    Spirit of Innovation 

    Location of the selected embankment work

    is in stopway, runway, and shoulder runway

    STA 0+090 to STA 2+410. The work also will

    back fill the location in runway that has

    been excavated in previous work. We do this

    because in new design the elevation of 

    proposed design is higher than the previousone.

    STA 2+410STA 0+090

    Note:

    Start of Work

    Finish of Work

    Direction of Work

    Work Area

    •   Stopway

    Length : 120 m

    Width : 60 m

    •   Runway

    Length : 2200

    Width : 45 m

    Width (turning pad) : 47.5 m

    •   Shoulder Runway

    Length : 2214.76 m

    Width : 7.5 m

    Total Area : 152125 m2

    MaterialEmbankment : Selected Sandy Gravel From

    Tono River

    Flowchart illustration

    CONTINUE TO NEXT LAYER

    SELECTED EMBANKMENT

    (LAYER1)

    START

    FINISH

    LAND CLEARING

    Yes

    Yes

    No

    No

    SUBGRADE COMPACTION

    COMPACTION (LAYER 1)

    LAND GRUBBING / STRIPPING

    SITE MANAGEMENT AND WORK AREA

  • 8/18/2019 Embankment Construktion Metod.pdf

    3/14

    Spirit of Innovation 

    Technical Specification

    •   Before Embankment Construction the surface of the ground shall be

    graded and compacted to achieve 90% of maximum dry density to a

    depth of 200 mm below resulting ground.

    •   The Fill is compacted to a minimum of 95% of maximum dry density.

    The area will be divided into 18 lanes. The width of each lane 2.5 meter. It refers to

    the spesification and also the equipment ability. For compaction,  we’ll  use two

    vibro rollers. One vibro start from the left side to centerline. And other start from

    centerline to the right side. If later on the equipments added for acceleration, the

    method will be adjusted in the field.

    The material will be spread 100 meters in advance of rolling. Number of passes is

    10 passes. It get from trial that has been done before.

    SEQUENCE 

    Note:

    Start of Work

    Finish of Work

    Direction of Work

    18 Lanes

    Equipment lanes and passes 

  • 8/18/2019 Embankment Construktion Metod.pdf

    4/14

    Spirit of Innovation 

    The area will be filled by Selected sandy gravel from tono river. Backfill will be

    divided into several layers (number of layers depend on the depth). Backfilling will

    be done under runway and shoulder pavement. Start from subgrade which has

    been compacted until reach the elevation bottom base course.

    The thickness of each layer 20 cm in compacted condition and maximum 25 cm in

    loose depth. The test will be done in each layer. If the requirements are met, then

    the work continue to the next layer.

    In the layer width will be made a longer span than the upper layer (see the picture

    above) to avoid the landslide and to tie the layer with embankment in stripway

    that will be done later on.

    SEQUENCE 

    Compacted Subgrade

    8% CBR

    Selected Sandy

    Gravel 35% CBR

    Bottom Base

    Layer @20 cm

    Total Layer 

  • 8/18/2019 Embankment Construktion Metod.pdf

    5/14

    Spirit of Innovation 

    1 Preparation

    The contractor prepare the equipments and access of the equipments to

    the site. Then the surveyor will measure and install the location of boundary

    markers clearing based on drawing.

    LAND CLEARING

    Clearing work

    Start

    Finish

    Preparation

    Transport material to

    disposal area

    Q

    No

    Yes

    Equipments

    •   Bulldozer : 1 unit

    •   Excavator : 1 unit

    •   Dump Truck : 4 unit

    Resources

    •   Operator : 2

    •   Driver : 4

    •   Surveyor : 1

    •   Asisstant Surveyor : 1

    •   Helper : 2

    •   Supervisor : 1

    •   Safety Officer : 1

    Productivity : 800m3/hour

    METHOD 

  • 8/18/2019 Embankment Construktion Metod.pdf

    6/14

    Spirit of Innovation 

    2 Land Clearing

    3 Transport to disposal area

    The material rubbish of cleaning result will be dumped to the disposal area

    that have been approved using dump truck and excavator to take material

    into dump truck.

    Excavator 

    Clearing the bushes and other material that are not needed anymore using

    bulldozer. The material will be stacked in some spots to ease the excavator loadthem to the dump truck.

    LAND CLEARING

    METHOD 

  • 8/18/2019 Embankment Construktion Metod.pdf

    7/14

    Spirit of Innovation 

    1 Preparation

    The contractor prepare the equipments and access of the equipments to

    the site. Then the surveyor will measure and install the location of boundary

    markers grubbing/ stripping based on drawing.

    LAND GRUBBING/STRIPPING

    Flowchart illustration

    Start

    Preparation

    Yes

    Q No

    Finish

    No

    Yes

    Removal Grubbing

    material and stripping

    top soil

    Transport to dump area

    Equipments

    •   Bulldozer : 1 unit

    •   Excavator : 1 unit

    •   Dump Truck : 4 unit

    Resources

    •   Operator : 2

    •   Driver : 4

    •   Surveyor : 1

    •   Asisstant Surveyor : 1

    •   Helper : 2

    •   Supervisor : 1

    •   Safety Officer : 1

    METHOD 

    Productivity : 400m2/hour

  • 8/18/2019 Embankment Construktion Metod.pdf

    8/14

    Spirit of Innovation 

    2) Removing existing bushes, undergrowth, etc and stripping top soil.

    Stumps exposed or buried logs, bushes, undergrowth, etc will be

    grubbed up by bulldozer. Then stripping the top soil to prevent

    contamination and subsequent mixing of the the selected embankment

    materials with organic soils.

    .

    3 Transport to disposal area

    The material rubbish of cleaning result will be dumped to the disposal

    area that have been approved using dump truck and excavator to take

    material into dump truck.Excavator 

    LAND GRUBBING/STRIPPING

    METHOD 

  • 8/18/2019 Embankment Construktion Metod.pdf

    9/14

    Spirit of Innovation 

    METHOD 

    Start

    Preparation

    Yes

    Finish

    Spreading

    Compacting

    Q

    No

    Yes

    Flowchart illustration

    SUBGRADE COMPACTION

    Equipments

    •   Motor Grader : 1 unit

    •   Vibro Roller : 1 unit

    •   Water tank : 2 unit

    1 Preparation

    The contractor prepare the equipment and access of the equipment to the

    work site. Then the surveyor put up stakes and elevation plans of the

    subgrade.

    Resources

    •   Operator : 2

    •   Driver : 2

    •   Surveyor : 1

    •   Asisstant Surveyor : 1

    •   Helper : 2

    •   Supervisor : 1

    •   Safety Officer : 1

    Productivity : 300m2/hour

  • 8/18/2019 Embankment Construktion Metod.pdf

    10/14

    Spirit of Innovation 

    Final compaction by vibro roller and also by spraying water to the

    compaction area surface. After that, the subgrade density field tested and

    witnessed by consultant.

    3) Compacting

    To obtain the elevation plan subgrade surface using a motor grader. The

    Ground is spreaded and levelled by motorgrader. Then doing initial

    compaction using vibro roller followed by watering to the surface using

    water tank until reach the optimum water content.

    2) Spreading

    METHOD 

    SUBGRADE COMPACTION

  • 8/18/2019 Embankment Construktion Metod.pdf

    11/14

    Spirit of Innovation 

    1) Back Filling

    The material is selected Sandy Gravel from tono river. The dump truck bring

    the material from stock pile and place it to the location.

    SELECTED EMBANKMENT

    Start

    Preparation

    Backfilling

    Finish

    Spreading

    Compacting

    Q

    No

    Yes

    Equipments

    •   Motor Grader : 1 unit

    •  Vibro Roller : 2 unit

    •   Dump Truck : 4 unit

    •   Water Tank : 2 unit

    METHOD 

    Resources

    •   Operator : 3

    •   Driver : 6

    •   Surveyor : 1

    •   Asisstant Surveyor : 1

    •   Helper : 2

    •   Supervisor : 1

    •   Safety Officer : 1

    Productivity : 100m2/hour

  • 8/18/2019 Embankment Construktion Metod.pdf

    12/14

    Spirit of Innovation 

    2) Spreading

    3) Compacting

    To obtain the elevation plan of selected embankment using a motorgrader. The material will be spreaded and levelled by motor grader until

    we get the thickness plan of layer in loose soil. As mentioned in

    spesification, The materials shall be laid in layers not greater than 250 mm

    loose depth. But it may be changed by considering of compaction trials

    result.

    Compacting the layer with vibro roller with a several passes (number of 

    passes depend on the trial test) then followed by watering with a water

    tank. After compaction work, the surveyor will check the thickness of layer.

    The layer density field tested and witnessed by consultant. If it takes the

    requirement, the work continue to back fill the next layer.

    SELECTED EMBANKMENT

    METHOD 

  • 8/18/2019 Embankment Construktion Metod.pdf

    13/14

    Spirit of Innovation 

    TRIAL TEST 

    Before embankment throughout the area, we do trial test for compaction

    work. The purpose of the trials is to optimise the method of working to

    achieve the compaction requirement. Material of selected sandy gravelfrom tono river shall be placed in a loose layer not greater than 250 mm

    in thickness.

    The area 45 m wide is divided into 4 zones. We name them as Zone A, B,

    C, and D. Each zone having a different number of passes.

    A

    B

    C

    D

    8 Passes

    10 Passes

    12 Passes

    14 Passes

    Requirement

    •   Field CBR : minimum 35%

    •   Laboratory CBR : minimum 35%

    •   Dry Density : Minimum of 95% of maximum dry density

    Method

    Result

    From trial test that has been done, we get the minimum passes that meet the

    requirement is 10 passes.

  • 8/18/2019 Embankment Construktion Metod.pdf

    14/14

    Spirit of Innovation

    1. Each personnel using general safety equipment's (mask,

    glasses, safety boot, gloves, etc.)2. Provide flagman to control traffic circulation

    3. Provide warning sign

    4. Provide working border area

    5. Periodic safety patrol control

    6. Tool box meeting before and after work

    7. Provide safety officer

    Standart safety equipments :

    SAFETY AND ENVIRONMENT