Upload
margaretmargaret-wright
View
227
Download
0
Embed Size (px)
DESCRIPTION
General installation planning 12/11/2015T.Eriksson CERN BE/OP/AD3
Citation preview
T.Eriksson CERN BE/OP/AD 1
ELENA:Commissioning & operation• ELENA beam commissioning
• Operation
12/11/2015
T.Eriksson CERN BE/OP/AD 2
General planning
12/11/2015
T.Eriksson CERN BE/OP/AD 3
General installation planning
12/11/2015
T.Eriksson CERN BE/OP/AD 4
Commissioning key dates (baseline)So far and imminent:
• AD ejection line modification & validation: completed / in operation
• Kicker pulse generators tested• Ion source installation & initial tests: completed• Ion source & Ion switch commissioning: early 2016
(Feb/Mars.)• 1:st part of AD to ELENA transfer line: could this be
done during 2016 AD start-up ?(April.) EPC/Vacuum ?
12/11/2015
T.Eriksson CERN BE/OP/AD 5
Beam commissioning key dates (baseline)
• ELENA ring HW installation & tests completed by 5/7/2016– All equipment tested incl. controls/SW
• Ring commissioning with Ions & Pbars (ppm) 5/7 – 14/11 2016; ~ 4 months. Pbar shift plan with AD users
• Ion operation could continue >14/11 if compatible with shutdown work
• 2016 physics run ends 14/11, by this date we will know more about:– Deceleration efficiency– Beam cooling performance– Emittances– Lifetime
• => decision point for new ejection line installation
12/11/2015
T.Eriksson CERN BE/OP/AD 6
ELENA setting-up 1
• 100 keV protons @ 1 Hz, ring in normal polarity & reverse direction:– Finalise set up of xfer line from source: need BTV:s, BPM– First injections & circulating beam: need ring BPM:s, tune msmnt, Schottky
system– Orbit/tune/coupling/chromaticity: validation of systems, corrections: need
RF– Acceptance check/studies: need scraper system– Lifetime/blow-up rates– Lattice validation with orbit response msmnts– Study effects of e-cooler solenoids– Acceleration tests & ramp corrections: further RF setup needed incl. B-train– Repeat at intermediate & top plateau
12/11/2015
T.Eriksson CERN BE/OP/AD 7
ELENA setting-up 2• 100 keV H- @ 1 Hz, ring in normal polarity & normal
direction:– Set-up e-cooler– If H- lifetime is too short: use protons, ring in reverse polarity &
normal direction, additional corrections might be necessary later for pbar operation due to remanence effects
– Recombination detection (protons), additional tool for alignment/tuning
– Extensive use of scraper system for profile and emittance msmnts– Schottky analysis for long. Emittances– Cooling time studies– Lifetime/blow-up rates
12/11/2015
T.Eriksson CERN BE/OP/AD 8
ELENA setting-up 3
• 100 keV protons or H- @ 1 Hz, ring in reverse or normal polarity & normal direction:– Initial setting-up of the extraction and ejection
lines (only short sections installed at this stage for main and GBAR lines)
– Need u-wire monitors + high sensitivity intensity msmnt pickup in lines
12/11/2015
T.Eriksson CERN BE/OP/AD 9
ELENA setting-up 4
• 5.3 MeV pbars @ .01 Hz, ring in normal polarity & normal direction:– Set-up transfer line from AD : need BTV, GEM,
TFA7049, BPM. (optics validation)– RF synchro s-u for bunch to bucket transfer– Ramp studies: orbits, tunes, slope– Further e-cooler set-up– Set-up of nominal cycle; obtain nominal emittances– Bunched beam cooling @ extraction
12/11/2015
T.Eriksson CERN BE/OP/AD 10
ELENA setting-up 5• Further studies with pbars: • Space charge studies on higher intensity bunches
(extraction on lower harmonics); compatibility with ejection lines
• Deceleration efficiency > 60% ?• Synthetic B-train, validation for use in regular operation
• => ELENA ring commission complete– ~4 months total time available– Overly optimistic ?
12/11/2015
T.Eriksson CERN BE/OP/AD 11
ELENA setting-up 6
• New transfer lines: 18/8 – 10/10 2017• 100 keV pbars or H-– Setting-up of ~ 100m electrostatic xfer lines– u-wire “semi-non-destructive” profile monitors– Set-up of deflectors used for fast switching
between experiments– Set-up of beam request/distribution SW/HW
• 2 months available
12/11/2015
Operation Sequencing 1/3
Based on ADE sequencing conceptsELENA will have a virtual super cycle ELENA cycle can be:
• Coupled to the Production Chain (beam from ADE)• Standalone mode (beam from source)
Goals Optimize the beam request in the beam production chain Maximize the beam availability for experiments Maximize the MD beams
Bunches destination «On Demand» and prioritized
ELENA Project Review - S.Pasinelli CERN BE/OP12/11/2015
Sequencing 2/3
12/11/2015 ELENA Project Review - S.Pasinelli CERN BE/OP
Sequencing 3/3
12/11/2015 ELENA Project Review - S.Pasinelli CERN BE/OP
ELENABeam Request Server
Experiments request
External conditions
Request Cycle
Human controls
ELENA Central TimingADE
Beam Request Server ELENA Local Timings
Experiments Schedule&
Priorities
Bunches Extraction Timings
12/11/2015 ELENA Project Review - S.Pasinelli CERN BE/OP
B1 B2 B3 B4
EJ Timing
T1
T2
T3
T4
Matrix
Ta Tb Tc ThTd Te Tf Tg
EXPA
EXPB
EXPC
EXPD
EXPE
EXPF
EXPG
EXPH
Constrains
• No more action on the ADE from experiments• Enable/disable extraction kicker
• Static settings in the Common Transfer Lines
12/11/2015 ELENA Project Review - S.Pasinelli CERN BE/OP
T.Eriksson CERN BE/OP/AD 17
OperationManpower
• Commissioning (immediately after AD start-up):– Op-team will work from ACR– AD start-up/operation + ELENA commissioning in 2016– 2 shifts per day can be covered, (weekends) by team of 7/8– Eq. specialists will also participate (EN, TE, BE/ABP etc.)– External help is welcome, discussions underway.
• Once AD/ELENA operational stability obtained:– Machine supervisor from BE/AD/OP team will look after the machines during
day-time and be on-call on weekly basis 24h/24, 7d/7– BE/OP/PS section will do routine operation + initial troubleshooting from the
ccc during nights and weekends– Equipment groups ensure “piquet” or best-effort coverage– Note: yearly AD start-ups are very time-consuming, with ELENA even more so
12/11/2015