END OF WELL REPORT
HON-GT-01-S2
Operator: Green Well Westland
Prepared by: Well Engineering Partners
Toldijk 17-19
7900 AP Hoogeveen (NL)
Tel: +31 (0) 528 227710
www.wellengineering.nl
Author: S.Kaldenbach, K. Boersma
Version: 1.0
Publication date: 21 August 2015
Reviewed by: Volkert de Ruiter
Agreed by: Maarten Middelburg
End of well report – HON GT-01-S2 v1.0
Page 1
Contents
1. General Project data ...................................................................................................... 3
2. Well summary ................................................................................................................ 4
2.1. Directional plot ......................................................................................................... 5
2.2. Casing ..................................................................................................................... 6
2.3. Cement .................................................................................................................... 6
2.4. Drilling fluid summary ............................................................................................... 6
3. Geology .......................................................................................................................... 7
4. Well schematic ............................................................................................................... 8
5. HSE performance ........................................................................................................... 9
5.1. General .................................................................................................................... 9
5.2. Incidents .................................................................................................................. 9
5.3. NORM ...................................................................................................................... 9
5.4. Drills / Emergency exercises .................................................................................... 9
6. Operations Review ....................................................................................................... 10
6.1. Time summary ....................................................................................................... 10
6.2. Mobilize and Rig Up HWU ..................................................................................... 12
6.3. Fishing run ............................................................................................................. 12
6.4. Set Bridge plug on wireline .................................................................................... 13
6.5. Whipstock and window milling ............................................................................... 14
6.6. Drill sidetrack ......................................................................................................... 15
6.7. Run 5” liner w/ screens .......................................................................................... 17
6.8. Rig down ................................................................................................................ 19
APPENDICES
Appendix I. GR log
Appendix II. Survey report
Appendix III. BHA’s
Appendix IV. 5” liner tally
Appendix V. Wellhead / Xmas tree Details
Appendix VI. Liner hangers
Appendix VII. Daily Drilling Reports
Appendix VIII. Daily Mud Reports
Appendix IX. Drilling Parameters
End of well report – HON GT-01-S2 v1.0
Page 2
Glossary BGL Below ground level
BHA Bottom hole assembly
BHR Basket handrail
BOP Blowout preventer
BPC Balance Point Control
DP Drill pipe
DSV Drilling supervisor
GL Ground level
GR Gamma-Ray
HSE Health, Safety & Environment
HWU Hydraulic workover unit
MD Measured depth
MWD Measurement while drilling
NAP Normaal Amsterdams Peil, standard water table in the Netherlands
NORM Naturally occurring radioactive material
NPT Non-productive time
PDM Positive displacement motor; or mud motor
PJSM Pre-job safety meeting
POOH Pull out of hole
ppf pounds per foot
RIH Run in hole
ROP Rate of penetration
RSS Rotary steerable system
sg Specific gravity
TD Total depth
TOL Top of liner
TVD True vertical depth
UBHO sub Universal bottom hole orientation sub
WWS Wire-wrapped screen
End of well report – HON GT-01-S2 v1.0
Page 3
1. General Project data
Field Honselersdijk Well Number: HON-GT-01S2 Well Name Geothermal Well HON-GT-01S2 Well Type Geothermal Well Producer Start rig mobilisation Spud date
08-06-2015; 07:00 hr 12-06-2015; 19:00 hr
End Date 02-07-2015; 18:00 hr Days Operational 25 Operator Green Well Westland BV
Latitude & Longitude Geographical
Surface Location 52° 00' 58.74"N 4° 13' 32.21"E
X= 75242.83 E Y= 448081.04 N
Grid Coordinate System Rijksdriehoeksmeting / Netherlands New Drilling Contractor BPC Drilling Rig HWU SpaceSaver II Depth reference Groundlevel (BGL), unless otherwise stated Project Management: Project Director G.J. Verkade Project Manager Jos Scheffers Drilling Manager Maarten Middelburg Lead ops Engineer Kornelius Boersma HSE Manager Ted Zwinkels Drilling Supervisors: Drilling Supervisor Bas Kaldenbach 08-06-2015 / 24-06-2015 Drilling Supervisor Art de Vetter 24-06-2015 / 30-06-2015
End of well report – HON GT-01-S2 v1.0
Page 4
2. Well summary
Goals of the well operations were the following:
1. Retrieve (part of) the damaged/plugged 4-½” liner with liner hanger 2. Seal off the original well bore of HON-GT-01-S1 3. Drill window inside 7” liner as close as possible to the top of the 4-½” liner hanger 4. Drill sidetrack through Delft Sandstone & complete same with 5” liner w/ screens 5. No accidents or incidents
From the above only the first goal was not achieved.
Below the well summary of the well operations.
Primary Objective Delft Sandstone Primary Objective Depth 2531 m MD 2346 m TVD Total Depth 2615 m MD 2419 m TVD Elevation Ground level (GL) BHR – GL 17.93 m Basket handrail (BHR) GL – NAP - 0.57 m (GL below NAP)
Table 1: HON-GT-01-S2 well summary
Item m MD m TVD Comments
4-½” Liner hanger
2400 2230
Fill up well with 1,09 sg brine. Attempted to retrieve the part of the 4-½” liner with the 7” x 4-½” liner hanger without success. LIH spear & grapple. Minor losses after fishing attempt
6-⅛” Hole TD
2615 2419
Set permanent bridge plug @ 2391m & test same to 50bar/20mins – OK. Set whipstock at 2391m. Milled window to 2393m. (top window @ 2386m & bottom window @ 2389m). Displace well to 1,10 sg DrillCarb drill-in fluid. P/U 6-⅛” drilling assembly & drill hole to 2615m. POOH & L/D BHA without hole issues.
5”Liner 2354
- 2606
2193 -
2411
P/U & RIH 5” liner with crane. RIH 2-⅞” inner string. Wash down last 3 jnts. Displace well to 1,09 sg NaCl brine. Set liner hanger packer & test to 50bar/20mins – OK. Try to release setting tool; unable. Run free-point wireline: free 4m above TOL. Run wireline & perforate liner hanger setting tool to allow circulation. Circulate successful and retrieve string: sediments had settled on TOL after displacement and during packer pressure test.
End of well report – HON GT-01-S2 v1.0
Page 5
2.1. Directional plot
Figure 1: HON-GT-01S2 Vertical Section plot and plan view plot- drilled vs. planned
End of well report – HON GT-01-S2 v1.0
Page 6
2.2. Casing
In the casing scheme below the original casings from HON-GT-01 & S1, which are part of the existing well structure, are included.
Table 2: HON-GT-01-S2 tubular summary
Item Top m
MD Bottom m
MD Weight Grade Connection
9 ⅝” casing 0 1103 53,5 ppf L80 TSH Blue
7” liner 1022 2386 29 ppf L80 VAGT
5” Liner 2354 2606 18 ppf base pipe 5-½ OD WWS*
L80 VAGT
*Screen interval from 2530 m – 2592 m
2.2.1. Pressure tests:
During the well operations on HON-GT-01-S2 the following pressure tests on the well have been performed:
- Against permanent bridgeplug @ 2391m – 50bar/20mins w/ 1,09 sg brine in the well - Against 5” liner hanger packer @ 2354m – 50bar/20mins w/ 1,09 sg brine in the well
2.3. Cement
No cement jobs have been performed in the drilling of sidetrack HON-GT-01-S2
2.4. Drilling fluid summary
Per section the following drilling fluid types have been used: Table 3: HON-GT-01-S2 drilling fluid summary
Section Type Density Min – Max
4-½” Viscosified brine (YP>25) 1.09 sg
6-⅛” Drill-in Fluid (AMC drillCarb) 1.10 – 1.14 s.g.
6-⅛” Brine (NaCl) 1.09 sg
End of well report – HON GT-01-S2 v1.0
Page 7
3. Geology
The actual and expected geology for the sidetrack section are listed below in Table 4.
Table 4: Lithostratigraphic column HON-GT-01-S2
The geology of the well HON-GT-01-S2 is very similar to the prognosis due to the close vicinity of the nearby wellbore of HON-GT-01-S1.
The top of the Delft Sandstone at HON-GT-01-S1 was found at 2351m TVD. A similar depth was expected at HON-GT-1-S2 but it was found at 2346m TVD
There are a series of geological possibilities which could explain the 5 meters. Most likely a slope of a point bar or a lens has been drilled into, as the Delft Sandstone is a fluvial deposit. Alternative theories which could explain the large depth difference include the presence of a fault or a strong formation dip. The nearest fault should be at least hundreds of meters away, based on the seismic data. A strong formation dip of the Delft Sandstone Formation (at about 23 degrees to the southwest) does not match the formation tops in to the original HON-GT-01 and the well HON-GT-02. In addition both of these options are not considered likely because the gamma-ray logs of the Delft Sandstone of S1 and S2 are very similar.
Era GroupPerio
d
Formatio
nEpoch (Age) Member Lithology
TV- GL
Depth
(m)
AH- GL
Depth
(m)
TV- GL
Depth
(m)
AH- GL
Depth
(m)
2218 2389
Hauterivian Rijswijk
Sandstone KNNSR
Light- to medium-grey sandstones with a very
fine to medium and locally gravelly grain size;
mica, lignitic matter and siderite concretions
are common.
2251 2425 2255 2428
Late Valanginian
to Early
Hauterivian
Rodenrijs
Claystone SLDNR
Medium- to dark-grey and dark brown, silty to
sandy lignitic claystones with laminated or
contorted bedding, and lignite/coal beds.
Traces of mollusc shells, pyrite and siderite.
2278 2457 2285 2462
Valanginian Delft Sandstone SLDND
Light-grey massive sandstone sequence, fine
to coarse-gravelly, fining upward, lignitic. 2351 2544 2346 2531
TD 2615
Vlieland
Sandstone KNNS
A succession of typically red and dark to light
(brownish) grey clay(stones) and variegated
clay- and siltstones, fine to medium grained
sandstones and massive, thick-bedded,
coarse grained sandstones. Coal & lignite
beds.
HON-GT-01-S2
Alblasserdam SLDNA
2402 2594Lower
Cretaceous to
Upper Jurassic
Ryazanian to
Valanginian
2401 2602
Schieland SL
Nieuwerkerk SLDN
Lithostratigraphic Column Green Well Westland 24-06-2015 HON-GT-01-S1
Cre
tac
eo
us
Bit start depth
@
Mesozoicum
Rijnland KN
Berkel
Sand/Claystone KNNSC
Alternation of fine-grained, argillaceous
sandstones and brown-grey silty to sandy
claystones. Locally sideritic concretions are
present.
Lower
Cretaceous Late
Hauterivian to
Early Barremian
2113 2261
End of well report – HON GT-01-S2 v1.0
Page 8
4. Well schematic
A detailed well schematic summarizing all casing sizes is shown below. Note: well depth is not to scale.
Figure 2: HON-GT-01S2 well schematic
Nr. Item Description Depth Depth Hole ID Collar
OD
Pipe ID Pipe ID
Depth Reference: (GL) m m in in in in
tvd ah (nom) (drift)
1 20" J55 10mm WT stove pipe 110 110 19,2"
13 3/8 x 9 5/8" Liner Hanger + Packer 1022 1022
2 9 5/8" 53,5ppf L80 TSH Blue 1103 1103 12-1/4" 10 5/8" 8,535 8,512
7" x 5" Liner hanger 2193 2354 4,173
3 7" 29ppf L80 VAGT (window) 2220 2386 8-1/2" 7,656 6,184 6,125
top screens 2345 2530
base screens 2400 2592
4 5" 18ppf 2411 2606 6-1/8" 5-1/2" 4,276 4,150
Open hole 6-1/8" (TD) 2419 2615
HON-GT-01-S2
13 5/8" 5K Wellhead
7 1/16" Xmastree
End of well report – HON GT-01-S2 v1.0
Page 9
5. HSE performance
5.1. General
To ensure that the operation is carried out in a safe manner, several HSE tools were in place during the operation:
Pre-spud meeting
Toolbox meetings
Pre-job safety meetings (PJSM)
Operation specific HSE plan (GW-HSE-20150423)
NORM plan (GW-NORM-20150423)
5.2. Incidents
No incidents have occurred during the well operations
5.3. NORM
During the operations all incoming and returned equipment was measured for NORM on the drilling location. No NORM contamination was found in any of the measurements.
This matches the expectations as the NORM was only found in the surface equipment during earlier measurements. This is expected to be related to the bubble point of the production fluid.
5.4. Drills / Emergency exercises
Regular drill / emergency exercises have been performed:
Muster drills (27-06-2015, 14-06-2015)
Fire drills (14-06-2015)
Kick drills (27-06-215, 14-06-2015)
End of well report – HON GT-01-S2 v1.0
Page 10
6. Operations Review
Below a summary is given of the various steps of the operation. For a detailed description of daily activities, see Appendix VII for daily reports.
6.1. Time summary
The summary for the operations are listed in Table 5. Actual timing is compared to the planned. After completing the operations the total delay is 9 days as a result of:
1. Some delays during rigging up
a. Working around production lines
b. Offloading operator equipment on small working location
2. Slow running in hole with the fishing BHA#1
a. Difficulty handling the 4-3/4” DC’s
b. Difficulty entering the top of the 7” liner (3,5 hrs)
3. Delays running the whipstock assembly
a. Difficulty making up the MWD (6hrs)
4. Delays while drilling 6-1/8” hole section
a. Sliding sections taking significant time – less efficient than on a rig
b. ROP lower than expected from offset data (2 m/hr actual vs. 6m/hr expected)
5. Delays while running the 5” WWS section
a. Making up liner slower than expected (crane based operations through HWU)
b. Long time (5 hrs) for rigging up to run the 2-7/8” inner string
c. Difficulty retrieving the setting tool (total 37hrs)
6. Slower tripping speeds and BHA handling than expected (for all trips).
a. For tripping the average was 140m/hr actual vs. 180m/hr planned (incl. lubrication, PJSM, drills & breaks etc.)
Some time was saved in comparison to the plan as a result of:
1. Fast & efficient wireline operations (both rigging up/down & operations)
2. Smooth rig down
End of well report – HON GT-01-S2 v1.0
Page 11
Table 5: Summary timing planned vs. actual
Cased hole sidetrack hrs day cum Start hrs day cumtotal
delay
Rig up (incl. P-testing) 78,0 3,3 3,3 8-jun 7:00 108 4,5 4,5 1,3
Attempt fish liner 38,8 1,6 4,9 12-jun 19:00 61 2,5 7,0 2,2
Set mechanical bridgeplug on wireline 16,3 0,7 5,5 15-jun 8:00 5 0,2 7,2 1,7
Set whipstock & mill window 48,6 2,0 7,6 15-jun 12:45 73 3,0 10,3 2,7
Drill cased hole sidetrack to 2520m 40,6 3,4 11,0 18-jun 13:15 181 7,5 17,8 6,8
RIH liner 43,2 1,8 12,8 26-jun 2:00 100 4,2 22,0 9,2
Rig down 64,0 2,7 15,4 30-jun 6:00 60 2,5 24,5 9,0
Total 393,8 16,4 587,0 24,5
Contingency 15% 2,5
Total 18,9
Planned Actual
End of well report – HON GT-01-S2 v1.0
Page 12
6.2. Mobilize and Rig Up HWU
Started: 08/06/2015 07:00 hr
Finished: 12/06/2015 19:00 hr
Planned: 78 hrs
Actual: 108 hrs
NPT: 0 hrs
6.2.1. Summary
Rig move and rig-up of the hydraulic workover unit
6.2.2. Highlights / Lowlights
Efficient and safe rig-up with no major problems despite the small location. - Had to reposition the lower BOP section to be able to fit the remaining BOP sections
with respect to the flowline of GT02.
6.3. Fishing run
Started: 12/06/2015 19:00 hr
Finished: 15/06/2015 08:00 hr
Planned: 38.8 hrs
Actual: 61 hrs
NPT: 0.0 hrs
6.3.1. Summary
The first BHA was made up to fulfill two purposes,
1) attempt to fish the 4-1/2” liner out of hole and
2) drift / scraper the 7” casing.
At the top of the 7” rotary was required to get inside the top of the liner hanger and the second 6-1/8” string mill-stabilizer also had to be rotated into the 7”, thereafter RIH went ok till the top of the 4-1/2” liner.
Before the itco spear (3.885” nominal) was latched on the wellbore fluid was circulated and made viscous w/ 3 kg/m³ XanBore.
The liner was latched on in the first attempt and straight pull up to 150mT overpull was applied, without success. Thereafter jarring commenced, and on the seventh jar cycle the BHA came loose, after checking the up weight against the original weight the BHA was POOH. At surface it was observed that the Itco spear and bullnose were lost down hole.
End of well report – HON GT-01-S2 v1.0
Page 13
Figure 3: Stripped connection inspected at surface
6.3.2. Highlights / Lowlights
Successfully run the fishing BHA combi run with 6-1/8” string mills and non-rotating scraper to the top of the liner (6-1/8” > standard 7” 29# regular drift).
All BHA items were retrieved without increased LSA activity. - Unable to retrieve the liner - Lost the Itco spear and bullnose down hole
6.4. Set Bridge plug on wireline
Started: 15/06/2015 08:00 hr
Finished: 15/06/2015 12:45 hr
Planned: 16.25 hrs
Actual: 4.75 hrs
NPT: 0.0 hrs
6.4.1. Summary
Good and efficient operations setting the 5.61” Owen Core-lab bridgeplug 1.93m above the first 7” connection above the liner hanger. The plug is set at 2391m BGL.
As on the fishing run 2x 6-1/8” stabilizers and a non-rotating casing scraper was run the initially planned dummy run was skipped.
After setting the bridge plug it was successfully pressure tested to 50bar with 1.09SG viscous brine in the well.
6.4.2. Highlights / Lowlights
Very efficient Bridge plug installation
End of well report – HON GT-01-S2 v1.0
Page 14
6.5. Whipstock and window milling
Started: 15/06/2015 12:45 hr
Finished: 18/06/2015 13:15 hr
Planned: 48.6 hrs
Actual: 72,5 hrs
NPT: 6.0 hrs Broken MWD pulser sleeve
6.5.1. Summary
The Whipstock was picked up with the laydown winch of the HWO unit and lowered and hung off in the window where the mill assembly was connected and lowered until the MWD carrier collar. During the attempt to load the MWD probe the MWD pulser sleeve got broken and the tungsten carbide pieces were not all retrieved. All BHA components were laid down to check if there were any tungsten carbide pieces had dropped inside the string. Some pieces were retrieved from the mill. The backup sleeve and pulser sub were picked up.
The BHA was RIH to setting depth, the Whipstock orientated to 270° and set. The window was cut in 3.5 hr’s and the additional 4m rathole in 6.5 hr.
Milling the rathole was consuming a lot of time and in conjunction with the DD it was decided to stop milling for more rathole (initial objective was 10m).
The window was reamed and a dry run in and out was performed successfully.
Prior of pulling out, the well was displaced to 1.10SG Drill-Carb Drill-in fluid with 700 to 800 lpm.
The return fluid was stored inside two containers (respectively 70m³ and 28m³), including a total of 5m³ mist zone. After the displacement the BHA was POOH and laid down. The mills were found up to spec passing the no-go ring gauge test.
Figure 4: Broken MWD pulser sleeve Figure 5: Mill with no-go gauge ring
6.5.2. Highlights / Lowlights
Spot on orientation of the Whipstock Good release of the mill and good progress milling steel. Mill’s came out and were checked with the “no-go” ring OK. - Difficulties loading the MWD and time delay due to the broken pulser sleeve
End of well report – HON GT-01-S2 v1.0
Page 15
6.6. Drill sidetrack
Started: 18/06/2015 13:15 hr
Finished: 26/06/2015 02:00 hr
Planned: 40,6 hrs
Duration: 180,75 hrs
NPT: 2.0 hrs Miss Measurement of UBHO sub
6.6.1. Summary
Prior of picking up the BHA, the 475 PDM (Frontline 4563 w/ 1.5° bent) was sent to WTF Den Helder to have the Bit made up as this was not possible to be made up in the HWO Unit. While making up the BHA, it was found that the UBHO sub was not properly measured, The MWD was reconfigured and loaded into the assembly and surface tested. RIH commenced and entered the top of the 7” without any problems.
At the window, on the first attempt to run the bit out of the window dry, some weight loss was observed, the string was picked up and rotated 30 degrees where after the bit was run outside the window without any hold up. The BHA was pulled back, also without problems. Drilling started. Throughout the section 1050 to 1100 lpm was used mainly to provide sufficient hole cleaning in the 9-5/8” casing section.
From the Rodenrijs claystone cavings throughout the section were observed (see below).
It was found that the ROP was significantly lower than initially expected (1.5-2 m/hr); GT-01 & GT-02 showing average on-bottom ROP of >8m/hr. In addition some efficiency loss accounts for the difference in average daily progress due to connection making: a Topdrive system (super single and triple systems) can add the next section immediately at connection depth where the HWO unit works with a wash joint (similar as a Kelly system) first having to pull back the Kelly / wash joint, add the next section of pipe and lower this into the hole and make up the Kelly / wash joint again.
Despite the fact that S2 was drilled in close vicinity of the original borehole and S1 (separation of ca. 16m) the top of the DelftSand was found higher than expected (2346 m MD actual vs. 2351m MD expected). See chapter 3 for further details
Drilling was continued to 2615m. GR signal was lost after 2578m. Circulated hole clean with 2x B/U. POOH to surface, initial drag on first 2 singles. No further drag was encountered. Laid down BHA and found the bit severely damaged with damaged cutters and washouts on the side. (grading: 6-4-WO-A-X-1-ER-TD), no cutters were missing. PDM shaft/bearing also showed signs of washout.
End of well report – HON GT-01-S2 v1.0
Page 16
6.6.2. Highlights / Lowlights
Good departure of the wellbore from the existing well Drill to well TD in single trip - Two unexpected doglegs of 17.5°/30m 2431m bgl and 9.6°/30m 2450m bgl without
the influence of sliding. - Caving’s coming over the shakers since drilling the rodenrijs claystone - Limited to no ability to treat the mud (no centrifuges and limited screens on site) - On-bottom ROP significantly lower than forecasted (1,5-2 m/hr vs. 5-12 m/hr) - Bit severely damaged/worn & 1/16” undergauge. Washed out. - PDM shaft/bearing showed signs of washout - Lost GR signal while drilling from 2578m to 2615m
End of well report – HON GT-01-S2 v1.0
Page 17
6.7. Run 5” liner w/ screens
Started: 26/06/2015 02:00 hr
Finished: 30/06/2015 06:00 hr
Planned: 43,2 hrs
Duration: 100 hrs
NPT: 37 hrs unable to retrieve setting tool
6.7.1. Summary
Picking & making up the screen section with the HWU required a heavy crane for assistance, since the HWU could not run the screen section without risking damage to the screens. Total screen & inner sting weight w/ liner hanger was 11t. Due to the crane reach and weight of the string a 200t crane was required.
Made up the liner/screen section with 5 jnts screens and hung off string in lower stationaries. Preparations to install the inner string with gooseneck/jackplate & extensions took over 5hrs as the HWU is not ideally suited for this type of operation.
Inner string was run further without issues and Liner hanger was made up OK.
String was RIH without drag up to 5jnts above TD.When the string weight was reduced the string was washed/rotated with 200lpm/15rpm to depth successfully (shoe @ 2606 BGL, TOL @ 2354m BGL).
Well was displaced to brine (550lpm/72bar, limited by liner hanger setting pressure).
Set the liner hanger & packer OK. Tested successfully to 50bar.
While retrieving the liner hanger setting tool the tool could not be retrieved. There was ca. 1,5m free travel and rotation could be achieved. Due to the setting of the packer circulation was not possible. On wireline a free-point indicator was run, which found the free-point 4m above the TOL. From these observations it was expected that the situation was caused by hole fill – sands from the displacement which had now settled above the top of the liner.
2 perforations were then made just above the liner hanger to allow circulation to attempt to loosen the sediment to allow the setting tool to be retrieved. These perforations were placed successfully at exactly the planned location.
Figure 6: Planned location of perforations (inside red circle)
Figure 7: Perforations after POOH
Initially a packer inside the 2-7/8” (below the liner hanger) was also considered to prevent
End of well report – HON GT-01-S2 v1.0
Page 18
injecting into the reservoir but due to unavailability at short notice an initial attempt was made without packer.
Circulation could be achieved and the first two joints were washed out. Thereafter POOH the string successfully without further circulation.
6.7.2. Highlights / Lowlights
Successful screen placement to TD Perforations successful to retrieve setting tool - Unable to retrieve setting tool, required to perforate tool to allow circulation - 2jnts inner string (out of 40) did not pass drift due to damage at tool joint
End of well report – HON GT-01-S2 v1.0
Page 19
6.8. Rig down
Started: 30/06/2015 06:00 hr
Finished: 02/07/2015 18:00 hr
Planned: 64 hrs
Duration: 60 hrs
NPT: none
6.8.1. Summary
Rig down went smooth.
All rental items were returned to the respective suppliers. All equipment was accounted for.
6.8.2. Highlights / Lowlights
Smooth operations All (rental) equipment accounted for