Enarcon India

Embed Size (px)

Citation preview

  • 7/31/2019 Enarcon India

    1/9

    Anarcon India: Project and

    PlanningBy

    Chetan panara

    Ram ChaudharyYashir Momin

    Dinesh Moyal

  • 7/31/2019 Enarcon India

    2/9

    Problems in case

    There are 4 Big problem in case.

    Weak project structure

    Top Management was unaware about the

    problem

    Only one manager in project

    Land acquisition process

    project have no Pre monsoon plan

    Project have scheduled in such manner

  • 7/31/2019 Enarcon India

    3/9

    Eraction problem

    Transportation

  • 7/31/2019 Enarcon India

    4/9

    Cost Benefit Analysis

    if the project is not finish on 30th sep.2003. On that condition clientdoes not get benefit from 600million project.

    Depreciation benefit(600-180/2) =240 million

    Corporate tax benefit at 30% =180 million

    Wind power benefit =7 million

    (1.4million *5 Rs. Per unit)

    Total =427 million

  • 7/31/2019 Enarcon India

    5/9

    Mathematical equation of the case

    Total investment for purchasing the crane 31,150,000

    (Addition of total landed cost of Rs 31,650,000 and (31.15million)

    provision for spares inventory @ 5 % of the landed cost)

    Annual cost of operating demag 665 crane 7,606,000

    Annual cost of hiring an equivalent crane from the market 15,600,000

    Annual saving by Enercon owning the crane 7,994,000

    (8.00million)

    Interest payable on capital borrowings 14 % per annum

    Additional Assumptions required for Calculations

    Operating life for a crane 10 years

    Salvage value at the end of operating life Rs 6.23 million

    ( 20 % of original investment of Rs 31.15 million) Equity-Debt ratio

    for project financing 60 : 40

    Return expected by Enercon on its own equity 20 % per annum

    Net total taxation rate applicable to Enercon 33 % on incremental profitsDepreciation provision on straight line basis

  • 7/31/2019 Enarcon India

    6/9

    Average Return on Investment (ROI)

    Annual savings by Enercon owning the crane Rs 8.00 million

    Return on investment (PBDIT) 31 %

    Pay-back Period for Investment Annual cash-flow (before depreciation) Rs 8.00 million

    Pay-back period for investment (31.15 /8.00 ) 3.9 years

    Net Present Value

    Calculation of Weighted Average Return on Capital (WACC)

    Post-tax cost of project term borrowings with 33 % income

    tax and 14 % market interest rate on 40 % project cost

    (= 0.40 x 14 x 0.67) 3.75 % per annum

    Cost of expected return on equity investment on 60 % of

    Project cost at 20 % per annum return on equity 12.00 % per annum

  • 7/31/2019 Enarcon India

    7/9

    Total weighted average cost of capital (WACC) 15.8 %per annum

    Net Present Value

    (Considering 20% salvaged value of investment at end of 10thyear) Rs 40.4 million

    Internal Rate of Return (IRR)23%

    Based on all the four criteria considered, it is clear that owninga 220 tonne crane is an attractive proposition. Hence, Enerconshould own at least one such crane initially.

  • 7/31/2019 Enarcon India

    8/9

    WBS

    Land identification and acquisition

    Micrositing and planning

    Approach road formation

    Foundation casting

    WEC delivery Tower delivery

    Blades delivery

    Machine eraction

    11 KV overhead line

    Pre-commissioning of WEC

    VCB and metering yard construction

    VCB and 11kv line charging

    Commissioning

  • 7/31/2019 Enarcon India

    9/9

    Thank you