EMC ® VNXe ® Replacing a link control card (LCC) in a 25-slot disk-array enclosure 302-000-217 REV 02 July, 2015 This document describes how to replace a link control card (LCC) in a 25-slot disk-array enclosure (DAE). The LCCs are accessible from the rear of the enclosure. Topics include: l Before you start ..........................................................................................................2 l Replacing the faulted hardware component ............................................................... 5 l Returning a faulted part ........................................................................................... 10

EMC VNXe Replacing a link control card (LCC) in a 25-slot ... · LCC to avoid dropping it. 2. Locate the orange handle buttons on the LCC handles. 3. Press the orange handle buttons

  • Upload
    hanhi

  • View
    218

  • Download
    0

Embed Size (px)

Citation preview

Page 1: EMC VNXe Replacing a link control card (LCC) in a 25-slot ... · LCC to avoid dropping it. 2. Locate the orange handle buttons on the LCC handles. 3. Press the orange handle buttons

EMC® VNXe®

Replacing a link control card (LCC) in a 25-slotdisk-array enclosure302-000-217REV 02

July, 2015

This document describes how to replace a link control card (LCC) in a 25-slot disk-arrayenclosure (DAE).

The LCCs are accessible from the rear of the enclosure.

Topics include:

l Before you start..........................................................................................................2l Replacing the faulted hardware component............................................................... 5l Returning a faulted part........................................................................................... 10

Page 2: EMC VNXe Replacing a link control card (LCC) in a 25-slot ... · LCC to avoid dropping it. 2. Locate the orange handle buttons on the LCC handles. 3. Press the orange handle buttons

Before you startBefore you begin this procedure, ensure that you have received the new part and havecorrectly identify its intended location in the system. Refer to your Unisphere online help(Servicing your system > Adding or replacing faulted hardware components > Replace afaulted hardware component) for instructions on how to identify failures, order new partsand handle hardware components.

NOTICE

This procedure involves storage processor (SP) reboots coordinated to ensure that atleast one SP is running at all times. During an SP reboot, data will be unavailable to front-or back-end connections that are not duplicated on the peer SP.

Handling replaceable unitsThis section describes the precautions that you must take and the general proceduresthat you must follow when removing, installing, and storing any replaceable unit.

Avoiding electrostatic discharge (ESD) damage

When replacing or installing hardware units, you can inadvertently damage the sensitiveelectronic circuits in the equipment by simply touching them. Electrostatic charge thathas accumulated on your body discharges through the circuits. If the air in the work areais very dry, running a humidifier in the work area will help decrease the risk of ESDdamage. Follow the procedures below to prevent damage to the equipment.

Read and understand the following instructions:

l Provide enough room to work on the equipment.

l Clear the work site of any unnecessary materials or materials that naturally build upelectrostatic charge, such as foam packaging, foam cups, cellophane wrappers, andsimilar items.

l Do not remove replacement or upgrade units from their antistatic packaging until youare ready to install them.

l Before you begin service, gather together the ESD kit and all other materials you willneed.

l Once servicing begins, avoid moving away from the work site; otherwise, you maybuild up an electrostatic charge.

l Use ESD anti-static gloves or an ESD wristband (with strap).If using an ESD wristband with a strap:

n Attach the clip of the ESD wristband to the ESD bracket or bare metal on acabinet/rack or enclosure.

n Wrap the ESD wristband around your wrist with the metal button against yourskin.

n If a tester is available, test the wristband.

l If an emergency arises and the ESD kit is not available, follow the procedures inEmergency Procedures (without an ESD kit).

2 EMC VNXe

Page 3: EMC VNXe Replacing a link control card (LCC) in a 25-slot ... · LCC to avoid dropping it. 2. Locate the orange handle buttons on the LCC handles. 3. Press the orange handle buttons

Emergency procedures (without an ESD kit)

In an emergency when an ESD kit is not available, use the following procedures to reducethe possibility of an electrostatic discharge by ensuring that your body and thesubassembly are at the same electrostatic potential.

NOTICE

These procedures are not a substitute for the use of an ESD kit. Follow them only in theevent of an emergency.

l Before touching any unit, touch a bare (unpainted) metal surface of the cabinet/rackor enclosure.

l Before removing any unit from its antistatic bag, place one hand firmly on a baremetal surface of the cabinet/rack or enclosure, and at the same time, pick up the unitwhile it is still sealed in the antistatic bag. Once you have done this, do not movearound the room or touch other furnishings, personnel, or surfaces until you haveinstalled the unit.

l When you remove a unit from the antistatic bag, avoid touching any electroniccomponents and circuits on it.

l If you must move around the room or touch other surfaces before installing a unit,first place the unit back in the antistatic bag. When you are ready again to install theunit, repeat these procedures.

Hardware acclimation times

Systems and components must acclimate to the operating environment before applyingpower. This requires the unpackaged system or component to reside in the operatingenvironment for up to 16 hours in order to thermally stabilize and prevent condensation.

Table 1 Hardware acclimation times (systems and components)

If the last 24 hours of theTRANSIT/STORAGEenvironment was this:

…and the OPERATINGenvironment is this:

…then let the system orcomponent acclimate inthe new environmentthis many hours:

Temperature Humidity

Nominal68-72°F (20-22°C)

Nominal40-55% RH

Nominal 68-72°F (20-22°C)40-55% RH

0-1 hour

Cold<68°F (20°C)

Dry<30% RH

<86°F (30°C) 4 hours

Cold<68°F (20°C)

Damp≥30% RH

<86°F (30°C) 4 hours

Hot>72°F (22°C)

Dry<30% RH

<86°F (30°C) 4 hours

Hot>72°F (22°C)

Humid30-45% RH

<86°F (30°C) 4 hours

Humid45-60% RH

<86°F (30°C) 8 hours

Replacing a link control card (LCC) in a 25-slot disk-array enclosure

Handling replaceable units 3

Page 4: EMC VNXe Replacing a link control card (LCC) in a 25-slot ... · LCC to avoid dropping it. 2. Locate the orange handle buttons on the LCC handles. 3. Press the orange handle buttons

Table 1 Hardware acclimation times (systems and components) (continued)

If the last 24 hours of theTRANSIT/STORAGEenvironment was this:

…and the OPERATINGenvironment is this:

…then let the system orcomponent acclimate inthe new environmentthis many hours:

Humid≥60% RH

<86°F (30°C) 16 hours

Unknown <86°F (30°C) 16 hours

NOTICE

l If there are signs of condensation after the recommended acclimation time haspassed, allow an additional eight (8) hours to stabilize.

l Systems and components must not experience changes in temperature and humiditythat are likely to cause condensation to form on or in that system or component. Donot exceed the shipping and storage temperature gradient of 45°F/hr (25°C/hr).

l Do NOT apply power to the system for at least the number of hours specified in Table1 on page 3. If the last 24 hours of the transit/storage environment is unknown, thenyou must allow the system or component 16 hours to stabilize in the newenvironment.

Removing, installing, or storing replaceable units

Use the following precautions when removing, handling, or storing replaceable units:

CAUTION

Some replaceable units have the majority of their weight in the rear of the component.Ensure that the back end of the replaceable unit is supported while installing orremoving it. Dropping a replaceable unit could result in personal injury or damage to theequipment.

NOTICE

l For a module that must be installed into a slot in an enclosure, examine the rearconnectors on the module for any damage before attempting its installation.

l A sudden jar, drop, or even a moderate vibration can permanently damage somesensitive replaceable units.

l Do not remove a faulted replaceable unit until you have the replacement available.

l When handling replaceable units, avoid electrostatic discharge (ESD) by wearing ESDanti-static gloves or an ESD wristband with a strap. For additional information, see: Avoiding electrostatic discharge (ESD) damage on page 2.

l Handle a replaceable unit gently. A sudden jar, drop, or vibration can permanentlydamage some replaceable units.

l Avoid touching any exposed electronic components and circuits on the replaceableunit.

l Never use excessive force to remove or install a replaceable unit. Take time to readthe instructions carefully.

4 EMC VNXe

Page 5: EMC VNXe Replacing a link control card (LCC) in a 25-slot ... · LCC to avoid dropping it. 2. Locate the orange handle buttons on the LCC handles. 3. Press the orange handle buttons

l Store a replaceable unit in the antistatic bag and the specially designed shippingcontainer in which you received it. Use the antistatic bag and special shippingcontainer when you need to return the replaceable unit.

l Replaceable units must acclimate to the operating environment before applyingpower. This requires the unpackaged component to reside in the operatingenvironment for up to 16 hours in order to thermally stabilize and preventcondensation. Refer to Hardware acclimation times on page 3 to ensure thereplaceable unit has thermally stabilized to the operating environment.

NOTICE

Your storage system is designed to be powered on continuously. Most components arehot swappable; that is, you can replace or install these components while the storagesystem is running. However, the system requires that:

l Front bezels should always be attached to ensure EMI compliance. Make sure youreattach the bezel after replacing a component.

l Each slot should contain a component or filler panel to ensure proper air flowthroughout the system.

Unpacking a partProcedure

1. Wear ESD gloves or attach an ESD wristband to your wrist and the enclosure in whichyou are installing the part.

2. Unpack the part and place it on a static-free surface.

3. If the part is a replacement for a faulted part, save the packing material to return thefaulted part.

Replacing the faulted hardware componentTake the following actions to remove the faulted hardware part and install thereplacement hardware part into the system.

Summary of tasks for replacing an LCCTo replace an LCC you must complete the tasks below in the order in which they appear.This document provides instructions for completing each task.

1. Identify the faulted LCC.

2. Prepare the storage processor (SP) associated with the faulted LCC for service.

3. Disconnect the SAS cables from the LCC.

4. Remove the faulted LCC from the enclosure.

5. Unpack the replacement LCC.

6. Install the replacement LCC in the enclosure.

7. Reconnect the SAS cables to the replacement LCC.

8. Reboot the SP.

9. Verify the operation of the replacement LCC.

Identifying a faulted LCCThe LCCs are visible from the rear of your DAE.

Replacing a link control card (LCC) in a 25-slot disk-array enclosure

Replacing the faulted hardware component 5

Page 6: EMC VNXe Replacing a link control card (LCC) in a 25-slot ... · LCC to avoid dropping it. 2. Locate the orange handle buttons on the LCC handles. 3. Press the orange handle buttons

Identify the faulted LCC by the amber fault LED (Figure 1 on page 6).

Figure 1 LCC fault LED

CL4580

Preparing the storage processor (SP) for service

NOTICE

To protect your VNXe system from accidental data loss while you add or replace a faultedLCC in a DAE connected to you VNXe system, you must prepare the SP associated with theLCC for service before you replace the LCC. You prepare an SP for service by putting it inService mode. Both SPs must NOT be in Service mode at the same time.

Procedure

1. Open Unisphere™.

2. Select Settings > Service System.

3. Log in with your service password.

4. In the System Components list, select the storage processor (SP A or SP B) associatedwith the faulted LCC:

l SP A for an LCC A

l SP B for an LCC B

5. Under Service Actions, select Enter Service Mode, then Execute service action.

6. Review the Service Confirmation dialog box and then click OK.

Putting an SP into Service mode takes about 10 minutes to complete. The storageprocessor fault LED will flash alternating amber and blue while the SP remains inService mode and is receiving active power.

7. Wait until the SP fault LED is flashing alternating amber and blue before continuing tothe next task.

Disconnecting the SAS cablesRemove each cable connected to the LCC by gently pulling the connector latches torelease the cable from the connector (Figure 2 on page 7).

Note where the cables connect to the LCC because you will reconnect them later.

6 EMC VNXe

Page 7: EMC VNXe Replacing a link control card (LCC) in a 25-slot ... · LCC to avoid dropping it. 2. Locate the orange handle buttons on the LCC handles. 3. Press the orange handle buttons

Figure 2 Disconnecting a SAS cable

CL4579

molex

molex

molex

Removing an LCCRefer to Figure 3 on page 8 while performing the procedure that follows.

Procedure

1. Attach an ESD wristband to your wrist and the enclosure.

NOTICE

When removing an LCC, in addition to holding the latches, be prepared to support theLCC to avoid dropping it.

2. Locate the orange handle buttons on the LCC handles.

3. Press the orange handle buttons to release the LCC, pull the latches outward, andremove the LCC from its slot.

4. Place the LCC on a clean, static-free surface.

Replacing a link control card (LCC) in a 25-slot disk-array enclosure

Removing an LCC 7

Page 8: EMC VNXe Replacing a link control card (LCC) in a 25-slot ... · LCC to avoid dropping it. 2. Locate the orange handle buttons on the LCC handles. 3. Press the orange handle buttons

Figure 3 Removing an LCC

CL4577

Installing a replacement LCCRefer to Figure 4 on page 8 while performing the procedure that follows.

Procedure

1. Attach an ESD wristband to your wrist and the enclosure.

2. Pull out the latches on the LCC and make sure they stay in the open position.

3. Align the LCC with the enclosure opening and gently push the LCC straight into theenclosure, being sure the LCC is completely seated in the enclosure.

4. Press the latches to secure the LCC.

Figure 4 Installing an LCC

CL4578

Results

The LCC power LED turns on (Figure 5 on page 9).

8 EMC VNXe

Page 9: EMC VNXe Replacing a link control card (LCC) in a 25-slot ... · LCC to avoid dropping it. 2. Locate the orange handle buttons on the LCC handles. 3. Press the orange handle buttons

Figure 5 LCC power LED

CL4580a

Reconnecting the SAS cablesProcedure

1. Reattach the SAS cables to the same connectors from which you removed them(Figure 6 on page 9).

2. Remove and store the ESD wristband.

Figure 6 Connecting a SAS cable

CL4579

molex

molex

molex

Replacing a link control card (LCC) in a 25-slot disk-array enclosure

Reconnecting the SAS cables 9

Page 10: EMC VNXe Replacing a link control card (LCC) in a 25-slot ... · LCC to avoid dropping it. 2. Locate the orange handle buttons on the LCC handles. 3. Press the orange handle buttons

Rebooting an SPWhen you have installed a part in the enclosure, reboot the recently serviced SP to ensurethat it leaves Service mode using the procedure that follows.

Procedure

1. From Unisphere, select Settings, then Service System.

2. Log in with your service password.

3. In the System Components column, select the storage processor currently in Servicemode (SP A or SP B).

4. Under Service Actions, select Reboot, then Execute service action.

It may take up to 12 minutes for the system to complete its reboot to return to normalmode.

5. Either refresh your browser or follow the on-screen instructions to bring the softwareout of service mode and restore full-function Unisphere.

Verifying the operation of a partVerify that the new part is recognized by your system, and operating correctly using theprocedure that follows.

Procedure

1. In Unisphere™, select System > System Health.

2. Select the part in the System Component list or the graphical view:

Note

To verify the status of a part contained within the storage processor, like a batterybackup unit, for example, you must locate the part in the System Component list.

l In the System Component list, the part should be marked with a status OK icon:

l In the graphical view, the part should be highlighted green.

If the system health monitor shows the part as faulted, contact your service provider.

Returning a faulted partWe appreciate the return of defective material within 5 business days (for US returns). ForInternational customers, please return defective material within 5-10 business days. Allinstructions and material required to return your defective part were supplied with yourgood part shipment.

Procedure

1. Package the faulted part in the shipping box that contained the replacement part, andseal the box.

2. Ship the failed part to your service provider as described in the instructions that wereincluded with the replacement part.

3. [Optional] For more information about returning customer-replaceable parts, fromUnisphere, click Support > Need more Help? > Customer Replaceable Parts > Return aCustomer Replaceable Part to enter the EMC Online Support website.

10 EMC VNXe

Page 11: EMC VNXe Replacing a link control card (LCC) in a 25-slot ... · LCC to avoid dropping it. 2. Locate the orange handle buttons on the LCC handles. 3. Press the orange handle buttons

If your screen does not show the Return a customer replaceable part option, contactyour service provider for instructions on what to do next.

Replacing a link control card (LCC) in a 25-slot disk-array enclosure

Returning a faulted part 11

Page 12: EMC VNXe Replacing a link control card (LCC) in a 25-slot ... · LCC to avoid dropping it. 2. Locate the orange handle buttons on the LCC handles. 3. Press the orange handle buttons

Copyright © 2014-2015 EMC Corporation. All rights reserved. Published in USA.

Published July, 2015

EMC believes the information in this publication is accurate as of its publication date. The information is subject to change withoutnotice.

The information in this publication is provided as is. EMC Corporation makes no representations or warranties of any kind withrespect to the information in this publication, and specifically disclaims implied warranties of merchantability or fitness for aparticular purpose. Use, copying, and distribution of any EMC software described in this publication requires an applicable softwarelicense.

EMC², EMC, and the EMC logo are registered trademarks or trademarks of EMC Corporation in the United States and other countries.All other trademarks used herein are the property of their respective owners.

For the most up-to-date regulatory document for your product line, go to EMC Online Support (https://support.emc.com).

12 EMC VNXe