U.S. EPA Chesapeake Bay Program Office June 1, 2012 Ensuring Progress: Oversight of Watershed Implementation Plans and 2-Year Milestones

Ensuring Progress: Oversight of Watershed Implementation Plans and 2-Year Milestones

  • Upload
    geoff

  • View
    39

  • Download
    0

Embed Size (px)

DESCRIPTION

Ensuring Progress: Oversight of Watershed Implementation Plans and 2-Year Milestones. U.S. EPA Chesapeake Bay Program Office June 1, 2012. Chesapeake Bay TMDL Based on 7 Watershed Implementation Plans. Taking It to the Streets : Phase II WIPs. Increase awareness - PowerPoint PPT Presentation

Citation preview

Page 1: Ensuring Progress: Oversight of Watershed Implementation Plans and 2-Year Milestones

U.S. EPA Chesapeake Bay Program Office

June 1, 2012

Ensuring Progress:Oversight of Watershed Implementation Plans and 2-

Year Milestones

Page 2: Ensuring Progress: Oversight of Watershed Implementation Plans and 2-Year Milestones

2

Chesapeake Bay TMDL Based on 7 Watershed Implementation Plans

Page 3: Ensuring Progress: Oversight of Watershed Implementation Plans and 2-Year Milestones

3

Taking It to the Streets: Phase II WIPs

• Increase awareness

• Modify strategies for greater benefits to communities

• Opportunity to strengthen long-term strategies

Page 4: Ensuring Progress: Oversight of Watershed Implementation Plans and 2-Year Milestones

150

175

200

225

250

275

2009 2011 2013 2015 2017 2019 2021 2023 2025

Del

iver

ed N

Loa

ds (m

il lb

s/yr

)EPA Will Assess ifMilestoneReductions on Schedule

Assumes Upfront Program-Building and Future ReductionsAssumes Constant Reduction Over TimeAssumes Upfront Low-Hanging Fruit and More Difficult Future Reductions

Interim Target: 60% by

2017

Two-Year Milestones

Page 5: Ensuring Progress: Oversight of Watershed Implementation Plans and 2-Year Milestones

5

Select Highlights

• Delaware: Commitment to address CAFO permit backlog. Stormwater: provided information on compliance monitoring and new regulations.

• District of Columbia: Significant engagement with federal agencies

• Maryland: Recent legislation to increase funding for POTWs, stormwater, and septic systems. Schedule to reissue MS4 permits with provisions to implement WIP strategies.

Page 6: Ensuring Progress: Oversight of Watershed Implementation Plans and 2-Year Milestones

6

Select Highlights

• Pennsylvania: Increasing compliance with existing agricultural programs. Guidance and training on Chesapeake Bay Pollutant Reduction Plans.

• Virginia: Detailed strategy for Resource Management Program. Commitment to finalize agreement in response to stormwater assessment.

• West Virginia: Agricultural strategies based on farmer feedback. Schedule for reissuing Construction General Permit.

Page 7: Ensuring Progress: Oversight of Watershed Implementation Plans and 2-Year Milestones

7

EPA Oversight of WIPs• EPA will monitor progress in all states and source sectors. (ongoing

oversight)• · Some sectors will require closer monitoring by EPA

(enhanced oversight):• o PA and WV agriculture strategies• o PA trading programo VA stormwater program• o The WIPs do not fully explain how these strategies will meet

pollution reduction goals.

• PA’s stormwater program will require detailed scrutiny (backstop action) to address shortcomings, and EPA is prepared to take steps to ensure progress continues in this sector.

Page 8: Ensuring Progress: Oversight of Watershed Implementation Plans and 2-Year Milestones

8

Shifting Focus from Planning to Implementation

• Turning plans into on the ground actions

• All practices in place by 2025

• 60% by 2017

• Near term actions to support long-term success

Page 9: Ensuring Progress: Oversight of Watershed Implementation Plans and 2-Year Milestones

9

Overseeing Progress• Interim and final reports to

Executive Council on milestone progress

• Quarterly oversight discussions

• Goals:No surprisesWork together to address

issues early

Page 10: Ensuring Progress: Oversight of Watershed Implementation Plans and 2-Year Milestones

10

Informing Ongoing EPA Activities

• Aligning grant work plans with WIP and milestone priorities

• Transparent tracking tools

• Permit reviews• Program assessments

Page 11: Ensuring Progress: Oversight of Watershed Implementation Plans and 2-Year Milestones

11

So We Can Have Less of This…

Page 12: Ensuring Progress: Oversight of Watershed Implementation Plans and 2-Year Milestones

And More of This…

Page 13: Ensuring Progress: Oversight of Watershed Implementation Plans and 2-Year Milestones

Jim EdwardDeputy Director

U.S. EPA Chesapeake Bay [email protected]

www.epa.gov/chesapeakebaytmdlhttp://stat.chesapeakebay.net/