Encotec Energy (India) Pvt. Ltd.(Finding New Ways to Energy solutions from Shovel to Socket)(Finding New Ways to Energy solutions from Shovel to Socket)
An Integrated Management Systems Company
Presentation on Plasma Ignition System (PIS)
at
Power Management Institute, NTPC, Noida
9 June 2017
Shareholding Structure
50 : 50
Range of services
Engineering services, Erection & Commissioning services, Operation &Maintenance services, Supply of Chinese Spares & Overhauling of ThermalPower plants; Operation & Maintenance services for Substations; EPC ofSolar PV Projects, Renewable & Climate Change
Sales ₹ 605 Million* of ENCOTEC
Profile
Member of VPC Group, A Leading German Company in the Field of Engineering Consultancy & Other Related Services for Energy Sector
Sales ₹ 605 Million* of ENCOTEC₹ 3500 Million of VPC
Human Resources
825* of ENCOTEC1,000* of VPC
Certified to ISO 9001 : 2008 Quality Management SystemISO 14001 : 2015 Environment Management SystemOHSAS 18001 : 2007 Occupational Health & Safety Management SystemCRISIL MSE * 2 High Credit Worthiness
*as at March 31, 2017
| ENCOTEC | Corporate Presentation | 2016-08-302
Spectrum of Services
POWER GENERATION
TRANSMISSION & DISTRI-BUTION
Engineering Services
Renovation & Modernization
Operation & Maintenance
Training &
Capacity Building
Erection, Testing & Commissioning
| ENCOTEC | Corporate Presentation | 2016-08-303
ENCOTEC
RENEWABLE &
CLIMATE CHANGE
PROJECT
MANAGEMENTQuality Assurance
& Auditing Services
Plasma Ignition System and
Chinese Power Plant Spares
Capacity Building
EPC Services
Operational Management, Measurements, On Site Testing and Laboratory Services
Some of the Clients
| ENCOTEC | Corporate Presentation | 2016-08-304
…& many more.
Energy Saving, Safe and High Efficiency, Low Nitrogen and Environment
Protection, Future Leading Science & Technology
Plasma Ignition System
5 | VPC | ENCOTEC | WOM | PIS | 2017-02-02
Anhui Xinneng Electric Technology Co., Ltd. is foundedin 2007, located in Hefei, which is China’s science andeducation city. The company is a science andtechnology company invested by Anhui ProvinceEnergy Group Co., Ltd., which relies on University ofScience of Technology of China and Plasma PhysicsResearch Institute of Chinese Academy of Sciences,and aims to combine production, study and research
About Our Partner
and aims to combine production, study and researchtogether.
Xinneng is part of WOM under Wenergy Group ofChina.
ENCOTEC is exclusive partner of WOM for PlasmaIgnition System design, supply, installation & after salesservice in India.
6 | VPC | ENCOTEC | WOM | PIS | 2017-02-02
Authorization as Exclusive Channel Partner
7 | VPC | ENCOTEC | WOM | PIS | 2017-02-02
In the early 1980s, with the industry recovering from the 1970s oil crisis and
the commissioning of new nuclear plants, technology was pursued to cycle
large fossil units down to low loads. The technical limitation of large coal units
being restricted to 30-40 percent load without additional fuel for flame stability
was one of the necessary topics to be addressed.
The objective was maintaining combustion stability while minimizing
secondary fuel costs.
Traditional igniter technology has been to use fuel oil as the primary fuel for
Background
8 | VPC | ENCOTEC | WOM | PIS | 2017-02-02
the igniter. The use of fuel oil for start up and stability is costly and causes
detrimental impacts to the plant air quality control equipment. The particulate
soot from igniter fuel oil combustion causes energization issues in
electrostatic precipitators, blinding and fire hazards in fabric filters, and
possible contamination and operational issues in wet FGD systems.
The Plasma Ignition Technology eliminates the fuel oil cost and environmental
issues, and as compared to natural gas, uses a readily available fuel source
at the coal-fired plant.
Results
Technology advances have been made in
ignition systems that would help coal plants
be more competitive when considering the
increasing challenge of part load operation.
Plasma Ignition Technology, a coal-fired
9 | VPC | ENCOTEC | WOM | PIS | 2017-02-02
Plasma Ignition Technology, a coal-fired
ignition system, has installed and operating
experience in helping coal plants reduce
costs and provide operating flexibility.
What is Plasma?
The plasma formation occurs by controlled generation
of an electrical discharge (arc) between two electrodes.
The passage of the air through and around the electric
arc causes it to become partially ionized and very hot.
An average temperature of 3,000°C would be typical.
The hot air forms high velocity luminous jet from the
anode, which is termed as plasma. It has a similar
appearance to a gas flame.
10 | VPC | ENCOTEC | WOM | PIS | 2017-02-02
The plasma is not a product of combustion but the
energized ionized air.
The position of both the anode and cathode are
controlled to optimum position for plasma quality and
extending electrode life.
Plasma Ignition Unit System
11 | VPC | ENCOTEC | WOM | PIS | 2017-02-02
The Plasma Torch Ignition of Pulverized Coal to Enlarge
Plasma jet
Three times wind
Secondary wind
Enriched Coal
Enriched Coal
FurnacePlasma jet
Secondary wind
Three times wind
The first
stage flame
The second
stage flame
The third
stage flame
12 | VPC | ENCOTEC | WOM | PIS | 2017-02-02
The Component of Plasma Igniter
Ignition unit
Cathode inlet
Working
Anode outlet
Anode
Plasma igniter is mainly composed of anode, cathode,
ignition devices and other components. The rear of the
igniter is equipped with working medium gas, cooling water,
water-cooled cables and control circuit interface.
Working medium
gas
Anode and
cathode inlet
13 | VPC | ENCOTEC | WOM | PIS | 2017-02-02
NO. Name Unit Result Remarks
1Primary duct wind speed
m/s 18.0~26.0Plasma burner ignition winds
2primary air temperature ℃
Room temperature
~75
The Main Design Parameters of the Plasma Burner
3 pulverized coal t/h 4.0~10.0
4pulverized coal concentration
kg/kg 0.18~0.625 primary air duct
5vents wind
speedm/s 40~50
nozzle temperature by
1000℃
6burner
resistancePa <1000
ignition combustion
14 | VPC | ENCOTEC | WOM | PIS | 2017-02-02
Product Type
Product Type PICS-I2-100 PICS-I2-150 PICS-300
Unit 100~1200MW 300~1200MW 300~1200MW
Received basis volatiles More than 18% 15%~18% More than 12%
Type of BurnerOnce-
Though/SwirlingOnce-
Though/SwirlingOnce-
Though/Swirling
Rate powerRate power 100kW 150kW 300kW
Voltage 380±10%V 380±10%V 380±10%V
Capacity 180kVA 250kVA 400kVA
Cooling water 4m³/h 5m³/h 7m³/h
Working gas 80Nm³/h 100Nm³/h 120Nm³/h
15 | VPC | ENCOTEC | WOM | PIS | 2017-02-02
Experience
No Power Plant Capacity UnitBoiler
manufacturerCombustion
modeType of coal Location
1 Hefei power plant 600MW #5 DECOpposed
Firing Bituminous coal Anhui
2 Tongling power plant 1000MW #5 SECTangential
FiringBituminous
coalAnhui
3 Maanshan power plant 660MW #1 SECTangential
FiringBituminous
coalAnhui
4Gansu jinchang
cogeneration power plant330MW #1、#2
Wuhan boiler manufacturer
Tangential Firing
Bituminous coal Gansu
5 Hefei power plant 600MW #6 DECOpposed Firing
Bituminous coal Anhui
6Xinjiang jiarun power
plant350MW #3、#4 SEC
Tangential Firing
Brown coal Xinjiang
7 Pingwei power plant 1000MW #5、#6 Beijing baweiOpposed
Bituminous coal Anhui7 Pingwei power plant 1000MW #5、#6 Beijing baweiOpposed
Firing Bituminous coal Anhui
8 Luan power plant 600MW #3、#4 SECTangential
FiringBituminous coal Anhui
9 Dapu power plant 660MW #1、#2 SECTangential
FiringBituminous coal Guangdong
10 Xuancheng power plant 660MW #2 HECTangential
FiringBituminous coal Anhui
11 Fuzhou power plant 1000MW #1、#2 DECOpposed
Firing Bituminous coal Jiangxi
12 Xinjiang qitai power plant 660MW #1、#2 HECOpposed
Firing Zhundong coal Xinjiang
13 Banji power plant 1000MW #1、#2 SECTangential
FiringBituminous coal Anhui
16 | VPC | ENCOTEC | WOM | PIS | 2017-02-02
On-Site Visits to China
ENCOTEC in coordination with WOM will arrange visits to Powerplants of WOM in Anhui province of China where similar PlasmaIgnition Systems (PIS) have been installed & operatingsatisfactorily for last many years.
17 | VPC | ENCOTEC | WOM | PIS | 2017-02-02
ENCOTEC - WOM Scope of Work
• Complete coordination with Owner;
• Design, Engineering & supply of PIS on CIF basis at any Indian port;
• Storage of PIS at site;
• Installation of PIS;
• Commissioning of PIS;
• Operation support to Owner;• Operation support to Owner;
• After Sale Services for next five (5) years including spares, which may
be further extended as per mutual agreement;
18 | VPC | ENCOTEC | WOM | PIS | 2017-02-02
Our Plasma ignition products are in safe operation and economic benefits, energy conservation, environmental protection and investment cost has been achieved by the major power generation companies, electric power design institute and boiler manufacturers.
… FOR BETTER RESULTS.