Upload
others
View
5
Download
0
Embed Size (px)
Citation preview
/ ....)i I~/~'
(i'- '1(- )<, (,' \ ( ; \.::
August 3 I, 2006
To All Document Holders:
a~-lISy'
GE 159 Plastics Avenue Pittsfield, MA 01201 USA
Re: Update Pages for GE's Emergency Action Plan (EAP) for Woods Pond Dam, Housatonic River, Lee/Lenox, MA
Enclosed are updated pages for the Emergency Action Plan (EAP) for Woods Pond Dam, which is owned by the General Electric Company (GE). These pages were updated to reflect the changes in the names and phone numbers of listed emergency contact persons, to reflect the most recent Structural Integrity Rep0l1 (April 2006), and to update the contact information for the occupants ofthe downstream, affected properties (Appendix D). The updated pages to be replaced include:
• Inside cover page (with date of revision); • Page i-ii Table of Contents; • Report Sections I-VII; • Exhibits 1-3 (Exhibit 2 is now 4 pages), & 5- 6; • Appendix B - all; • Appendix C - all; and • Appendix D - all.
If you have any questions associated with the EAP or Woods Pond Dam, please contact me at (413) 448-5910.
Very truly yours,
K~ Kevin Mooney GE Project Manager
Enclosure
CO'P<lral~ EM"omr,€ontoi Prcgr[]rr",
GENERAL ELECTRIC COMPANY Pittsfield, Massachusetts
EMERGENCY ACTION PLAN
for
WOODS POND DAM
Housatonic River Lee/Lenox, Massachusetts
Updated August 2006
Originally compiled March 4, 2003 by:
MWH Chicago, Illinois
Woods Pond Dam EAP Table of Contents
WOODS POND DAM EMERGENCY ACTION PLAN
TABLE OF CONTENTS
Section
I. Statement of Purpose
II. Project Description A. Background
B. Project Features
III. Potential Flood Limits
IV. Emergency Detection, Evaluation, and Classification
A. Condition A - Failure Is Imminent or Has Occurred B. Condition B - Potential Failure Situation Is Developing
V. Notification Flowchatis and Contact Numbers A. Condition A - Failure Is Imminent or Has OcculTed
B. Condition B - Potential Failure Situation Is Developing
VI. General Responsibilities Under the EAP A. General Electric Responsibilities
B. Responsibility for Notification
C. Responsibility for Evacuation
D. Responsibility for Duration, Secutity, Tetmination and Follow-Up
E. EAP Coordinator Responsibility
VII. Preparedness
A. Surveillance
B. Response DUling Periods of Darkness
C. Access to Site
D. Response During Weekends and Holidays
E. Response DUling Petiods of Adverse Weather
F. Availability and Use ofAlternate Communication Systems
G. Emergency Supplies and Resources
Updated August 2006
Woods Pond Dam EAP Table of Contents
TABLE OF CONTENTS (cont'd)
Exhibits I Project Location Map
2 General Plan
3 Potential Flood Limits
4 Possible Emergency Occurrences
5 Notification Flowchart, Condition A - Failure Is Imminent or Has Occurred
6 Notification Flowchart, Condition B - Potcntial Failure Situation is Developing
Appendices A Woods Pond Dam - Replacement Overflow Spillway Drawings
B Investigation of Potential Flood Limits C Plans for Training, Updating, and Posting the EAP
D List of Potentially Affected Downstream Residents
E GE Designated Contractors and List of Emergency Supplies and Resources
F Approval of the EAP G EAP Review Comments/Recommcndations (Local and State Emergency Agencies
and Local Emergency Coordinators)
Updated August 2006 ii
Woods Pond Dam EAP Statement of PUrpose
I. STATEMENT OF PURPOSE
This Emergency Action Plan (EAP) has been prepared on behalf of the General Electric
Company (GE) for Woods Pond Dam, which is owned by GE. The purpose of this EAP is
to:
1. Define the responsibilities of various officials involved in emergency management;
2. Provide procedures designed to identifY, in a timely manner, unusual and unlikely
conditions which may endanger the structural integrity of Woods Pond Dam;
3. IdentilY actions to take to mitigate an ongoing or developing situation; and
4. Provide procedures to notilY the appropriate emergency management officials, if
possible, of impending or actual failure of the dam.
In accordance with the regulations of the Massachusetts Depatiment of Conservation and
Recreation, Division of State Parks and Recreation (DCR) (fOlmerly known as the
Environmental Management (DEM)) Regulations (Chapter 302 CMR 10.06, November 4, 2005), Woods Pond Dam is designated as a "large" size dam with a "significant" hazard
(Class II) potential. This size classification is based on the storage capacity that occurs
during the spillway design flood, while the hazard potential classification is based on the
presumption that failure of the dam may result in the loss of life and significant property
damage immediately downstream ofthe dam.
According to DCR Regulations (Chapter 302 CMR 10.11, November 2005), all dams
classified as "high" hazard (Class I) shall have an EAP. Ifthe Commissioner requires it, a
facility with a non-high hazard dam shall also provide an EAP. DCR requested that GE
prepare an EAP for Woods Pond Dam; GE prepared this EAP in response to that request and
as an exercise of good engineering judgment. The EAP conforms to the requirements for
EAPs outlined in Section 10.11 of the DCR Regulations. All EAPs are subject to approval
by the DCR. The dam owner shall submit a copy of the proposed EAP to the local and state
emergency agencies and all local emergency coordinators involved in the plan for review.
The owner shall incorporate applicable recommendations received and provide the
documented recommendations in appendices to the final version of the EAP. Annually, the
owner shall review the EAP and update it as necessary
Updated August 2006 I·'
Woods Pond Dam EAP Statement ofPurpose
The EAP shall, at a minimum, contain the following:
I. The identification of equipment, manpower, and material available for
implementation ofthe Plan;
2. A notification procedure for infolming local emergency agencies;
3. A topographic map showing the stream which will be flooded; and
4. A procedure for warning nearby local residents if failure of the dam is imminent
and a listing of addresses and telephone numbers of downstream residents that
may be affected by failure of the dam.
As described in Section IV, "Emergency Detection, Evaluation and Classification," two alert
conditions have been adopted for Woods Pond Dam:
I. Condition A - Failure Is Imminent or Has Occurred, and
2. Condition B - Potential Failure Situation Is Developing
A notification flowchart for each of these alert conditions is presented in this EAP.
Updated August 2006 1-2
Woods Pond Dam EAP Project Description
II. PROJECT DESCRIPTION
A. Background
The original Woods Pond Dam was reportedly constructed around 1864 on the Housatonic
River near the towns of Lee and Lenox, Massachusetts, as shown on Exhibit I. The original
structure consisted of a 9-foot-high rock-filled timber crib overflow dam with a 14-foot-high
earthfill embankment parallel to the river channel as its east (left) abutment (left and right
refer to the side of the river channel when viewed looking in the downstream direction).
There are no design drawings or information available for any of the original project
structures. The original dam structure was replaced in 1989 with a new concrete overflow
spillway and new abutments of concrete and steel sheet pile. The earthfill (raceway) embankment separates the main river channel fi'om the 30 to 50-foot-wide raceway channel
along the left bank of the river. The raceway channel conveys flow to a small mill pond,
which at one time was a forebay for a water-powered mill that has since been retired. The
dam impounds the Woods Pond Reservoir, part of the Housatonic River Valley Wildlife
Management Area.
Prior to the 1989 rehabilitation, Woods Pond Dam was in a deteriorated condition. The original project could not pass a flood greater than about the lO-year flood event without
overtopping the earthen raceway embankment. Oveltopping of the embankment could have
caused a breach of the embankment, resulting in the uncontrolled release of the reservoir
water and sediments that had settled to the bottom ofthe reservoir.
Beginning in 1979, studies and investigations were performed to assess the condition of the
dam and develop recommendations for repair and rehabilitation of the dam. In 1983, the
timber planking and heavy gage sheet metal on the main overflow dam were replaced with an
18-inch-thick reinforced concrete cap. After placement of the cap, a leak developed at the
east abutment masomy wall, presumably due to the cut-off of natural seepage through the
timber crib dam. The joints in the masomy wall were filled with mortar shortly after the
1983 construction, temporarily stopping the leakage, but contributing to pressure buildup
behind the wall, causing lateral movement ofthe wall.
In 1988, a plan was developed to rehabilitate thc dam to provide a safer, more reliable project
structure. The rehabilitation was carried out in two stages. The first stage consisted of the
construction of a raceway closure structure with concrete stoplogs to divelt flow away fi'om
the raceway and mill pond. The purpose of the closure structure is to protect the raceway
Updated August 2006 II-I
Woods Pond Dam EAP Project Description
embankment from oveliopping and potential failure during high flows. The second stage
consisted of the constmction of a replacement spillway and non-overflow gravity dam a ShOli
distance downstream of the original spillway. A rockfill berm was also conshucted on the
west (right) bank of the river between the original spillway and new spillway, and the top
2.5 feet the original timber crib spillway was demolished. The original sluice gate stmcture
at the downstream end of the raceway embankment was rehabilitated in 1991. This stmcture
controls the water level in the Mill Pond.
Additional modifications to the project were perfolmed in 2001 to address recommendations
made in the January 2001 Stmctural Integrity Assessment Repoli, and in 2003 to address
recommendations made in the May 2003 Stmctural Integrity Assessment Report. The 2001
modifications included repair to deteriorated masomy at the raceway closure stmcture;
removal of trees and other vegetation along the raceway embankment; regrading of the
raceway channel slopes; and removal of the masonry wall and reworking of the riprap at the upstream raceway embankment. The 2003 modifications included removal of trees and other
vegetation and the placement of riprap along the river side of the raceway embankment.
Based on the stmctural integrity assessment inspection conducted subsequently in
November 2004, the dam, raceway closure stmcture, and riprap constmcted in 1989 are in good condition, and there was no indication of deterioration or distress to the spillway and
tailrace.
MWH conducted a visual inspection in November 2005 and made recommendations for
some minor physical modifications. GE is in the process of implementing these
recommendations. For details, refer to 2005 Stmctural Integrity Assessment RepOli by
MWH, dated April 2006.
A general plan of the rehabilitated project is shown on Exhibit 2. Drawings for the 1989
rehabilitation are included in Appendix A for reference. The "General Design Report for
Woods Pond Dam Rehabilitation" for the 1989 rehabilitation was filed with the DCR and is
included in Appendix B of the March 1999 Woods Pond Dam Inspection Report.
B. Project Features
The present dam consists of a 140-foot-Iong concrete overflow spillway, a concrete non
overflow gravity section at the west (right) abutment, and a concrete and steel sheetpile
raceway closure stmcture at the east (left) abutment, all constmcted since 1989. All the dam
stmctures are founded on bedrock. The dam has a maximum height of approximately 14 feet,
Updated August 2006 JI-2
Woods Pond Dam EAr Project Description
with an ogee-shaped spillway with a crest elevation of 948.3 feet National Geodetic Vertical
Datum (NGVD). The west (light) abutment is a concrete gravity structure with a sloped
downstream face and a top elevation of 954.0 feet NGVD. The raceway closure structure
forms the east (left) abutment of the dam and has a top elevation of 954.0 feet NGVD. The
drawings for the dam and raceway closure structure are provided in Appendix A. The CUlTent
structure is completely independent of the oliginal structure and does not rely on any of the
oliginal structures for support.
The current structures are founded on shallow bedrock, which is veliically bedded and is
generally fine grained, hard with valiable medium to close joint spacing. This was
detelmined during the 1988 geotechnical investigation program which included soil bolings
and water pressure testing of the rock. Details of the subsurface field investigation can be
found in the "General Design Report for Woods Pond Dam Rehabilitation" filed with the DCR in 1989 and included in the March 1999 Woods Pond Dam Inspection RepOli.
The raceway embankment upstream of the dam is earthen fill with liprap over the surface and
is no longer a water-retaining shucture serving no dam safety function. Failure of this
portion of the raceway embankment would have no impact on the safety or integrity of the
dam.
Downstream of the dam and raceway closure shucture is an earthen embankment protected with riprap along the length of the channel. This embankment is located between the tailrace
of the current overflow spillway and the raceway channel. The embankment has a crest
width of about 8 to 10 feet. The water elevation in the raceway is a few feet higher than the water elevation in the tailrace and river channel downstream of the dam.
Updated August 2006 II-3
Woods Pond Dam EAP Potential Flood Limits
III. POTENTIAL FLOOD LIMITS
Exhibit 3 shows a map of potential flood limits due to the failure of Woods Pond Dam under
"Sunny-day" and "Flood-day" conditions. Flood limits are for failure when the abutments
would be overtopped by two feet. "Sunny-day" means a fair-weather, non-rainy day. "Flood
day" means a rainy, non-fair-weather day. The term "day" includes nighttime. The potential
flood limits are plotted on Exhibit 3 to show the maximum inundation area due to dam failure
to the point downstream where the water would be contained within the banks of the river.
These limits were estimated based on the infolmation and data provided in two repOlis
entitled:
1. "Woods Pond Dam, Phase 1 Inspection Report, Lee and Lenox, Massachusetts,
prepared for EPA Region 1, prepared by U.S. Anny Corps of Engineers, Omaha District, September 1987,"
2. "Flood Insurance Study, Town of Lee, Massachusetts, Berkshire County by Federal Emergency Management Agency, December 1, 1981."
Refer to Appendix B - Investigation of Potential Flood Limits - for additional infonnation.
Updated August 2006 Ill-I
Woods Pond Dam EAP Emergency Detection, Evaluation. and Classification
IV. EMERGENCY DETECTION, EVALUATION, AND CLASSIFICATION
This EAP has been prepared to aid GE personnel in the timely detection, evaluation, and
classification of an existing or potential emergency situation at the dam. The EAP provides
two classifications of dam failure emergency according to their severity and urgency:
Condition A - Failure is Imminent or Has OccUlTed, and Condition B - Potential Failure
Situation Is Developing. The conditions or measures for detection and evaluation of an
existing or potential emergency are described below.
For purposes of this EAP, GE has designated a Facility Manager and an Alternate Facility
Manager (as specified in Section V). The Facility Manager shall have plimmy responsibility
for carrying out this Plan on behalf of GE. In the event that the Facility Manager is
unavailable, the Alternate Facility Manager shall be the point of contact and shall have all the duties and powers of the Facility Manager as set forth in this Plan. In addition, GE has pre
selected contractors, also specified in Section V, to assist in emergency response under this
EAP.
A. Condition A - Failure is Imminent or Has Occurred
The following conditions may lead to the "Failure is Imminent or Has Occun-ed" emergency situation. These conditions should not be considered inclusive of all conditions that might
occur:
• Rapidly developing stmctural problems involving the spillway, raceway embankment,
abutments, and appul1enant stmctures. Some of the potential causes of developing
stmctural problems are listed on Exhibit 4.
The notification procedures of Section V, "Notification Flowcharts and Contact Numbers"
and given on the flowchart for Condition A (Exhibit 5), should be invoked if any of the
situations listed on Exhibit 4 are observed. An imminent situation at the dam site will
probably manifest itself as an excessive increase in flow in the Housatonic River and/or an
unexpected drop or lise in water level in the reservoir, river channel, raceway channel or mill
pond.
When failure is observed, the Observer (as defined in Section V) shall inform the Facility
Manager. The Facility Manager shall decide the severity of the problem and invoke the
notification procedure if appropriate.
Updated August 2006 VIol
Woods Pond Dam EAP Emergency Detection. Evaluation. and Classification
The message fi'om the Facility Manager to the persons identified on the flowchart for this
situation (Exhibit 5) will contain the following information:
• Name and title (GE position) of the person making the call.
• A statement that this is an emergency call, due to a reported failure or imminent
failure of Woods Pond Dam.
• A statement that the person receiving the message must initiate contacts as per the
flowchart for "Condition A - Failure is Imminent or Has Occurred."
• A statement that warning and evacuation should begin immediately.
B. Condition B - Potential Failure Situation is Developing
The conditions that may lead to the "Potential Failure Situation is Developing" emergency
situation are also listed on Exhibit 4. Upon confinuing any of the situations listed on Exhibit
4, the notification procedures will be implemented by the Facility Manager. There will be
two messages from the Facility Manager for this situation. The first message will contain the
following infonnation:
• Name and title (GE position) of the person making the call.
• A statement that a potential failure situation is developing at Woods Pond Dam that
may lead to failure ofthe dam.
• A statement that the person receiving the message should put his or her contacts on
alert for a second notification message.
• A statement that emergency personnel should be ready for an evacuation process.
If failure of the dam becomes imminent, the second message from the Facility Manager shall
be as given in this section under "Condition A - Failure Is Imminent or Has Occurred."
If the dam failure is averted and the developing situation is mitigated, the emergency will be
called off via the same communication channels. In such an event, the message will contain
the following information:
• Name and title (GE position) of the person making the call.
• A statement that the potential failure situation at Woods Pond Dam has been averted,
and that the recipients' contacts should stand down fi'om emergency alert.
Updated August 2006 VI-2
Woods Pond Dam EAP Notification Flowcharts and Contact Numbers
V. NOTIFICATION FLOWCHARTS AND CONTACT NUMBERS
The flowcharts shown in Exhibits 5 and 6 summarize who is to be notified and who is
responsible for notifying individuals and organizations in the order designated for the
following emergency situations:
A. Faillire Is Imminent or Has Occurred (Condition A): COiTesponds to situations where
a failure either has occlmed, is occurring, or obviously is just about to occur. The
notification flowchart for Condition A is printed on red paper.
B. Potential Failure Situation is Developing (Condition B): COl1"esponds to situations
where a dam failure may develop, but preplanned actions may prevent or mitigate
failure. Generally, there is more time available under this condition than under
Condition A to take preventative action and bring the situation under control. The
notification flowchart for Condition B is printed on yellow paper.
A copy of the flowchmis shall be prominently posted near the telephone or radio transmitter
of each person identified on the flowchatis as a caller. The key personnel of GE and police depatiments shall have copies in their offices and at homes (see Appendix C for EAP
distribution).
Detailed information supplementing the flowchmis is provided in Section N - Emergency
Detection, Evaluation, and Classification. The location of the dam, reservoir, and streams are
described in the Section II - Project Description. Potential inundation limits are discussed in
Section III - Potential Flood Limits. In addition to the individuals and agencies listed as
contacts in Actions 1 through 8 for Condition A and Condition B, GE has additional notification requirements under the Consent Decree for the GE-PittsfieldlHousatonic River
Site (the Consent Decree). The contacts for those notifications are listed in Action 9.
Paragraph 90 of the Consent Decree requires that notice be given "[i]n the event of any action
or occurrence during the performance of the Work which causes or threatens a release of
Waste Material from the Site that constitutes an emergency situation or may present an
immediate threat to public health or welfare or the environment." The phrase "constitutes an
emergency situation or may present an immediate threat to public health or welfare or the
environment" is further defined to mean "an unforeseen combination of circumstances, or the
conditions resulting from such circumstances, not normally anticipated to occur as part of the
Work, that require immediate action to avoid harm or an immediate threat of hmm to human
health, welfare or the environment."
Updated August 2006 V-I
Woods Pond Dam EAP Notification Flowcharts and Contact Numbers
For Condition A, notification to the contacts listed in Action 10 is required. For Condition
B, the Facility Manager shall provide notification to the contacts listed in Action 10 as
appropriate, based on the requirements of Paragraph 90 ofthe Consent Decree quoted above.
Updated August 2006 V-2
Woods Pond Dam EAP Notification Flowcharts and Contact Numbers
A. Condition A - Failure Is Imminent 01' Has Occurred
In the event that failure is imminent or has occurred at Woods Pond Dam, GE personnel shall
initiate the notification actions in accordance with the flowchart shown on Exhibit 5. The
positions and the sequence of notification for the flowchatis are explained below.
Observer
The Observer will be the GE employee or contractor who monitors the condition of the dam
and its appurtenant structures (as described in Section VLA). In the event of a tIn'eatening
situation at the dam site, the Observer shall immediately notify the following GE contacts:
General Electric
Primary Contact:
Kevin Mooney, Facility Manager Phone No: (413) 448-5910
Home Phone: (413) 447-9362
Cell No: (413) 441-4610
Secondary Contact:
John Levesque, Alternate Facility Manager Phone No: (413) 48-5914
Home Phone: (413) 743-3245
Cell No: (413) 441-4786
Once aware of an imminent failure of the dam, the Facility Manager shall send a team to the
dam site and shall initiate the following required actions:
Action 1. Notify GE Response Contractor
The following contractors have been pre-selected by GE to assist in response actions under
this EAP:
LB Corporation
Designated Person:
Thomas R. Ga111ty Phone No: (413) 243-1072
LB Corporation Home Phone: (413) 243-1246
Cell No: (413) 441-9317
Updated August 2006 V-3
Woods Pond Dam EAP Notification Flowcharts and Contact Numbers
Alternate Contacts:
Thomas M. Gan'ity
LB Corporation
Steve Garrity
LB Corporation
Maxymillian Technologies
Designated Person:
Keith Hoag
Maxymillian Technologies Inc.
Alternate Contacts:
PenyFlood
Maxymillian Technologies Inc.
BlUce Rustemeyer
Maxymillian Technologies Inc.
Vern Palen
Maxymillian Technologies Inc.
Phone No: (413) 243-1072
Home Phone: (413) 243-1908
Cell No: (413) 441-9318
Phone No: (413) 243-1072
Home Phone: (413) 243-2505
Cell No: (413) 441-1412
Cell No: (413) 441-3379
Pager No: (413) 261-5034
Home Phone: (413) 743-0197
Cell No: (413) 441-3850
Pager No: (413) 261-5725
Home Phone: (413) 243-2789
Cell No: (413) 441-6291
Home Phone: (413) 634-5047
Cell No: (413) 441-4095
Pager No: (413) 292-8502
Home Phone: (413) 623-8343
Updated August 2006 V-4
Woods Pond Dam EAP Notification Flowcharts and Contact Numbers
Action 2. Notify Berkshire County Sheriff Communication Centel'
Designated Person:
Desk Officer/Dispatcher Phone No: (413) 442-0512
Altemate Contact:
Desk Officer/Dispatcher Phone No: (413) 445-4559
(Berkshire County Sheriff Communication Center handles the 911 calls for Lenox and
Stockbridge. Calling the listed telephone numbers is equivalent to calling 911 in Lenox or
Stockbridge)
Action 3. Notify Town of Lenox Police Department
Designated Person:
Stephen E. O'Blien Phone No: (413) 637-2346
Alternate Contact:
Tony Salvatore Phone No: (413) 499-7357
Action 4. Notify Town of Lee Police Department
Designated Person:
Ronald Glidden Phone No: (413) 243-2100
Alternate Contact:
Desk Officer Phone No: (413) 243-0678
(Lee Police depattment handles the 911 calls for Lee. Calling the listed telephone numbers is
equivalent to calling 911 in Lee)
Action 5. Notify Town of Stockbridge Police Department
Designated Person:
Richard B. Wilcox Phone No: (413) 298-5520
Altemate Contact:
Desk Officer Phone No: (413) 298-5530
Updated August 2006 V-5
Woods Pond Dam EAP Notification Flowcharts and Contact Numbers
Action 6. Notify Massachusetts Department of Environmental Protection (DEP)
Designated Person:
Spill Emergency Number (Toll Free) Phone No: (888) 304-1133
Action 7. Notify Massachusetts State Police (Rte. 20, Lee)
Designated Person:
Desk Officer Phone No: (413) 243-0600
Altel1late Contact:
Troop B Duty Officer
Northampton, MA Phone No: (413) 587-5517
Action 8. Notify Department of Conservation and Recreation, Division of State Parks
and Recreation
Designated Person:
William Sa10mma Phone No: (617) 626-1410
Action 9. Notify Massachusetts Emergency Management Agency
Designated Person:
Patrick Call1evale, Director Phone No: (413) 323-6306
Action 10. Notify Regulatory Contacts U1~der Consent Decree
(required for Condition A)
• U.S. Environmental Protection Agency:
Designated Person:
Susan Svirsky Phone No: (617) 918-1434
Altel1late Contact:
EPA New England Emergency
Response Section Phone No: (617) 918-1260
Updated August 2006 V-6
Woods Pond Dam EAP Notification Flowcharts and Contact Numbers
• Massachusetts Department of Environmental Protection:
Designated Person:
Susan Steenshup Phone No: (413) 755-2264
Altemate Contact:
Anna Symington Phone No: (413) 755-2220
• Connecticut Department of Envil·onmental Protection
Designated Contact:
Oil & Chemical Response Division Phone No: (860) 424-3338
Action11. Notify Housatonic Railroad Company
Designated Person:
Matt Boardman Phone No: (860) 824-0850, Ext. 17
Altemate Contact:
Dispatcher Phone No: (860) 824-0850, Ext. 12
After contacting the above parties, the Facility Manager will continue to monitor the situation
and infOlm the agencies as needed. Once notified by the Facility Manager, the agencies wiII
coordinate emergency operations. The agencies will also maintain contact with the Facility
Manager.
Town of Lenox Police Department
Once notified by the Facility Manager, the Town of Lenox Police Depatiment should initiate
the following actions to assist them in coordinating their efforts.
Action 1. Notify Town of Lenox Fire Department
Designated Person:
Dan Clifford Phone No: (413) 637-2347
Altemate Contact:
Dan Clifford Phone No: (413) 499-7357
Once notified, fire department perSOlmel will assist police depmiment personnel 111
evacuating the residents to safe places and providing necessary shelters and food.
Updated August 2006 V-7
Woods Pond Dam EAP Notification Flowcharts and Contact Numbers
Action 2. Notify Town of Lenox Department of Public Works (DPW)
Designated Person:
Jeff Vincent Phone No: (413) 637-5525
Alternate Contact:
R. Scott Jarvis Phone No: (413) 637-5520
Once notified, Lenox DPW personnel will place banicades on roads leading to the inundated
areas.
Action 3. Notify Potentially Affected Downstream Residents in Town of Lenox
Police depmiment personnel will contact the potentially affected downstream residents in the
Town of Lenox listed in Appendix D, and will issue appropriate inshuctions regarding
evacuation and temporary shelters.
Town of Lee Police Department
Once notified by the Facility Manager, the Town of Lee Police Department should initiate the
following actions to assist them in coordinating their efforts.
Action 1. Notify Town of Lee Fire Department
Designated Person:
Ron Driscoll Phone No: (413) 243-2100
Once notified, fire department personnel will assist police depmiment personnel III
evacuating affected residents to safe places and providing necessmy shelters and food.
Action 2. Notify Town of Lee Department of Public Works (DPW)
Designated Person:
Mike Towler Phone No: (413) 243-5526
Alternate Contact:
Mike Towler Phone No: (413) 243-2100
Once notified, Lee DPW personnel will place barricades on roads leading to the inundated
areas.
Updated August 2006 V-8
Woods Pond Dam EAP Notification Flowcharts and Contact Numbers
Action 3. Notify Potentially Affected Downstream Residents in Town of Lee
Police department persOlmel will contact the potentially affected downstream residents in the
Town of Lee listed in Appendix D, and will issue appropriate instructions regarding
evacuation and temporaIY shelters.
Town of StocI{bridge Police Department
Once notified by the Facility Manager, the Town of Stockbridge Police Department should
initiate the following actions to assist them in coordinating their efforts:
Action 1. Notify Town of Stockbridge Fire Department
Designated Person:
Louis Peyron Phone No: (413) 298-4886
Once notified, fire depaliment personnel will assist police department personnel in evacuating affected residents to safe places and providing neceSSalY shelters and food.
Action 2. Notify Town of Stockbridge Highway Department
Designated Person:
Clint Schneyer Phone No: (413) 298-5506
Once notified, Stockbridge highway department personnel will place barricades on roads
leading to the inundated areas.
Action 3. Notify Potentially Affected Downstream Residents in Town of Stockbridge
Police department personnel will contact the potentially affected downstream residents in the
Town of Stockbridge listed in Appendix D, and will issue appropriate instructions regarding
evacuation and temporaIY shelters.
Updated August 2006 V-9
Woods Pond Dam EAP Notification Flowcharts and Contact Numbers
B. Condition B - Potential Failure Situation Is Developing
In the event that a potentially hazardous situation is developing at Woods Pond Dam, GE
personnel shall initiate notification procedures according to the flowchati shown in Exhibit 6.
The positions and sequence of notification for the flowchart are explained below.
Observer
In the event that a potential failure situation is developing at the dam site, the Observer shall
immediately notify the following GE contacts:
General Electric
Primary Contact:
Kevin Mooney, Facility Manager Phone No: (413) 448-5910
Home Phone: (413) 447-9362
Cell No: (413) 441-4610
SecondalY Contact:
John Levesque, Alternate Facility Manager Phone No: (413) 48-5914
Home Phone: (413) 743-3245
Cell No: (413) 441-4786
Once aware of a potential failure situation at the dam, the Facility Manager shall send a team
to the dam site to mitigate the situation. The following actions shall be initiated:
Action 1. Notify GE Response Contractor
The following contractors have been pre-selected by GE to assist in response actions under
this EAP:
LB Corporation
Designated Person:
Thomas R. Garrity Phone No: (413) 243-1072
LB Corporation Home Phone: (413) 243-1246
Cell No: (413) 441-9317
Updated August 2006 V-IO
Woods Pond Dam EAP Notification Flowcharts and Contact Numbers
Altemate Contacts:
Thomas M. Garrity
LB Corporation
Steve Garrity
LB Corporation
Maxymillian Technologies
Designated Person:
Keith Hoag
Maxymillian Technologies Inc.
Altemate Contacts:
Perry Flood
Maxymillian Technologies Inc.
Bruce Rustemeyer
Maxymillian Technologies Inc.
Vem Palen
Maxymillian Technologies Inc.
Phone No: (413) 243-1072
Home Phone: (413) 243-1908
Cell No: (413)441-9318
Phone No: (413) 243-1072
Home Phone: (413) 243-2505
Cell No: (413) 441-1412
Cell No: (413) 441-3379
Pager No: (413) 261-5034
Home Phone: (413) 743-0197
Cell No: (413) 441-3850
Pager No: (413) 261-5725
Home Phone: (413) 243-2789
Cell No: (413) 441-6291
Home Phone: (413) 634-5047
Cell No: (413) 441-4095
Pager No: (413) 292-8502
Home Phone: (413) 623-8343
Action 2. Notify Berkshire County Sheriff COllllllunication Center
Designated Person:
Desk OfficerlDispatcher Phone No: (413) 442-0512
Altemate Contact:
Desk Officer/Dispatcher Phone No: (413) 445-4559
(Berkshire County Sheriff Communication Center handles the 911 calls for Lenox
and Stockbridge. Calling the listed telephone numbers is equivalent to calling 911 in
Lenox or Stockbridge)
Updated August 2006 V-II
Woods Pond Dam EAP Notification Flowcharts and Contact Numbers
Action 3. Notify Town of Lenox Police Dcpm'tment
Designated Person:
Stephen O'Brien Phone No: (413) 637-2346
Alternate Contact:
Tony Salvatore Phone No: (413) 499-7357
Action 4. Notify Town of Lee Police Department (same as 911 for Lec)
Designated Person:
Ronald Glidden Phone No: (413) 243-2100
Alternate Contact:
Desk Officer Phone No: (413) 243-0678
(Lee Police department handles the 911 calls for Lee, Calling the listed telephone numbers is
equivalent to calling 911 in Lee)
Action 5. Notify Town of Stockbridge Police Department
Designated Person:
Richard Wilcox Phone No: (413) 298-5520
Alternate Contact:
Desk Officer Phone No: (413) 447-7357
Action 6. Notify Massachusetts Department of Environmental Protection (DEP)
Designated Person:
Spill Emergency Number (Toll Free) Phone No: (888) 304-1133
Alternate Contact:
Spill Emergency Number Phone No: (617) 556-1133
Action 7. Notify Massachusetts State Policc (Rte. 20, Lee)
Designated Person:
Desk Officer Phone No: (413) 243-0600
Updated August 2006 V-12
Woods Pond Dam EAP Notification Flowcharts and Contact Numbers
Alternate Contact:
Troop B Duty Officer
NOlthampton, MA Phone No: (413) 587-5517
Action 8. Notify Department of Conservation and Recreation, Division of State Parks
and Recreation
Designated Person:
Michael Misslin Phone No: (617) 626-4927
Alternate Contact:
Michael Misslin Cell Phone No: (617) 828-1649
Action 9. Notify Massachnsetts Emergency Management Agency
Designated Person:
Patrick Carnevale, Director Phone No: (413) 323-6306
Action 10. Notify Regulatory Contacts under Consent Decree
(as appropriate for Condition B)
• U.S. Environmental Protection Agency:
Designated Person:
Susan Svirsky Phone No: (617) 918-1434
Alternate Contact:
EPA New England Emergency
Response Section Phone No: (617) 918-1260
• Massachusetts Department of Environmental Protection:
Designated Person:
Susan Steensttup Phone No. 413-755-2264
Alternate Contact:
Anna Symington Phone No. 413-755-2220
• Connecticut Department of Environmental Protection
Designated Contact:
Oil & Chemical Spill Response Division Phone No. 860-424-3338
Updated August 2006 V-13
Woods Pond Dam EAP Notification Flowcharts and Contact Numbers
Action 11. Notify Housatonic Railroad Company
Designated Person:
Matt Boardman Phone No: (860) 824-0850, Ext. 17
Altemate Contact:
Dispatcher Phone No: (860) 824-0850, Ext. 12
While in contact with the above agencies, the Facility Manager will advise them to be on
alert and wait for a second call on further developments at the dam site. The Facility
Manager will continue to monitor the situation and inform the agencies as needed. Once
notified by the Facility Manager, the respective agencies will come up with a plan for
emergency operations. The agencies will also maintain contact with the Facility Manager.
Town of Lenox Police Department
Once notified by the Facility Manager, the Town of Lenox Police Department should initiate
the following actions to assist them in coordinating their effolis.
Action 1. Notify Town of Lenox Fire Department
Designated Person:
Dan Clifford Phone No: (413) 637-2347
Alternate Contact:
Dan Clifford Phone No: (413) 499-7357
Once notified, fire department personnel will assist police department personnel 1ll
evacuating the residents to safe places and providing necessary shelters and food.
Action 2. Notify Town of Lenox Department of Public Works (DPW)
Designated Person:
Jeff Vincent Phone No: (413) 637-5525
Alternate Contact:
R. Scott Jarvis Phone No: (413) 637-5520
Once notified, Lenox DPW personnel will place bmTicades on roads leading to the inundated
areas.
Updated August 2006 V-14
Woods Pond Dam EAP Notification Flowcharts and Contact Numbers
Action 3. Notify Potentially Affected Downstream Residents in Town of Lenox
Police department personnel will contact the potentially affected downstream residents in the
Town of Lenox listed in Appendix D, and will issue appropriate instructions regarding
evacuation and temporary shelters.
Town of Lee Police Department
Once notified by the Facility Manager, the Town of Lee Police Department should initiate
the following actions to assist them in coordinating their efforts.
Action 1. Notify Town of Lee Fire Department
Designated Person:
Ron Driscoll Phone No: (413) 243-2100
Once notified, fire department personnel will assist police department personnel III
evacuating affected residents to safe places and providing necessary shelters and food.
Action 2. Notify Town of Lee Department of Public Works (DPW)
Designated Person:
Mike Towler Phone No: (413) 243-5526
Alternate Contact:
Mike Towler Phone No: (413) 243-2100
Once notified, Lee DPW personnel will place balTicades on roads leading to the inundated
areas.
Action 3. Notify Potentially Affected Downstream Residents in Town of Lee
Police department personnel will contact the potentially affected downstream residents in the
Town of Lee listed in Appendix D, and will issue appropriate instructions regarding
evacuation and temporaty shelters.
Updated August 2006 V-IS
Woods Pond Dam EAP Notification Flowcharts and Contact Numbers
Town of Stockbridge Police Department
Once notified by the Facility Manager, the Town of Stockbridge Police Depatiment should
initiate the following actions to assist them in coordinating their efforts.
Actionl. Notify Town of Stockbridge Fire Department
Designated Person:
Louis Peyron Phone No: (413) 243-3242
Once noti fied, fire depatiment personnel will assist police department personnel m
evacuating. affected residents to safe places and providing necessmy shelters and food.
Action 2. Notify Town of Stockbridge Highway Department
Designated Person:
Clint Schneyer Phone No: (413) 298-5506
Once notified, Stockbridge highway department personnel will place barricades on roads leading to the inundated areas.
Action 3. Notify Potentially Affected Downstream Residents in Town of Stockbridge
Police department personnel will contact the potentially affected downstream residents in the
Town of Stockbridge listed in Appendix D, and will issue appropriate insttuctions regarding
evacuation and temporary shelters.
Updated August 2006 V-16
Woods Pond Dam EAP General Responsibilities Under The EAP
VI. GENERAL RESPONSIBILITIES UNDER THE EAP
Failure of Woods Pond Dam would present a potential hazard to downstream areas. Areas of
concern at the project include a few houses located near the gravel pit and sewage disposal
plant. Numerous downstream roads and houses, primarily in the flood plains and close to the
banks of the river, would be flooded. Refer to the inundation map, Exhibit 3.
Once an emergency condition is identified, it is important to the success of the EAP that
responsible personnel respond immediately. Specific responsibilities of the persons or
organizations for the maintenance and operation of the dam and implementing various phases
of the plan are discussed below.
A. General Electric Responsibilities
GE has a plant in Pittsfield, Massachusetts, located approximately 12 miles upstream from
the dam. A member ofGE's Corporate Environmental Programs (CEP) stafffi'om that plant,
or a contractor designated by GE, will perform a routine visit to the dam site and its appurtenant stlUctures at least monthly (or more frequently as wan-anted by weather, river
levels, or other conditions). This person will be the "Observer," as defined in Section V
(''Notification Flowchatis and Contact Numbers") in case of an occun'ence at the dam. The person will carry a two-way radio and/or telephone and/or pager, and will be properly
equipped to perform a watch during nighttime surveillance and severe weather.
In addition, the Facility Manager or the designated contractor wiII conduct an inspection of
the dam and its appurtenant sttuctures at least quarterly to identify any changes in site
conditions that might indicate a problem for the dam. (This inspection wiII be combined with
one of the monthly site visits described above.). GE will provide a repOli on each such
quatierly inspection to the Lead Administrative Trustee (LAT) designated under Paragraph 113 of the Consent Decree.
GE wiII also arrange for a licensed professional engineer to conduct an assessment, at least
once every two years, of the structural integrity of Woods Pond Dam, and to provide to GE a
repOli on that assessment and any recommendations of measures necessmy to maintain dam
integrity. GE will provide a copy of each such report to the LAT.
The GE Facility Manager will have the authority to declare an emergency at Woods Pond
Dam or to change the degree of severity of an existing occurrence.
Updated August 2006 VI-l
Woods Pond Dam EAP General Responsibilities Under The EAP
Upon receiving information of a threatening situation at Woods Pond Dam fi'om the Observer
(or fi'om other sources), it will be the primaty responsibility of the Facility Manager to direct
the designated person(s) of GE to proceed to the site. Included in this group will be one of
the persons who conduct routine inspections of the dam. It is the responsibility of this person
to know the signs of developing hazards such as those noted in Section IV, "Emergency
Detection, Evaluation and Classification," and to inform the Facility Manager immediately.
As a result of the site inspection, the Facility Manager will declare an emergency situation if
walTanted, and will designate the proper degree of severity. The Facility Manager will also
initiate all notification calls.
The Facility Manager will serve as the emergency coordinator for all local agencies and will
direct all mitigation effOlis at the dam site. The Facility Manager will also set up an appropriate central emergency headquarters fi'om which all emergency operations will be
directed.
In notifYing the contacts involved with the situation, the Facility Manager will briefly state (after having queried the Observer for the information):
I. Name of dam 2. Emergency condition
• Condition A - Failure is Imminent or Has Occurred, or • Condition B - Failure Situation is Developing
3. Severity of situation 4. Type of failure occurring or developing (e.g. overtopping, cracking or piping)
5. Time of observation, and time of failure, if occulTed and known, otherwise estimate
The Facility Manager will keep local authorities and news media infonned of changing
conditions at the dam site. However, the plan is not intended for the Facility Manager or his
designated person to assume the responsibility of governmental authotities duting an
emergency.
The Facility Manager is the EAP coordinator as described in Pati E of this section. The
Facility Manager will closely coordinate effolis with the staff at the dam site and local
agencies to serve as a communications hub for the duration of the emergency.
The officials who must be notified are shown in Section V ("Notification Flowcharts and
Contact Numbers") and on Exhibits 5 and 6 (Notification Flowcharts). As GE's top
Updated August 2006 VI-2
Woods Pond Dam EAP General Responsibilities Under The EAP
communications representative and day-to-day manager during the emergency, the Facility
Manager will be at the top of the command chain and will speak for GE and engineering
personnel at the site.
B. Responsibility for Notification
The Facility Manager is authorized to notifY authorities of the emergency, including the
police in the Towns of Lenox, Lee and Stockbridge, as well as the Berkshire County Sheriffs
Department, Emergency Management offices and other federal, state and local agencies listed
on the notification flowcharts (Exhibits 5 and 6). The Facility Manager will have the
authority to issue statements to the press concerning the situation at the dam.
The town police and fire departments will serve as the lead authorities during emergency
situations. Once notified of an emergency condition, they will be responsible for notifYing
potentially affected downstream residents (listed in Appendix D) and coordinating warning
and evacuation procedures with other authorities, including the emergency management offices and other county and town departments (fire, ambulance, and transportation).
Major responsibilities ofthese authOlities include:
• Issuing wa1l1ings and evacuating residential and commercial buildings as needed
• Controlling traffic and placement of bani cades on roads
• Coordinating with federal and state agencies
• Coordinating utility services
• Setting up health centers
• Informing the public through radio and television media
• Providing shelter for evacuated people
• Maintaining law and order
The chiefs of police for the towns of Lenox, Lee and Stockbridge will serve as local
coordinators for their municipalities. These local coordinators will keep in contact with the
Facility Manager and will be responsible for requesting support from other local, county or
state agencies as needed. The Facility Manager will be responsible for advising these local
coordinators of the need to warn andlor evacuate local residents depending upon the
conditions at the dam site.
Updated August 2006 VI-3
Woods Pond Dam EAP General Responsibilities Under The EAP
Local coordinators will have the authOlity to release that information necessaty to assure the
safety of tile public and to expedite an orderly evacuation when required. GE will coordinate
press releases conceming conditions at the dam with local coordinators. The local public
infOlmation centers will be responsible for infonning the public of the provisions of this plan
and coordinating public input.
C. Responsibility for Evacuation
Following notification by the Facility Manager, the waming and evacuation of residents, as
necessary, will be performed by the local police, fire and civil defense departments.
Residents will be moved to pre-designated temporaty shelters.
The Lenox and Lee DPWs and the Stockbridge Highway Depatlment will take the lead roles
in placing and manning barricades on the affected roads, with assistance from police, to
prevent motorists from enteling the inundated areas. A map showing potential flood limits is
attached as Exhibit 3.
D. Responsibility for Duration, Security, Termination, and Follow-Up
As noted above under GE's responsibilities, the Facility Manager will keep local autholities,
primarily through the police depatiments and county emergency management offices, advised
of conditions at the dam by phone or messenger.
The local authorities will be responsible for termination of the emergency response activities,
with the advice of the Facility Manager.
For any emergency situation, after completion of all notification responsibilities, all officials,
including GE personnel, will maintain a log, report, or tape recording of all notifications and
decisions made by their offices for the duration of the emergency. The reports should include
the following infOlmation:
• Subject: (what happened and name or title of incident)
• Time and date:
• Location: (where incident OCCUlTed)
• Summary of incident:
• Names and titles of persons involved:
Updated August 2006 VI-4
Woods Pond Dam EAP General Responsibilities Under The EAP
• Agencies notified: (e.g. sheriff, fire department, etc.)
• Status of incident: (completed and pending actions and decision)
E. EAP Coordinator Responsibility
The Facility Manager will be responsible for activities related to the EAP, including
reviewing and revising the plan, distributing copies of the flowchatis and plan, and
establishing training for personnel in charge of the dam (see Appendix C). Also, the Facility
Manager will be the contact should any questions arise about the plan.
Updated August 2006 VI-5
Woods Pond Dam EAP Preparedness
VII. PREPAREDNESS
Preparedness actions are taken to prevent a dam failure or to help reduce the effects of a dam
failure and to facilitate a response to emergencies.
A. Surveillance
An emergency situation may be detected by inspection of the dam or by observation of
reservoir levels.
SUlveiIlance of the dam wiII be made in accordance with the procedures described in Section
VI.A (General Responsibilities under the EAP - General Electric Responsibility). If night
inspections are made, the inspector should be accompanied by a second individual, and they
wiII carry flashlights and a two-way radio (walkie-talkie) or cellular phone to communicate.
Any observance of a failure or potential failure situation will be recorded and action shall be
taken immediately. Such situations are given in Section IV ("Emergency Detection,
Evaluation, and Classification").
Based on experience, a breach could fully develop in an hour or less after breach initiation.
The flood wave could reach the downstream residences in a few minutes. Therefore,
readiness for quick implementation of the EAP is impOliant.
B. Response During Periods of Darkness
Once an emergency situation is detected, notification procedures during periods of darkness
will be the same as during daylight hours. Home phone numbers are provided on the
notification flowchmis to facilitate contact during non-business hours.
For any response actions taken during periods of darkness, at least two individuals should be
present, and they will cany flashlights and a two-way radio (walkie-talkie) or cellular phone
to communicate.
Due to the availability ofphones and two-way radios, no special procedure wiII be needed for
contacting people on the appropriate flowchart.
Updated August 2006 VlI-l
Woods Pond Dam EAP Preparedness
C. Access to Site
Access to dam site will be by car and foot.
D. Response During Weekends and Holidays
Once an emergency situation is detected, notification procedures during weekends and
holidays will be the same as during weekdays. Home telephone numbers provided on the
notification flowcharts will be used during weekends and holidays. Notification response
time during weekends and holidays is expected to be similar to response times for
emergencies occurring during weekdays.
E. Response During Periods of Adverse Weather
During a severe stom1, some roads may be under water that would be dry during fair weather conditions. Consequently, emergency-response vehicles may have to bypass roads that are
under water in order to get to the dam or affected areas.
Response during adverse weather (a storm) following observation of an emergency condition,
comprising notifications and waming to downstream areas, is expected to take more time
than under normal conditions.
F. Availability and Use of Alternative Communication Systems
Telephones will be the main system of communication on and off the dam site. Also, two
way radios (walkie-talkies) will be available for site communication.
If the above methods fail, communications on-site and with emergency agencies in towns of
Lenox, Lee and Stockbridge will proceed by messenger.
G. Emergency Supplies and Resources
GE will be responsible for emergency supplies and resources for on-site use. GE will rely on
its designated contractor to assist in providing such supplies and resources, as described
below.
Updated August 2006 VII-2
Woods Pond Dam EAP Preparedness
GE and its designated contractor will provide men and equipment for emergency repair of the
dam. GE's designated contractors and a list of the equipment they are responsible for
providing, are listed in Appendix E. Fill, comprised of earth and rock, would be obtained
fi-om available borrow areas. However, due to possibly rapid development of a breach and
consequently a ve1y Sh011 warning time, emergency repair of a dam will not be relied on as a
preventative or control action.
Updated August 2006 VII-3
EXIIII3IT 1
\ - ." 'I ,,-.- \ . , ' r I " I I \ k' " If;,J' r -')(./ I \
1-, Tf I I h' I I I,i I (, ( \ ' '
.~ I, t.:
l'"\t'- I:.;, "-('II " ,1,,1
I . ,./
I
"
"
., ~. •"
I OCA TION iV1l\P
//t.-LII.. ,r.'.r- - [X llII lrr \
---------SITE ACCESS (SEE NOTE 2)
z
CRYSTAl STREET
HOUSATONIC RAILROAD
E25,000
--------------,r-------
BUILDING
(
.j
I I
I~
RACEW Y STOP LOG SLUICE STRUCTURE
"0,.<.IS",/:
O~/C'
BUILOING L_--f--,----::
lily!"ty
WEST IRIGHTJ ABUTMENT NON'OVERFLOW GRAVITY DAM
NORMAL TAILWATER E1.9423
OVERFLOW SPILLWAY
././
UPSTREAM RACEWAY .... / EI.I8ANKMEN: ...... • .... • _,/'
LOCKED ACCESS GATE
BERM
/
·..... .!.Oit'"
~ABANDONED DAM SUBMERGED (TIDAl.! n. 946)
E25 00 ro~·.2J:Jt
I I I I I I I I I I
<>l I I I I I I I I I I
BUILDING
iI
ILL POND :
1 1
tf '-I I I I I I I I I I I I
--".~
_____________ JII .... _------------ ---------------------------,-------------------
LSEE DRAWING C2
LEGEND:SITE PLAN -0 UTILITY POLE
EXISTING RAILROAD TRAC!<S
REFERENCE DRAWINGS: WORK THIS DRAWING WITH 1349SA*C2
NOTES: I, DETAILS OF WORK PERFORMED BY COUTRACTOR ARE
SHOWN ON DRAWING 1349SA-C2. 2. ACCESS TO SITE VIA CRYSTAL STREET FROM THE WEST
ANO VALLEY ROAD FROM THE EAST,
3. ALL ElEVATiONS ARE BASED ON NATiONAL GEODETIC VERTICAL DATUM (NGVO) OF 1929.
4, RECORD DRAWINGS WERE PREPARED BASED ON FJELD OBSERVATIONS MADE ON NOvEMBER 29. 2005 ANO ARE APPROXIMATE.
61l1lOt.
i/OVOt.
VllJOt.
lAP AJ4) 01101 hAN t.Fi>AT[
ZOOS STRlJCTtAAl HTECJlnyA SES II£NJ '"R£COflO ORAWtlCS
CO. "W
"W
"'. 6118/06
DAlE
20* UP ANO otu WNI,IAl i.POATE
n4Tlfi( Of RlV!SlON
". "
US
Cf/l:.O.
.. mo.
0 ,. l/2VOl
10/00/01
DATE
flECORO ORAJf1.!GS
1$$tJ[o rOIl SO/CONSTRUCTION
NATURE or MVI$K»4
",W
..W
"
..'" ..'" US .. '" US ..us
0'«0. APPO.
SCALE 0 50 100 FEET I, • I I ,I
,': 50'
GENERAL ELECTRIC COMPANY PITTSFIELD. MASSACHUSETTS
WOODS POND DAM
SITE PLAN
DWG.NO.
BM 121 ,&
A""";
RACEWAY EMBANKMENT CRES TEL. 952t
RAISED LOW SPOT ON EMBANKMENT CREST TO Elo 952.0 (SEE OWG. 1349SA-C])
-" '-. '-.
TA!LWATER E1.942t
"., ··""·"··960
CREST El. 954 ==,.}
'-. '-. '-.
....
OVERFLOW SPILLWAY
n. 94B.3±
REMOVED VEGETATION, CLEAN AND RESEAL JOINTS IN CONCRETE SLABS AT EAST ILEfT)
ABANDONED DAM SUBMERGED H/DAI.! El.
ABUTMENT •• ""
CABLE
..
REPAIRED DAMAGE TO MASONRY WAll (SEE DWG. 1349SA-C3)
. ....... "
.. ..........
NORMAL Elo 949t
LEGEND:
UTILITY POLE
ExiSTING RAILROAD TRACKS
B" 120,& BENCHMARK
NOTES: I. EMBANKMENT SLOPES ARE REGRAOEDD ON RIGHT SIDE OF
RACEWAY CHANNEL ALONG ENTIRE LENGTH OF CHANNEL AND FOR 130 FEET DOWNSTREAM OF RACEWAY CLOSURE STRUCTURE ON LEFT SIDE EMBANKMENT OF RACEWAY CHANNEL. SLOPES ARE RECRAOEOD TO NO STEEPER THAN I.SHIIV IN ACCORDANCE WllH THE SPEclF"!CATIONS.
2. ADDITIONAL DETAILS ARE SHOWN ON ORAWING 1349SA-C3.
3. RECORD DRAWINGS WERE PREPARED BASED ON FIELD OBSERVATIONS MADE ON NOVEMBER 29. 2005 AND ARE APPROXIMATE.
BENCH MARK No.
BM 119
BM 121
ELEVATION
956.22
953.26
DESCRIPTION
"PK" NAIL IN POlE, WEST SlOE OF GRAVEL ROAD 125'+ NORTH OF DAM. 25'+ SOUTH OF BASELINE STATION"HR-29, BM IS 1.4' ABOVE GROUND.
NAil IN POLE. WEST SIDE OF GRAVEL ROAD, 100'+ NORTH OF GATE HOUSE 10 FEEDER CANAL. 8M IS 1.2' ABOVE GROUND.
WOODS POND
'.
HEADWATER
SCALE 0 20 40 FEET L........L~-'!_~_J!
"z 20'
GENERAL ELECTRIC COMPANY PIlTSFIELO, MASSACHUSETTS
WOODS POND DAM
PLAN
~________________________________________________________tiU~~~~~~~~~~~~~L-~~~ ~ 1349SA-G2
--~--AlZ__
E1.9S2±
NORMAL POOL lEl.949)
\l
E1.94B.3± WOODS POND RESERVOIR NORMAL POOL (Elo 949)
'\ REMOVED "H')U'to~ REGRADE EXISTING GROUTED RIPRAP TO REMAIN \
-_'2'<
MASONRY WALL 116" THICK) TIEl.95tH L..c
EXISTING RIPRAP
=--------- ---------------~ ___~APPROXIMATE NORMAL ~ "'-- - - WATER LINE El,949t
GROUTEO RIPRAP REMOVED
EXISTING GROUTED RIPRAP
~ EXISTING .. ~ MISC. FILl----· .
REMOVED EXISTING MASONRY
EXISTING CONCRETE RETAINING WAll IT/El.955±)
NOTES: I. RECORD DRAWINGS WERE PREPAREO BASEO ON flElO
OBSERVATIONS MADE ON NOVEMBER 29, 2005 AND ARE APPROXIMATE,
SCALE 0 10 20 FEET 'II!!' .. ,,!
J" = 10'
GENERAL ELECTRIC COMPANY PITISFIELD, MASSACHUSETTS
WOODS POND DAM
PLAN AND SECTION UPSTREAM RACEWAY
EMBANKMENT
WAll AND CONCRETE CAP DOWN TO El.947,5t AND REPLACEO MASONRY TO n. 949
C C SCALE 0 <I FEET
L'L'''-'~'--',
IN= ''-D'
LARGE TREES AND BRUSH UP TO 30" DlAM. REMOVED 6' TO 10' WIDEIN AREAS OF NEW RJPRAP.---------~_
LARGE TREES AND BRUSH UPRACEWAY CHANNEL NORMAL , TO 30" OIAM. REMOVED ALONGWATER EL. 946± ENTIRE EMBANKMENT10
VARIE~',,,, ',;~,~~~~~~~N~O~.~"~Al~T~A~ll~W~A~T=:ERSl fl, 942r
-~ .ANOOM FILL ~ ',,~~~~~~~G~R~OU~N~0~El~.-9~'~0~. NEW RIPRAP AND BEDDING MATERIAL ALONG ENTIRE SLOPE ISEE NOTE 2)
TYPICAL SECTION A - A RACEWAY CHANNEL AND RACEWAY EMBANKMENT MODIFICATIONS
SCALE 0 4 fEET NOTES:I" • I I
I. EXISTING RIPRAP ANO BEDDING MATERIAL EXTENDS PARTIALLY UPSLOPE.
\ 2. RIPRAP AND BEDDING MATERIAL ALONG RACEWAY CHANNEL"
EMBANKMENT TO BRING SLOPES TO MINIMUM 1.5HJlV. LEFT EMBANKMENT IS REGRADEO fOR 130 FEET DOWNSTREAM or RACEWAY CLOSURE STRUCTURE. RIGHT EMBANKMENT IS REGRADED ALONG THE ENTIRE LENGTH Of THE CHANNEL. GEOTEXTILE PLACED ON RIGHT EMBANKMENT ON PREPARED SURfACE BELOW RIPRAP FOR A LENGTH OF 100 FEET FROM SOUTHERN END.
3. RECORD ORAWINGS WERE PREPARED BASED ON FJELD OBSERVATIONS92'-6" MADE ON NOVEMBER 29. 2005 AND ARE APPRoxiMATE.
r ~ B
L w ~
g NORMAL HEADWATER EL. 949* L
PLAN OF JOINTS IN EAST (LEFT) ABUTMENT OF RACEWAY CLOSURE STRUCTURE
SCALE 0 JO FEET '1'"I"p'
I' = 10'
GENERAL ELECTRIC COMPANY CONSTRUCTION pmSFIELD, MASSACHUSETTSJOINT
ELEVATION UPSTREAM MASONRY
SCALE 0 2 FEET I " ,!B - B Yl' : 1'-0'
SCALEr "=10'-0'
..co. " "',. APPO,"
WALL WOODS POND DAM
SECTIONS AND DETAILS 612"06
61()V06
UP 1.110 OUI PLAt.! uPDATE
Ws~lft~T'i%~rT£GRHr
LRU
til!'!
kJI
III
Iff
108'
1112/06 R[tORn OAAINeS lRU lIS I.If
MWH CHICAGO. illINOIS OWG.NO. 1349SA-C3
, " '"
B/ll/02
IO/~/OJ
DATE
/: 1."6"
.".~. "
", .
16'-6"
: .r CONTROL V JO[NT~
16'-6"
CONSTRUCTION JOINT~ B
-.J
..... STOP lOGBAY
~~"~:':~~:"--~""~'~":~'~~'~':'--~~l
EXHIBIT 3
r .~ : ? ~ '"
"
. .
.:r-,
. '. X ;,0-C·~O
"... ~ .;\ ~ '!
Cl ~ , .... ) . / . . ..j
1 . : :: : :. ;::
I '
/
I' )'
r.
. . ~
-.:;-:==--?-.."",.J~:"'--.,..,. =::::_ _ _ f I ' .
, I ,', ,
I t I
I ( I , '
J/
f 1 ,
/
I
~
f
, ~-
" ",<1
0
I I
/,I
(
• /IUAfI OW 1/
. /
'; It::: Q
- .
--, -r;--
v ~ ;"
\._- '--_--:
" :,. ~
" ,. I
PO~NT1Al FLOOD UMITS VIln;t IN STREAM BANKS
•P. /,- .-, , " - - . -~ ...... ...-- -----.r-"
~
...L __ _
LEGEND:
GENERAL ELECTRIC COMPANY flOOD llIJITS. fAILURE UNDER flOOD COflOlTIOtl
i PlTISFIELD, MASSACHUSETIS
fLOOD 1I1,1 1T S. fAILURE Ut:OER SUlun DAY Cor,'O ITIOt/ WOODS POND ON.i
POTENTIAL FLOOD LIMITS 3 ~ ~ l OO6 ElP AAO o.u Wll.l~ L LPtl4![ LI<V V I Id
6121106 [AP A~ 0& 11 P\.A~ LPOAl( l RI.I UI Wf ~ L__________________________________________________________________~~-Vf·~·OAl£'a~~~~~~~~NAT~( or A[ V;ilO/i (H.l.O. ~~~~CH ICAGO, = ~ ' '~DJ; ~'E"[~~~~[w';. til W'PO. ILlIU Q1S SHEET 1 OF 2 ~
.. --~)' ,
s T
R 1 D
I
<"' ·f :iST. , t
~ - ~~ . , I
" r I ~, , ' (j ' , I,. / · ~
0
~ I ~~
.. / ~ , I ~ !i •~ ~
• l ~ ,
•~ ~• i s s
'-'
~ 1 10\ ~I
I 1· , C) .,<"d!I 'oJ. 'i~ Drnd ,
r :;:=' I I,
I... !
I J
, ~
r, ,
;0 a a o
~ ~
a a a
r m G) m 2 <:l
<
E
" ~ 0
~ ~ ~ ~
'"
'"
o 0
.fOi\i'.Sr-~, : i .
I ,I
n
n• " ? ~
" ~ 52 ~
a o · n ~ ~~
~
rJ> :I: m "l '" 0
" '"
~ 3: :! ::t
" 0 -i m
~ §» 0 r ~
-n ~ rz 0 ° g ~ C s: ::j en
G) m
.,,2_m iB~:o r i"mPhi
~~ 00
:I: c O '"030;:: ~ ~
z -<
m X I m ::j
'"
EXHIBITNOTIFICATION F' ";HART CONDITIO.. . .
FAILURE IS IMMINENT OR HAS OCCURRED I DESCRIPTION OF CONDITIONS: I, Failure is imminent or has occurred (Condition A) corresponds to situations where a dam failure either has occurred. is occurred, or obviously is just about to occur. i
! i
COMMUNICATION MESSAGE: "
The General Electric Company has declared an emergency due to significant problems at the Woods Pond Dam on the Housatonic River. Dam failure either has i
occurred, is occurred, or obviously is just about to occur. Local authorities are to initiate contacts per this Notification Flowchart that a potential failure situation may exists. Contacts should be on alert for a second notification message. \
I OBSERVER
1 I•
HOUSATONIC RAILROAD CO. MASS OCR Matt Boardman(617) 626-4927 (860) 829-0850r ,IMEMA(617) 828-1649
----I
GENERAL ELECTRIC COMPANY
Primary: Kevin Mooney. Facility Manager Worle (413) 448-5910 Home: (413) 447-9362 Cell No: (413) 441-4610
Secondary: John Levesque, Altemate Facility Manager Work: (413) 448-5914 Home: (413) 743-3245 Cell No: (413) 441-4786
11413) 323-6306 Ext. 17, Ext. 12Emergency: Plant Protect'lon 24~Hour
(413) 448-,7550 I'- I'-
CD ® ,
~ CD C0 C0 CD 0 CD CD 0), Ir Ir Ir
,® Ir I
GE RESPONSE BERKSHIRE LENOX POLICE I I LEE POLICE l STOCKBRIDGE MASS DEP ,I MASS STATE 1. U.S. EPA CONTRACTORS COUNTY (413) 637-2346 (41;; 243-0678 POLICE 11888) 304-1133 POLICE Susan Svirsky
SHERIFF i413 499-7357 i413 243-2100 ;;13) 298-5520 (RT20-LEE) (617) 918-1434 Thomas R. Garrity COMMUNICATIONS 413 449-7357 (413) 243-0600 Altemate: LB Corporation CENTER (413) 587-5517 EPA New England (413) 243-1072 (413) 442-0512
1. LEE FIRE DEPT~ Emergency Response
(413) 441-9317 (413) 446-4559 1413) 243-2100 ~r' STOCKBRIDGE FIRE DEPT 1 (617) 918-1260
Keith Haag 1. LENOX FIRE 14131298-3242
DEPT 2. MASS OEP
Maxymillian Tech. +- Susan Steenstrup (413) 441-3379 (413) 637-2347 . LEE DPW r- w· STOCKBRIDGE HIGHWAY DEPT I (413)743-0197 (413) 499-7357 i:1~l243-5526 (413) 298-5506
(413) 755-2264
413 243-2100 Altemate:
2. LENOX DPW Anna Symington
i;1;l637-5525 +- (413) 755-2220
413 637-5520 F' DOWNSTREAM ~ ~. DOWNSTREAM 1
RESIDENTS RESIDENTS 3. CT DEP
3. DOWNSTREAM !+-Oil & Chemical Response
Division RESIDENTS 186-0) 424-3338
--------,r- --..-~ ~~-- -~-
EXHIBITNOTIFICATION F .CHART
CONDITION B POTENTIAL FAILURE SITUATION IS DEVELOPING
DESCRIPTION OF CONDITIONS: Potential failure situation is developing (Condition 8) corresponds to situations where a dam failure may develop, but preplanned actions may prevent or mitigate
failure.
COMMUNICATION MESSAGE: The General Electric Company has declared an alert due to Significant problems at the Woods Pond Dam on the Housatonic River. Dam failure may develop, but preplanned actions may prevent or mitigate failure. Local authorities are to be advised per this Notification Flowchart that a potential failure situation may exists. Contacts should be on alert for a second notification message.
I OBSERVER
.. GENERAL ELECTRIC COMPANY
Primary: Kev'ln Mooney, Faciflty Manager Work: (413) 448-5910 Home: (413) 447-9362 Cell No: (413) 441-4610
Secondary: John Levesque, Alternate Facility Manager HOUSATONIC Work: (413) 448-5914 RAILROAD CO.MASS OCRHome: (413) 743~3245 Matt Boardman Cell No: (413) 441-4786 i~';( 626-4927
CD
Keith Hoag
I I I MEMA l I (860) 829-0850617 828-1649 114131323-6306 Emergency: Plant p~~t~;on 24-Hour 'I"
Ext 17, Ext 12
413 448,7550
CD CD ®~ 0) CD 0) 0) CD
r CD ®.. ,.. GE RESPONSE BERKSHIRE LENOX POLICE \ \ LEE POLICE \ STOCKBRIDGE MASS DEP -, MASS STATE NOTIFY AS APPROPRIATE CONTRACTORS COUNTY (413) 637-2346 (413) 243-0678 POLICE (8881304-1133 POLICE FOR CONDITION B
SHERIFF i413) 499-7357 i413) 243-2100 (413) 298-5520 (RT20- LEE) ,. U.S. EPA Thomas R. Garrity COMMUNICATIONS i413 449-7357 i;'~( 243-{)600 Susan Svirsky LB Corporation CENTER 413 587-5517 (617) 918-1434 (413) 243-1072 (413) 442-0512
1. (;Ei)FIRE DEPT~ Alternate:
(413)441-9317 i 413) 445-4559 413 243-2100 [-+[1. ~T~~KBRIDGE FIRE DEPT I EPA New England
1. LENOX FIRE 413 298-3242 Emergency Response
Maxymillian Tech. DEPT +-
(617) 918-1260
(413) 441-3379 (413) 637-2347 . LEEDPW r- H'STOCKBRIDGE HIGHWAY 2. MASS DEP (413') 743-0197 (413\ 499-7357 1;";( 243-5526 DEPT Susan Steenstrup
413 243-2100 (413) 298-5506 (413) 755-2264 . LENOXDPW Alternate:1:";; 637-5525 +- rDOWNSTREAM ~
L.r' DOWNSTREAM' Anna Symington 413 637-5520 RESIDENTS (413) 755-2220
RESIDENTS 3. CT DEP3. DOWNSTREAM +-RESIDENTS Oil & Chemical Response
(86~)~~~~3338
I
I
Woods Pond Dam EAP AppendixB
APPENDIXB
INVESTIGATION OF POTENTIAL FLOOD LIMITS
Areas and streams downstream from Woods Pond Dam (Valley Mill Dam) that would most
likely be inundated in case of a failure of the dam have been identified.
A dam break study was not perfonned for Woods Pond Dam because it was not needed as per
requirements of the DCR. The stream affected due to a failure would be the Housatonic
River. There would be some backwater effect on small hibutaries joining the Housatonic
River (fi'om upstream to downstream: a small urmamed stream, Washington Mountain Brook, Codding Brook, small unnamed stream, Goose Pond Brook and Hop Brook). Further
downstream, the backwater effect on the tributaries might not be significant. Exhibit 3 shows
a portion of the Housatonic River and hibutaries downstream fium the dam.
Although the DCR does not require a dam failure inundation map for "significant" hazard
(Class II) dams, the identification of roads and residences likely to be affected due to a failure of Woods Pond Dam was considered necessary for warning purposes. This required some
approximation of inundation boundaries along the Housatonic River. To draw these
inundation boundaries, guidance was obtained from two previous reports. First was the dam
break analysis made by U.S. Army Corps of Engineers, Omaha District (COE), presented in
the Woods Pond Dam Phase 1 Inspection Report, Lee and Lenox, Massachusetts, September
1987. The second report was the Flood Insurance Study for the town of Lee, Massachusetts,
Berkshire County, Community No 250028, December 1981 by the Federal Emergency
Management Agency (FEMA).
A hypothetical failure of Woods Pond Dam could occur either on a sunny day or during a
flood. For failure under the sunny day condition, COE assumed the failure to occur at a
reservoir elevation of 952.7 ft, 4.4 ft above the spillway crest. Failure under this condition
resulted in a maximum outflow of about 11,200 cfs and a water surface elevation of about
948.2 feet at a distance of 0.5 mile downstream from the dam. The FEMA study indicated a
100-year flood of about 11,700 cfs and a 500-year flood of about 16,300 cfs.
The water surface elevations computed by FEMA for the 100-year flood in the river reach
immediately downstream of the dam confilID the water surface elevation of 948.2 feet
estimated by COE. Further downstream, the dam break flood wave will attenuate resulting in
water surface elevations lower than the elevations based on a steady state flow of 11,200 cfs.
Updated August 2006 B-1
Woods Pond Dam EAP Appendix B
However, for a conservative estimate of the inundation limits under a sunny day failure, the
water surface elevations computed by FEMA conesponding to a flow of 11,700 cfs were
used. The inundation limits are shown on Exhibit 3 by a solid line.
Inundation downstream fi'om the dam during the spillway design flood or a flood
approaching the probable maximum flood (PMF) would be extensive compared to the solid
line shown on Exhibit 3. Contribution to the inundation area due to failure of the dam during
a flood would not be significant because of the small storage behind the dam at the spillway
crest elevation, only 460 acre-feet (COE). Due to flood surcharge, the storage will be about
5,300 acre-feet at elevation 954.0, the top of the abutments.
Under flood conditions, the COE assumed the dam to fail when the old canal (raceway)
embankment would have been oveliopped by two feet. For failure under this condition, the
maximum outflow would be about 16,000 cfs. This flow is nearly same as the 500-year flood
estimated by FEMA. The inundation limits based on this flood and assuming a steady state
flow are shown as dotted lines on Exhibit 3. The limits are conservative because a flood wave due to dam failure would attenuate and the water surface elevations would be lower
than those shown.
Updated August 2006 B-2
Woods Pond Dam EAP Appendix C
APPENDIXC
PLANS FOR TRAINING, UPDATING, AND POSTING THE EAP
Training
The Facility Manager will conduct a bienoial in-house EAP training session. In that session,
the Facility Manager will present detailed instmctions, as noted earlier in the plan, to GE
personoel to follow during a dam failure emergency. The instmction will include description
of the chain of command. Technical personoel will be trained in problem detection and
evaluation and appropriate remedial measures. Training may include testing the training and
readiness of key personoel responsible for action during an emergency to determine that they
know the required procedures and actions.
A statement on the training session will be included in the anoual review of the EAP review if a training session occurred during the previous year. The statement will include date of
session, attendance list, and summary of topics discussed. The annual review of the EAP will
include any plan revisions indicated by the outcome of the training.
Updating
GE will anoually review and update the EAP in accordance with DCR Regulations. Updates will reflect changes in names, titles, and phone numbers of people with responsibility to take
action during a dam emergency.
Review will identifY any new developments or other changes upstream or downstream, which
might necessitate revising the EAP. Ifthere is such a change, GE will promptly infotm DCR,
determine in consultation with agencies and others whether revision is necessmy, and
distribute any resulting revisions.
All updates and revisions will be immediately furnished to DCR (three copies) and all other
EAP holders (two copies) to keep the plan workable. Revised pages will be marked
"Updated Month Year".
Updated August 2006 C-J
Woods Pond Dam EAP Appendix C
Posting and Distribution of the Notification Flowchart
A copy of the notification flowcharts will be posted prominently, near a phone or radio
transmitter, in the office of all personnel identified as callers on the chatis. Copies of this
EAP will be distributed to the personnel for office and home posting as given in the
following table:
WOODS POND DAM
EMERGENCY ACTION PLAN
DISTRIBUTION LIST
1. Massachusetts Depatiment of Conservation and Recreation, Division of State Parks and Recreation - Office of Dam Safety
2. Massachusetts Emergency Management Agency
3. GE Facility Manager
4. GE Alternate Facility Manager
5. GE's Designated Contractors
6. Berkshire County Communications Center
7. Town of Lenox Police Department
8. Town of Lenox Fire Department
9. Town of Lenox DPW
10. Town of Lee Police Department
11. Town of Lee Fire Department
12. Town of Lee DPW
13. Town ofStockbridge Police Department
14. Town of Stockbridge Fire Department
15. Town of Stockbridge Highway Department
16. Massachusetts State Police
17. Massachusetts Department of Environmental Protection
18. U.S. Environmental Protection Agency
19. Connecticut Department of Environmental Protection
20. Housatonic Railroad Company
Updated August 2006 C-2
Woods Pond Dam EAP Appendix C
WOODS POND DAM
EMERGENCY ACTION PLAN
DISTRIBUTION LIST
I) MA Depmiment of Conservation and Recreation Division of State Parks and Recreation Michael Misslin John Augustus Hall 180 Beaman Street West Boylston, MA 01583
2) Massachusetts Emergency Management Agency: Patlick Camevale, Director Massachusetts Emergency Management Agency Area III PO Box 1190 Belchertown, MA 0 I 007 Tel: (413) 323-6306
3) GE Facility Manager: Kevin Mooney General Electric Company 159 Plastics Avenue Pittsfield, MA 01201 Tel: (413) 448-5910
4) GE Altemate Facility Manager: John Levesque 159 Plastics Avenue Pittsfield, MA 0120 I Tel: (413) 448-5914
5) GE's Designated Contractors: Keith Hoag Maxyrnillian Technologies Inc. 1801 East Street Pittsfield, MA 01201 Tel: (413) 441-3379
Thomas R. Gml'ity LB Corporation 95 Marble Street Lee, MA 01238 Tel: (413) 243-1072
Updated August 2006 C-3
Woods Pond Dam EAP Appendix C
6) Berkshire County Sheriff Communications Center: Desk OfficerlDispatcher 76 East Street Pittsfield, MA 01201 Tel: (413) 442-0512
7) Town of Lenox Police Depmiment: Stephen O'Brien, Chief Town of Lenox Police Department 6 Walker Street Lenox, MA 01240 Tel: (413) 637-2346
8) Town of Lenox Fire Department: Dan Clifford, Chief Town of Lenox Fire Depaliment 6 Walker Street Lenox, MA 01240 Tel: (413) 637-2345
9) Town of Lenox Department of Public Works: Jeff Vincent Town of Lenox Department of Public Works 275 Main Street Lenox, MA 01240 Tel: (413) 637-5525
10) Town of Lee Police Department: Ronald Glidden, Chief Town of Lee Police Department 32 Main Street Lee, MA 01238 Tel: (413) 243-2100
11) Town of Lee Fire Depmiment: Ron Driscoll Town of Lee Fire Department 45 Railroad Street Lee, MA 01238 Tel: (413) 243-2100
Updated August 2006 C-4
Woods Pond Dam EAP AppendixC
12) Town of Lee Department of Public Works: Mike Towler Town of Lee Department of Public Works 32 Main Street Lee, MA 01238 Tel: (413) 243-5526
13) Town of Stockbridge Police Department: Richard B. Wilcox, Chief Town of Stockbridge Police Department 6 Main Street Stockbridge, MA 01262 Tel: (413) 298-5520
14) Town of Stockbridge Fire Depatiment: Louis Peyron, Chief Town of Stockbridge Fire Department P.O. Box417 Stockbridge, MA 01262 Tel: (413) 298-3242
15) Town of Stockbridge Highway Department Clint Schneyer Town of Stockbridge Highway DepaJiment Route 102 Stockbridge, MA 01262 Tel: (413) 298-5506
16) Massachusetts State Police: Desk Officer Massachusetts State Police Route 20 Lee, MA Tel: (413) 243-0600
17) Massachusetts Department of Environmental Protection: Susan Steenstmp Department of Environmental Protection 436 Dwight Street Springfield, MA 01103 Tel: (413) 755-2264
Updated August 2006 C-5
Appendix C Woods Pond Dam EAP
18) U.S. Environmental Protection Agency: Susan Svirsky U.S. Environmental Protection Agency One Congress Street, Suite 1100 Boston, MA 02214-2023 Tel: (617) 918-1434
19) Connecticut Department of Enviromnental Protection Susan Peterson Department ofEnviromnental Protection 79 Elm Street Hartford, CT 06106 Tel: (860) 424-3854
20) Housatonic Railroad Company Matt Boardman 1 Railroad Street Canaan, CT 06018 (860) 824-0850, Ext. 17
Updated August 2006 C-6
l J
"1 WOODS POND DAM
J ] STRUCTURAL INTEGRITY
ASSESSMENT TRAINING ]
J ]
1
.-,. ,
"
I .,
Pl'/wJeged"nd Conlldenll"J 2(1(1$
Prepared for: Prepared by:
• ((I}) MWH PIHsfleld, MA
]/ Woods Pond Dam Structural Integrity Assessment Training
]/ CONTENTS
] Section Page
1 A. INTRODUCTION .................................................................................................. 1
B. STRUCTURAL INTEGRITY ASSESSMENTS ..................................................... 2 1 INSPECTION OF EARTH EMBANKMENT STRUCTURES ........................................................... 7
INSPECTION OF CONCRETE AND MASONRY STRUCTURES ................................................ 13
) INSPECTION OF STOPLOG STRUCTURES AND CHANNELS ................................................. 16
C. INSTRUMENTATION ......................................................................................... 17
J D. REPORTING PROCEDURES AND DOCUMENTATION ................................... 21
E. MONTHLY AND QUARTERLY INSPECTION FORMS ...................................... 22
I F. PHOTOGRAPHS OF FEATURES TO BE INSPECTED .................................... 34
I
®)MWH
GENERAL ELECTRIC COMPANY Pittsfield, Massachusetts
EMERGENCY ACTION PLAN
for
WOODS POND DAM
Housatonic River Lee/Lenox, Massachusetts
Updated August 2006
Ol'iginally compiled March 4, 2003 by:
MWH Chicago, Illinois
Woods Pond Dam EAP Table of Contents
WOODS POND DAM EMERGENCY ACTION PLAN
TABLE OF CONTENTS
Section
I. Statement of Purpose
II. Project Description
A. Background
B. Project Features
III. Potential Flood Limits
IV. Emergency Detection, Evaluation, and Classification
A. Condition A - Failure Is Imminent or Has OccUlTed
B. Condition B - Potential Failure Situation Is Developing
V. Notification Flowcharts and Contact Numbers
A. Condition A - Failure Is Imminent or Has Occun'ed
B. Condition B - Potential Failure Situation Is Developing
VI. General Responsibilities Under the EAP
A. General Electric Responsibilities
B. Responsibility for Notification
C. Responsibility for Evacuation
D. Responsibility for Duration, Security, Telmination and Follow-Up
E. EAP Coordinator Responsibility
VII. Preparedness
A. Surveillance
B. Response During Periods of Darkness
C. Access to Site
D. Response During Weekends and Holidays
E. Response During Periods ofAdverse Weather
F. Availability and Use of Altemate Communication Systems
G. Emergency Supplies and Resources
Updated August 2006
Woods Pond Dam EAP Table of Contents
TABLE OF CONTENTS (cont'd)
Exhibits
1 Project Location Map
2 General Plan
3 Potential Flood Limits
4 Possible Emergency OccUlTences
5 Notification Flowchart, Condition A - Failure Is Imminent or Has OccUlTed
6 Notification Flowchart, Condition B - Potential Failure Situation is Developing
Appendices
A Woods Pond Dam - Replacement Overflow Spillway Drawings
B Investigation of Potential Flood Limits
C Plans for Training, Updating, and Posting the EAP D List ofPotentially Affected Downstream Residents
E GE Designated Contractors and List of Emergency Supplies and Resources
F Approval of the EAP
G EAP Review CommentslRecommendations (Local and State Emergency Agencies and Local Emergency Coordinators)
Updated August 2006 ii
Woods Pond Dam EAP Statement of Purpose
I. STATEMENT OF PURPOSE
This Emergency Action Plan (EAP) has been prepared on behalf of the General Electric
Company (GE) for Woods Pond Dam, which is owned by GE. The purpose of this EAP is
to:
I. Define the responsibilities of various officials involved in emergency management;
2. Provide procedures designed to identifY, in a timely manner, unusual and unlikely
conditions which may endanger the stlUctural integtity of Woods Pond Dam;
3. IdentifY actions to take to mitigate an ongoing or developing situation; and
4. Provide procedures to notifY the appropriate emergency management officials, if possible, of impending or actual failure of the dam.
In accordance with the regulations of the Massachusetts Department of Conservation and
Recreation, Division of State Parks and Recreation (DCR) (fOlmerly known as the Environmental Management (DEM» Regulations (Chapter 302 CMR 10.06, November 4,
2005), Woods Pond Dam is designated as a "large" size dam with a "significant" hazard
(Class II) potential. This size classification is based on the storage capacity that occurs during the spillway design flood, while the hazard potential classification is based on ~he
presumption that failure of the dam may result in the loss of life and significant propelty
damage immediately downstream of the dam.
According to DCR Regulations (Chapter 302 CMR 10.11, November 2005), all dams classified as "high" hazard (Class I) shall have an EAP. If the Commissioner requires it, a
facility with a non-high hazard dam shall also provide an EAP. DCR requested that GE
prepare an EAP for Woods Pond Dam; GE prepared this EAP in response to that request and
as an exercise of good engineering judgment. The EAP conforms to the requirements for
EAPs outlined in Section 10.11 of the DCR Regulations. All EAPs are subject to approval
by the DCR. The dam owner shall submit a copy of the proposed EAP to the local and state
emergency agencies and all local emergency coordinators involved in the plan for review.
The owner shall inCOlJlOrate applicable recommendations received and provide the
documented recommendations in appendices to the final version of the EAP. Annually, the
owner shall review the EAP and update it as necessaty
Updated August 2006 1- I
Woods Pond Dam EAP Statement of Purpose
The EAP shall, at a minimum, contain the following:
1. The identification of equipment, manpower, and material available for
implementation of the Plan;
2. A notification procedure for infonning local emergency agencies;
3. A topographic map showing the stream which will be flooded; and
4. A procedure for waming nearby local residents if failure of the dam is imminent
and a listing of addresses and telephone numbers of downstream residents that
may be affected by failure ofthe dam.
As desClibed in Section IV, "Emergency Detection, Evaluation and Classification," two aleli
conditions have been adopted for Woods Pond Dam:
1. Condition A - Failure Is Imminent or Has Occurred, and
2. Condition B - Potential Failure Situation Is Developing
A notification flowchmt for each of these alert conditions is presented in this EAP.
Updated August 2006 1-2
Woods Pond Dam EAP Project Description
II. PROJECT DESCRIPTION
A. Backgl'ound
The original Woods Pond Dam was reportedly constructed around 1864 on the Housatonic
River near the towns of Lee and Lenox, Massachusetts, as shown on Exhibit 1. The original
structure consisted of a 9-foot-high rock-filled timber crib overflow dam with a 14-foot-high
eatihfill embankment parallel to the river challllel as its east (left) abutment (left and right
refer to the side of the river challllel when viewed looking in the downstream direction).
There are no design drawings or information available for any of the original project
structures. The original dam structure was replaced in 1989 with a new concrete overflow
spillway and new abutments of concrete and steel sheet pile. The emihfill (raceway)
embankment separates the main river challllel from the 30 to 50-foot-wide raceway challllel along the left bank of the river. The raceway challllel conveys flow to a small mill pond,
which at one time was a forebay for a water-powered mill that has since been retired. The
dam impounds the Woods Pond Reservoir, part of the Housatonic River Valley Wildlife
Management Area.
Prior to the 1989 rehabilitation, Woods Pond Dam was in a deteriorated condition. The
original project could not pass a flood greater than about the lO-year flood event without overtopping the eatihen raceway embankment. Oveliopping of the embankment could have
caused a breach of the embankment, resulting in the uncontrolled release of the reservoir
water and sediments that had settled to the bottom of the reservoir.
Beginning in 1979, studies and investigations were performed to assess the condition of the
dam and develop recommendations for repair and rehabilitation of the dam. In 1983, the
timber planking and heavy gage sheet metal on the main overflow dam were replaced with an
18-inch-thick reinforced concrete cap. After placement of the cap, a leak developed at the
east abutment masomy wall, presumably due to the cut-off of natural seepage through the
timber crib dam. The joints in the masomy wall were filled with mortar shortly after the
1983 construction, temporarily stopping the leakage, but contributing to pressure buildup
behind the wall, causing lateral movement of the wall.
In 1988, a plan was developed to rehabilitate the dam to provide a safer, more reliable project
structure. The rehabilitation was carded out in two stages. The first stage consisted of the
construction of a raceway closure structure with concrete stoplogs to diveli flow away fi'om
the raceway and mill pond. The purpose of the closure structure is to protect the raceway
Updated August 2006 I1-l
Woods Pond Dam EAP Project Description
embankment from overtopping and potential failure during high flows. The second stage
consisted of the construction of a replacement spillway and non-overflow gravity dam a short
distance downstream of the original spillway. A rockfill berm was also constmcted on the
west (right) bank of the river between the original spillway and new spillway, and the top
2.5 feet the original timber crib spillway was demolished. The original sluice gate stmcture
at the downstream end of the raceway embankment was rehabilitated in 1991. This stmcture
controls the water level in the Mill Pond.
Additional modifications to the project were perfOlmed in 2001 to address recommendations
made in the January 2001 Stmctural Integrity Assessment RepOlt, and in 2003 to address
recommendations made in the May 2003 Stmctural Integrity Assessment Report. The 2001
modifications included repair to deteriorated masonry at the raceway closure stmcture;
removal of trees and other vegetation along the raceway embankment; regrading of the
raceway channel slopes; and removal of the masonry wall and reworking of the riprap at the
upstream raceway embankment. The 2003 modifications included removal of trees and other vegetation and the placement of riprap along the river side of the raceway embankment.
Based on the stmctural integrity assessment inspection conducted subsequently in
November 2004, the dam, raceway closure stmcture, and riprap constmcted in 1989 are in good condition, and there was no indication of deterioration or distress to the spillway and
tailrace.
MWH conducted a visual inspection in November 2005 and made recommendations for
some minor physical modifications. GE is in the process of implementing these
recommendations. For details, refer to 2005 Stmctural Integlity Assessment Report by
MWH, dated Aplil 2006.
A general plan of the rehabilitated project is shown on Exhibit 2. Drawings for the 1989
rehabilitation are included in Appendix A for reference. The "General Design Report for
Woods Pond Dam Rehabilitation" for the 1989 rehabilitation was filed with the DCR and is
included in Appendix B ofthe March 1999 Woods Pond Dam Inspection Report.
B. Project Featm'es
The present dam consists of a 140-foot-Iong concrete overflow spillway, a concrete non
overflow gravity section at the west (right) abutment, and a concrete and steel sheetpile
raceway closure stmcture at the east (left) abutment, all constmcted since 1989. All the dam
structures are founded on bedrock. The dam has a maximum height of approximately 14 feet,
Updated August 2006 II-2
Woods Pond Dam EAP Project Description
with an ogee-shaped spillway with a crest elevation of 948.3 feet National Geodetic Vertical
Datum (NGVD). The west (right) abutment is a concrete gravity structure with a sloped
downstream face and a top elevation of 954.0 feet NGVD. The raceway closure structure
forms the east (left) abutment of the dam and has a top elevation of 954.0 feet NGVD. The
drawings for the dam and raceway closure structure are provided in Appendix A. The current
structure is completely independent of the original structure and does not rely on any of the
original structures for support.
The CutTent structures are founded on shallow bedrock, which is vertically bedded and is
generally fine grained, hard with vmiable medium to close joint spacing. This was
determined duting the 1988 geoteclmical investigation program which included soil borings
and water pressure testing of the rock. Details of the subsurface field investigation can be
found in the "General Design Report for Woods Pond Dam Rehabilitation" filed with the DCR in 1989 and included in the March 1999 Woods Pond Dam Inspection RepOit.
The raceway embankment upstream of the dam is emthen fill with riprap over the surface and
is no longer a water-retaining structure serving no dam safety function. Failure of this portion of the raceway embankment would have no impact on the safety or integrity of the
dam.
Downstream of the dam and raceway closure structure is an earthen embankment protected with riprap along the length of the channel. This embankment is located between the tailrace
of the current overflow spillway and the raceway channel. The embankment has a crest
width of about 8 to 10 feet. The water elevation in the raceway is a few feet higher than the
water elevation in the tailrace and river channel downstream of the dam.
Updated August 2006 II-3
Woods Pond Dam EAP Potential Flood Limits
III. POTENTIAL FLOOD LIMITS
Exhibit 3 shows a map of potential flood limits due to the failure of Woods Pond Dam under
"Sunny-day" and "Flood-day" conditions. Flood limits are for failure when the abutments
would be overtopped by two feet. "Sunny-day" means a fair-weather, non-rainy day. "Flood
day" means a rainy, non-fair-weather day. The tenn "day" includes nighttime. The potential
flood limits are plotted on Exhibit 3 to show the maximum inundation area due to dam failure
to the point downstream where the water would be contained within the banks of the river.
These limits were estimated based on the information and data provided in two reports
entitled:
1. "Woods Pond Dam, Phase I Inspection Report, Lee and Lenox, Massachusetts,
prepared for EPA Region 1, prepared by U.S. Anny Corps of Engineers, Omaha
District, September 1987,"
2. "Flood Insurance Study, Town of Lee, Massachusetts, Berkshire County by Federal
Emergency Management Agency, December 1, 1981."
Refer to Appendix B - Investigation of Potential Flood Limits - for additional infonnation.
Updated August 2006 III-I
Woods Pond Dam EAP Emergency Detection. Evaluation. and Classification
IV. EMERGENCY DETECTION, EVALUATION, AND CLASSIFICATION
This EAP has been prepared to aid GE personnel in the timely detection, evaluation, and
classification of an existing or potential emergency situation at the dam. The EAP provides
two classifications of dam failure emergency according to their severity and urgency:
Condition A - Failure is Imminent or Has OCCUlTed, and Condition B - Potential Failure
Situation Is Developing. The conditions or measures for detection and evaluation of an
existing or potential emergency are described below.
For purposes of this EAP, GE has designated a Facility Manager and an Alternate Facility
Manager (as specified in Section V). The Facility Manager shall have primary responsibility
for catTying out this Plan on behalf of GE. In the event that the Facility Manager is
unavailable, the Alternate Facility Manager shall be the point of contact and shall have all the
duties and powers of the Facility Manager as set forth in this Plan. In addition, GE has pre
selected contractors, also specified in Section V, to assist in emergency response under this
EAP.
A. Condition A - Failure is Imminent or Has Occurred
The following conditions may lead to the "Failure is Imminent or Has Occurred" emergency
situation. These conditions should not be considered inclusive of all conditions that might
occur:
• Rapidly developing sttuctural problems involving the spillway, raceway embankment,
abutments, and appUlienant structures. Some of the potential causes of developing
structural problems are listed on Exhibit 4.
The notification procedures of Section V, ''Notification Flowchatis and Contact Numbers"
and given on the flowchati for Condition A (Exhibit 5), should be invoked if any of the
situations listed on Exhibit 4 are observed. An imminent situation at the dam site will
probably manifest itself as an excessive increase in flow in the Housatonic River and/or an
unexpected drop or rise in water level in the reservoir, river channel, raceway channel or mill
pond.
When failure is observed, the Observer (as defined in Section V) shall inform the Facility
Manager. The Facility Manager shall decide the severity of the problem and invoke the
notification procedure if appropriate.
Updated August 2006 VJ-l
Woods Pond Dam EAP Emergency Detection, Evaluation, and Classification
The message from the Facility Manager to the persons identified on the flowchart for this
situation (Exhibit 5) will contain the following information:
• Name and title (GE position) ofthe person making the call,
• A statement that this is an emergency call, due to a reported failure or imminent
failure of Woods Pond Dam,
• A statement that the person receiving the message must initiate contacts as per the
flowchart for "Condition A - Failure is Imminent or Has OCCUlTed,"
• A statement that waming and evacuation should begin immediately,
D, Condition D - Potential Failure Situation is Developing
The conditions that may lead to the "Potential Failure Situation is Developing" emergency
situation are also listed on Exhibit 4. Upon confirming any of the situations listed on Exhibit
4, the notification procedures will be implemented by the Facility Manager. There will be
two messages fi'om the Facility Manager for this situation. The first message will contain the
following information:
• Name and title (GE position) of the person making the call.
• A statement that a potential failure situation is developing at Woods Pond Dam that
may lead to failure ofthe dam.
• A statement that the person receiving the message should put his or her contacts on
alert for a second notification message.
• A statement that emergency personnel should be ready for an evacuation process.
If failure of the dam becomes imminent, the second message fi'om the Facility Manager shall
be as given in this section under "Condition A - Failure Is Imminent or Has Occurred."
If the dam failure is avelied and the developing situation is mitigated, the emergency will be
called off via the same communication channels. In such an event, the message will contain
the following information:
• Name and title (GE position) of the person making the call.
• A statement that the potential failure sihJation at Woods Pond Dam has been averted,
and that the recipients' contacts should stand down from emergency alert.
Updated August 2006 VI-2
Woods Pond Dam EAP Notification Flowcharts and Contact Numbers
V. NOTIFICATION FLOWCHARTS AND CONTACT NUMBERS
The flowcharts shown in Exhibits 5 and 6 summarize who is to be notified and who is
responsible for notifYing individuals and organizations in the order designated for the
following emergency situations:
A. Failure Is Imminent or Has Occurred (Condition A): COiTesponds to situations where
a failure either has occUlTed, is occurring, or obviously is just about to occur. The
notification flowchart for Condition A is printed on red paper.
B. Potential Failure Situation is Developing (Condition B): COiTesponds to sihmtions
where a dam failure may develop, but preplanned actions may prevent or mitigate
failure. Generally, there is more time available under this condition than under Condition A to take preventative action and bring the situation under conh·ol. The
notification flowchart for Condition B is printed on yellow paper.
A copy of the flowcharts shall be prominently posted near the telephone or radio transmitter
of each person identified on the flowcharts as a caller. The key personnel of GE and police
depallments shall have copies in their offices and at homes (see Appendix C for EAP distribution).
Detailed infOimation supplementing the flowcharts is provided in Section N - Emergency
Detection, Evaluation, and Classification. The location of the dam, reservoir, and streams are described in the Section II - Project Description. Potential inundation limits are discussed in
Section III - Potential Flood Limits. In addition to the individuals and agencies listed as
contacts in Actions 1 through 8 for Condition A and Condition B, GE has additional
notification requirements under the Consent Decree for the GE-PittsfieldIHousatonic River
Site (the Consent Decree). The contacts for those notifications are listed in Action 9.
Paragraph 90 of the Consent Decree requires that notice be given "[i]n the event of any action
or occurrence during the perfOimance of the Work which causes or threatens a release of
Waste Material from the Site that constitutes an emergency situation or may present an
immediate threat to public health or welfare or the environment." The phrase "constitutes an
emergency situation or may present an immediate threat to public health or welfare or the
environment" is fil1lher defined to mean "an unforeseen combination of circumstances, or the
conditions resulting from such circumstances, not nOimally anticipated to occur as pall of the
Work, that require immediate action to avoid harm or an immediate threat of hann to human
health, welfare or the environment."
Updated August 2006 V-I
Woods Pond Dam EAP Notification Flowcharts and Contact Numbers
For Condition A, notification to the contacts listed in Action 10 is required. For Condition
B, the Facility Manager shall provide notification to the contacts listed in Action 10 as
appropriate, based on the requirements of Paragraph 90 of the Consent Decree quoted above.
Updated August 2006 V-2
Woods Pond Dam EAP Notification Flowcharts and Contact Numbers
A. Condition A - Failure Is Imminent 01' Has OcculTed
In the event that failure is imminent or has occUlTed at Woods Pond Dam, GE personnel shall
initiate the notification actions in accordance with the flowchart shown on Exhibit 5. The
positions and the sequence ofnotification for the flowcharts are explained below.
Observer
The Observer will be the GE employee or contractor who monitors the condition of the dam
and its appurtenant structures (as described in Section VLA). In the event of a tlu'eatening
situation at the dam site, the Observer shall immediately notifY the following GE contacts:
General Electric
Primary Contact:
Kevin Mooney, Facility Manager Phone No: (413) 448-5910
Home Phone: (413) 447-9362
Cell No: (413) 441-4610
Secondary Contact:
John Levesque, Alternate Facility Manager Phone No: (413) 48-5914
Home Phone: (413) 743-3245
Cell No: (413) 441-4786
Once aware of an imminent failure of the dam, the Facility Manager shall send a team to the
dam site and shall initiate the following required actions:
Action 1. Notify GE Response Contractor
The following contractors have been pre-selected by GE to assist in response actions under
this EAP:
LB Corporation
Designated Person:
Thomas R. Garrity Phone No: (413) 243-1072
LB Corporation Home Phone: (413) 243-1246
Cell No: (413) 441-9317
Updated August 2006 V-3
Woods Pond Dam EAP Notification Flowcharts and Contact Numbers
Altemate Contacts:
Thomas M. Garrity
LB Corporation
Steve Garrity
LB Corporation
Maxymillian Technologies
Designated Person:
Keith Hoag
Maxymillian Technologies Inc.
Altemate Contacts:
Perry Flood
Maxymillian Technologies Inc.
BlUce Rustemeyer
Maxymillian Technologies Inc.
Vem Palen
Maxymillian Technologies Inc.
Phone No: (413) 243-1072
Home Phone: (413) 243-1908
Cell No: (413) 441-9318
Phone No: (413) 243-1072
Home Phone: (413) 243-2505
Cell No: (413) 441-1412
Cell No: (413) 441-3379
Pager No: (413) 261-5034
Home Phone: (413) 743-0197
Cell No: (413) 441-3850
Pager No: (413) 261-5725
Home Phone: (413) 243-2789
Cell No: (413) 441-6291
Home Phone: (413) 634-5047
Cell No: (413) 441-4095
Pager No: (413) 292-8502
Home Phone: (413) 623-8343
Updated August 2006 V-4
Woods Pond Dam EAP Notification Flowcharts and Contact Numbers
Action 2. Notify Berl{shire County Sheriff Communication Center
Designated Person:
Desk Officer/Dispatcher Phone No: (413) 442-0512
Alternate Contact:
Desk OfficerlDispatcher Phone No: (413) 445-4559
(Berkshire County Sheriff Communication Center handles the 911 calls for Lenox and
Stockbridge. Calling the listed telephone numbers is equivalent to calling 911 in Lenox or
Stockbridge)
Action 3. Notify Town of Lenox Police Department
Designated Person:
Stephen E. O'Brien Phone No: (413) 637-2346
Alternate Contact:
Tony Salvatore Phone No: (413) 499-7357
Action 4. Notify Town of Lee Police Department
Designated Person:
Ronald Glidden Phone No: (413) 243-2100
Altemate Contact:
Desk Officer Phone No: (413) 243-0678
(Lee Police department handles the 911 calls for Lee. Calling the listed telephone numbers is
equivalent to calling 911 in Lee)
Action 5. Notify Town of Stockbridge Police Department
Designated Person:
Richard B. Wilcox Phone No: (413) 298-5520
Altemate Contact:
Desk Offi cer Phone No: (413) 298-5530
Updated August 2006 V-5
Woods Pond Dam EAP Notification Flowcharts and Contact Numbers
Action 6. Notify Massachusetts Department of Environmental Protection (DEP)
Designated Person:
,Spill Emergency Number (Toll Free) Phone No: (888) 304-1133
Action 7. Notify Massachusetts State Police (Rte. 20, Lee)
Designated Person:
Desk Officer Phone No: (413) 243-0600
Alte11late Contact: Troop B Duty Officer
Northampton, MA Phone No: (413) 587-5517
Action 8. Notify Department of Conservation and Recreation, Division of State Parks
and Recreation
Designated Person: William Salomma Phone No: (617) 626-1410
Action 9. Notify Massachusetts Emergency Management Agency
Designated Person: Patrick Call1evale, Director Phone No: (413) 323-6306
Action 10. Notify Regulatory Contacts under Consent Decree
(required for Condition A)
• U.S. Environmental Protection Agency:
Designated Person:
Susan Svirsky Phone No: (617) 918-1434
Alte11late Contact:
EPA New England Emergency
Response Section Phone No: (617) 918-1260
Updated August 2006 V-6
Woods Pond Dam EAP Notification Flowcharts and Contact Numbers
• Massachusetts Department of Environmental Protection:
Designated Person:
Susan Steenstrup Phone No: (413) 755-2264
Alternate Contact:
Anna Symington Phone No: (413) 755-2220
• Connecticut Department of Environmental Protection
Designated Contact:
Oil & Chemical Response Division Phone No: (860) 424-3338
Action 11. Notify Housatonic Railroad Company
Designated Person:
Matt Boardman Phone No: (860) 824-0850, Ext. 17
Alternate Contact:
Dispatcher Phone No: (860) 824-0850, Ext. 12
After contacting the above parties, the Facility Manager will continue to monitor the situation
and inform the agencies as needed. Once notified by the Facility Manager, the agencies will
coordinate emergency operations. The agencies will also maintain contact with the Facility
Manager.
Town of Lenox Police Department
Once notified by the Facility Manager, the Town of Lenox Police Department should initiate
the following actions to assist them in coordinating their effotts.
Action 1. Notify Town of Lenox Fire Department
Designated Person:
Dan Clifford Phone No: (413) 637-2347
Alternate Contact:
Dan Clifford Phone No: (413) 499-7357
Once notified, fire depmtment personnel will assist police depmtment personnel III
evacuating the residents to safe places and providing necessmy shelters and food.
Updated August 2006 V-7
Woods Pond Dam EAP Notification Flowcharts and Contact Numbers
Action 2. Notify Town of Lenox Department of Public Works (DPW)
Designated Person:
Jeff Vincent Phone No: (413) 637-5525
Altemate Contact:
R. Scott Jarvis Phone No: (413) 637-5520
Once notified, Lenox DPW personnel will place barricades on roads leading to the inundated
areas.
Action 3. Notify Potentially Affected Downstream Residents in Town of Lenox
Police depmiment personnel will contact the potentially affected downstream residents in the
Town of Lenox listed in Appendix D, and will issue appropriate instlUctions regarding
evacuation and temporary shelters.
Town of Lee Police Department
Once notified by the Facility Manager, the Town of Lee Police Department should initiate the
following actions to assist them in coordinating their efforts.
Action 1. Notify Town of Lee Fire Department
Designated Person:
Ron Driscoll Phone No: (413) 243-2100
Once notified, fire department personnel will assist police depmiment personnel III
evacuating affected residents to safe places and providing necessmy shelters and food.
Action 2. Notify Town of Lee Department of Public Works (DPW)
Designated Person:
Mike Towler Phone No: (413) 243-5526
Altemate Contact:
Mike Towler Phone No: (413) 243-2100
Once notified, Lee DPW personnel will place bmTicades on roads leading to the inundated
areas.
Updated August 2006 V-8
Woods Pond Dam EAP Notification Flowcharts and Contact Numbers
Action 3. Notify Potentially Affected Downstream Residents in Town of Lee
Police depmiment persOlmel will contact the potentially affected downstream residents in the
Town of Lee listed in Appendix D, and will issue appropriate instructions regarding
evacuation and tempormy shelters.
Town of Stockbridge Police Department
Once notified by the Facility Manager, the Town of Stockbridge Police Department should
initiate the following actions to assist them in coordinating their efforts:
Action 1. Notify Town of Stockbridge Fire Department
Designated Person:
Louis Peyron Phone No: (413) 298-4886
Once notified, fire department personnel will assist police depmiment personnel in
evacuating affected residents to safe places and providing necessary shelters and food.
Action 2. Notify Town of Stockbridge Highway Department
Designated Person:
Clint Schneyer Phone No: (413) 298-5506
Once notified, Stockbridge highway department personnel will place barricades on roads
leading to the inundated areas.
Action 3. Notify Potentially Affected Downstream Residents in Town of Stockbridge
Police department personnel will contact the potentially affected downstream residents in the
Town of Stockbridge listed in Appendix D, and will issue appropriate instlUctions regarding
evacuation and tempormy shelters.
Updated August 2006 V-9
Woods Pond Dam EAP Notification Flowcharts and Contact Numbers
B. Condition B - Potcntial Failure Situation Is Dcveloping
In the event that a potentially hazardous situation is developing at Woods Pond Dam, GE
personnel shall initiate notification procedures according to the flowchart shown in Exhibit 6.
The positions and sequence of notification for the flowchart are explained below.
Observer
In the event that a potential failure situation is developing at the dam site, the Observer shall
immediately notify the following GE contacts:
General Electric
PrimalY Contact: Kevin Mooney, Facility Manager Phone No: (413) 448-5910
Home Phone: (413) 447-9362
Cell No: (413) 441-4610
SecondaIY Contact:
John Levesque, Alternate Facility Manager Phone No: (413) 48-5914
Home Phone: (413) 743-3245
Cell No: (413) 441-4786
Once aware of a potential failure situation at the dam, the Facility Manager shall send a team
to the dam site to mitigate the situation. The following actions shall be initiated:
Action 1. Notify GE Response Contractor
The following contractors have been pre-selected by GE to assist in response actions under
this EAP:
LB Corporation
Designated Person:
Thomas R. Garrity Phone No: (413) 243-1072
LB Corporation Home Phone: (413) 243-1246
Cell No: (413) 441-9317
Updated August 2006 V-IO
Woods Pond Dam EAP Notification Flowcharts and Contact Numbers
Alternate Contacts:
Thomas M. GaJl'ity
LB Corporation
Steve Garrity
LB Corporation
Maxymillian Technologies
Designated Person:
Keith Hoag
Maxymillian Technologies Inc.
Alternate Contacts:
Peny Flood
Maxymillian Technologies Inc.
Bruce Rustemeyer
Maxymillian Technologies Inc.
Vern Palen
Maxymillian Technologies Inc.
Phone No: (413) 243-1072
Home Phone: (413) 243-1908
Cell No: (413) 441-9318
Phone No: (413) 243-1072
Home Phone: (413) 243-2505
Cell No: (413) 441-1412
Cell No: (413) 441-3379
Pager No: (413) 261-5034
Home Phone: (413) 743-0197
Cell No: (413) 441-3850
Pager No: (413) 261-5725
Home Phone: (413) 243-2789
Cell No: (413) 441-6291
Home Phone: (413) 634-5047
Cell No: (413) 441-4095
Pager No: (413) 292-8502
Home Phone: (413) 623-8343
Action 2. Notify Berkshire County Sheriff Communication Center
Designated Person:
Desk OfficerlDispatcher Phone No: (413) 442-0512
Alternate Contact:
Desk OfficerlDispatcher Phone No: (413) 445-4559
(Berkshire County Sheriff Communication Center handles the 911 calls for Lenox
and Stockbridge. Calling the listed telephone numbers is equivalent to calling 911 in
Lenox or Stockbridge)
Updated August 2006 V-II
Woods Pond Dam EAP Notification Flowcharts and Contact Numbers
Action 3. Notify Town of Lenox Police Department
Designated Person:
Stephen O'Brien Phone No: (413) 637-2346
Alternate Contact:
Tony Salvatore Phone No: (413) 499-7357
Action 4. Notify Town of Lee Police Department (same as 911 for Lee)
Designated Person:
Ronald Glidden Phone No: (413) 243-2100
Alternate Contact:
Desk Officer Phone No: (413) 243-0678
(Lee Police department handles the 911 calls for Lee. Calling the listed telephone numbers is
equivalent to calling 911 in Lee)
Action S. Notify Town of Stockbridge Police Department
Designated Person:
Richard Wilcox Phone No: (413) 298-5520
Alternate Contact:
Desk Officer Phone No: (413) 447-7357
Action 6. Notify Massachusetts Department of Environmental Protection (DEP)
Designated Person:
Spill Emergency Number (Toll Free) Phone No: (888) 304-1133
Alternate Contact:
Spill Emergency Number Phone No: (617) 556-1133
Action 7. Notify Massachusetts State Police (Rte. 20, Lee)
Designated Person:
Desk Officer Phone No: (413) 243-0600
Updatcd August 2006 V-12
Woods Pond Dam EAP Notification Flowcharts and Contact Numbers
Altel11ate Contact:
Troop B Duty Officer
Northampton, MA Phone No: (413) 587-5517
Action 8. Notify Department of Conservation and Recreation, Division of State Parks
and Recreation
Designated Person:
Michael Misslin Phone No: (617) 626-4927
Altel11ate Contact:
Michael Misslin Cell Phone No: (617) 828-1649
Action 9. Notify Massachusetts Emergency Management Agency
Designated Person:
Patrick Call1evale, Director Phone No: (413) 323-6306
Action 10. Notify Regulatory Contacts under Consent Decl'ee
(as appropriate for Condition B)
• U.S. Environmental Protection Agency:
Designated Person:
Susan Svirsky Phone No: (617) 918-1434
Altel11ate Contact:
EPA New England Emergency
Response Section Phone No: (617) 918-1260
• Massachusetts Department of Environmental Protection:
Designated Person:
Susan Steenstrup Phone No. 413-755-2264
Altel11ate Contact:
Anna Symington Phone No. 413-755-2220
• Connecticut Department of Environmental Protection
Designated Contact:
Oil & Chemical Spill Response Division Phone No. 860-424-3338
Updated August 2006 V-13
Woods Pond Dam EAP Notification Flowcharts and Contact Numbers
Action 11. Notify Housatonic Railroad Company
Designated Person:
Matt Boardman Phone No: (860) 824-0850, Ext. 17
Altemate Contact:
Dispatcher Phone No: (860) 824-0850, Ext. 12
While in contact with the above agencies, the Facility Manager will advise them to be on
alert and wait for a second call on further developments at the dam site. The Facility
Manager will continue to monitor the situation and infOlm the agencies as needed. Once
notified by the Facility Manager, the respective agencies will come up with a plan for
emergency operations. The agencies will also maintain contact with the Facility Manager.
Town of Lenox Police Department
Once notified by the Facility Manager, the Town of Lenox Police Department should initiate
the following actions to assist them in coordinating their effOlis.
Action 1. Notify Town of Lenox Fire Department
Designated Person:
Dan Clifford Phone No: (413) 637-2347
Altemate Contact:
Dan Clifford Phone No: (413) 499-7357
Once notified, fire department personnel will assist police department personnel III
evacuating the residents to safe places and providing necessary shelters and food.
Action 2. Notify Town of Lenox Department of Public Works (DPW)
Designated Person:
Jeff Vincent Phone No: (413) 637-5525
Alternate Contact:
R. Scott Jarvis Phone No: (413) 637-5520
Once notified, Lenox DPW personnel will place bmTicades on roads leading to the inundated
areas.
Updated August 2006 V-14
Woods Pond Dam EAP Notification Flowcharts and Contact Numbers
Action 3. Notify Potentially Affected Downstream Residents in Town of Lenox
Police depatiment personnel will contact the potentially affected downstream residents in the
Town of Lenox listed in Appendix D, and will issue appropriate instructions regarding
evacuation and temporary shelters.
Town of Lee Police Department
Once notified by the Facility Manager, the Town of Lee Police Depaliment should initiate
the following actions to assist them in coordinating their effolis.
Action 1. Notify Town of Lee Fire Department
Designated Person:
Ron Driscoll Phone No: (413) 243-2100
Once notified, fire department personnel will assist police depatiment personnel m
evacuating affected residents to safe places and providing necessalY shelters and food.
Action 2. Notify Town of Lee Department of Public Works (DPW)
Designated Person: Mike Towler Phone No: (413) 243-5526
Alternate Contact:
Mike Towler Phone No: (413) 243-2100
Once notified, Lee DPW personnel will place ban'icades on roads leading to the inundated
areas.
Action 3. Notify Potentially Affected Downstream Residents in Town of Lee
Police department personnel will contact the potentially affected downstream residents in the
Town of Lee listed in Appendix D, and will issue appropriate instructions regarding
evacuation and temporary shelters.
Updated August 2006 V-IS
Woods Pond Dam EAP Notification Flowcharts and Contact Numbers
Town of Stockbridge Police Department
Once notified by the Facility Manager, the Town of Stockbridge Police Depmiment should
initiate the following actions to assist them in coordinating their efforts.
Action 1. Notify Town of Stockbridge Fire Department
Designated Person:
Louis Peyron Phone No: (413) 243-3242
Once notified, fire department personnel will assist police depmiment personnel In
evacuating affected residents to safe places and providing necessary shelters and food.
Action 2. Notify Town of Stockbridge Highway Department
Designated Person:
Clint Schneyer Phone No: (413) 298-5506
Once notified, Stockbridge highway department personnel will place barricades on roads
leading to the inundated areas.
Action 3. Notify Potentially Affected Downstream Residents in Town of Stockbridge
Police department personnel will contact the potentially affected downstream residents in the
Town of Stockbridge listed in Appendix D, and will issne appropriate instructions regarding
evacuation and tempormy shelters.
Updated August 2006 V-16
Woods Pond Dam EAP General Responsibilities Under The EAP
VI. GENERAL RESPONSIBILITIES UNDER THE EAP
Failure of Woods Pond Dam would present a potential hazard to downstream areas. Areas of
concern at the project include a few houses located near the gravel pit and sewage disposal
plant. Numerous downstream roads and houses, primarily in the flood plains and close to the
banks ofthe river, would be flooded. Refer to the inundation map, Exhibit 3.
Once an emergency condition is identified, it is important to the success of the EAP that
responsible personnel respond immediately. Specific responsibilities of the persons or
organizations for the maintenance and operation of the dam and implementing various phases
ofthe plan are discussed below.
A. General Electric Responsibilities
GE has a plant in Pittsfield, Massachusetts, located approximately 12 miles upstream from
the dam. A member ofGE's Corporate Environmental Programs (CEP) staff from that plant,
or a contractor designated by GE, will perform a routine visit to the dam site and its
appUltenant stmctures at least monthly (or more frequently as watTanted by weather, river levels, or other conditions). This person will be the "Observer," as defined in Section V
(,'Notification Flowcharts and Contact Numbers") in case of an occurrence at the dam. The
person will cany a two-way radio and/or telephone andlor pager, and will be properly equipped to perfOlID a watch dming nighttime surveillance and severe weather.
In addition, the Facility Manager or the designated contractor will conduct an inspection of
the dam and its appUltenant stmctures at least quarterly to identify any changes in site
conditions that might indicate a problem for the dam. (This inspection will be combined with
one of the monthly site visits described above.). GE will provide a report on each such
quatterly inspection to the Lead Administrative Trustee (LAT) designated under
Paragraph 113 of the Consent Decree.
GE will also arrange for a licensed professional engineer to conduct an assessment, at least
once evelY two years, of the structural integrity of Woods Pond Dam, and to provide to GE a
repOlt on that assessment and any recommendations of measures necessaty to maintain dam
integrity. GE will provide a copy of each such report to the LAT.
The GE Facility Manager will have the authority to declare an emergency at Woods Pond
Dam or to change the degree of severity of an existing occut1'ence.
Updated August 2006 V[-l
Woods Pond Dam EM General Responsibilities Under The EAP
Upon receiving information of a threatening situation at Woods Pond Dam from the Observer
(or from other sources), it will be the primaty responsibility ofthe Facility Manager to direct
the designated person(s) of GE to proceed to the site. Included in this group will be one of
the persons who conduct routine inspections of the dam. It is the responsibility of this person
to know the signs of developing hazards such as those noted in Section IV, "Emergency
Detection, Evaluation and Classification," and to inform the Facility Manager immediately.
As a result of the site inspection, the Facility Manager will declare an emergency situation if
wan'anted, and will designate the proper degree of severity. The Facility Manager will also
initiate all notification calls.
The Facility Manager will serve as the emergency coordinator for all local agencies and will
direct all mitigation efforts at the dam site. The Facility Manager will also set up an appropriate central emergency headquarters from which all emergency operations will be
directed.
In notifYing the contacts involved with the situation, the Facility Manager will briefly state (after having queried the Observer for the information):
1. Name of dam 2. Emergency condition
• Condition A - Failure is Imminent or Has Occurred, or
• Condition B - Failure Situation is Developing
3. Severity of situation 4. Type of failure occUlTing or developing (e.g. overtopping, cracking or piping)
5. Time of observation, and time of failure, if occurred and known, otherwise estimate
The Facility Manager will keep local authorities and news media informed of changing
conditions at the dam site. However, the plan is not intended for the Facility Manager or his
designated person to assume the responsibility of govenunental authorities during an
emergency.
The Facility Manager is the EAP coordinator as described in Part E of this section. The
Facility Manager will closely coordinate efforts with the staff at the dam site and local
agencies to serve as a communications hub for the duration of the emergency.
The officials who must be notified are shown in Section V ("Notification Flowcharts and
Contact Numbers") and on Exhibits 5 and 6 (Notification Flowcharts). As GE's top
Updated August 2006 VI-2
Woods Pond Dam EAP General Responsibilities Under The EAP
communications representative and day-to-day manager during the emergency, the Facility
Manager will be at the top of the command chain and will speak for GE and engineering
personnel at the site.
B. Responsibility foJ' Notification
The Facility Manager is authorized to notifY authorities of the emergency, including the
police in the Towns of Lenox, Lee and Stockbridge, as well as the Berkshire County Sheriffs
Depatiment, Emergency Management offices and other federal, state and local agencies listed
on the notification flowcharts (Exhibits 5 and 6). The Facility Manager will have the
authority to issue statements to the press concerning the situation at the dam.
The town police and fire departments will serve as the lead authorities during emergency
situations. Once notified of an emergency condition, they will be responsible for notifYing potentially affected downstream residents (listed in Appendix D) and coordinating warning
and evacuation procedures with other authorities, including the emergency management
offices and other county and town departments (fire, ambulance, and transportation).
Major responsibilities of these authorities include:
• Issuing warnings and evacuating residential and commercial buildings as needed
• Controlling traffic and placement ofbat rica des on roads
• Coordinating with federal and state agencies
• Coordinating utility services
• Setting up health centers
• Informing the public through radio and television media
• Providing shelter for evacuated people
• Maintaining law and order
The chiefs of police for the towns of Lenox, Lee and Stockbridge will serve as local
coordinators for their municipalities. These local coordinators will keep in contact with the
Facility Manager and will be responsible for requesting support fi'om other local, county or
state agencies as needed. The Facility Manager will be responsible for advising these local
coordinators of the need to warn and/or evacuate local residents depending upon the
conditions at the dam site.
Updated August 2006 VI-3
Woods Pond Dam EAP General Responsibilities Under The EAP
Local coordinators will have the authority to release that infonnation necessary to assure the
safety of the public and to expedite an orderly evacuation when required. GE will coordinate
press releases concerning conditions at the dam with local coordinators. The local public
information centers will be responsible for informing the public of the provisions of this plan
and coordinating public input.
C. Responsibility for Evacuation
Following notification by the Facility Manager, the warning and evacuation of residents, as
necessary, will be perfonned by the local police, fire and civil defense departments.
Residents will be moved to pre-designated temporary shelters.
The Lenox and Lee DPWs and the Stockbridge Highway Depat1ment will take the lead roles
in placing and manning batl'icades on the affected roads, with assistance from police, to
prevent motorists fi'om entering the inundated areas. A map showing potential flood limits is
attached as Exhibit 3.
D. Responsibility for Duration, Security, Termination, and Follow-Up
As noted above under GE's responsibilities, the Facility Manager will keep local authorities,
primarily through the police depat1ments and county emergency management offices, advised
of conditions at the dam by phone or messenger.
The local authorities will be responsible for tennination of the emergency response activities,
with the advice of the Facility Manager.
For any emergency situation, after completion of all notification responsibilities, all officials,
including GE personnel, will maintain a log, report, or tape recording of all notifications and
decisions made by their offices for the duration of the emergency. The reports should include
the following information:
• Subject: (what happened and name or title of incident)
• Time and date:
• Location: (where incident occurred)
• Summaty of incident:
• Names and titles ofper sons involved:
Updated August 2006 VI-4
Woods Pond Dam EAP General Responsibilities Under The EAP
• Agencies notified: (e.g. sheriff, fire depat1ment, etc.)
• Status of incident: (completed and pending actions and decision)
E. EAP Coordinator Responsibility
The Facility Manager will be responsible for activities related to the EAP, including
reviewing and revising the plan, distributing copies of the flowchat1s and plan, and
establishing training for personnel in charge of the dam (see Appendix C). Also, the Facility
Manager will be the contact should any questions arise about the plan.
Updated August 2006 VI-5
Woods Pond Dam EAP Preparedness
VII. PREPAREDNESS
Preparedness actions are taken to prevent a dam failure or to help reduce the effects of a dam
failure and to facilitate a response to emergencies.
A. Surveillance
An emergency situation may be detected by inspection of the dam or by observation of
reservoir levels.
Surveillance of the dam will be made in accordance with the procedures described in Section
VI.A (General Responsibilities under the EAP - General Electric Responsibility). If night
inspections are made, the inspector should be accompanied by a second individual, and they
will cany flashlights and a two-way radio (walkie-talkie) or cellular phone to communicate.
Any observance of a failure or potential failure situation will be recorded and action shall be
taken immediately. Such situations are given in Section IV ("Emergency Detection,
Evaluation, and Classification").
Based on experience, a breach could fully develop in an hour or less after breach initiation.
The flood wave could reach the downstream residences in a few minutes. Therefore,
readiness for quick implementation of the EAP is important.
B. Response During Periods of Darkness
Once an emergency situation is detected, notification procedures during periods of darkness
will be the same as dmlng daylight hours. Home phone numbers are provided on the
notification flowcharts to facilitate contact dmlng non-business hours.
For any response actions taken during periods of darkness, at least two individuals should be
present, and they will cany flashlights and a two-way radio (walkie-talkie) or cellular phone
to communicate.
Due to the availability ofphones and two-way radios, no special procedure will be needed for
contacting people on the appropdate flowchart.
Updated August 2006 VII-l
Woods Pond Dam EAP Preparedness
C. Access to Site
Access to dam site will be by car and foot.
D. Response During 'Veekends and Holidays
Once an emergency situation is detected, notification procedures during weekends and
holidays will be the same as during weekdays. Home telephone numbers provided on the
notification flowchatts will be used during weekends and holidays. Notification response
time during weekends and holidays is expected to be similar to response times for
emergencies occurring during weekdays.
E. Response During Periods of Adverse Weather
During a severe storm, some roads may be under water that would be dry during fair weather conditions. Consequently, emergency-response vehicles may have to bypass roads that are
under water in order to get to the dam or affected areas.
Response during adverse weather (a storm) following observation of an emergency condition,
comprising notifications and warning to downstream areas, is expected to take more time
than under normal conditions.
F. Availability and Use of Alternative Communication Systems
Telephones will be the main system of communication on and off the dam site. Also, two
way radios (walkie-talkies) will be available for site communication.
If the above methods fail, communications on-site and with emergency agencies in towns of
Lenox, Lee and Stockbridge will proceed by messenger.
G. Emergency Supplies and Resources
GE will be responsible for emergency supplies and resources for on-site use. GE will rely on
its designated contractor to assist in providing such supplies and resources, as described
below.
Updated August 2006 VlI-2
Woods Pond Dam EAP Preparedness
GE and its designated contractor will provide men and equipment for emergency repair of the
dam. GE's designated contractors and a list of the equipment they are responsible for
providing, are listed in Appendix E. Fill, comprised of earth and rock, would be obtained
from available borrow areas. However, due to possibly rapid development of a breach and
consequently a very short wal11ing time, emergency repair of a dam will not be relied on as a
preventative or control action.
Updated August 2006 VII-3