Upload
ngokien
View
215
Download
1
Embed Size (px)
Citation preview
Energy Association of Pennsylvania Meeting
PECO Energy Utility Integrated Concord Microgrid Project
March 21, 2017
Background 2
In October 2015 PECO introduced it’s intention to develop a microgrid as part of it’s System 2020 five year plan
PECO evaluated many potential projects with a focus on providing critical goods and services to customers during extended outage periods. Projects were evaluated with a selection criteria that focused on; customer mix, reliability need, capacity need, surrounding population density, and area accessibility
Conceptual designs of the four highest potential pilot opportunities were further developed and evaluated by performing formal feasibility and business case studies. The final four projects were re-ranked and the Concord Microgrid Project was selected
The Concord Microgrid is a clustered microgrid design supporting 30 customer connections with a peak load of 8.6 MW and estimated cost of $35M. PECO filed a petition for allowance with the Pennsylvania PUC to construct the Concord Microgrid Project in May of 2016
In October of 2016, PECO withdrew it’s microgrid filing with the PUC based on concerns around utility ownership of generation, business case challenges, project size and cost, and rate structure challenges
PECO will enter into collaborative discussions with key stakeholders in an effort to obtain better alignment and move this project forward
Feasibility / Business Case Analysis
Feasibility Study• Initial conceptual designs were optimized to provide maximum benefit and stakeholder appeal• Base case and advanced case designs with additional customer involvement and more
advanced technology were developed for each pilot• Pocket reliability studies and root cause analysis were performed• Post microgrid reliability improvements were estimated• Load profile and consumption studies were done to estimate and optimize the generation mix• Operational characteristics were identified
Business Model Framework, Approach and Analysis • Project challenges• Base and advanced case functionality and economic performance• Key financial and maintenance cost assumptions• Business model inputs; cost, revenue, tax credits, and public funding • Capital and O&M cost breakdowns• Revenue opportunities / market participation • Cash flow and NPV• Customer reliability savings – Interruption Cost Estimator – LBNL ICE Model
3
Types of Microgrids 4
Source: EPRI
Utility Integrated Microgrid Design & Challenges 5
Each utility has it’s own unique electrical distribution configuration
In the case of the Concord Microgrid, the targeted public purpose customers are connected to five different circuits operating at 34kV and 4kV
Each microgrid requires a common point of interconnection (POI) to enable islanding operation
Creation of POI will require moderate to extensive distribution system reconfiguraton – more costly than a campus style microgrid
Customer selection and mix is a key selection criteria that has a huge impact on the electrical reconfiguration cost. Some projects that had a very favorable customer mix were removed from consideration because of the high complexity and cost of the electrical reconfiguration. Who’s in and who’s out?
Aerial facilities within the microgrid footprint need to be hardened against storm damage
Project Approach / Phases 6
Establish firm goals and objectives prior to design Customer mix is a key selection criteria for a public purpose microgrid Systemic thinking achieves optimal operational & functional requirements
7
Privileged & Confidential – Prepared at the Request of Counsel – Not For Distribution
Microgrid Site Geographic Overview
Complex
Green - Microgrid 1Yellow - Microgrid 2
Slide 8
Concord Microgrid Project
*Sited on Customer Property
Microgrid 1Microgrid 2
*Li-Ion BESS2x100 kW
*Roof-Top PV260 kW
*Carport PV74 kW
*Wind Turbine160 kW
*Rooftop PV930 kW
Municipal Building, and Fire Station
Level 2 EV Chargers
Level 3 EV Chargers
CC
C
Shopping Center
CHotel
Shopping Center Hotel
CCShopping Centers
NG Engine 1980 kW
NG Engine 1980 kW
NG Engine 1980 kW
NG Engine 1980 kW
NG Engine 1980 kW
Shopping Center
Multiple Building Locations
Retirement Home, Gas Station, Food, ATM,
Sewage Plant
Shopping Center
4.0 MW Peak
4.6 MW Peak
Ground Mount PV500 kW
8
Customers include; medical and surgery centers, retirement community, township building, fire station, sewage plant, gas stations, supermarkets, convenience stores, restaurants, pharmacies, bank services, home improvement, hotels, shelter, and retail space
*EV Chargers
Li-Ion BESS200 kW
Slide 9
Microgrid #1 – Conceptual Single Line Diagram
HealthcareHealthcare
Wholesale Store
Hea
lthca
re
Hotel266.4 kW
Hotel
Office Supply
Restaurant
Grocery
Large Retailer
Shopping Center
Hotel129.6 kW
Shopping Center
9
Home Improvement
Store
SC Trans
Shelter
34kV Circuit X
Microgrid #2 – Conceptual Single Line Diagram
2*1.98MVAJ162 Gas Engine
N/O MG Tie Switch
Concord Sewage385kVA
34kV/4.6kV
to MG1
~4000'
RCLC
52
Wawa76.5kVA
Maris Grove3529.8kVA
91857
~700'
250kW
10kW
Main Grid
RCLC52
52
RCLCPOI
LEGENDRCLC: Remotely Controllable Load CenterPOI: Point of Interconnection to Main GridMG1: Cluster Microgrid 1
Border line of customer propertiesAerial cableUnderground cable
MG2 Generation Station
1NOTE
: Distributed Generation for Advanced Case
1
1
Gas, Food, ATM
Retirement Home
Sewage Plant
10
Microgrid 1
34kV Circuit Y
Operational & Design Overview 11
Peak generation capacity allows for full islanding without demand response Transition between all modes of operation Environmentally friendly renewable DER BESS to maintain high power quality - renewable smoothing, generator loading, loading shedding,
and demand transitions Uninterruptible power supply for fire house, township building, and shelter Remotely controlled load centers to coordinate load block management and fault isolation Coordination with existing utility distribution automation schemes Protection and control coordination with utility for island and parallel operation Economic dispatch of DER during parallel operation Remote DMS control and monitoring from PECO Operations Control Center
Utility Integration of the Microgrid 12
Source: EPRI Integrated Grid
EPRI Microgrid Optimization Study 13
The objective of this study is optimize the current conceptual design
One year of historical load profile is being used to optimize DER resource type and size to deliver optimal operational effectiveness and economic dispatch
Data integrity and organization has been a challenge
Load profile data is being organized in a nodal (load center) format to perform the analysis
DER-CAM - Distributed Energy Resources Customer Adoption Model is the primary tool that is being used to perform this analysis
• Allows users to perform scenario analysis of system to optimize design• Economic and environmental model of customer DER adoption• Determine the optimal Microgrid configurations as well as operating strategies• Developed at Lawrence Berkley National Lab in 2000• Aims to minimize the cost of operating on-site generation
Other tools are also being used to provide additional insights
EPRI Microgrid Optimization Study
Challenges• Extracting one year of Demand Data to develop an aggregate load profile for
customers served by the microgrid Interval Mix (15 & 30 min) Variety of meter types Data gaps due to customer relocations and meter upgrades occurring within
the sample data set
• Extracting existing infrastructure information need for power flow modeling. Conductor Type Impedance Lengths Nodes
14
EPRI Microgrid Optimization Project 15
Current Project Status• Report is being finalized
EPRI Deliverable• DER-CAM scenario report for 4 seasons• Power Flow Model (multi-node analysis)• Cost/Benefit Analysis• Recommended location and sizing of DERs• Recommendation on load block size and sectionalizing options
Project Objectives • Further develop project and prepare for next phases; design, planning, and HIL• Support DER-CAM tool development and enhancement for utility use• Provide feedback on how to make tool more effective and user friendly• Support EPRI’s Integrated Grid Vision - process for taking a project from concept
to execution
16
Design Framework• Selection of critical public purpose customers dispersed among disparate feeders and voltages• Creation of Point of Common Coupling (PCC) • Minimize foundational hardening and reconfiguration cost• Contingency Management
Demand Data Granularity• Traditional utility analysis philosophy may not be adequate• Readily available information lacks high resolution• Customer-level analysis requires AMI infrastructure with adequate sampling rate• Data repository access may be a challenge
Island Mode Operational Pillars• PA law mandated voltage band must be maintained
120V nominal (+/-5% for residential and +/-10% for commercial/industrial)• Generation capacity must support total load for utility application• Multi-customer coordination and integration of existing DERs must be considered
Safety, Standards, Operating Practices • Safe operation and new equipment will require testing, new construction standards, operating
practices, and training• Microgrid industry standards are under development
Utility Integrated Microgrid Challenges
Microgrid / Utility Grid Integration Benefits 17
Benefits for Both Grids…….
The Utility Grid Benefits the Microgrid• Enhances microgrid reliability by providing a reliable source of power • Provides a low cost alternative to microgrid generation - DERMS
platform enables economic dispatch and improves bottom line cost• Provides demand (market) for renewable generation / promotes
renewable penetration
The Microgrid Benefits the Utility Grid• Generation can be used to alleviate overloads on utility circuits –
dependent on electrical configuration and type of microgrid • Microgrid generation at point of interconnection can be incorporated
into existing utility grid distribution automation scheme (virtual tie circuit) to provide additional contingency and improved reliability
18
Business cases for utility integrated microgrids focused on reliability and resiliency are challenging. Need to improve our ability to quantify savings associated with reliability, resiliency, public safety, and deferred investments.
Need to educate key stakeholders on the value of the resiliency – insurance policy analogy
Regulatory framework needs to change to enable microgrids and DER applications
Utility philosophies must adapt to properly conceive, implement, and successfully build & operate effective microgrids
Operational approach moves from a reactive mode to a proactive / optimization mode
Grid-connected and islanded modes of operation will result in different fault current levels – traditional relay protective schemes will not be adequate
Next steps for Concord are; preliminary design, planning, and hardware in the loop (HIL) simulation testing to evaluate dynamic system response and protection and control requirements
Closing Thoughts