1 [Type the document title]
Engineering and Commercial Infrastructure -
Water Services
17 October 2015 to 6 November 2015
Page 2
Engineering & Commercial Infrastructure Monthly Review > 17 October 2015 to 6 November 2015
OVERVIEW ............................................................................................................................. 3
SAFETY ................................................................................................................................ 4
1.1. Incident Statistics ........................................................................................................ 4 1.2. Preventative Actions .................................................................................................... 4
TEAM CULTURE ................................................................................................................ 5
2.1. Team Engagement ...................................................................................................... 5 2.2. Performance Appraisals .............................................................................................. 5 2.3. Annual Turn Over ........................................................................................................ 6 2.4. Operational Hours ....................................................................................................... 6 2.5. Employee Satisfaction Rating ..................................................................................... 8
FINANCE .............................................................................................................................. 8
3.1. Water Operating Revenue Less Expenditure .............................................................. 8 3.2. Accrued Water Operating Revenue Less Expenditure ................................................ 9 3.3. Wastewater Operating Revenue Less Expenditure .................................................... 9 3.4. Accrued Wastewater Operating Revenue less Expenditure...................................... 10 3.5. Capital Expenditure Performance ............................................................................. 10
CLIENT SERVICES ......................................................................................................... 11
4.1. Requests ................................................................................................................... 11 4.2. Request Types .......................................................................................................... 11 4.3. Plumbing Applications ............................................................................................... 12 4.4. Electronic Plumbing Applications .............................................................................. 13 4.5. Plumbing Inspections ................................................................................................ 13 4.6. Trade Waste Approvals ............................................................................................. 14 4.7. Annual Trade Waste Activity ..................................................................................... 14 4.8. Trade Waste Compliance .......................................................................................... 15 4.9. Building Over Adjacent Sewers ................................................................................. 16 4.10. Scientific and Analytical Services .............................................................................. 16 4.11. Community Engagement ........................................................................................... 17
ASSET MANAGEMENT ................................................................................................ 18
5.1. Surface Water Raw Water Storage Capacities ......................................................... 18 5.2. Annual Water Consumption vs Allocation by Source ................................................ 19 5.3. Water Consumption by Locality ................................................................................. 19 5.4. Wastewater - Mackay North and Mackay South Inflows ........................................... 20 5.5. Wastewater – Sarina and Mirani/Marian Inflows ....................................................... 20 5.6. Sewer Inspections – CCTV Camera ......................................................................... 21 5.7. Projects ..................................................................................................................... 22
REGULATORY COMPLIANCE ..................................................................................... 29
6.1. Drinking Water Compliance ....................................................................................... 29 6.2. Wastewater Compliance ........................................................................................... 30 6.3. Backflow Testing ....................................................................................................... 30
Page 3
Engineering & Commercial Infrastructure Monthly Review > 17 October 2015 to 6 November 2015
OVERVIEW
This report is for Water Services activities for October/November 2015. Please note that references to the October/November reporting period covers the period 17 October 2015 to 6 November 2015. Significant items in this period include:
Water Services staffed a stand in Caneland Central encouraging people to sign up to the
MyH2O website during National Water Week (18 - 24 October 2015)
Television and radio campaigns commenced on 1 November 2015, encouraging residents to
sign up to the MyH20 website, leading into and following the release of water bills in mid-
November
Twenty Members of the Mackay Rotary Club attended a tour of the Nebo Road Water
Treatment Plant and Scientific and Analytical Services Laboratory on 20 October 2015
Industry Regulation was discussed by QBCC guest speakers at the Plumbing Industry
Information Session held on 29 October 2015
Officers attended the Queensland Water Directorate Queensland Urban Water Innovation
Forum in Maroochydore on 5 November 2015
No environmental incidents occurred between 17 October 2015 and 6 November 2015
Acting Director Engineering and Commercial Infrastructure
Page 4
Engineering & Commercial Infrastructure Monthly Review > 17 October 2015 to 6 November 2015
SAFETY
1.1. Incident Statistics
The incident statistic details a summary of the Water Services safety incident performance. Water Services aspires to achieve zero harm with a stretch target of zero injuries.
1.2. Preventative Actions
To achieve improved safety performance a range of improvement initiatives are undertaken on a monthly basis. The following figure tracks the improvement process through implementation of the SafePlan Monthly Action Plans (MAPs) and the hazard inspections.
3 Non Injury Incidents -Abusive Phone Call, Vehicle Incident and working outside fitness for work policy and 1 No Lost Time incidents, this included a vehicle incident
Data is for period 17 October 2015 to 6th November 2015
0
2
4
6
8
10
No
. of
Inci
den
ts
Lost Time Injuries
Lost Time Injuries Safety Incidents
For the month of October, 18 scheduled Hazard insepctions were scheduled and 4 remain outstanding. One outstanding inspection from September was completed in October. MAP's completed in October is at 98%
Data is for October 2015
80
90
100
0123456789
101112131415161718192021222324
Per
cen
tag
e o
f M
AP
s co
mp
lete
d
No
. of
Haz
ard
In
spec
tio
ns
Hazard Inspections MAPs Target MAPS
Page 5
Engineering & Commercial Infrastructure Monthly Review > 17 October 2015 to 6 November 2015
TEAM CULTURE
2.1. Team Engagement
Water Services believes that a high performing culture is an essential part of a successful business. The following chart tracks the initiatives to achieve an engaged, aligned and performing workplace culture through regular team meetings.
2.2. Performance Appraisals
The following chart tracks the initiatives to achieve an engaged, aligned and performing workplace by conducting regular performance appraisals.
02468
10121416182022
No
. To
olb
ox
Tal
ks
No. Toolbox talks held No. Toolbox talks target
Toolboxes meetings conducted as scheduled
Data is for period 17 October 2015 to 6 November 2015
0
5
10
15
20
Per
form
ance
Ap
pra
isal
s O
uts
tan
din
g
Appraisals Outstanding Target
There were 6 appraisals outstanding as at 6th November 2015.
Data is for period 17 October 2015 to 6 November 2015
Page 6
Engineering & Commercial Infrastructure Monthly Review > 17 October 2015 to 6 November 2015
2.3. Annual Turn Over
The following staff turnover statistics are presented as an indicator of staff stability in the business. The business aims to keep the annual turnover under 10%.
2.4. Operational Hours
The following charts detail Scheduled and Unscheduled overtime performed as well as total hours worked.
No staff members left between 17 October to 6 November 2015.The total number of vacancies as at 6th November 2015 was 14.
Data is for period 17 October 2015 to 6 November 2015
0%
2%
4%
6%
8%
10%
12%
02468
101214161820
% A
nn
ual
Tu
rno
ver
Nu
mb
er o
f S
taff
Staff Turnover Total Vacancies % Annual Turnover
Scheduled overtime decreased from the previous month and unscheduled overtime has decreased from the previous month. The reporting period is 3 weeks
Data is for period 17 October 2015 to 6 November 2015
0
500
1000
1500
2000
2500
No
. Ho
urs
per
Mo
nth
Operational Hours
Scheduled Overtime (hrs) Unscheduled Overtime (hrs)
Page 7
Engineering & Commercial Infrastructure Monthly Review > 17 October 2015 to 6 November 2015
The following chart shows the breakdown of overtime between Water and Sewerage for Water Networks, Water Treatment and Plumbing and Trade Waste for the October 2015
The reporting period is 3 weeks, this accounts for the total hours worked decreased from the previous month. The Overtime as a % of total hours decreased.
Data is for period 17 October 2015 to 6 November 2015
0%
2%
4%
6%
8%
10%
12%
14%
0
5000
10000
15000
20000
25000
30000
% O
ver
tim
e
No
. Ho
urs
per
Mo
nth
Operational Hours
Total Worked (hrs) Overtime Performed (hrs)% Overtime of Total Hours worked
0
5000
10000
15000
20000
25000
30000
Water Networks Water Treatment Plumbing and TradeWaste
Ove
rtm
ie (
$)
Water Sewage
Overtime for October went over budget. For the YTD the budget is $42k underspent
Financial data is for October 2015.
Page 8
Engineering & Commercial Infrastructure Monthly Review > 17 October 2015 to 6 November 2015
2.5. Employee Satisfaction Rating
The following chart shows the average Employee Satisfaction Rating for those that have completed a Performance Appraisal within the reporting period
FINANCE
3.1. Water Operating Revenue Less Expenditure
The following shows the actual, budget and forecast Earnings before Interest, Taxes and Amortization (EBITA) based on cash accounting for the 2015/2016 financial year. The saw tooth nature of the graph is reflective of the timing of water revenue received. The capital revenue has been excluded from this graph
7 Performance Appraisals were completed during the reporting period
Data is for period 17 October 2015 to 6 November 2015
02468101214161820
0
1
2
3
4
5
No
. of
Ap
pra
isal
s C
om
ple
ted
Saf
isfa
ctio
n R
atin
g
Satisfaction Rating Appraisals Completed
ExtremelySatisfiedVerySatisified
Satsified
Somewhat SatisfiedNot Satisified
-
5,000,000
10,000,000
15,000,000
20,000,000
25,000,000
30,000,000
Rev
enu
e le
ss e
xpen
dit
ure
(m
arg
in)
$
Budget - Water Actuals - Water Projected Actuals - Water
Water Fund is $1.58M surplus. Income is up by $406K with an underspend of $731k in Goods & Services and underspend of $401K in Employee Costs
Financial data is up to October 2015.
Page 9
Engineering & Commercial Infrastructure Monthly Review > 17 October 2015 to 6 November 2015
3.2. Accrued Water Operating Revenue Less Expenditure
The following shows the estimation of the accrued revenue less expenditure. The capital revenue has been excluded
3.3. Wastewater Operating Revenue Less Expenditure
The following shows the actual, budget and forecast EBITA based on cash accounting for the 2015/2016 financial year. The saw tooth nature of the graph is reflective of the timing of water revenue received. The capital revenue has been excluded from this graph.
-
5,000,000
10,000,000
15,000,000
20,000,000
25,000,000
Sep-15 Dec-15 Mar-16 Jun-16
Rev
enu
e le
ss e
xpen
dit
ure
(m
arg
in)
$
Budget - Water Accrual Actual - Water Accrual Proj. Accrual Actuals - Water
On an accrual basis , water actuals YTD are surplus of budget by $994K. The annual Surplus is projected to be $1.07M.
Financial data is from September 2015.
-
5,000,000
10,000,000
15,000,000
20,000,000
25,000,000
30,000,000
35,000,000
Rev
enu
e le
ss e
xpen
dit
ure
(m
arg
in)
$
Budget - Sewerage Actuals - Sewerage Projected Actuals - Sewerage
Sewage Fund is $1.6 million surplus . Income is up by $265K with an underspend of $1.253m in Goods & Services and Employee cost os $84k .
Financial data is up to October 2015.
Page 10
Engineering & Commercial Infrastructure Monthly Review > 17 October 2015 to 6 November 2015
3.4. Accrued Wastewater Operating Revenue less Expenditure
The following shows the estimation of the accrued revenue less expenditure. The capital revenue has been excluded
3.5. Capital Expenditure Performance
The following trend provides a high level overview of the capital expenditure to monitor forecast expenditure against actual expenditure. The forecast expenditure profile is based on the project delivery schedule within Water Services.
.
-
5,000,000
10,000,000
15,000,000
20,000,000
25,000,000
30,000,000
Sep-15 Dec-15 Mar-16 Jun-16
Rev
enu
e le
ss e
xpen
dit
ure
(m
arg
in)
$
Budget - Sewerage Accrual Actual - Sewerage AccrualProj. Accrual Actuals - Sewarage
On an accrual basis , water actuals YTD are surplus of budget by $527K. The annual Surplus is projected to be $1.3M.
Financial data is from September 2015.
-
5,000,000
10,000,000
15,000,000
20,000,000
25,000,000
Exp
end
itu
re (
$)
YTD Actual Capital ExpenditureYTD Actual + Committals Capital ExpenditureForecast Cash Flow Capital
Capital expenditure actuals resulted in a 24% spend of Budget. Including committals 57% of the total budget is spent.
Financial data is up to October 2015.
Page 11
Engineering & Commercial Infrastructure Monthly Review > 17 October 2015 to 6 November 2015
CLIENT SERVICES SRVE
4.1. Requests
This graph details the client requests received and recorded via pathways that relate to the Water Business. The target is to have 90% of all client requests closed at any one point in time.
4.2. Request Types
The following chart displays a summary of the client request types received for the month.
0%10%20%30%40%50%60%70%80%90%100%110%
0
100
200
300
400
500
600
% C
lien
t R
equ
ests
Co
mp
lete
d
To
tal C
lien
t R
equ
ests
Monthly Client Requests Received
% of total Client Requests Completed
Completion Target %
97% of Client Requests completed in October 2015
Data available to end October 2015 only
Small increase in water service leaks this month with a decrease in meter broken/leaking
Data is for October 2015 only.
0
50
100
150
Sew
era
gebl
ocka
ge/s
pill
Sew
era
ge o
dou
r
Sew
er M
isce
llan
eou
s
Bac
kflo
w P
reve
ntio
n
Dirt
y w
ater
/Clo
udy
wa
ter
Fire
Hyd
rant
/S
erv
ice
Val
ve
No
Wa
ter
/ Low
Wat
er
Pub
lic A
men
ities
/ R
ecF
acili
ties
Wat
er
Lea
k S
ervi
ce
Wat
er
Lea
k M
ain
Wat
er
Met
er
Bro
ken/
Lea
kin
gW
ate
rO
dour
/Tas
te/S
me
ll
To
tal C
lien
t R
equ
ests
Page 12
Engineering & Commercial Infrastructure Monthly Review > 17 October 2015 to 6 November 2015
4.3. Plumbing Applications
In accordance with the Plumbing and Drainage Act a plumbing application is required for all new plumbing installations or modifications to existing plumbing. A plumbing application must be lodged to Local Government. Water Services has a regulatory time frame of 20 business days to assess a plumbing application. An internal target of 5 business days has been set for all residential plumbing applications.
An indication of the amount of building activity in each population centre of the Mackay region can be derived by assessing the building activity by location. This is summarised in the graph below
Plumbing applications are down due to the shorter reporting period. Approval Time are at 3 days which is the average for the year
.
Data is for the period from 17 October to 6 November 2015
0
2
4
6
0
50
100
Ap
pro
val
Tim
e (D
ays)
Ap
plic
atio
ns
Information Requests Sent Total Approved Plumbing Applications
Average Approval Time Target Plumbing Approval Turn around Time
0
20
40
Ap
plic
atio
ns
Plumbing Applications Received Central (South) Plumbing Applications Received Central (North)
Plumbing Applications Received West Plumbing Applications Received South
Page 13
Engineering & Commercial Infrastructure Monthly Review > 17 October 2015 to 6 November 2015
4.4. Electronic Plumbing Applications
Clients have the option to lodge Plumbing Applications electronically or directly with council in hard-copy.
4.5. Plumbing Inspections
In accordance with the Plumbing and Drainage Act plumbing inspections must be carried out within 48 hours of a plumbing inspection being booked. If Water Services cannot attend the plumbing inspections within the regulated 48 hour period, a plumber can submit a form 3 booking and proceed without an inspection, 1 hour after the 48 hour period. Notifiable Work requires a Form 4 to be lodged with Queensland Building and Construction Commission. Notifiable Work is any work that a plumber or drainer can do without a local government permit or any need for a mandatory inspection.
100% of applications have been received electronically
Data is for the period from 17 October to 6 November 2015
0%
20%
40%
60%
80%
100%
120%
0
5
10
15
20
25
30
35
40
Ele
ctro
nic
Lo
dg
eme
nt
%
Ap
plic
atio
ns
Rec
eiv
ed
Applications received via Electronic Lodgement
% Applications Received via Electronic Lodgement
Inspections decreased from the previous period due to the 3 week reporting period. No Form 3 booking's for the period
Data is for the period from 17 October to 6 November 2015
0
1
2
3
4
5
6
7
0
100
200
300
400
Fo
rm 3
Bo
oki
ng
s
To
tal I
nsp
ect
ion
s
Total Inspections Undertaken Form 4 Audits
Form 3 Inspections Form 3 Bookings
Page 14
Engineering & Commercial Infrastructure Monthly Review > 17 October 2015 to 6 November 2015
4.6. Trade Waste Approvals
The program for undertaking trade waste assessment and licensing of all applicable businesses that discharge trade waste is ongoing. As part of the Trade Waste Assessment process a temporary Trade Waste Approval is put in place while the formal approval process is undertaken. The table below summarises the number of Trade Waste Approvals for the Mackay Region.
4.7. Annual Trade Waste Activity
Annual targets are set for the Trade Waste team with respect to licensing Trade Waste Businesses. The target has been set at 250 new licensed businesses and audits completed by June 2016. The following graph shows the Actual Approvals, Temporary Approvals and Audits achieved and the number of the target remaining.
22
150
42 53
100
0% 20% 40% 60% 80% 100%
Target Trade Waste Approvals & Audits Completed
YTD Audits Remaining Audits YTD Approvals
Temporary Approvals Remaining Approvals
250 combined Approvals and Audits is the target for FY 2015/2016
Data is for the period17 October to 6 November 2015
Total Approved
Businesses
Temporary Approvals In
Place
New Approved Businesses for
the Month
Mackay South 693 47 6
Mackay North 59 4 0
Sarina 56 2 0
Mirani/Marian 28 0 1
Total 836 53 6
6 new businesses were identified for the month
Page 15
Engineering & Commercial Infrastructure Monthly Review > 17 October 2015 to 6 November 2015
4.8. Trade Waste Compliance
Trade Waste compliance testing is undertaken on a routine basis for all trade waste generators that have pre-treatment devices installed. The compliance testing is aimed at ensuring that Trade Waste discharges will not adversely impact on the treatment plant. A summary of the trade waste compliance tests undertaken in each Wastewater Treatment Plant catchment is detailed below
The following graph shows the waste compliance test within limits undertaken in each Wastewater Treatment Plant catchment
Overall 91.59% of tests are within compliance test limites for this period
Data is for the period from 17 October to 6 November 2015
0%
20%
40%
60%
80%
100%
120%
Ap
plic
atio
ns
% Compliance Test within limits South % Compliance Test within limits North
% Compliance Test within limits Sarina % Compliance Test within limits Mirani
Compliance Tests
within Limits Compliance Test
Outside limits
Mackay South 39 7
Mackay North 8 0
Sarina 9 1
Mirani 0 0
Total 56 8
75 Samples collected, 64 analysed
Page 16
Engineering & Commercial Infrastructure Monthly Review > 17 October 2015 to 6 November 2015
4.9. Building Over Adjacent Sewers
Building over Adjacent Sewer applications are lodged where the construction of a structure is proposed within close proximity of a sewer main. The application is assessed in accordance with Councils building over and adjacent to sewer policy. In accordance with the policy, Building Over Sewer Applications are assessed within 20 business days. Future reporting will include performance against turnaround time targets.
4.10. Scientific and Analytical Services
Scientific and Analytical Services provides laboratory analysis in accordance with National Association of Testing Authorities (NATA) Standards to both Mackay Regional Council and external clients. A summary of the laboratory activities are detailed below.
There was 1 BOAS approval issued for the month.
Data is for the period from 17 October to 6 November 2015
0
2
4
Ap
plic
atio
ns
BOAS Applications
02000400060008000
100001200014000160001800020000
0
200
400
600
800
1000
1200
Tes
t P
erfo
rmed
Sam
ple
s
Samples Analysed Test Performed
The lab has increased its workload by 11 % year to date over the same period last year.
Data is available to end of October 2015 only
Page 17
Engineering & Commercial Infrastructure Monthly Review > 17 October 2015 to 6 November 2015
4.11. Community Engagement
This section monitors Water Services engagement on the services provided. The following chart shows the number of media releases, media updates and the number of people that were reached by the Media Releases on Facebook
The following chart shows the number of likes and positive comments, the number of neutral comments and the number of negative comments received on Facebook from Media Releases and Media updates for Water Services
Media Releases include: Sign up to myh2o & save and Water use up six per cent
Data is for period 17 October to 6 November 2015
0
5000
10000
15000
20000
25000
30000
35000
0
1
2
3
4
5
6
7
8
9
10
Rea
ch o
n F
aceb
oo
k (P
eop
le)
Rel
ease
s
Media Releases Media Update Facebook People Reached
There were comments in regard to using water and that Council sporting grounds should not be watered during the day
Data is for period 17 October to 6 November 2015
0
50
100
150
200
250
300
Fac
ebo
ok
Fee
db
ack
Likes Neutral Negative
Page 18
Engineering & Commercial Infrastructure Monthly Review > 17 October 2015 to 6 November 2015
The following chart shows the cumulative number of myh20 registrations for the reporting period
ASSET MANAGEMENT
5.1. Surface Water Raw Water Storage Capacities
Water Services sources water from a combination of surface water and groundwater sources. With the exception of Middle Creek Dam the storage facilities are owned and operated by SunWater. Middle Creek Dam is under Council’s control. The water stored in each of the storages is detailed below.
There were 146 myh2o registrations over the reporting period.
Data is for period 17 October 2015 - 6 November 2015
5000
6000
7000
8000
9000
10000
Aug-15 Sep-15 Oct-15 Nov-15 Dec-15
Nu
mb
er o
f M
yh2o
Reg
istr
atio
ns
myh2o registrations myh20 Target Registrations 2015/2016
2,8
00
3,9
80
6,10
8
1,3
80
491,
400
147
,500
0%
20%
40%
60%
80%
100%
Mirani Weir MarianWeir
DumbletonWeir
MiddleCreek Dam
Peter FaustDam
TeemburraDam
% V
olu
me
Sto
red
Volume Stored
ML
ML
ML
ML M
L
ML
Mirani, Marian and Dumbleton Weirs are full
Data is as at 31 October 2015
Page 19
Engineering & Commercial Infrastructure Monthly Review > 17 October 2015 to 6 November 2015
5.2. Annual Water Consumption vs Allocation by Source
Water Services has a water allocation or water license for each water source. The water allocation and year to date water consumption for each of the water sources is detailed below.
5.3. Water Consumption by Locality
Water Services supplies water to both residential and commercial water clients throughout the Mackay Region. The average water consumption in each of the three major community centres is detailed below. The water consumption is presented as litres per equivalent population per day. This graph provides a summary of water consumption including commercial water use.
4,34611
4230
722
203
6917
1623010
13222
-50% 0% 50% 100%
DumbletonNebo Rd Bores
Plane CreekSarina Bores
Mirani BoreMarian Bores
Marwood BoresBloomsbury BoreProserpine River
Eton BoresBally Keel BoreKoumala Bores
Armstrong Beach BoreFinch Hatton Bore
Gargett BoresMarian Weir
Wat
er V
olu
me
(ML
)
YTD Water Consumed Allocation
Water use has increased across all sites
Data is as at 31 October 2015
6046
23035
15062
270022
59595
100300236390
16000
460
Water consumption is high and is in line with expectations, due to low rainfall
Data is as at end October 2015
0
50
100
150
200
250
300
350
400
0
100
200
300
400
500
600
Rai
nfa
ll (m
m)
Wat
er C
on
sum
pti
on
(l/p
/d)
Rainfall Sarina L/P/DMackay L/P/D Mirani L/P/DTarget Consumption
Page 20
Engineering & Commercial Infrastructure Monthly Review > 17 October 2015 to 6 November 2015
5.4. Wastewater - Mackay North and Mackay South Inflows
The inflow into Wastewater Treatment Plants is impacted by the number of sewage connections and the extent of inflow and infiltration. The monthly inflow into the Mackay North and Mackay South Water Recycling Facilities is detailed below.
5.5. Wastewater – Sarina and Mirani/Marian Inflows
The monthly inflow into the Sarina and Mirani/Marian Wastewater Treatment Plants is detailed below.
Inflows to both plants is low and is in line with expectations, due to low rainfall
Data recorded for month of October 2015 only
0
100
200
300
400
500
600
0
50
100
150
200
250
300
350
400
Mo
nth
ly In
flo
w (
ML
)
Rai
nfa
ll (m
m)
Rainfall Mackay South Mackay North
Page 21
Engineering & Commercial Infrastructure Monthly Review > 17 October 2015 to 6 November 2015
5.6. Sewer Inspections – CCTV Camera
To protect and identify defects in the sewer system Water Services routinely undertakes CCTV inspections of the sewer system. CCTV inspections are undertaken for both developers as part of the process to create a new subdivision and on existing sewer assets as part of the routine sewer inspection program. A summary of the CCTV activity is displayed below measured as meters of sewer inspected.
Less distance was covered this month due to equipment failure and buried manholes. Carried out CCTV discharge SMH Audits and SMH rehabilitation audits with Pole Camera
Data recorded for month of October 2015 only.
0500
100015002000250030003500400045005000
Len
gth
Insp
ect
ed (
m)
CCTV Inspections
Development Maintenance
Page 22
Engineering & Commercial Infrastructure Monthly Review > 17 October 2015 to 6 November 2015
5.7. Projects
Water Services undertakes a range of projects across the water business. Projects take the form of Capital Projects, Planning Studies and investigations. Information was current as at 6 November 2015.
Program Project % Complete
ID Retic ‐ Meter Replacement
Program (15/16 )
20%
Status Budget Time
Preliminary reconaissance visits to properties completed. Meter replacement works have commenced.
30 meters have been replaced.
Construction
Program Project % Complete
ID Digitisation of Telemetry ‐
Water (14/15)
80%
Design/ Procurement
Status Budget Time
Quotes for the Nebo Road WTP conversion to Clear SCADA are currently being evaluated, following
interviews with the Companies that submitted quotes. Quotes for the remaining program of works have
now closed and evaluation will commence shortly.
Program Project % Complete
ID Marian WTP 98%
Time
Though a number of issues have been identified and addressed, Contractor is still investigating the
presence of sub‐surface water on the site. The defect list is being monitored and reviewed regularly and
Contractor is attending to issues identified. As‐Constructed drawings have been generally accepted
though there is some details still to be addressed before final signed copies are provided. Submission of
remaining quality control documentation and As‐Constructed drawings along with there being no critical
defects allowed Practical Completion to be awarded in late October.
Status Budget
Waiting on As‐
Constructed
Information
Page 23
Engineering & Commercial Infrastructure Monthly Review > 17 October 2015 to 6 November 2015
Program Project % Complete
ID Reservoir Chlorination System 98%
Budget Time
O&M manuals have been submitted. As constructed information has been provided ‐ drawings to be
finalised.
Status
Waiting on As‐
Constructed
Information
Program Project % Complete
ID WMT Midge Point Line 98%
Time
O&M manuals have been submitted. As constructed information has been provided ‐ drawings to be
finalised.
Waiting on As‐
Constructed
Information
Status Budget
Program Project Status % Complete
ID WRT ‐ Smart Metering Construction 20% Staff have commenced AMR retrofit installations. Approx. 100 retrofits on existing water meters have
been completed to date.
TimeBudget
Program Project % Complete
ID
Commercial Water Meter
replacement 20%
Time
Construction
Preliminary reconaissance visits to identified properties completed. Meter Replacement works have
commenced with 40 water meters replaced to date.
Status Budget
Program Project % Complete
ID Heaths Road (Valetta Dr‐
Fursden St) ‐ 200 mm link
98%●
As constructed information has been collated and drafting to be completed.
Status Budget Time
Construction
Program Project % Complete
ID Reservoir Corrosion Project 50% ●
Status
14/15 works completed. Scope for 15/16 being prepared based on additional investigations undertaken
on Mt Pleasant Reservoir No. 1 as well as results of the previous high level condition assessment of
Council's reservoir fleet.
Planning
Budget Time
Program Project % Complete
ID WMR Patch Street, Boyle Road
and Cyril McKie Court
98%●
Time
Construction
Construction complete. As Constructed information has been collated, plans to be drafted.
Status Budget
Page 24
Engineering & Commercial Infrastructure Monthly Review > 17 October 2015 to 6 November 2015
Program Project Status % Complete
ID WMR Leslie St Sarina 95% Stage 2 cut‐ins (Installation of flow meter) to be undertaken once long lead materials (pipe specials)
received. This is expected to be complete by end of November.
Construction
Budget Time
Program Project Status % Complete
ID WMR Bruce H'way near Ablett
St (Sarina)
98%
As Constructed information has been collated, plans to be drafted.
TimeBudget
Construction
Program Project Status % Complete
ID WMR West St Sarina 98%
Budget Time
Construction
As Constructed information has been collated, plans to be drafted.
Program Project % Complete
ID WTP ‐ Nebo Rd support
improvements/ upgrades
98%
All four (4) packages of work ‐ fencing, CCTV upgrades, clarifier repairs and replacement of WTP building
roof complete. Waiting on as constructed documentation from Contractor.
Time
Construction
BudgetStatus
Program Project % Complete
ID WMR Renewals (Sandy Creek) 50% Status Budget Time
Construction
Stage 1 is complete. Stage 2: Options for crossing Sandy Creek are still being investigated. A potential
alignment change to bring our water main closer to the bridge was rejected by DTMR. The geotechnical
conditions may impact ability (and cost effectiveness) to use directional drilling while the nature of the
creek banks would create problems for traditional trenching.
Program Project % Complete
ID Chlorine Gas Detection 98% Construction
As constructed information received, plans to be drafted.
Status Budget Time
Page 25
Engineering & Commercial Infrastructure Monthly Review > 17 October 2015 to 6 November 2015
Program Project Status % Complete
ID WMR Downie Avenue 85% Budget Time
Construction
The 450m section of water main from Old Shoal Point Road to Waverley is now complete, including the
installation of new water services. Construction of the section from Waverley St to the Esplanade has
commenced.
Program Project Status % Complete
ID Malcomson St Mackay Bucasia
Rd to Charles Hodge
80%
Budget Time
Design
Works involve new enveloper to be constructed in conjunction with road works. Technical Services
finalising the design ‐ design expected to be finalised in February 2016.
Program Project Status % Complete
ID East Boundary Road Connors Rd
Success St
70%
Budget Time
Design
Additional potholing has been completed to assist with design. The design is still to be revised to include
additional connections identified from hydraulic modelling.
Program Project Status % Complete
ID Investigator St Join the two
ends of Investigator St
100%
Budget Time
Design
Roads driven project. Design complete.
Program Project Status % Complete
ID WMR Waverley St, Bucasia
(Fisher St to Williams Ave)
0%
Budget Time
Construction
Originally scheduled for 16/17, these works have been brought forward to match the Roads capital
program. The design has been completed and construction is anticipated to commence in late
November.
Program Project Status % Complete
ID Blacks Beach Road (Florence to
Hancock)
0%
Budget Time
Construction
Timing of construction still to be confirmed.
Program Project Status % Complete
ID Water Balance Implementation ‐
Mackay & Sarina Level 1 and
Level 2 Flow Meters
5%
Budget Time
Design
Preliminary reconaissance visits to confirm scope of works in progress.
Program Project Status % Complete
ID Mt Oscar HLZ Augmentation
Servicing Mt Pleasant
15%
Budget Time
Design
Design investigation works continuing.
Program Project Status % Complete
ID Mt Bassett Drive 20% Budget Time
Design
Concept design has been completed for the majority of the alignment though options for crossing of
Harbour Rd are still to be considered
Program Project Status % Complete
ID WMR East Gordon St 55% Budget Time
Planning
Planning of renewal options in progress, before detailed scope can be finalised.
Page 26
Engineering & Commercial Infrastructure Monthly Review > 17 October 2015 to 6 November 2015
Program Project Status % Complete
ID Cape Hillsborough 80% Budget Time
Planning
Planning of renewal options in progress, before detailed scope can be finalised. Site investigations
undertaken to ascertain extent of problematic water main.
Program Project Status % Complete
ID Conditions Assessments 95% Budget Time
Planning
Detailed scope for condition assessments being finalised.
Program Project Status % Complete
ID Water Services Replacements
and Repairs
35%
Budget Time
Construction
Infrastructure Delivery crew continue to replace identified water services with works for 30 properties
completed to date.
Program Project Status % Complete
ID Water Pump Stations ‐
Renewals Program
85%
Investigations under way to deternine works required on lifting gantries. Condition /compliance report
expected within the next 2 weeks for review.
Budget Time
Planning
Program Project % Complete
ID Sewer Structural Lining Program 25% Construction
CCTV works in progress. Relining Works tender package under review due to recent case history before reverting
back to out to tender process.
Status TimeBudget
Program Project % Complete
ID Digitisation of Telemetry ‐
Sewage
80%
Status Budget Time
Quotations for 15/16 program of works have been received and are currently being evaluated.
Procurement
Program Project % Complete
ID Base Hospital SPS Replacement 100%
TimeStatus Budget
Construction
Construction of new sewage pump station completed. As‐constructed plans are submitted and finalised.
Page 27
Engineering & Commercial Infrastructure Monthly Review > 17 October 2015 to 6 November 2015
Program Project % Complete
ID SPS Wattle Street Sewerage
Pump Station
98%
The contractor has completed construction works of the sewage pump station and rising main upgrade works. As‐
constructed information has been received and plans to be drafted.
Budget Time
Construction
Status
Program Project % Complete
ID SPS Heaths Road No.1 Sewerage
Pump Station
98%
Status Budget Time
Construction
The contractor has completed construction works of the sewage pump station upgrade works. As‐constructed
information has been received and plans to be drafted.
Program Project % Complete
ID SPS Refurbishment/ Renewals
(Magpie Street)
98%
The contractor has completed construction works of the sewage pump station upgrade works. As‐constructed
information has been received and plans to be drafted.
Time
Construction
Status Budget
Program Project % Complete
ID SPS Hicks Road Sewerage Pump
Station
98%
Status Budget
Construction
Time
The contractor has completed construction works of the sewage pump station upgrade works. As‐constructed
information has been received and plans to be drafted.
Program Project % Complete
ID Symons Farm SPS Upgrade 35%
Time
Design
A report on Symons Farm SPS to Prawn Farm SPS SRM and trunk gravity sewer concept alignment is under review.
Due to issues regarding TMR approval of MRC preferred corridor in Mackay‐Eimeo Road this project is being
considered for a scope change, but may revert back to a prior strategic planning review of identified options.
BudgetStatus
Program Project % Complete
ID Trunk gravity sewer main from
McCreadys Creek SPS to Symons
Farm SPS
10%
Status Budget Time
Procurement
Tender documentation is 95% complete. Tender process for construction to commence at end of November.
Page 28
Engineering & Commercial Infrastructure Monthly Review > 17 October 2015 to 6 November 2015
Program Project % Complete
ID Pump Replacement SPS Shoal
Point Road No.1
100%
Status Budget Time
Procurement
New pumps have been received. Installation of pumps will be done together with wet well relining works
Program Project % Complete
ID Manhole Inspections and
Repairs work
20%
Status Budget Time
Construction
Networks crews continue with Manhole inspection and repair work. Approximately 20 Manhole's have been
repaired and 200 Manhole's Inspected.
Program Project % Complete
ID Switchboards Replacement 20% Status Budget Time
Design
Finalising stakeholder requirements and preliminary design information. Ergon applications have been
completed and submitted. Delivery will be packaged together with vent pole replacements, access improvement
and wet well rehabilitation. Development of site layout plans and detailed design to commence in November.
Program Project % Complete
ID Vent Poles Replacement 5% Status Budget Time
Design
Planning investigation scope of works finalised and project initiation commenced. Delivery will be packaged
together with switchboard replacements, access improvement and wet well rehabilitation. Site inspections and
survey data collection, and development of site layout plans to commence in November
Program Project % Complete
ID Access Improvements and
Ownership
50%
Status Budget Time
Design
Finalising site surveys and commencing detailed designs. Delivery will be packaged together with switchboard
and vent pole replacements and wet well rehabilitation.
Program Project % Complete
ID Wet well Rehabilitation 5% Status Budget Time
Design
Planning investigation scope of works finalised and project initiation commenced. Delivery will be packaged
together with switchboard and vent pole replacements and access improvement. Site inspections and survey data
collection, and development of site layout plans to commence in November
Program Project % Complete
ID Decommisioning of Brewers Rd
STP Sarina
20%
Status Budget Time
Construction
Pumping of Stagnant water in the open tanks completed. Leachate from the Digesters has been drawn down and
passed throught the drying beds. Concrete panels have been cut and removed from each digester to allow access
by excavator to remove sludge. Council crew preparing to clean and disinfect the digesters prior to demolition.
Program Project % Complete
ID Mirani Sewerage Treatment
Stage 1 (STP Mirani Growth
Upgrade)
90%
Status Budget Time
Planning
Details are still being confirmed regarding the latest option of building an MRC owned dam on a section of the
farm adjacent to the Mirani Wastewater Recycling Facility. Once these have been finalised, a multi‐criteria
analysis will be completed to compare this option with the original plan to utilise a dam owned by a nearby
farmer.
Page 29
Engineering & Commercial Infrastructure Monthly Review > 17 October 2015 to 6 November 2015
REGULATORY COMPLIANCE
6.1. Drinking Water Compliance
Safe Water supplies are provided in accordance with the requirements of the Water Supply Safety and Reliability Act and are measured against the Australian Drinking Water Quality Guidelines. Drinking Water samples are taken at the outlet of Water Treatment Plants and within the reticulation network. A summary of the performance is detailed below.
No health based exceedences.
This data is reported 1 month in arrears and due to regulatory reporting requirements is reported by calendar month.
60
65
70
75
80
85
90
95
100
0102030405060708090
100110120130140150160
Co
mp
lian
ce (
%)
Tes
ts C
on
du
cted
Health Parameter Test Results
Non Compliant Health Parameter Tests Drinking Water Test Completed
% Compliance Target
Bloomsbury, Eton and Koumala exceeded the recommended hardness of 200 mg/L CaCO3 and Gargett had a pH below the recommended level of 6.5
This data is reported 1 month in arrears and due to regulatory reporting requirements is reported by calendar month..
0102030405060708090
100110120130140150160170180
Tes
ts C
on
du
cted
Aesthetic Parameter Test Results
Drinking Water Test Completed Non-Complaint Aesthetic Parameter Tests
Page 30
Engineering & Commercial Infrastructure Monthly Review > 17 October 2015 to 6 November 2015
6.2. Wastewater Compliance
The discharges from wastewater treatment facilities are regulated by Development Approvals issued by the Department of Environment and Resource Management. The licence requirements differ based on the time the Development Approval was issued and the receiving environment associated with any discharges.
6.3. Backflow Testing
Backflow devices are installed on water services where there is a risk that water could return from a private property back into the Water Reticulation network. The requirement for backflow devices is regulated in accordance with the Standard Plumbing and Drainage Regulation.
All Wastewater tests over this period were compliant
Results are to end of October 2015 due to statutory reporting requirements.
0
10
20
Tes
ts C
on
du
cted
Samples Tested Non Compliant tests
Wastewater Test Results
Numbers of devices tested has decreased from last month due to a 3 week reporting period
Data is for 17 October to 6 November 2015
0
10
20
30
40
50
60
70
80
90
100
0
20
40
60
80
100
120
Tes
ted
by
Co
un
cil
No
. of
Dev
ices
Reg
iste
red
/Can
celle
d
Monthly Devices Registered Devices Cancelled Tested By Council
Page 31
Engineering & Commercial Infrastructure Monthly Review > 17 October 2015 to 6 November 2015
Another mail out of 2nd test reminders were sent last week.
Data is for period 17 October to 6 November 2015
0
20
40
60
80
100
120
140
160
180
200D
evic
es R
egis
tere
d
Commercial Devices Overdue Domestic Devices Overdue
Overdue Commercial & Domestic Backflow Device Breakdown
1 Waste Services Monthly Review > March 2013
Engineering and Commercial Infrastructure -
Waste Services
Monthly Review -
17 October 2015 to 06 November 2015
Page 2
Engineering & Commercial Infrastructure Monthly Review > 17 October 2015 to 06 November 2015
Overview……………………………………………………………………………....………………3
1.0 Finance........................................................................................................................4
1.1 Community Service Obligations – Fee Waivers 1.2 Waste Operating Revenue Less Expenditure 1.3 Accrued Waste Operating Revenue Less Expenditure 1.4 Capital Expenditure 2.0 Client Service..............................................................................................................6 2.1 Client Requests 2.2 Number of Bin Requests Actioned by Bin Contractors 2.3 Contractor Service Delivery Performance 2.4 Education
2.4.1 Materials Recovery Facility Tours 2.4.2 Waste Education Program in Schools
2.5 Dump Vouchers 2.6 Community Engagement 3.0 Asset Management...................................................................................................10
3.1 Hogan’s Pocket Landfill Waste Disposal Tonnages 3.2 Landfill Gas 3.3 Greenwaste Management 3.4 Projects 3.4.1 Hogan's Pocket Cell 3 Development 3.4.2 Waste Services Contract Development 3.5 Materials Recovery Facility Operations 4.0 Regulatory/Compliance..............................................................................................14
4.1 Surface Water Discharge Management 4.2 Waste Facility Audits
Page 3
Engineering & Commercial Infrastructure Monthly Review > 17 October 2015 to 06 November 2015
Overview This report is for Waste Services activities for October/November 2015. Please note that references to the October/November reporting period covers the period 17 October to 6 November 2015. Significant items in this period include:
The Materials Recovery Facility (MRF) is recycling 90% of the material that is received
Waste to landfill tonnes continues to decline with the lowest October tonnage for four years being recording
The performance of the Waste and Recycling Bin Collection Contractor continues to improve with only 3.25% of requests exceeding the SLA of three days
Acting Director Engineering & Commercial Infrastructure
Page 4
Engineering & Commercial Infrastructure Monthly Review > 17 October 2015 to 06 November 2015
FINANCE
1.1 Community Service Obligations – Fee Waivers
Not for Profit Organisations – Total Waste Disposals 17 October 2015 to 06 November 2015.
YTD actuals remain below YTD budget.
Data is for 2015/2016 Financial Year, as at 06 November, 2015
$15,519.66
$60,234
$- $10,000 $20,000 $30,000 $40,000 $50,000 $60,000 $70,000
$ (inclGST)
Budget for 2015/2016 YTD Expenditure 2015/2016
1.2 Waste Operating Revenue Less Expenditure
The following chart shows the actual budget and forecast Earnings before Interest, Taxes and Amortization (EBITA) based on cash accounting for the 2015/2016 financial year. The saw tooth nature of the graph is reflective of the timing of waste revenue due.
‐
2,000,000
4,000,000
6,000,000
8,000,000
10,000,000
12,000,000
14,000,000
16,000,000$
Budget ‐ Waste Actuals ‐ Waste Projected Actuals ‐ Waste
YTD Actuals exceed YTD budget by $1.04M. However, revenue is under budget by $480K -mainly as a result of gate fees $593K less than budget due to a drop in tonnages waste processed. Expenditure is under budget by $1.5M mainly due to contract invoices not yet received - $1.08M. Saving of $160k in the Hogans Pocket contract as a result of the drop in tonnage waste processed.Financial data is for October 2015..
Page 5
Engineering & Commercial Infrastructure Monthly Review > 17 October 2015 to 06 November 2015
1.3 Accrued Waste Operating Revenue Less Expenditure
The following chart shows the estimation of the accrued revenue less expenditure. The capital revenue has been excluded.
‐
1,000,000
2,000,000
3,000,000
4,000,000
5,000,000
6,000,000
7,000,000
8,000,000
9,000,000
10,000,000$
Budget ‐ Waste Accrual Actual ‐ Waste Accrual Proj. Accrual Actuals ‐ Waste
On an accrual basis YTD actuals exceed budget by $227.6K. It is projected that based on the trend over the first quarter, Waste services will exceed annual budget by $505.5K
Financial data is up to September'15.
1.4 Capital Expenditure
The following graph provides an overview of the capital expenditure and monitors forecast expenditure against actual expenditure.
‐
1,000,000
2,000,000
3,000,000
4,000,000
5,000,000
6,000,000
7,000,000
YTD Actual + Committals Capital Expenditure Budget Cash Flow Capital
Forecast Cash Flow Capital YTD Actual Capital Expenditure
Forecast exceeds budget by $1.38M mainly due to funds not being carried over from 2014/2015.
Financial data is up to October' 15.
Page 6
Engineering & Commercial Infrastructure Monthly Review > 17 October 2015 to 06 November 2015
CLIENT SERVICE
2.1 Client Requests
The following graph shows the number of Staff Requests by Type for the three-week period 17 October 2015 to 06 November 2015.
Multiple bins requests in progress are 731 with 135 added this period. Multiple bins are flagged through regular bin audits and contractor reports. Waste Services are working to identify the validity of these reports and realise savings to council through the retrieval of multiple bins or the inclusion of additional services on rates notices where appropriate.
Data is for period 17 October 2015 to 06 November 2015
0
20
40
60
80
100
120
140
160
To
tal C
lien
t R
equ
ests
2.2 Number of Bin Requests Actioned by Bin Contractors
The following graph shows the number of bin requests actioned by Bin Contractors for the three-week period 17 October 2015 to 06 November 2015
Although a shorter reporting period, new services have hit a low of 21. A new request type for Bulk Bins has been created to support service delivery of that service type
Data is for period 17 October 2015 to 06 November 2015
0
20
40
60
80
100
120
140
160
Bin
Req
ues
ts A
ctio
ned
Page 7
Engineering & Commercial Infrastructure Monthly Review > 17 October 2015 to 06 November 2015
2.3 Contractor Service Delivery Performance The following graph identifies the total number of requests for the reporting period. The columns are illustrated to demonstrate the number of requests that were met the contractor according to the Service Level Agreement (SLA) target of 3 days or as a breach of the SLA.
Only 3.25% of requests exceeded the SLA of 3 days.
Data is for period 17 October 2015 to 06 November 2015
0
100
200
300
400
500
600
700
800
900
1000
1100
No
of
Req
ues
ts
Bin Contractor within SLA Bin Contractor Breach The following graph illustrates the completion time for the service delivery requests versus the target day of three days or less.
Contractor KPI target for request completion is 3 days.
Data is for period 17 October 2015 to 06 November 2015
154
56 50
9
2
11
5
25
125
625
Lo
g. o
f N
o. o
f R
equ
ests
Co
mp
lete
d
Service Delivery Requests Completed Target Days
Page 8
Engineering & Commercial Infrastructure Monthly Review > 17 October 2015 to 06 November 2015
The following chart illustrates service reliability through missed general waste and recycle waste services.
Missed collection services levels remain low.
Data is for period 17 October 2015 to 06 November 2015
0
1
2
3
4
5
6
7
8
9
10
Week 1 Week 2 Week 3
No
of
Bin
s M
isse
d f
or
Co
llect
ion
Missed General Waste Missed Recycle
2.4 Education
2.4.1 Materials Recovery Facility tours
Blue River Family Daycare Group.
2.4.2 Waste Education Program in Schools
Recycling and worm farming education was given to three groups of pre-preps students at Mackay Christian College.
Recycling education was given to two groups of children at Hot Tots West Mackay. Recycling education talk was given at Resthaven Aged Care Home North Mackay.
2.5 Dump Vouchers Voucher Season Issued Used %
‘15’ (valid to 31 March 2015) 145,344 34,747 23.9%
‘15A’(valid to 30 Sept 2015) 146,313 32,733 22.4%
‘15B’(valid to 31 March 2016) 146,790 12,358* 8.4%
Total $ value of vouchers presented to date: 2014/2015 Financial Year $419,2272015/2016 Financial Year (to 06.11.2015) $185,769 * To 6 November 2015
Page 9
Engineering & Commercial Infrastructure Monthly Review > 17 October 2015 to 06 November 2015
The graph reflects 13periods to allow comparison with the same period last year.
Data is for 17 October 2015 to 06 November 2015 i.e. 3 week period only.
0
1000
2000
3000
4000
5000
6000
7000
8000
9000V
ou
cher
s P
rese
nte
d f
or
Per
iod
Green Waste Trans. Using Vouchers General Waste Trans. Using Vouchers
2.6 Community Engagement This section monitors Waste Services engagement on the service provided. The following chart shows the number of media releases, media updates and the number of people reached by media releases on Facebook.
One Press Release during the period:* "Bring the family and check out council's state-of-the-art recycling facility".
Media Update during the period:* "Recycling trial wants farm bags
884 people reached via Facebook.
Data is for period 17 October 2015 to 06 November 2015
0
2000
4000
6000
8000
10000
12000
14000
16000
18000
20000
0
1
2
3
4
5
6
7
Rea
ch o
n F
aceb
oo
k (P
eop
le)
Rel
ease
s
Media Releases Media Update Facebook People Reached
Page 10
Engineering & Commercial Infrastructure Monthly Review > 17 October 2015 to 06 November 2015
The following chart shows the number of likes and positive comments, the number of neutral comments and the number of negative comments received on Facebook from media releases and media updates for Waste services.
There were no neutral or negative comments over this period. 4 'Likes" were recorded on Facebook.
Data is for period 17 October 2015 to 06 November 2015
0
20
40
60
80
100
120
140
160
180
Likes Neutral Negative
ASSET MANAGEMENT 3.1 Hogan’s Pocket Landfill Waste Disposal Tonnages
The following chart represents the monthly tonnes disposed of at Hogan's Pocket Landfill. This chart shows that tonnes this financial year have been down when compared with previous financial years.
6000
7000
8000
9000
10000
11000
12000
Tonnes Waste Received
12/13 13/14 14/15 15/16
Waste to landfill tonnes continue to decrease with the recording of the lowest October tonnage for four years.
Data is for period 01 July 2012 to 31 October 2015
Page 11
Engineering & Commercial Infrastructure Monthly Review > 17 October 2015 to 06 November 2015
3.2 Landfill Gas
The following chart depicts the monthly tonnes of CO2-e destroyed.
0
500
1000
1500
2000
2500
3000
Tonnes CO2
14/15 15/16
Tonnes of CO2-e destroyed for October remianed steady
Data is for period 01 July 2014 to 31 October 2015
3.3 Greenwaste Management
The following graph illustrates the tonnage rates for greenwaste processed for the period, the cumulative tonnes of greenwaste processed for the year to date and the tonnes of greenwaste projected to be processed linearly. The production of processed greenwaste remains highly variable and the projected totals are a guide only.
0
1000
2000
3000
4000
5000
6000
7000
8000
9000
10000
Tonnes of Greenwaste Processed
Month Cumulative Total Projected Tonnes
The production of greenwaste remains variable.
Data is for October 2015
Page 12
Engineering & Commercial Infrastructure Monthly Review > 17 October 2015 to 06 November 2015
3.4 Projects
Waste Services undertakes a range of projects across the business. Projects take the form of capital projects, planning, research and investigations.
3.4.1 Hogan’s Pocket Cell 3 Development
Program Project % Complete
WS Cell 3 Construction 50%
Status Budget Time
ConstructionThe project continues to progress well with the improved subgrade and groundwater relief drains almost completed. Both clay and geosynthetic materials deliveries continue. Some wet weather has slightly delayed works, however the project remains on budget and is still expected to be completed early January 2016.
3.4.2 Waste Services Contract Development
Program Project % Complete
WS Tenders 70% Status Budget Time
In progress
Finalised Tenders: o MRC 2014-066 Waste and Recycling Collection Serviceso MRC 2014-072 Recyclables Processing Services o MRC 2015-020 Transfer Stations Site Control Serviceso MRC 2015-026 Resource Recovery Facility Services
Evaluation phase:o MRC 2014-079 Expression of Interest Development of Construction and Demolition Waste Facilities o MRC 2016-002 RORO Waste Haulage Services The following tenders are being drafted for future release:o Landfill Operations and Haulageo Paget Transfer Station Operations and Managemento Green Waste Processing Services
Both the RORO (Roll On - Roll Off) bins and the Construction and Demolition Waste Recycling Facilities tenders have closed and evaluation for these two tenders has commenced. Tender reports are planned to be provided to Council in the second quarter of the Financial Year. During the reporting period work continued on the development of the Landfill operations and haulage tender along with the Paget transfer station operations management tender with a focus on the revision of the Site Based Management Plan (SBMP). The release of both these tenders has moved to November due to additional work that is being required to be done to manage the risks of these proposed contracts which have evolved from the current agreements which were drafted over ten years ago. The Green waste processing services tender is scheduled to be released in December 2015.
Page 13
Engineering & Commercial Infrastructure Monthly Review > 17 October 2015 to 06 November 2015
3.5 Material Recovery Facility Operations
The following graph identifies tonnages inbound and product to market for the Material Recovery Facility.
Types of product output will vary each reporting period. No glass fines went to landfill during October 2015.
0
200
400
600
800
1000
1200
1400
1600
Inbound tonnages
Product 2015/2016
Waste 2015/2016
Glass Fines to Landfill 2015/2016
To
nn
es
MRF operations achieved zero glass fines to landfill for October 2015. 273 tonnes of crushed glass were produced during the month.90% of inbound tonnage was recycled.
Data is for October 2015
The following graph shows tonnages for inbound product received from domestic collections within the Mackay Region, Commercial collections and Isaac Regional Council.
0
200
400
600
800
1000
1200
1400
1600
Commercial Inbound
Isaac Regional Council Comingled Inbound
MRC Commingled Inbound
Tonnes
Tonnages are expected to increase over the summerperiod in line with the seasonal trend.Whitsunday Shire Councils recycled waste is received as part of a commercial load and counted within that total.
Data is for October 2015
Page 14
Engineering & Commercial Infrastructure Monthly Review > 17 October 2015 to 06 November 2015
REGULATORY COMPLIANCE
4.1 Surface Water Discharge Management
No matters to report.
4.2 Waste Facility Audits
Internal audits of MRC Waste Facilities have been ongoing. No significant issues to report for this reporting period.