ELECTRICAL SAFETY INSPECTION REPORT

A & B OUTERWEAR LTD.

Plot # 29-30, CEPZ, Chittagong, Bangladesh.

Factory List:

1. A & B Outerwear Ltd.

Inspected by: Al-Amin

Report Generated by: Al-Amin

Inspected on March 7th 2015

Page 2: ELECTRICAL SAFETY INSPECTION REPORTaccord.fairfactories.org/accord_bgd_files/1/Audit_Files/18842.pdf · ELECTRICAL SAFETY INSPECTION REPORT ... The A & B Outerwear Ltd. factory is

Page 2 of 12

A & B Outerwear Ltd.

SUMMARY

The A & B Outerwear Ltd. factory is established in owned three building and four shed. Building-1 is three

storied; Building-2 is two storied and building three is one storied. Building-1 was constructed in 2010 and

production started in same year. Building-2 was constructed in 2011 and production started in same year.

Building-3 was constructed in 2011. The factory had approximately 1114 workers.

The Factory was surveyed for electrical safety by Woosun Energy and Construction Co., Ltd. (WEC). The

purpose of the survey was to identify significant electrical safety issues and to provide recommendations for

remediation based on applicable standards specified by the Accord.

The scope of this initial electrical safety inspection was limited to the review and identification of major

electrical safety issues. The inspection did not include identification of minor deficiencies, which would be

further dealt with as part of follow-up inspections.

Table below summarizes the major electrical safety issues identified during the inspection.

Recommendations have been provided to address each issue.

The implementation schedule shall be developed by the factory to remediate each of the findings. The

specific timing of improvements, including any requested extensions due to design/installation constraints,

shall be submitted to the Accord for an approval.

Page 3: ELECTRICAL SAFETY INSPECTION REPORTaccord.fairfactories.org/accord_bgd_files/1/Audit_Files/18842.pdf · ELECTRICAL SAFETY INSPECTION REPORT ... The A & B Outerwear Ltd. factory is

Page 3 of 12

A & B Outerwear Ltd.

FINDINGS AND RECOMMENDATIONS

FINDING NO: E- 1

CATEGORY: DESIGN, DRAWINGS & RECORDS

FINDING: Thermographic scanning of the entire electrical system has not been performed.

RECOMMENDATION: Thermographic scanning of the entire electrical system must be performed twice in a year.

PRIORITY: P2

REMEDIATION TIMEFRAME: 8 WEEKS

FINDING NO: E-2

CATEGORY: DESIGN, DRAWINGS & RECORDS

FINDING: Electrical Single Line Diagram (SLD) is unavailable.

RECOMMENDATION: Have a qualified engineer to create an as-built electrical SLD, mentioning all the required information, and get it reviewed by Accord.

PRIORITY: P2

REMEDIATION TIMEFRAME: 12 WEEKS

FINDING NO: E- 3

CATEGORY: DESIGN, DRAWINGS & RECORDS

FINDING: Insulation resistance test of electrical equipment is not performed.

RECOMMENDATION: Insulation resistant test of all the cables must be performed once every 2 year cycle and recorded (this must require a complete power shut off).

PRIORITY: P2

REMEDIATION TIMEFRAME: 8 WEEKS

Page 4: ELECTRICAL SAFETY INSPECTION REPORTaccord.fairfactories.org/accord_bgd_files/1/Audit_Files/18842.pdf · ELECTRICAL SAFETY INSPECTION REPORT ... The A & B Outerwear Ltd. factory is

Page 4 of 12

A & B Outerwear Ltd.

FINDING NO: E- 4

CATEGORY: DESIGN, DRAWINGS & RECORDS

FINDING: Electric safety program is not initiated.

RECOMMENDATION: Electrical safety training and awareness program for the electrical personnel and workers must be initiated and recorded.

PRIORITY: P2

REMEDIATION TIMEFRAME: 8 WEEKS

FINDING NO: E- 5

CATEGORY: DESIGN, DRAWINGS & RECORDS

FINDING: Factory does not have maintenance record.

RECOMMENDATION: Maintenance Manager or Safety Officer must keep accurate records and ensure that they reflect actual factory day to day operations.

PRIORITY: P2

REMEDIATION TIMEFRAME: 8 WEEKS

FINDING NO: E- 6

CATEGORY: DESIGN, DRAWINGS & RECORDS

FINDING: Transformer Oil Test report is unavailable.

RECOMMENDATION: Check the transformer oil condition by performing oil test, this must be done twice a year and recorded.

PRIORITY: P2

REMEDIATION TIMEFRAME: 8 WEEKS

FINDING NO: E- 7

CATEGORY: DESIGN, DRAWINGS & RECORDS

FINDING: Earth Pit resistance record is unavailable.

RECOMMENDATION: Record earth pit resistances for all the earth pits, and do it once a year.

PRIORITY: P2

REMEDIATION TIMEFRAME: 8 WEEKS

Page 5: ELECTRICAL SAFETY INSPECTION REPORTaccord.fairfactories.org/accord_bgd_files/1/Audit_Files/18842.pdf · ELECTRICAL SAFETY INSPECTION REPORT ... The A & B Outerwear Ltd. factory is

Page 5 of 12

A & B Outerwear Ltd.

FINDING NO: E-8

CATEGORY: DESIGN, DRAWINGS & RECORDS

FINDING: Instruction for CPR (Cardiopulmonary Resuscitation) or Electrical shock restoration is not present.

RECOMMENDATION: Hang this first aid and CPR instructions near all electrical equipment (LT panel, MDB, FDB, DB, SDB) on a visible location.

PRIORITY: P2

REMEDIATION TIMEFRAME: 8 WEEKS

FINDING NO: E- 9

HT cable protected by DO fuse, dropping from pole.

CATEGORY: CABLE & CABLE SUPPORTS

FINDING: Wire is used in place of DO fuse and HT cables dropping from 11kV OH line not supported firmly to the pole.

RECOMMENDATION: Replace the wire with standard DO fuse and the HT cable dropping from 11kV pole must be firmly fixed to the pole with supports and clamps.

PRIORITY: P2

REMEDIATION TIMEFRAME: 6 WEEKS

FINDING NO: E- 10

315 kVA transformer in substation.

CATEGORY: TRANSFORMER ROOM

FINDING: No separation between LT panels and HT units (transformer, HT switchgear).

Recommendation: Make a brick built separation between LT and HT units; ensure that after making separator you have adequate ventilation (cross ventilation) and working clearance around each electrical equipment.

PRIORITY: P3

REMEDIATION TIMEFRAME: 16 WEEKS

Page 6: ELECTRICAL SAFETY INSPECTION REPORTaccord.fairfactories.org/accord_bgd_files/1/Audit_Files/18842.pdf · ELECTRICAL SAFETY INSPECTION REPORT ... The A & B Outerwear Ltd. factory is

Page 6 of 12

A & B Outerwear Ltd.

FINDING NO: E- 11

HT and LT cable.

CATEGORY: TRANSFORMER ROOM

FINDING: HT cable laid over the LT cables.

RECOMMENDATION: Cables of different voltage levels must be separated in different trays.

PRIORITY: P2

REMEDIATION TIMEFRAME: 6 WEEKS

FINDING NO: E- 12

500 kVA transformer in substation.

CATEGORY: TRANSFORMER ROOM

FINDING: No space around transformer for performing maintenance work.

Recommendation: Ensure a minimum 1.07m working space around the transformer.

PRIORITY: P2

REMEDIATION TIMEFRAME: 16 WEEKS

FINDING NO: E- 13

500 KVA transformer

CATEGORY: TRANSFORMER ROOM

FINDING: Oil leakage has been observed from transformer.

RECOMMENDATION: Stop oil leakage from transformer and keep top of transformer clean.

PRIORITY: P2

REMEDIATION TIMEFRAME: 8 WEEKS

Page 7: ELECTRICAL SAFETY INSPECTION REPORTaccord.fairfactories.org/accord_bgd_files/1/Audit_Files/18842.pdf · ELECTRICAL SAFETY INSPECTION REPORT ... The A & B Outerwear Ltd. factory is

Page 7 of 12

A & B Outerwear Ltd.

FINDING NO: E- 14

Transformer breather

CATEGORY: TRANSFORMER ROOM

FINDING: Silica gel inside the breather is replaced by pebbles.

Recommendation: Remove the pebbles from breather and replace it by silica gel after thorough cleaning of breather. The oil cup attached to breather must be filled by clean transformer oil.

PRIORITY: P1

REMEDIATION TIMEFRAME: 6 WEEKS

FINDING NO: E- 15

Main earthing busbar.

CATEGORY: EARTHING SYSTEM

FINDING: Impedance of main earthing of factory electrical system is very high (255.7 ohms)

Recommendation: Check properly may be loose connection is one of the cause.

PRIORITY: P2

REMEDIATION TIMEFRAME: 6 WEEKS

FINDING NO: E- 16

LT panel.

CATEGORY:DISTRIBUTION BOARD & PANEL

FINDING: No base plate and compression gland, excessive dust, lint and debris deposit underneath the panel (typical issue).

RECOMMENDATION: Dust, lint and debris must be thoroughly cleaned to avoid fire hazard. Provide covers (of noncombustible material) if any additional gap remains after installing cable glands.

PRIORITY: P1

REMEDIATION TIMEFRAME: 6 WEEKS

Page 8: ELECTRICAL SAFETY INSPECTION REPORTaccord.fairfactories.org/accord_bgd_files/1/Audit_Files/18842.pdf · ELECTRICAL SAFETY INSPECTION REPORT ... The A & B Outerwear Ltd. factory is

Page 8 of 12

A & B Outerwear Ltd.

FINDING NO: E- 17

MCCB inside the LT panel.

CATEGORY:DISTRIBUTION BOARD & PANEL

FINDING:

Cable connected MCCB without Lug. (Typical issue)

Recommendation: Cable must be connected to MCCB by cable lug.

PRIORITY: P1

REMEDIATION TIMEFRAME: 6 WEEKS

FINDING NO: E- 18

Bus bar inside the LT panel

CATEGORY:DISTRIBUTION BOARD & PANEL

FINDING: Cable connected to busbar without lug (typical).

Recommendation: Cables must be connected to busbar with proper size of cable lug.

PRIORITY: P1

REMEDIATION TIMEFRAME: 6 WEEKS

FINDING NO: E- 19

Inappropriate earthing

CATEGORY: EARTHING SYSTEM

FINDING: Earthing system of LT panel is not properly done. (Typical)

Recommendation: Every panel must be used earthing busbar.

PRIORITY: P1

REMEDIATION TIMEFRAME: 6 WEEKS

Page 9: ELECTRICAL SAFETY INSPECTION REPORTaccord.fairfactories.org/accord_bgd_files/1/Audit_Files/18842.pdf · ELECTRICAL SAFETY INSPECTION REPORT ... The A & B Outerwear Ltd. factory is

Page 9 of 12

A & B Outerwear Ltd.

FINDING NO: E- 20

Distribution cables

CATEGORY:CABLE & CABLE SUPPORTS

FINDING: Cable passes through wall are not protected and not supported.

RECOMMENDATION: Cable must be supported by cable tray and remaining gap is must be sealed.

PRIORITY: P2

REMEDIATION TIMEFRAME: 8 WEEKS

FINDING NO: E- 21

Cables terminating at MCCB in panel on production floor.

CATEGORY:DISTRIBUTION BOARD & PANEL

FINDING: Phase barrier/separator not installed (typical issue).

RECOMMENDATION: Put a purposely made phase separator (rubber type) between two phases; also terminate cables by proper sized cable lugs and cover cable lugs by heat shrink.

PRIORITY: P2

REMEDIATION TIMEFRAME: 8 WEEKS

FINDING NO: E- 22

Distribution cables

CATEGORY: CABLE & CABLE SUPPORTS

FINDING: Cables are covered by lint and dust.

RECOMMENDATION: Thoroughly clean the combustible materials. Suggested to include in routine cleanliness/maintenance work.

PRIORITY: P1

REMEDIATION TIMEFRAME: 8 WEEKS

Page 10: ELECTRICAL SAFETY INSPECTION REPORTaccord.fairfactories.org/accord_bgd_files/1/Audit_Files/18842.pdf · ELECTRICAL SAFETY INSPECTION REPORT ... The A & B Outerwear Ltd. factory is

Page 10 of 12

A & B Outerwear Ltd.

FINDING NO: E- 23

Cable raceways in production floor.

CATEGORY: WIRINGS

FINDING: Cable duct/channels have excessive lint/dust (typical issue).

RECOMMENDATION: Clean all the cable channels/ducts and cover them with checkered/perforated plates.

PRIORITY: P1

REMEDIATION TIMEFRAME: 8 WEEKS

FINDING NO: E- 24

Hot spot inside distribution board.

CATEGORY:DISTRIBUTION BOARD & PANEL

FINDING: Hot spots detected at termination point of MCCB due to loose connection. (72 degree)

RECOMMENDATION: Arrange periodic inspection & thermal scan to identify the overloading, loose connection, unbalanced load which may cause the excessive heat-rise and take action immediately

PRIORITY: P1

REMEDIATION TIMEFRAME: 4 WEEKS

FINDING NO: E- 25

Cable terminating at MCCB in panel.

CATEGORY:DISTRIBUTION BOARD & PANEL

FINDING: Multiple cable termination at a terminal of MCCB (typical issue).

RECOMMENDATION: Multiple cables connecting at a MCCB terminal must be disconnected. Existing multiple circuits may be distributed through bus bars.

PRIORITY: P2

REMEDIATION TIMEFRAME: 2 WEEKS

Page 11: ELECTRICAL SAFETY INSPECTION REPORTaccord.fairfactories.org/accord_bgd_files/1/Audit_Files/18842.pdf · ELECTRICAL SAFETY INSPECTION REPORT ... The A & B Outerwear Ltd. factory is

Page 11 of 12

A & B Outerwear Ltd.

FINDING NO: E- 26

Panel on ground floor.

CATEGORY:DISTRIBUTION BOARD & PANEL

FINDING: Cables inside distribution board is disorganized.

RECOMMENDATION: Organize all the power cables securely and neatly inside distribution board to prevent from electrical hazards.

PRIORITY: P1

REMEDIATION TIMEFRAME: 6 WEEKS

FINDING NO: E- 27

Cable terminating at MCCB inside distribution

board.

CATEGORY:DISTRIBUTION BOARD & PANEL

FINDING:

Power cables are bent excessively (typical issue).

RECOMMENDATION: Avoid power cable bending in electrical system;

in unavoidable case bend cables without any

stress but not less than 135 degrees.

PRIORITY: P2

REMEDIATION TIMEFRAME: 6 WEEKS

FINDING NO: E- 28

Wires terminating at busbar inside panel.

CATEGORY:DISTRIBUTION BOARD & PANEL

FINDING: Multiple cables connected in the busbar through a single lug (typical issue).

RECOMMENDATION: Every cable must be connected to the busbar through its own single lug (one lug per cable).

PRIORITY: P1

REMEDIATION TIMEFRAME: 4 WEEKS

Page 12: ELECTRICAL SAFETY INSPECTION REPORTaccord.fairfactories.org/accord_bgd_files/1/Audit_Files/18842.pdf · ELECTRICAL SAFETY INSPECTION REPORT ... The A & B Outerwear Ltd. factory is

Page 12 of 12

A & B Outerwear Ltd.

FINDING NO: E- 29

Cables terminating at MCCB.

CATEGORY:DISTRIBUTION BOARD & PANEL

FINDING: MCCB without enclosure and mounted on wooden plank.

RECOMMENDATION: Remove the wooden plank. Provide standard MCCB protective enclosures.

PRIORITY: P2

REMEDIATION TIMEFRAME: 4 WEEKS