EMA tracking tool: relocation to AmsterdamMain milestones
Nov Feb Feb FebNov NovAug AugMay May MayJan Jan JanOct OctJul JulApr Apr AprDec Mar Mar MarDec DecSep SepJun Jun Jun
2018 2019 2020
15.11 Permanent buildingfully operational
01.01 SPARK building fully operational 09.08
New work stream established
31.12 Staff relocation to permanent building finalised
30.03 Staff relocation to temporary building finalised
01.07 Seat agreementsigned by EMA and NL
26.01Final decision ontemporary building
20.11.2017EU27 decision on Amsterdam as new EMA seat
22.02 Approval of permanent building by Budgetary Authorityas initially expected
15.01Joint governance structure implemented
PermanentBuilding
TemporaryBuilding
EMA Staff
Financial,governance,legal
Removal and logistics
Please click on the icons to be directed to the related work streams.EMA stands for European Medicines Agency and NL stands for the Netherlands.The status bar shows the current status of the work stream, including its history and, where relevant, previous changes in status.
progress on trackprogress delayed but overall still on trackprogress at risk
*last updated on 24 January 2019
completedongoingdeadline missednot started
EMA+NLin charge
Legend:
EMA in charge
NL in charge
EUin charge
*last updated on 24 January 2019
progress on trackprogress delayed but overall still on trackprogress at risk
EMA tracking tool: relocation to AmsterdamPermanent building
Feb Feb FebNov NovAug AugMay May May2018 2019 2020Jan Jan JanOct OctJul JulApr Apr AprDec Mar Mar MarDec DecSep SepJun Jun Jun
15.11 Permanent building fully operational
22.02 Approval of permanent building by Budgetary Authority as initially expected
completedongoingdeadline missednot started
EMA+NLin charge
Legend:
EMA in charge
NL in charge
EUin charge
*last updated on 24 January 2019
progress on trackprogress delayed but overall still on trackprogress at risk
EMA tracking tool: relocation to AmsterdamTemporary building
Feb Feb FebNov NovAug AugMay May May2018 2019 2020Jan Jan JanOct OctJul JulApr Apr AprDec Mar Mar MarDec DecSep SepJun Jun Jun
26.01Final decision ontemporary building
01.01 SPARK building fully operational
completedongoingdeadline missednot started
EMA+NLin charge
Legend:
EMA in charge
NL in charge
EUin charge
*last updated on 24 January 2019
progress on trackprogress delayed but overall still on trackprogress at risk
EMA tracking tool: relocation to AmsterdamEMA Staff
Feb Feb FebNov NovAug AugMay May May2018 2019 2020Jan Jan JanOct OctJul JulApr Apr AprDec Mar Mar MarDec DecSep SepJun Jun Jun
30.03 Staff relocation to temporary buildingfinalised
31.12 Staff relocation to permanent buildingfinalised
completedongoingdeadline missednot started
EMA+NLin charge
Legend:
EMA in charge
NL in charge
EUin charge
progress on trackprogress delayed but overall still on trackprogress at risk
*last updated on 24 January 2019
Feb Feb FebNov NovAug AugMay May May2018 2019 2020Jan Jan JanOct OctJul JulApr Apr AprDec Mar Mar MarDec DecSep SepJun Jun Jun
01.07Seat agreementsigned
15.01Joint governance structure implemented
EMA tracking tool: relocation to AmsterdamFinancial, governance, legal
completedongoingdeadline missednot started
EMA+NLin charge
Legend:
EMA in charge
NL in charge
EUin charge
Feb Feb FebNov NovAug AugMay May May2018 2019 2020Jan Jan JanOct OctJul JulApr Apr AprDec Mar Mar MarDec DecSep SepJun Jun Jun
EMA tracking tool: relocation to AmsterdamRemoval and logistics
*last updated on 24 January 2019
progress on trackprogress delayed but overall still on trackprogress at risk