Upload
eithne
View
51
Download
0
Embed Size (px)
DESCRIPTION
Endcap Muons. John Layter US CMS Collaboration Meeting May 19, 2001. Outline. Muon System Overview CSC Production FAST Sites Electronics Progress Integration and Installation CPA, ETC Plans for the next six months Summary. CMS Endcap Muon System. - PowerPoint PPT Presentation
Citation preview
US CMS Collaboration Meeting, UC Riverside, May 19, 2001 1
Endcap MuonsEndcap MuonsEndcap MuonsEndcap Muons
John Layter
US CMS Collaboration Meeting
May 19, 2001
US CMS Collaboration Meeting, UC Riverside, May 19, 2001 2
OutlineOutlineOutlineOutline
• Muon System Overview
• CSC Production
• FAST Sites
• Electronics Progress
• Integration and Installation
• CPA, ETC
• Plans for the next six months
• Summary
US CMS Collaboration Meeting, UC Riverside, May 19, 2001 3
CMS Endcap Muon SystemCMS Endcap Muon SystemCMS Endcap Muon SystemCMS Endcap Muon System
360 CSCs, not counting ME1/1 and ME4•144 Large CSCs (3.4x1.5 m2):72 ME2/2 chambers72 ME3/2 chambers•Small CSCs (1.8x1.1 m2):72 ME1/2 chambers 72 ME1/3 chambers•20o CSCs (1.9x1.5 m2):36 ME2/1 chambers36 ME3/1 chambers
•Frontend Electronics:•170K Cathode channels 140K Anode channels
•Trigger&DAQ (on-chamber part) •Alignment&Services
US CMS Collaboration Meeting, UC Riverside, May 19, 2001 4
Endcap Muon SystemEndcap Muon SystemEndcap Muon SystemEndcap Muon System
US CMS Collaboration Meeting, UC Riverside, May 19, 2001 5
EMU - Yearly BCWSEMU - Yearly BCWSEMU - Yearly BCWSEMU - Yearly BCWS
FY01 is the second largest year of EMU funding:
• Production of chambers at Fermilab at nominal rate
• Purchasing of significant part of FE electronics
• Finalization of integration and installation design EMU BCWS by Fiscal Year
0
1,000,000
2,000,000
3,000,000
4,000,000
5,000,000
6,000,000
7,000,000
8,000,000
9,000,000
FY96 FY97 FY98 FY99 FY00 FY01 FY02 FY03 FY04 FY05
US CMS Collaboration Meeting, UC Riverside, May 19, 2001 6
EMU Chamber StatusEMU Chamber StatusEMU Chamber StatusEMU Chamber Status
Fermilab Site (Panels for 410 CSCs; Assembly of 148 Large CSCs):
• Panel production since 5/99; 52% of chambers done; on schedule
• CSC assembly since 6/00; 32/148 large CSCs done; ~2 wks late
UF and UC Sites (Final Assembly and System Tests of Large CSCs)
• First 5 CSCs arrived at UC and UF; long term HV test will start
• Begin mounting and testing electronics 9/01, ~3 mo. late
• Delivery of on-chamber electronics is on critical path
PNPI Site (114 smaller CSCs)
• Critical tooling commissioned; 2 chambers assembled
• PRR—June 7-8; start production in August
IHEP Site (148 smaller CSCs)
• Critical tooling arrived, being commissioned, begin assembly
• PRR—July 30-31; start production in September
US CMS Collaboration Meeting, UC Riverside, May 19, 2001 7
Week From To Total Total Total Total Total TotalME234/2 ME1/2 ME2/1 ME1/3 ME3/1 ME4/1
October 10/1/99 10/31/99 - - - - - - November 11/1/99 11/30/99 - - - - - - December 12/1/99 12/31/99 - - - - - - January 1/1/00 1/31/00 - 1 - - - - February 2/1/00 2/28/00 - 1 - - - - March 3/1/00 3/31/00 1 - - - - - April 4/1/00 4/30/00 1 - - - - - May 5/1/00 5/31/00 - - - - - - June 6/1/00 6/30/00 2 - - - 1 - July 7/1/00 7/31/00 1 - - - - - August 8/1/00 8/31/00 2 - - - - - September 9/1/00 9/30/00 2 - - - - -
FY00 Summary 9 2 - - 1 - Grand Total 9 2 - - 1 - October 10/1/00 10/31/00 3 - - - - - November 11/1/00 11/30/00 3 - - 1 - - December 12/1/00 12/31/00 3 - - - - - January 1/1/01 1/31/01 4 - - - - - February 2/1/01 2/28/01 4 - - - - - March 3/1/01 3/31/01 4 - - - - - April 4/1/01 4/30/01 - - - - - - May 5/1/01 5/31/01 - - - - - - June 6/1/01 6/30/01 - - - - - - July 7/1/01 7/31/01 - - - - - - August 8/1/01 8/31/01 - - - - - - September 9/1/01 9/30/01 - - - - - -
FY01 Summary 21 - - 1 - - Grand Total 30 2 - 1 1 - October 10/1/01 10/31/01 - - - - - - November 11/1/01 11/30/01 - - - - - - December 12/1/01 12/31/01 - - - - - - January 1/1/02 1/31/02 - - - - - - February 2/1/02 2/28/02 - - - - - - March 3/1/02 3/31/02 - - - - - - April 4/1/02 4/30/02 - - - - - - May 5/1/02 5/31/02 - - - - - - June 6/1/02 6/30/02 - - - - - - July 7/1/02 7/31/02 - - - - - - August 8/1/02 8/31/02 - - - - - - September 9/1/02 9/30/02 - - - - - -
FY02 Summary - - - - - - Grand Total 30 2 - 1 1 - October 10/1/02 10/7/02 - - - - - - November 11/1/02 10/14/02 - - - - - - December 12/1/02 10/21/02 - - - - - - January 1/1/03 10/28/02 - - - - - - February 2/1/03 11/4/02 - - - - - - March 3/1/03 11/11/02 - - - - - - April 4/1/03 11/18/02 - - - - - - May 5/1/03 11/25/02 - - - - - - June 6/1/03 12/2/02 - - - - - - July 7/1/03 12/9/02 - - - - - - August 8/1/03 12/16/02 - - - - - - September 9/1/03 12/23/02 - - - - - -
FY03 Summary - - - - - - Grand Total 30 2 - 1 1 -
FNAL Factory Status - Chamber assembly at MP9
• 32 large CSCs assembled by May 2001
• > 20% complete
• Production ~ at nominal rate
• ~ On schedule
CSC Production at MP9(ME234/2)
-40
0
40
80
120
1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 33 35 37 39 41 43
Month in productionN
um
be
r o
f C
ha
mb
ers
Shortage
DONE
Goal = 148 Chambers
FY00 FY01 FY02 FY03
US CMS Collaboration Meeting, UC Riverside, May 19, 2001 8
Chamber AssemblyChamber AssemblyChamber AssemblyChamber AssemblyGluing Station
(anode bars, gap bars are glued to panels)Winding Station
(wires are wound directly on panels)Soldering Station
(automated soldering of wires)
Wire Tension/Spacing Station(tension and spacing of wires are checked)
Ionized Air Knife Station(dust is removed from wires and panels)
Assembly Station(panels are stacked to make chamber)
US CMS Collaboration Meeting, UC Riverside, May 19, 2001 9
CSCs at UC FAST SiteCSCs at UC FAST SiteCSCs at UC FAST SiteCSCs at UC FAST Site
US CMS Collaboration Meeting, UC Riverside, May 19, 2001 10
CSCs at UC FAST SiteCSCs at UC FAST SiteCSCs at UC FAST SiteCSCs at UC FAST Site
US CMS Collaboration Meeting, UC Riverside, May 19, 2001 11
CSC Production at PNPICSC Production at PNPICSC Production at PNPICSC Production at PNPI
PreproductionPrototype (P3) assembled at PNPI
US CMS Collaboration Meeting, UC Riverside, May 19, 2001 12
CSC production at IHEPCSC production at IHEPCSC production at IHEPCSC production at IHEP
Critical tooling received
Wire Tension measurement machine
US CMS Collaboration Meeting, UC Riverside, May 19, 2001 13
Functions of ElectronicsFunctions of ElectronicsFunctions of ElectronicsFunctions of Electronics
Acquire precise muon data for offline analysis
• Cathode strips: precise azimuthal position (in bending plane) in each layer by interpolation of induced strip charges.
• Anode wires: precise timing and coarse radial position.
Generate primitives for Level 1 trigger• Identify Local Charged Track (LCT) segments
using cathode and anode signals.
US CMS Collaboration Meeting, UC Riverside, May 19, 2001 14
Electronics System LayoutElectronics System LayoutElectronics System LayoutElectronics System Layout
US CMS Collaboration Meeting, UC Riverside, May 19, 2001 15
US CMS Collaboration Meeting, UC Riverside, May 19, 2001 16
Radiation Tolerance TestsRadiation Tolerance TestsRadiation Tolerance TestsRadiation Tolerance Tests
Measure Single Event Upset (SEU) and Total Ionization Dosage (TID) effects with 63 MeV proton beam at UC Davis.
Measure effects due to Displacement damage of bipolar and biCMOS with 1MeV neutrons at OSU.
Results:• Negligible degradation of analog performance due to
TID (>10kRad) or displacement (2x1012 cm-2 neutrons).
• No latch-ups observed up to p fluence of 2x1012 cm-2.
• SEUs in FPGAs observed and cross sections measured. All SEUs recoverable by reloading FPGAs. SEU rate at peak LHC luminosity manageable for CFEB, but higher for ALCT.
US CMS Collaboration Meeting, UC Riverside, May 19, 2001 17
On-chamber Electronics IOn-chamber Electronics I On-chamber Electronics IOn-chamber Electronics I
Three out of four on-chamber boards designed and tested:
• Cathode Front End Board (CFEB)
• Anode Front End Board (AFEB)
• Low Voltage Distribution Board (LVDB)
Most of the components for these boards (excluding rad hard LV-regulators) procured in quantities sufficient to start production
Production costs at or below estimates
US CMS Collaboration Meeting, UC Riverside, May 19, 2001 18
On-chamber Electronics IIOn-chamber Electronics II On-chamber Electronics IIOn-chamber Electronics II
LV-regulators (CERN design, standard for LHC experiments) are not available. Will define the schedule of production of CFEB and LVDB. On critical path
ALCT being redesigned using Xilinx FPGA (faster reloading) to deal with SEU problem. Preproduction boards to be delivered by September 2001. On critical path
US CMS Collaboration Meeting, UC Riverside, May 19, 2001 19
Status of On-chamber Status of On-chamber BoardsBoards
Status of On-chamber Status of On-chamber BoardsBoards
US CMS Collaboration Meeting, UC Riverside, May 19, 2001 20
Off-chamber ElectronicsOff-chamber Electronics Off-chamber ElectronicsOff-chamber Electronics
Progress made on next round of prototype boards and on VME custom backplane.
Updated versions of the prototype boards will be delivered to the FAST sites during this summer.
These will be used for tests of mass-produced on-chamber electronics assembled with chambers.
US CMS Collaboration Meeting, UC Riverside, May 19, 2001 21
Integration & InstallationIntegration & InstallationIntegration & InstallationIntegration & Installation
Infrastructure:• Walkways
• Piping, cooling, cabling
• Chamber mounting
Installation:• Fixture
• Strategy
• Schedule
US CMS Collaboration Meeting, UC Riverside, May 19, 2001 22
US CMS Collaboration Meeting, UC Riverside, May 19, 2001 23
US CMS Collaboration Meeting, UC Riverside, May 19, 2001 24
US CMS Collaboration Meeting, UC Riverside, May 19, 2001 25
Mounting DetailMounting DetailMounting DetailMounting Detail
US CMS Collaboration Meeting, UC Riverside, May 19, 2001 26
Chamber MountsChamber MountsChamber MountsChamber Mounts
US CMS Collaboration Meeting, UC Riverside, May 19, 2001 27
Mounting PrecisionMounting PrecisionMounting PrecisionMounting Precision
US CMS Collaboration Meeting, UC Riverside, May 19, 2001 28
Integration and installation designIntegration and installation design
• EMU integration design advanced (mechanical, gas, cooling, power)
• Installation procedures being defined
• Installation fixture fully designed and built
US CMS Collaboration Meeting, UC Riverside, May 19, 2001 29
CSC installation fixtureCSC installation fixtureCSC installation fixtureCSC installation fixture
Counterweight movement keeps balance w/ or w/o chamber Chamber can rotate at any angle
Counterweight
US CMS Collaboration Meeting, UC Riverside, May 19, 2001 30
US CMS Collaboration Meeting, UC Riverside, May 19, 2001 31
Chamber Production and Chamber Production and Installation Schedule (V31)Installation Schedule (V31)Chamber Production and Chamber Production and
Installation Schedule (V31)Installation Schedule (V31)
• CMS Schedule V31: Installation of all CSCs on the surface at SX5, beginning in 2002.
• Very tight, advanced by ~1 year compared to V30. Pressure on production and installation rate.
US CMS Collaboration Meeting, UC Riverside, May 19, 2001 32
EMU Critical Path Analysis - IEMU Critical Path Analysis - IEMU Critical Path Analysis - IEMU Critical Path Analysis - I
FY01: Delivery of on-chamber electronics is on the critical path:
• ALCT Board redesign and start of production
• Rad Hard Voltage regulators: CFEB, LVDB production
FY02: CSC assembly at FAST sites and installation at CERN is on the critical path
US CMS Collaboration Meeting, UC Riverside, May 19, 2001 33
EMU Critical Path Analysis - IIEMU Critical Path Analysis - IIEMU Critical Path Analysis - IIEMU Critical Path Analysis - II
FY03: CSC Installation (station ME3) is on the critical path:
• short installation window (two shifts necessary)
FY04: CSC Installation (station ME1) is on the critical path:
• RPCs must be installed before CSCs• HE, EE, SE, ME1/1 cables should be installed
before CSCs• Short installation windows (two shifts)
Available Slack analysis:~25-30 working days in 2002. Very tight in 2003 –2004. Need two shifts for production at IHEP and ME1/2,3
installation
US CMS Collaboration Meeting, UC Riverside, May 19, 2001 34
EMU – Estimate to CompleteEMU – Estimate to CompleteEMU – Estimate to CompleteEMU – Estimate to Complete
EMU - ETC 18.9 AYM$
EDIA (k$)
M&S (k$)
Mfg Labor (k$)
EMU Estimate to Complete: 18.9 Actual Year M$ Dominated by M&S (mostly electronics)
US CMS Collaboration Meeting, UC Riverside, May 19, 2001 35
Plans for the Next 6 MonthsPlans for the Next 6 MonthsPlans for the Next 6 MonthsPlans for the Next 6 Months
• Continue CSC production at Fermilab.
• Start production at PNPI and IHEP.
• Continue FE electronics production.
• Start electronics assembly and begin chamber tests at FAST sites.
• Complete integration drawings for all chamber types.
• Begin preparations for receiving and installing chambers at CERN.
US CMS Collaboration Meeting, UC Riverside, May 19, 2001 36
SummarySummarySummarySummary
• Nominal rate of chamber production at FNAL achieved. Chamber production on schedule.
• FE electronics production started; first cost experience positive.
• LV-regulators and trigger boards on the critical path; defines beginning of assembly at FAST sites.
• Endcap infrastructure designed; installation fixture exists.
• Adequate base program support is critical to maintain the schedule.