    Karnataka Rural Water Supply and Sanitation Agency RD and PR Department Additional Financing - Jal Nirm

    BILL

    No.DESCRIPTION OF ITEM PAGE No.

    Amount

    (Rs)IN WORDS (Rs)

    1SUPPLYING, LAYING AND JOINTING OF GRAVITY MAIN FROM ZBT TO

    VILLAGE OHTs

    2

    CONSTRUCTION OF RCC 4 NUMBERS OF OVER HEAD TANK (ELSR) 75 KL WITH

    A STAGING OF 7.50 INCLUDING BARBED WIRE FENCING OF 80 Mtr EACH FOR

    Adrahalli,Hullur,sankadal,and devihal villages

    3CONSTRUCTION OF RCC OVER HEAD TANK (ELSR) 50,000 LITERS CAPACITY

    OVER A STAGING OF 6.5 Mtr FOR SOGIWAL VILLAGE.

    4CONSTRUCTION OF RCC OVER HEAD TANK (ELSR) 50,000 LITERS CAPACITY

    OVER A STAGING OF 6.0 Mtr FOR KONDIKOPPA VILLAGE.

    5CONSTRUCTION OF RCC OVER HEAD TANK (ELSR) 50,000 LITERS CAPACITY

    OVER A STAGING OF 10.50 Mtr FOR KUNDRAHALLI TANDA VILLAGE.

    6CONSTRUCTION OF RCC OVER HEAD TANK (ELSR) 50,000 LITERS CAPACITY

    OVER A STAGING OF 12.00 Mtr FOR adrakatti VILLAGE.

    7CONSTRUCTION OF RCC OVER HEAD TANK (ELSR) 50,000 LITERS CAPACITY

    OVER A STAGING OF 12.00 Mtr FOR HARADAGATTI VILLAGE.

    8 CONSTRUCTION OF THRUST BLOCK OF SIZE (1.2 x 1.2 x 1.2 m ) .39nos

    1

    2 Unit rates and prices shall be quoted by the bidder in Indian rupee [ITB Clause 14.1].

    3 Where there is a discrepancy between the rate in figures and words, the rates in words will govern.[ITB Clause 27.1]

    4 Where there is a discrepancy between the unit rate and the line item total resulting from multiplying the unit rate by quantity, the unit rate quoted shall govern [ITB Clause 27.1 (b)].

    BILL OF QUANTITIES -PACKAGE 3

    Item for which no rate or price has been entered in will not be paid for by the Employer when executed and shall be deemed covered by the other rates and prices in the Bill of Quantity (refer:

    ITB Clause 13.2 and GCC Clause 43.3).

    Signature of Contractor

    No. of Correction(s) ( )

    No. of Overwriting(s)( ) Signature of Ady

  • 8/11/2019 Elsr Boq Exampl

    2/30

    Karnataka Rural Water Supply and Sanitation Agency RD and PR Department Additional Financing - Jal Nirm

    BILL

    No.DESCRIPTION OF ITEM PAGE No.

    Amount

    (Rs)IN WORDS (Rs)

    11 CONSTRUCTION OF AIR VALVE CHAMBER 41 Nos

    12 CONSTRUCTION OF scour valve chamber 62 No's

    1

    2 Unit rates and prices shall be quoted by the bidder in Indian rupee [ITB Clause 14.1].

    3 Where there is a discrepancy between the rate in f igures and words, the rates in words will govern.[ITB Clause 27.1]

    4

    Item for which no rate or price has been entered in will not be paid for by the Employer when executed and shall be deemed covered by the other rates and prices in the Bill of Quantity (refer:

    ITB Clause 13.2 and GCC Clause 43.3).

    Where there is a discrepancy between the unit rate and the line item total resulting from multiplying the unit rate by quantity, the unit rate quoted shall govern [ITB Clause 27.1 (b)].

    TOTAL =

    TOTAL IN WORDS

    TOTAL IN FIGURES

    Signature of Contractor

    No. of Correction(s) ( )

    No. of Overwriting(s)( ) Signature of Ady

  • 8/11/2019 Elsr Boq Exampl

    3/30

    Karnataka Rural Water Supply and Sanitation Agency RD and PR Department

    In

    Figures

    (Rs.)

    In Wor

    1 2 3 4 5 6 71 Earth Work Exacavation for pipeline trenches including

    depositing on bank upto a lead of 50 m including shoring and

    strutting danger lighting and using sight rails and boning

    rods at every 100 mtrs where ever necessary as directed in the

    following strata Mechanical means. complete with all respect

    as per specification as directed by engineers incharge

    For Pipe of dia 250mm and above

    a) In Ordinary Soil Cum 9246.15

    b) In Hard Soil Cum 9044.09

    c) In Soft Rock Cum 2649.40

    d) In Hard Rock with blasting Cum 3101.61

    For Pipe Below 250mm Dia

    a) In Ordinary Soil Cum 26851.19

    b) In Hard Soil Cum 22946.58

    c) In Soft Rock Cum 10980.18

    d) In Hard Rock with Blasting Cum 7604.05

    1

    2 Unit rates and prices shall be quoted by the bidder in Indian rupee [ITB Clause 14.1].

    3 Where there is a discrepancy between the rate in figures and words, the rates in words will govern.[ITB Clause 27.1]

    4 Where there is a discrepancy between the unit rate and the line item total resulting from multiplying the unit rate by quantity, the unit rate quoted shall gover

    2 to 2.11/

    71 to 77

    Unit Quantity

    Rate

    Item for which no rate or price has been entered in will not be paid for by the Employer when executed and shall be deemed covered by the other rates and prices

    ITB Clause 13.2 and GCC Clause 43.3).

    o. :- , s e er raw nSECTION OF GRAVITY MAIN OF ALL ZONES

    2 to 2.11/

    71 to 77

    Sl.N

    oDescription

    Technical

    Specifications

    Para no/Page

    no/Item no

    Signature of Contractor

    No. of Correction(s) ( )

    No. of Overwriting(s)( )

  • 8/11/2019 Elsr Boq Exampl

    4/30

    Karnataka Rural Water Supply and Sanitation Agency RD and PR Department

    InFigures

    Rs.

    In Wo

    1 2 3 4 5 6 7

    Unit Quantity

    .

    o Description

    Para no/Page

    no/Item no

    2 Providing murrum or sand bedding for pipeline including

    watering and consolidation by punners etc. complete with all

    lead and lift (in black cotton soil & rock reaches) complete

    with all respect as per specification as directed by engineers

    incharge

    2.4.4 / 74 & 4.20.17

    / 112Cum 2737.97

    3 Cutting of road surface for pipeline trenches and disposing of

    the exacavated stuff as directed including barricading, danger

    lighting etc. in the following classification.complete with all

    respect as per specification as directed by engineers incharge

    Cutting macadam road Cum 18.00

    Cutting asphalt road Cum 39.00

    4 Providing and laying reinforced cement concrete pipe NP2

    for culverts including pointing ends, and fixing collers with

    cement morter 1:2 including cost of all materials, labour,

    curing complete as per specifications.as directed by engineer

    incharge

    450mm dia (For 250mm dia and above) Rmt 85.00

    300mm dia (For below 250mm dia) Rmt 255.00

    1

    2 Unit rates and prices shall be quoted by the bidder in Indian rupee [ITB Clause 14.1].

    3 Where there is a discrepancy between the rate in figures and words, the rates in words will govern.[ITB Clause 27.1]

    4

    2.5.3 / 75

    5.1 to 5.2.1 / 153 to

    154

    tem or w c no rate or pr ce as een entere n w not e pa or y t e mp oyer w en execute an s a e eeme covere y t e ot er rates an pr ce

    ITB Clause 13.2 and GCC Clause 43.3).

    Where there is a discrepancy between the unit rate and the line item total resulting from multiplying the unit rate by quantity, the unit rate quoted shall gov

    Signature of Contractor

    No. of Correction(s) ( )

    No. of Overwriting(s)( )

  • 8/11/2019 Elsr Boq Exampl

    5/30

    Karnataka Rural Water Supply and Sanitation Agency RD and PR Department

    InFigures

    Rs.

    In Wo

    1 2 3 4 5 6 7

    Unit Quantity

    o Description

    Para no/Page

    no/Item no

    5 Refilling the Basement and pipeline trenches with selected

    avalable earth from trench exacavation including, watering,

    Consolidation in layers of 15 cm. thick including disposing of

    the surplus earth with a lead of 200 meters.complete with all

    respect as per specification as directed by engineers incharge

    2.5 to 2.5.2 / 74 Cum 21303.28

    6 Providing and installing at site of work P.V.C. pipes

    including cost of pipes and specials and labour, including

    lowering into trenches, laying true to line, level and perfect

    linking at joints leak proof including jointing of approved

    type with all labour and lift charge, handling charges

    including encacing the pipe alround to a depth not less than

    15 cms with gravel or selected earth available from the

    excavation etc.Giving hydraulic test for C.I., R.C.C., P.V.C.,

    H.D.P.E., or A.C pipe line to the pressure equal to 2 items the

    working pressure including cost of supply of water., complete

    with all respect as per specification as directed by engineers

    incharge

    10 to 10.5 / 93 to 97

    PVC - 10 Ksc Pi es200 mm dia Rmt 900.00

    63 mm dia Rmt 121.54PVC - 6 Ksc Pipes

    200 mm dia Rmt 9590.00

    180 mm dia Rmt 4000.00160 mm dia Rmt 9145.00

    1

    2 Unit rates and prices shall be quoted by the bidder in Indian rupee [ITB Clause 14.1].3 ere t ere s a screpancy etween t e rate n gures an wor s, t e rates n wor s w govern. ause .

    4

    10 to 10.5 / 93 to 97

    10 to 10.5 / 93 to 97

    Item for which no rate or price has been entered in will not be paid for by the Employer when executed and shall be deemed covered by the other rates and prices

    ITB Clause 13.2 and GCC Clause 43.3).

    Where there is a discrepancy between the unit rate and the line item total resulting from multiplying the unit rate by quantity, the unit rate quoted shall gover

    Signature of Contractor

    No. of Correction(s) ( )

    No. of Overwriting(s)( )

  • 8/11/2019 Elsr Boq Exampl

    6/30

    Karnataka Rural Water Supply and Sanitation Agency RD and PR Department

    InFigures

    (Rs.)

    In Wo

    1 2 3 4 5 6 7

    Unit Quantity

    o Description

    Para no/Page

    no/Item no

    140 mm dia Rmt 10045.00

    110 mm dia Rmt 18865.00

    90 mm dia Rmt 8625.00

    75 mm dia Rmt 3685.00

    63 mm dia Rmt 4950.00

    50 mm dia Rmt 5850.00

    payment conditions

    providing and installing at site of work PVC pipes ,valves

    and specials as per relevant IS Codes including cost ofpipe,valves and specials and labour,including lowering into

    trenches,layuing true to line,level and perfect linking at

    joints leak proof including jointing of approved type with

    all labour and lift charges ,handling charges including

    encasing the pipe alround to a depth not lessthan 15 cms

    with gravel or selected earth available from the excavation

    etc complete including Water Meters excluding the Nala and

    state highway crossings-60%

    Hydraulic test for PVC pipelines to the pressure equal to

    two times respectively the workuing pressure including cost

    of supply of water -20%

    commissioning-20%

    1

    2 Unit rates and prices shall be quoted by the bidder in Indian rupee [ITB Clause 14.1].

    3 Where there is a discrepancy between the rate in figures and words, the rates in words will govern.[ITB Clause 27.1]

    4

    Item for which no rate or price has been entered in will not be paid for by the Employer when executed and shall be deemed covered by the other rates and prices

    ITB Clause 13.2 and GCC Clause 43.3).

    Where there is a discrepancy between the unit rate and the line item total resulting from multiplying the unit rate by quantity, the unit rate quoted shall gov

    Signature of Contractor

    No. of Correction(s) ( )

    No. of Overwriting(s)( )

  • 8/11/2019 Elsr Boq Exampl

    7/30

    Karnataka Rural Water Supply and Sanitation Agency RD and PR Department

    InFigures

    (Rs.)

    In Words

    1 2 3 4 5 6 7

    Unit Quantity

    .

    o Description

    Para no/Pageno/Item no

    7 Supplying H.D.P.E pipes conferming to IS 4948:1995 with

    latest amendments and conveying to work site including

    loading and unloading at both destination and rolling,

    lowering into trenches,laying true to line and joining to pipes

    and specials including encasing the pipe around to a depth of

    not less than 15cm with soft gravel or selected earth available

    from the excavation etc., complete. giving hydraulic test as

    per relevant ISS with all lead and lift including testing and

    commissioning.The rate is exclusive of required specials and

    fittings etc., complete(Contractor will make his own

    arrangement for procuring water for testing) complete with allrespect as per specification as directed by engineers incharge

    10 to 10.5 / 93 to 97

    H.D.P.E Pipes

    400 mm dia Rmt 8465.00

    355 mm dia Rmt 3875.00

    280 mm dia Rmt 3550.00

    250 mm dia Rmt 5480.00

    payment conditions

    providing and installing at site of work HDPE pipes ,valvesand specials as per relevant IS Codes including cost of

    pipe,valves and specials and labour,including lowering into

    trenches,layuing true to line,level and perfect linking at joints

    leak proof including jointing of approved type with all labour

    and lift charges ,handling charges including encasing the pipe

    alround to a depth not lessthan 15 cms with gravel or selected

    earth available from the excavation etc complete including

    Water Meters excluding the Nala and state highway crossings

    60%

    Signature of Contractor

    No. of Correction(s) ( )

    No. of Overwriting(s)( )

  • 8/11/2019 Elsr Boq Exampl

    8/30

    Karnataka Rural Water Supply and Sanitation Agency RD and PR Department

    In

    Figures

    (Rs.)

    In W

    1 2 3 4 5 6

    Unit Quantity

    .o Description

    Para no/Page

    no/Item no

    Hydraulic test for HDPE pipelines to the pressure equal to

    two times respectively the workuing pressure including cost

    of supply of water-20%

    commissioning-20%

    9 Supplying and fixing CI valves of Board approved make

    conforming to relevant ISS with latest amendments as

    detailed below of following diameters and types and

    conveying to work site, loading, unloading, stacking etc,

    complete with all lead and lift as per specification as directed

    by engineers

    1

    2 Unit rates and prices shall be quoted by the bidder in Indian rupee [ITB Clause 14.1].

    3 Where there is a discrepancy between the rate in figures and words, the rates in words will govern.[ITB Clause 27.1]

    4

    Item for which no rate or price has been entered in will not be paid for by the Employer when executed and shall be deemed covered by the other rates and pri

    ITB Clause 13.2 and GCC Clause 43.3).

    Where there is a discrepancy between the unit rate and the line item total resulting from multiplying the unit rate by quantity, the unit rate quoted shall g

    Signature of Contractor

    No. of Correction(s) ( )

    No. of Overwriting(s)( )

  • 8/11/2019 Elsr Boq Exampl

    9/30

    Karnataka Rural Water Supply and Sanitation Agency RD and PR Department

    In

    Figures

    (Rs.)

    In W

    1 2 3 4 5 6

    Unit Quantity

    .o

    Description

    Para no/Page

    no/Item no

    (A) CI D.F. Non rising spindle Sluice valves (Category-1)

    Body & Seat ring SS PN 1.6 Conforming to IS 14846 : 2000

    350 mm dia Each 5.00

    300 mm dia Each 1.00

    250 mm dia Each 6.00

    200 mm dia Each 4.00

    150 mm dia Each 8.00

    100 mm dia Each 16.00

    80 mm dia 19.00

    As Scour Valve

    80 mm dia Each 70.00

    (B) CI Tamper proof Air valves PN 1.6-dimension as per

    sketch enclosed and specification Conforming to IS 14845 :

    2000

    25 mm dia Each 71.00

    1

    2 Unit rates and prices shall be quoted by the bidder in Indian rupee [ITB Clause 14.1].

    3 Where there is a discrepancy between the rate in figures and words, the rates in words will govern.[ITB Clause 27.1]

    4

    11 to 12.1 / 98 to 99

    11 to 12.1 / 98 to 99

    em or w c no ra e or pr ce as een en ere n w no e pa or y e mp oyer w en execu e an s a e eeme covere y e o er raes an p

    ITB Clause 13.2 and GCC Clause 43.3).

    Where there is a discrepancy between the unit rate and the line item total resulting from multiplying the unit rate by quantity, the unit rate quoted shall g

    Signature of Contractor

    No. of Correction(s) ( )

    No. of Overwriting(s)( )

  • 8/11/2019 Elsr Boq Exampl

    10/30

    Karnataka Rural Water Supply and Sanitation Agency RD and PR Department

    InFigures

    Rs.

    In Wo

    1 2 3 4 5 6 7

    Unit Quantity

    o Description

    Para no/Page

    no/Item no

    10 Providing and fixing of Double Flanged Bulk Water Meter.

    Elster (ABB / Kent) H4000 Make Woltmann Type Double

    Flanged Turbine Type Bulk Water Meter with removable

    mechanism and magnetic drive. The Water Meters would

    strictly conform to Class - B of ISO : 4064 Standard and will

    bear EEC Certification Mark. The Registration Box would be

    hermetically sealed and would be a completely separate unit

    with super dry dial and straight reading type. The Impeller

    would be hydro dynamically balanced for long term

    meteorological reliability and would be the only unit to comein direct contact with flowing water. All other mechanisms

    would be completely sealed. Basket Type Dirt Box with

    Stainless Steel Strainer suitable for Flanged Connections in

    installation of Bulk Water Meters. complete as per

    specification as directed by engineers incharge

    1 to 15.7/103 to 104

    350 mm dia part-19 / 1 to

    15.7/103 to 104Each 1.00

    300 mm dia part-19 / 1 to

    15.7/103 to 104Each 1.00

    250 mm diapart-19 / 1 to15.7/103 to 104 Each 6.00

    200 mm dia part-19 / 1 to

    15.7/103 to 104Each 4.00

    150 mm dia part-19 / 1 to

    15.7/103 to 104Each 8.00

    100 mm dia part-19 / 1 to

    15.7/103 to 104Each 16.00

    80 mm dia part-19 / 1 to

    15.7 103 to 104Each 19.00

    Tot

    1

    2 Unit rates and prices shall be quoted by the bidder in Indian rupee [ITB Clause 14.1].

    3 Where there is a discrepancy between the rate in figures and words, the rates in words will govern.[ITB Clause 27.1]

    4 Where there is a discrepancy between the unit rate and the line item total resulting from multiplying the unit rate by quantity, the unit rate quoted shall gov

    Item for which no rate or price has been entered in will not be paid for by the Employer when executed and shall be deemed covered by the other rates and price

    ITB Clause 13.2 and GCC Clause 43.3).

    Signature of Contractor

    No. of Correction(s) ( )

    No. of Overwriting(s)( )

  • 8/11/2019 Elsr Boq Exampl

    11/30

  • 8/11/2019 Elsr Boq Exampl

    12/30

    Karnataka Rural Water Supply and Sanitation Agency RD and PR Department Addition

    In Figures

    (Rs.)In Words Amou

    1 2 3 4 5 6 7

    QuantitySl No Unit

    Technical

    Specifications

    Para no/Page

    no/Item no

    Description

    Rate in Rs

    Supplying valves of board approved make confirming torelevant ISS with latest amendments as detailed below of

    following diameters and types and conveying to work site,

    loading, unloading, stakinf etc. complete with all lead and lift

    and fixing CI valves. the rate is inclusive of cost jointing

    materials

    Sluice Valve 100 mm dia No 4.00

    Scour Valve 80 mm dia No 12.00

    Providing and casting RCC spiral stair case for the OHT

    including steel reinforcement etc..complete. No 4.00

    4 nos of chain link Fencing for P-OHT's for a length of 80 Mtrs

    each No 4.00

    All the above works be carried out as per the drawings enclosed,

    as per the specifications and also as per the instructions of the

    Engineer-in-Charge.

    PAYMENT CONDITION FOR OHT (ELSR)Completion of earth work and foundation - 10%

    Completion of bottom slab - 15%

    Completion of side wall - 20%

    Completion of fencing & roof slab - 15%

    Finishing works - 10%

    Pipe connections and accessories - 15%Hydraulic Testing - 10%

    Commissioning and trial running - 5%

    TOTAL

    1

    2 Unit rates and prices shall be quoted by the bidder in Indian rupee [ITB Clause 14.1].

    3 Where there is a discrepancy between the rate in figures and words, the rates in words will govern.[ITB Clause 27.1]

    4 Where there is a discrepancy between the unit rate and the line item total resulting from multiplying the unit rate by quantity, the unit rate quoted shall govern [ITB Clause 27.1 (b)].

    em or w c no ra e or pr ce as een en ere n w no e pa or y e mp oyer w en execu e an s a e eeme covere y e o er ra es an pr ces n e o uan y re er

    Clause 13.2 and GCC Clause 43.3).

    13 to 16 / 99 to 105

    Signature of Contractor

    No. of Correction(s) ( )

    No. of Overwriting(s)( )

  • 8/11/2019 Elsr Boq Exampl

    13/30

    Karnataka Rural Water Supply and Sanitation Agency RD and PR Department Additiona

    In Figures

    Rs.In Words Amount (R

    1 Constructing RCC Over Head Tank (ELSR) of 50,000 litres

    capacity over a staging of 6.5 Mtr, conforming to the design

    and drawing enclosed with the bid document including

    excavation in all types of strata providing and casting column

    footing/ Raft, columns, braces, ring beams, bottom dome,

    conical portion, shell portion, top dome, landing with

    providing and fabricating required steel reinforcement as per

    design etc.. complete. All structural members and water

    retaining structures are to be in M-30 concrete. For shell

    portion CM plastering 1:3 proportion 20 mm thick with an

    admixture of water proof compound of requisite proportion

    and of approved quality to be provided for inside. Providingtwo coats of water proof cement painting of approved colour

    and shade over one coat of primer, including providing and

    fixing all accessories as given below:-

    RCC Hexa onal finial and ventilator. No 1M.S.Inspection door of size 60cms x60 cms with MS frame.

    No 1

    Enamelled gauge plate water level indicator. No 1

    Copper Lightening Arrestor No 1

    Providin and fixin 32 MM dia GI i e 'A' class i e railin RMT 37.39Anodised Aluminium ladder No 4

    1

    2 Unit rates and prices shall be quoted by the bidder in Indian rupee [ ITB Clause 14.1].

    3 Where there is a discrepancy between the rate in figures and words, the rates in words will govern.[ITB Clause 27.1]

    4

    Item for which no rate or price has been entered in will not be paid for by the Employer when executed and shall be deemed covered by the other rates and prices in the Bill of Quantity (refer: ITBClause 13.2 and GCC Clause 43.3).

    Where there is a discrepancy between the unit rate and the line item total resulting from multiplying the unit rate by quantity, the unit rate quoted shall govern [ITB Clause 27.1 (b)].

    BILL. NO. 3. CONSTRUCTION OF RCC OVER HEAD TANK (ELSR) 50,000 LITERS CAPACITY OVER A STAGING OF 6.5 Mtr

    INCLUDING CHAIN LINK FENCING FOR SOGIWAL VILLAGE. (DWG NO ADH/MVS/GADAG/PCC-OHT-05)

    QuantitySl

    No Unit

    Technical

    Specifications

    Para no/Page

    no/Item no

    Rate in Rs

    Description

    13 to 14 / 99 to 103

    Signature of Contractor

    No. of Correction(s) ( )

    No. of Overwriting(s)( )

  • 8/11/2019 Elsr Boq Exampl

    14/30

    Karnataka Rural Water Supply and Sanitation Agency RD and PR Department

    In Figures

    Rs.In Words A

    QuantitySl

    NoUnit

    Technical

    Specifications

    Para no/Page

    no/Item no

    Rate in RsDescription

    Supplying valves of board approved make confirming torelevant ISS with latest amendments as detailed below of

    following diameters and types and conveying to work site,

    loading, unloading, stakinf etc. complete with all lead and lift

    and fixing CI valves. the rate is inclusive of cost jointing

    materials

    Sluice Valve 100 mm dia No 1

    Scour Valve 80 mm dia No 3

    Providing and casting RCC spiral stair case for the OHT

    including steel reinforcement etc..complete.No 1

    chain link Fencing for P-OHT's for a length of 80 Mtrs eachNo 1.00

    All the above works be carried out as per the drawingsenclosed, as per the specifications and also as per the

    instructions of the Engineer-in-Charge.

    PAYMENT CONDITION FOR OHT (ELSR)Completion of earth work and foundation - 10%

    Completion of bottom slab - 15%

    Completion of side wall - 20%

    Completion of fencing & roof slab - 15%

    Finishing works - 10%

    Pipe connections and accessories - 15%

    Hydraulic Testing - 10%

    Commissioning and trial running - 5%

    1

    2 Unit rates and prices shall be quoted by the bidder in Indian rupee [ITB Clause 14.1].

    3 Where there is a discrepancy between the rate in figures and words, the rates in words will govern.[ITB Clause 27.1]

    4

    Total Rs.Item for which no rate or price has been entered in will not be paid for by the Employer when executed and shall be deemed covered by the other rates and prices in the Bill of Quant

    Clause 13.2 and GCC Clause 43.3).

    Where there is a discrepancy between the unit rate and the line item total resulting from multiplying the unit rate by quantity, the unit rate quoted shall govern [ITB Clause 27.1 (b)].

    13 to 16 / 99 to 105

    Signature of Contractor

    No. of Correction(s) ( )

    No. of Overwriting(s)( )

  • 8/11/2019 Elsr Boq Exampl

    15/30

    Karnataka Rural Water Supply and Sanitation Agency RD and PR Department Additiona

    In Figures

    (Rs.)In Words Amount (R

    1 Constructing RCC Over Head Tank (ELSR) of 50,000 litres

    capacity over a staging of 6.0 Mtr, conforming to the design and

    drawing enclosed with the bid document including excavation in

    all types of strata providing and casting column-footing/ Raft,

    columns, braces, ring beams, bottom dome, conical portion, shell

    portion, top dome, landing with providing and fabricating

    required steel reinforcement as per design etc.. complete. All

    structural members and water retaining structures are to be in M-

    30 concrete. For shell portion CM plastering 1:3 proportion 20

    mm thick with an admixture of water proof compound ofrequisite proportion and of approved quality to be provided for

    inside. Providing two coats of water proof cement painting of

    approved colour and shade over one coat of primer, including

    providing and fixing all accessories as given below:-

    RCC Hexagonal finial and ventilator. No 1

    M.S.Inspection door of size 60 cms x 60 cms with MS frame.No 1.00

    Enamelled gauge plate water level indicator.(2.65m long) No 1.00

    Copper Lightening Arrestor No 1.00

    Providin and fixin 32 MM dia GI i e 'A' class i e railin in 2 Rmt 37.38Anodised Aluminium ladder Rmt 4

    1

    2 Unit rates and prices shall be quoted by the bidder in Indian rupee [ITB Clause 14.1].

    3 Where there is a discrepancy between the rate in figures and words, the rates in words will govern.[ITB Clause 27.1]

    4

    Technical

    SpecificationsPara no/Page no/Item

    no

    Rate in Rs

    Description

    Item for which no rate or price has been entered in will not be paid for by the Employer when executed and shall be deemed covered by the other rates and prices in the Bill of Quantity (refer: ITB

    Clause 13.2 and GCC Clause 43.3).

    Where there is a discrepancy between the unit rate and the line item total resulting from multiplying the unit rate by quantity, the unit rate quoted shall govern [ITB Clause 27.1 (b)].

    BILL. NO. 4. CONSTRUCTION OF RCC OVER HEAD TANK (ELSR) 50,000 LITERS CAPACITY OVER A STAGING OF 6.0 Mtr

    INCLUDING CHAIN LINK FENCING FOR KONDIKOPPA VILLAGE. (Refer Drawing no -ADH/MVS/GADAG/PCC-OHT-05 )

    QuantitySlNo

    Unit

    13 to 14 / 99 to 103

    Signature of Contractor

    No. of Correction(s) ( )

    No. of Overwriting(s)( )

  • 8/11/2019 Elsr Boq Exampl

    16/30

    Karnataka Rural Water Supply and Sanitation Agency RD and PR Department

    In Figures

    (Rs.)

    In Words Am

    Technical

    Specifications

    Para no/Page no/Item

    no

    Rate in Rs

    Description QuantitySl

    NoUnit

    Supplying valves of board approved make confirming to relevant

    ISS with latest amendments as detailed below of following

    diameters and types and conveying to work site, loading,

    unloading, stakinf etc. complete with all lead and lift and fixing

    CI valves. the rate is inclusive of cost jointing materials

    Sluice Valve 200 mm dia

    Sluice Valve 100 mm dia No 1

    Scour Valve 80 mm dia No 3

    Conducting hydraulic/ water tightness test for container.

    Providing and casting RCC spiral stair case for the OHTincluding steel reinforcement etc..complete.

    No 1

    chain link Fencing for P-OHT's for a length of 80 Mtrs eachNo 1.00

    All the above works be carried out as per the drawings enclosed,

    as per the specifications and also as per the instructions of the

    Engineer-in-Charge.

    PAYMENT CONDITION FOR OHT (ELSR)Completion of earth work and foundation - 10%

    Completion of bottom slab - 15%

    Completion of side wall - 20%

    Completion of fencing & roof slab - 15%

    Finishing works - 10%

    Pipe connections and accessories - 15%

    Hydraulic Testing - 10%

    Commissioning and trial running - 5%

    1

    2 Unit rates and prices shall be quoted by the bidder in Indian rupee [ITB Clause 14.1].

    3 Where there is a discrepancy between the rate in figures and words, the rates in words will govern.[ITB Clause 27.1]

    4

    13 to 16 / 99 to 105

    Total Rstem or w c no rate or prce as een entere n w not e pa or y t e mp oyer w en execute an s a e eeme covere y t e ot er rates an pr ces n t e o uant ty r

    Clause 13.2 and GCC Clause 43.3).

    Where there is a discrepancy between the unit rate and the line item total resulting from multiplying the unit rate by quantity, the unit rate quoted shall govern [ITB Clause 27.1 (b)].

    Signature of Contractor

    No. of Correction(s) ( )

    No. of Overwriting(s)( )

  • 8/11/2019 Elsr Boq Exampl

    17/30

    Karnataka Rural Water Supply and Sanitation Agency RD and PR Department

    In Figures

    (Rs.)In W

    1 Constructing RCC Over Head Tank (ELSR) of 50,000 litres capacity

    over a staging of 10.50 Mtr, conforming to the design and drawing

    enclosed with the bid document including excavation in all types of

    strata providing and casting column-footing/ Raft, columns, braces,

    ring beams, bottom dome, conical portion, shell portion, top dome,

    landing with providing and fabricating required steel reinforcement

    as per design etc.. complete. All structural members and water

    retaining structures are to be in M-30 concrete. For shell portion CM

    plastering 1:3 proportion 20 mm thick with an admixture of water

    proof compound of requisite proportion and of approved quality to be

    provided for inside. Providing two coats of water proof cement

    painting of approved colour and shade over one coat of primer,

    includin rovidin and fixin all accessories as iven below:-

    RCC Hexagonal finial and ventilator. No 1.00

    M.S.Inspection door of size 60 cms x 60 cms with MS frame. No 1.00

    Enamelled gauge plate water level indicator. No 1.00

    Copper Lightening Arrestor No 1.00

    Providing and fixing 32 MM dia GI pipe 'A' class pipe railing in 2

    rows on top dome, flat slab and landings.Rmt 37.39

    Anodised Aluminium ladder No 4.00

    1

    2 Unit rates and prices shall be quoted by the bidder in Indian rupee [ITB Clause 14.1].

    3 Where there is a discrepancy between the rate in figures and words, the rates in words will govern.[ITB Clause 27.1]

    4

    Item for which no rate or price has been entered in will not be paid for by the Employer when executed and shall be deemed covered by the other rates and prices in the Bill of Quantity

    Clause 43.3).

    Where there is a discrepancy between the unit rate and the line item total resulting from multiplying the unit rate by quantity, the unit rate quoted shall govern [ITB Clause 27.1 (b)].

    BILL. NO. 5. CONSTRUCTION OF RCC OVER HEAD TANK (ELSR) 50,000 LITERS CAPACITY OVER A STAGING OF 10

    CHAIN LINK FENCING FOR KUNDRAHALLI TANDA VILLAGE. (Refer Drawing no -ADH/MVS/GADAG/PC

    QuantitySlNo

    13 to 14 / 99 to 103

    Unit

    Technical

    SpecificationsPara no/Page no/Item

    no

    RaDescription

    Signature of Contractor

    No. of Correction(s) ( )

    No. of Overwriting(s)( )

  • 8/11/2019 Elsr Boq Exampl

    18/30

    Karnataka Rural Water Supply and Sanitation Agency RD and PR Department

    In Figures

    Rs.

    QuantitySl

    No

    Unit

    Technical

    Specifications

    Para no/Page no/Item

    no

    Description

    Supplying valves of board approved make confirming to relevant ISS

    with latest amendments as detailed below of following diameters and

    types and conveying to work site, loading, unloading, stakinf etc.

    complete with all lead and lift and fixing CI valves. the rate is

    inclusive of cost jointing materials

    Sluice Valve 200 mm dia

    Sluice Valve 100 mm dia No 1.00

    Scour Valve 80 mm dia No 3.00

    Conducting hydraulic/ water tightness test for container.

    Providing and casting RCC spiral stair case for the OHT including

    steel reinforcement etc..complete.No 1.00

    chain link Fencing for P-OHT's for a length of 80 Mtrs each No 1.00

    All the above works be carried out as per the drawings enclosed, as

    per the specifications and also as per the instructions of the Engineer-

    in-Charge.

    PAYMENT CONDITION FOR OHT (ELSR)Completion of earth work and foundation - 10%

    Completion of bottom slab - 15%

    Completion of side wall - 20%

    Completion of fencing & roof slab - 15%

    Finishing works - 10%

    Pipe connections and accessories - 15%

    Hydraulic Testing - 10%

    Commissioning and trial running - 5%

    1

    2 Unit rates and prices shall be quoted by the bidder in Indian rupee [ITB Clause 14.1].

    3 Where there is a discrepancy between the rate in figures and words, the rates in words will govern.[ITB Clause 27.1]

    4 Where there is a discrepancy between the unit rate and the line item total resulting from multiplying the unit rate by quantity, the unit rate quoted shall govern [ITB Clause

    Item for which no rate or price has been entered in will not be paid for by the Employer when executed and shall be deemed covered by the other rates and prices in the Bill

    Clause 43.3).

    13 to 15 / 99 to 105

    Signature of Contractor

    No. of Correction(s) ( )

    No. of Overwriting(s)( )

  • 8/11/2019 Elsr Boq Exampl

    19/30

    Karnataka Rural Water Supply and Sanitation Agency RD and PR Department

    In Figures

    (Rs.)In Words A

    1 Constructing RCC Over Head Tank (ELSR) of 50,000 litres

    capacity over a staging of 12.00 Mtr, conforming to the design and

    drawing enclosed with the bid document including excavation in

    all types of strata providing and casting column-footing/ Raft,

    columns, braces, ring beams, bottom dome, conical portion, shell

    portion, top dome, landing with providing and fabricating

    required steel reinforcement as per design etc.. complete. All

    structural members and water retaining structures are to be in M-

    30 concrete. For shell portion CM plastering 1:3 proportion 20 mm

    thick with an admixture of water proof compound of requisite

    proportion and of approved quality to be provided for inside.

    Providing two coats of water proof cement painting of approved

    colour and shade over one coat of primer, including providing

    and fixing all accessories as given below:-

    RCC Hexagonal finial and ventilator. No 1.00

    M.S.Ins ection door of size 60 cms x 60 cms with MS frame. No 1Enamelled gauge plate water level indicator. No 1

    Copper Lightening Arrestor No 1Providing and fixing 32 MM dia GI pipe 'A' class pipe railing in 2

    rows on top dome, flat slab and landings.Rmt 37.39

    Anodised Aluminium ladder

    1

    2 Unit rates and prices shall be quoted by the bidder in Indian rupee [ITB Clause 14.1].

    3 Where there is a discrepancy between the rate in figures and words, the rates in words will govern.[ITB Clause 27.1]

    4

    Item for which no rate or price has been entered in will not be paid for by the Employer when executed and shall be deemed covered by the other rates and prices in the Bill of Quantity (re

    Clause 13.2 and GCC Clause 43.3).

    Where there is a discrepancy between the unit rate and the line item total resulting from multiplying the unit rate by quantity, the unit rate quoted shall govern [ITB Clause 27.1 (b)].

    BILL. NO. 6. CONSTRUCTION OF RCC OVER HEAD TANK (ELSR) 50,000 LITERS CAPACITY OVER A STAGING OF 12.0

    INCLUDING CHAIN LINK FENCING FOR adrakatti VILLAGE. (Refer Drawing no -ADH/MVS/GADAG/PCC-OHT-05

    Quantity

    Rate in Rs

    13 to 14 / 99 to

    103

    Sl

    NoDescription

    Technical

    Specifications

    Para no/Page

    no/Item no

    Unit

    Signature of Contractor

    No. of Correction(s) ( )

    No. of Overwriting(s)( )

  • 8/11/2019 Elsr Boq Exampl

    20/30

    Karnataka Rural Water Supply and Sanitation Agency RD and PR Department

    Supplying valves of board approved make confirming to relevant

    ISS with latest amendments as detailed below of following

    diameters and types and conveying to work site, loading,

    unloading, stakinf etc. complete with all lead and lift and fixing CI

    valves. the rate is inclusive of cost jointing materials

    Sluice Valve 200 mm dia No 1.00

    Scour Valve 80 mm dia No 3.00

    Conducting hydraulic/ water tightness test for container.

    Providing and casting RCC spiral stair case for the OHT including

    steel reinforcement etc..complete.No 1.00

    chain link Fencing for P-OHT's for a length of 80 Mtrs eachNo 1.00

    All the above works be carried out as per the drawings enclosed,

    as per the specifications and also as per the instructions of the

    Engineer-in-Charge.

    PAYMENT CONDITION FOR OHT (ELSR)Completion of earth work and foundation - 10%

    Completion of bottom slab - 15%

    Completion of side wall - 20%

    Completion of fencing & roof slab - 15%

    Finishing works - 10%

    Pipe connections and accessories - 15%

    Hydraulic Testing - 10%

    Commissioning and trial running - 5% TOTAL

    1

    2 Unit rates and prices shall be quoted by the bidder in Indian rupee [ITB Clause 14.1].3 Where there is a discrepancy between the rate in figures and words, the rates in words will govern.[ITB Clause 27.1]

    4

    Item for which no rate or price has been entered in will not be paid for by the Employer when executed and shall be deemed covered by the other rates and prices in the Bill

    Clause 13.2 and GCC Clause 43.3).

    Where there is a discrepancy between the unit rate and the line item total resulting from multiplying the unit rate by quantity, the unit rate quoted shall govern [ITB Clause 2

    13 to 16 / 99 to

    105

    Signature of Contractor

    No. of Correction(s) ( )

    No. of Overwriting(s)( )

  • 8/11/2019 Elsr Boq Exampl

    21/30

    Karnataka Rural Water Supply and Sanitation Agency RD and PR Department

    In Figures

    (Rs.)In W

    1 Constructing RCC Over Head Tank (ELSR) of 50,000 litres

    capacity over a staging of 12.00 Mtr, conforming to the design and

    drawing enclosed with the bid document including excavation in

    all types of strata providing and casting column-footing/ Raft,

    columns, braces, ring beams, bottom dome, conical portion, shell

    portion, top dome, landing with providing and fabricating

    required steel reinforcement as per design etc.. complete. All

    structural members and water retaining structures are to be in M-

    30 concrete. For shell portion CM plastering 1:3 proportion 20 mm

    thick with an admixture of water proof compound of requisite

    proportion and of approved quality to be provided for inside.

    Providing two coats of water proof cement painting of approved

    colour and shade over one coat of primer, including providing

    and fixing all accessories as given below:-

    RCC Hexagonal finial and ventilator. No 1.00

    M.S.Inspection door of size 60 cms x 60 cms with MS frame.No 1.00

    Enamelled gauge plate water level indicator. No 1.00

    Copper Lightening Arrestor No 1.00Providin and fixin 32 MM dia GI i e 'A' class i e railin in 2 RMTR 37.39

    Anodised Aluminium ladder

    1

    2 Unit rates and prices shall be quoted by the bidder in Indian rupee [ITB Clause 14.1].

    3 Where there is a discrepancy between the rate in figures and words, the rates in words will govern.[ITB Clause 27.1]

    4

    Item for which no rate or price has been entered in will not be paid for by the Employer when executed and shall be deemed covered by the other rates and prices in the Bill of Quantity (

    43.3).

    Where there is a discrepancy between the unit rate and the line item total resulting from multiplying the unit rate by quantity, the unit rate quoted shall govern [ITB Clause 27.1 (b)].

    BILL. NO. 7. CONSTRUCTION OF RCC OVER HEAD TANK (ELSR) 50,000 LITERS CAPACITY OVER A STAGING OF 12.00

    LINK FENCING FOR HARADAGATTI VILLAGE. (Refer Drawing no -ADH/MVS/GADAG/PCC-OHT-

    Quantity

    Rate

    13 to 14 / 99 to

    103

    Sl No Description

    TechnicalSpecifications

    Para no/Page

    no/Item no

    Unit

    ignature of Contractor

    No. of Correction(s) ( )

    No. of Overwriting(s)( )

  • 8/11/2019 Elsr Boq Exampl

    22/30

    Karnataka Rural Water Supply and Sanitation Agency RD and PR Department

    In Figures(Rs.)

    Quantity

    Sl No Description

    Technical

    Specifications

    Para no/Page

    no/Item no

    Unit

    Supplying valves of board approved make confirming to relevant

    ISS with latest amendments as detailed below of following

    diameters and types and conveying to work site, loading,

    unloading, stakinf etc. complete with all lead and lift and fixing CI

    valves. the rate is inclusive of cost jointing materials

    Sluice Valve 200 mm dia No 1.00

    Scour Valve 80 mm dia No 3.00

    Conducting hydraulic/ water tightness test for container.

    Providing and casting RCC spiral stair case for the OHT including

    steel reinforcement etc..complete. No 1.00

    chain link Fencing for P-OHT's for a length of 80 Mtrs each No 1.00

    All the above works be carried out as per the drawings enclosed,

    as per the specifications and also as per the instructions of the

    Engineer-in-Charge.

    PAYMENT CONDITION FOR OHT (ELSR)Completion of earth work and foundation - 10%

    Completion of bottom slab - 15%

    Completion of side wall - 20%

    Completion of fencing & roof slab - 15%

    Finishing works - 10%

    Pipe connections and accessories - 15%

    Hydraulic Testing - 10%Commissioning and trial running - 5%

    TOTAL

    1

    2 Unit rates and prices shall be quoted by the bidder in Indian rupee [ITB Clause 14.1].

    3 Where there is a discrepancy between the rate in figures and words, the rates in words will govern.[ITB Clause 27.1]

    4

    Item for which no rate or price has been entered in will not be paid for by the Employer when executed and shall be deemed covered by the other rates and prices in the Bill

    43.3).

    Where there is a discrepancy between the unit rate and the line item total resulting from multiplying the unit rate by quantity, the unit rate quoted shall govern [ITB Clause 27

    13 to 16 / 99 to

    105

    Signature of Contractor

    No. of Correction(s) ( )

    No. of Overwriting(s)( )

  • 8/11/2019 Elsr Boq Exampl

    23/30

    Karnataka Rural Water Supply and Sanitation Agency RD and PR Department

    In

    Figures

    (Rs.)

    Materials

    civil works

    1 Earth Work Exacavation for foundation and removing the excavated stuff to adistance not exceeding 50mtrs and with a lift upto 1.50 mtrs. including shoring,

    strutting, barricading, danger lighting etc., complete by Mechanical means.

    Complete in all respect as directed by engineers in charge

    a) in Ordinary soil cum 35.10

    b) in Hard soil cum 35.10c) in Ordinary rock Without blasting cum 35.10

    d) in Hard Rock with blasting cum 12.09

    2 Providing and laying granite or trap jelly M-10 cement concrete using 40 mmand down size jelly for foundation laid in 15 cms thick layers and well

    compacted including machine mixing, curing as per specification etc., complete

    for foundation. With all respect as dirtected by engineer incharge

    3 to 3.13.2

    77 to 80cum 7.80

    3 Providing& laying C.C 1 M-15 grade using granite or basalt or trap jelly 20 mmand down size including mixing laying, tamping, curing plastering for exposed

    faces with cement mortar 1:3 by mixing 1 kg of water proof compound for

    every one bag of cement for top plaster finish and with necessary centering and

    form work etc. complete for flooring of GLSR. cills, coping, bond slab and for

    any other such workcom,plete with all respect as directgd by engineers

    incharge

    5.3 / 83 cum 70.20

    4 Labour charges for fabricating M.S. bars/ TMT for steel bars of all sizesincluding cleaning, straightening, cutting, bending, hooking, lapping and or

    welding, wherever required, placing in position and tieing with binding wire of

    approved quality and guage as per design including cost of binding wire,

    hoisting etc., complete with all respect as directed by engineers incharge

    9.1.3 to 9.1.5 / 88 cum 1971.45

    1

    2 Unit rates and prices shall be quoted by the bidder in Indian rupee [ITB Clause 14.1].

    3 Where there is a discrepancy between the rate in figures and words, the rates in words will govern.[ITB Clause 27.1]

    4

    Item for which no rate or price has been entered in will not be paid for by the Employer when executed and shall be deemed covered by the other rates and p

    ITB Clause 13.2 and GCC Clause 43.3).

    Where there is a discrepancy between the unit rate and the line item total resulting from multiplying the unit rate by quantity, the unit rate quoted shall gover

    2 to 2.11 / 70 to 76

    BILL. NO. 8. CONSTRUCTION OF THRUST BLOCK OF SIZE (1.2 x 1.2 x 1.2 m )-39Nos . (Refer Drg. No. ADH/M

    13 )

    Sl No Description

    Technical

    Specifications

    Para no/Page

    no/Item no

    Unit Quantity

    Signature of Contractor

    No. of Correction(s) ( )

    No. of Overwriting(s)( )

  • 8/11/2019 Elsr Boq Exampl

    24/30

    Karnataka Rural Water Supply and Sanitation Agency RD and PR Department

    In Fig

    (R

    Materials

    civil works

    1 Earth Work Exacavation for foundation and removing the

    excavated stuff to a distance not exceeding 50mtrs and with a lift

    upto 1.50 mtrs. including shoring, strutting, barricading, danger

    lighting etc., complete by Mechanical means. Complete in all

    respect as directed by engineers in charge

    a) in Ordinary soil cum 120.24b) in Hard soil cum 120.24

    c) in Ordinary rock Without blasting cum 120.24

    d) in Hard Rock with blasting cum 36.74

    2 Providing and laying granite or trap jelly M-10 cement concrete

    using 40 mm and down sizejelly for foundation laid in 15 cms

    thick layers and well compacted including machine mixing,

    curing as per specification etc., complete for foundation. With all

    respect as dirtected by engineer incharge

    3 to 3.13.2

    77 to 80cum 30.06

    3 Providing& laying C.C 1 M-15 grade using granite or basalt or

    trap jelly 20 mm and down size including mixing laying,

    tamping, curing plastering for exposed faces with cement mortar

    1:3 by mixing 1 kg of water proof compound for every one bag ofcement for top plaster finish and with necessary centering and

    form work etc. complete for flooring of GLSR. cills, coping,

    bond slab and for any other such workcom,plete with all

    respect as directgd by engineers incharge

    5.3 / 83 cum 173.68

    4 Labour charges for fabricating M.S. bars/ TMT for steel bars of

    all sizes including cleaning, straightening, cutting, bending,

    hooking, lapping and or welding, wherever required, placing in

    position and tieing with binding wire of approved quality and

    guage as per design including cost of binding wire, hoisting etc.,

    complete with all respect as directed by engineers incharge

    9.1.3 to 9.1.5 / 88 cum 13026.00

    1

    2 Unit rates and prices shall be quoted by the bidder in Indian rupee [ITB Clause 14.1].

    3 Where there is a discrepancy between the rate in figures and words, the rates in words will govern.[ITB Clause 27.1]

    4

    Item for which no rate or price has been entered in will not be paid for by the Employer when executed and shall be deemed covered by the other rates and

    13.2 and GCC Clause 43.3).

    Where there is a discrepancy between the unit rate and the line item total resulting from multiplying the unit rate by quantity, the unit rate quoted shall gov

    2 to 2.11 / 70 to 76

    BILL. NO. 9. CONSTRUCTION OF THRUST BLOCK OF SIZE (0.8 x 0.8 x 0.8 m )-334 Nos . (Refer Drg. No.

    13 )

    Sl No Description

    TechnicalSpecifications

    Para no/Page

    no/Item no

    Unit Quantity

    Rate in

    Signature of Contractor

    No. of Correction(s) ( )

    No. of Overwriting(s)( )

  • 8/11/2019 Elsr Boq Exampl

    25/30

    arnataka Rural Water Supply and Sanitation Agency RD and PR Department Addi

    In Figures(Rs.)

    In Words Amount (Rs)

    1 2 3 4 5 6 7 8

    1 Earth Work Exacavation for foundation and removing the excavated

    stuff to a distance not exceeding 50mtrs and with a lift upto 1.50 mtrs.

    including shoring, strutting, barricading, danger lighting etc.,

    complete by Mechanical means. Complete in all respect as directed

    by engineers incharge

    in ordinary soil Cum 150.88

    in hard soil Cum 113.16

    in Ordinary rock Without blasting Cum 113.16

    2 Providing and laying granite or trap jelly M-10 cement concrete using

    40 mm and down sizejelly for foundation laid in 15 cms thick layers

    and well compacted including machine mixing, curing as per

    specification etc., complete for foundation.with all respect as directed

    by Engineers incharge

    3 to 3.13.277 to 80

    Cum 28.98

    3 Providing and constructing granite or trap or basalt or sand stone,

    Coursed Rubble Second Sort Size Masonry with CM 1:6 proportion,

    courses not less than 20 cms high with bond stones at 2M apart in

    each course, edges of stone chisel dressed and all corners 2 line

    dressed 5 cms wide on each face, including scaffolding, curing etc.,

    complete as per specifications.as directed by engineers incharge

    5.3 / 83 Cum 201.02

    1

    2 Unit rates and prices shall be quoted by the bidder in Indian rupee [ITB Clause 14.1].

    3 Where there is a discrepancy between the rate in figures and words, the rates in words will govern.[ITB Clause 27.1]

    4

    em or w c no ra e or pr ce as een en ere n w no e pa or y e mp oyer w en execu e an s a e eeme covere y e o er ra es an

    prices in the Bill of Quantity (refer: ITB Clause 13.2 and GCC Clause 43.3).

    Where there is a discrepancy between the unit rate and the line item total resulting from multiplying the unit rate by quantity, the unit rate quoted shall

    govern [ITB Clause 27.1 (b)].

    2 to 2.11 / 70

    to 76

    BILL No.10:-CONSTRUCTION OF sluice valve chamber 1 No's (Refer Drawing no - ADH/MVS/GADAG/HW/PCC-12 )

    Sl.No Description

    Technical

    Specificatio

    nsPara

    no/Page

    Unit Quantity

    Rate in RS

    gnature of Contractor

    No. of Correction(s) ( )

    No. of Overwriting(s)( )

  • 8/11/2019 Elsr Boq Exampl

    26/30

    arnataka Rural Water Supply and Sanitation Agency RD and PR Department Addi

    4 Providing pointing to stone masonry walls in C.M. 1:3 proportion

    after raking the joints to a depth of 25 mm and nicely lining including

    scaffolding, curing, etc., complete as per specifications.

    As directed by engineers incharge

    9.1.3 to 9.1.5

    / 88Cum 308.20

    5 Providing and laying cement concrete (M-10) proportion using

    granite or trap or basalt jelly 20 mm and down size including

    watering mixing, laying, tamping, curing and plastering to exposed

    faces with cement mortar 1.3 proportion and with necessary

    centering, form work etc.,complete as per specifications

    As directed by engineers in charge

    3 to 3.13.2

    77 to 80Cum 6.90

    6 Providing& laying C.C (M15) grade using granite or basalt or trap

    jelly 20 mm and down size including mixing laying, tamping, curing

    plastering for exposed faces with cement mortar 1:3 by mixing 1 kg of

    water proof compound for every one bag of cement for top plaster

    finish and with necessary centering and form work etc. complete for

    flooring of GLSR. cills, coping, bond slab and for any other such work

    3 to 3.13.2

    77 to 80Cum 9.20

    7 Providing and laying M-25 Cement concrete proportion using clean

    graded granite or trap or basalt jelly 20 mm and down size for RCC

    Roof Slab, canopies of all spans with steel or plywood or plank

    centering and shuttering, including machine mixing, lifting, laying,

    vibrating, tamping, including smooth finishing, curing for all exposed

    faces complete in all respect as directed by engineer incharge

    3 to 3.13.2

    77 to 80Cum 18.40

    8 Labour charges for fabricating M.S. bars/ TMT for steel bars of all

    sizes including cleaning, straightening, cutting, bending, hooking,

    lapping and or welding, wherever required, placing in position and

    tieing with binding wire of approved quality and guage as per design

    including cost of binding wire, hoisting etc., complete including

    conveying steel rods. (Including providing steel bars)

    3 to 3.13.2

    77 to 80Kg 2233.30

    TOTAL

    1

    2 Unit rates and prices shall be quoted by the bidder in Indian rupee [ITB Clause 14.1].

    3 Where there is a discrepancy between the rate in figures and words, the rates in words will govern.[ITB Clause 27.1]

    4

    Item for which no rate or price has been entered in will not be paid for by the Employer when executed and shall be deemed covered by the other rates and

    prices in the Bill of Quantity (refer: ITB Clause 13.2 and GCC Clause 43.3).

    Where there is a discrepancy between the unit rate and the line item total resulting from multiplying the unit rate by quantity, the unit rate quoted shall

    govern [ITB Clause 27.1 (b)].

    gnature of Contractor

    No. of Correction(s) ( )

    No. of Overwriting(s)( )

  • 8/11/2019 Elsr Boq Exampl

    27/30

    Karnataka Rural Water Supply and Sanitation Agency RD and PR Department

    In Figures(Rs.)

    In Words Amo(Rs

    1 2 3 4 5 6 7 8

    1 Earth Work Exacavation for foundation and removing the excavated

    stuff to a distance not exceeding 50mtrs and with a lift upto 1.50 mtrs.

    including shoring, strutting, barricading, danger lighting etc.,

    complete by Mechanical means.

    in ordinary soil Cum 134.48

    in hard soil Cum 100.86

    in Ordinary rock Without blasting Cum 100.86

    2 Providing and laying granite or trap jelly M-10 cement concrete using

    40 mm and down sizejelly for foundation laid in 15 cms thick layers

    and well compacted including machine mixing, curing as per

    specification etc., complete for foundation.

    Concreting in Foundation Bed C.C 1:4:8

    3 to 3.13.2

    77 to 80Cum 25.83

    3 Providing and constructing granite or trap or basalt or sand stone,

    Coursed Rubble Second Sort Size Masonry with CM 1:6 proportion,

    courses not less than 20 cms high with bond stones at 2M apart in each

    course, edges of stone chisel dressed and all corners 2 line dressed 5

    cms wide on each face, including scaffolding, curing etc., complete as

    per specifications.

    For basement

    5.3 / 83 Cum 179.17

    4 Providing pointing to stone masonry walls in C.M. 1:3 proportion

    after raking the joints to a depth of 25 mm and nicely lining including

    scaffolding, curing, etc., complete as per specifications.

    9.1.3 to 9.1.5

    / 88Cum 274.70

    1

    2 Unit rates and prices shall be quoted by the bidder in Indian rupee [ITB Clause 14.1].

    3 Where there is a discrepancy between the rate in figures and words, the rates in words will govern.[ITB Clause 27.1]

    4

    Item for which no rate or price has been entered in will not be paid for by the Employer when executed and shall be deemed covered by the other rates an

    prices in the Bill of Quantity (refer: ITB Clause 13.2 and GCC Clause 43.3).

    Where there is a discrepancy between the unit rate and the line item total resulting from multiplying the unit rate by quantity, the unit rate quoted shall go

    [ITB Clause 27.1 (b)].

    2 to 2.11 / 70

    to 76

    BILL No.11:-CONSTRUCTION OF AIR valve chamber 10 No's (Refer Drawing no - ADH/MVS/GADAG/AW-06

    Sl.No Description

    Technical

    Specificatio

    nsPara no/Page

    no/Item no

    Unit Quantity

    Rate in RS

    Signature of Contractor

    No. of Correction(s) ( )

    No. of Overwriting(s)( )

  • 8/11/2019 Elsr Boq Exampl

    28/30

    Karnataka Rural Water Supply and Sanitation Agency RD and PR Department

    In Figures

    (Rs.)In Words

    Am

    (

    1 2 3 4 5 6 7

    Sl.No Description

    Technical

    Specificatio

    ns

    Para no/Page

    no/Item no

    Unit Quantity

    Rate in RS

    5 Providing and laying cement concrete 1:3:6 (M-10) proportion using

    granite or trap or basalt jelly 20 mm and down size including watering

    mixing, laying, tamping, curing and plastering to exposed faces with

    cement mortar 1.3 proportion and with necessary centering, form work

    etc.,complete as per specifications

    For cills, coping, Bond slab

    3 to 3.13.2

    77 to 80Cum 6.15

    6 Providing& laying C.C m15 proportion using granite or basalt or trap

    jelly 20 mm and down size including mixing laying, tamping, curing

    plastering for exposed faces with cement mortar 1:3 by mixing 1 kg of

    water proof compound for every one bag of cement for top plaster

    finish and with necessary centering and form work etc. complete forflooring of GLSR. cills, coping, bond slab and for any other such work

    For coping

    3 to 3.13.2

    77 to 80Cum 8.20

    7 Providing and laying M-25 Cement concrete proportion using clean

    graded granite or trap or basalt jelly 20 mm and down size for RCC

    Roof Slab, canopies of all spans with steel or plywood or plank

    centering and shuttering, including machine mixing, lifting, laying,

    vibrating, tamping, including smooth finishing, curing for all exposed

    faces (exclusive of cost of steel and fabrication charges)

    3 to 3.13.2

    77 to 80Cum 25.01

    8 Labour charges for fabricating M.S. bars/ TMT for steel bars of all

    sizes including cleaning, straightening, cutting, bending, hooking,

    lapping and or welding, wherever required, placing in position and

    tieing with binding wire of approved quality and guage as per designincluding cost of binding wire, hoisting etc. , complete including

    conveying steel rods. (Including providing steel bars)

    3 to 3.13.2

    77 to 80

    Kg 1980.30

    1

    2 Unit rates and prices shall be quoted by the bidder in Indian rupee [ITB Clause 14.1].

    3 Where there is a discrepancy between the rate in figures and words, the rates in words will govern.[ITB Clause 27.1]

    4

    Item for which no rate or price has been entered in will not be paid for by the Employer when executed and shall be deemed covered by the other rates

    prices in the Bill of Quantity (refer: ITB Clause 13.2 and GCC Clause 43.3).

    Where there is a discrepancy between the unit rate and the line item total resulting from multiplying the unit rate by quantity, the unit rate quoted shall

    [ITB Clause 27.1 (b)].

    Signature of Contractor

    No. of Correction(s) ( )

    No. of Overwriting(s)( )

  • 8/11/2019 Elsr Boq Exampl

    29/30

    Karnataka Rural Water Supply and Sanitation Agency RD and PR Department

    1 2 3 4

    1 Earth Work Exacavation for foundation and removing the

    excavated stuff to a distance not exceeding 50mtrs and with a lift

    upto 1.50 mtrs. including shoring, strutting, barricading, danger

    lighting etc., complete by Mechanical means. Complete in all

    respect as directed by engineers incharge

    in ordinary soil Cum

    in hard soil Cum

    in Ordinary rock Without blasting Cum

    2 Providing and laying granite or trap jelly M-10 cement concrete

    using 40 mm and down sizejelly for foundation laid in 15 cms

    thick layers and well compacted including machine mixing,

    curing as per specification etc., complete for foundation.with all

    respect as directed by ingineers incharge

    3 to 3.13.2

    77 to 80Cum

    3 Providing and constructing granite or trap or basalt or sand stone,

    Coursed Rubble Second Sort Size Masonry with CM 1:6

    proportion, courses not less than 20 cms high with bond stones at

    2M apart in each course, edges of stone chisel dressed and al l

    corners 2 line dressed 5 cms wide on each face, including

    scaffolding, curing etc., complete as per specifications.as directedby engineers incharge

    5.3 / 83 Cum

    4 Providing pointing to stone masonry walls in C.M. 1:3 proportion

    after raking the joints to a depth of 25 mm and nicely lining

    including scaffolding, curing, etc., complete as per specifications.

    As directed by engineers incharge

    9.1.3 to 9.1.5 /

    88Cum

    5 Providing and laying cement concrete (M-10) proportion using

    granite or trap or basalt jelly 20 mm and down size including

    watering mixing, laying, tamping, curing and plastering to

    exposed faces with cement mortar 1.3 proportion and with

    necessary centering, form work etc.,complete as per specifications

    As directed by engineers in charge

    3 to 3.13.2

    77 to 80Cum

    6 Providing& laying C.C (M15) grade using granite or basalt or trapjelly 20 mm and down size including mixing laying, tamping,

    curing plastering for exposed faces with cement mortar 1:3 by

    mixing 1 kg ofwater proof compound for every one bag of cement

    for top plaster finish and with necessary centering and form work

    etc. complete for flooring of GLSR. cills, coping, bond slab and for

    any other such work

    3 to 3.13.2

    77 to 80Cum

    1

    2 Unit rates and prices shall be quoted by the bidder in Indian rupee [ITB Clause 14.1].

    3 Where there is a discrepancy between the rate in figures and words, the rates in words will govern.[ITB Claus

    4

    tem or w c no rate or pr ce as een entere n w not e pa or y t e mp oyer w en execute an s a

    Bill of Quantity (refer: ITB Clause 13.2 and GCC Clause 43.3).

    Where there is a discrepancy between the unit rate and the line item total resulting from multiplying the unit ra

    Clause 27.1 (b)].

    2 to 2.11 / 70 to

    76

    BILL No.12:-CONSTRUCTION OF scour valve chamber 20 No's (Refer Drawing no -

    Sl.No Description

    Technical

    Specifications

    Para no/Page

    no/Item no

    Unit Q

    Signature of Contractor

    No. of Correction(s) ( )

    No. of Overwriting(s)( )

  • 8/11/2019 Elsr Boq Exampl

    30/30

    Karnataka Rural Water Supply and Sanitation Agency RD and PR Department

    1 2 3 4

    Sl.No Description

    Technical

    SpecificationsPara no/Page

    no/Item no

    Unit Q

    7 Providing and laying M-25 Cement concrete proportion using

    clean graded granite or trap or basalt jelly 20 mm and down size

    for RCC Roof Slab, canopies of all spans with steel or plywood or

    plank centering and shuttering, including machine mixing, lifting,

    laying, vibrating, tamping, including smooth finishing, curing for

    all exposed faces complete in all respect as directed by engineer

    incharge

    3 to 3.13.2

    77 to 80Cum

    8 Labour charges for fabricating M.S. bars/ TMT for steel bars of

    all sizes including cleaning, straightening, cutting, bending,

    hooking, lapping and or welding, wherever required, placing in

    position and tieing with binding wire of approved quality and

    guage as per design including cost of binding wire, hoisting etc.,

    complete including conveying steel rods. (Including providing

    steel bars)

    3 to 3.13.2

    77 to 80Kg 5

    9 Supplying laying, jointing testing and commissioning of GI pipes

    conforming to IS 1239 : 1990 with latest amendments including

    fixing collars, elbows, tees, bends, gland cocks and other fittings

    (excluding cost of specials) with cuts and threads wherever

    necessary including conveying the materials to work spot

    including testing for water tightness, with all lead. (constructor

    will make his own arrangements for procuring water for testing).

    80mm dia pipe (Medium duty) 1m on either side of CI valves

    10 to 10.5 / 93 to

    97Rmt

    1

    2 Unit rates and prices shall be quoted by the bidder in Indian rupee [ITB Clause 14.1].

    3 Where there is a discrepancy between the rate in figures and words, the rates in words will govern.[ITB Clause

    4

    Item for which no rate or price has been entered in will not be paid for by the Employer when executed and sha

    Bill of Quantity (refer: ITB Clause 13.2 and GCC Clause 43.3).

    Where there is a discrepancy between the unit rate and the line item total resulting from multiplying the unit ra

    Clause 27.1 (b)].