Electrical Work Procedure

Embed Size (px)

Citation preview

  • 8/11/2019 Electrical Work Procedure

    1/19

    !"#$%&'

    !)*+,-. ./0*,/1 2/3/4*5

    !6%&789&67'

    ,-:!-3 *.*,0; $9& 4#&"$' *

    !6%&789& .6B

    569CD$%& 4#&"$' *2*!4,/!12 @-,E =,-!*5?,*

    569B ,$F

    58&$

    ,$G#H#6% I

    !"#$ &'#("!) *+,!-."/$

    =,*=1,*5 J;1B ?31,

    ,-:!-3

    !)*!E*5 J; !B /0?5/1 ,-:!-3

    1==,-+*5 J;0B -J1

  • 8/11/2019 Electrical Work Procedure

    2/19

    !"#$%&'" )$'*+#,* -%.,$ )$'/,#. 0'1#'2 !3,$45 6,$&7#," 8727.,* 9:,&$'3 ;74,$7% 8727.,*

    Page 2 of 19

    !?,#.$7#%? -'$@ )$'#,*+$,!?,#.$7#%? -'$@ )$'#,*+$,

    ELECTRICAL WORK PROCEDURE

    TABLE OF CONTENTS

    1.0 PURPOSE

    2.0 SCOPE

    3.0 REFERENCE

    4.0 DEFINITIONS

    5.0 RESPONSIBILITIES

    6.0 PROCEDURE

    7.0 ELECTRICAL EQUIPMENT INSTALLATIONS

    8.0 ATTACHMENTS: TEST

  • 8/11/2019 Electrical Work Procedure

    3/19

    !"#$%&'" )$'*+#,* -%.,$ )$'/,#. 0'1#'2 !3,$45 6,$&7#," 8727.,* 9:,&$'3 ;74,$7% 8727.,*

    Page 3 of 19

    !?,#.$7#%? -'$@ )$'#,*+$,!?,#.$7#%? -'$@ )$'#,*+$,

    1.0 PURPOSE

    The purpose of this document is to ensure safe, high quality and

    consistent installation of the electrical system at the Escravos

    Produced Water Disposal facility.

    2.0 SCOPE

    This Electrical work procedure covers all onshore electrical

    construction activities, Installation, inspection and testing of electrical

    system on Main deck, Cellar deck, Jacket and Bridge of the Escravos

    Produced Water Disposal facility. The overviews of work are as follows:

    Unboxing and Sorting of Lighting Accessories

    Cable drum testing

    Fabrication and Installation of Cable Tray Supports

    Fabrication and Installation of Cable Tray

    Earth Bonding

    Junction Box Installation

    Bridge Conduit Installation and Wiring

    Fabrication and Installation of Stanchion / Pendant Light support

    Installation of Plant Lighting Systems

    Transformers Installation and Termination

    Electric Motors Installation and Termination

    MV, LV Power and Control Cable Pulling

    Cable Glanding and Termination

    Cable Tagging and Core Identification

    Testing (Meggering and Continuity)

    Mechanical Completion Checks

  • 8/11/2019 Electrical Work Procedure

    4/19

    !"#$%&'" )$'*+#,* -%.,$ )$'/,#. 0'1#'2 !3,$45 6,$&7#," 8727.,* 9:,&$'3 ;74,$7% 8727.,*

    Page 4 of 19

    !?,#.$7#%? -'$@ )$'#,*+$,!?,#.$7#%? -'$@ )$'#,*+$,

    3.0 REFERENCE

    All construction work, installation and testing shall be carried out in

    accordance with good engineering practice and shall satisfy all

    statutory requirements of the National and/or local authorities in which

    the installations will be located.

    The following Standards and requirements shall form an integral part of

    the electrical construction work, Installation, inspection and testing in

    the Escravos Produced Water Disposal facility:

    PWD-D017-ELE-DTL- Electrical Installation Details

    NET-000-90005 (Power & Control) Offshore

    API RP 14F Recommended Practice for Design and

    Installation of Electrical System for Offshore

    Production Platforms

    ASTM A123 Specification for Zinc (Hot- Galvanized)

    Coating

    on Product Fabricated from Rolled,

    Pressed, and Forged Steel Shaped Plates,

    Bars, and Strip

    ASTM A386 Specification for Zinc-Coating (Hot-Dip) on

    Assembled Steel Products

    IEEE 45 Recommended Practice for Electric

    Installation

    on Shipboard

    NPFA National Electrical Code 70

    NPFA Lightning Protection Code 78

  • 8/11/2019 Electrical Work Procedure

    5/19

    !"#$%&'" )$'*+#,* -%.,$ )$'/,#. 0'1#'2 !3,$45 6,$&7#," 8727.,* 9:,&$'3 ;74,$7% 8727.,*

    Page 5 of 19

    !?,#.$7#%? -'$@ )$'#,*+$,!?,#.$7#%? -'$@ )$'#,*+$,

    4.0 DEFINITION

    NONE

  • 8/11/2019 Electrical Work Procedure

    6/19

    !"#$%&'" )$'*+#,* -%.,$ )$'/,#. 0'1#'2 !3,$45 6,$&7#," 8727.,* 9:,&$'3 ;74,$7% 8727.,*

    Page 6 of 19

    !?,#.$7#%? -'$@ )$'#,*+$,!?,#.$7#%? -'$@ )$'#,*+$,

    5.0 RESPONSIBILITIES

    ! Electrical Team Lead

    Shall ensure proper implementation of this procedure. He shall

    coordinate the activities of the Electrical Engineer who leads the

    Electrical team.

    ! Electrical Engineer

    The Electrical Engineer shall be responsible for the following:

    Verifying all activities relevant to installation and testing of field

    mounted Equipment and Lighting accessories.

    Verifying the availability of the materials required for installation.

    Preparation and submission of as-built drawings and resolving

    all technical problems that may arise during installation

    activities. He is also responsible for coordinating with the QA /

    QC Engineer for resolving technical queries.

    ! Electrical Supervisor

    Shall lead the Electrical activities at construction stage; carry out all

    inspection required; issue the relevant report or checklist and

    coordinate with the QA / QC Inspector and the Electrical Engineer.

    ! Quality Control Inspector

    Shall monitor the proper implementation of the project procedures and

    specifications. Shall also be responsible for conducting of tests on

    cables and instruments during delivery and before installation;

    responsible for all final inspection activities; rectify all punch list items

    and sign off all finished works.

    ! Electrical Technician

    Electrical Technicians shall be responsible for Installing all Electrical

    equipment and lighting. Coordinating with the Electrical Supervisor,

    QA/QC Engineer and Electrical Engineer in electrical installation and in

    resolving technical issues.

  • 8/11/2019 Electrical Work Procedure

    7/19

    !"#$%&'" )$'*+#,* -%.,$ )$'/,#. 0'1#'2 !3,$45 6,$&7#," 8727.,* 9:,&$'3 ;74,$7% 8727.,*

    Page 7 of 19

    !?,#.$7#%? -'$@ )$'#,*+$,!?,#.$7#%? -'$@ )$'#,*+$,

    6.0 PROCEDURE

    6.1 Receiving and Inspection of Electrical Equipment / Material

    Upon receipt of electrical materials the QC Inspector and

    warehouse personnel shall inspect visually the materials and

    equipment for possible defects, physical damages or missing

    part.

    The conformance of the electrical equipment to specifications,

    hazardous area classification and mechanical certification shall

    be verified.

    The provision in the following documents shall form the basis for

    all the inspection required.

    Quality Assurance/Quality Control

    Inspection and Test Plan

    Manufacturers data and technical manuals

    Electrical equipment shall be visually inspected for possible

    damage and defects during handling and shipment.

    However, for MV / LV Switchgear panels in the MCC, high

    voltage test on the panel should have been carried out as part of

    the manufacturers scope in accordance with the relevant CNLs

    or international Standards; all relevant documents duly signed.

    6.2 Pre-Installation Test and Inspection

    Tests shall be carried out on cables and wires at delivery and

    before installation and the QC inspector shall perform these test.

    6.2.1 Test on Cables

    The order of test shall be

    Insulation Resistance Test for

    " Low Voltage Power Cable (LV)

    " Low Voltage Control Cable (LV)

    " Medium Voltage Cable (MV)

    Continuity Test for

    " Low Voltage Power Cable (LV)

    " Low Voltage Control Cable (LV)

    Medium Voltage Test for Medium Voltage Cable (HV)

  • 8/11/2019 Electrical Work Procedure

    8/19

    !"#$%&'" )$'*+#,* -%.,$ )$'/,#. 0'1#'2 !3,$45 6,$&7#," 8727.,* 9:,&$'3 ;74,$7% 8727.,*

    Page 8 of 19

    !?,#.$7#%? -'$@ )$'#,*+$,!?,#.$7#%? -'$@ )$'#,*+$,

    Test equipment to be used are as follows

    Megger Tester 1000V or 5000V

    Fluke Multi-tester

    Hi-Pot Tester6.3 Electrical Equipment Storage and Preservation

    Material storage shall comply with the material Control

    Procedure provided for this project.

    6.3.1 The Electrical equipment shall be stored where appropriate in

    accordance with vendor advice.

    On receiving the motors, it shall be stored in a dry and clean

    shelter position, which is free from vibration and rapid change in

    temperature.

    The motor shall be covered completely with tarpaulins to prevent

    ingress of dust or moisture until such a time installation is

    complete.

    Where the motor is fitted with anti-condensation heater. With the

    client approval, a suitable power supply shall be made available;

    the heater shall be switched on throughout the storage period,

    particularly where the storage period is likely to be prolonged.

    Warning notice shall be attached to this effect.

    6.4 Calibration

    All test equipment shall be calibrated in accordance with

    calibration control procedure and shall be traceable to the

    applicable standards.

    7.0 ELECTRICAL EQUIPMENT INSTALLATION

    7.1 Cable tray Supports Fabrication and Installation

    Structural welders shall carry out fabrication of cable tray

    support.

    These Cable tray supports shall be installed on horizontal

    base plate unless otherwise field adjustments are required.

    The cable tray supports shall be fastened with bolts and nuts

    and angular iron for bracing wherever possible for

  • 8/11/2019 Electrical Work Procedure

    9/19

    !"#$%&'" )$'*+#,* -%.,$ )$'/,#. 0'1#'2 !3,$45 6,$&7#," 8727.,* 9:,&$'3 ;74,$7% 8727.,*

    Page 9 of 19

    !?,#.$7#%? -'$@ )$'#,*+$,!?,#.$7#%? -'$@ )$'#,*+$,

    reinforcement.

    Cable tray support shall provide strength and safe working

    capacity (SWL) sufficient to meet the load requirement of the

    cables to be laid on top cable trays. The cable tray support material shall agree with the EPWD

    project specification.

    Special consideration will be given to center-supported

    systems considering eccentric loading.

    7.2 Paint Touch-up for Cable Tray Support

    Paint touch-up for cable tray support shall be done with zinc-

    rich galvanizing materials that meet the required

    specification.

    Cable trays that have a Hot-dip galvanized coating shall be

    re-touched after fabrication i.e. after cutting and drilling since

    the coating gets damaged over time.

    Other protective coatings that are cut or damaged must be

    touched up with compatible coatings.

    7.3 Cable Trays Installation

    Cable tray shall be installed in conformance with NEC A318

    and standards set forth in NEMA VE-1 and VE-2 as well that

    provided by the project (PWD-D017-ELE-DTL- NET-000-

    90005 Electrical Installation Details (Power & Control)

    Offshore

    Consideration shall be given to loads associated with future

    cable additions or any other loads to the cable tray system or

    cable tray support system.

    Cable tray cut section shall be treated to remove sharp

    edges, which could cause damage to cables and cause

    injury to personnel.

    Insulation separators and insulated fitting materials shall be

    used to prevent contact corrosion due to the use of SS-316

    in combination with steel supports.

    Cable tray hardware (nuts, bolts and washers..) to be used

  • 8/11/2019 Electrical Work Procedure

    10/19

    !"#$%&'" )$'*+#,* -%.,$ )$'/,#. 0'1#'2 !3,$45 6,$&7#," 8727.,* 9:,&$'3 ;74,$7% 8727.,*

    Page 10 of 19

    !?,#.$7#%? -'$@ )$'#,*+$,

    during the installation shall be of 316 stainless steel

    materials.

    Where cable trays are linked together, splice plate

    connectors/hinges shall be used to bolt them and cable trayshall be grounded according to EPWD Grounding

    specification.

    The linking points shall be bonded together using a

    dedicated bond wires, and bonding wires shall have a good

    surface contacts.

    Competent and qualified persons familiar with standards

    electrical construction practices, electrical equipment shall

    perform the work.

    7.4 Cable Pulling.

    Prior to cable installation, cable path shall be examined to

    ensure that all areas are free of hazards that may cause

    damage during cable installation.

    All cables shall be pulled from the top of the drum and in the

    direction indicated on the drum according to vendors

    recommendation.

    Sufficient cables rollers and side roller (when required) shall

    be used when pulling cable in position. This will reduce the

    effort required and ensure the cable outer sheath is not

    damaged.

    The minimum bending radius of the cable shall be

    maintained to prevent damage to the cable

    After pulling of cables, temporary identification tags shall be

    attached. Permanent tags shall be attached at the end of

    termination activities.

    Correct power and control cable size and type shall be

    pulled.

    After pulling, the cable end shall be sealed to prevent

    moisture ingress

  • 8/11/2019 Electrical Work Procedure

    11/19

    !"#$%&'" )$'*+#,* -%.,$ )$'/,#. 0'1#'2 !3,$45 6,$&7#," 8727.,* 9:,&$'3 ;74,$7% 8727.,*

    Page 11 of 19

    !?,#.$7#%? -'$@ )$'#,*+$,

    7.5 Cable Glanding

    Proper sizes of cable gland suitable for the cable shall be

    used to match the appropriate cable.

    Any unused cable entry hole shall be plugged. While glanding power cables, it shall be ensured that the

    loads of the cables are not coming on the glands.

    Close attention shall be paid to the cable glanding and

    sealing arrangements on all electrical equipment.

    7.6 Cable Termination

    Termination (wiring connection) shall be done as per

    specification, wiring drawings and/or manufacturers

    instruction.

    Core shall be terminated with pin crimps or cable lugs. These

    shall be installed with crimping / compression tools and shall

    be tightened to manufacturers recommended torques.

    Each lug shall correctly match the cross-sectional area of the

    conductor and shall be crimped on with the correct

    compression tools and dies.

    Power cables and control cables shall be anchored to the

    cable tray by using cable ties (tie wraps).

    Sufficient length of cable for connection shall be coiled near

    the equipment side.

    Certified HV/MV jointer shall perform all MV cable

    termination and joints where required.

    7.7 Cable Tagging and Core Identification

    Each cable shall be correctly tagged as per project

    specification and standards for suitable identification.

    Identification numbers for power and control cables shall

    read from terminals outwards

    Identification shall be in the form of captive o ring ferrule of

    appropriate diameter engraved or indelibly printed with the

    cable number, the core number and the terminal number.

    Wire maker shall be provided for cable wires/cores for power

  • 8/11/2019 Electrical Work Procedure

    12/19

    !"#$%&'" )$'*+#,* -%.,$ )$'/,#. 0'1#'2 !3,$45 6,$&7#," 8727.,* 9:,&$'3 ;74,$7% 8727.,*

    Page 12 of 19

    !?,#.$7#%? -'$@ )$'#,*+$,

    cables and control cables.

    7.8 Grounding System

    All metallic enclosures of equipment, cable trays, cable tray

    structural supports, vessels, skids, structural steel supports etc.

    as found in bridge, main deck, cellar deck and jacket shall be

    grounded by connection to the common Earth Grid. The

    Earthing System / Pattern shall be in accordance with the

    approved drawings. All Earthing cables shall be PVC covered.

    7.9 Electric Motor

    Electric motors shall be erected or installed in full accordance

    with the manufacturer instructions and project specification with

    regards to foundation, alignment, shimming etc. Before

    electrical hook-up of the electric motor, the Electrical Equipment

    Field Inspection report form shall be filled, signed and duly

    approved by all relevant parties. The terminations shall be in

    correct Phase-Sequence arrangement and marked L1, L2 & L3

    at each end.

    The metal casing of the electric motors shall be earthed using

    the specified wire size according to project spec.

  • 8/11/2019 Electrical Work Procedure

    13/19

    !"#$%&'" )$'*+#,* -%.,$ )$'/,#. 0'1#'2 !3,$45 6,$&7#," 8727.,* 9:,&$'3 ;74,$7% 8727.,*

    Page 13 of 19

    !?,#.$7#%? -'$@ )$'#,*+$,

    8.0 ATTACHMENTS

    Basic Inspection (Electrical Equipment)

    Cable Installation Check Procedure Cable Tray/Ladder Inspection

    Electrical Installation Checklist

    Lighting Circuit Insulation Resistance Test

    Lighting Installation Check Procedure

  • 8/11/2019 Electrical Work Procedure

    14/19

    !"#$%&'" )$'*+#,* -%.,$ )$'/,#. 0'1#'2 !3,$45 6,$&7#," 8727.,* 9:,&$'3 ;74,$7% 8727.,*

    Page 14 of 19

    !?,#.$7#%? -'$@ )$'#,*+$,

    !"#$%&'$("

    !"#$%& ()

    )*+,- ,/+0!-1,2/

    *+,-&./ 012&3

    4%56478/&2 )&8.+#9/#,"

    )+1:#"; $%#92&"/EF#+.%#/ #A&"/#=#.1/#,"

    NC H+&1 .?188#=#.1/#,"

    OC J79& ,= >L 9+,/&./#,"E;18 ;+,%9E/&29&+1/%+& .?188

    PC HA&$%1/& 9+,/&./#," ,= &$%#92&"/ 1"A .15?&8 1;1#"8/ .,++,8#,"Q /@&

    :&1/@&+Q R#5+1/#," 1"A ,/@&+ 1AR&+8& =1./,+8

    F@&.S /@& =,??,:#"; #/&28 1"A +&9,+/ 1"7 A&R#1/#,"EA&=&./8 %"A&+ +&21+S83

    MC T15&?#"; .,++&./

    NC 0, %"1%/@,+#U&A 2,A#=#.1/#,"8

    OC >".?,8%+& 1"A ;?188&8 81/#8=1./,+7

    BC 4&1?8 1"A ;18S&/8 81/#8=1./,+7

    DC V,?/8 1"A ;?1"A8 .,29?&/& 1"A /#;@/

    KC 0, %"A%& 1..%2%?1/#," ,= A%8/ 1"A A#+/

    WC 0, ?&1S1;& ,= ,#?E.,29,%"A

    XC 0, A121;& /, 15,R&6;+,%"A 91+/ ,= .,""&./&A .15?&8

    MYC G,/,+ =1"8 1"A .,%9?#";8 ",/ +%55#"; ," .,:?8E;%1+A8MMC >1+/@#"; #" ;,,A .,"A#/#,"

    MNC Z#? ?&R&?8 #" 8#;@/ ;?188&8 .,++&./

    MOC 4#?#.1 ;&? #" 5+&1/@&+8 81/#8=1./,+7

    MBC *+&88%+#U1/#," 878/&2 .,++&./ [ /&8/&A4%#/15?& =,+ 1+&1 .?188#=#&A \>4 0Z >$%#92&"/ 1..&9/&A \>4 0Z

    4#;"1/%+&

    )1/&

    -"#%#? )@ 7

  • 8/11/2019 Electrical Work Procedure

    15/19

    !"#$%&'" )$'*+#,* -%.,$ )$'/,#. 0'1#'2 !3,$45 6,$&7#," 8727.,* 9:,&$'3 ;74,$7% 8727.,*

    Page 15 of 19

    !?,#.$7#%? -'$@ )$'#,*+$,

    !"#$ %#&'("

    )

    *

    +

    ,

    -

    .

    /0

    1

    23456"'7#

    86"#

    !"#$%&'&( *+ ,"-."#!"/0'12.'3"/

    ,"-."# 4! !56 !"/0'12.'3"/

    9:$$#5"&;

  • 8/11/2019 Electrical Work Procedure

    16/19

    !"#$%&'" )$'*+#,* -%.,$ )$'/,#. 0'1#'2 !3,$45 6,$&7#," 8727.,* 9:,&$'3 ;74,$7% 8727.,*

    Page 16 of 19

    !?,#.$7#%? -'$@ )$'#,*+$,

    !!!!!!!!!!!!

    !!!!!!!!!!!!

    !!!!!!!!!!!!

    !!!!!!!!!!!!

    !!!!!!!!!!!!

    !!!!!!!!!!!!

    !!!!!!!!!!!!

    !!!!!!!!!!!!

    !!!!!!!!!!!!

    !!!!!!!!!!!!

    !!!!!!!!!!!!

    "#$%

    !"#$%&'!(" (*

    &+,-% '.+/0-+11%.

    &2345 623 78998:;

  • 8/11/2019 Electrical Work Procedure

    17/19

    !"#$%&'" )$'*+#,* -%.,$ )$'/,#. 0'1#'2 !3,$45 6,$&7#," 8727.,* 9:,&$'3 ;74,$7% 8727.,*

    Page 17 of 19

    !?,#.$7#%? -'$@ )$'#,*+$,

    !"#$ %#&'("

    )

    *

    +

    ,

    -

    .

    /

    0

    1

    )2

    34567"'8#

    97"#

    !"#$%&'&( *+ ,"-."#

    !"/0'12.'3"/ ,"-."# 4! !56 !"/0'12.'3"/

    :;$$#6"&"4;6 @AB#8# 7CC(4>7D(#E

    :B#>F D;G#& H;8 #7>B (46# 6'$D##8 "; D# $78F#I A4"B JK ;8 L=

    :;88#>" M'6>"4;6 D;G 46&"7((#I 7>>;8I465 "; #6>(;&'8# >(7&&4H4>7"4;6 76I 78#

    >(7&&4H4>7"4;6N 76I 46 7>>;8I76># A4"B (;>7"4;6 I87A465

    O7D#(465N 6'$D#8465 76I H#88'(# >;88#>"P

    Q'6>"4;6 D;G $#>B764>7((R &;'6IN &;(4I(R 76I >;88#>"(R $;'6"#IP S#8$467(

    D(;>F& 78# ;H >;88#>" "RC# >;88#>"(R $;'6"#IN $#>B764>7((R &;'6I 76I

    >(#78(R $778F#IP T7884#8& H4""#I AB#8# 8#U'48#I 76I 7(( >;66#>"4;6& "45B"P

    V78"B465 D;6I465 76I >;(;8465 >;88#>"P !6&"8'$#6" &>8##6& :#57"#I

    H8;$ #(#>"84>7( #78"BP

    L; ";C #6"8R >7D(#& '6(#&& 7'"B;84W#IP 3C78# #6"84#& C('55#IP

    X(76I C(7"# >;88#>"(R 46&"7((#I 76I I8746 C('5 46&"7((#I AB#8# 7CC(4>7D(#

    3'HH4>4#6" 7>>#&& H;8 46>;$465 >7D(#&

    VU'4C$#6" (;>7"#I >;88#>"(R "; 7((;A 7>>#&& H;8 $746"#676>#P

    VG Y !Z 87"465 7& C#8 I7"7 &B##"N >;88#>"(R $746"746#I DR ' ;H C('5&N

    5(76I&N (&P

    :B#>F "B7" C8#[7"4;6 76I $#>B764>7( C8;"#>"4;6 4& 46 7>>;8I76># A4"B

    C8;M#>" &C#>4H4>7"4;6 76I 76R I4&"'8D#I C8#[7"4;6 8#C(7>#IP

    987A465 %#H#8#6>#

    Z8;M#>" L7$#\ 3'D]3R&"#$ L;

    3'D]3R&"#$ 9#&>84C"4;6 97"# Z846"#I

    7%&.'13.8%

    ^64U'# !9 !"#$

  • 8/11/2019 Electrical Work Procedure

    18/19

    !"#$%&'" )$'*+#,* -%.,$ )$'/,#. 0'1#'2 !3,$45 6,$&7#," 8727.,* 9:,&$'3 ;74,$7% 8727.,*

    Page 18 of 19

    !?,#.$7#%? -'$@ )$'#,*+$,

    !"#$ !"#$

    %$&'()"*

    ,)--$.#

    ($/'0$

    !"#$

    %$1"-2&3

    ,'-0)'#

    4)15$-

    67'##'.8& ('&09..$0#$(:!"#!

    $%#&'(!$)% +"#$#!(%,"

    '$-.!$%- ,$+,&$!

    ;"*)$ ,'-0)'# ;"*)$

    !"#$

  • 8/11/2019 Electrical Work Procedure

    19/19

    !"#$%&'" )$'*+#,* -%.,$ )$'/,#. 0'1#'2 !3,$45 6,$&7#," 8727.,* 9:,&$'3 ;74,$7% 8727.,*

    Page 19 of 19

    !?,#.$7#%? -'$@ )$'#,*+$,

    !"#$ %#&'("

    )

    *

    +

    ,

    -

    .

    /

    0

    1

    )2

    ))

    )*

    )+

    ),

    )-

    34&'5# 7(( 89:"'5#& 7& ;#5 57?94@ 74> 7& A'9(" ?B#5# 7;;(9C7A(#D

    E9@B(9@B"# "F &BF? 7(( CB#CG#> #H'9;$#4"

    =""7CB 7 CF;I F8 J9@B"94@ K95C'9" L94@(# (94# >97@57$ E9@B(9@B"#> "F &BF? 7((

    !4&;#C"#> C7A(#& J9@B"& MF:#& 74> L?9"CB#&

    L9@47"'5#

    N7"#

    KF$$#4"&O=C"9F4 P?B#5# 7;;(9C7A(#Q

    !"#$%&'&(

    *+

    ,"-."#

    !"/0'12.'3"/ ,"-."# 4! !56 !"/0'12.'3"/

    L;75# BF(#& ;('@@#> ?9"B CF55#C" 57"#> ;('@ 74> !R ?7&B#5D P?B#5# 7;;(9C7A(#Q

    =(( 4'"&S AF("& 74> ?7&B#5& 89""#> 74> 7CCF5>94@ "F &;#C

    !4"#547( #75"B94@ CF55#C"D

    L'889C9#4" 7CC#&& 8F5 94CF$94@ C7A(#&

    J9@B"94@ 94&"7((7"9F4 94&"7((#> ?9"B &'889C9#4" 7CC#&& 8F5 $794"#474C#

    KB#CG CF5# CF4"94'9"I 74> C95C'9" ;F(759"I F8 #7CB C95C'9" 74> &';;(ID T7:

    7CC#;"7A(# U7('#V 2D* WB$

    KB#CG 94&'(7"9F4 5#&9&"74C# 85F$ >9&"D MF75> 8F5 CF$;(#"# C95C'9" 7" -22X>CS

    (9U# CF4>'C"F5 "F #75"B 4#'"57( "F #75"BS $949$'$ 7CC#;"7A(# U7('# * TFB$&

    Y#5$947"9F4& CF55#C" 74> "9@B"

    Z'4C"9F4 AF: @7&G#" 89""#> "F (9> CFU#5

    KB#CG AF:#& 8F5 #7CB (94# 4'$A##5 "F A# $75G#> ?9"B W[ F5 \=

    =(( #H'9;$#4" 94&"7((#> 7CCF5>94@ "F >57?94@S &;#C989C7"9F4 74> 75#7

    C(7&&989C7"9F4S !4C('>94@ 7(( ]'4C"9F4 AF:#&D

    =(( "7@ 4'$A#5& CF55#C"S C'5#(I 7""7CB#> 74> 5#7>7A(#D

    =(( #H'9;$#4" '4>7$7@#> 74> CF55#C"(I $F'4"#>D J9@B" 89:"'5#& (#> 74>

    C(#74

    KF55#C" "I;# F8 @(74>& 89""#> 74> "9@B"#4#>S !R ?7&B#5 89""#>DP?B#5# 7;;(9C7A(#Q

    L'A^LI&"#$ N#&C59;"9F4 N7"# R594"#>

    N57?94@ %#8#5#4C#

    _49H'# !N !"#$OY7@ \FD

    R5F]#C" \7$#V L'A^LI&"#$ \F

    7%&.'13.8%

    !97!: ;,,7

    767!?,@!A6

    6@B9?@5B @5C?A66A?@