86
Empire State Building Performance Year 4 M&V Report April 2, 2015

Empire State Building Performance Year 4 M&V Report April ... · Empire State Building Performance Year 4 M&V Report Section 1 - Executive Summary 1 1. Empire State Building (ESB)

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Empire State Building Performance Year 4 M&V Report April ... · Empire State Building Performance Year 4 M&V Report Section 1 - Executive Summary 1 1. Empire State Building (ESB)

Empire State Building Performance Year 4 M&V Report April 2, 2015

Page 2: Empire State Building Performance Year 4 M&V Report April ... · Empire State Building Performance Year 4 M&V Report Section 1 - Executive Summary 1 1. Empire State Building (ESB)

Empire State Building Performance Year 4 M&V Report

Table of Contents i

Table of Contents

Table of Contents .................................................................................................i

1. Executive Summary ....................................................................................... 1

2. Project Overview ............................................................................................ 8

2.1 Project Guaranteed Savings .................................................................... 9

2.2 eQUEST Model Setup Overview ............................................................ 10

Model Build .................................................................................................. 10

3. ECM 1: Window Retrofit ............................................................................. 11

3.1 ECM 1: Window Retrofit ........................................................................ 11

3.1.1 ECM Description ............................................................................... 11

3.1.2 Pre-Installation System Conditions .................................................... 11

3.1.3 Post-Installation System Conditions .................................................. 11

3.1.4 ECM M&V Methodology .................................................................... 12

4. ECM 2: Radiator Insulation and Steam Trap Retrofit ............................... 13

4.1 ECM 2.1: Radiator Insulation ................................................................ 13

4.1.1 ECM Description ............................................................................... 13

4.1.2 Pre-Installation System Conditions .................................................... 13

4.1.3 Post-Installation System Conditions .................................................. 13

4.1.4 ECM M&V Methodology .................................................................... 13

4.2 ECM 2.2: Steam Trap Retrofit ............................................................... 15

4.2.1 ECM Description ............................................................................... 15

4.2.2 Pre-Installation System Conditions .................................................... 15

4.2.3 Post-Installation System Conditions .................................................. 15

4.2.4 ECM M&V Methodology .................................................................... 15

5. ECM 3: BMS Retrofit ................................................................................... 16

5.1 ECM 3.1: BMS Damper Retrofit and DCV............................................. 16

5.1.1 ECM Description ............................................................................... 16

5.1.2 Pre-Installation System Conditions .................................................... 16

5.1.3 Post-Installation System Conditions .................................................. 17

5.1.4 ECM M&V Methodology .................................................................... 17

Page 3: Empire State Building Performance Year 4 M&V Report April ... · Empire State Building Performance Year 4 M&V Report Section 1 - Executive Summary 1 1. Empire State Building (ESB)

Empire State Building Performance Year 4 M&V Report

Table of Contents ii

5.2 ECM 3.2: Fan Scheduling ...................................................................... 17

5.2.1 ECM Description ............................................................................... 17

5.2.2 Pre-Installation System Conditions .................................................... 18

5.2.3 Post-Installation System Conditions .................................................. 18

5.2.4 ECM M&V Methodology .................................................................... 18

6. ECM 4: Chiller Plant Retrofit ...................................................................... 19

6.1 ECM 4.1: Chiller Tubes and Chiller VFD Retrofit ................................ 19

6.1.1 ECM Description ............................................................................... 19

6.1.2 Pre-Installation System Conditions .................................................... 20

6.1.3 Post-Installation System Conditions .................................................. 20

6.1.4 ECM M&V Methodology .................................................................... 20

6.2 ECM 4.2: CHW Supply Temperature Reset .......................................... 21

6.2.1 ECM Description ............................................................................... 21

6.2.2 Pre-Installation System Conditions .................................................... 21

6.2.3 Post-Installation System Conditions .................................................. 21

6.2.4 ECM M&V Methodology .................................................................... 22

6.3 ECM 4.3: CHW Loop Delta-T Enhancement ......................................... 22

6.3.1 ECM Description ............................................................................... 22

6.3.2 Pre-Installation System Conditions .................................................... 23

6.3.3 Post-Installation System Conditions .................................................. 23

6.3.4 ECM M&V Methodology .................................................................... 23

6.4 ECM 4.4: CHW Pump VFD Automation ................................................ 24

6.4.1 ECM Description ............................................................................... 24

6.4.2 Pre-Installation System Conditions .................................................... 25

6.4.3 Post-Installation System Conditions .................................................. 25

6.4.4 ECM M&V Methodology .................................................................... 26

6.5 ECM 4.5: Condenser Water Supply Temperature Reset .................... 26

6.5.1 ECM Description ............................................................................... 26

6.5.2 Pre-Installation System Conditions .................................................... 27

6.5.3 Post-Installation System Conditions .................................................. 27

6.5.4 ECM M&V Methodology .................................................................... 27

6.6 ECM 4.6: Cooling Tower Fan VFD Automation ................................... 28

6.6.1 ECM Description ............................................................................... 28

6.6.2 Pre-Installation System Conditions .................................................... 29

6.6.3 Post-Installation System Conditions .................................................. 29

6.6.4 ECM M&V Methodology .................................................................... 29

Page 4: Empire State Building Performance Year 4 M&V Report April ... · Empire State Building Performance Year 4 M&V Report Section 1 - Executive Summary 1 1. Empire State Building (ESB)

Empire State Building Performance Year 4 M&V Report

Table of Contents iii

6.7 ECM 4.7: CW Pump VFD Automation .................................................. 30

6.7.1 ECM Description ............................................................................... 30

6.7.2 Pre-Installation System Conditions .................................................... 31

6.7.3 Post-Installation System Conditions .................................................. 31

6.7.4 ECM M&V Methodology .................................................................... 31

7. ECM 5: Tenant Energy Management Portal .............................................. 32

7.1 ECM 5: TEM Portal ................................................................................. 32

7.1.1 ECM Description ............................................................................... 32

7.1.2 Pre-Installation System Conditions .................................................... 32

7.1.3 Post-Installation System Conditions .................................................. 33

7.1.4 ECM M&V Methodology .................................................................... 33

8. ECM 6: Low Zone and Mid Zone PFHX ..................................................... 34

8.1 ECM 6: Low Zone and Mid Zone PFHX ................................................ 34

8.1.1 ECM Description ............................................................................... 34

8.1.2 Pre-Installation System Conditions .................................................... 34

8.1.3 Post-Installation System Conditions .................................................. 34

8.1.4 ECM M&V Methodology .................................................................... 34

Appendix List .................................................................................................... 35

Appendix 1: BMS Retrofit Data Analysis .................................................... 36

Damper Retrofit and DCV ............................................................................ 36

Fan Scheduling ............................................................................................ 39

Mid Zone/High Zone AHU Supply Fan Scheduling ...................................... 39

Appendix 2: Chiller Retrofit Data Analysis ................................................. 45

Chiller Curve Fit Modeling Methodology ...................................................... 45

Low Zone Chiller-1 Performance Curves ..................................................... 47

Mid Zone Chiller-4 Performance Curves ...................................................... 49

Mid Zone Chiller-5 Performance Curves ...................................................... 51

High Zone Chiller-6 Performance Curves..................................................... 53

Appendix 3: Chiller Plant Retrofit Data Analysis ....................................... 55

CHWST Reset .............................................................................................. 55

CHW Loop Delta-T Enhancement ................................................................ 57

CHW Pump VFD Automation ....................................................................... 58

CW Supply Temperature Reset ................................................................... 59

Cooling Tower Fan VFD Automation ............................................................ 60

CW Pump VFD Automation .......................................................................... 61

Appendix 4: PFHX Data Analysis ................................................................ 62

Page 5: Empire State Building Performance Year 4 M&V Report April ... · Empire State Building Performance Year 4 M&V Report Section 1 - Executive Summary 1 1. Empire State Building (ESB)

Empire State Building Performance Year 4 M&V Report

Table of Contents iv

Appendix 5: ESB eQUEST Model Inputs .................................................... 65

Appendix 6: Baseline Adjustments ............................................................. 69

List of 2014 Baseline Adjustments ............................................................... 69

Weather Data ............................................................................................... 69

Utility Analysis .............................................................................................. 69

Construction Floor Data ............................................................................... 69

Construction Floor Space Temperature Analysis ......................................... 70

Tenant Vacancy Analysis ............................................................................. 70

Tenant Space Temperature Analysis ........................................................... 74

Broadcast Floors Electric Load Data ............................................................ 74

VAV AHU Upgrades ..................................................................................... 75

Appendix 7: ESB Utility Rates ..................................................................... 76

Glossary ............................................................................................................ 78

Report Delivery Acknowledgement ................................................................. 80

Page 6: Empire State Building Performance Year 4 M&V Report April ... · Empire State Building Performance Year 4 M&V Report Section 1 - Executive Summary 1 1. Empire State Building (ESB)

Empire State Building Performance Year 4 M&V Report

Section 1 - Executive Summary 1

1.

Empire State Building (ESB) has committed to a major sustainability retrofit in order to become a leading example of economic and environmental revitalization. A Johnson Controls Energy Performance Contract (EPC) was undertaken to install five Energy Conservation Measures (ECM) of the Sustainability Program at ESB. In addition, a Plate and Frame Heat Exchanger (PFHX) ECM was installed in 2013 as part of a change order to the original EPC. This report documents the project savings in Performance Year (PY) 2014.

Annual savings for all ECMs are calculated based on International Performance Measurement and Verification Protocol (IPMVP) Option D, which utilizes building performance simulation software (eQUEST®). However, the steam trap savings were contractually agreed to be non-measured savings and the PFHX savings are directly derived from measurements.

Figure 1.1 shows the Contract Guaranteed savings, the PY Target Guaranteed savings, the PY ECM Performance savings, the PY Actual Operation savings and the PY Actual Utility savings. Johnson Controls savings guarantee obligation is evaluated by comparing total PY ECM Performance savings with total PY Target Guaranteed savings. The total PY ECM Performance savings exceeded the PY Target Guaranteed savings for the 2014 period. Not all PY ECM Performance savings are captured in ESB’s actual utility bills due to ECM field operation deviations from design. PY Actual Utility savings reflect the savings seen on the actual utility bills.

Page 7: Empire State Building Performance Year 4 M&V Report April ... · Empire State Building Performance Year 4 M&V Report Section 1 - Executive Summary 1 1. Empire State Building (ESB)

Empire State Building Performance Year 4 M&V Report

Section 1 - Executive Summary 2

No. ECM

Contract Guaranteed

Savings1

(Unadjusted, from Contract)

PY Target Guaranteed

Savings2 (Using 2014

Baseline Adjustments)

PY ECM Performance

Savings3 (Using 2014

Measurements)

PY Actual Operation Savings4

(Using 2014 Actual Operations Data)

PY Actual Utility Savings5

(Using 2014 Actual Utility Rates)

[A] [B] [C] [D] [E] [F] [G]

1 Windows Retrofit $338,508 $370,112 $275,104 $275,104 $282,694

2 Radiator Insulation and Steam Traps

$491,191 $523,450 $627,710 $627,710 $617,835

3 BMS Retrofit $774,388 $886,453 $1,090,078 $1,090,078 $1,015,826

4 Chiller Plant Retrofit6 $611,641 $650,157 $867,700 $838,887 $764,703

5 Tenant Energy Management

$25,000 $27,334 $0 $0 $0

6 PFHX7 $133,607 $202,899 $202,899 $202,899 $186,676

Total $2,374,335 $2,660,405 $3,063,491 $3,034,678 $2,867,734

Note:

1. Contract Guaranteed savings were calculated using the 2007 Baseline and 2007 utility rates. Johnson Controls guaranteed 90.6% of the modeled contract savings for all ECMs except steam traps, TEM and PFHX.

2. PY Target Guaranteed savings were calculated by making 2014 Baseline adjustments to the 2007 Contract Guaranteed savings model and using 3.02% annually escalated contract utility rate, escalation starting from PY2 (called the “PY contract utility rate”).

3. PY ECM Performance savings were calculated by inputting measurements of 2014 ECM performance to the PY Target Guaranteed savings model and using PY contract utility rate.

4. In certain cases, the ECM equipment was operated to accommodate building operational necessities and not as programmed. Operations data accounts for such changes in ECM operation (see Appendix 3 for details). PY Actual Operation savings were calculated by inputting 2014 operations data to the PY ECM Performance savings model and using PY contract utility rate.

5. PY Actual Utility savings were calculated by inputting 2014 actual utility rates into the PY Actual Operation savings model.

6. The Chiller Plant Retrofit savings numbers from the eQuest model includes the PFHX savings during the shoulder season. The Chiller Plant Retrofit savings numbers shown here are adjusted using PFHX shoulder season savings numbers to avoid double accounting.

7. The PFHX ‘Contract Guaranteed Savings’ uses 2011 energy usage as the baseline and uses the original contract rate (2007 utility rate with annual escalation) for utility rates. The PFHX ‘PY Target Guaranteed Savings’ uses 2014 energy usage as the adjusted baseline and uses the original contract rate (2007 utility rate with annual escalation) for utility rates..

Figure 1.1: 2014 Project Savings

ECM performance accounts for the following:

The window testing is conducted every two years. The latest test was conducted in 2013. The measured performance of the windows outperformed the target (see Section 3 for details). But, ECM performance savings are still lower than the target savings because Johnson Controls is upholding a higher target that was incorrectly calculated at the time of contract.

Page 8: Empire State Building Performance Year 4 M&V Report April ... · Empire State Building Performance Year 4 M&V Report Section 1 - Executive Summary 1 1. Empire State Building (ESB)

Empire State Building Performance Year 4 M&V Report

Section 1 - Executive Summary 3

The one time measurement of radiator insulation thermal resistance (tested in 2010) showed that the Radiator Insulation ECM is projected to outperform contract savings for all Performance Periods (see Section 4 for details).

Steam trap surveying is used to identify leaking or failed traps. However, they are contracted to be non-measured savings. The latest survey was conducted in March 2013. The survey results were published in 2013 Q1 report.

Trending analysis for 2014 indicated that the ECM savings for the Building Management System (BMS) retrofit exceeds target savings in PY4.

Trending analysis for 2014 indicated that the savings for the Chiller Plant Retrofit ECM exceeds contracted savings in PY4. In certain cases, the mechanical equipment was operated to accommodate building operational necessities and not as programmed (see Appendix 3 for details). PY Actual Operation savings reflect the savings in the actual field operation scenario using PY contract utility rates. PY Actual Utility savings reflect the savings in the actual field operation scenario using PY actual utility rates.

ESB and Johnson Controls agreed to not claim Tenant Energy Management (TEM) savings in 2014 because of Tenant submeter inaccuracy issues. Majority of the issues are currently resolved.

2014 trending analysis indicated that the PFHX is operating within the contract performance specifications and the ECM performance savings meets the target savings.

Figure 1.2 illustrates that ESB’s Post-Installation electric utility consumption was reduced by 29% during base load conditions and was reduced by at least 33% during the hottest month.

Page 9: Empire State Building Performance Year 4 M&V Report April ... · Empire State Building Performance Year 4 M&V Report Section 1 - Executive Summary 1 1. Empire State Building (ESB)

Empire State Building Performance Year 4 M&V Report

Section 1 - Executive Summary 4

Figure 1.2: Reduction in ESB’s Baseline Electric Utility Consumption

during Performance Periods

Figure 1.3 illustrates reduction in ESB’s Baseline electric demand. The relative increase in 2014 demand is attributed to the escalation in summer electric chiller usage and building tenant occupancy. Summer electric chiller usage increase was a direct result of the change in ESB’s 2014 chiller operation, which was changed from steam chiller primary to electric chiller primary; a transformation recommended by Johnson Controls. As a result of this modification, ESB significantly benefitted with increase in revenues as shown below.

Decrease in summer steam cost as illustrated by Figure 1.4, which led to decrease in total utility cost.

In addition to the decrease in total utility cost, the shift to electric chiller primary resulted in a larger Demand Response scope and therefore higher Demand Response revenue.

Page 10: Empire State Building Performance Year 4 M&V Report April ... · Empire State Building Performance Year 4 M&V Report Section 1 - Executive Summary 1 1. Empire State Building (ESB)

Empire State Building Performance Year 4 M&V Report

Section 1 - Executive Summary 5

Figure 1.3: Reduction in ESB’s Baseline Electric Utility Consumption and Demand

during Performance Periods

Figure 1.4: Reduction in ESB’s Baseline Summer Steam Utility Consumption

during Performance Periods

Page 11: Empire State Building Performance Year 4 M&V Report April ... · Empire State Building Performance Year 4 M&V Report Section 1 - Executive Summary 1 1. Empire State Building (ESB)

Empire State Building Performance Year 4 M&V Report

Section 1 - Executive Summary 6

Figure 1.5 illustrates ESB’s winter steam consumption change with heating degree days. Increased occupancy and construction activities lead to increase in the winter steam usage.

Figure 1.5: Reduction in ESB’s 2007 Baseline Winter Steam Utility Consumption

during Performance Period

Figure 1.6 illustrates that ESB’s unadjusted total utility costs have decreased significantly.

2014 total utility costs are reduced by 40% when compared with the 2007 Baseline.

2014 total electric costs are reduced by 45% when compared with the 2007 Baseline and the consumption is reduced by 25% during the same period.

2014 steam costs are reduced by 16% when compared with the 2007 Baseline and the consumption is reduced by 10% during the same period.

The unadjusted actual utility cost reductions shown in Figure 1.6 reflect energy savings due to various factors including installation of Johnson Controls ECMs.

Page 12: Empire State Building Performance Year 4 M&V Report April ... · Empire State Building Performance Year 4 M&V Report Section 1 - Executive Summary 1 1. Empire State Building (ESB)

Empire State Building Performance Year 4 M&V Report

Section 1 - Executive Summary 7

Figure 1.6: Reduction in ESB’s Unadjusted Baseline Utility Costs

during Performance Period

Page 13: Empire State Building Performance Year 4 M&V Report April ... · Empire State Building Performance Year 4 M&V Report Section 1 - Executive Summary 1 1. Empire State Building (ESB)

Empire State Building Performance Year 4 M&V Report

Section 2 - Project Overview 8

2.

Johnson Controls developed an EPC to install five ECMs of the Sustainability Program at ESB. The EPC consolidated the balance of Direct Digital Control (DDC) and Demand Control Ventilation (DCV) measures into one BMS Retrofit ECM. In addition, a PFHX ECM was installed in 2013 as part of a change order to the original EPC. Therefore, a total of six measures have been documented in the EPC. The contract-guaranteed savings for each ECM is listed in Figure 2.1.

No. ECM Electric kWh

Savings Electric kW

Savings Steam Mlb

Savings

Unadjusted Year 1 Contract Guaranteed

Savings

[A] [B] [C] [D] [E] [F]

1 Windows Retrofit 1,329,797 116 5,115 $338,508

2 Radiator Insulation and Steam Traps

14,870 $491,191

3 BMS Retrofit 1,621,091 138 16,744 $774,388

4 Chiller Plant Retrofit 2,963,656 1,095 824 $611,641

5 Tenant Energy Management 160,256

$25,000

6 PFHX 1,100,725 $133,607

Total 7,175,525 1,349 37,553 $2,374,335

Figure 2.1: Shows the contract savings in kWh, kW, Mlb and total unadjusted guaranteed savings for each ECM

Page 14: Empire State Building Performance Year 4 M&V Report April ... · Empire State Building Performance Year 4 M&V Report Section 1 - Executive Summary 1 1. Empire State Building (ESB)

Empire State Building Performance Year 4 M&V Report

Section 2 - Project Overview 9

2.1

Figure 2.2 shows the unadjusted project guaranteed savings for the 15-year guarantee period.

Year

Total Unadjusted Guaranteed

Savings

Windows Retrofit

Radiator Insulation/Steam

Traps Retrofit

Chiller Plant Retrofit

BMS Retrofit TEM PFHX

[A] [B] [C] [D] [E] [F] [G] [H]

1 $2,240,728 $338,508 $491,191 $611,641 $774,388 $25,000 $0

2 $2,310,490 $348,731 $506,025 $630,113 $799,866 $25,755 $0

3 $2,382,428 $359,263 $521,307 $649,142 $826,183 $26,533 $0

4 $2,590,214 $370,112 $537,050 $668,746 $853,365 $27,334 $133,607

5 $2,670,744 $381,290 $553,269 $688,942 $881,441 $28,160 $137,642

6 $2,753,782 $392,805 $569,978 $709,748 $910,442 $29,010 $141,799

7 $2,839,404 $404,667 $587,191 $731,183 $940,396 $29,886 $146,081

8 $2,927,695 $416,888 $604,925 $753,264 $971,336 $30,789 $150,493

9 $3,018,734 $429,478 $623,193 $776,013 $1,003,294 $31,718 $155,038

10 $3,112,611 $442,449 $642,014 $799,449 $1,036,303 $32,676 $159,720

11 $3,209,411 $455,811 $661,403 $823,592 $1,070,399 $33,663 $164,543

12 $3,309,225 $469,576 $681,377 $848,464 $1,105,616 $34,680 $169,512

13 $3,412,150 $483,757 $701,954 $874,088 $1,141,992 $35,727 $174,632

14 $3,518,282 $498,367 $723,154 $900,485 $1,179,564 $36,806 $179,906

15 $3,627,720 $513,417 $744,993 $927,680 $1,218,373 $37,918 $185,339

Total $43,923,616 $6,305,119 $9,149,024 $11,392,550 $14,712,958 $465,655 $1,898,310

Figure 2.2: Unadjusted Project Guaranteed Savings

Note: The savings for each year is annually escalated by 3.02% from the baseline year.

Page 15: Empire State Building Performance Year 4 M&V Report April ... · Empire State Building Performance Year 4 M&V Report Section 1 - Executive Summary 1 1. Empire State Building (ESB)

Empire State Building Performance Year 4 M&V Report

Section 2 - Project Overview 10

2.2

Modeling Software

eQUEST v3.64 with patch

Model Author

Quest Energy Group, LLC 1620 W Fountainhead Pkwy #303 Tempe, AZ 85282 +1 480 467 2480

Model Build

A detailed architectural model of the building was created from detailed analysis of archive drawings, photos taken on-site and thorough inspections verifying wall and roof constructions, external shading, and glass types.

Schedules, based on building operation, were also employed in the model to simulate real-world conditions.

Lighting demand and energy (schedules) were calculated into the model based upon the lighting information provided by JLL.

Representative internal equipment loads, by space type (office, corridor, etc.), were incorporated into the model.

Heating, Ventilating, and Air-Conditioning (HVAC) equipment, including their demonstrated efficiencies, were added to the model with each zone being assigned to the appropriate HVAC system. Zoning was determined by the base building core areas including elevator shafts, restrooms, corridors, etc. and the tenant occupy-able areas, which were zoned using perimeter/core areas by orientation. HVAC equipment efficiencies were based on field measurements, nameplate data, or mechanical plans as available (this method dovetails into your report's description of field measured data, etc.).

Vacancy rates for the building were included in the model.

The contract model eQUEST version did not have the capability to model individual ESB floors. There have been improvements in eQUEST software which enabled Quest Energy Group to model individual ESB floors.

Page 16: Empire State Building Performance Year 4 M&V Report April ... · Empire State Building Performance Year 4 M&V Report Section 1 - Executive Summary 1 1. Empire State Building (ESB)

Empire State Building Performance Year 4 M&V Report

Section 3 - ECM 1: Window Retrofit 11

3.

The savings numbers associated with the window retrofit is shown below:

PY Target Performance savings was calculated to be $370,112 by using PY Adjusted Baseline and by using Contract Target Performance.

PY ECM Performance savings was calculated to be $275,104 by using PY Adjusted Baseline and by using 2013 measurements.

PY Actual Operation savings was calculated to be $275,104 by using PY Adjusted Baseline and by using 2013 measurements.

3.1

3.1.1

The window retrofit ECM served to upgrade the existing Insulated Glass (IG) for 6,514 double-hung windows by adding suspended coated film Alpen glass. The required re-manufacturing of the (2 x 6,514 =) 13,028 IG units was conducted on-site at ESB. IG units were removed and moved to a production area located on the 5th Floor. Either Alpen glass TC88 or SC75 was used as the suspended film depending upon window orientation. A mixture of krypton/argon gas was used to fill the window glass chamber. This ECM improved the thermal resistance of the glass and reduced solar heat gain values. As an additional contribution to sustainability, glass removed from the windows was recycled.

3.1.2

Pre-Installation double pane windows were estimated (not measured at that time) to have 0.48 U-Value and 0.645 Solar Heat Gain Coefficient (SHGC). After testing, it was found that Pre-Installation window performance was 0.58 in U-Value and that calculated savings would exceed estimated savings.

3.1.3

North windows were targeted to attain 0.365 U-Value and 0.448 SHGC through Krypton/Argon gas fill and TC88 suspended film. S-E-W windows were targeted to attain 0.384 U-Value and 0.325 SHGC through Krypton gas fill and SC75 suspended film. The Post-Installation north facing windows were tested in 2013 to attain ECM Performance values shown in Figure 3.2. The next windows test is due by December 2015.

Page 17: Empire State Building Performance Year 4 M&V Report April ... · Empire State Building Performance Year 4 M&V Report Section 1 - Executive Summary 1 1. Empire State Building (ESB)

Empire State Building Performance Year 4 M&V Report

Section 3 - ECM 1: Window Retrofit 12

3.1.4

IG units were sent to an independent testing agency (Architectural Testing, Inc. [ATI]) for evaluation of several window performance indices including the ones used as eQUEST inputs (Whole window U-Value and SHGC).

ATI, located in York, PA, is a premier window testing company boasting extensive experience and testing in the field of window testing. ATI is accredited with several agencies including the National Fenestration Rating Council (NFRC), American National Standards Institute, Insulating Glass Certification Council, American Architectural Manufacturers Association, Window and the Door Manufacturers Association. Comprehensive information about ATI, ATI’s work, testing facility and certificate of accreditations is given in the attached test report. A total of four old windows and six new windows were tested for performance.

IG unit performance was tested in accordance with NFRC 102-2010 in a thermal test chamber. The two sides of the chamber were simulated for standard exterior (-0.4˚F at 15mph wind speed) and interior (70˚F) environment. Interior conditions were maintained using an electric heater, the output of which can be measured. IG unit U-factor was calculated using measured heat loss and delta-T.

Whole window (IG unit and frame) performance was evaluated using a combination of gas fill test and industry standard computer simulation. Gas fill tests were performed using a standard gas chromatograph device.

SHGC tests were performed using a window energy profiler device (WP4500) that measures ultraviolet, visible light, infrared transmission values and SHGC. Results from the testing were used to generate the following eQUEST Model inputs that determine the ECM savings.

Contract Baseline

PY Adjusted Baseline

PY Target Performance

PY ECM Performance

PY Actual Operation

North Windows 0.48 / 0.645 0.58 / 0.645 0.365 / 0.448 0.274 / 0.39 0.274 / 0.39

East Windows 0.48 / 0.645 0.58 / 0.645 0.384 / 0.325 0.320 / 0.27 0.320 / 0.27

South Windows 0.48 / 0.645 0.58 / 0.645 0.384 / 0.325 0.337 / 0.27 0.337 / 0.27

West Windows 0.48 / 0.645 0.58 / 0.645 0.384 / 0.325 0.324 / 0.27 0.324 / 0.27

Figure 3.2: Windows ECM Model Inputs (shown as U-value / SHGC)

Figure 3.1: ESB Windows when tested at ATI (left); Schematic of ATI’s window testing chamber (right)

Page 18: Empire State Building Performance Year 4 M&V Report April ... · Empire State Building Performance Year 4 M&V Report Section 1 - Executive Summary 1 1. Empire State Building (ESB)

Empire State Building Performance Year 4 M&V Report

Section 4 - ECM 2: Radiator Insulation and Steam Trap Retrofit 13

4.

The savings numbers associated with radiator insulation and steam trap retrofit is shown below:

PY Target Performance savings was calculated to be $523,450 by using PY Adjusted Baseline and by using Contract Target Performance.

PY ECM Performance savings was calculated to be $627,710 by using PY Adjusted Baseline and 2010 measurements.

PY Actual Operation savings was calculated to be $627,710 by using PY Adjusted Baseline and by using 2010 measurements.

4.1

4.1.1

The Radiator Insulation ECM involved the installation of 6,514 insulated reflective barriers behind radiator units located on the perimeter of the building. In addition, the unit itself was cleaned and the thermostat repositioned to the front side of the unit. The reduction of thermal heat loss through the exterior building wall, as a result of installing the reflective barriers, results in measurable energy savings.

4.1.2

Pre-Installation “wall+no-insulation” U-Value was estimated to be 0.209. Post-Installation "wall+insulation" U-Value was estimated to be 0.122. All radiator insulation in the building perimeter wall reduces heat loss.

4.1.3

Radiator insulation was installed in the perimeter wall. Johnson Controls was unable to install the barriers in broadcasting spaces because those spaces were overheating resulting in the radiator assemblies being removed. But, there will be additional savings beyond those that the tests demonstrated due to the reflective layer on the insulation.

4.1.4

Radiator insulation boards were sent to ATI, an independent testing agency, for a one-time measurement of thermal performance.

ATI, located in York, PA, is a fenestration testing company with extensive experience in the field of fenestration testing. ATI is accredited by several agencies; including National Fenestration Rating Council, American National Standards Institute, Insulating Glass Certification Council, American Architectural Manufacturers Association and the Window and Door Manufacturers Association. Comprehensive information about ATI, ATI’s work, testing facility and certificate of accreditations is detailed in the attached test report.

Page 19: Empire State Building Performance Year 4 M&V Report April ... · Empire State Building Performance Year 4 M&V Report Section 1 - Executive Summary 1 1. Empire State Building (ESB)

Empire State Building Performance Year 4 M&V Report

Section 4 - ECM 2: Radiator Insulation and Steam Trap Retrofit 14

A total of ten radiator insulation locations were tested for performance.

Figure 4.1: Insulation Testing Equipment at ATI

Radiator Insulation was tested using American Society for Testing and Materials (ASTM) C 518, Standard Test Methodology for Steady State Heat Flux Measurements and Thermal Transmission Properties by Means of Heat Flow Meter Apparatus. The test method includes the measurement of steady state thermal transmission through flat specimens using a heat flow meter apparatus which is a comparative method of measurement that was calibrated to a specimen traceable to National Institute of Materials supplied material.

The cold plate was maintained at a nominal 50˚F and the hot plate was maintained at a nominal 100˚F. A heat flux transducer was introduced on the warm side. Insulation U-factor was calculated using measured heat loss and delta-T.

Results from the testing were used to generate the following eQUEST Model inputs that determine the ECM savings.

Contract Baseline

PY Adjusted Baseline

PY Target PY ECM

Performance PY Actual Operation

Radiative Wall U-Value 0.209 0.209 0.122 0.102 0.102

Figure 4.2: Radiator Insulation ECM Model Inputs

Page 20: Empire State Building Performance Year 4 M&V Report April ... · Empire State Building Performance Year 4 M&V Report Section 1 - Executive Summary 1 1. Empire State Building (ESB)

Empire State Building Performance Year 4 M&V Report

Section 4 - ECM 2: Radiator Insulation and Steam Trap Retrofit 15

4.2

4.2.1

Steam traps are designed to prevent steam from passing beyond its point of use and to allow condensate to be expelled as soon as it forms. The traps perform a function similar to that of automatic valves. Steam traps open, close or modulate automatically. Over time, internal parts of steam traps wear out and result in failure to open and close properly. Open traps typically result in loss of live steam, while a closed trap may result in loss of heat transfer to the area and possible water hammering. Water hammering can eventually damage the valves and other components in steam systems, a condition that could result in steam leaks.

All ESB steam radiators are fitted with thermostatic steam traps which incorporate a diaphragm or bellows, comprising a volatile liquid, sealed under vacuum. The trap opens and closes in a modulating manner dependent upon the temperature affecting it. The trap’s normal state is wide open to expel air and condensate. When surrounded by steam at saturated temperature, the volatile fill flashes, creating an internal pressure equal to the surrounding pressure. Equalization of pressures allows the bellows to expand to their natural length or closed position, preventing steam from passing. The presence of condensate sufficiently cools the bellows to condense the vapor within. Once again, the external pressure is greater and the bellows reverts back to its contracted, or open position, allowing the condensate to drain from the trap, permitting more steam to enter the radiator, thus modulating action of the trap.

Failure of a Pre-Installation steam trap at ESB could result in steam loss or equipment operational issues. Retrofitting all of the steam traps has greatly reduced steam wastage in the structure.

4.2.2

All of the steam radiators at ESB are fitted with thermostatic steam traps to prevent Pre-Installation traps from failing at ESB.

4.2.3

As part of the performance contract, all radiator steam traps were retrofitted.

4.2.4

The non-measured savings for this ECM is contingent upon the successful installation of the steam traps. Johnson Controls’ energy savings calculation showed an annual steam savings of $520,180 at the time of contract. Johnson Controls was conservative in discounting the projected savings by 38.5% and in guaranteeing $320,000 (equivalent to 9,786 Mlb in eQUEST Model). The PY guaranteed savings are annually escalated by 3.02%.

Page 21: Empire State Building Performance Year 4 M&V Report April ... · Empire State Building Performance Year 4 M&V Report Section 1 - Executive Summary 1 1. Empire State Building (ESB)

Empire State Building Performance Year 4 M&V Report

Section 5 - ECM 3: BMS Retrofit 16

5.

The savings numbers associated with the BMS retrofit is shown below:

PY Target Performance savings was calculated to be $886,453 by using PY Adjusted Baseline and by using Contract Target Performance.

PY ECM Performance savings was calculated to be $1,090,078 by using PY Adjusted Baseline and by using 2014 measurements.

PY Actual Operation savings was calculated to be $1,090,078 by using PY Adjusted Baseline and by using 2014 measurements.

5.1

5.1.1

Prior to retrofit, sample spaces were tested disclosing the building’s overall outside air intake was 0.25 cfm/sf. The goal of the ECM was to reduce the building’s overall outside air intake by retrofitting the non-Alerton Air-Handling Unit (AHU) with DCV and modulating dampers. Johnson Controls used American Society of Heating, Refrigerating, and Air-Conditioning Engineers (ASHRAE) calculations to estimate that the minimum outside air ventilation requirement is 0.12 cfm/SF for an office building with 7 persons per 1,000 SF. Minimum outside air ventilation is possible when CO2 based DCV is combined with the ability to open dampers just enough to satisfy the ventilation demand. This cannot be achieved with the old two-position dampers, but can be achieved with CO2-based DCV controls and modulating dampers.

Demand-controlled operation is used to modulate outside air ventilation based on real-time occupancy. DCV reduces unnecessary over-ventilation that may occur when existing AHUs are programmed to provide ventilation for a maximum assumed occupancy. DCV saves energy while ensuring that ASHRAE Standard 62 ventilation rates are maintained at all times. Johnson Controls retrofitted non-Alerton AHUs with CO2 sensors on the return air duct. DCV was programmed for outside air activation at 800 ppm return air CO2 threshold.

Johnson Controls retrofitted non-Alerton AHU units by replacing their two-position pneumatic damper system with new dampers (if broken), new actuators and DDC controls. The new damper system has the capability to modulate between 0% to 100% open/close positions. In the DCV mode, the dampers linearly modulate between 10% to 100% open position in response to return air CO2 levels between 800 ppm and 1000 ppm.

Reducing outside air intake reduces the load on the building’s HVAC system and generates energy savings.

5.1.2

Prior to the retrofit, non-Alerton AHUs in the building were equipped with pneumatic dampers and actuators exhibiting no DCV. Sample spaces were tested and it was found that the building’s average outside air intake was 0.25 cfm/SF.

Page 22: Empire State Building Performance Year 4 M&V Report April ... · Empire State Building Performance Year 4 M&V Report Section 1 - Executive Summary 1 1. Empire State Building (ESB)

Empire State Building Performance Year 4 M&V Report

Section 5 - ECM 3: BMS Retrofit 17

5.1.3

Johnson Controls retrofitted non-Alerton AHUs with CO2 sensors on the return air duct. DCV was programmed for outside air activation at 800 ppm ‘return air CO2’ threshold. Johnson Controls also installed the new DDC damper system that is maintained at 10% minimum open position when the outside air temperature is higher than 68°F. During other times, the damper modulates in accordance with the supply valve position. Controls were programmed so that the DCV takes precedence over temperature-based damper control when return air CO2 reaches threshold.

5.1.4

The performance contract required that Johnson Controls retrofit the two-position pneumatic damper system in non-Alerton AHU units with new dampers (if broken), new actuators, DCV and DDC controls (ECM Target).

The new dampers, new actuators, DCV and DDC controls were verified to be operational (ECM Performance).

The new dampers, new actuators, DCV and DDC controls were operated in the field as designed (Actual Operation).

The analyzed plots are presented in Appendix 1. The data for the analysis was retrieved from the Metasys® trend repository and from Facility Performance Indexing‘s (FPI) trend archive. Results from the trending analysis were used to generate the following eQUEST Model inputs that determine the ECM savings.

Contract Baseline

PY Adjusted Baseline

PY Target PY ECM

Performance PY Actual Operation

Outside Air Flow Rate (cfm/sf) 0.25 0.25 0.12 0.12 0.12

Figure 5.1: BMS Retrofit ECM Model Inputs

5.2

5.2.1

The building utilizes fans to provide AHU supply air, exhaust toilet space air and to exhaust building space air. Prior to the performance contract, these fans were manually turned On/Off and did not have DDC controls to automatically schedule On/Off. Johnson Controls installed DDC controls on the AHU fans to automatically schedule On/Off. The reduced fan run time resulted in:

Reduced fan motor electric power consumption

Reduced outside air intake, thereby reducing the need to condition it

Page 23: Empire State Building Performance Year 4 M&V Report April ... · Empire State Building Performance Year 4 M&V Report Section 1 - Executive Summary 1 1. Empire State Building (ESB)

Empire State Building Performance Year 4 M&V Report

Section 5 - ECM 3: BMS Retrofit 18

As part of the BMS retrofit, all non-Alerton AHUs were connected to the newly-installed Johnson Controls field controllers. These field controllers communicate with Network Automation Engines (NAEs) that tie into ESB’s central Application and Data Server (ADX). ESB’s Metasys operator workstation allows building operations personnel to program, monitor and change HVAC schedules.

5.2.2

Prior to the performance contract, the fans did not have DDC controls to automatically schedule On/Off. The fans were manually turned On/Off. The following table shows the manually operated Pre-Installation schedule.

Fan Type Manually Operated

Pre-Installation ON Time

AHU Supply Fan (Mid Zone and High Zone) 18hrs/5d (ON-Time)

General Exhaust and Toilet Exhaust Fans 24hrs/7d (ON-Time)

Figure 5.2: Pre-Installation Schedule

5.2.3

As part of the BMS retrofit, all non-Alerton AHU supply fans were connected to BMS and the scheduling feature was enabled. The following table shows the Post-Installation conditions.

Fan Type Automatically Scheduled Post-Installation ON Time

(Target)

Automatically Scheduled Post-Installation ON Time (ECM Performance)

AHU Supply Fan (Mid Zone and High Zone) 15hrs/5d (ON-Time) 13.8hrs/5d (ON-Time)

General Exhaust and Toilet Exhaust Fans 19hrs/7d (ON-Time) 20.1hrs/7d (ON-Time)

Figure 5.3: Post-Installation Target and ECM Performance Schedule

5.2.4

The data for the analysis was retrieved from Metasys scheduling BMS page, Metasys trend repository and from FPI’s trend archive. The analyzed information is presented in this Report’s Appendix. Results from the BMS analysis were used to generate the following eQUEST Model inputs that determine the ECM savings.

Contract Baseline

PY Adjusted Baseline

PY Target PY ECM

Performance PY Actual Operation

High/Mid Fans 18hrs/5d

(ON-Time) 18hrs/5d

(ON-Time) 15hrs/5d

(ON-Time) 13.8hrs/5d (ON-Time)

13.8hrs/5d (ON-Time)

General Exhaust and Toilet Exhaust Fans

24hrs/7d (ON-Time)

24hrs/7d (ON-Time)

19hrs/7d (ON-Time)

20.1hrs/7d (ON-Time)

20.1hrs/7d (ON-Time)

Figure 5.4: Fan Scheduling ECM Model Inputs

Page 24: Empire State Building Performance Year 4 M&V Report April ... · Empire State Building Performance Year 4 M&V Report Section 1 - Executive Summary 1 1. Empire State Building (ESB)

Empire State Building Performance Year 4 M&V Report

Section 6 - ECM 4: Chiller Plant Retrofit 19

6.

The savings numbers associated with the chiller plant retrofit is shown below:

PY Target Performance savings was calculated to be $694,795 by using PY Adjusted Baseline and by using Contract Target Performance.

PY ECM Performance savings was calculated to be $912,338 by using PY Adjusted Baseline and by using performance programmed in the chiller controls.

PY Actual Operation savings was calculated to be $883,525 by using PY Adjusted Baseline and by using 2014 measurements.

6.1

6.1.1

There were four constant-speed electric chillers previously installed at ESB. This ECM provided for a retrofit of these chiller compressors with Variable Frequency Drives (VFD) and replaced chiller tubes.

1.1.. Chiller VFD Retrofit

A constant-speed chiller reacts to lower load or lower entering-condenser-water temperature by closing its pre-rotation vanes, which throttles the refrigerant flow through the compressor in an effort to economize the energy consumption. As the vanes continue to close, they create frictional losses that affect the chiller’s efficiency and limit the energy-saving potential of this approach.

Use of a VFD allows the compressor speed to modulate in response to load, evaporator pressure, and condenser pressure. Despite the small power penalty attributed to the VFDs, this control measure for the chiller yields outstanding overall efficiency improvement. Most chillers operate at part-load nearly 99% of the time which serves to enhance the overall value of this retrofit. Additionally, the soft start feature, provided by the VFD, provides further maintenance-related value by incurring less stress on the compressor motor, gears and electrical components than does a traditional motor starter.

With its patented Adaptive Capacity Control, the VFD drive learns and remembers optimum speeds for various load and operational conditions. Unlike constant-speed chillers, a variable-speed chiller also maintains a stable power factor.

1.1.. Chiller Tubes Retrofit

Pre-Installation chillers at ESB were about 18 years old. The evaporator and condenser tubes were significantly degraded over time, thereby increasing the fouling factor of the tubes which impedes heat transfer, which, in turn, negatively impacts chiller capacity and efficiency. Johnson Controls replaced the evaporator and condenser tubes with new tubes, thereby increasing chiller capacity, efficiency and service life.

Page 25: Empire State Building Performance Year 4 M&V Report April ... · Empire State Building Performance Year 4 M&V Report Section 1 - Executive Summary 1 1. Empire State Building (ESB)

Empire State Building Performance Year 4 M&V Report

Section 6 - ECM 4: Chiller Plant Retrofit 20

6.1.2

There were four constant speed electric chillers in the building. The evaporator and condenser tubes were 18 years old and were significantly fouled over time.

6.1.3

All four of the constant-speed electric chillers in the building were retrofitted with VFDs. Johnson Controls also replaced the fouled evaporator and condenser tubes with new tubes.

6.1.4

Department of Energy (DOE) electric chiller curves, available in eQUEST, were used to simulate target performance. The curves were customized for ESB by adjusting them for York-prescribed full-load performance at Air-Conditioning and Refrigeration Institute (ARI) conditions 100% load at 44°F Chilled Water (CHW) temperatures and 85°F Condenser Water (CW) temperatures (ECM Target).

Post-Installation chiller efficiency (kw/ton) was measured at the following conditions (ECM Performance):

Load conditions: 100%, 75%, 50% and 25%

CHW temperatures: 42°F, 44°F and 46°F

CW temperatures: 65°F, 75°F and 85°F

In the case of the chiller retrofit ECM, the ECM Performance represents and Actual Operation. The data analysis is presented in Appendix 2. The data for the analysis was retrieved from the Metasys trend repository and from FPI’s trend archive.

The following eQUEST Model inputs were used to determine the ECM savings.

Contract Baseline PY Adjusted Baseline PY Target PY ECM Performance PY Actual Operation

Chiller-1 (Elec) Capacity

750 Ton (Constant Speed)

750 Ton (Constant Speed)

750 Ton (VFD) 750 Ton (VFD) 750 Ton (VFD)

Chiller-1 Performance

*See Baseline Chiller Curves

*See Baseline Chiller Curves

*See Target Chiller Curves

*See Curve Fit to Measured Data

*See Curve Fit to Measured Data

Chiller-4 (Elec) Capacity

1000 Ton (Constant Speed)

1000 Ton (Constant Speed)

1000 Ton (VFD) 1000 Ton (VFD) 1000 Ton (VFD)

Chiller-4 Performance

*See Baseline Chiller Curves

*See Baseline Chiller Curves

*See Target Chiller Curves

*See Curve Fit to Measured Data

*See Curve Fit to Measured Data

Chiller-5 (Elec) Capacity

1000 Ton (Constant Speed)

1000 Ton (Constant Speed)

1000 Ton (VFD) 1000 Ton (VFD) 1000 Ton (VFD)

Chiller-5 Performance

*See Baseline Chiller Curves

*See Baseline Chiller Curves

*See Target Chiller Curves

*See Curve Fit to Measured Data

*See Curve Fit to Measured Data

Chiller-6 (Elec) Capacity

1000 Ton (Constant Speed)

1000 Ton (Constant Speed)

1000 Ton (VFD) 1000 Ton (VFD) 1000 Ton (VFD)

Chiller-6 Performance

*See Baseline Chiller Curves

*See Baseline Chiller Curves

*See Target Chiller Curves

*See Curve Fit to Measured Data

*See Curve Fit to Measured Data

*The chiller curves are presented in Appendix 2.

Figure 6.1: Chiller Retrofit ECM Model Inputs

Page 26: Empire State Building Performance Year 4 M&V Report April ... · Empire State Building Performance Year 4 M&V Report Section 1 - Executive Summary 1 1. Empire State Building (ESB)

Empire State Building Performance Year 4 M&V Report

Section 6 - ECM 4: Chiller Plant Retrofit 21

6.2

6.2.1

Chiller performance improves when higher temperature CHW is produced. For example, a typical centrifugal chiller's efficiency can be improved 15 to 25% when producing CHW at 55°F versus 42°F. In addition, the use of medium temperature CHW is a common method of preventing uncontrolled dehumidification while conditioning the sensible loads, thus significantly improving the savings available from free cooling waterside economization.

Low CHW temperatures are required to meet the building load during hot summer days. Chiller performance improvisation, without compromising capacity requirements, can be improved by incorporating CHW supply-temperature reset controls. The BMS automatically resets the Chilled Water Supply Temperature (CHWST) setpoint in response to outside air temperature conditions. Internal operation of the chiller remains within the factory-supplied Chiller Plant Controls.

However, any increase in CHWST results in greater variability of the CHW pumping system’s energy consumption. This penalty can be minimized by tuning the system to maintain minimum design flow through the AHU coils.

6.2.2

The CHWST setpoint was manually maintained at a constant 44°F temperature during most of the chiller plant operating hours.

6.2.3

The performance contract requires Johnson Controls to install a functional CHWST reset control system capable of 42°F to 50°F reset based on two-way valve positions (Contract Target).

Johnson Controls determined based on the field conditions that outside air temperature reset will better suit ESB’s needs. Also, it was determined that the increased tenant cooling requirements cannot be met with a 50°F high limit. Therefore, Johnson Controls implemented 42°F to 48°F CHWST reset for 65°F to 55°F outside air temperature (PY Target, PY ECM Performance).

ESB operated CHWST reset ECM equipment in the manual mode at constant 42°F setpoint during 2014 summer to satisfy tenant CHWST requirements (Actual Operation).

Johnson Controls retested the ECM in December 2014 for auto mode operation and found it to be working correctly during the test period. ESB is planning on operating the ECM in auto mode during 2015 summer.

Page 27: Empire State Building Performance Year 4 M&V Report April ... · Empire State Building Performance Year 4 M&V Report Section 1 - Executive Summary 1 1. Empire State Building (ESB)

Empire State Building Performance Year 4 M&V Report

Section 6 - ECM 4: Chiller Plant Retrofit 22

6.2.4

The implementation of CHWST reset control was verified by analyzing CHWST vs. time. The analyzed plots are presented in Appendix 3. The data for the analysis was retrieved from the Metasys trend repository and from FPI’s trend archive.

Results from the trending analysis were used to generate the following eQUEST Model inputs that determine the ECM savings.

6.3

6.3.1

During designed operating conditions, the Pre-Installation CHW loop was running at less than 10°F CHW delta-T conditions. This lower CHW delta-T decreases chiller efficiency and also increases CHW pump flow thereby its electric power consumption. A low delta-T also inhibits the ability of the chiller to operate at peak capacity. Hence, increasing the CHW loop delta-T to an optimal design setting was desired.

CHW loop delta-T was increased by:

Changing out the three-way valves for two-way valves in the Pre-Installation AHUs that were included in the project

Minimizing CHW flow rate using CHW pump VFD automation

Post-Installation CHW loop delta-T was targeted to operate close to 10°F at design conditions. This ECM improves energy savings by increasing chiller efficiency and also improves operational capability by increasing chiller capacity.

Page 28: Empire State Building Performance Year 4 M&V Report April ... · Empire State Building Performance Year 4 M&V Report Section 1 - Executive Summary 1 1. Empire State Building (ESB)

Empire State Building Performance Year 4 M&V Report

Section 6 - ECM 4: Chiller Plant Retrofit 23

6.3.2

The following conditions were observed during the Pre-Installation building audit:

Low Zone CHW loop design condition delta-T: less than 7.8°F

Mid Zone CHW loop design condition delta-T: less than 6°F

High Zone CHW loop design condition delta-T: less than 6.9°F

6.3.3

In order to achieve the objective of this ECM, the performance contract required Johnson Controls to:

Replace the three-way valves with two-way valves in the Pre-Installation AHUs that were included in project and minimize CHW flow rate using CHW pump VFD automation (ECM Target).

The above scope was verified to be implemented by Johnson Controls (ECM Performance).

Most of the three way valves in ESB’s lobby are manually held open and the lobby is kept cool during summer. Several floors in the low zone are empty and the CHW pipes are flanged off (so no load). This contributes to the low delta-T in the low zone. Existence of 3‐way valves is not local to the lobby but to parts of the entire building. The replacement of those 3‐way valves is ESB's responsibility and ESB is currently working on issuing a PO for the replacements. Three way valves contribute to the low delta-T in the high zone and mid zone. Johnson Controls trended the loop delta-T under part-load conditions and the summary of the results are shown below (Actual Operation). The details of the analysis are shown in the Appendix 3.

Low Zone CHW loop part-load condition delta-T: 2°F to 8°F

Mid Zone CHW loop part-load condition delta-T: 3°F to 11°F

High Zone CHW loop part-load condition delta-T: 3°F to 9°F

6.3.4

The implementation of CHW loop delta-T was verified by checking the two-way valve implementation and the CHW VFD automation implementation. Actual building operation was verified by analyzing CHW loop delta-T vs. time. The analyzed plots are presented in this Report’s Appendix 3. The data for the analysis was retrieved from the Metasys trend repository and from FPI’s trend archive.

The following eQUEST Model inputs were used to determine the ECM savings:

Page 29: Empire State Building Performance Year 4 M&V Report April ... · Empire State Building Performance Year 4 M&V Report Section 1 - Executive Summary 1 1. Empire State Building (ESB)

Empire State Building Performance Year 4 M&V Report

Section 6 - ECM 4: Chiller Plant Retrofit 24

Contract Baseline

PY Adjusted Baseline

PY Target PY ECM

Performance PY Actual Operation

Low Zone Loop Delta T

7.8°F (At Design Load)

7.8°F (At Design Load)

10°F (At Design Load)

10°F (At Design Load)

10°F (At Design Load)

Mid Zone Loop Delta T

<6°F (At Design Load)

<6°F (At Design Load)

10°F (At Design Load)

10°F (At Design Load)

10°F (At Design Load)

High Zone Loop Delta T

<6°F (At Design Load)

<6°F (At Design Load)

10°F (At Design Load)

10°F (At Design Load)

10°F (At Design Load)

Figure 6.3: CHW Loop Delta-T Enhancement ECM Model Inputs

6.4

6.4.1

This ECM automated the manually-controlled variable flow CHW system into an automatically controlled variable flow CHW system. The pump flow is automatically controlled to meet the CHW loop differential pressure setpoint. The installed system was tuned in the field to find the correct differential pressure setpoint enabling system to meet varying building load conditions.

Varying the speed of a motor to match the actual load improves control as well as reduces electrical motor power (kW), which may result in both comfort improvement and electrical energy savings.

Varying the speed of the motor is accomplished by varying voltage and frequency to the motor. The motor is connected to the CHW pump. As the system’s load changes, consequently so does the required motor driven output. A control program and the VFD will modulate the speed of the motor and match the output to the load. By reducing the speed of an electric motor, the energy required by the motor is reduced significantly. The actual power required is proportional to the cube of the speed. For example, if a motor’s speed is reduced to 80%, the motor’s energy consumption is decreased by approximately 50%. The theoretical energy savings through speed reduction is shown in the general relationship below:

(bhp2/bhp1)= (W2/W1)^3

where:

w2 = VFD controlled motor speed (varies)

w1 = motor/fan/pump existing speed (constant)

bhp2 = VFD controlled motor brake horsepower (varies)

bhp1 = Brake horsepower required before VFD is installed

The generic pump characteristic plot below illustrates that generic pump power consumption reduces with reduction in VFD speed. For example, reducing the VFD speed by 10% reduces pump energy usage by 27%.

Page 30: Empire State Building Performance Year 4 M&V Report April ... · Empire State Building Performance Year 4 M&V Report Section 1 - Executive Summary 1 1. Empire State Building (ESB)

Empire State Building Performance Year 4 M&V Report

Section 6 - ECM 4: Chiller Plant Retrofit 25

Figure 6.4: Reduction in Generic Pump Power Consumption when Retrofitted with VFD

Two-way valves on the cooling coils ensure that CHW is supplied only when there is demand at the AHU. Hence, two-way valves create differential pressure variation in the CHW loop. The VFD speed is reduced when loop differential pressure decreases and the loop minimum flow can still be maintained.

In addition to the energy savings, this ECM increases equipment reliability and decreases operating cost by reducing the load on the bearings.

6.4.2

All CHW pumps were equipped with VFDs. But the drives were not set up to adjust speed automatically with varying building differential pressure. All VFDs were operating at constant full speed during most of the operating times.

6.4.3

The performance contract requires Johnson Controls to install a functional CHW pump VFD automation system capable of automatically varying VFD speed between 100% and 50% (min) to meet building differential pressure setpoint (ECM Target). The unit is fully installed for automatically varying VFD Speed between 100% and 33% (ECM Performance).

Trending analysis shows that, in 2014, the CHW pump VFDs were run in the manual mode at reduced speeds (Actual Operation). The verification indicates that:

Low Zone pumps were operating at an average speed of 59%.

Mid Zone pumps were operating at an average speed of 67%.

High Zone pumps were operating at an average speed of 67%.

CHW pumps in the automatic mode used to go offline in the event of a temporary control system outage. ESB could not risk temporary loss of CHW pumps due to stringent new tenant requirements. Therefore, ESB had to operate the CHW pumps in the manual mode. ESB installed a new UPS/RIB relay system in late 2014 summer that will prevent loss of CHW pumps in the event of a control system outage. This installation will help ESB operate the ECM in the automatic mode in 2015 summer.

Page 31: Empire State Building Performance Year 4 M&V Report April ... · Empire State Building Performance Year 4 M&V Report Section 1 - Executive Summary 1 1. Empire State Building (ESB)

Empire State Building Performance Year 4 M&V Report

Section 6 - ECM 4: Chiller Plant Retrofit 26

6.4.4

The implementation of CHW pump VFD automation was verified by checking the Metasys software. Actual building operation was verified by analyzing VFD speed vs. time. The analyzed plots are presented in Appendix 3. The data for the analysis was retrieved from the Metasys trend repository and from FPI’s trend archive.

Results from the trending analysis were used to generate the following eQUEST Model inputs that determine the ECM savings.

Contract Baseline PY Adjusted Baseline PY Target PY ECM Performance PY Actual Operation

Flow Ctrl/Min

VFD Manual (100% Speed All Times)

VFD Manual (100% Speed All Times)

VFD Auto (100% to 50% Min)

VFD Auto (100% to 33% Min)

VFD Manual (59% average)

Flow Ctrl/Min

VFD Manual (100% Speed All Times)

VFD Manual (100% Speed All Times)

VFD Auto (100% to 50% Min)

VFD Auto (100% to 33% Min)

VFD Manual (67% average)

Flow Ctrl/Min

VFD Manual (100% Speed All Times)

VFD Manual (100% Speed All Times)

VFD Auto (100% to 50% Min)

VFD Auto (100% to 33% Min)

VFD Manual (67% average)

Figure 6.5: CHW Pump VFD Automation ECM Model Inputs

6.5

6.5.1

Chiller performance increases significantly at lower CW temperatures. CW supply-temperature-reset strategy was implemented to provide low temperature CW, to the extent allowed by the chiller manufacturer. Cooling tower fan power increases to produce lower temperature CW, but chiller efficiency gains will typically dominate the economic considerations of this optimization strategy.

Most of the energy consumed by a chiller is used to move refrigerant vapor from the evaporator (low pressure) to the condenser (high pressure). As the pressure differential between the evaporator and condenser increases, the compressor must work harder to move the refrigerant. Lowering CW temperature decreases this pressure differential, so the compressor does less work. Electric chiller efficiency improves with decreased CW supply temperature.

Cooling tower controls are initially set to achieve 70°F tower water during design conditions. When ambient conditions are appropriate, the controls can be reset to produce water that is cooler than 70°F. The cooling tower water supply temperature was reset to achieve 5°F cooling tower approach above ambient wet-bulb temperature and it will generate significant energy savings without wasting cooling tower fan energy. The reset was programmed to be 60°F to 75°F, when outside air wet bulb temperature was between 55°F and 70°F.

Page 32: Empire State Building Performance Year 4 M&V Report April ... · Empire State Building Performance Year 4 M&V Report Section 1 - Executive Summary 1 1. Empire State Building (ESB)

Empire State Building Performance Year 4 M&V Report

Section 6 - ECM 4: Chiller Plant Retrofit 27

6.5.2

The cooling tower water supply temperature setpoint was manually maintained at a constant 70°F temperature during most of the operating times.

6.5.3

The performance contract requires Johnson Controls to install a functional CW reset control system that is capable of achieving 65°F to 70°F reset (Contract Target).

The CWST reset was programmed in the field as 60°F to 75°F reset (which is operator adjustable) to suit field conditions (PY Target and PY ECM Performance). The CWST reset logic was switched to auto mode for the first time on August 19, 2014. It was observed that CWST reset was responding to changes in OADPT and the towers were not capable of achieving 5°F approach. The programming was changed on August 25, 2014 so that CWST reset would respond to OAWBT and to a 7°F tower approach. This change has resulted in reduced tower fan operation. The base project incorporated an automatic 72°F CWST setpoint when the steam chillers are operated.

Trending analysis shows that the building operation personnel manually maintained CW supply temperature at 65°F most of the time in 2014 summer to satisfy tenant CW requirements (Actual Operation).

ESB will use the ECM in the automatic mode in 2015 summer.

6.5.4

The implementation of CW supply temperature reset controls was verified by analyzing Metasys programming. Actual building operation was verified by analyzing CW supply temperature vs. time trends. The analyzed plots are presented in Appendix 3. The data for the analysis was retrieved from the Metasys trend repository and from FPI’s trend archive.

Results from the trending analysis were used to generate the following eQUEST Model inputs that determine the ECM savings.

Contract Baseline

PY Adjusted Baseline

PY Target PY ECM Performance PY Actual Operation

Setpoint Control 70°F Fixed 70°F Fixed 60°F to 75°F Reset 60°F to 75°F Reset 65°F Fixed (Manual)

Figure 6.6: CW Supply Temperature Model Inputs

Page 33: Empire State Building Performance Year 4 M&V Report April ... · Empire State Building Performance Year 4 M&V Report Section 1 - Executive Summary 1 1. Empire State Building (ESB)

Empire State Building Performance Year 4 M&V Report

Section 6 - ECM 4: Chiller Plant Retrofit 28

6.6

6.6.1

The cooling tower has ten cells, each of which is fitted with a separate cooling fan. Eight of the fans are single speed On/Off type. Two of the fans were fitted with manually controllable VFD.

This ECM automated the manually controlled cooling tower VFD system into an automatically controlled cooling tower VFD system. The fan speed is now automatically controlled to meet the Cooling Tower Water Leaving Temperature (CTWLT) setpoint. In addition, controls were installed to automatically stage the two fan VFDs.

Varying the speed of a motor to match the actual load improves control as well as reduces electrical motor power (kW) which typically results in both comfort improvement and electrical energy savings.

Varying the speed of the motor is accomplished by varying voltage and frequency to the fan motor. As a consequence of the system load changes, the required motor driven output is changed also. A control program and the VFD modulate the speed of the motor matching the output to the load. By reducing the speed of an electric motor, the energy required by the motor is reduced significantly. The actual power required is proportional to the cube of the speed. For example, if a motor’s speed is reduced to 80%, the motor’s energy consumption is decreased by approximately 50%. The theoretical energy savings through speed reduction is shown in the general relationship below:

(bhp2/bhp1)= (W2/W1)^3

where:

w2 = VFD controlled motor speed (varies)

w1 = motor/fan/pump existing speed (constant)

bhp2 = VFD controlled motor brake horsepower (varies)

bhp1 = Brake horsepower required before VFD is installed

The generic pump characteristic plot below illustrates that generic pump power consumption reduces with reduction in VFD speed. For example, reducing the VFD speed by 10% reduces pump energy usage by 27%.

Page 34: Empire State Building Performance Year 4 M&V Report April ... · Empire State Building Performance Year 4 M&V Report Section 1 - Executive Summary 1 1. Empire State Building (ESB)

Empire State Building Performance Year 4 M&V Report

Section 6 - ECM 4: Chiller Plant Retrofit 29

Figure 6.7: Reduction in Generic Fan Power Consumption when Retrofitted with VFD

In addition to the energy savings, this ECM increases equipment reliability and decreases operating cost by reducing the load on the bearings.

6.6.2

The cooling tower has ten cells each of which is fitted with a separate cooling fan. Eight of the fans are single speed On/Off type. Two of the fans were fitted with manually controllable VFD.

6.6.3

The performance contract requires Johnson Controls to install an automatic cooling tower VFD system (ECM Target).

Johnson Controls verified that the manually-controlled cooling tower VFD system was converted into an automatically-controlled cooling tower VFD system. The fan speed is now automatically controlled to meet the CTWLT setpoint. In addition, controls were installed to automatically stage the two fan VFDs (ECM Performance).

2014 trending analysis shows that the ECM equipment was operated as designed (Actual Operation).

6.6.4

The implementation of cooling tower fan VFD automation was verified by analyzing VFD speed trends. The analyzed plots are presented in this Report’s Appendix. The data for the analysis was retrieved from the Metasys trend repository and from FPI’s trend archive.

Results from the trending analysis were used to generate the following eQUEST Model inputs that determine the ECM savings.

Contract Baseline

PY Adjusted Baseline

PY Target PY ECM

Performance PY Actual Operation

Tower Fan VFD One Speed

Fan One Speed

Fan VFD on

Towers 4 and 5 VFD on

Towers 4 and 5 VFD on

Towers 4 and 5

Figure 6.8: Cooling Tower Fan VFD Automation ECM Model Inputs

Page 35: Empire State Building Performance Year 4 M&V Report April ... · Empire State Building Performance Year 4 M&V Report Section 1 - Executive Summary 1 1. Empire State Building (ESB)

Empire State Building Performance Year 4 M&V Report

Section 6 - ECM 4: Chiller Plant Retrofit 30

6.7

6.7.1

This ECM automated the manually-controlled variable flow CW system into an automatically controlled variable flow CW system. The pump flow is automatically controlled to meet CW flow setpoint determined by the electric chiller loading conditions.

Varying the speed of a motor to match the actual load improves control as well as reduces electrical motor power (kW) which results in both comfort improvement and electrical energy savings.

Varying the speed of the motor is accomplished by varying voltage and frequency to the motor. The motor is connected to the CW pump. As the system load changes, consequently, so does the required motor driven output. A control program and the VFD will modulate the speed of the motor and match the output to the load. By reducing the speed of an electric motor, the energy required by the motor is reduced significantly. The actual power required is proportional to the cube of the speed. For example, if a motor’s speed is reduced to 80%, the motor’s energy consumption is decreased by approximately 50%. The theoretical energy savings through speed reduction is shown in the general relationship below:

(bhp2/bhp1)= (W2/W1)^3

where:

w2 = VFD controlled motor speed (varies)

w1 = motor/fan/pump existing speed (constant)

bhp2 = VFD controlled motor brake horsepower (varies)

bhp1 = Brake horsepower required before VFD is installed

The generic pump characteristic plot below illustrates that generic pump power consumption reduces with reduction in VFD speed. For example, reducing the VFD speed by 10% reduces pump energy usage by 27%.

Figure 6.9: Reduction in Generic Pump Power Consumption when Retrofitted with VFD

Page 36: Empire State Building Performance Year 4 M&V Report April ... · Empire State Building Performance Year 4 M&V Report Section 1 - Executive Summary 1 1. Empire State Building (ESB)

Empire State Building Performance Year 4 M&V Report

Section 6 - ECM 4: Chiller Plant Retrofit 31

In addition to the energy savings, this ECM increases equipment reliability and decreases operating cost by reducing the load on the pump bearings.

6.7.2

All CW pumps were equipped with VFDs, but the drives were not configured to adjust speed automatically with varying chiller load. All VFDs were operating at constant full speed during most of the operating times.

6.7.3

The savings from this ECM were not guaranteed in the contract (ECM Target).

Johnson Controls installed a functional CW pump VFD automation system that is capable of automatically varying VFD speed to meet CW flow requirements set by the electric chiller load conditions. CW pump VFD automation cannot be used when the steam chillers are operational (ECM Performance).

Trending analysis shows that the CW pump VFDs were run in the manual mode in 2014 at an average speed of 80% (Actual Operation).

ESB is unable to use this ECM that reduces CW flow due to new tenant requirements that require high CW flow. ESB plans on doing a hydronic study in 2015 that will help them to operate this ECM in the automatic mode.

6.7.4

The implementation of CW pump VFD automation was verified by checking the Metasys software. Actual building operation was verified by analyzing VFD speed vs. time. The analyzed plots are presented in this Report’s Appendix. The data for the analysis was retrieved from the Metasys trend repository and from FPI’s trend archive.

Results from the trending analysis were used to generate the following eQUEST Model inputs that determine the ECM savings.

Contract Baseline

PY Adjusted Baseline

PY Target PY ECM

Performance PY Actual Operation

CW Pump Control

100% Fixed 100% Fixed 100% Fixed VFD Auto (100%

to 33% Min) 80% Manual

(Average)

Figure 6.10: CW Pump VFD Automation ECM Model Inputs

Page 37: Empire State Building Performance Year 4 M&V Report April ... · Empire State Building Performance Year 4 M&V Report Section 1 - Executive Summary 1 1. Empire State Building (ESB)

Empire State Building Performance Year 4 M&V Report

Section 7 - ECM 5: Tenant Energy Management Portal 32

7.

The savings numbers associated with the TEM is shown below:

PY Target Performance savings was calculated to be $27,334 by using 3.02% annual escalation rate.

PY ECM Performance savings was calculated to be $0.

PY Actual Operation savings was calculated to be $0.

7.1

7.1.1

Johnson Controls set up an improvised energy dashboard for the customer. The dashboard was developed using Johnson Controls’ Gridlogix software and functions as a web-based tool that displays a number of energy use variables.

Johnson Controls provides a connection to the building controls system with automatic data transfers of electric submeter data. The dashboard shows energy use compared to relevant variables. It also provides information for each floor of the building and is password protected. A series of alarms is triggered if energy use exceeds expected ranges on any tenant floor. The tenant is able to view current energy consumption in kilowatts along with associated metrics (kW/sq. ft., kW, kWh etc.) and compare it to historical consumption. The tenant can also view their comparative consumption relative to other tenants who are under the same ownership structure.

A web-based portal displaying tenant-specific electric utility consumption is metered building-wide using a Satec BFM136 utility grade smart-meter network, endorsing energy-efficient practices within the tenant space.

The EnNET®/AEM platform provides 15 minute meter data and creates a normalized data base that can be used to support Time Series profiling, reporting to ISO and future integration with property management software for creating invoices based on current meter read should a tenant terminate a lease.

7.1.2

Johnson Controls’ Gridlogix software verified the connectivity to each meter. Gridlogix was not responsible for the physical connection (wired or wireless) to the existing main/sub meters or a third party device required to collect the 15 minute pulse data. The data was, however, in a protocol format that Johnson Controls supports; protocols such as Modbus, BACnet®, Simple Network Management Protocol. The data protocol used was BACnet, which fully supported auto discovery. Gridlogix commissioned and verified the EnNET software connection and read the meter data properly. The Gridlogix software established the rules base and monitored notifications for successfully creating, archiving and ensuring quality of service. Gridlogix, too, commissioned the AEM application and built the web pages to properly display metering data,

Page 38: Empire State Building Performance Year 4 M&V Report April ... · Empire State Building Performance Year 4 M&V Report Section 1 - Executive Summary 1 1. Empire State Building (ESB)

Empire State Building Performance Year 4 M&V Report

Section 7 - ECM 5: Tenant Energy Management Portal 33

time series analysis, real-time metering information and created notifications based on usage parameters.

7.1.3

The deployment of TEM was completed in Year 2011. Due to increasing installation of submeters and requests to contemporize existing TEM, Johnson Controls proceeded with the development of enhanced TEM. During third quarter of Year 2012, a new dashboard, TEM2, went into production to meet and exceed the growing platform at the site. TEM2 platform includes customer facing interactive applications such as:

A green kiosk displaying ‘how to save energy’ tips

Building/industry tweets

Sustainability trending

Information on various retrofits performed at site

Tenant-specific dashboard to display various matrices

Reporting module – tenant and administration based

Energy analyzer with ability to view sub-metering at a granular level

The new platform was launch in first quarter of 2013. The platform includes two front end interfaces, namely, tenant portal and admin portal. The tenant portal allows tenants to view metered data based on each floor they occupy along with ability to dissect data to display various loads within each leased floors. This includes, floor by floor analysis for multi-floor tenants, and for large tenants, ability to view plug, HVAC and lighting loads along with a cost widget section which enables tenants to review estimated energy costs and savings based on their actual energy rates. The admin portal allows ESB to view metered data by building, floor, or by suite. It allows ESB to monitor efficient tenants and place best practices and incentives to other tenants.

ESB and Johnson Controls agreed to not claim TEM savings in 2014 because of Tenant submeter inaccuracy issues.

7.1.4

The contract methodology calls for observing tenant behavior improvement by measuring space temperature variations to setpoint. Johnson Controls finds that this methodology is not practically possible. Given the magnitude of this ECM savings relative to the entire project savings and the practical complexity in measurement, Johnson Controls requests the customer that this ECM savings be made non-measured.

Page 39: Empire State Building Performance Year 4 M&V Report April ... · Empire State Building Performance Year 4 M&V Report Section 1 - Executive Summary 1 1. Empire State Building (ESB)

Empire State Building Performance Year 4 M&V Report

Section 8 - ECM 6: Low Zone and Mid Zone PFHX 34

8.

The savings numbers associated with the PFHX is shown below:

PY Target Performance savings was calculated to be $202,899 by using 2014 field measurements.

PY ECM Performance savings was calculated to be $202,899 by using 2014 field measurements.

PY Actual Operation savings was calculated to be $202,899 by using 2014 field measurements.

8.1

8.1.1

ESB’s CHW requirement during winter/shoulder months has increased in the past few years due to change in tenant occupancy patterns. Chiller plant efficiency is low when the plant is operated under low part-load winter/shoulder conditions. PFHXs can provide free cooling by using the cold cooling tower water to chill the CHW and keep the mechanical chillers off. Energy is saved by avoiding chiller plant operation during low load.

8.1.2

Electric chillers were primarily used to produce chilled water during winter/shoulder months.

8.1.3

A 500 ton PFHX was installed in the low zone and a 1000 ton PFHX was installed in the mid zone. Cold tower water is redirected through the cold side of the two PFHXs when the OAWBT is less than 43°F. CHW is cooled by redirecting it through the hot side of the PFHXs.

8.1.4

The PFHXs are guaranteed to achieve 2.6°F approach temperature (including the measurement tolerance of 0.6°F) when operating under design conditions shown in Figure 8.1. The approach temperatures and PFHX cooling loads were measured in the field (see Appendix 4). It can be observed that the PFHXs did not operate near design load conditions, but the approach temperature was within the 2.6°F limit during most conditions.

PFHX Capacity

(Tons) Design Cold Side

Flow (gpm) Design Hot Side

Flow (gpm)

Low Zone PFHX 500 1,200 1,200

Mid Zone PFHX 1,000 2,400 2,400

Figure 8.1: PFHX design operating condition

The process of incorporating a PFHX model into the ESB eQUEST Model is very complex. Therefore, the savings are directly derived by measuring the PFHX cooling load and calculating the corresponding electric chiller avoided cost. The field data for the first three months in the PY is missing and it is replaced with a degree day based average cooling load calculated from PFHX field data collected during rest of the PY months.

Page 40: Empire State Building Performance Year 4 M&V Report April ... · Empire State Building Performance Year 4 M&V Report Section 1 - Executive Summary 1 1. Empire State Building (ESB)

Empire State Building Performance Year 4 M&V Report

Appendix 35

Appendix List

Appendix 1: BMS Retrofit Data Analysis

Appendix 2: Chiller Retrofit Data Analysis

Appendix 3: Chiller Plant Retrofit Data Analysis

Appendix 4: PFHX Data Analysis

Appendix 5: ESB eQUEST Model Input Table

Appendix 6: Baseline Adjustments

Appendix 7: Utility Analysis

Page 41: Empire State Building Performance Year 4 M&V Report April ... · Empire State Building Performance Year 4 M&V Report Section 1 - Executive Summary 1 1. Empire State Building (ESB)

Empire State Building Performance Year 4 M&V Report

Appendix 1: BMS Retrofit Data Analysis 36

Appendix 1: BMS Retrofit Data Analysis

Damper Retrofit and DCV

The goal of the ECM was to reduce the building’s overall outside air intake by retrofitting the non-Alerton AHU with DCV and modulating dampers. Minimum outside air ventilation is possible when CO2-based DCV is combined with the ability to open dampers just enough to satisfy the ventilation demand. This cannot be achieved with the old two-position dampers, but can be achieved with CO2 based DCV controls and modulating dampers.

Demand-controlled ventilation is used to modulate outside air ventilation based on real time occupancy. DCV reduces over-ventilation that may result when existing AHUs are set to provide ventilation for a maximum assumed occupancy.

Also, the dampers modulate based on outside air temperature for temperature/economizer control.

Johnson Controls retrofitted non-Alerton AHUs with CO2 sensor on the return air duct. DCV was programmed for outside air activation at 800 ppm ‘return air CO2’ threshold. Also, Johnson Controls retrofitted non-Alerton AHU units by replacing their two-position pneumatic damper system with new dampers (if broken), new actuators and DDC controls. The new damper system has the capability to modulate anywhere between 0% to 100% open/close position.

Outside air dampers are in their minimum position when the CO2 level is below the 800 ppm threshold and the temperature control is not calling for dampers to open further. Outside air dampers modulate linearly between their minimum (10%) position and full open (100%) position when the CO2 level is between 800ppm and 1000 ppm, and/or when the temperature control is calling for dampers to open further. The analyzed data trends (shown in this section) indicated that outside damper position increased when the CO2 ppm in the return air increased above the threshold level of 800ppm. The data trends demonstrate that the DCV system was installed and is operational.

Figures A-1.1 through Figures A-1.4 shows the behavior of dampers relative to return air CO2 levels for a few sample AHUs.

Page 42: Empire State Building Performance Year 4 M&V Report April ... · Empire State Building Performance Year 4 M&V Report Section 1 - Executive Summary 1 1. Empire State Building (ESB)

Empire State Building Performance Year 4 M&V Report

Appendix 1: BMS Retrofit Data Analysis 37

Figure A-1.1: AHU 27-3 Mixed Damper Position vs Return Air CO2 Level

Figure A-1.2: AHU 68-2 Mixed Damper Position vs Return Air CO2 Level

Page 43: Empire State Building Performance Year 4 M&V Report April ... · Empire State Building Performance Year 4 M&V Report Section 1 - Executive Summary 1 1. Empire State Building (ESB)

Empire State Building Performance Year 4 M&V Report

Appendix 1: BMS Retrofit Data Analysis 38

Figure A-1.3: AHU 51-4 Mixed Damper Position vs Return Air CO2 Level

Figure A-1.4: AHU 68-3 Mixed Damper Position vs Return Air CO2 Level

Page 44: Empire State Building Performance Year 4 M&V Report April ... · Empire State Building Performance Year 4 M&V Report Section 1 - Executive Summary 1 1. Empire State Building (ESB)

Empire State Building Performance Year 4 M&V Report

Appendix 1: BMS Retrofit Data Analysis 39

Fan Scheduling

The building utilizes fans to provide AHU supply air, exhaust toilet space air and to exhaust building space air. Prior to the performance contract, the fans did not have the DDC controls to automatically schedule On/Off. Johnson Controls installed DDC controls on the AHU’s to automatically schedule On/Off.

As part of the BMS retrofit, all non-Alerton AHU supply fans were connected to BMS and the scheduling feature was enabled.

Mid Zone/High Zone AHU Supply Fan Scheduling

Supply fan run status data was taken from the Metasys data server and the trend data for sample units are shown in Figures A-1.6 through A-1.14. Figure A-1.5 shows the average fan operating hours.

AHU Name Average

Operating Hours

AHU 26-2 13.0

AHU 30-5 13.9

AHU 40-1 14.0

AHU 42-2 13.8

AHU 48-4 13.9

AHU 51-3 14.0

AHU 51-4 13.9

AHU 68-3 13.6

AHU 76-1 14.0

Average 13.8

Figure A-1.5: Average Daily Operating Hours for AHU Fans

Page 45: Empire State Building Performance Year 4 M&V Report April ... · Empire State Building Performance Year 4 M&V Report Section 1 - Executive Summary 1 1. Empire State Building (ESB)

Empire State Building Performance Year 4 M&V Report

Appendix 1: BMS Retrofit Data Analysis 40

Figure A-1.6: AHU 26-2 Daily Operation Hours

Figure A-1.7: AHU 30-5 Daily Operation Hours

Page 46: Empire State Building Performance Year 4 M&V Report April ... · Empire State Building Performance Year 4 M&V Report Section 1 - Executive Summary 1 1. Empire State Building (ESB)

Empire State Building Performance Year 4 M&V Report

Appendix 1: BMS Retrofit Data Analysis 41

Figure A-1.8: AHU 40-1 Daily Operation Hours

Figure A-1.9: AHU 42-2 Daily Operation Hours

Page 47: Empire State Building Performance Year 4 M&V Report April ... · Empire State Building Performance Year 4 M&V Report Section 1 - Executive Summary 1 1. Empire State Building (ESB)

Empire State Building Performance Year 4 M&V Report

Appendix 1: BMS Retrofit Data Analysis 42

Figure A-1.10: AHU 48-4 Daily Operation Hours

Figure A-1.11: AHU 51-3 Daily Operation Hours

Page 48: Empire State Building Performance Year 4 M&V Report April ... · Empire State Building Performance Year 4 M&V Report Section 1 - Executive Summary 1 1. Empire State Building (ESB)

Empire State Building Performance Year 4 M&V Report

Appendix 1: BMS Retrofit Data Analysis 43

Figure A-1.12: AHU 51-4 Daily Operation Hours

Figure A-1.13: AHU 68-3 Daily Operation Hours

Page 49: Empire State Building Performance Year 4 M&V Report April ... · Empire State Building Performance Year 4 M&V Report Section 1 - Executive Summary 1 1. Empire State Building (ESB)

Empire State Building Performance Year 4 M&V Report

Appendix 1: BMS Retrofit Data Analysis 44

Figure A-1.14: AHU 76-1 Daily Operation Hours

Page 50: Empire State Building Performance Year 4 M&V Report April ... · Empire State Building Performance Year 4 M&V Report Section 1 - Executive Summary 1 1. Empire State Building (ESB)

Empire State Building Performance Year 4 M&V Report

Appendix 2: Chiller Retrofit Data Analysis 45

Appendix 2: Chiller Retrofit Data Analysis

Chiller Curve Fit Modeling Methodology

Trended chiller data was used to create custom chiller performance curves in eQUEST for best fit of the data. The data that was used to calculate chiller performance includes:

Chiller input kW

CHWST

CHWRT (used for comparison and troubleshooting)

CHW flow rate

Condenser Water Leaving Temperature (CWLT) (used for comparison and troubleshooting)

Condenser Water Entering Temperature (CWET)

From the trended data, several output values were calculated, including

Chiller load (tons)

Adjusted chiller capacity, to account for CHWST and CWET impacts (this was calculated using the default eQUEST capacity adjustment curve, which is typical for most centrifugal chillers.)

% Full-load, using calculated adjusted capacity and calculated load

Chiller Efficiency (kW/ton)

To compare the DOE2 default curves to the actual trended chiller data, the chiller kW was calculated for the given trend conditions for all of the data points, which was then compared to the trended chiller kW by calculating the Mean Bias Error (MBE), and the Root Mean Square Error (RMSE). For the entire data set, an overall MBE and Coefficient of variation (Cv) for the RMSE was then calculated.

MBE =𝑘𝑊𝑚𝑒𝑎𝑠𝑢𝑟𝑒𝑑−𝑘𝑊𝑐𝑎𝑙𝑐𝑢𝑙𝑎𝑡𝑒𝑑

𝑘𝑊𝑚𝑒𝑎𝑠𝑢𝑟𝑒𝑑 𝐶𝑉(𝑅𝑀𝑆𝐸) =

√∑ (𝑘𝑊𝑚𝑒𝑎𝑠𝑢𝑟𝑒𝑑−𝑘𝑊𝑐𝑎𝑙𝑐𝑢𝑙𝑎𝑡𝑒𝑑)2𝑛

1𝑛

𝑘𝑊̅̅ ̅̅ ̅𝑚𝑒𝑎𝑠𝑢𝑟𝑒𝑑

The best fit was determined by applying the solver function in Microsoft Excel® to minimize the Coefficient of Variation for the data set, while using constraints to maintain the specified full-load ARI condition efficiency. For many of the chillers, limited data was available for standard ARI rating conditions (ARI rating conditions are 100% load at 85°F entering CWET and 44°F leaving CHWST). These ARI data points are values at which the eQUEST performance curves are normalized. For the chillers with no trended points at ARI conditions, engineering judgment was used to determine an acceptable ARI rating for the chiller. This involved finding the full-load points available, and adjusting the measured performance at that point to account for the variance in conditions from ARI rating conditions (e.g. a chiller operating at full-load with 75°F CWET has a lower kW/ton than the same chiller operating at 85°F CWET).

Page 51: Empire State Building Performance Year 4 M&V Report April ... · Empire State Building Performance Year 4 M&V Report Section 1 - Executive Summary 1 1. Empire State Building (ESB)

Empire State Building Performance Year 4 M&V Report

Appendix 2: Chiller Retrofit Data Analysis 46

After finding a best-fit for the data by solving for the curves to minimize the coefficient of variation, these custom curves were used to calculate the ECM performance of the chillers. Target and ECM performance fit information for each chiller is shown on the following pages.

Figure A-2.1 compares the Baseline, contract target and 2014 ECM chiller performance numbers.

Baseline Target ECM Performance

Low Zone

Chiller-1

Rated Efficiency at ARI conditions (kW/ton)

0.74 0.80 0.65

IPLV - Integrated Part-load Value (kW/ton)

0.65 0.47 0.53

Curves Default DOE2 Centrifugal Curves

Default DOE2 Variable Speed Drive (VSD) Centrifugal Curves

Custom best-fit to trended data

Source Contract Contract Trended data

Mid Zone Chiller-4

Rated Efficiency at ARI conditions (kW/ton)

0.73 0.71 0.62

IPLV - Integrated Part-load Value (kW/ton)

0.64 0.42 0.52

Curves Default DOE2 Centrifugal Curves

Default DOE2 VSD Centrifugal Curves

Custom best-fit to trended data

Source Contract Contract Trended data

Mid Zone Chiller-5

Rated Efficiency at ARI conditions (kW/ton)

0.73 0.71 0.58

IPLV - Integrated Part-load Value (kW/ton)

0.64 0.42 0.47

Curves Default DOE2 Centrifugal Curves

Default DOE2 VSD Centrifugal Curves

Custom best-fit to trended data

Source Contract Contract Trended data

High Zone

Chiller-6

Rated Efficiency at ARI conditions (kW/ton)

0.85 0.82 0.62

IPLV - Integrated Part-load Value (kW/ton)

0.75 0.48 0.49

Curves Default DOE2 Centrifugal Curves

Default DOE2 VSD Centrifugal Curves

Custom best-fit to trended data

Source Contract Contract Trended data

Figure A-2.1: ESB Chiller Performance Summary

Page 52: Empire State Building Performance Year 4 M&V Report April ... · Empire State Building Performance Year 4 M&V Report Section 1 - Executive Summary 1 1. Empire State Building (ESB)

Empire State Building Performance Year 4 M&V Report

Appendix 2: Chiller Retrofit Data Analysis 47

Low Zone Chiller-1 Performance Curves

Figure A-2.2: CH-1 Baseline, Target, and ECM Performance (Curve Fit) Curves at

42°F CHWST and 80°F CWET.

Figure A-2.3: CH-1 Baseline, Target, and ECM Performance (Curve Fit) Curves at

42°F CHWST and 75°F CWET

Page 53: Empire State Building Performance Year 4 M&V Report April ... · Empire State Building Performance Year 4 M&V Report Section 1 - Executive Summary 1 1. Empire State Building (ESB)

Empire State Building Performance Year 4 M&V Report

Appendix 2: Chiller Retrofit Data Analysis 48

Figure A-2.4: CH-1 Baseline, Target, and ECM Performance (Curve Fit) Curves at

42°F CHWST and 65°F CWET

Figure A-2.5 shows the Cv and MBE associated with the Chiller-1 curve fit. The low MBE and reasonable Cv reflects a good curve fit.

CWET MBE Cv(RMSE)

60.00 -0.1% 42.4%

65.00 1.5% 19.3%

70.00 1.8% 13.5%

75.00 0.6% 13.1%

80.00 -3.4% 11.3%

85.00 6.2% 6.2%

Overall 0.1% 16.0%

Figure A-2.5: MBE and Cv Associated with Chiller-1 Curve Fit

Page 54: Empire State Building Performance Year 4 M&V Report April ... · Empire State Building Performance Year 4 M&V Report Section 1 - Executive Summary 1 1. Empire State Building (ESB)

Empire State Building Performance Year 4 M&V Report

Appendix 2: Chiller Retrofit Data Analysis 49

Mid Zone Chiller-4 Performance Curves

Figure A-2.6: CH-4 Baseline, Target, and ECM Performance (Curve Fit) Curves at

42°F CHWST and 80°F CWET

Figure A-2.7: CH-4 Baseline, Target, and ECM Performance (Curve Fit) Curves at

42°F CHWST and 75°F CWET

Page 55: Empire State Building Performance Year 4 M&V Report April ... · Empire State Building Performance Year 4 M&V Report Section 1 - Executive Summary 1 1. Empire State Building (ESB)

Empire State Building Performance Year 4 M&V Report

Appendix 2: Chiller Retrofit Data Analysis 50

Figure A-2.8: CH-4 Baseline, Target, and ECM Performance (Curve Fit) Curves at

42°F CHWST and 65°F CWET

Figure A-2.9 shows the Cv and MBE associated with the Chiller-4 curve fit. The low MBE and reasonable Cv reflects a good curve fit.

CWET MBE Cv(RMSE)

60.00 -34.4% 44.6%

65.00 -11.3% 14.0%

70.00 -6.9% 7.4%

75.00 -3.4% 17.4%

80.00 7.2% 21.3%

85.00 32.3% 32.3%

Overall 0.1% 22.4%

Figure A-2.9: MBE and Cv Associated with Chiller-4 Curve Fit

Page 56: Empire State Building Performance Year 4 M&V Report April ... · Empire State Building Performance Year 4 M&V Report Section 1 - Executive Summary 1 1. Empire State Building (ESB)

Empire State Building Performance Year 4 M&V Report

Appendix 2: Chiller Retrofit Data Analysis 51

Mid Zone Chiller-5 Performance Curves

Figure A-2.10: CH-5 Baseline, Target, and ECM Performance (Curve Fit) Curves at

42°F CHWST and 80°F CWET

Figure A-2.11: CH-5 Baseline, Target, and ECM Performance (Curve Fit) Curves at

42°F CHWST and 75°F CWET

Page 57: Empire State Building Performance Year 4 M&V Report April ... · Empire State Building Performance Year 4 M&V Report Section 1 - Executive Summary 1 1. Empire State Building (ESB)

Empire State Building Performance Year 4 M&V Report

Appendix 2: Chiller Retrofit Data Analysis 52

Figure A-2.12: CH-5 Baseline, Target, and ECM Performance (Curve Fit) Curves at

42°F CHWST and 65°F CWET

Figure A-2.13 shows the Cv and MBE associated with the Chiller-5 curve fit. The low MBE and reasonable Cv reflects a good curve fit.

CWET MBE Cv(RMSE)

60.00 -1.5% 40.2%

65.00 7.8% 12.7%

70.00 -0.9% 15.6%

75.00 0.5% 9.2%

80.00 -3.3% 8.0%

85.00 5.4% 5.4%

Overall 0.1% 13.0%

Figure A-2.13: MBE and Cv Associated with Chiller-5 Curve Fit

Page 58: Empire State Building Performance Year 4 M&V Report April ... · Empire State Building Performance Year 4 M&V Report Section 1 - Executive Summary 1 1. Empire State Building (ESB)

Empire State Building Performance Year 4 M&V Report

Appendix 2: Chiller Retrofit Data Analysis 53

High Zone Chiller-6 Performance Curves

Figure A-2.14: CH-6 Baseline, Target, and ECM Performance (Curve Fit) Curves at

42°F CHWST and 80°F CWET

Figure A-2.15: CH-6 Baseline, Target, and ECM Performance (Curve Fit) Curves at

42°F CHWST and 75°F CWET

Page 59: Empire State Building Performance Year 4 M&V Report April ... · Empire State Building Performance Year 4 M&V Report Section 1 - Executive Summary 1 1. Empire State Building (ESB)

Empire State Building Performance Year 4 M&V Report

Appendix 2: Chiller Retrofit Data Analysis 54

Figure A-2.16: CH-6 Baseline, Target, and ECM Performance (Curve Fit) Curves at

42°F CHWST and 65°F CWET

Figure A-2.17 shows the Cv and MBE associated with the Chiller-6 curve fit. The low MBE and reasonable Cv reflects a good curve fit.

CWET MBE Cv(RMSE)

60.00 4.7% 10.0%

65.00 -1.2% 10.2%

70.00 0.4% 8.2%

75.00 1.5% 6.8%

80.00 -1.4% 6.3%

85.00 -14.2% 14.9%

Overall -0.1% 8.1%

Figure A-2.17: MBE and Cv Associated with Chiller-6 Curve Fit

Page 60: Empire State Building Performance Year 4 M&V Report April ... · Empire State Building Performance Year 4 M&V Report Section 1 - Executive Summary 1 1. Empire State Building (ESB)

Empire State Building Performance Year 4 M&V Report

Appendix 3: Chiller Plant Retrofit Data Analysis 55

Appendix 3: Chiller Plant Retrofit Data Analysis

CHWST Reset

Figures A-3.1 through Figure A-3.4 shows the CHWST, CHWST setpoint and outside air temperature trends. The analysis uses 8 a.m. to 5 p.m. weekday trend data. It can be observed that the CHWST setpoint does not change with outside air temperature during summer and this indicates manual operation of the CHWST reset ECM.

Figure A-3.1: Low Zone Chiller 1 CHW Supply Temperature and CHW Supply Temperature

Setpoint, Outside Air Temperature versus Time

Figure A-3.2: Mid Zone Chiller 4 CHW Supply Temperature and CHW Supply Temperature

Setpoint, Outside Air Temperature versus Time

Page 61: Empire State Building Performance Year 4 M&V Report April ... · Empire State Building Performance Year 4 M&V Report Section 1 - Executive Summary 1 1. Empire State Building (ESB)

Empire State Building Performance Year 4 M&V Report

Appendix 3: Chiller Plant Retrofit Data Analysis 56

Figure A-3.3: Mid Zone Chiller 5 CHW Supply Temperature and CHW Supply Temperature

Setpoint, Outside Air Temperature versus Time

Figure A-3.4: High Zone Chiller 6 CHW Supply Temperature and CHW Supply Temperature

Setpoint, Outside Air Temperature versus Time

Page 62: Empire State Building Performance Year 4 M&V Report April ... · Empire State Building Performance Year 4 M&V Report Section 1 - Executive Summary 1 1. Empire State Building (ESB)

Empire State Building Performance Year 4 M&V Report

Appendix 3: Chiller Plant Retrofit Data Analysis 57

CHW Loop Delta-T Enhancement

Figure A-3.5 showcases the frequency of low delta-T (°F) plant operation. The analysis uses 8 a.m. to 5 p.m. summer weekday trend data. It was observed that the low zone delta-T (°F) was operating mostly between 2°F to 8°F, the mid zone delta-T (°F) was operating between 3°F to 11°F and the high zone delta-T (°F) was operating between 3°F to 9°F. Zone delta-Ts (°F) are not fully operating as optimally desired. The root cause was found to be the existence of a number of three-way valves in the system, and the fact that the electric chillers are run at low load conditions. Also, the bypass valve opens during low load conditions and therefore, the delta-T (°F) across the chiller suffers. The bypass valve operation is unavoidable but the three-way valve situation can be improved in future projects. ESB is currently working on designing a project to replace the three-way valves with two-way valves.

Figure A-3.5: CHW Delta-T Histogram

Page 63: Empire State Building Performance Year 4 M&V Report April ... · Empire State Building Performance Year 4 M&V Report Section 1 - Executive Summary 1 1. Empire State Building (ESB)

Empire State Building Performance Year 4 M&V Report

Appendix 3: Chiller Plant Retrofit Data Analysis 58

CHW Pump VFD Automation

CHW pump VFDs were operated in the manual mode and Figure A-3.6 shows that the VFD speeds associated with the manual operation (50% to 82%).

Figure A-3.6: CHW Pump Speed Histogram

Page 64: Empire State Building Performance Year 4 M&V Report April ... · Empire State Building Performance Year 4 M&V Report Section 1 - Executive Summary 1 1. Empire State Building (ESB)

Empire State Building Performance Year 4 M&V Report

Appendix 3: Chiller Plant Retrofit Data Analysis 59

CW Supply Temperature Reset

CWST reset logic was switched to auto mode for the first time on August 19, 2014. It was observed upon data analysis that the CWST reset was incorrectly responding to changes in OADPT and the 5°F approach was not enough for the cooling towers. The programming was changed on August 25, 2014 so that CWST reset responds to OAWBT with a 7°F tower approach. The CWST reset logic is operating correctly now and it can be observed in Figure A-3.7 that the CWST meets the setpoint. Note that CWST and CTWLT shown in the Figure are the same parameters.

Figure A-3.7: Outside Air Temperature Wet Bulb, CW Temperature and

CW Temperature Setpoint vs Time

Page 65: Empire State Building Performance Year 4 M&V Report April ... · Empire State Building Performance Year 4 M&V Report Section 1 - Executive Summary 1 1. Empire State Building (ESB)

Empire State Building Performance Year 4 M&V Report

Appendix 3: Chiller Plant Retrofit Data Analysis 60

Cooling Tower Fan VFD Automation

The cooling tower has ten cells, each of which is fitted with a separate cooling fan. Eight of the fans are single speed On/Off type. Two of the fans were fitted with manually controllable VFD.

This ECM automated the manually-controlled cooling tower VFD system into an automatically controlled cooling tower VFD system. The fan speed is now automatically controlled to meet the CTWLT setpoint. Additionally, controls were installed to automatically stage the two fan VFDs.

The fan speed is automatically controlled to meet the CTWLT setpoint. Cooling Tower fan VFDs are operated in the automatic mode and Figure A-3.8 shows the VFD speed modulation.

Figure A-3.8: Cooling Tower Fan VFD Histogram

Page 66: Empire State Building Performance Year 4 M&V Report April ... · Empire State Building Performance Year 4 M&V Report Section 1 - Executive Summary 1 1. Empire State Building (ESB)

Empire State Building Performance Year 4 M&V Report

Appendix 3: Chiller Plant Retrofit Data Analysis 61

CW Pump VFD Automation

CW pump VFDs were operated in the manual mode and Figure A-3.9 shows that the VFD speeds associated with the manual operation (40% to 100%).

Figure A-3.9: Cooling Water Pump VFD Histogram

Page 67: Empire State Building Performance Year 4 M&V Report April ... · Empire State Building Performance Year 4 M&V Report Section 1 - Executive Summary 1 1. Empire State Building (ESB)

Empire State Building Performance Year 4 M&V Report

Appendix 4: PFHX Data Analysis 62

Appendix 4: PFHX Data Analysis

The low zone and mid zone PFHXs are guaranteed to achieve 2.6°F approach temperature (including the measurement tolerance of 0.6°F) when operating under design conditions shown in Figure 8.1. The approach temperatures and PFHX cooling loads were measured in the field are shown in Figure A-4.2 and FigureA-4.3. It can be observed that the PFHXs did not operate near design load conditions, but the approach temperature was within the 2.6°F limit during most conditions.

PFHX Capacity (Tons)

Design Cold Side Flow (gpm)

Design Hot Side Flow (gpm)

Low Zone PFHX 500 1,200 1,200

Mid Zone PFHX 1,000 2,400 2,400

Figure A-4.1: PFHX Design Operating Condition

Figure A-4.2: Low Zone Cooling Load vs Approach Temperature

Page 68: Empire State Building Performance Year 4 M&V Report April ... · Empire State Building Performance Year 4 M&V Report Section 1 - Executive Summary 1 1. Empire State Building (ESB)

Empire State Building Performance Year 4 M&V Report

Appendix 4: PFHX Data Analysis 63

Figure A-4.3: Mid Zone Cooling Load vs Approach Temperature

The process of incorporating a PFHX model into the ESB eQUEST Model is very complex. Therefore the savings are directly derived by measuring the PFHX cooling load and calculating the corresponding electric chiller avoided cost. The cumulative PFHX cooling load recorded in the field is shown in Figure A-4.4 and FigureA-4.5.

Note: The field data for the first three months in the PY is missing and it is replaced with a degree day based average cooling load calculated from PFHX field data collected during rest of the PY months.

Figure A-4.4: Low Zone Cumulative Cooling Load

Page 69: Empire State Building Performance Year 4 M&V Report April ... · Empire State Building Performance Year 4 M&V Report Section 1 - Executive Summary 1 1. Empire State Building (ESB)

Empire State Building Performance Year 4 M&V Report

Appendix 4: PFHX Data Analysis 64

Figure A-4.5: Mid Zone Cumulative Cooling Load

Page 70: Empire State Building Performance Year 4 M&V Report April ... · Empire State Building Performance Year 4 M&V Report Section 1 - Executive Summary 1 1. Empire State Building (ESB)

Empire State Building Performance Year 4 M&V Report

Appendix 5: ESB eQUEST Model Inputs and Outputs 65

Appendix 5: ESB eQUEST Model Inputs

Page 71: Empire State Building Performance Year 4 M&V Report April ... · Empire State Building Performance Year 4 M&V Report Section 1 - Executive Summary 1 1. Empire State Building (ESB)

Empire State Building Performance Year 4 M&V Report

Appendix 5: ESB eQUEST Model Inputs and Outputs 66

Contract Baseline Contract Target PY Adjusted

BaselinePY Target

PY ECM

Performance

PY Actual

OperationPY Actual Utility

% 10% 10%11% - per CHW

Zone

11% - per CHW

Zone

11% - per CHW

Zone

11% - per CHW

Zone

11% - per CHW

Zone

HVAC Setbacks No No Yes Yes Yes Yes Yes

Weather Location, Year NY, 2007 NY, 2007 NY, 2014 NY, 2014 NY, 2014 NY, 2014 NY, 2014

Electric Utility Rate Year 2007 2007 PY Contract Rate PY Contract Rate PY Contract Rate PY Contract Rate 2014

Steam Utility Rate Year 2007 2007 PY Contract Rate PY Contract Rate PY Contract Rate PY Contract Rate 2014

Number of Radiator Insulations Installed 0 6400 0 6400 6400 6400 6400

Radiative Wall U Value 0.209 0.122 0.209 0.122 0.102 0.102 0.102

North (U-value/SHGC) 0.48 / 0.645 0.365 / 0.448 0.58 / 0.645 0.365 / 0.448 0.274 / 0.395 0.274 / 0.395 0.274 / 0.395

East (U-value/SHGC) 0.48 / 0.645 0.384 / 0.325 0.58 / 0.645 0.384 / 0.325 0.320 / 0.27 0.320 / 0.27 0.320 / 0.27

South (U-value/SHGC) 0.48 / 0.645 0.384 / 0.325 0.58 / 0.645 0.384 / 0.325 0.337 / 0.27 0.337 / 0.27 0.337 / 0.27

West (U-value/SHGC) 0.48 / 0.645 0.384 / 0.325 0.58 / 0.645 0.384 / 0.325 0.324 / 0.27 0.324 / 0.27 0.324 / 0.27

Window Infiltration Multiplier 4 2 4 2 2 2 2

Low Loop

Chiller #1 (Elec) Capacity 750 750 VFD 750 750 VFD 750 VFD 750 VFD 750 VFD

kW/ton

See Baseline

Chiller Curves

(Contract)

See Target Chiller

Curves (Appendix

2)

See Baseline

Chiller Curves

(Contract)

See Target Chiller

Curves (Appendix

2)

See Target Chiller

Curves (Appendix

2)

See Target Chiller

Curves (Appendix

2)

See Target Chiller

Curves (Appendix

2)

Chiller #2 (STM) Capacity 1000 1000 1000 1000 1000 1000 1000

Overall COP 1.01 1.01

hp/ton 0.709 0.709

lbm/tonhr 13.9 13.9

Chiller StagingBaseload Electric

Chiller

Baseload Electric

Chiller

Electric Chiller

Only

Electric Chiller

Only

Electric Chiller

Only

Electric Chiller

Only

Electric Chiller

Only

CHW Pumping

Flow Ctrl /Min

VFD Manual

(100% Speed All

Times)

VFD Auto (100%

to 50% Min)

VFD Manual

(100% Speed All

Times)

VFD Auto (100%

to 50% Min)

VFD Auto (100%

to 50% Min)VFD Manual (59%) VFD Manual (59%)

Valve-Type 3-way 2-way 3-way 2-way 2-way 2-way 2-way

Pump Power (kW) 161 161 161 161 161 161 161

Total Pump Head (Feet) 258 258 258 258 258 258 258

Flow (gpm) 2310 /2 2310 /2 2310 /2 2310 /2 2310 /2 2310 /2 2310 /2

CHWST 44°F (Fixed)

42°F to 50°F

based on valve

position

44°F (Fixed)42°F @ 65°F OAT,

50°F @ 55°F OAT

42°F @ 65°F OAT,

50°F @ 55°F OAT42°F (Fixed) 42°F (Fixed)

Loop Delta T7.8°F (At Design

Load)

10°F (At Design

Load)

7.8°F (At Design

Load)

10°F (At Design

Load)

10°F (At Design

Load)

10°F (At Design

Load)

10°F (At Design

Load)

Windows

Vacancy

Utility Data

Radiator Insulation

Chiller Plant - Low

Loop

York Chiller

Curves

York Chiller

Curves

York Chiller

Curves

York Chiller

Curves

York Chiller

Curves

Page 72: Empire State Building Performance Year 4 M&V Report April ... · Empire State Building Performance Year 4 M&V Report Section 1 - Executive Summary 1 1. Empire State Building (ESB)

Empire State Building Performance Year 4 M&V Report

Appendix 5: ESB eQUEST Model Inputs and Outputs 67

Contract Baseline Contract Target PY Adjusted

BaselinePY Target

PY ECM

Performance

PY Actual

OperationPY Actual Utility

Mid Loop

Chiller #3 (Stm) Capacity 2000 2000 2000 2000 2000 2000 2000

Overall COP 1.09 1.09York Chiller

Curves

hp/ton 0.665 0.665 0

lbm/tonhr 13.8 13.8 0

Chiller #4 (Elec) Capacity 1000 1000 VFD 1000 1000 VFD 1000 VFD 1000 VFD 1000 VFD

Chiller Curves

See Baseline

Chiller Curves

(Contract)

See Target Chiller

Curves (Appendix

2)

See Baseline

Chiller Curves

(Contract)

See Target Chiller

Curves (Appendix

2)

See Target Chiller

Curves (Appendix

2)

See Target Chiller

Curves (Appendix

2)

See Target Chiller

Curves (Appendix

2)

Chiller #5 (Elec) Capacity 1000 1000 VFD 1000 1000 VFD 1000 VFD 1000 VFD 1000 VFD

Chiller Curves

See Baseline

Chiller Curves

(Contract)

See Target Chiller

Curves (Appendix

2)

See Baseline

Chiller Curves

(Contract)

See Target Chiller

Curves (Appendix

2)

See Target Chiller

Curves (Appendix

2)

See Target Chiller

Curves (Appendix

2)

See Target Chiller

Curves (Appendix

2)

Chiller StagingBaseload Electric

Chillers

Baseload Electric

Chillers

Electric Chiller

Only

Electric Chiller

Only

Electric Chiller

Only

Electric Chiller

Only

Electric Chiller

Only

CHW Pumping

Flow Ctrl /Min

VFD Manual

(100% Speed All

Times)

VFD Auto (100%

to 50% Min)

VFD Manual

(100% Speed All

Times)

VFD Auto (100%

to 50% Min)

VFD Auto (100%

to 33% Min)VFD Manual (67%) VFD Manual (67%)

Valve-Type 3-way 2-way 3-way 2-way 2-way 2-way 2-way

CHWST 44°F (Fixed)

42°F to 50°F

based on valve

position

44°F (Fixed)42°F @ 65°F OAT,

50°F @ 55°F OAT

42°F @ 65°F OAT,

50°F @ 55°F OAT44°F (Fixed) 44°F (Fixed)

Loop Delta T<6°F (At Design

Load)

10°F (At Design

Load)

<6°F (At Design

Load)

10°F (At Design

Load)

10°F (At Design

Load)

10°F (At Design

Load)

10°F (At Design

Load)

Chiller Plant - Mid

Loop

York Chiller

Curves

York Chiller

Curves

York Chiller

Curves

York Chiller

Curves

Page 73: Empire State Building Performance Year 4 M&V Report April ... · Empire State Building Performance Year 4 M&V Report Section 1 - Executive Summary 1 1. Empire State Building (ESB)

Empire State Building Performance Year 4 M&V Report

Appendix 5: ESB eQUEST Model Inputs and Outputs 68

Figure A-5.1: 2014 eQUEST Model Inputs Table

Contract Baseline Contract Target PY Adjusted

BaselinePY Target

PY ECM

Performance

PY Actual

OperationPY Actual Utility

High Loop 0 0

Chiller #6 (Elec) Capacity 1000 1000 VFD 1000 1000 VFD 1000 VFD 1000 VFD 1000 VFD

Chiller Curves

See Baseline

Chiller Curves

(Contract)

See Custom

Curves

(Appendix 2)

See Baseline

Chiller Curves

(Contract)

See Custom

Curves

(Appendix 2)

See Custom

Curves

(Appendix 2)

See Custom

Curves (Appendix

2)

See Custom

Curves (Appendix

2)

Chiller #7 (Stm) Capacity 1294 1294 1294 1294 1294 1294 1294

Overall COP 1.03 1.03

hp/ton 0.724 0.724

lbm/tonhr 13.4 13.4

Chiller StagingBaseload Electric

Chillers

Baseload Electric

Chillers

Electric Chillers

Only

Electric Chillers

Only

Electric Chillers

Only

Electric Chillers

Only

Electric Chillers

Only

0

CHW Pumping

VFD Manual

(100% Speed All

Times)

VFD Auto (100%

to 50% Min)

VFD Manual

(100% Speed All

Times)

VFD Auto (100%

to 50% Min)

VFD Auto (100%

to 33% Min)VFD Manual (67%) VFD Manual (67%)

Valve-Type 3-way 2-way 3-way 2-way 2-way 2-way 2-way

CHWST 44°F (Fixed)

42°F to 50°F

based on valve

position

44°F (Fixed)42°F @ 65°F OAT,

50°F @ 55°F OAT

42°F @ 65°F OAT,

50°F @ 55°F OAT42°F (Fixed) 42°F (Fixed)

Loop Delta T6.9°F (At Design

Load)

10°F (At Design

Load)

6.9°F (At Design

Load)

10°F (At Design

Load)

10°F (At Design

Load)

10°F (At Design

Load)

10°F (At Design

Load)

Number of Cells 10 10 10 10 10 10 10

Setpoint Control 70°F FixedWet Bulb Reset

(65°F Min)70°F Fixed Wet Bulb Reset (60°F-75°F)

Wet Bulb Reset

(60°F-75°F)65°F Fixed 65°F Fixed

Tower Fan VFD One Speed FanVFD on TWRS 4

&5One Speed Fan

VFD on TWRS 4

&5

VFD on TWRS 4

&5

VFD on TWRS 4

&5

VFD on TWRS 4

&5

CW Pump Control CV CV CV CVVFD Auto (100%

to 33% Min)VFD Manual (80%) VFD Manual (80%)

OA Reduction - Damper Retrofit (cfm/sf) 0.25 0.15 0.25 0.15 0.15 0.15 0.15

OA Reduction - DCV (cfm/sf) 0.15 0.12 0.15 0.12 0.12 0.12 0.12

High/Mid Fans18hrs / 5d (ON-

Time)

15hrs / 5d (ON-

Time)

18hrs / 5d (ON-

Time)

15hrs / 5d (ON-

Time)

14hrs / 5d (ON-

Time)

14hrs / 5d (ON-

Time)

14hrs / 5d (ON-

Time)

General Exhaust & Toilet Exhaust Fans24hrs / 7d (ON-

Time)

19hrs / 7d (ON-

Time)

24hrs / 7d (ON-

Time)

19hrs / 7d (ON-

Time)

20hrs / 7d (ON-

Time)

20hrs / 7d (ON-

Time)

20hrs / 7d (ON-

Time)

York Chiller

Curves

York Chiller

Curves

Chiller Plant - High

Loop

York Chiller

Curves

York Chiller

Curves

Condenser Water

System

Typical Floor AHUs

(Office)

York Chiller

Curves

Page 74: Empire State Building Performance Year 4 M&V Report April ... · Empire State Building Performance Year 4 M&V Report Section 1 - Executive Summary 1 1. Empire State Building (ESB)

Empire State Building Performance Year 4 M&V Report

Appendix 6: Baseline Adjustments 69

Appendix 6: Baseline Adjustments

List of 2014 Baseline Adjustments

The list of Baseline adjustments made in the model is shown below.

2014 weather

2014 utility analysis

2014 construction floors

2014 construction floor space temperatures

2014 tenant vacancy

2014 tenant space temperatures

2014 broadcast floors electric load

2014 variable air volume AHU upgrades

Weather Data

Baseline adjustments were made to incorporate 2014 New York City weather data.

Utility Analysis

Utility rates were updated in the model to reflect 2014 contract utility rate and 2014 actual utility rate. The data is shown in Appendix 7 of this Report.

Construction Floor Data

Floors under construction have elevated space temperatures during winter and, the HVAC electric loads and cooling loads are turned off during summer. The list of floors that were under construction in 2014 is shown below.

Floors under construction during first half of 2014:

3, 6, 10, 15, 16, 17, 18, 19, 20, 21, 29, 30, 31, 35, 39, 45, 49, 54

Floors under construction during second half of 2014:

3, 6, 10, 28, 29, 42, 49, 52, 54, 55, 56, 57, 60, 62

Page 75: Empire State Building Performance Year 4 M&V Report April ... · Empire State Building Performance Year 4 M&V Report Section 1 - Executive Summary 1 1. Empire State Building (ESB)

Empire State Building Performance Year 4 M&V Report

Appendix 6: Baseline Adjustments 70

Construction Floor Space Temperature Analysis

BMS wiring is cut off in most construction floors. Therefore, the space temperature data for most construction floors could not be recorded in the BMS. However, the data is available for a few construction floors and a sample is shown in Figure A-6.1.

Figure A-6.1: 29th Floor Space Temperature vs Time

Tenant Vacancy Analysis

PY building occupancy data was provided by ESB’s leasing agent. Actual move-in and move-out dates from the monthly plan book were utilized to accurately calculate the vacancy rate of the building. The following calculation method was utilized to estimate floor level vacancy rate:

Floor (n) Vacancy Rate (%) = (Total Vacant SF on Floor (n)) / (Total SF on Floor (n))

Where, (n) represents a specific floor.

The monthly averages were used to calculate the total annual average vacancy per floor. The annual average vacancy rates were then used to determine an overall average vacancy rate per CHW zone based on average level vacancy rates and modeled usable square footages per level. The low CHW zone serves the concourse level through Level 5, the mid CHW zone serves Levels 6 through 41, and the high CHW zone serves Levels 42 through 103. Based on the total annual average per CHW zone, an annual vacant square footage is determined.

Vacancy rate was applied to the "modeled tenant SF" and the resulting vacant spaces were setback. Non-tenant SF (=Total SF –Tenant SF) was assumed to be conditioned, but not setback.

Page 76: Empire State Building Performance Year 4 M&V Report April ... · Empire State Building Performance Year 4 M&V Report Section 1 - Executive Summary 1 1. Empire State Building (ESB)

Empire State Building Performance Year 4 M&V Report

Appendix 6: Baseline Adjustments 71

Johnson Controls physically measured all the floor spaces in ESB and calculated the total building SF to be 2,575,565 SF (this includes tenant space, corridors, mechanical rooms, elevator shafts, stairwells, etc.). The plan book shows that, as much as 2,070,966 SF is used as tenant spaces. These numbers compares closely with the modeled square feet which were based on building floor plans.

A number of modeled levels are assumed to be vacant to match this annual vacant square footage, which is indicated by the highlighted floors in the tables on the following pages. The vacant levels are modeled with no tenant loads and are assumed to have 24/7 HVAC setbacks in the tenant areas, as well as the corridors, restrooms, and building core support spaces on the vacant levels. The occupied tenant SF, elevator shaft, corridors and stairwells are all setback per the AHU supply fan schedule. Orange rows indicate floors modeled as construction floors.

Figure A-6.2 shows the detailed vacancy rate calculations.

Page 77: Empire State Building Performance Year 4 M&V Report April ... · Empire State Building Performance Year 4 M&V Report Section 1 - Executive Summary 1 1. Empire State Building (ESB)

Empire State Building Performance Year 4 M&V Report

Appendix 6: Baseline Adjustments 72

Page 78: Empire State Building Performance Year 4 M&V Report April ... · Empire State Building Performance Year 4 M&V Report Section 1 - Executive Summary 1 1. Empire State Building (ESB)

Empire State Building Performance Year 4 M&V Report

Appendix 6: Baseline Adjustments 73

Figure A-6.2: 2014 Vacancy Rate Calculation

Page 79: Empire State Building Performance Year 4 M&V Report April ... · Empire State Building Performance Year 4 M&V Report Section 1 - Executive Summary 1 1. Empire State Building (ESB)

Empire State Building Performance Year 4 M&V Report

Appendix 6: Baseline Adjustments 74

Tenant Space Temperature Analysis

Space temperatures from several floors were sampled and the resultant average space temperature used in the model is shown in the Figure A-6.3.

Cooling Season Heating Season

Space Type

Weekday Occupied Space

Temperature (°F)

Weekday Unoccupied

Space Temperature

(°F)

Weekend Space Temperature

(°F)

Weekday Occupied Space

Temperature (°F)

Weekday Unoccupied

Space Temperature

(°F)

Weekend Space Temperature

(°F)

Leased 72.5 73.9 75.7 74.1 70.9 69.4

Vacant 73.9 75.2 75.7 69.2 68.3 66.2

Construction HVAC Off HVAC Off HVAC Off 82.0 82.0 82.0

Figure A-6.3: Average Tenant Space Temperatures

Broadcast Floors Electric Load Data

The broadcast floor electric load in the model was updated using the 2014 data shown in Figure A-6.4.

Figure A-6.4: Broadcast Floor Electric Demand

Page 80: Empire State Building Performance Year 4 M&V Report April ... · Empire State Building Performance Year 4 M&V Report Section 1 - Executive Summary 1 1. Empire State Building (ESB)

Empire State Building Performance Year 4 M&V Report

Appendix 6: Baseline Adjustments 75

VAV AHU Upgrades

Several constant volume AHUs in the building were upgraded to VAV AHUs in the past few years. The list of upgraded AHUs is shown in Figure A-6.5 and the model was updated to reflect the upgrade. Note that the AHU name reflects the floor number and unit number. For example, AHU-15-4 denotes unit number 4 installed on the 15th floor.

Figure A-6.5: List of VAV AHU Upgrades

Page 81: Empire State Building Performance Year 4 M&V Report April ... · Empire State Building Performance Year 4 M&V Report Section 1 - Executive Summary 1 1. Empire State Building (ESB)

Empire State Building Performance Year 4 M&V Report

Appendix 7: ESB Utility Rates 76

Appendix 7: ESB Utility Rates

2007

Actual Rate

2011 Actual Rate

2012 Actual Rate

2013 Actual Rate

2014 Actual Rate

2014 Modeled

Rate

Customer Charge ($/day) $2.13 $2.13 $2.13 $2.59 $3.39 N/A

Energy Charges $/kWh $0.13 $0.13 $0.13 $0.11 $0.11 $0.17

G&T Demand $/kW $8.00 $8.00 $6.43 $8.42 $8.39 $6.35

Primary Demand (June - Sep) $/kW $14.97 $14.97 $17.80 $15.86 $15.81 $11.79

Secondary Demand (June - Sep) $/kW $16.06 $16.06 $19.55 $16.96 $16.90 $13.30

Primary Demand (October - May) $/kW $11.04 $11.04 $11.04 $11.98 $11.71 $8.73

Secondary Demand (October - May) $/kW $5.15 $5.15 $5.15 $5.73 $5.51 $4.23

Figure A-7.1: Baseline and Performance Period Electric Utility Rate Comparison

2007

Actual Rate 2008

Actual Rate 2014

Modeled Rate

Monthly Charge $/month $2,722.18 $2,722.18 $2,976.33

General Demand Charge $/therm/hr $10.526 $10.526 $11.51

Steam Demand Peak $/therm/hr $99.62 $99.623 $108.92

Summer Steam Consumption

First 2,500 Mlb $/therm $2.176 $2.176 $2.38

Next 7,500 Mlb $/therm $2.428 $2.428 $2.65

All additional Mlb $/therm $2.363 $2.363 $2.58

Winter Steam Consumption

First 2,500 Mlb $/therm $2.187 $2.187 $2.39

Next 12,500 Mlb $/therm $3.226 $3.226 $3.53

Next 35,000 Mlb $/therm $3.106 $3.106 $3.40

Next 200,000 Mlb $/therm $3.044 $3.044 $3.33

All additional Mlb $/therm $2.953 $2.953 $3.23

Swing Steam Consumption

First 2,500 Mlb $/therm $2.275 $2.275 $2.49

Next 12,500 Mlb $/therm $3.661 $3.661 $4.00

Next 35,000 Mlb $/therm $3.500 $3.500 $3.83

Next 200,000 Mlb $/therm $3.418 $3.418 $3.74

All additional Mlb $/therm $3.297 $3.297 $3.60

Figure A.7.2: 2007 Actual, 2008 Actual and 2014 Modeled Steam Utility Rate Structure

Page 82: Empire State Building Performance Year 4 M&V Report April ... · Empire State Building Performance Year 4 M&V Report Section 1 - Executive Summary 1 1. Empire State Building (ESB)

Empire State Building Performance Year 4 M&V Report

Appendix 7: ESB Utility Rates 77

2011 Actual

Rate 2012 Actual

Rate 2013 Actual

Rate 2014 Actual

Rate

Customer Charge $/day $207.71 $232.90 $254.95 $241.67

Winter All-time Peak Demand Charge (Applied all time during December to March) $/Mlb/hr

$151.03 $170.03 $193.26 $182.46

Winter On-peak Demand Charge (Applied 6 a.m.to 11 a.m. during December to March) $/Mlb/hr

$1,453.87 $1,636.71 $1,860.01 $1,755.71

Summer (May to October) Steam Energy Charge (for all additional Mlb) $/Mlb

$16.70 $15.19 $18.51 $14.71

Winter (December to March) Steam Energy Charge (for all additional Mlb) $/Mlb

$32.42 $32.35 $31.82 $28.17

Swing (April and November) Steam Energy Charge (for all additional Mlb) $/Mlb

$35.68 $34.02 $36.83 $34.39

Note: All consumption charges include GRT, MTA, state and city taxes

GRT and MTA taxes 2.48% 2.81% 2.65% 2.37%

State and City Taxes 8.88% 8.88% 8.88% 8.87%

Figure A.7.3: 2011 through 2014 Steam Utility Rate Structure

Page 83: Empire State Building Performance Year 4 M&V Report April ... · Empire State Building Performance Year 4 M&V Report Section 1 - Executive Summary 1 1. Empire State Building (ESB)

Empire State Building Performance Year 4 M&V Report

Glossary 78

Glossary

Acronym Definition

ADX Application and Data Server

AEM Automated Enterprise Management

AHU Air-Handling Unit

ARI Air-Conditioning and Refrigeration Institute

ASHRAE American Society of Heating, Refrigerating, and Air-Conditioning Engineers

ASTM American Society for Testing and Materials

ATI Architectural Testing, Inc.

BMS Building Management System

cfm cubic feet per minute

CH Chiller

CHW Chilled Water

CHWRT Chilled Water Return Temperature (building to chiller)

CHWST Chilled Water Supply Temperature (chiller to building)

CT Cooling Tower

CTWET Cooling Tower Water Entering Temperature

CTWLT Cooling Tower Water Leaving Temperature

Cv Coefficient of Variation

CW Condenser Water

CWET Condenser Water Entering Temperature (entering the chiller)

CWLT Condenser Water Leaving Temperature (leaving the chiller)

CWST Condenser Water Supply Temperature (to the chiller)

DCV Demand Control Ventilation

DDC Direct Digital Control

DOE Department of Energy

ECM Energy Conservation Measures

EPC Energy Performance Contract

ESB Empire State Building

FPI Facility Performance Indexing

gpm gallons per minute

GRT Gross Receipts Tax

HVAC Heating, Ventilating, and Air-Conditioning

IG Insulated Glass

Page 84: Empire State Building Performance Year 4 M&V Report April ... · Empire State Building Performance Year 4 M&V Report Section 1 - Executive Summary 1 1. Empire State Building (ESB)

Empire State Building Performance Year 4 M&V Report

Glossary 79

IPLV Integrated Part-Load Values

IPMVP International Performance Measurement and Verification Protocol

ISO International Organization for Standardization

M&V Measurement and Verification

MBE Mean Bias Error

Mlb 1000 lb

MTA Metropolitan Transportation Authority

NAE Network Automation Engines

NFRC National Fenestration Rating Council

OAT Outside Air Temperature

PFHX Plate and Frame Heat Exchanger

ppm parts per million

PY Performance Year

RIB Relay in a Box

RMSE Root Mean Square Error

SF Square Feet

SHGC Solar Heat Gain Coefficient

TEM Tenant Energy Management

UPS Uninterruptible Power Supply

VFD Variable Frequency Drive

VSD Variable Speed Drive

Page 85: Empire State Building Performance Year 4 M&V Report April ... · Empire State Building Performance Year 4 M&V Report Section 1 - Executive Summary 1 1. Empire State Building (ESB)

Empire State Building Performance Year 4 M&V Report

Report Delivery Acknowledgement

Report Delivery Acknowledgement

Empire State Building and Johnson Controls here by acknowledge that the Performance Year 4 (January 2014 to December 2014) Annual Energy Report was delivered on April 2, 2015.

Empire State Building:

Signature: ____________________________

Name: _______________________________

Title: ________________________________

Date: ________________________________

Johnson Controls:

Signature: ____________________________

Name: _______________________________

Title: ________________________________

Date: ________________________________

Page 86: Empire State Building Performance Year 4 M&V Report April ... · Empire State Building Performance Year 4 M&V Report Section 1 - Executive Summary 1 1. Empire State Building (ESB)

Empire State Building Performance Year 4 M&V Report

Report Completion Acknowledgement

Empire State Building and Johnson Controls here by acknowledge that the Performance Year 4 (January 2014 to December 2014) Annual Energy Report was completed as required by the energy performance contract and Empire State Building here by accepts the report.

Empire State Building:

Signature: ____________________________

Name: _______________________________

Title: ________________________________

Date: ________________________________

Johnson Controls:

Signature: ____________________________

Name: _______________________________

Title: ________________________________

Date: ________________________________