24
Patha Bapushetty Cluster Environment Management Plan Team Labs and Consultants 11 ENVIRONMENT MANAGEMENT PLAN 1.0 Introduction This report discusses the management plan for mitigation/abatement of adverse environmental impacts and enhancement of beneficial impacts due to mining. The EMP has been designed within the framework of various legislative and regulatory requirements on environmental and socioeconomic aspects. Sri Patha Bapushetty proposes to conduct opencast manual method quarrying for Building Stone and Road metal and building stone extraction of 214824 m 3 /annum in an area of 8.0 ha at Survey No. 147, Rachapally Village, Dharmaram Mandal, Peddapally District, Telangana State. In principle of application for grant of quarry lease notice issued by The Deputy Director of Mines and Geology, Warangal vide notice no. 7586/Q2/2015 dated 21.01.2016. Quarry Plan was scrutinized by the Deputy Director of Mines and Geology, Warangal vide letter no. 5468/QP3/KNR/16 dated 03.12.2016. Capital cost of the proposed quarrying activity is Rs. 60 Lakhs. Sri Patha Bapushetty is conscious of its environmental responsibility towards the society in minimizing the pollution load due to this project and accordingly decided to carry out the Environment Management Plan. The objective of preparing environment management plan is to delineate effective measures to control and to mitigate the environmental pollution. This report presents the environment management plan, detailing the environmentally sound technology and the measures needed to contain and mitigate the anticipated environmental impacts due to the project. 1.1 Granite and its uses Granite is a very common intrusive igneous rock. It is lightcolored granulose plutonic rock composed of the minerals feldspar, quartz and biotite & muscovite mica. These minerals make granite white, pink, or light grey. Granite also contains small amounts of dark brown, darkgreen, or black minerals, such as hornblende and biotite mica. Granite is very hard and dense. It can be readily cut into very large blocks and it takes an extremely high polish. The name granite is derived from the Latin word granum, which means grain, an obvious reference to the granular texture of granite. The average density of granite is between 2.65 and 2.75 g/cm 3 , with a compressive strength of above 200 Mega Pascal (MPa).

ENVIRONMENT MANAGEMENT PLAN 1.0 …environmentclearance.nic.in/writereaddata/FormB/EC/EIA...Patha Bapushetty Cluster Environment Management Plan Team Labs and Consultants . . . ‐

Embed Size (px)

Citation preview

Page 1: ENVIRONMENT MANAGEMENT PLAN 1.0 …environmentclearance.nic.in/writereaddata/FormB/EC/EIA...Patha Bapushetty Cluster Environment Management Plan Team Labs and Consultants . . . ‐

Patha Bapushetty    Cluster Environment Management Plan 

Team Labs and Consultants 1‐1 

 ENVIRONMENT MANAGEMENT PLAN 

1.0 Introduction 

This  report  discusses  the  management  plan  for  mitigation/abatement  of  adverse 

environmental  impacts and enhancement of beneficial  impacts due to mining. The EMP has 

been designed within  the  framework of various  legislative and  regulatory  requirements on 

environmental and socio‐economic aspects. 

Sri Patha Bapushetty proposes  to conduct opencast manual method quarrying  for Building 

Stone and Road metal and building stone extraction of 214824 m3/annum in an area of 8.0 ha 

at  Survey No.  147,  Rachapally  Village, Dharmaram Mandal,  Peddapally District,  Telangana 

State.  In  principle  of  application  for  grant  of  quarry  lease  notice  issued  by  The  Deputy 

Director of Mines and Geology, Warangal vide notice no. 7586/Q2/2015 dated 21.01.2016. 

Quarry Plan was  scrutinized by  the Deputy Director of Mines  and Geology, Warangal  vide 

letter  no.  5468/QP3/KNR/16  dated  03.12.2016.  Capital  cost  of  the  proposed  quarrying 

activity is Rs. 60 Lakhs.  

Sri Patha Bapushetty  is conscious of  its environmental responsibility towards the society  in 

minimizing  the pollution  load due  to  this project and accordingly decided  to  carry out  the 

Environment Management Plan. The objective of preparing environment management plan is 

to delineate effective measures to control and to mitigate the environmental pollution. This 

report  presents  the  environment management  plan,  detailing  the  environmentally  sound 

technology and the measures needed to contain and mitigate the anticipated environmental 

impacts due to the project. 

1.1 Granite and its uses 

Granite  is a very common  intrusive  igneous  rock.  It  is  light‐colored granulose plutonic  rock 

composed  of  the minerals  feldspar,  quartz  and  biotite & muscovite mica.  These minerals 

make granite white, pink, or  light grey. Granite also contains small amounts of dark brown, 

dark‐green, or black minerals, such as hornblende and biotite mica. Granite is very hard and 

dense. It can be readily cut  into very  large blocks and  it takes an extremely high polish. The 

name  granite  is  derived  from  the  Latin  word  granum,  which  means  grain,  an  obvious 

reference  to  the  granular  texture  of  granite.  The  average density of  granite  is  between 

2.65 and 2.75 g/cm3, with a compressive strength of above 200 Mega Pascal (MPa).  

Page 2: ENVIRONMENT MANAGEMENT PLAN 1.0 …environmentclearance.nic.in/writereaddata/FormB/EC/EIA...Patha Bapushetty Cluster Environment Management Plan Team Labs and Consultants . . . ‐

Patha Bapushetty    Cluster Environment Management Plan 

Team Labs and Consultants 1‐2 

Uses 

Granite has been extensively used as  a dimension  stone and  as  flooring  tiles  in public  and 

commercial buildings and monuments.  With  increasing amounts of acid rain in parts of the 

world, granite has begun to supplant marble as a monument material, since it is much more 

durable.  Engineers have  traditionally  used  polished  granite  surfaces  to  establish  a plane of 

reference,  since  they  are  relatively  impervious  and  inflexible.  Granite  tables  are  used 

extensively  as  a  base  for  optical  instruments  due  to  granite's  rigidity,  high  dimensional 

stability  and  excellent  vibration  characteristics.  Rough‐cut  and  polished  granite  is  used  in 

buildings, bridges, paving, monuments and many other exterior projects.  Indoors, polished 

granite  slabs  and  tiles  are  used  in  countertops,  tile  floors,  stair  treads  and many  other 

practical  and  decorative  features.  Presently,  cut  and  polished  granite  slabs  of  20  mm 

thickness  are  preferred  for  flooring,  while  tiles  of  10  or  12  mm  thickness  are  used  for 

cladding.  

1.2 Mining Method  

The  road metal and building stone  in  the quarry  lease area  is exposed on  the surface with 

sheet.  Hence,  it  is  proposed  to  quarry  the  sheet  by  opencast  and  manual  method  by 

developing 6m height with single slice of 1.5m bench width with shallow drilling and blasting. 

The development of benches in the sheet rock will be maintained @60Osafety slopes.  

1.3 Mine Location 

Sri Patha Bapushetty propose to conduct semi mechanized open cast quarrying for maximum 

granite production of 214824 m3/annum. The quarry lease area of 8.0 ha at Survey No. 147, 

Rachapally  Village,  Dharmaram Mandal,  Peddapally  District,  Telangana  State.  The  quarry 

lease area  falls  in  the Survey of  India  topo  sheet no. 56 N/6 with  co‐ordinates of  Latitude  

18°42'43.93"Nand Longitude  79°19'39.65"Ewith an elevation of 252 m. The nearest village is 

Rachapally located at a distance of 1.1 km from the quarry lease area in SW direction. Putnur 

to Dongaturti road passing at a distance of 1.0 km from the QL area in west direction. Nearest 

Railway  station  and nearest  town Raghavapuram RS  located  at  a distance of 9.5  km  in  SE 

direction.  District  Head  Quarters  is  Peddapalli  at  a  distance  of  11.9  km  SE  direction. 

Khanampalli RF  located at a distance of 2.3 km  in NW direction, Maredpalli RF  located at a 

distance  of  7.6  km  in  NW  direction,  Putnur  RF  located  at  a  distance  of  4.4  km  in  North 

direction.  Seasonal  Bandala  Vagu  at  a  distance  of  3.7  km  in  NE  direction.  There  is  no 

Page 3: ENVIRONMENT MANAGEMENT PLAN 1.0 …environmentclearance.nic.in/writereaddata/FormB/EC/EIA...Patha Bapushetty Cluster Environment Management Plan Team Labs and Consultants . . . ‐

Patha Bapushetty    Cluster Environment Management Plan 

Team Labs and Consultants 1‐3 

national/state boundary, national park, wildlife/bird  sanctuary  and  critically polluted  areas 

within 10 km  radius  from  the quarry  lease area. Quarry  lease  location map  is presented  in 

figure 1.1. Details of the quarry lease area are presented in table 1.1. 

Table 1.1 Details of the Lease area 

State and District  Mandal  Village  Sy. No./ Plot No. 

Area in hectares 

Ownership of occupancy 

Telangana and Peddapalli  Dharmaram Rachapalli  147  8.0  Govt. Land 

 1.4 Land use pattern of the lease area 

The area is a gentle sloping with slopes towards north and having rocky outcrops. 

Table 1.2 Land use in Lease Area S. No  Purpose  Extent (Ha) 1  Area under quarrying  7.0 2  Road  0.03 3  Infrastructure(Office, rest shelter)  0.01 4  Green belt  0.075 5  Vacant  0.885    Total  8.0 

Page 4: ENVIRONMENT MANAGEMENT PLAN 1.0 …environmentclearance.nic.in/writereaddata/FormB/EC/EIA...Patha Bapushetty Cluster Environment Management Plan Team Labs and Consultants . . . ‐

Patha Bapushetty    Cluster Environment Management Plan 

Team Labs and Consultants 1‐4 

Fig 1.1 Location map of Sri Patha Bapushetty 

 

Page 5: ENVIRONMENT MANAGEMENT PLAN 1.0 …environmentclearance.nic.in/writereaddata/FormB/EC/EIA...Patha Bapushetty Cluster Environment Management Plan Team Labs and Consultants . . . ‐

Patha Bapushetty    Cluster Environment Management Plan 

Team Labs and Consultants 1‐5 

 Fig 1.2 Quarry Lease Area sketch of Sri Patha Bapushetty  

Page 6: ENVIRONMENT MANAGEMENT PLAN 1.0 …environmentclearance.nic.in/writereaddata/FormB/EC/EIA...Patha Bapushetty Cluster Environment Management Plan Team Labs and Consultants . . . ‐

Patha Bapushetty    Cluster Environment Management Plan 

Team Labs and Consultants 1‐6 

2.0 Topography  

The area is a gentle sloping with slopes towards north of the Q.L applied area. Boundary pillar 

to the NW side of the applied Q.L area is taken as assumed bench mark of 210 m. The highest 

R.L  is 238 m and the  lowest  is 202 m. Thus, the area  is having an altitudinal range of 36 m 

from the general ground level. 

3.0 Regional Geology  

The regional geology of  the area covering northern part of State  is belonging  to Peninsular 

Gneiss of Archean group. The Karimnagar belt  located along the tectonic  joint between the 

Dharwar belt and Bastar Cratons  in northeastern part of the State and made up of rocks of 

high  grade  metamorphism,  migmatisation  and  intense  deformation.  The  Quarry  Lease 

applied area is rock type might have been derived from migmatisation of different rock types 

of a  stone metal material, which might have  taken  from magma, The  coarse grains of  the 

mineral  assemblage  indicates  the  slow  cooling  of  magma  following  Bowen's  reaction 

principle. The rock  is  formed  in NW‐SE trend. Stone metal of this group  form high hills and 

prominent topographical highs in an otherwise flat or gently undulating country underlain by 

gneissic  rocks  and  schists.  The  Inselbergs,  nubbins,  corestone,  pedestal  rocks, whaleback, 

castle Koppies and such other landforms characterize this stone metal 

4.0 Local Geology 

The  Quarry  Lease  applied  area  comprises  of  granite  boulders  and  massive  sheet  rock 

formation  in  the entire Quarry  lease applied area. This  rock  type might have been derived 

from migmatisation  of  different  rock  types  of  a  granite material, which might  have  taken 

from magma. 

   Alluvial Soil  :   1m to 2m 

Stone metal    :  Massive formation 30m ‐50m. 

5.0 Exploration 

Present Status 

The proposed Quarry is new quarry. 

6.0 Estimation and Calculation of Geological Reserves 

The reserves are computed basing on the available surface massive body over a thickness of 

35m‐40m. However, thickness available upto RL 185 m level in the Q.L area from the ground 

level i.e. 202 m is taken for computation of proved deposit and 10m each below the proved 

Page 7: ENVIRONMENT MANAGEMENT PLAN 1.0 …environmentclearance.nic.in/writereaddata/FormB/EC/EIA...Patha Bapushetty Cluster Environment Management Plan Team Labs and Consultants . . . ‐

Patha Bapushetty    Cluster Environment Management Plan 

Team Labs and Consultants 1‐7 

as probable and possible deposit (as seen from the working quarries of the similar formation 

nearby the Q.L area, whereas, the depths have gone more than 25m from the general ground 

level. The  reserves are calculation by  the cross  sectional method, and  the proved  reserves 

below the ground  level about RL185m. The deposit  is found to be  irregular  in shape. Hence 

cross sectional method adopted for Estimation of Geological Reserves. 7 Section A‐A1 to G ‐

G1 were drawn at equal distance perpendicular  to  the  trend direction of  the  formation  to 

estimate the reserves. The cross sections were drawn perpendicular to the trend direction, 

the cross sectional area of the  individual sections are calculated to arrive at sectional area, 

the area thus arrived  is multiplied by the sectional  influence of 80 M (average) to arrive the 

volume of Road Metal. Details of calculation and their categorization are given below in table 

1.3. 

Table 1.3 Reserves Estimation

Category  Section  Sectional Influence (m) (A) 

Section Area in m² (B) 

Volume in m³ (AxB) 

Reserves @100% m3 

Proved Reserves (111) 

A‐A1  80  5054  404320  404320 B‐B1  80  5143  411440  411440 C‐C1  80  4854  388320  388320 D‐D1  80  4663  373040  373040 E‐E1  80  4433  354640  354640 F‐F1  80  2802  224160  224160 G‐G1  60  1738  104280  104280 

Sub ‐ Total     2260200  2260200 

Probable Resources 

(121) 

A‐A1  80  5054  404320  404320 B‐B1  80  5143  411440  411440 C‐C1  80  4854  388320  388320 D‐D1  80  4663  373040  373040 E‐E1  80  4433  354640  354640 F‐F1  80  2802  224160  224160 G‐G1  60  1738  104280  104280 

Sub ‐ Total     2260200  2260200 Reserves blocked under 7.5m buffer zone 

Category  Section  Sectional Influence (m) (A)

Section Area in m² (B) 

Volume in m³ (AxB)  Reserves @100% m3 

Proved Reserves (111) 

A‐A1  80  452  36160  36160 B‐B1  80  425  34000  34000 C‐C1  80  409  32720  32720 D‐D1  80  430  34400  34400 E‐E1  80  377  30160  30160 

Page 8: ENVIRONMENT MANAGEMENT PLAN 1.0 …environmentclearance.nic.in/writereaddata/FormB/EC/EIA...Patha Bapushetty Cluster Environment Management Plan Team Labs and Consultants . . . ‐

Patha Bapushetty    Cluster Environment Management Plan 

Team Labs and Consultants 1‐8 

F‐F1  80  253  20240  20240 G‐G1  60  319  19140  19140 Sub ‐ Total     206820  206820 

Probable Resources 

(121) 

A‐A1  80  151  12080  12080 B‐B1  80  151  12080  12080 C‐C1  80  150  12000  12000 D‐D1  80  150  12000  12000 E‐E1  80  150  12000  12000 F‐F1  80  165  13200  13200 G‐G1  60  165  9900  9900 Sub ‐ Total     83260  60160 

Reserves blocked under safety slopes 

Category  Section  Sectional Influence (m) (A)

Section Area in m² (B) 

Volume in m³ (AxB)  Reserves @100% m3 

Proved Reserves (111) 

A‐A1  80  185  14800  14800 B‐B1  80  163  13040  13040 C‐C1  80  182  14560  14560 D‐D1  80  189  15120  15120 E‐E1  80  130  10400  10400 F‐F1  80  43  3440  3440 G‐G1  60  68  4080  4080 Sub ‐ Total     75440  75440 

Probable Resources 

(121) 

A‐A1  80  160  12800  12800 B‐B1  80  151  12080  12080 C‐C1  80  146  11680  11680 D‐D1  80  153  12240  12240 E‐E1  80  139  11120  11120 F‐F1  80  91  7280  7280 G‐G1  60  108  6480  6480 Sub ‐ Total     73680  59920 

6.1 Mineable Reserves and Life of the Quarry  

Proved Reserves blocked in 7.5 buffer zone  =   206820 m3 

Proved Reserves blocked under Safety  =   75440 m3 

Total Reserves         =   2260200 m3 

Total mineable reserves = ((2260200 – (206820+75440))  = 1977940 m3 

Life of Mine  =  Total Mineable Reserves and Resources/ Proposed Production 

  =  1977940/ 214824 = 9.20 Years or Say 9 Years 

 

Page 9: ENVIRONMENT MANAGEMENT PLAN 1.0 …environmentclearance.nic.in/writereaddata/FormB/EC/EIA...Patha Bapushetty Cluster Environment Management Plan Team Labs and Consultants . . . ‐

Patha Bapushetty    Cluster Environment Management Plan 

Team Labs and Consultants 1‐9 

7.0 Mining & Methods 

The  road metal and building stone  in  the quarry  lease area  is exposed on  the surface with 

sheet.  Hence,  it  is  proposed  to  quarry  the  sheet  by  opencast  and  manual  method  by 

developing 6m height with single slice of 1.5m bench width with shallow drilling and blasting. 

The development of benches in the sheet rock will be maintained @60Osafety slopes. 

8.0 Year wise Production Plan 

It has been proposed to continue quarrying operation from the existing working pits of the Q.L 

area  from  the existing benches. During  the ensuing  five years  the metal shall be handled by 

developing the existing bench faces and reducing the bench heights. The proposed projections 

are made for the five years period and the workings shall be from all the bench faces north to 

achieve the targeted production of 214824 cu.m. 

1st Year: 

During  first  year  quarry  operations  shall  be  commenced  from  North  side  of  the  first  year 

workings of the Q.L area at 232 top contour by developing a ramp with box cut trench till reach 

bench height of an average 6m upto 204m contour and advance towards South of the mound to 

a  thickness  ranging  in between  6m.  In  the  first  year,  it  is  proposed  to  excavate  an  area  of 

34248m2  with  single  bench  operation  during  the  year  the  quarry  operations  shall  be  in 

between contour 232 – 204 m to RL 226‐198. An average thickness of 6m is quarried with 100% 

recovery about 205488 m3.  

2nd Year: 

During second year quarry operations shall be commenced from Southern side of the first year 

workings of the Q.L area at 236 top contour by developing a ramp with box cut trench till reach 

bench height of an average 6m upto 206m contour and advance towards South of the mound to 

a thickness ranging  in between 6m. In the Second year,  it  is proposed to excavate an area of 

25804m2  with  single  bench  operation  during  the  year  the  quarry  operations  shall  be  in 

between contour 236‐206 m to RL 230‐200m. An average thickness of 6m is quarried with 100% 

recovery about 214824 m3. 

3rd Year: 

During  third year quarry operations shall be commenced below  first year workings of the Q.L 

area at 226 top contour by developing a ramp with box cut trench till reach bench height of an 

average  6m  upto  198m  contour  and  advance  towards  South  of  the mound  to  a  thickness 

Page 10: ENVIRONMENT MANAGEMENT PLAN 1.0 …environmentclearance.nic.in/writereaddata/FormB/EC/EIA...Patha Bapushetty Cluster Environment Management Plan Team Labs and Consultants . . . ‐

Patha Bapushetty    Cluster Environment Management Plan 

Team Labs and Consultants 1‐10 

ranging in between 6m. In the third year, it is proposed to excavate an area of 33259m2 with 

single bench operation during  the  year  the quarry operations  shall be  in between  contour 

226‐198 m to RL 220‐192m. An average thickness of 6m is quarried with 100% recovery about 

199554 m3.   

4th Year: 

During fourth year quarry operations shall be commenced below second year workings of the 

Q.L area at RL 230 top contour by developing a ramp with box cut trench till reach bench height 

of  an  average  6m upto 200m RL  and  advance  towards  southern of  the mound  contour  and 

advance towards South of the mound to a thickness ranging in between 6m. In the fourth year, 

it  is proposed  to excavate an area of 34863m2 with single bench operation during the year 

the quarry operations shall be in between contour RL 230‐200 m to RL 224‐196m. An average 

thickness of 6m is quarried with 100% recovery about 209178 m3. 

5th Year: 

During  fifth year quarry operations shall be commenced below third year workings of the Q.L 

area at 220 top contour by developing a ramp with box cut trench till reach bench height of an 

average  6m  upto  192m  contour  and  advance  towards  South  of  the mound  to  a  thickness 

ranging in between 6m. In the fifth year, it  is proposed to excavate an area of 32279m2 with 

single bench operation during  the  year  the quarry operations  shall be  in between  contour 

220‐192 m to RL 214‐188m. An average thickness of 6m is quarried with 100% recovery about 

193674 m3. 

During the five years operations a total road metal mass 1022718 m3 will be excavated out of 

which 1022718 m3 road metal will be produced and there is no wastage material. Year wise 

production and waste generation details are presented in table 1.5. 

Table 1.5 Year wise Granite Production and Waste generation Year  Working Areas m3  Bench Height m  Volume in m3  Production (100%) m3

I Year  34248  6  205488  205488 II Year  35804  6  214824  214824 III Year  33259  6  199554  199554 IV Year  34863  6  209178  209178 V year  32279  6  193674  193674 

Grand ‐ Total  1022718  1022718  

 

Page 11: ENVIRONMENT MANAGEMENT PLAN 1.0 …environmentclearance.nic.in/writereaddata/FormB/EC/EIA...Patha Bapushetty Cluster Environment Management Plan Team Labs and Consultants . . . ‐

Patha Bapushetty    Cluster Environment Management Plan 

Team Labs and Consultants 1‐11 

9.0 List of Machinery  

Drilling Machines   :   1 No. 

Tractor with trailers  :  2 No’s 

Jack Hammers 

10.0 Employment Potential Table 1.4 Employment potential 

S. No.  Description  Quantity 1  Mines Manager/Supervisor  1 2  Supervisors  1 3  Skilled workers  6 4  Semi Skilled Workers  6 5  Un Skilled Workers  11   Total  25 

11.0 Drilling & Blasting  

54mm hammer drilling will be employed for blasting holes in staggered pattern of 3m x 2.5m 

with depth of 3m.  

1. Drill holes diameter: 54 mm upto 3 ‐ 3.25m long 

2. Drill hole of 3m depth will be drilled in a staggered pattern at 3m x 2.5m interval. 

3. Depth and inclination of the blast holes: Generally drilled vertically in an alignment.  

4. Explosive type: ANFO + Booster & Detonator fuse. 

12.0 Site services 

It  is proposed to provide the site services  like mine office and other statutory constructions 

like  rest  shelter,  first aid, work  shed and drinking water as  required near  the quarry  lease 

area.  Drinking  water  will  be  supplied  to  the  workers  from  the  bore  well  opened  in  the 

adjacent agricultural field or from nearby village.  

13.0 Water requirement 

Water requirement is mainly for drinking purpose, domestic purpose, green belt maintaining 

and for sprinkling on Mine haulage roads the water shall be drawn from nearby village. The 

domestic waste water shall be sent to septic tank followed by soak pit.  Rainwater Catch Pond 

of 20 KL capacity will be provided to collect the storm water for reuse.  This will ensure that 

the  rainwater  is effectively used  and minimizes  the drawl of  ground water  resources.  The 

water requirement is presented in table 1.6.  

  

Page 12: ENVIRONMENT MANAGEMENT PLAN 1.0 …environmentclearance.nic.in/writereaddata/FormB/EC/EIA...Patha Bapushetty Cluster Environment Management Plan Team Labs and Consultants . . . ‐

Patha Bapushetty    Cluster Environment Management Plan 

Team Labs and Consultants 1‐12 

Table 1.6 Water Requirement  S. No.  Water Usage  Quantity KLD 1  Wet drilling operation (On production basis @ 100 Ltr/1 m3)  5.3 2  Water sprinkling on haul roads   1.6 3  Domestic @ 45 Ltr/Head (25 No’s)  1.1 4  Green Belt @ 0.2 KL  – 2 times a day  0.4 

Total  8.4 14.0 Environment Management Plan 

Environmental protection  is an  issue  that no organization can neglect and hope  to survive.  

The products of  civilization are being dumped upon  the environment  to a degree  that  the 

environment finds difficult to assimilate. The key to the success of the integrated approach to 

pollution  prevention  and  control  is  the management  and  operation  of  the  organization.  

Effective  committed management delivers a  successful operation. As  total  commitment  to  the 

environment, not  just for compliance with  legal or regulatory compliance will be the essence of 

environment management. Many  companies have  recognized  the benefits of  implementing an 

effective  environmental  management  system.  Environmental  management  plan  can  be 

effectively implemented to mitigate the pollution levels by observing the following: 

a. Pollution will be prevented or reduced at the source 

b. Pollution that cannot be prevented will be recycled in an environmentally safe manner. 

c. Pollution that cannot be prevented or recycled will be treated in environmentally safe manner 

and 

d. Disposal and other releases into the environment will be used only as a last resort and will be 

conducted in an environmentally safe manner. 

The proposed project is granite mine. The mine owners are aware of the adverse impacts due to 

the mining activity and propose to initiate a number of measures for the environment protection 

within  the mine  area  and  in  the  surrounding  areas.  The  company has  a  stated  environmental 

policy of ensuring regulatory compliance with respect to the statutory  laws and regulations and 

those periodically  issued by the Ministry of Environment, GOI, New Delhi, CPCB, New Delhi and 

State Pollution Control Board.  

14.1 Sources of Pollution and Control Measures 

The  sources of pollution are air and noise  from  the proposed activity mainly  from Mining, 

drilling, Blasting and transportation of mineral. 

  

Page 13: ENVIRONMENT MANAGEMENT PLAN 1.0 …environmentclearance.nic.in/writereaddata/FormB/EC/EIA...Patha Bapushetty Cluster Environment Management Plan Team Labs and Consultants . . . ‐

Patha Bapushetty    Cluster Environment Management Plan 

Team Labs and Consultants 1‐13 

14.1.1 Air pollution and its control 

The granite quarrying does not  involve much dust  formation. The dust would be generated 

during drilling, smooth blasting, quarrying and also during handling and transportation of the 

material. The dust anticipated at drilling place will be suppressed by putting cloth around the 

hole.  Use  of  sharp  drill  pits  for  drilling  holes  and  drills with water  flushing  systems  (wet 

drilling) to reduce dust generation. Water spraying to be adopted at Faces/sites before and 

after  blasting,  Faces/sites while  loading.  Over  charging  of  blast  holes  should  be  avoided. 

Personal  protective  equipments  like  nose mask  and  goggles  etc  will  be  provided  to  the 

workers. Regular water spraying on haul roads during transportation of mineral and waste by 

water sprinklers. Over loading of transport equipments should be avoided to prevent spillage. 

Also, measures such as covering tarpaulin over the loaded material will prevent spreading of 

dust particles from the trucks. Speed controls on vehicle movements to limited speed. Wind 

reduction  control  by  plantation.  Limiting  the  height  and  slope  of  the  stockpiles  can  also 

reduce wind speed. Regular checking and maintenance of vehicles should be conducted and 

pollution under control certificate be obtained. Periodical monitoring of ambient air quality 

will helps to take steps to control the pollutants. 

14.1.2 Noise pollution and its control 

The  major  source  of  noise  pollution  is  due  to  drilling  of  drill  holes,  machinery,  smooth 

blasting and vehicular movement. Blasting operations will be carried out only during daytime 

so  as  to  avoid  high  noise  intensity  in  night  time. Noise  barriers  in  the  form  of  trees  are 

provided  to  attenuate  the  noise  levels  and  greenbelt  of  5m width  shall  be  developed  to 

mitigate propagation of noise. Protective equipment to reduce the noise levels like ear muffs 

and  other  protective  devices will  be  provided  to  the  staff working  near  noise  generating 

sources like drill machine operators and dumper drivers. Training would be imparted to mine 

personnel to generate awareness about the damaging effects of noise. The transport activity 

shall be  restricted  to day  time  to  reduce  impact on habitation. The engines of  the  tractors 

shall be switched off during loading operation, and shall be periodically maintained to ensure 

low noise levels. Proper maintenance of the equipment will also reduce the noise.  

15.0 Occupational Safety and Health 

Health  and  safety  aspects of  the mine will be  taken  care off  as per  the World Bank  (WB) 

guidelines on open pit mining. The guidelines provide the detailed information on the aspects 

Page 14: ENVIRONMENT MANAGEMENT PLAN 1.0 …environmentclearance.nic.in/writereaddata/FormB/EC/EIA...Patha Bapushetty Cluster Environment Management Plan Team Labs and Consultants . . . ‐

Patha Bapushetty    Cluster Environment Management Plan 

Team Labs and Consultants 1‐14 

that are required to be taken  into account  for maintaining proper health and safety  issues.   

The workers continuously exposed to dust will be provided with protective devices  like dust 

mask to prevent respiratory disorders. The workers continuously exposed to a high noise will 

be  provided with  ear muffs/  earplugs. Green  belt  in  and  around  the mining  area will  be 

developed to attenuate noise and dust impact. The blasting carried out in the mine area will 

be carefully planned and executed under the supervision of a responsible officer, to avoid any 

accidents. Provisions of rest shelter for mine workers with facility of drinking water supply for 

the employees will be provided by the project authority. The standard of the drinking water 

will be per WHO guidelines. Periodical  training programme  to  inform  the employees about 

their  task, associated  risk, and safe working practices will be undertaken. Conduct of mock 

drill, Safe storage & handling of explosives. Training will also include information on accident 

prevention,  proper  control  and  maintenance  of  equipment  and  safe  material  handling 

practices. Awareness on safety and ensure using of personal protective equipments (PPE) by 

workers. Regular maintenance and testing of equipments will be done.  A regular monitoring 

of  the Occupational  Health  and  Safety will  reduce  the  chances  of  accidents  in  the mine. 

Records of  job related accidents and  illness should be maintained.   This  information will be 

reviewed  and  evaluated  to  improve  the  effectiveness  of  Environmental Health  and  Safety 

programme. 

Occupational Safety and Health to Control Dust Inhalation 

Very  little  dust  is  expected  to  be  generated  during  mining  and  does  not  affect  the 

environment. However while drilling, wet drilling will be practiced.  It  is a small scale mining 

activity and not much vehicular movement  is expected. All the above precautions would be 

adopted to prevent dust generation at site and to be dispersed  in the outside environment. 

However, for the safety of workers at site, engaged at the strategic locations/dust generation 

points  like  drills,  loading &  unloading  points  dust masks would  be  provided.  Dust masks 

would  prevent  inhalation  of  RSPM  thereby  reducing  the  risk  of  lung  diseases  and  other 

respiratory disorders. Regular health monitoring of workers will be carried out. 

15.1 Occupational Safety and Health to Control Exposure to Noise 

Blasting will be done using non delay detonators  to  reduce  vibrations, and  the amount of 

explosive used will also be  less at a  time. There will not be heavy earth moving machinery 

which may create some noise pollution. Thus the vibration and noise will be well controlled 

Page 15: ENVIRONMENT MANAGEMENT PLAN 1.0 …environmentclearance.nic.in/writereaddata/FormB/EC/EIA...Patha Bapushetty Cluster Environment Management Plan Team Labs and Consultants . . . ‐

Patha Bapushetty    Cluster Environment Management Plan 

Team Labs and Consultants 1‐15 

within  permissible  limits.  To  protect  the  workers  from  exposure  to  high  levels  of  noise, 

following measures would be adopted: 

Provision of protective devices like ear muffs/ear plugs to workers who cannot be isolated 

from the source of high intensity noise, e.g. blasting; 

Reducing the exposure time of workers to the higher noise levels by shift management. 

Smooth blasting techniques, special explosives and silent non‐explosive demolishing agent 

will be used. 

Muffed  blasting  and  use  of  Milli‐second  detonators  will  help  in  reducing  the  noise 

pollution. 

15.2 Control of Ground Vibration & Fly Rock generation 

In  this area  the applicant proposes  to deploy blasting with  less quantity of non‐explosives. 

There will not be any impact on surroundings, as there are less blasting and intended to use 

low power explosives  in this mine.  It  is a small scale mine and only  limited No. of holes are 

blasted.  Ground vibrations due to blasting and its impact on various mine structures, should 

be  studied  in details when  the mine becomes operational, especially  the  charge per delay 

factor.   General measures to reduce ground vibration & fly rocks resulting from blasting are 

given below:  

Blasting should be carried out in the daytime, as during the night time the sound intensity 

becomes higher; 

Blasting should not be carried out when strong winds are blowing towards the inhabited 

areas; 

Maximum permissible charge per delay should be decided on the basis of the distance of structure to be protected from the blasting. 

The number of rows  in a blast should not be more than four so that fly rock generation and ground vibration is reduced.  

Peak  particle  velocity  or  ground  vibrations  for  safety  of  nearby  structures  and    

residential buildings should be well within 12.5 mm/sec; 

To contain  fly  rocks, stemming column should not be  less  than  the burden of  the hole, 

and the blasting area should be muffled; 

Each blast should be carefully planned, checked, and executed under the supervision of a 

responsible officer. Blasting data/observations should be recorded; and 

Page 16: ENVIRONMENT MANAGEMENT PLAN 1.0 …environmentclearance.nic.in/writereaddata/FormB/EC/EIA...Patha Bapushetty Cluster Environment Management Plan Team Labs and Consultants . . . ‐

Patha Bapushetty    Cluster Environment Management Plan 

Team Labs and Consultants 1‐16 

As per the mining plan, in order to ensure slope stabilization, controlled production blasting 

shall be adopted  to  avoid  tension  cracks  and back breaks.  Such  cracks may  get  filled with 

water, which reduces the stability of excavated slopes and the angle of slopes. 

16.0 Water Quality Management 

There  is no chemical discharge either  from the quarry or  from the processing quarry, there 

will not be water pollution. The proposed quarry workings will not touch the ground water 

aquifer.  Quarrying  operations will  be  carried  out  on  the  slope  of  the  Rocky  terrain.  The 

ground water  level  in  this  area  is  20m  BGL  and  the  quarrying will  be  done  on  above  the 

surface  level. Maximum depth of the quarry will be 20m from top of the hill which  is about 

50m height from ground  level, flooding by ground water  is not anticipated. However during 

rainy months, there is a possibility of wet conditions developing in the working pit this will be 

minimized,  if not altogether eliminated, by adopting simple techniques like digging trenches 

all  round  to drain off  rainwater and preventing  surface  run off  from entering and  flooding 

working pit.  The water  from  the pits will be pumped by deploying  suitable pumps,  if  and 

when required, the mine drainage can be effectively managed and the pit kept dry to keep up 

the production schedule.  

17.0 Water Resources 

In this area water table is at greater depth of 20 m BGL. There are no wells or springs in the 

area. Hence  there will not be adverse effect on ground water due  to quarrying.   The daily 

water  requirement  for  the  mine  operations  would  be  approximately  8.4  KLD.  Water 

sprinkling on mine haulage roads etc shall consume 1.6 KLD. Wet drilling operations consume 

about 5.3 KLD. For green belt development water consumption  is about 0.4 KLD. Domestic 

purpose  is about 1.1 KLD. The drinking water  is  to be sourced  from nearby village  through 

tankers and rainwater collected will be used for sprinkling, green belt development and etc. 

The generation of wastewater  from domestic  sources  is expected  to be approximately 0.9 

KLD, which will be sent to septic tank followed by soak pit.   

17.1 Water Management 

Following measures will be adopted to mitigate the impact on the water resources: 

The blasting activities will have to take care on the sinkholes, cracks and  fissures  in the 

site activities. 

During  excavation  and  drilling  activities  effort must  be  taken  to  avoid  face  collapse  at 

Page 17: ENVIRONMENT MANAGEMENT PLAN 1.0 …environmentclearance.nic.in/writereaddata/FormB/EC/EIA...Patha Bapushetty Cluster Environment Management Plan Team Labs and Consultants . . . ‐

Patha Bapushetty    Cluster Environment Management Plan 

Team Labs and Consultants 1‐17 

these cracks and fissures. 

To prevent surface water contamination by oil/grease, leak proof containers shall be used 

for storage and transportation of oil/grease. The floors of oil/grease handling area will be 

kept effectively impervious.  

To  prevent  degradation  and maintain  the water  quality  during  rainy  season,  adequate 

control measures should be adopted to check the mine run‐off into the natural streams.  

17.2 Catchment Area Treatment Plan 

A  catchment  area  treatment  plan  has  been  developed  keeping  in mind  the  results  of  the 

hydrology/ hydrogeology of the area and the climate data. As there are no perennial water 

sources running on or through the site, the mine water discharge  is  limited to the monsoon 

season only.  To keep water from entering the mine during this period, a garland drain will be 

developed along  the mine’s  top bench, which will bend  to guide  the water  to  the nearest 

natural  surface  drain.  In  terms  of  water  quality,  good  mining  practices  are  planned, 

additionally  the  natural  state  of  surrounding  areas,  should  ensure  that  rain water  run‐off 

from the mine does not contain any toxic elements. As the site has no overburden, potential 

discharge of sediments is quite limited and any residual particles which are washed down will 

be captured by a sump located at the lowest bench. The sump will be cleaned regularly and 

discharge water monitored consistently. If required, based on monitoring, an additional catch 

pit can be located at the main garland drain. The sump proposed in the bottom bench will be 

designed  based  on  the  peak  discharge  and  will  be  expanded  over  a  period  of  time  to 

accommodate  the  increasing  quantum  of water  discharge.    Presently,  the  capacity  of  the 

sump  is  designed  to  hold  the  entire  quantum  of  peak  discharge water  for more  than  10 

minutes. The garland drain shall be provided surrounding the mine area. Garland drain and 

siltation pond need  to be constructed of appropriate  size  to arrest  silt and  sediment  flows 

from soil. The water so collected will be utilised for watering the mine area, roads, green belt 

development etc. The drain should be regularly desilted and maintained. The garland drain 

(size, gradient and  length) and  sump  capacity will be designed  keeping 50%  safety margin 

over and above  the peak sudden rainfall and maximum discharge  in  the area adjoining  the 

mine  site. Sump capacity  should also provide adequate  retention period  to provide proper 

settling  of  silt  material.  The  surface  water  around  the  mine,  and  infrastructure  will  be 

regularly  tested  and  appropriate  control  measures  adopted  in  case  of  any  pollutant  is 

Page 18: ENVIRONMENT MANAGEMENT PLAN 1.0 …environmentclearance.nic.in/writereaddata/FormB/EC/EIA...Patha Bapushetty Cluster Environment Management Plan Team Labs and Consultants . . . ‐

Patha Bapushetty    Cluster Environment Management Plan 

Team Labs and Consultants 1‐18 

detected above the prescribed limits. 

18.0 Waste Management plan 

During the plan period a total volume of 1022718 m3 will be excavated out of which 1022718 

m3 of road metal and building stone will be produced and there is no waste is anticipated in 

this mine area. 

19.0 Dump Area 

No waste will be generated  in  this quarry. This material  can be utilized  to  fill  the pits and 

completed pit areas used as water storage tanks after completion of quarrying. 

20.0 Land Management 

Land  degradation  is  one  of  the major  adverse  impacts  of  opencast mining  in  the  form  of 

excavated  voids  and  also  in  the  form  of  waste  dumps.  Land  reclamation  plan  must  be 

implemented simultaneously with the mining activities. 

20.1 Land Reclamation 

The proposed quarry lease area will not reach the mineable depth by the end of first five year 

plan period, no reclamation activities as proposed presently.  

20.1.1 Soil Conservation Measures 

The applied area is hill in the wavy and irregular. Therefore, the growth of trees and plants is 

uncertain  and  not  satisfactory. Hence,  in  this  area  few  small  plants  and  thorny  trees  are 

grown here and there. Except this, no big trees are seen  in this area. Top soil,  if any will be 

used as greenery purpose following measures shall be adopted:  

• Garland drains will be provided around the mine wherever required to arrest any soil 

from the mine area being carried away by the rain water; 

• Toe drains with suitable baffles will be provided all along the toe of the soil dumps to 

arrest any soil from the dump slopes being carried away by the rain water; 

• Loose material slopes will be covered by mineation by making contour trenches at 5 

m interval to check soil erosion both due to wind and rain; 

Retaining walls (concrete or  local stone) will be provided, around the stockpile or wherever 

required,  to support  the benches or any  loose material as well as  to arrest sliding of  loose 

debris. 

21.0 House Keeping 

Proper housekeeping and cleanliness will be maintained  in the  infrastructure facilities.   Wet 

Page 19: ENVIRONMENT MANAGEMENT PLAN 1.0 …environmentclearance.nic.in/writereaddata/FormB/EC/EIA...Patha Bapushetty Cluster Environment Management Plan Team Labs and Consultants . . . ‐

Patha Bapushetty    Cluster Environment Management Plan 

Team Labs and Consultants 1‐19 

mopping will be adopted to conserve water.  Sign boards will be provided in the work areas 

and the road and building highlighting the safety and occupational aspects. 

22.0 Transport Systems 

Putnur to Dongaturti road passing at a distance of 1.0 km from the QL area in west direction. 

Nearest Railway station and nearest town Raghavapuram RS located at a distance of 9.5 km 

in SE direction. The finished product and waste material is transported by road using trucks of 

17 Tons capacity.  The number of trips will be approximately 42 per day for transportation of 

mineral  and  the  trucks  are  covered  with  tarpaulin.  The  lessee  will  deploy  2  tippers  to 

transport the finished product, waste blocks, unfinished and finished blocks from quarry site 

to yard and trucks to transport sized dimensional blocks from yard to destination. Cranes will 

do the loading of blocks. The materials while transporting do not pose any hazard. Sufficient 

parking facilities will be provided for vehicles loading and unloading of material. Safety signs 

will be displayed  inside and outside the mine to avoid road accidents.    In cluster area total 

mines  are  transporting  the  trips  will  be  approximately  15  per  day  for  transportation  of 

mineral and the trucks are covered with tarpaulin. In this cluster, the mine lease holders are 

having 12 tippers. All mine lease holders are follow all rules in this cluster 

23.0 Environmental Greening Program 

Environmental  greening  program  is  an  important  component  of  the  Environment 

Management Plan and is an imperative requirement for sink of air pollutants including noise 

as  per  the  guidelines  issued  by  the Ministry  of  Environment  and  forests,  Govt.  of  India.  

Conceptualization, design and  implementation of the proposed activity, taking  into account 

the  specific  requirement  of  the  proposed  mining  activity  and  the  site  conditions  are 

presented. Green  cover  in mining  area  not  only  help  in  reducing  pollution  level,  but  also 

improves  the  ecological  conditions  and  prevent  soil  erosion  to  great  extent.  It  further 

improves  the  aesthetics  and  beneficially  influences  the microclimate  of  the  surrounding.  

During the plan period it is proposed to plant 150 saplings in the ensuing period at the rate of 

30  saplings  per  annum  at  the NE  side of  the  area of  about  0.075 m2.  The  shelterbelt will 

contain  species,  which  act  as  windbreakers  so  that  the  environment  within  the mine  is 

contained; the planting of different species in rows is envisaged in general in the greenbelt. A 

dedicated  cell  in  the mine  should  be  established  for  post  plantation  care, which  include, 

regular watering, manuring, protective measures  etc. Diseased  and dead plants  should be 

Page 20: ENVIRONMENT MANAGEMENT PLAN 1.0 …environmentclearance.nic.in/writereaddata/FormB/EC/EIA...Patha Bapushetty Cluster Environment Management Plan Team Labs and Consultants . . . ‐

Patha Bapushetty    Cluster Environment Management Plan 

Team Labs and Consultants 1‐20 

uprooted and  replaced by  fresh  saplings. Regular monitoring on  survival  rate and  remedial 

action should be done in an organized and planned manner.  

24.0 Socio‐economic Environment 

The  project  provides  an  opportunity  for  the  local  people  to  get  employment  directly  or 

indirectly and helps in the upliftment of the socioeconomic status of the area. The proposed 

project would generate an employment of 25. The  local  inhabitants of  the area  live  in  the 

villages surrounding  the mine area and  their main occupation  is Agriculture.  In a small way 

they  rear  cattle  and  sheep  for  sustenance.  The mining  activity  in  this belt will  benefit  the 

locals both directly and indirectly. The direct beneficiaries will be those who get employed in 

the mines as skilled and un‐skilled workers. The indirect beneficiaries will be those who open 

small  business  to  sell  goods  required  by  the  residents whose  “Per  Capita”  income will  be 

enhanced by the mining activity, and thereby their purchasing power. In the long run a lot of 

social good is expected in the comparatively backward area when the inhabitants will be able 

to  send  their children  to  school. The change,  though  slow,  is bound  to be perceptible. The 

management  will  involve  in  social  activities  of  stakeholders/surrounding  community  by 

planning  the  betterment  of  neighboring  social  conditions  through  awareness  and welfare 

programs to ensure an improved relation, useful in the long run.  Many of the beneficiaries of 

such programs will  include own employees as well.   The goodwill of  the  local populace can 

never  be  ignored.    It  is  proposed  to  supply  drinking  water  and medical  facilities  to  the 

villagers. The management will also support for vocational training and assistance in utilizing 

government programs. The channels employed may vary either through direct contact or by 

means of local organizations. Another important facet of social environment identified by the 

project proponents  is a green appearance; hence the management will develop a green belt 

towards aesthetic beautification as the same  is necessary to be considered as a responsible, 

social neighbour. 

26.0  Disaster Planning 

The mining operation shall be carried out under the management control and direction of a 

qualified mines manager  holding  a  Second  class manager’s  certificate  of  competency  to 

manage  a metalliferous mine  granted by Director General of mines  safety  (DGMS). DGMS 

have  been  issuing  a  number  of  standing  orders  and  circulars  to  be  followed  by  the mine 

management  in  case of disaster,  if any. Moreover mining  staff would be  sent  to  refresher 

Page 21: ENVIRONMENT MANAGEMENT PLAN 1.0 …environmentclearance.nic.in/writereaddata/FormB/EC/EIA...Patha Bapushetty Cluster Environment Management Plan Team Labs and Consultants . . . ‐

Patha Bapushetty    Cluster Environment Management Plan 

Team Labs and Consultants 1‐21 

courses  from  time  to  time  to  keep  them  abreast  of  the  regulations.  However  following 

natural/ quarrying hazards may occur during normal operation  

Slope failure at the mine faces; 

Accident due to explosives; 

Accident due to heavy equipment/machinery; 

Sabotage in case of magazine; and 

Accidents due to fly rocks and boulders. 

In order to take care of above hazards/disasters, the following control shall be adopted: 

All  safety precautions and provisions of Metalliferous Mine  regulation 1961 are  strictly 

followed during all mining operations; 

Checking  and  regular maintenance  of  garland  drains  and  earthen  bunds  to  avoid  any 

inflow of surface water into mining area; 

Entry of unauthorized persons shall be prohibited; 

Fire fighting and first aid provisions in the mines office  and mining Area; 

Provision  of  all  the  safety  appliances  such  as  safety  boots,  helmets,  dust masks,  ear 

mufflers, goggles etc. would be made available  to  the employees and  regular  check  to 

ensure the use; 

Training and refresher courses for all the employees working in the hazardous premises; 

Working  of  mine  as  per  approved  plan,  related  amendments  and  other  regulatory 

provisions; 

Cleaning of mine faces shall be done regularly; 

Handling of explosives, charging and blasting shall be carried out by competent persons 

only; 

Provision of magazine at safe place with fencing and necessary security arrangement; 

Suppression of dust on the haulage roads by providing water sprinkling. 

27.0 Environment Management Cell 

A Cell  for Environmental Management within Mine  lease area at the project  level, will take 

the  overall  responsibility  for  co‐ordination  of  the  actions  required  for  environmental 

management and mitigation, and for monitoring the progress of the proposed management 

plans and actions to be taken for the project. The Cell will be under the overall supervision of 

the Mine Manager,  and  responsible  for monitoring  of  the  implementation  of  the  various 

Page 22: ENVIRONMENT MANAGEMENT PLAN 1.0 …environmentclearance.nic.in/writereaddata/FormB/EC/EIA...Patha Bapushetty Cluster Environment Management Plan Team Labs and Consultants . . . ‐

Patha Bapushetty    Cluster Environment Management Plan 

Team Labs and Consultants 1‐22 

actions which  are  to  be  executed  by  the  agencies  specified  in  the  EMP.  The  Cell will  be 

headed by Mine Manager and the other members of the cell that will include a Horticulturist. 

The EMC will prepare a formal report on environmental management and mitigation for the 

Environmental  issues  at  the  Mine,  at  six‐monthly  intervals.  Reports  on  any  urgent  or 

significant  issues may  be  prepared  at  shorter  intervals.  Apart  from  responsibilities  listed 

above, the EMC will have the responsibility of the following: 

Collection of  water and air samples within and outside the  work zone; 

Analyzing the water and air samples; 

Implementation  of the control and protective measures; 

Land reclamation and vegetation; 

Co‐ordination of the environment related activities; 

Collection of the statistics of health of workers; 

Green belt development; 

Awareness and implementing safety programmes; and 

Monitor the progress of implementation of EMP. 

27.1  Post Project Monitoring  

The survey of post project monitoring comprises of the following monitoring aspects; 

a. Ambient air quality survey 

b. Noise Level Monitoring 

c. Water quality monitoring 

 Ambient air quality and noise level Monitoring will be carried out at minimum four stations, 

two  stations within mine  site  and  two  stations nearby  residential  areas outside  the mine.  

Parameters like particulate matter, sulphur dioxide, oxides of nitrogen carbon monoxide and 

lead will be monitored in case of ambient air quality. Water quality monitoring will be carried 

out  in  the mine  working  area,  sump  and  nearby  village.  The  frequency  of monitoring  is 

preferably  once  in  three  months  on  24  hour  basis.  The  samples  will  be  collected  in 

accordance with the procedures given by CPCB.   

27.2  Other Management Aspects 

Records will  be maintained  for  the  analysis  of  ambient  air  quality,  noise  levels  and water 

quality.   These records are not only required  for the perusal of the Pollution Control Board 

authorities to take preventive action against the environmental pollution. The management 

Page 23: ENVIRONMENT MANAGEMENT PLAN 1.0 …environmentclearance.nic.in/writereaddata/FormB/EC/EIA...Patha Bapushetty Cluster Environment Management Plan Team Labs and Consultants . . . ‐

Patha Bapushetty    Cluster Environment Management Plan 

Team Labs and Consultants 1‐23 

will maintain  the  records as per  the hazardous waste  regulations and EPA  regulations and 

apply for the annual consents for air and water, and renewal of authorization for the storage 

of hazardous waste as per the Hazardous Waste (Handling & Management) Rules, 1989.  The 

records of hazardous waste manifest will be maintained.   The mine will obtain the consent 

for establishment (CFE) and consent for operation (CFO) from State Pollution Control Board 

as required under section 25/26 of the Water act, 1974 and under section 21/22 of Air Act, 

1981, before  commissioning  and production  as directed by  the Hon’ble  Supreme Court of 

India. The CFO will be renewed each year by the management in consultation with SPCB. The 

mine  will  submit  environmental  statement  every  year  before  September  30.  The 

management ensures that it will comply with all the directions and regulations issued by the 

Ministry of Environment and Forests, New Delhi, State and Central Pollution Control Boards. 

The  Consent  for  Establishment,  Consent  for Operation will  be  displayed  in  a  conspicuous 

location for the information of the inspecting authorities of different departments. 

28.0 Cost proposed for Environmental Protection Measures 

The cost estimate of environment management is presented in table 1.8.  

Table 1.8 Environment Management ‐ Cost Estimate 

S. No.  Description  Item  Capital 

cost (Rs.)Recurring cost (Rs.)  Remarks 

1  Air pollution 

Nose masks 25 No's  24000  2400  Once a week. Replaceable, and cost may increase with time 

Cloth for drillers 20no's 1m each.  4800  2560  Issued quarterly 

Gunny bags for covering the surface of jackhammer holes  11200  3120  As and when needed, Lump sum.

Road wetting @ 1 Ltr/400 Sq. m.   54000  3240  Water tanker cost @ one 

tankers per day for 300 days Plantation on road side ‐ 3m interval and buffer zone  ‐ 3m interval plus maintenance 

37917  7583 

Re‐plant the non‐surviving plants, watering and protection from animals 

Sub Total   131916  18903    

2  Water  pollution 

Construction of garland drains   62901  25230  Once only for the lease 

period/life of mine De‐silting operations   66080  31270  Yearly and manual operations 

Construction of check dams   117360  68460  Once in year, cost incurred is to buy sand bags and filling sand 

Construction of retaining  76960  34336  Cost of construction of wall  

Page 24: ENVIRONMENT MANAGEMENT PLAN 1.0 …environmentclearance.nic.in/writereaddata/FormB/EC/EIA...Patha Bapushetty Cluster Environment Management Plan Team Labs and Consultants . . . ‐

Patha Bapushetty    Cluster Environment Management Plan 

Team Labs and Consultants 1‐24 

wall  Sub Total   323301  159296    

3  Noise pollution 

Maintenance of machinery suitably ‐ Rs. 4000 per 3 months 

60000  33000 Included in main cost 

PPE's like Ear muffs ‐ Rs. 15 each  1500  1000  Once in six months 

Sub Total   61500  34000    

4 Occupational Safety and Health 

First aid kits ‐ 2 No's  Fire extinguishers ‐ 2 No's  6000  2000  Once in year, replace by 

conducting periodical checkup PPE's to all employees (hand gloves @ Rs. 30, safety shoe @ Rs. 1500 and helmet @ Rs. 100) 

73580  30904 

Safety shoe twice in a year, helmets once in three years and hand gloves thrice in a year 

Training and awareness programs on risk factors during emergencies by the experts 

10000  5000 

Once in six months and create sign boards about the risk and safety precautions regularly 

Periodical medical checkup and supply of medicines ‐ Rs. 600 per head 

20000  3000 Once in a year and supply of medicines for every three months 

   Sub Total   109580  40904    

5  Environmental monitoring 

Ambient air quality studies ‐ Once in six months ‐ 2 locations 

‐  13600 

Will be done through MoEF &CC/NABL recognised 

laboratories  

Water quality studies ‐ Once a year ‐ 2 Locations  ‐  3000 

Noise studies ‐ Once in six months ‐ 2 Locations   ‐  4400 

Vibration studies ‐ Once in year ‐ 1 locations  ‐  7800 

 Sub Total  0  28800     Grand Total   626297  281903