Karnataka Rural Water Supply and Sanitation Agency RD and PR Department Additional Financing - Jal Nirm
BILL
No.DESCRIPTION OF ITEM PAGE No.
Amount
(Rs)IN WORDS (Rs)
1SUPPLYING, LAYING AND JOINTING OF GRAVITY MAIN FROM ZBT TO
VILLAGE OHTs
2
CONSTRUCTION OF RCC 4 NUMBERS OF OVER HEAD TANK (ELSR) 75 KL WITH
A STAGING OF 7.50 INCLUDING BARBED WIRE FENCING OF 80 Mtr EACH FOR
Adrahalli,Hullur,sankadal,and devihal villages
3CONSTRUCTION OF RCC OVER HEAD TANK (ELSR) 50,000 LITERS CAPACITY
OVER A STAGING OF 6.5 Mtr FOR SOGIWAL VILLAGE.
4CONSTRUCTION OF RCC OVER HEAD TANK (ELSR) 50,000 LITERS CAPACITY
OVER A STAGING OF 6.0 Mtr FOR KONDIKOPPA VILLAGE.
5CONSTRUCTION OF RCC OVER HEAD TANK (ELSR) 50,000 LITERS CAPACITY
OVER A STAGING OF 10.50 Mtr FOR KUNDRAHALLI TANDA VILLAGE.
6CONSTRUCTION OF RCC OVER HEAD TANK (ELSR) 50,000 LITERS CAPACITY
OVER A STAGING OF 12.00 Mtr FOR adrakatti VILLAGE.
7CONSTRUCTION OF RCC OVER HEAD TANK (ELSR) 50,000 LITERS CAPACITY
OVER A STAGING OF 12.00 Mtr FOR HARADAGATTI VILLAGE.
8 CONSTRUCTION OF THRUST BLOCK OF SIZE (1.2 x 1.2 x 1.2 m ) .39nos
1
2 Unit rates and prices shall be quoted by the bidder in Indian rupee [ITB Clause 14.1].
3 Where there is a discrepancy between the rate in figures and words, the rates in words will govern.[ITB Clause 27.1]
4 Where there is a discrepancy between the unit rate and the line item total resulting from multiplying the unit rate by quantity, the unit rate quoted shall govern [ITB Clause 27.1 (b)].
BILL OF QUANTITIES -PACKAGE 3
Item for which no rate or price has been entered in will not be paid for by the Employer when executed and shall be deemed covered by the other rates and prices in the Bill of Quantity (refer:
ITB Clause 13.2 and GCC Clause 43.3).
Signature of Contractor
No. of Correction(s) ( )
No. of Overwriting(s)( ) Signature of Ady
8/11/2019 Elsr Boq Exampl
2/30
Karnataka Rural Water Supply and Sanitation Agency RD and PR Department Additional Financing - Jal Nirm
BILL
No.DESCRIPTION OF ITEM PAGE No.
Amount
(Rs)IN WORDS (Rs)
11 CONSTRUCTION OF AIR VALVE CHAMBER 41 Nos
12 CONSTRUCTION OF scour valve chamber 62 No's
1
2 Unit rates and prices shall be quoted by the bidder in Indian rupee [ITB Clause 14.1].
3 Where there is a discrepancy between the rate in f igures and words, the rates in words will govern.[ITB Clause 27.1]
4
Item for which no rate or price has been entered in will not be paid for by the Employer when executed and shall be deemed covered by the other rates and prices in the Bill of Quantity (refer:
ITB Clause 13.2 and GCC Clause 43.3).
Where there is a discrepancy between the unit rate and the line item total resulting from multiplying the unit rate by quantity, the unit rate quoted shall govern [ITB Clause 27.1 (b)].
TOTAL =
TOTAL IN WORDS
TOTAL IN FIGURES
Signature of Contractor
No. of Correction(s) ( )
No. of Overwriting(s)( ) Signature of Ady
8/11/2019 Elsr Boq Exampl
3/30
Karnataka Rural Water Supply and Sanitation Agency RD and PR Department
In
Figures
(Rs.)
In Wor
1 2 3 4 5 6 71 Earth Work Exacavation for pipeline trenches including
depositing on bank upto a lead of 50 m including shoring and
strutting danger lighting and using sight rails and boning
rods at every 100 mtrs where ever necessary as directed in the
following strata Mechanical means. complete with all respect
as per specification as directed by engineers incharge
For Pipe of dia 250mm and above
a) In Ordinary Soil Cum 9246.15
b) In Hard Soil Cum 9044.09
c) In Soft Rock Cum 2649.40
d) In Hard Rock with blasting Cum 3101.61
For Pipe Below 250mm Dia
a) In Ordinary Soil Cum 26851.19
b) In Hard Soil Cum 22946.58
c) In Soft Rock Cum 10980.18
d) In Hard Rock with Blasting Cum 7604.05
1
2 Unit rates and prices shall be quoted by the bidder in Indian rupee [ITB Clause 14.1].
3 Where there is a discrepancy between the rate in figures and words, the rates in words will govern.[ITB Clause 27.1]
4 Where there is a discrepancy between the unit rate and the line item total resulting from multiplying the unit rate by quantity, the unit rate quoted shall gover
2 to 2.11/
71 to 77
Unit Quantity
Rate
Item for which no rate or price has been entered in will not be paid for by the Employer when executed and shall be deemed covered by the other rates and prices
ITB Clause 13.2 and GCC Clause 43.3).
o. :- , s e er raw nSECTION OF GRAVITY MAIN OF ALL ZONES
2 to 2.11/
71 to 77
Sl.N
oDescription
Technical
Specifications
Para no/Page
no/Item no
Signature of Contractor
No. of Correction(s) ( )
No. of Overwriting(s)( )
8/11/2019 Elsr Boq Exampl
4/30
Karnataka Rural Water Supply and Sanitation Agency RD and PR Department
InFigures
Rs.
In Wo
1 2 3 4 5 6 7
Unit Quantity
.
o Description
Para no/Page
no/Item no
2 Providing murrum or sand bedding for pipeline including
watering and consolidation by punners etc. complete with all
lead and lift (in black cotton soil & rock reaches) complete
with all respect as per specification as directed by engineers
incharge
2.4.4 / 74 & 4.20.17
/ 112Cum 2737.97
3 Cutting of road surface for pipeline trenches and disposing of
the exacavated stuff as directed including barricading, danger
lighting etc. in the following classification.complete with all
respect as per specification as directed by engineers incharge
Cutting macadam road Cum 18.00
Cutting asphalt road Cum 39.00
4 Providing and laying reinforced cement concrete pipe NP2
for culverts including pointing ends, and fixing collers with
cement morter 1:2 including cost of all materials, labour,
curing complete as per specifications.as directed by engineer
incharge
450mm dia (For 250mm dia and above) Rmt 85.00
300mm dia (For below 250mm dia) Rmt 255.00
1
2 Unit rates and prices shall be quoted by the bidder in Indian rupee [ITB Clause 14.1].
3 Where there is a discrepancy between the rate in figures and words, the rates in words will govern.[ITB Clause 27.1]
4
2.5.3 / 75
5.1 to 5.2.1 / 153 to
154
tem or w c no rate or pr ce as een entere n w not e pa or y t e mp oyer w en execute an s a e eeme covere y t e ot er rates an pr ce
ITB Clause 13.2 and GCC Clause 43.3).
Where there is a discrepancy between the unit rate and the line item total resulting from multiplying the unit rate by quantity, the unit rate quoted shall gov
Signature of Contractor
No. of Correction(s) ( )
No. of Overwriting(s)( )
8/11/2019 Elsr Boq Exampl
5/30
Karnataka Rural Water Supply and Sanitation Agency RD and PR Department
InFigures
Rs.
In Wo
1 2 3 4 5 6 7
Unit Quantity
o Description
Para no/Page
no/Item no
5 Refilling the Basement and pipeline trenches with selected
avalable earth from trench exacavation including, watering,
Consolidation in layers of 15 cm. thick including disposing of
the surplus earth with a lead of 200 meters.complete with all
respect as per specification as directed by engineers incharge
2.5 to 2.5.2 / 74 Cum 21303.28
6 Providing and installing at site of work P.V.C. pipes
including cost of pipes and specials and labour, including
lowering into trenches, laying true to line, level and perfect
linking at joints leak proof including jointing of approved
type with all labour and lift charge, handling charges
including encacing the pipe alround to a depth not less than
15 cms with gravel or selected earth available from the
excavation etc.Giving hydraulic test for C.I., R.C.C., P.V.C.,
H.D.P.E., or A.C pipe line to the pressure equal to 2 items the
working pressure including cost of supply of water., complete
with all respect as per specification as directed by engineers
incharge
10 to 10.5 / 93 to 97
PVC - 10 Ksc Pi es200 mm dia Rmt 900.00
63 mm dia Rmt 121.54PVC - 6 Ksc Pipes
200 mm dia Rmt 9590.00
180 mm dia Rmt 4000.00160 mm dia Rmt 9145.00
1
2 Unit rates and prices shall be quoted by the bidder in Indian rupee [ITB Clause 14.1].3 ere t ere s a screpancy etween t e rate n gures an wor s, t e rates n wor s w govern. ause .
4
10 to 10.5 / 93 to 97
10 to 10.5 / 93 to 97
Item for which no rate or price has been entered in will not be paid for by the Employer when executed and shall be deemed covered by the other rates and prices
ITB Clause 13.2 and GCC Clause 43.3).
Where there is a discrepancy between the unit rate and the line item total resulting from multiplying the unit rate by quantity, the unit rate quoted shall gover
Signature of Contractor
No. of Correction(s) ( )
No. of Overwriting(s)( )
8/11/2019 Elsr Boq Exampl
6/30
Karnataka Rural Water Supply and Sanitation Agency RD and PR Department
InFigures
(Rs.)
In Wo
1 2 3 4 5 6 7
Unit Quantity
o Description
Para no/Page
no/Item no
140 mm dia Rmt 10045.00
110 mm dia Rmt 18865.00
90 mm dia Rmt 8625.00
75 mm dia Rmt 3685.00
63 mm dia Rmt 4950.00
50 mm dia Rmt 5850.00
payment conditions
providing and installing at site of work PVC pipes ,valves
and specials as per relevant IS Codes including cost ofpipe,valves and specials and labour,including lowering into
trenches,layuing true to line,level and perfect linking at
joints leak proof including jointing of approved type with
all labour and lift charges ,handling charges including
encasing the pipe alround to a depth not lessthan 15 cms
with gravel or selected earth available from the excavation
etc complete including Water Meters excluding the Nala and
state highway crossings-60%
Hydraulic test for PVC pipelines to the pressure equal to
two times respectively the workuing pressure including cost
of supply of water -20%
commissioning-20%
1
2 Unit rates and prices shall be quoted by the bidder in Indian rupee [ITB Clause 14.1].
3 Where there is a discrepancy between the rate in figures and words, the rates in words will govern.[ITB Clause 27.1]
4
Item for which no rate or price has been entered in will not be paid for by the Employer when executed and shall be deemed covered by the other rates and prices
ITB Clause 13.2 and GCC Clause 43.3).
Where there is a discrepancy between the unit rate and the line item total resulting from multiplying the unit rate by quantity, the unit rate quoted shall gov
Signature of Contractor
No. of Correction(s) ( )
No. of Overwriting(s)( )
8/11/2019 Elsr Boq Exampl
7/30
Karnataka Rural Water Supply and Sanitation Agency RD and PR Department
InFigures
(Rs.)
In Words
1 2 3 4 5 6 7
Unit Quantity
.
o Description
Para no/Pageno/Item no
7 Supplying H.D.P.E pipes conferming to IS 4948:1995 with
latest amendments and conveying to work site including
loading and unloading at both destination and rolling,
lowering into trenches,laying true to line and joining to pipes
and specials including encasing the pipe around to a depth of
not less than 15cm with soft gravel or selected earth available
from the excavation etc., complete. giving hydraulic test as
per relevant ISS with all lead and lift including testing and
commissioning.The rate is exclusive of required specials and
fittings etc., complete(Contractor will make his own
arrangement for procuring water for testing) complete with allrespect as per specification as directed by engineers incharge
10 to 10.5 / 93 to 97
H.D.P.E Pipes
400 mm dia Rmt 8465.00
355 mm dia Rmt 3875.00
280 mm dia Rmt 3550.00
250 mm dia Rmt 5480.00
payment conditions
providing and installing at site of work HDPE pipes ,valvesand specials as per relevant IS Codes including cost of
pipe,valves and specials and labour,including lowering into
trenches,layuing true to line,level and perfect linking at joints
leak proof including jointing of approved type with all labour
and lift charges ,handling charges including encasing the pipe
alround to a depth not lessthan 15 cms with gravel or selected
earth available from the excavation etc complete including
Water Meters excluding the Nala and state highway crossings
60%
Signature of Contractor
No. of Correction(s) ( )
No. of Overwriting(s)( )
8/11/2019 Elsr Boq Exampl
8/30
Karnataka Rural Water Supply and Sanitation Agency RD and PR Department
In
Figures
(Rs.)
In W
1 2 3 4 5 6
Unit Quantity
.o Description
Para no/Page
no/Item no
Hydraulic test for HDPE pipelines to the pressure equal to
two times respectively the workuing pressure including cost
of supply of water-20%
commissioning-20%
9 Supplying and fixing CI valves of Board approved make
conforming to relevant ISS with latest amendments as
detailed below of following diameters and types and
conveying to work site, loading, unloading, stacking etc,
complete with all lead and lift as per specification as directed
by engineers
1
2 Unit rates and prices shall be quoted by the bidder in Indian rupee [ITB Clause 14.1].
3 Where there is a discrepancy between the rate in figures and words, the rates in words will govern.[ITB Clause 27.1]
4
Item for which no rate or price has been entered in will not be paid for by the Employer when executed and shall be deemed covered by the other rates and pri
ITB Clause 13.2 and GCC Clause 43.3).
Where there is a discrepancy between the unit rate and the line item total resulting from multiplying the unit rate by quantity, the unit rate quoted shall g
Signature of Contractor
No. of Correction(s) ( )
No. of Overwriting(s)( )
8/11/2019 Elsr Boq Exampl
9/30
Karnataka Rural Water Supply and Sanitation Agency RD and PR Department
In
Figures
(Rs.)
In W
1 2 3 4 5 6
Unit Quantity
.o
Description
Para no/Page
no/Item no
(A) CI D.F. Non rising spindle Sluice valves (Category-1)
Body & Seat ring SS PN 1.6 Conforming to IS 14846 : 2000
350 mm dia Each 5.00
300 mm dia Each 1.00
250 mm dia Each 6.00
200 mm dia Each 4.00
150 mm dia Each 8.00
100 mm dia Each 16.00
80 mm dia 19.00
As Scour Valve
80 mm dia Each 70.00
(B) CI Tamper proof Air valves PN 1.6-dimension as per
sketch enclosed and specification Conforming to IS 14845 :
2000
25 mm dia Each 71.00
1
2 Unit rates and prices shall be quoted by the bidder in Indian rupee [ITB Clause 14.1].
3 Where there is a discrepancy between the rate in figures and words, the rates in words will govern.[ITB Clause 27.1]
4
11 to 12.1 / 98 to 99
11 to 12.1 / 98 to 99
em or w c no ra e or pr ce as een en ere n w no e pa or y e mp oyer w en execu e an s a e eeme covere y e o er raes an p
ITB Clause 13.2 and GCC Clause 43.3).
Where there is a discrepancy between the unit rate and the line item total resulting from multiplying the unit rate by quantity, the unit rate quoted shall g
Signature of Contractor
No. of Correction(s) ( )
No. of Overwriting(s)( )
8/11/2019 Elsr Boq Exampl
10/30
Karnataka Rural Water Supply and Sanitation Agency RD and PR Department
InFigures
Rs.
In Wo
1 2 3 4 5 6 7
Unit Quantity
o Description
Para no/Page
no/Item no
10 Providing and fixing of Double Flanged Bulk Water Meter.
Elster (ABB / Kent) H4000 Make Woltmann Type Double
Flanged Turbine Type Bulk Water Meter with removable
mechanism and magnetic drive. The Water Meters would
strictly conform to Class - B of ISO : 4064 Standard and will
bear EEC Certification Mark. The Registration Box would be
hermetically sealed and would be a completely separate unit
with super dry dial and straight reading type. The Impeller
would be hydro dynamically balanced for long term
meteorological reliability and would be the only unit to comein direct contact with flowing water. All other mechanisms
would be completely sealed. Basket Type Dirt Box with
Stainless Steel Strainer suitable for Flanged Connections in
installation of Bulk Water Meters. complete as per
specification as directed by engineers incharge
1 to 15.7/103 to 104
350 mm dia part-19 / 1 to
15.7/103 to 104Each 1.00
300 mm dia part-19 / 1 to
15.7/103 to 104Each 1.00
250 mm diapart-19 / 1 to15.7/103 to 104 Each 6.00
200 mm dia part-19 / 1 to
15.7/103 to 104Each 4.00
150 mm dia part-19 / 1 to
15.7/103 to 104Each 8.00
100 mm dia part-19 / 1 to
15.7/103 to 104Each 16.00
80 mm dia part-19 / 1 to
15.7 103 to 104Each 19.00
Tot
1
2 Unit rates and prices shall be quoted by the bidder in Indian rupee [ITB Clause 14.1].
3 Where there is a discrepancy between the rate in figures and words, the rates in words will govern.[ITB Clause 27.1]
4 Where there is a discrepancy between the unit rate and the line item total resulting from multiplying the unit rate by quantity, the unit rate quoted shall gov
Item for which no rate or price has been entered in will not be paid for by the Employer when executed and shall be deemed covered by the other rates and price
ITB Clause 13.2 and GCC Clause 43.3).
Signature of Contractor
No. of Correction(s) ( )
No. of Overwriting(s)( )
8/11/2019 Elsr Boq Exampl
11/30
8/11/2019 Elsr Boq Exampl
12/30
Karnataka Rural Water Supply and Sanitation Agency RD and PR Department Addition
In Figures
(Rs.)In Words Amou
1 2 3 4 5 6 7
QuantitySl No Unit
Technical
Specifications
Para no/Page
no/Item no
Description
Rate in Rs
Supplying valves of board approved make confirming torelevant ISS with latest amendments as detailed below of
following diameters and types and conveying to work site,
loading, unloading, stakinf etc. complete with all lead and lift
and fixing CI valves. the rate is inclusive of cost jointing
materials
Sluice Valve 100 mm dia No 4.00
Scour Valve 80 mm dia No 12.00
Providing and casting RCC spiral stair case for the OHT
including steel reinforcement etc..complete. No 4.00
4 nos of chain link Fencing for P-OHT's for a length of 80 Mtrs
each No 4.00
All the above works be carried out as per the drawings enclosed,
as per the specifications and also as per the instructions of the
Engineer-in-Charge.
PAYMENT CONDITION FOR OHT (ELSR)Completion of earth work and foundation - 10%
Completion of bottom slab - 15%
Completion of side wall - 20%
Completion of fencing & roof slab - 15%
Finishing works - 10%
Pipe connections and accessories - 15%Hydraulic Testing - 10%
Commissioning and trial running - 5%
TOTAL
1
2 Unit rates and prices shall be quoted by the bidder in Indian rupee [ITB Clause 14.1].
3 Where there is a discrepancy between the rate in figures and words, the rates in words will govern.[ITB Clause 27.1]
4 Where there is a discrepancy between the unit rate and the line item total resulting from multiplying the unit rate by quantity, the unit rate quoted shall govern [ITB Clause 27.1 (b)].
em or w c no ra e or pr ce as een en ere n w no e pa or y e mp oyer w en execu e an s a e eeme covere y e o er ra es an pr ces n e o uan y re er
Clause 13.2 and GCC Clause 43.3).
13 to 16 / 99 to 105
Signature of Contractor
No. of Correction(s) ( )
No. of Overwriting(s)( )
8/11/2019 Elsr Boq Exampl
13/30
Karnataka Rural Water Supply and Sanitation Agency RD and PR Department Additiona
In Figures
Rs.In Words Amount (R
1 Constructing RCC Over Head Tank (ELSR) of 50,000 litres
capacity over a staging of 6.5 Mtr, conforming to the design
and drawing enclosed with the bid document including
excavation in all types of strata providing and casting column
footing/ Raft, columns, braces, ring beams, bottom dome,
conical portion, shell portion, top dome, landing with
providing and fabricating required steel reinforcement as per
design etc.. complete. All structural members and water
retaining structures are to be in M-30 concrete. For shell
portion CM plastering 1:3 proportion 20 mm thick with an
admixture of water proof compound of requisite proportion
and of approved quality to be provided for inside. Providingtwo coats of water proof cement painting of approved colour
and shade over one coat of primer, including providing and
fixing all accessories as given below:-
RCC Hexa onal finial and ventilator. No 1M.S.Inspection door of size 60cms x60 cms with MS frame.
No 1
Enamelled gauge plate water level indicator. No 1
Copper Lightening Arrestor No 1
Providin and fixin 32 MM dia GI i e 'A' class i e railin RMT 37.39Anodised Aluminium ladder No 4
1
2 Unit rates and prices shall be quoted by the bidder in Indian rupee [ ITB Clause 14.1].
3 Where there is a discrepancy between the rate in figures and words, the rates in words will govern.[ITB Clause 27.1]
4
Item for which no rate or price has been entered in will not be paid for by the Employer when executed and shall be deemed covered by the other rates and prices in the Bill of Quantity (refer: ITBClause 13.2 and GCC Clause 43.3).
Where there is a discrepancy between the unit rate and the line item total resulting from multiplying the unit rate by quantity, the unit rate quoted shall govern [ITB Clause 27.1 (b)].
BILL. NO. 3. CONSTRUCTION OF RCC OVER HEAD TANK (ELSR) 50,000 LITERS CAPACITY OVER A STAGING OF 6.5 Mtr
INCLUDING CHAIN LINK FENCING FOR SOGIWAL VILLAGE. (DWG NO ADH/MVS/GADAG/PCC-OHT-05)
QuantitySl
No Unit
Technical
Specifications
Para no/Page
no/Item no
Rate in Rs
Description
13 to 14 / 99 to 103
Signature of Contractor
No. of Correction(s) ( )
No. of Overwriting(s)( )
8/11/2019 Elsr Boq Exampl
14/30
Karnataka Rural Water Supply and Sanitation Agency RD and PR Department
In Figures
Rs.In Words A
QuantitySl
NoUnit
Technical
Specifications
Para no/Page
no/Item no
Rate in RsDescription
Supplying valves of board approved make confirming torelevant ISS with latest amendments as detailed below of
following diameters and types and conveying to work site,
loading, unloading, stakinf etc. complete with all lead and lift
and fixing CI valves. the rate is inclusive of cost jointing
materials
Sluice Valve 100 mm dia No 1
Scour Valve 80 mm dia No 3
Providing and casting RCC spiral stair case for the OHT
including steel reinforcement etc..complete.No 1
chain link Fencing for P-OHT's for a length of 80 Mtrs eachNo 1.00
All the above works be carried out as per the drawingsenclosed, as per the specifications and also as per the
instructions of the Engineer-in-Charge.
PAYMENT CONDITION FOR OHT (ELSR)Completion of earth work and foundation - 10%
Completion of bottom slab - 15%
Completion of side wall - 20%
Completion of fencing & roof slab - 15%
Finishing works - 10%
Pipe connections and accessories - 15%
Hydraulic Testing - 10%
Commissioning and trial running - 5%
1
2 Unit rates and prices shall be quoted by the bidder in Indian rupee [ITB Clause 14.1].
3 Where there is a discrepancy between the rate in figures and words, the rates in words will govern.[ITB Clause 27.1]
4
Total Rs.Item for which no rate or price has been entered in will not be paid for by the Employer when executed and shall be deemed covered by the other rates and prices in the Bill of Quant
Clause 13.2 and GCC Clause 43.3).
Where there is a discrepancy between the unit rate and the line item total resulting from multiplying the unit rate by quantity, the unit rate quoted shall govern [ITB Clause 27.1 (b)].
13 to 16 / 99 to 105
Signature of Contractor
No. of Correction(s) ( )
No. of Overwriting(s)( )
8/11/2019 Elsr Boq Exampl
15/30
Karnataka Rural Water Supply and Sanitation Agency RD and PR Department Additiona
In Figures
(Rs.)In Words Amount (R
1 Constructing RCC Over Head Tank (ELSR) of 50,000 litres
capacity over a staging of 6.0 Mtr, conforming to the design and
drawing enclosed with the bid document including excavation in
all types of strata providing and casting column-footing/ Raft,
columns, braces, ring beams, bottom dome, conical portion, shell
portion, top dome, landing with providing and fabricating
required steel reinforcement as per design etc.. complete. All
structural members and water retaining structures are to be in M-
30 concrete. For shell portion CM plastering 1:3 proportion 20
mm thick with an admixture of water proof compound ofrequisite proportion and of approved quality to be provided for
inside. Providing two coats of water proof cement painting of
approved colour and shade over one coat of primer, including
providing and fixing all accessories as given below:-
RCC Hexagonal finial and ventilator. No 1
M.S.Inspection door of size 60 cms x 60 cms with MS frame.No 1.00
Enamelled gauge plate water level indicator.(2.65m long) No 1.00
Copper Lightening Arrestor No 1.00
Providin and fixin 32 MM dia GI i e 'A' class i e railin in 2 Rmt 37.38Anodised Aluminium ladder Rmt 4
1
2 Unit rates and prices shall be quoted by the bidder in Indian rupee [ITB Clause 14.1].
3 Where there is a discrepancy between the rate in figures and words, the rates in words will govern.[ITB Clause 27.1]
4
Technical
SpecificationsPara no/Page no/Item
no
Rate in Rs
Description
Item for which no rate or price has been entered in will not be paid for by the Employer when executed and shall be deemed covered by the other rates and prices in the Bill of Quantity (refer: ITB
Clause 13.2 and GCC Clause 43.3).
Where there is a discrepancy between the unit rate and the line item total resulting from multiplying the unit rate by quantity, the unit rate quoted shall govern [ITB Clause 27.1 (b)].
BILL. NO. 4. CONSTRUCTION OF RCC OVER HEAD TANK (ELSR) 50,000 LITERS CAPACITY OVER A STAGING OF 6.0 Mtr
INCLUDING CHAIN LINK FENCING FOR KONDIKOPPA VILLAGE. (Refer Drawing no -ADH/MVS/GADAG/PCC-OHT-05 )
QuantitySlNo
Unit
13 to 14 / 99 to 103
Signature of Contractor
No. of Correction(s) ( )
No. of Overwriting(s)( )
8/11/2019 Elsr Boq Exampl
16/30
Karnataka Rural Water Supply and Sanitation Agency RD and PR Department
In Figures
(Rs.)
In Words Am
Technical
Specifications
Para no/Page no/Item
no
Rate in Rs
Description QuantitySl
NoUnit
Supplying valves of board approved make confirming to relevant
ISS with latest amendments as detailed below of following
diameters and types and conveying to work site, loading,
unloading, stakinf etc. complete with all lead and lift and fixing
CI valves. the rate is inclusive of cost jointing materials
Sluice Valve 200 mm dia
Sluice Valve 100 mm dia No 1
Scour Valve 80 mm dia No 3
Conducting hydraulic/ water tightness test for container.
Providing and casting RCC spiral stair case for the OHTincluding steel reinforcement etc..complete.
No 1
chain link Fencing for P-OHT's for a length of 80 Mtrs eachNo 1.00
All the above works be carried out as per the drawings enclosed,
as per the specifications and also as per the instructions of the
Engineer-in-Charge.
PAYMENT CONDITION FOR OHT (ELSR)Completion of earth work and foundation - 10%
Completion of bottom slab - 15%
Completion of side wall - 20%
Completion of fencing & roof slab - 15%
Finishing works - 10%
Pipe connections and accessories - 15%
Hydraulic Testing - 10%
Commissioning and trial running - 5%
1
2 Unit rates and prices shall be quoted by the bidder in Indian rupee [ITB Clause 14.1].
3 Where there is a discrepancy between the rate in figures and words, the rates in words will govern.[ITB Clause 27.1]
4
13 to 16 / 99 to 105
Total Rstem or w c no rate or prce as een entere n w not e pa or y t e mp oyer w en execute an s a e eeme covere y t e ot er rates an pr ces n t e o uant ty r
Clause 13.2 and GCC Clause 43.3).
Where there is a discrepancy between the unit rate and the line item total resulting from multiplying the unit rate by quantity, the unit rate quoted shall govern [ITB Clause 27.1 (b)].
Signature of Contractor
No. of Correction(s) ( )
No. of Overwriting(s)( )
8/11/2019 Elsr Boq Exampl
17/30
Karnataka Rural Water Supply and Sanitation Agency RD and PR Department
In Figures
(Rs.)In W
1 Constructing RCC Over Head Tank (ELSR) of 50,000 litres capacity
over a staging of 10.50 Mtr, conforming to the design and drawing
enclosed with the bid document including excavation in all types of
strata providing and casting column-footing/ Raft, columns, braces,
ring beams, bottom dome, conical portion, shell portion, top dome,
landing with providing and fabricating required steel reinforcement
as per design etc.. complete. All structural members and water
retaining structures are to be in M-30 concrete. For shell portion CM
plastering 1:3 proportion 20 mm thick with an admixture of water
proof compound of requisite proportion and of approved quality to be
provided for inside. Providing two coats of water proof cement
painting of approved colour and shade over one coat of primer,
includin rovidin and fixin all accessories as iven below:-
RCC Hexagonal finial and ventilator. No 1.00
M.S.Inspection door of size 60 cms x 60 cms with MS frame. No 1.00
Enamelled gauge plate water level indicator. No 1.00
Copper Lightening Arrestor No 1.00
Providing and fixing 32 MM dia GI pipe 'A' class pipe railing in 2
rows on top dome, flat slab and landings.Rmt 37.39
Anodised Aluminium ladder No 4.00
1
2 Unit rates and prices shall be quoted by the bidder in Indian rupee [ITB Clause 14.1].
3 Where there is a discrepancy between the rate in figures and words, the rates in words will govern.[ITB Clause 27.1]
4
Item for which no rate or price has been entered in will not be paid for by the Employer when executed and shall be deemed covered by the other rates and prices in the Bill of Quantity
Clause 43.3).
Where there is a discrepancy between the unit rate and the line item total resulting from multiplying the unit rate by quantity, the unit rate quoted shall govern [ITB Clause 27.1 (b)].
BILL. NO. 5. CONSTRUCTION OF RCC OVER HEAD TANK (ELSR) 50,000 LITERS CAPACITY OVER A STAGING OF 10
CHAIN LINK FENCING FOR KUNDRAHALLI TANDA VILLAGE. (Refer Drawing no -ADH/MVS/GADAG/PC
QuantitySlNo
13 to 14 / 99 to 103
Unit
Technical
SpecificationsPara no/Page no/Item
no
RaDescription
Signature of Contractor
No. of Correction(s) ( )
No. of Overwriting(s)( )
8/11/2019 Elsr Boq Exampl
18/30
Karnataka Rural Water Supply and Sanitation Agency RD and PR Department
In Figures
Rs.
QuantitySl
No
Unit
Technical
Specifications
Para no/Page no/Item
no
Description
Supplying valves of board approved make confirming to relevant ISS
with latest amendments as detailed below of following diameters and
types and conveying to work site, loading, unloading, stakinf etc.
complete with all lead and lift and fixing CI valves. the rate is
inclusive of cost jointing materials
Sluice Valve 200 mm dia
Sluice Valve 100 mm dia No 1.00
Scour Valve 80 mm dia No 3.00
Conducting hydraulic/ water tightness test for container.
Providing and casting RCC spiral stair case for the OHT including
steel reinforcement etc..complete.No 1.00
chain link Fencing for P-OHT's for a length of 80 Mtrs each No 1.00
All the above works be carried out as per the drawings enclosed, as
per the specifications and also as per the instructions of the Engineer-
in-Charge.
PAYMENT CONDITION FOR OHT (ELSR)Completion of earth work and foundation - 10%
Completion of bottom slab - 15%
Completion of side wall - 20%
Completion of fencing & roof slab - 15%
Finishing works - 10%
Pipe connections and accessories - 15%
Hydraulic Testing - 10%
Commissioning and trial running - 5%
1
2 Unit rates and prices shall be quoted by the bidder in Indian rupee [ITB Clause 14.1].
3 Where there is a discrepancy between the rate in figures and words, the rates in words will govern.[ITB Clause 27.1]
4 Where there is a discrepancy between the unit rate and the line item total resulting from multiplying the unit rate by quantity, the unit rate quoted shall govern [ITB Clause
Item for which no rate or price has been entered in will not be paid for by the Employer when executed and shall be deemed covered by the other rates and prices in the Bill
Clause 43.3).
13 to 15 / 99 to 105
Signature of Contractor
No. of Correction(s) ( )
No. of Overwriting(s)( )
8/11/2019 Elsr Boq Exampl
19/30
Karnataka Rural Water Supply and Sanitation Agency RD and PR Department
In Figures
(Rs.)In Words A
1 Constructing RCC Over Head Tank (ELSR) of 50,000 litres
capacity over a staging of 12.00 Mtr, conforming to the design and
drawing enclosed with the bid document including excavation in
all types of strata providing and casting column-footing/ Raft,
columns, braces, ring beams, bottom dome, conical portion, shell
portion, top dome, landing with providing and fabricating
required steel reinforcement as per design etc.. complete. All
structural members and water retaining structures are to be in M-
30 concrete. For shell portion CM plastering 1:3 proportion 20 mm
thick with an admixture of water proof compound of requisite
proportion and of approved quality to be provided for inside.
Providing two coats of water proof cement painting of approved
colour and shade over one coat of primer, including providing
and fixing all accessories as given below:-
RCC Hexagonal finial and ventilator. No 1.00
M.S.Ins ection door of size 60 cms x 60 cms with MS frame. No 1Enamelled gauge plate water level indicator. No 1
Copper Lightening Arrestor No 1Providing and fixing 32 MM dia GI pipe 'A' class pipe railing in 2
rows on top dome, flat slab and landings.Rmt 37.39
Anodised Aluminium ladder
1
2 Unit rates and prices shall be quoted by the bidder in Indian rupee [ITB Clause 14.1].
3 Where there is a discrepancy between the rate in figures and words, the rates in words will govern.[ITB Clause 27.1]
4
Item for which no rate or price has been entered in will not be paid for by the Employer when executed and shall be deemed covered by the other rates and prices in the Bill of Quantity (re
Clause 13.2 and GCC Clause 43.3).
Where there is a discrepancy between the unit rate and the line item total resulting from multiplying the unit rate by quantity, the unit rate quoted shall govern [ITB Clause 27.1 (b)].
BILL. NO. 6. CONSTRUCTION OF RCC OVER HEAD TANK (ELSR) 50,000 LITERS CAPACITY OVER A STAGING OF 12.0
INCLUDING CHAIN LINK FENCING FOR adrakatti VILLAGE. (Refer Drawing no -ADH/MVS/GADAG/PCC-OHT-05
Quantity
Rate in Rs
13 to 14 / 99 to
103
Sl
NoDescription
Technical
Specifications
Para no/Page
no/Item no
Unit
Signature of Contractor
No. of Correction(s) ( )
No. of Overwriting(s)( )
8/11/2019 Elsr Boq Exampl
20/30
Karnataka Rural Water Supply and Sanitation Agency RD and PR Department
Supplying valves of board approved make confirming to relevant
ISS with latest amendments as detailed below of following
diameters and types and conveying to work site, loading,
unloading, stakinf etc. complete with all lead and lift and fixing CI
valves. the rate is inclusive of cost jointing materials
Sluice Valve 200 mm dia No 1.00
Scour Valve 80 mm dia No 3.00
Conducting hydraulic/ water tightness test for container.
Providing and casting RCC spiral stair case for the OHT including
steel reinforcement etc..complete.No 1.00
chain link Fencing for P-OHT's for a length of 80 Mtrs eachNo 1.00
All the above works be carried out as per the drawings enclosed,
as per the specifications and also as per the instructions of the
Engineer-in-Charge.
PAYMENT CONDITION FOR OHT (ELSR)Completion of earth work and foundation - 10%
Completion of bottom slab - 15%
Completion of side wall - 20%
Completion of fencing & roof slab - 15%
Finishing works - 10%
Pipe connections and accessories - 15%
Hydraulic Testing - 10%
Commissioning and trial running - 5% TOTAL
1
2 Unit rates and prices shall be quoted by the bidder in Indian rupee [ITB Clause 14.1].3 Where there is a discrepancy between the rate in figures and words, the rates in words will govern.[ITB Clause 27.1]
4
Item for which no rate or price has been entered in will not be paid for by the Employer when executed and shall be deemed covered by the other rates and prices in the Bill
Clause 13.2 and GCC Clause 43.3).
Where there is a discrepancy between the unit rate and the line item total resulting from multiplying the unit rate by quantity, the unit rate quoted shall govern [ITB Clause 2
13 to 16 / 99 to
105
Signature of Contractor
No. of Correction(s) ( )
No. of Overwriting(s)( )
8/11/2019 Elsr Boq Exampl
21/30
Karnataka Rural Water Supply and Sanitation Agency RD and PR Department
In Figures
(Rs.)In W
1 Constructing RCC Over Head Tank (ELSR) of 50,000 litres
capacity over a staging of 12.00 Mtr, conforming to the design and
drawing enclosed with the bid document including excavation in
all types of strata providing and casting column-footing/ Raft,
columns, braces, ring beams, bottom dome, conical portion, shell
portion, top dome, landing with providing and fabricating
required steel reinforcement as per design etc.. complete. All
structural members and water retaining structures are to be in M-
30 concrete. For shell portion CM plastering 1:3 proportion 20 mm
thick with an admixture of water proof compound of requisite
proportion and of approved quality to be provided for inside.
Providing two coats of water proof cement painting of approved
colour and shade over one coat of primer, including providing
and fixing all accessories as given below:-
RCC Hexagonal finial and ventilator. No 1.00
M.S.Inspection door of size 60 cms x 60 cms with MS frame.No 1.00
Enamelled gauge plate water level indicator. No 1.00
Copper Lightening Arrestor No 1.00Providin and fixin 32 MM dia GI i e 'A' class i e railin in 2 RMTR 37.39
Anodised Aluminium ladder
1
2 Unit rates and prices shall be quoted by the bidder in Indian rupee [ITB Clause 14.1].
3 Where there is a discrepancy between the rate in figures and words, the rates in words will govern.[ITB Clause 27.1]
4
Item for which no rate or price has been entered in will not be paid for by the Employer when executed and shall be deemed covered by the other rates and prices in the Bill of Quantity (
43.3).
Where there is a discrepancy between the unit rate and the line item total resulting from multiplying the unit rate by quantity, the unit rate quoted shall govern [ITB Clause 27.1 (b)].
BILL. NO. 7. CONSTRUCTION OF RCC OVER HEAD TANK (ELSR) 50,000 LITERS CAPACITY OVER A STAGING OF 12.00
LINK FENCING FOR HARADAGATTI VILLAGE. (Refer Drawing no -ADH/MVS/GADAG/PCC-OHT-
Quantity
Rate
13 to 14 / 99 to
103
Sl No Description
TechnicalSpecifications
Para no/Page
no/Item no
Unit
ignature of Contractor
No. of Correction(s) ( )
No. of Overwriting(s)( )
8/11/2019 Elsr Boq Exampl
22/30
Karnataka Rural Water Supply and Sanitation Agency RD and PR Department
In Figures(Rs.)
Quantity
Sl No Description
Technical
Specifications
Para no/Page
no/Item no
Unit
Supplying valves of board approved make confirming to relevant
ISS with latest amendments as detailed below of following
diameters and types and conveying to work site, loading,
unloading, stakinf etc. complete with all lead and lift and fixing CI
valves. the rate is inclusive of cost jointing materials
Sluice Valve 200 mm dia No 1.00
Scour Valve 80 mm dia No 3.00
Conducting hydraulic/ water tightness test for container.
Providing and casting RCC spiral stair case for the OHT including
steel reinforcement etc..complete. No 1.00
chain link Fencing for P-OHT's for a length of 80 Mtrs each No 1.00
All the above works be carried out as per the drawings enclosed,
as per the specifications and also as per the instructions of the
Engineer-in-Charge.
PAYMENT CONDITION FOR OHT (ELSR)Completion of earth work and foundation - 10%
Completion of bottom slab - 15%
Completion of side wall - 20%
Completion of fencing & roof slab - 15%
Finishing works - 10%
Pipe connections and accessories - 15%
Hydraulic Testing - 10%Commissioning and trial running - 5%
TOTAL
1
2 Unit rates and prices shall be quoted by the bidder in Indian rupee [ITB Clause 14.1].
3 Where there is a discrepancy between the rate in figures and words, the rates in words will govern.[ITB Clause 27.1]
4
Item for which no rate or price has been entered in will not be paid for by the Employer when executed and shall be deemed covered by the other rates and prices in the Bill
43.3).
Where there is a discrepancy between the unit rate and the line item total resulting from multiplying the unit rate by quantity, the unit rate quoted shall govern [ITB Clause 27
13 to 16 / 99 to
105
Signature of Contractor
No. of Correction(s) ( )
No. of Overwriting(s)( )
8/11/2019 Elsr Boq Exampl
23/30
Karnataka Rural Water Supply and Sanitation Agency RD and PR Department
In
Figures
(Rs.)
Materials
civil works
1 Earth Work Exacavation for foundation and removing the excavated stuff to adistance not exceeding 50mtrs and with a lift upto 1.50 mtrs. including shoring,
strutting, barricading, danger lighting etc., complete by Mechanical means.
Complete in all respect as directed by engineers in charge
a) in Ordinary soil cum 35.10
b) in Hard soil cum 35.10c) in Ordinary rock Without blasting cum 35.10
d) in Hard Rock with blasting cum 12.09
2 Providing and laying granite or trap jelly M-10 cement concrete using 40 mmand down size jelly for foundation laid in 15 cms thick layers and well
compacted including machine mixing, curing as per specification etc., complete
for foundation. With all respect as dirtected by engineer incharge
3 to 3.13.2
77 to 80cum 7.80
3 Providing& laying C.C 1 M-15 grade using granite or basalt or trap jelly 20 mmand down size including mixing laying, tamping, curing plastering for exposed
faces with cement mortar 1:3 by mixing 1 kg of water proof compound for
every one bag of cement for top plaster finish and with necessary centering and
form work etc. complete for flooring of GLSR. cills, coping, bond slab and for
any other such workcom,plete with all respect as directgd by engineers
incharge
5.3 / 83 cum 70.20
4 Labour charges for fabricating M.S. bars/ TMT for steel bars of all sizesincluding cleaning, straightening, cutting, bending, hooking, lapping and or
welding, wherever required, placing in position and tieing with binding wire of
approved quality and guage as per design including cost of binding wire,
hoisting etc., complete with all respect as directed by engineers incharge
9.1.3 to 9.1.5 / 88 cum 1971.45
1
2 Unit rates and prices shall be quoted by the bidder in Indian rupee [ITB Clause 14.1].
3 Where there is a discrepancy between the rate in figures and words, the rates in words will govern.[ITB Clause 27.1]
4
Item for which no rate or price has been entered in will not be paid for by the Employer when executed and shall be deemed covered by the other rates and p
ITB Clause 13.2 and GCC Clause 43.3).
Where there is a discrepancy between the unit rate and the line item total resulting from multiplying the unit rate by quantity, the unit rate quoted shall gover
2 to 2.11 / 70 to 76
BILL. NO. 8. CONSTRUCTION OF THRUST BLOCK OF SIZE (1.2 x 1.2 x 1.2 m )-39Nos . (Refer Drg. No. ADH/M
13 )
Sl No Description
Technical
Specifications
Para no/Page
no/Item no
Unit Quantity
Signature of Contractor
No. of Correction(s) ( )
No. of Overwriting(s)( )
8/11/2019 Elsr Boq Exampl
24/30
Karnataka Rural Water Supply and Sanitation Agency RD and PR Department
In Fig
(R
Materials
civil works
1 Earth Work Exacavation for foundation and removing the
excavated stuff to a distance not exceeding 50mtrs and with a lift
upto 1.50 mtrs. including shoring, strutting, barricading, danger
lighting etc., complete by Mechanical means. Complete in all
respect as directed by engineers in charge
a) in Ordinary soil cum 120.24b) in Hard soil cum 120.24
c) in Ordinary rock Without blasting cum 120.24
d) in Hard Rock with blasting cum 36.74
2 Providing and laying granite or trap jelly M-10 cement concrete
using 40 mm and down sizejelly for foundation laid in 15 cms
thick layers and well compacted including machine mixing,
curing as per specification etc., complete for foundation. With all
respect as dirtected by engineer incharge
3 to 3.13.2
77 to 80cum 30.06
3 Providing& laying C.C 1 M-15 grade using granite or basalt or
trap jelly 20 mm and down size including mixing laying,
tamping, curing plastering for exposed faces with cement mortar
1:3 by mixing 1 kg of water proof compound for every one bag ofcement for top plaster finish and with necessary centering and
form work etc. complete for flooring of GLSR. cills, coping,
bond slab and for any other such workcom,plete with all
respect as directgd by engineers incharge
5.3 / 83 cum 173.68
4 Labour charges for fabricating M.S. bars/ TMT for steel bars of
all sizes including cleaning, straightening, cutting, bending,
hooking, lapping and or welding, wherever required, placing in
position and tieing with binding wire of approved quality and
guage as per design including cost of binding wire, hoisting etc.,
complete with all respect as directed by engineers incharge
9.1.3 to 9.1.5 / 88 cum 13026.00
1
2 Unit rates and prices shall be quoted by the bidder in Indian rupee [ITB Clause 14.1].
3 Where there is a discrepancy between the rate in figures and words, the rates in words will govern.[ITB Clause 27.1]
4
Item for which no rate or price has been entered in will not be paid for by the Employer when executed and shall be deemed covered by the other rates and
13.2 and GCC Clause 43.3).
Where there is a discrepancy between the unit rate and the line item total resulting from multiplying the unit rate by quantity, the unit rate quoted shall gov
2 to 2.11 / 70 to 76
BILL. NO. 9. CONSTRUCTION OF THRUST BLOCK OF SIZE (0.8 x 0.8 x 0.8 m )-334 Nos . (Refer Drg. No.
13 )
Sl No Description
TechnicalSpecifications
Para no/Page
no/Item no
Unit Quantity
Rate in
Signature of Contractor
No. of Correction(s) ( )
No. of Overwriting(s)( )
8/11/2019 Elsr Boq Exampl
25/30
arnataka Rural Water Supply and Sanitation Agency RD and PR Department Addi
In Figures(Rs.)
In Words Amount (Rs)
1 2 3 4 5 6 7 8
1 Earth Work Exacavation for foundation and removing the excavated
stuff to a distance not exceeding 50mtrs and with a lift upto 1.50 mtrs.
including shoring, strutting, barricading, danger lighting etc.,
complete by Mechanical means. Complete in all respect as directed
by engineers incharge
in ordinary soil Cum 150.88
in hard soil Cum 113.16
in Ordinary rock Without blasting Cum 113.16
2 Providing and laying granite or trap jelly M-10 cement concrete using
40 mm and down sizejelly for foundation laid in 15 cms thick layers
and well compacted including machine mixing, curing as per
specification etc., complete for foundation.with all respect as directed
by Engineers incharge
3 to 3.13.277 to 80
Cum 28.98
3 Providing and constructing granite or trap or basalt or sand stone,
Coursed Rubble Second Sort Size Masonry with CM 1:6 proportion,
courses not less than 20 cms high with bond stones at 2M apart in
each course, edges of stone chisel dressed and all corners 2 line
dressed 5 cms wide on each face, including scaffolding, curing etc.,
complete as per specifications.as directed by engineers incharge
5.3 / 83 Cum 201.02
1
2 Unit rates and prices shall be quoted by the bidder in Indian rupee [ITB Clause 14.1].
3 Where there is a discrepancy between the rate in figures and words, the rates in words will govern.[ITB Clause 27.1]
4
em or w c no ra e or pr ce as een en ere n w no e pa or y e mp oyer w en execu e an s a e eeme covere y e o er ra es an
prices in the Bill of Quantity (refer: ITB Clause 13.2 and GCC Clause 43.3).
Where there is a discrepancy between the unit rate and the line item total resulting from multiplying the unit rate by quantity, the unit rate quoted shall
govern [ITB Clause 27.1 (b)].
2 to 2.11 / 70
to 76
BILL No.10:-CONSTRUCTION OF sluice valve chamber 1 No's (Refer Drawing no - ADH/MVS/GADAG/HW/PCC-12 )
Sl.No Description
Technical
Specificatio
nsPara
no/Page
Unit Quantity
Rate in RS
gnature of Contractor
No. of Correction(s) ( )
No. of Overwriting(s)( )
8/11/2019 Elsr Boq Exampl
26/30
arnataka Rural Water Supply and Sanitation Agency RD and PR Department Addi
4 Providing pointing to stone masonry walls in C.M. 1:3 proportion
after raking the joints to a depth of 25 mm and nicely lining including
scaffolding, curing, etc., complete as per specifications.
As directed by engineers incharge
9.1.3 to 9.1.5
/ 88Cum 308.20
5 Providing and laying cement concrete (M-10) proportion using
granite or trap or basalt jelly 20 mm and down size including
watering mixing, laying, tamping, curing and plastering to exposed
faces with cement mortar 1.3 proportion and with necessary
centering, form work etc.,complete as per specifications
As directed by engineers in charge
3 to 3.13.2
77 to 80Cum 6.90
6 Providing& laying C.C (M15) grade using granite or basalt or trap
jelly 20 mm and down size including mixing laying, tamping, curing
plastering for exposed faces with cement mortar 1:3 by mixing 1 kg of
water proof compound for every one bag of cement for top plaster
finish and with necessary centering and form work etc. complete for
flooring of GLSR. cills, coping, bond slab and for any other such work
3 to 3.13.2
77 to 80Cum 9.20
7 Providing and laying M-25 Cement concrete proportion using clean
graded granite or trap or basalt jelly 20 mm and down size for RCC
Roof Slab, canopies of all spans with steel or plywood or plank
centering and shuttering, including machine mixing, lifting, laying,
vibrating, tamping, including smooth finishing, curing for all exposed
faces complete in all respect as directed by engineer incharge
3 to 3.13.2
77 to 80Cum 18.40
8 Labour charges for fabricating M.S. bars/ TMT for steel bars of all
sizes including cleaning, straightening, cutting, bending, hooking,
lapping and or welding, wherever required, placing in position and
tieing with binding wire of approved quality and guage as per design
including cost of binding wire, hoisting etc., complete including
conveying steel rods. (Including providing steel bars)
3 to 3.13.2
77 to 80Kg 2233.30
TOTAL
1
2 Unit rates and prices shall be quoted by the bidder in Indian rupee [ITB Clause 14.1].
3 Where there is a discrepancy between the rate in figures and words, the rates in words will govern.[ITB Clause 27.1]
4
Item for which no rate or price has been entered in will not be paid for by the Employer when executed and shall be deemed covered by the other rates and
prices in the Bill of Quantity (refer: ITB Clause 13.2 and GCC Clause 43.3).
Where there is a discrepancy between the unit rate and the line item total resulting from multiplying the unit rate by quantity, the unit rate quoted shall
govern [ITB Clause 27.1 (b)].
gnature of Contractor
No. of Correction(s) ( )
No. of Overwriting(s)( )
8/11/2019 Elsr Boq Exampl
27/30
Karnataka Rural Water Supply and Sanitation Agency RD and PR Department
In Figures(Rs.)
In Words Amo(Rs
1 2 3 4 5 6 7 8
1 Earth Work Exacavation for foundation and removing the excavated
stuff to a distance not exceeding 50mtrs and with a lift upto 1.50 mtrs.
including shoring, strutting, barricading, danger lighting etc.,
complete by Mechanical means.
in ordinary soil Cum 134.48
in hard soil Cum 100.86
in Ordinary rock Without blasting Cum 100.86
2 Providing and laying granite or trap jelly M-10 cement concrete using
40 mm and down sizejelly for foundation laid in 15 cms thick layers
and well compacted including machine mixing, curing as per
specification etc., complete for foundation.
Concreting in Foundation Bed C.C 1:4:8
3 to 3.13.2
77 to 80Cum 25.83
3 Providing and constructing granite or trap or basalt or sand stone,
Coursed Rubble Second Sort Size Masonry with CM 1:6 proportion,
courses not less than 20 cms high with bond stones at 2M apart in each
course, edges of stone chisel dressed and all corners 2 line dressed 5
cms wide on each face, including scaffolding, curing etc., complete as
per specifications.
For basement
5.3 / 83 Cum 179.17
4 Providing pointing to stone masonry walls in C.M. 1:3 proportion
after raking the joints to a depth of 25 mm and nicely lining including
scaffolding, curing, etc., complete as per specifications.
9.1.3 to 9.1.5
/ 88Cum 274.70
1
2 Unit rates and prices shall be quoted by the bidder in Indian rupee [ITB Clause 14.1].
3 Where there is a discrepancy between the rate in figures and words, the rates in words will govern.[ITB Clause 27.1]
4
Item for which no rate or price has been entered in will not be paid for by the Employer when executed and shall be deemed covered by the other rates an
prices in the Bill of Quantity (refer: ITB Clause 13.2 and GCC Clause 43.3).
Where there is a discrepancy between the unit rate and the line item total resulting from multiplying the unit rate by quantity, the unit rate quoted shall go
[ITB Clause 27.1 (b)].
2 to 2.11 / 70
to 76
BILL No.11:-CONSTRUCTION OF AIR valve chamber 10 No's (Refer Drawing no - ADH/MVS/GADAG/AW-06
Sl.No Description
Technical
Specificatio
nsPara no/Page
no/Item no
Unit Quantity
Rate in RS
Signature of Contractor
No. of Correction(s) ( )
No. of Overwriting(s)( )
8/11/2019 Elsr Boq Exampl
28/30
Karnataka Rural Water Supply and Sanitation Agency RD and PR Department
In Figures
(Rs.)In Words
Am
(
1 2 3 4 5 6 7
Sl.No Description
Technical
Specificatio
ns
Para no/Page
no/Item no
Unit Quantity
Rate in RS
5 Providing and laying cement concrete 1:3:6 (M-10) proportion using
granite or trap or basalt jelly 20 mm and down size including watering
mixing, laying, tamping, curing and plastering to exposed faces with
cement mortar 1.3 proportion and with necessary centering, form work
etc.,complete as per specifications
For cills, coping, Bond slab
3 to 3.13.2
77 to 80Cum 6.15
6 Providing& laying C.C m15 proportion using granite or basalt or trap
jelly 20 mm and down size including mixing laying, tamping, curing
plastering for exposed faces with cement mortar 1:3 by mixing 1 kg of
water proof compound for every one bag of cement for top plaster
finish and with necessary centering and form work etc. complete forflooring of GLSR. cills, coping, bond slab and for any other such work
For coping
3 to 3.13.2
77 to 80Cum 8.20
7 Providing and laying M-25 Cement concrete proportion using clean
graded granite or trap or basalt jelly 20 mm and down size for RCC
Roof Slab, canopies of all spans with steel or plywood or plank
centering and shuttering, including machine mixing, lifting, laying,
vibrating, tamping, including smooth finishing, curing for all exposed
faces (exclusive of cost of steel and fabrication charges)
3 to 3.13.2
77 to 80Cum 25.01
8 Labour charges for fabricating M.S. bars/ TMT for steel bars of all
sizes including cleaning, straightening, cutting, bending, hooking,
lapping and or welding, wherever required, placing in position and
tieing with binding wire of approved quality and guage as per designincluding cost of binding wire, hoisting etc. , complete including
conveying steel rods. (Including providing steel bars)
3 to 3.13.2
77 to 80
Kg 1980.30
1
2 Unit rates and prices shall be quoted by the bidder in Indian rupee [ITB Clause 14.1].
3 Where there is a discrepancy between the rate in figures and words, the rates in words will govern.[ITB Clause 27.1]
4
Item for which no rate or price has been entered in will not be paid for by the Employer when executed and shall be deemed covered by the other rates
prices in the Bill of Quantity (refer: ITB Clause 13.2 and GCC Clause 43.3).
Where there is a discrepancy between the unit rate and the line item total resulting from multiplying the unit rate by quantity, the unit rate quoted shall
[ITB Clause 27.1 (b)].
Signature of Contractor
No. of Correction(s) ( )
No. of Overwriting(s)( )
8/11/2019 Elsr Boq Exampl
29/30
Karnataka Rural Water Supply and Sanitation Agency RD and PR Department
1 2 3 4
1 Earth Work Exacavation for foundation and removing the
excavated stuff to a distance not exceeding 50mtrs and with a lift
upto 1.50 mtrs. including shoring, strutting, barricading, danger
lighting etc., complete by Mechanical means. Complete in all
respect as directed by engineers incharge
in ordinary soil Cum
in hard soil Cum
in Ordinary rock Without blasting Cum
2 Providing and laying granite or trap jelly M-10 cement concrete
using 40 mm and down sizejelly for foundation laid in 15 cms
thick layers and well compacted including machine mixing,
curing as per specification etc., complete for foundation.with all
respect as directed by ingineers incharge
3 to 3.13.2
77 to 80Cum
3 Providing and constructing granite or trap or basalt or sand stone,
Coursed Rubble Second Sort Size Masonry with CM 1:6
proportion, courses not less than 20 cms high with bond stones at
2M apart in each course, edges of stone chisel dressed and al l
corners 2 line dressed 5 cms wide on each face, including
scaffolding, curing etc., complete as per specifications.as directedby engineers incharge
5.3 / 83 Cum
4 Providing pointing to stone masonry walls in C.M. 1:3 proportion
after raking the joints to a depth of 25 mm and nicely lining
including scaffolding, curing, etc., complete as per specifications.
As directed by engineers incharge
9.1.3 to 9.1.5 /
88Cum
5 Providing and laying cement concrete (M-10) proportion using
granite or trap or basalt jelly 20 mm and down size including
watering mixing, laying, tamping, curing and plastering to
exposed faces with cement mortar 1.3 proportion and with
necessary centering, form work etc.,complete as per specifications
As directed by engineers in charge
3 to 3.13.2
77 to 80Cum
6 Providing& laying C.C (M15) grade using granite or basalt or trapjelly 20 mm and down size including mixing laying, tamping,
curing plastering for exposed faces with cement mortar 1:3 by
mixing 1 kg ofwater proof compound for every one bag of cement
for top plaster finish and with necessary centering and form work
etc. complete for flooring of GLSR. cills, coping, bond slab and for
any other such work
3 to 3.13.2
77 to 80Cum
1
2 Unit rates and prices shall be quoted by the bidder in Indian rupee [ITB Clause 14.1].
3 Where there is a discrepancy between the rate in figures and words, the rates in words will govern.[ITB Claus
4
tem or w c no rate or pr ce as een entere n w not e pa or y t e mp oyer w en execute an s a
Bill of Quantity (refer: ITB Clause 13.2 and GCC Clause 43.3).
Where there is a discrepancy between the unit rate and the line item total resulting from multiplying the unit ra
Clause 27.1 (b)].
2 to 2.11 / 70 to
76
BILL No.12:-CONSTRUCTION OF scour valve chamber 20 No's (Refer Drawing no -
Sl.No Description
Technical
Specifications
Para no/Page
no/Item no
Unit Q
Signature of Contractor
No. of Correction(s) ( )
No. of Overwriting(s)( )
8/11/2019 Elsr Boq Exampl
30/30
Karnataka Rural Water Supply and Sanitation Agency RD and PR Department
1 2 3 4
Sl.No Description
Technical
SpecificationsPara no/Page
no/Item no
Unit Q
7 Providing and laying M-25 Cement concrete proportion using
clean graded granite or trap or basalt jelly 20 mm and down size
for RCC Roof Slab, canopies of all spans with steel or plywood or
plank centering and shuttering, including machine mixing, lifting,
laying, vibrating, tamping, including smooth finishing, curing for
all exposed faces complete in all respect as directed by engineer
incharge
3 to 3.13.2
77 to 80Cum
8 Labour charges for fabricating M.S. bars/ TMT for steel bars of
all sizes including cleaning, straightening, cutting, bending,
hooking, lapping and or welding, wherever required, placing in
position and tieing with binding wire of approved quality and
guage as per design including cost of binding wire, hoisting etc.,
complete including conveying steel rods. (Including providing
steel bars)
3 to 3.13.2
77 to 80Kg 5
9 Supplying laying, jointing testing and commissioning of GI pipes
conforming to IS 1239 : 1990 with latest amendments including
fixing collars, elbows, tees, bends, gland cocks and other fittings
(excluding cost of specials) with cuts and threads wherever
necessary including conveying the materials to work spot
including testing for water tightness, with all lead. (constructor
will make his own arrangements for procuring water for testing).
80mm dia pipe (Medium duty) 1m on either side of CI valves
10 to 10.5 / 93 to
97Rmt
1
2 Unit rates and prices shall be quoted by the bidder in Indian rupee [ITB Clause 14.1].
3 Where there is a discrepancy between the rate in figures and words, the rates in words will govern.[ITB Clause
4
Item for which no rate or price has been entered in will not be paid for by the Employer when executed and sha
Bill of Quantity (refer: ITB Clause 13.2 and GCC Clause 43.3).
Where there is a discrepancy between the unit rate and the line item total resulting from multiplying the unit ra
Clause 27.1 (b)].