist for switchboards
Inspection aspect Comments / Example Location Suitable access and egress Protective devices Overload
rating and residual current rating, fault current
Isolating devices Main switches, isolating transformers
Connection devices Neutral and earth bars, and active links
Connection and switchgear
fixing of wiring and -
Correct identification electrical equipment
and labelling of Neutral/active labelling
Protection against external influences -
Table 4 – Visual inspection checklist for wiring systems
Inspection aspect Comments / Example Conductor size Current-carrying capacity and voltage drop
Identification of cable cores -
Adequate support and fixing -
Connections and enclosures -
Particular installation conditions Underground, aerial, emergency systems
Segregation from other services and electrical installations
-
Protection against external influences Enclosure
Table 5 – Visual inspection checklist for electrical equipment
Inspection aspect
Comments / Example Isolation and switching devices for protection against injury from mechanical
-
Isolation and switching devices for protection against thermal effects
Motors, room heaters, water heaters
Switching devices for particular electrical equipment
Socket outlets, cooking appliances
Particular installation conditions and the suitability for connection of the equipment
Locations affected by water, explosive atmospheres, extra- low voltage, high voltage
Compliance with required Standard -
Connection, support and fixing -
Protection against external influences -
© State of NSW through Transport for NSW Page 25 of 29
T HR EL 17001 ST Electrical Distribution System Installation Connection and Inspection
Version 1.0 Issued Date: 12 February 2015
Table 6 – Visual inspection checklist for earthing
Inspection aspect Comments / Example Earth/Neutral connection at transformer/switchboard (where applicable)
-
Earth grid - Earthing conductors Size, identification
Equipotential bonding conductors Size, identification
Connections, joints and terminations -
Protection against external influences -
Correct connection to earthing ements farrang e or other systems (Not
Signalling, communications, traction
Creation of ear thed situation that mayrequire earthing of additional electrical
-
© State of NSW through Transport for NSW Page 26 of 29
T HR EL 17001 ST Electrical Distribution System Installation Connection and Inspection
Version 1.0 Issued Date: 12 February 2015
Appendix D - Guidelines for completing defect forms Following is an extract of section 9 & 10 of the Energy Authority of NSW publication -
“Recommend Standard Inspection Procedure for Existing Electrical Installations” (June 1981). It
is included as guidance to inspectors in completing defect forms.
9. REPORTS TO CONSUMERS
9.1 Reports of defects or unsatisfactory conditions found in installations should be set
out in such a manner that they will be clearly understood by the consumer or his contractor and
so as to assist the contractor as much as possible in locating and identifying the faulty portion
and in determining what action he must take to remedy the fault.
9.2 Each item of the report should consist of a clear statement describing the defective
condition. Attempts to set out the method of rectifying the fault should be avoided. For
example, if it is found that trees and vines have grown up and fouled aerial conductors, the
report should read somewhat as follows:
“The aerial conductors to the garage were fouled by trees and vines”.
and NOT
“Trees and vines, fouling aerial conductors to the garage, to be cut back”.
(The consumer may prefer to rectify the defect by raising or re-routing the aerial
conductor instead of by cutting his trees.)
9.3 It is, of course, important to identify the particular portion of the installation to which
the report refers in order that the contractor will not be in doubt as to the portion requiring
attention.
9.4 In setting out the results of their inspection, Inspectors should appreciate the
importance of always using correct terms, and should remember that the use of “trade jargon”
frequently leads to serious misunderstandings. Experience has shown that if the correct terms
are consistently used by the inspection officers, they will always be understood by Electrical
Contractors and will be rapidly adopted by them.
9.5 The words “not satisfactory” or “unsatisfactory” should not be used to avoid
specifying defects. Such an expression, however, may be used to describe a condition
provided it us qualified by stating the reason or reasons why it is not satisfactory. It may also be
used in the case where the whole of an installation is found to be in such bad condition that
there would be little point in specifying particular defects. Such a report would read:
“The whole of the installation was in such an unsatisfactory condition that it requires a complete
overhaul”.
10. SAMPLE DEFECT STATEMENTS
© State of NSW through Transport for NSW Page 27 of 29
T HR EL 17001 ST Electrical Distribution System Installation Connection and Inspection
Version 1.0 Issued Date: 12 February 2015
10.1 The following sample statements indicate the proper method of reporting defects
that will commonly be found by Inspectors. These sample statements need not, of course, be
followed exactly if an alternative statement is either more concise or more definite and conforms
to the principles set out in these guidelines.
10.1.1 The rigid pendant in the kitchen was insecure.
10.1.2 The ceiling switch in the bathroom was insecure, thus placing strain on the
conductors.
10.1.3 The conduits on the back verandah were not securely fixed in position where they
passed along the back wall.
10.1.4 The conduits on the back verandah were not mechanically and electrically
continuous as they had pulled apart at the fittings.
10.1.5 The flexible cord for the radiator was frayed and damaged.
10.1.6 The flexible cord, from the plug socket in the second bedroom to the standard lamp
in the hall, was damaged where it passed through the doorway.
10.1.7 The insulation on the flexible pendant in the kitchen was perished, thus exposing
live conductors (temporarily made safe by taping).
10.1.8 The use of lampholder and adaptor to join the flexible cord for the radio was not
satisfactory.
10.1.9 The improvised hand-lamp consisting of a lampholder mounted on a wooden block
and having an unguarded lamp was not satisfactory. (Situated in the garage.) DISCONNECTED
-LABELLED
10.1.10 The frame of the motor in the garage was not earthed.
10.1.11 The frame of the washing machine was earthed by means of a conductor not
forming part of the flexible cord supplying the machine.
10.1.12 The earthing conductor above the bench in the garage was broken.
10.1.13 The earthing conductor adjacent to the laundry door was not securely fixed.
10.1.14 Some of the joints in the earthing conductor near the switchboard were not soldered
or suitably clamped.
10.1.15 The metallic conduits in the garage were not earthed.
10.1.16 The connection of the earthing conductor to conduits at the main switchboard was
not electrically effective.
10.1.17 The main earthing conductor on the southern side of the house was not connected
to the water service (no earth clip fitted.)
© State of NSW through Transport for NSW Page 28 of 29
T HR EL 17001 ST Electrical Distribution System Installation Connection and Inspection
Version 1.0 Issued Date: 12 February 2015
10.1.18 The resistance between earth and metallic conduits at the switchboard was
high (measured 200 ohms).
10.1.19 The metallic conduits in the following locations were not earthed:
(a) Kitchen,
(b) Back verandah,
(c) Main switchboard.
10.1.20 The metallic conduits in the garage were not earthed in a satisfactory manner.
(Earthed to a separate electrode instead of to the main earth.)
10.1.21 The sheathing of an isolated length of lead covered cable in the garage was not
earthed and was not protected against mechanical damage.
10.1.22 The switch for the plug socket in the dining room did not control the active
conductor.
10.1.23 The main switch was broken and inoperative in the “ON” position and
thereby the installation was not longer under the control of a main switch.
10.1.24 The metal cover of the switch in the bathroom was alive, (temporarily made safe by
lining the switch cover with an insulating material.)
10.1.25 The plug socket in the dining room was not controlled by a switch.
10.1.26 The switch controlling the plug socket in the dining room was inoperative in the “ON”
position.
10.1.27 The cover of the light switch in the bathroom was broken thus exposing live metal
(temporarily made safe by taping).
10.1.28 The porcelain base of the power circuit fuse on the main switchboard was broken
thus exposing live contacts (temporarily made safe by taping).
10.1.29 The heating element of the toaster was broken and likely to made contact with the
frame., (toaster and the permanently attached flexible cord DISCONNECTED - LABELLED).
10.1.30 The electric jug was not provided with a lid and thus exposed live conductor.
DISCONNECTED - LABELLED.
10.1.31 The aerial conductors to the garage were fouled by trees and vines.
10.1.32 The insulation resistance between earth and the neutral conductor of the power
circuit was extremely low. (measured.__ ohms).
10.1.33 The insulation resistance between the frame and the elements of the radiator was
very low. (measured ohms).
© State of NSW through Transport for NSW Page 29 of 29