Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
SASOL SYNFUELS OPERATIONS: WATER AND ASH
ENVIRONMENTAL AUTHORISATION AND ENVIRONMENTAL MANAGEMENT PROGRAMME COMPLIANCE AUDIT REPORT 17/2/2/1(E) MP-04 - WATER RECOVERY GROWTH
06 JUNE 2019
CONFIDENTIAL
WSP Environmental (Pty) Ltd.
ENVIRONMENTAL AUTHORISATION AND ENVIRONMENTAL MANAGEMENT PROGRAMME COMPLIANCE AUDIT REPORT
17/2/2/1(E) MP-04 - WATER RECOVERY GROWTH
SASOL SYNFUELS OPERATIONS: WATER
AND ASH
TYPE OF DOCUMENT (VERSION)
CONFIDENTIAL
PROJECT NO.: 41101534
DATE: JUNE 2019
WSP
BUILDING C
KNIGHTSBRIDGE, 33 SLOANE STREET
BRYANSTON, 2191
SOUTH AFRICA
T: +27 11 361 1392
F: +27 11 361 1381
WSP.COM
Q U A L I T Y M A N A G E M E N T
ISSUE/REVISION FIRST ISSUE REVISION 1 REVISION 2 REVISION 3
Remarks Draft for Review –
Compliance Audit
EA Ref: 17/2/2/1(e)
MP-04
Final – Compliance
Audit
EA Ref: 17/2/2/1(e)
MP-04
Date April 2019 June 2019
Prepared by Tutayi Chifadza Tutayi Chifadza
Signature
Checked by Ashlea Strong Ashlea Strong
Signature
Authorised by Jenny Cope Jenny Cope
Signature
Project number 41101534 41101534
Report number 010 010
File reference W:\000 NEW Projects\41101534 - Sasol EA and EMP Audits\42 ES\2-
REPORTS\010_SSO_WA_EA_17.2.2.1(e) MP-04\01 Draft report
S I G N A T U R E S
PREPARED BY
Tutayi Chifadza
Consultant
REVIEWED BY
Ashlea Strong
Principal Consultant
This Compliance Audit report (Report) has been prepared by WSP Environmental (Pty) Ltd (WSP) on behalf and
at the request of Sasol Synfuels: Secunda Operations (Client), to provide the Client with an understanding of their
compliance with the conditions included in the Environmental Authorisation and associated Environmental
Management Plan.
Unless otherwise agreed by us in writing, we do not accept responsibility or legal liability to any person other than
the Client for the contents of, or any omissions from, this Report.
To prepare this Report, we have reviewed only the documents and information provided to us by the Client or any
third parties directed to provide information and documents to us by the Client. We have not reviewed any other
documents in relation to this Report, except where otherwise indicated in the Report.
P R O D U C T I O N T E A M
SASOL
SHE Specialist: Environment Broni van der Meer
Water and Ash Production Senior
Manager, Secunda Synfuels Operations
Rakesh Durjan
WSP
Associate Jenny Cope
Lead Auditor Ashlea Strong
Consultant Tutayi Chifadza
ENVIRONMENTAL AUTHORISATION AND ENVIRONMENTAL MANAGEMENT PROGRAMME COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL SYNFUELS OPERATIONS: WATER AND ASH
WSP June 2019
TABLE OF CONTENTS
1 INTRODUCTION ........................................ 1
1.1 Terms of Reference ................................................. 1
1.2 Water Recovery Growth Project (Authorisation
Number: 17/2/2/1(E) MP-04) .................................... 1
2 AUDIT SCOPE ........................................... 4
3 AUDIT METHODOLOGY ........................... 5
3.1 Audit Checklist ........................................................ 5
3.2 Site Inspection ......................................................... 5
3.3 Documentation Considered ................................... 5
3.4 Audit Compliance Assessment .............................. 6
3.5 Audit Team ............................................................... 6
3.6 Assumptions and Limitations ................................ 7
4 AUDIT FINDINGS ...................................... 8
5 SUMMARY OF THE AUDIT FINDINGS ... 48
5.1 Environmental Authorisation ............................... 48
5.2 Environmental Management Plan ........................ 51
ENVIRONMENTAL AUTHORISATION AND ENVIRONMENTAL MANAGEMENT PROGRAMME COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL SYNFUELS OPERATIONS: WATER AND ASH
WSP June 2019
TABLES
TABLE 1: COMPLIANCE LEVEL DEFINITION AND TARGET COMPLETION DATES .................. 6
TABLE 2: AUDIT FINDINGS – ENVIRONMENTAL AUTHORISATION ......................... 8
TABLE 3: AUDIT FINDINGS – ENVIRONMENTAL MANAGEMENT PLAN ................. 19
TABLE 4: SUMMARY OF EA COMPLIANCE AUDIT FINDINGS ........................ 48
TABLE 5: SUMMARY OF EMPR COMPLIANCE AUDIT FINDINGS .................................... 51
FIGURES
FIGURE 1-1: WRG PROCESS FLOW ................ 1 FIGURE 1-2: WATER RECOVERY GROWTH
PLANT (SOURCE: GOOGLE EARTH, 2018) ............................... 3
FIGURE 5-1: NUMBER/COUNT CONTRIBUTION OF FINDINGS MADE TO THE EA CONDITIONS PER SECTION ............................ 49
FIGURE 5-2: OVERALL COUNT FINDINGS ON COMPLIANCE TO THE EA CONDITIONS .............................. 49
FIGURE 5-3: PERCENTAGE CONTRIBUTION OF FINDINGS MADE TO THE EA CONDITIONS PER SECTION ..... 50
FIGURE 5-4: OVERALL PERCENTAGE FINDINGS ON COMPLIANCE TO THE EA CONDITIONS ................ 50
FIGURE 5-5: NUMBER/COUNT CONTRIBUTION OF FINDINGS MADE TO THE EMPR CONDITIONS PER SECTION ..... 52
FIGURE 5-6: OVERALL COUNT FINDINGS ON COMPLIANCE TO THE EMPR CONDITIONS .............................. 52
FIGURE 5-7: PERCENTAGE CONTRIBUTION OF FINDINGS MADE TO THE EMPR CONDITIONS PER SECTION ..................................... 53
FIGURE 5-8: OVERALL PERCENTAGE FINDINGS ON COMPLIANCE TO THE EMPR CONDITIONS........... 53
ENVIRONMENTAL AUTHORISATION AND ENVIRONMENTAL MANAGEMENT PROGRAMME COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL SYNFUELS OPERATIONS: WATER AND ASH
WSP June 2019
APPENDICES
A ENVIRONMENTAL AUTHORISATION (17/2/2/1(E) MP-
04)
ENVIRONMENTAL AUTHORISATION AND ENVIRONMENTAL MANAGEMENT PROGRAMME COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL SYNFUELS OPERATIONS: WATER AND ASH
WSP June 2019
Page 1
1 INTRODUCTION
1.1 TERMS OF REFERENCE
Sasol South Africa (Pty) Limited operating through its Secunda Synfuels Operations (Sasol) appointed WSP
Environmental (Pty) Ltd (WSP) as an independent environmental consultant, to undertake a compliance audit and
compile an audit report according to the requirements of the National Environmental Management Act (No. 107
of 1998) as amended (NEMA). This report presents the findings of the compliance audit completed for the
Environmental Authorisation (EA) (Reference number: 17/2/2/1(e) MP-04 issued on 16 September 2008) as well
as the associated Environmental Management Plan (dated: August 2008) for the period December 2014 to
February 2019.
1.2 WATER RECOVERY GROWTH PROJECT
(AUTHORISATION NUMBER: 17/2/2/1(E) MP-04)
The Synthol process produces reaction water as a by-product which contains volatile fatty acids (VFAs) as the
major organic pollutant, with acetic acid being the major portion. The chemical oxygen demand (COD), which is
the measure of the amount of oxygen required to oxidise the hydrocarbons to carbon dioxide and water is used to
characterise the organic content. The COD level in the reaction water ranges between approximately 12 000 and
18 000 mg/l.
The Water Recovery Growth (WRG) Plant (Unit 352) was designed to operate at a constant average daily COD
load and is able to handle short term spikes resulting from variations in COD concentration. Consequently, Unit
352 is fed at a constant COD loading and the reaction water feed rate is adjusted either according to the average
daily COD analysis or the online Total Organic Carbon (TOC) measurement.
The major processing steps include:
— Anaerobic digestion by means of Anaerobic digesters (ADs);
— AD effluent upgrading by means of activated sludge Aerobic reactors;
— Solid / liquid separation by means of a settling.
The plant is not yet running at full capacity because it only came into operation in November 2014. The design
COD feed rate is 200.4 tons per day with the Organic Loading Rate (OLR) 12kg COD/m3/day. Currently the plant
operates at an OLR of 4kg COD/m3/day and it is expected to be on full load by December 2018. The process flow
described above is shown in Figure 1-1 below.
Figure 1-1: WRG Process Flow
ENVIRONMENTAL AUTHORISATION AND ENVIRONMENTAL MANAGEMENT PROGRAMME COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL SYNFUELS OPERATIONS: WATER AND ASH
WSP June 2019
Page 2
The reaction water received from the Synfuels operation is treated with a Hydraulic Retention Time (HRT) of 15-
20 minutes. The treated water is routed to Water Recovery from where it can be sent back to the factory for use
as utility water or stored in the Process Water dam system until such time that it is needed. The treated water is
also utilised for cooling water makeup, urea make-up and supply to the desludging compressor at WRG. The
sludge that is generated by the process is sent to the incinerators at Water Recovery.
All stormwater runoff from areas of the WRG plant where no pollution is expected drains directly to the
environment. The water is routed via a canal to the south of the WRG site from where it drains to the
Bossiespruit.
Runoff from contaminated areas drains to a sump, from where the water is pumped back into the process
circuit of WRG.
There is a risk for the sump which collects the runoff from the potentially contaminated areas of WRG to overflow
during high rainfall events resulting in the release of the potentially contaminated water to the environment. The
sump level is monitored regularly and maintained as low as possible to prevent potential overflows. Sampling is
also undertaken to monitor the quality of the water contained within the sump. These aspects have been captured
in the Standard Operating Procedure (SOP), which has been developed for the plant.
The WRG facility location on the Synfuels facility is indicated in Figure 1-2 below.
ENVIRONMENTAL AUTHORISATION AND ENVIRONMENTAL MANAGEMENT PROGRAMME COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL SYNFUELS OPERATIONS: WATER AND ASH
WSP June 2019
Page 3
Figure 1-2: Water Recovery Growth Plant (Source: Google Earth, 2018)
ENVIRONMENTAL AUTHORISATION AND ENVIRONMENTAL MANAGEMENT PROGRAMME COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL SYNFUELS OPERATIONS: WATER AND ASH
WSP June 2019
Page 4
2 AUDIT SCOPE The 7 April 2017 amendment to the Environmental Impact Assessment (EIA) regulations introduced the
requirement for the auditing for all EAs and EMPrs in effect on 8 December 2014 and submission of audit reports
to the Department of Environmental Affairs (DEA) by 7 December 2019 and every five years thereafter. This
audit is designed to meet the requirements of Regulation 34 of the EIA Regulations, 2014.
The Audit period runs from December 2014 to February 2019, therefore any construction related conditions that
would have been relevant pre-December 2014 are considered not applicable (outside audit period).
The objective of the audit was to:
— Assess the level of compliance with the conditions of the EA, EMPr;
— Assess the extent to which the avoidance, management and mitigation measures provided for in the EMPr,
achieve the objectives and outcomes laid out in these documents;
— Identify and assess any new impacts and risks that result from undertaking the activity;
— Critically evaluate the effectiveness of the EMPr;
— Identify shortcomings in the EMPr;
— Identify the need for any changes to the avoidance, management and mitigation measures provided for in the
EMPr; and
— Make recommendations in order to achieve compliance in terms of the EA and EMPr.
ENVIRONMENTAL AUTHORISATION AND ENVIRONMENTAL MANAGEMENT PROGRAMME COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL SYNFUELS OPERATIONS: WATER AND ASH
WSP June 2019
Page 5
3 AUDIT METHODOLOGY The International Organisation of Standardisation (ISO) 14010, ISO 14011 and ISO 14012 guideline documents
were utilised as a template during the compliance audit process. This methodology ensures that the compliance
audit was conducted in a systematic and independent manner that was documented and objectively evaluated to
determine compliance to the EA and associated EMPr conditions.
The audit process comprised the following:
— Confirmation of the audit checklist;
— Site inspection (27 March 2019);
— Review of documentation relevant to the conditions of the EA and associated EMPr (e.g. records,
permits/certificates/maintenance logs/monitoring results/previous reports etc.); and
— Compilation of an audit report.
3.1 AUDIT CHECKLIST
WSP compiled an audit checklist to assist with the EA and EMPr compliance audit (Section 4).
3.2 SITE INSPECTION
Tutayi Chifadza conducted the site inspection on 27 March 2019. The findings and observations of the site visit
are recorded and summarised in Section 4 with evidence included in Table 2 and Table 3. Key personnel
interviewed included:
— Brendan Govender (Area Manager: Water Recovery).
3.3 DOCUMENTATION CONSIDERED
The following documentation was provided and considered:
— EMP_17.2.2.1(e) MP-04_Water Recovery-Amend_2013-03-15;
— Environment Impact register_ New FY19_2019-02-18;
— Environment emergency procedure_SGR-SHE000023_rev6_2015-11;
— 3.21_EA_Emergency Procedure WRG;
— Waste Management Procedure for Sasol Secunda (SGR-SHE000017);
— Environmental Complaints Register (2008-2019);
— EA_EX Handover_SSO_WA-Process Water;
— EA_EX Handover_SSO_WA-Process Water_Amend VP
— 3.19_EA_SAS-579A WRG SOP rev 0 (3) July 2018;
— AEL Sasol Synfuels 0016-2018-F03 (2018);
— IWWMP SIC 2015 Final_2018-05-15;
— SIC IWWMP Appendix 1 - WRG 2017 Rev 1;
— Phase 1_Contaminated Land Assessment_November_2015_Final 1.0;
— Secunda Contaminated Land Phase 2 Report_Final v1 part 1 of 2_2018-08-28;
— GWMonitor Report May 2018 Final_Prj6164rev-01_2018-11-20;
— EA Name Change applications_Transmittal_2017-03-29_signed;
— SGI-SHE-000014 rev 6 - Minimum requirements for ERA_Published;
— Induction_Mod4_ProcessSafetyManagement;
ENVIRONMENTAL AUTHORISATION AND ENVIRONMENTAL MANAGEMENT PROGRAMME COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL SYNFUELS OPERATIONS: WATER AND ASH
WSP June 2019
Page 6
— Induction_Mod5_WorkPlaceSafety;
— Induction_Mod7_Occupational;
— SSO_BSOHSAS18001_IQNet_2018-08-24;
— Site photos; and
— Various email correspondence.
3.4 AUDIT COMPLIANCE ASSESSMENT
WSP utilised a pre-prepared audit checklist to assist with the audit execution (Table 2 and Table 3). The checklist
included the conditions and associated requirements as specified in the EA and associated EMPr.
Each condition was verified, either by reviewing documentation, interviewing employees and/or visually
inspecting the facility. Each condition was rated in accordance with Table 1 below, and recommendations with
associated target completion dates included.
It should be noted that some of the EA and associated EMPr conditions were apportioned according to the elements
requiring compliance assessment therein. Although some elements of the condition may have been compliant, if
one of the elements was determined to be non-compliant, the entire condition has been reported as such (and
counted as such during percentage compliance calculation). This apportionment further allowed for the
development of focussed recommendations and timeframes.
Table 1: Compliance Level Definition and Target Completion Dates
COMPLIANCE LEVEL DEFINITION
Compliant (C) Sasol could provide evidence for compliance with the commitment and condition and/or
relevant actions were implemented.
Non-compliant (NC) Specified commitments, conditions and documents were not in place or implemented according
to the requirements of the EA and associated EMPr. Non-complaint conditions are given target
completion dates, as follows:
— Short term: 0 – 6 months.
— Medium term: 6 – 12 months.
— Long term: 12 – 18 months.
Not applicable (N/A) These are commitments are either not required yet or not applicable to Sasol.
— Conditions marked as “Noted” are considered information points only.
— Where conditions are considered “not auditable” within the scope of this assessment this
is stated and explained within the condition commentary.
Refer to Section 4 for the detailed audit findings (including evidence, recommendations and target completion
dates).
3.5 AUDIT TEAM
The Auditor, Tutayi Chifadza, was hosted by Broni van der Meer and Brendan Govender to whom we express
our gratitude for their time and attention during our visit. A brief summary of the external auditors’ experience is
provided below.
— Auditor: Tutayi Chifadza
Tutayi Chifadza has 5 years’ experience and is an Environmental Consultant for WSP at the Johannesburg,
Bryanston office in the Environmental Services division. He holds a Bachelor of Science (Honours), Applied
Science in Environmental Technology, and Bachelor of Science, Chemistry from the University of Pretoria.
Tutayi has experience in undertaking Water Use Licence (WUL) applications, Basic Assessments and
ENVIRONMENTAL AUTHORISATION AND ENVIRONMENTAL MANAGEMENT PROGRAMME COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL SYNFUELS OPERATIONS: WATER AND ASH
WSP June 2019
Page 7
Environmental Impact Assessments as well as technical compliance audits including for Transnet and Sasol.
He conducted Water Use Licence audits for four sections at South 32 and its reporting. He is also responsible
for conducting WUL And Waste Management Licence audits.
— Lead Auditor and Quality Assurance: Ashlea Strong
Ashlea has 16 years’ experience and holds a Masters in Environmental Management; a BTech (Nature
Conservation), and a National Diploma (Nature Conservation); She is also a Certified Environmental
Assessment Practitioner of South Africa (CEAPSA). She currently provides technical and strategic expertise
on a diverse range of projects in the environmental management field, including environmental scoping and
impact assessment studies, environmental management plans, waste and water management, as well as the
provision of environmental management solutions and mitigation measures. She has been involved in the
management of a number of large EIAs within South Africa and has environmental auditing and training
experience and expertise. Ashlea has carried out over 50 compliance audits and is well versed in the audit
process.
— Project Manager and Quality Assurance: Jenny Cope
Jenny is an environmental due diligence specialist, with over 11 years’ experience in the Environmental
Sector. Jenny’s experience includes managing and completing projects and portfolios internationally;
undertaking both detailed and broad Environmental, Health & Safety compliance and audits of across a range
of sectors. Jenny’s recent experience includes completion and management of several pan-European and
global projects requiring reviews of extensive virtual data rooms, on a very rapid turnaround, and providing
clients with ‘red flag’ reports to give clear commercial advice. Jenny has worked both in environmental
consultancies and with a developer, giving context to understanding the practicalities of implementing
recommendations.
3.6 ASSUMPTIONS AND LIMITATIONS
This Report has been prepared by WSP on behalf and at the request of Sasol, to provide the Client an
understanding of the Relevant Documents.
Unless otherwise agreed by us in writing, we do not accept responsibility or legal liability to any person other than
the Client for the contents of, or any omissions from, this Report.
To prepare this Report, we have reviewed only the documents and information provided to us by the Client or any
third parties directed to provide information and documents to us by the Client. We have not reviewed any other
documents in relation to this Report and except where otherwise indicated in the Report.
The findings, recommendations and conclusions given in this report are based on the author’s best scientific and
professional knowledge, as well as available information. This report is based on survey and assessment
techniques which are limited by time and budgetary constraints relevant to the type and level of investigation
undertaken; WSP and its staff reserve the right to modify aspects of the report including the recommendations if
and when new information may become available from on-going research or further work in this field, or
pertaining to this investigation.
Although WSP exercises due care and diligence in rendering services and preparing documents, WSP accepts no
liability, and Sasol, by receiving this document, indemnifies WSP and its directors, managers, agents and
employees against all actions, claims, demands, losses, liabilities, costs, damages and expenses arising from or in
connection with the services rendered, directly or indirectly by the use of the information contained in this
document.
This report must not be altered or added to without the prior written consent of the author. This also refers to
electronic copies of this report which are supplied for the purposes of inclusion as part of other reports. Similarly,
any recommendations, statements or conclusions drawn from or based on this report must make reference to this
report. If this report is used as part of a main report, the report in its entirety must be included as an appendix or
separate section to the main report.
ENVIRONMENTAL AUTHORISATION AND ENVIRONMENTAL MANAGEMENT PROGRAMME COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL SYNFUELS OPERATIONS: WATER AND ASH
WSP June 2019
Page 8
4 AUDIT FINDINGS Table 2: Audit Findings – Environmental Authorisation
REF: COMMITMENT COMPLIANCE FINDING RECOMMENDATION
SCOPE OF AUTHORISATION
3.1 Authorisation of the activity is subject to the conditions
contained in this authorisation that are part of the
environmental authorisation and are legally binding on the
holder of the authorisation.
N/A Noted. None
3.2 The activity which is authorised may only be carried out at the
property indicated above. C The EA authorised the construction of the WRG facility at
coordinates 26°32’58”S, 29°08’40”E. these were verified during the
site visit and as shown below.
Evidence:
WRG location
None
ENVIRONMENTAL AUTHORISATION AND ENVIRONMENTAL MANAGEMENT PROGRAMME COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL SYNFUELS OPERATIONS: WATER AND ASH
WSP June 2019
Page 9
REF: COMMITMENT COMPLIANCE FINDING RECOMMENDATION
3.3 The holder of the authorisation must ensure compliance with
the conditions by any person acting on his or her behalf,
including but not limited to, an agent, sub-contractor,
employee or person rendering a service to the holder of the
authorisation.
C All site personnel that work on the WRG project undergo Safety,
Health and Environment (SHE) induction to ensure that they are
familiar with the site’s SHE aspects and requirements. All of Sasol’s
training is done through the regional SHE learning and development
academy in order to help gain compliance.
There is no requirement within the licence to audit against it
regularly both internally and externally, as such, any audits other
than the post-construction audit are from a best practice perspective.
No non-compliances were observed over the course of this audit.
None
3.4 Any changes to, or deviations from, the project description set
out in this authorisation must be approved, in writing, by the
Department before such changes or deviations may be
effected. In assessing whether to grant such approval or not,
the Department may request such information as it deems
necessary to evaluate the significance and impacts of such
changes or deviations and it may be necessary for the holder
of the authorisation to apply for further authorisation in terms
of the regulations.
C Following Sasol’s proposal to amend the EA, the Department
granted the amendment application in order to remove Section 7.7
of the EMPr (“Flaring only to be used during emergencies and start-
up conditions”) and allow for the continuous flaring on the site
based on the motivation provided by Sasol. The amendment was
granted on 15 March 2013 and the proof was available for review.
Evidence:
— EMP_17.2.2.1(e) MP-04_Water Recovery-Amend_2013-03-
15
None
3.5 This activity must commence within a period of two (2) years
from the date of issue. If commencement of the activity does
not occur within that period, the authorisation lapses and a
new application for environmental authorisation must be
made in order for the activity to be undertaken.
N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None
3.6 This authorisation does not negate the holder of the
authorisation, responsibility to comply with any other
statutory requirements that may be applicable to the
undertaking of the activity.
N/A Noted. None
ENVIRONMENTAL AUTHORISATION AND ENVIRONMENTAL MANAGEMENT PROGRAMME COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL SYNFUELS OPERATIONS: WATER AND ASH
WSP June 2019
Page 10
REF: COMMITMENT COMPLIANCE FINDING RECOMMENDATION
APPEAL OF AUTHORISATION
3.7 The holder of the authorisation must notify every registered
interested and affected party, in writing and within seven (7)
calendar days, of receiving of the Department’s decision to
authorise the activity.
N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None
3.8 The notification referred to in 3.7 must:
a) Specify the date on which the authorisation was issued; N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None
b) Inform the interested and affected parties of the appeal
procedure provided for in Chapter 7 of the regulations;
and
N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None
c) Advise the interested and affected parties that a copy of
the authorisation and reasons for the decision will be
furnished on request.
N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None
MANAGEMENT AND MONITORING OF THE ACTIVITY
3.9 Compile a monitoring programme to ensure conformance
with the conditions contained in this Environmental
Management Plan.
C The auditor was informed that all conditions of the EMPr are loaded
on the SAP system and tasks assigned as required in order to ensure
conformance with the conditions. Reports can then be loaded from
the system as and when required.
Evidence:
— EMP_17.2.2.1(e) MP-04_Water Recovery-Amend_2013-03-
15
None
ENVIRONMENTAL AUTHORISATION AND ENVIRONMENTAL MANAGEMENT PROGRAMME COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL SYNFUELS OPERATIONS: WATER AND ASH
WSP June 2019
Page 11
REF: COMMITMENT COMPLIANCE FINDING RECOMMENDATION
3.10 The Department retains the right to monitor and/or inspect the
proposed project during both construction and operational
phases.
C The auditor was informed that the Department conducts site visits
but no feedback has been provided following the visits. The
assumption is that since there are no findings during the site walks,
and therefore there is no need for the Department to make further
contact on the site.
Evidence:
— Personnel Communication
None
COMMISSIONING AND OPERATION OF THE ACTIVITY
3.11 Fourteen (14) days written notice must be given to the
Department that the activity will commence. Commencement
for the purposes of this condition includes site preparation.
The notice must include a date on which it is anticipated that
the activity will commence.
N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None
3.12 Before construction commences, the applicant must assign the
activity to a full time Environmental Control Officer who will
ensure:
N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None
3.12.1 Strict compliance of the activity with the conditions of the
Environmental Authorisation as well as the measures
contained in the Environmental Management Plan.
N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
For the operational phase, compliance with the EA and EMPr is
covered under Condition 3.3.
None
3.12.2 Ensure that the contractors on site are aware of their
requirements in terms of the requirements of the
environmental authorisation and the Environmental
Management Plan (EMP).
C All site personnel that work on the WRG undergo SHE induction to
ensure that they are familiar with the site’s SHE aspects and
requirements. All of Sasol’s training is completed through the
regional SHE learning and development academy. The induction
presentation was available for review. During induction, contractors
are made aware of the EMPr requirements for the specific site.
None
ENVIRONMENTAL AUTHORISATION AND ENVIRONMENTAL MANAGEMENT PROGRAMME COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL SYNFUELS OPERATIONS: WATER AND ASH
WSP June 2019
Page 12
REF: COMMITMENT COMPLIANCE FINDING RECOMMENDATION
3.12.3 Monitor compliance during construction and operation of the
activity; C Sasol has an environmental team that manages the site according to
the legislative requirements and ensure EA compliance. Due to the
vast number of operations on the Synfuels facility, there is no one
officer assigned to a particular site. The Sasol environmental team
works together to ensure compliance on the WRG facility.
Furthermore, the auditor was informed that all conditions of the
EMPr are loaded on the SAP system and tasks assigned as required
in order to ensure conformance with the conditions. Reports can
then be loaded from the system as and when required since there is
no strict auditing requirement against the EA conditions.
None
3.12.4 Keep record of all environmental audits; N/A This audit represents the first required audit for this EA. Prior to the
introduction of the 7 April 2017 amendment to the Environmental
Impact Assessment (EIA) regulations, no audit against this EA was
required.
OFI:
This current Audit must be
kept on record as required.
Target Completion:
Short Term
3.12.5 Ensure implementation of contingency plans in the event of
unforeseen circumstances. C Sasol have an environment emergency procedure (SGR-
SHE000023) that covers different scenarios on the site as well as an
environmental incident procedure process flow that indicates steps
taken when an incident occurs. Furthermore, the
WRG has its own specific emergency procedure that was available
for review.
No incidents were noted regarding the facility when the incidents
register was reviewed that needed the site personnel to implement
contingency plans. An incident procedure is available for
implementation in the event of an incident. Furthermore, the
WRG has its own specific emergency procedure that was available
for review.
Evidence:
— Environment Impact register_ New FY19_2019-02-18
None
ENVIRONMENTAL AUTHORISATION AND ENVIRONMENTAL MANAGEMENT PROGRAMME COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL SYNFUELS OPERATIONS: WATER AND ASH
WSP June 2019
Page 13
REF: COMMITMENT COMPLIANCE FINDING RECOMMENDATION
— Environment emergency procedure_SGR-
SHE000023_rev6_2015-11
— 3.21_EA_Emergency Procedure WRG
3.13 The construction area must be clearly demarcated on the site
plan. N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None
3.14 Waste must be separated into different categories and be
placed in separate waste containers before disposal. C All waste on the site is managed according to the waste management
procedure (SGR-SHE000017) for the waste generated on the site
following a waste management hierarchy. Waste is disposed of at
registered landfill sites.
Waste was observed to be appropriately stored during the site walk.
Evidence:
— Waste Management Procedure for Sasol Secunda (SGR-
SHE000017)
None
3.15 All petroleum products must be kept in properly bunded areas.
The fuels must be stored at a designated storage facility
outside the construction site.
N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None
3.16 Rocks and other materials from the excavation process must
be disposed of in a manner that does not impact negatively on
aesthetic of the environment.
N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None
3.17 Adequate measures must be put in place to control surface
water flows across and around all construction sites. N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None
3.18 The applicant must ensure that storm water leaving the
footprint of the proposed development is not contaminated by
any substance, whether liquid, solid, etc.
C The site is completely concreted, with stormwater channels that lead
to the out-sump. This water is then channelled back to the system to
be reworked. Furthermore, all the tanks with reagents used in the
process are bunded and contained to help prevent any flow of
contaminated stormwater to the surrounding environment. The
sumps which collect contaminated water are monitored for both the
None
ENVIRONMENTAL AUTHORISATION AND ENVIRONMENTAL MANAGEMENT PROGRAMME COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL SYNFUELS OPERATIONS: WATER AND ASH
WSP June 2019
Page 14
REF: COMMITMENT COMPLIANCE FINDING RECOMMENDATION
quality and level so as to prevent an overflow into the surrounding
environment.
Sasol monitors both surface and groundwater to ensure there is no
contamination. Surface water and the borehole monitoring points
are indicated in the IWWMP. Two of the monitoring boreholes
adjacent to this site (REGM-128 and REGM-129) with groundwater
considered to be within quality requirements, with no actions
required and no exceedances observed.
Evidence:
— IWWMP SIC 2015 Final_2018-05-15
— GWMonitor Report May 2018 Final_Prj6164rev-01_2018-11-
20
Concreted surface and bunded tanks
3.19 The flaring system to be utilised must ensure that there is no
flaring visible or audible to the surrounding communities. C Sasol uses enclosed or ground based flares rather than elevated
flares. The flares used reduce noise, luminosity and heat radiation.
Furthermore, the system used provides wind protection and
effective emission monitoring.
None
ENVIRONMENTAL AUTHORISATION AND ENVIRONMENTAL MANAGEMENT PROGRAMME COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL SYNFUELS OPERATIONS: WATER AND ASH
WSP June 2019
Page 15
REF: COMMITMENT COMPLIANCE FINDING RECOMMENDATION
The complaints register was reviewed and there were no complaints
regarding the flaring system related to this EA.
Evidence:
— Environmental Complaints Register (2008-2019)
3.20 The necessary air permit must be obtained prior to
commencement of this activity. C The sludge produced in the process is sent to the two incinerators on
the site. This was as confirmed in the SOP. The use of the site
biosludge incinerators is licensed in the AEL (under subcategory 8.1
- thermal treatment of general and hazardous waste), which was
provided for review.
Evidence:
— 3.19_EA_SAS-579A WRG SOP rev 0 (3) July 2018
— AEL Sasol Synfuels 0016-2018-F03 (2018)
None
3.21 An Emergency/ Contingency Plan must be developed before
commissioning of the activity. Such a plan must among others
address safety, fire hazards, etc.
C Sasol have an environment emergency procedure (SGR-
SHE000023) that covers different scenarios on the site as well as an
environmental incident procedure process flow that indicates steps
taken when an incident occurs. Furthermore, the
WRG has its own specific emergency procedure that was available
for review.
Evidence:
— Environmental emergency procedure (Rev 6): SGR-
SHE000023
— 3.21_EA_Emergency Procedure WRG
None
3.22 The Applicant must implement appropriate measures to
reduce or prevent contamination of ground and surface water
as a result of spills of potentially dangerous substances.
C The site is completely concreted, with stormwater channels that lead
to the out-sump. This water is then channelled back to the system to
be reworked. Furthermore, all the tanks with reagents used in the
process are bunded and contained to help prevent any flow of
contaminated stormwater to the surrounding environment. The
sumps which collect contaminated water are monitored for both the
quality and level so as to prevent an overflow into the surrounding
environment.
None
ENVIRONMENTAL AUTHORISATION AND ENVIRONMENTAL MANAGEMENT PROGRAMME COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL SYNFUELS OPERATIONS: WATER AND ASH
WSP June 2019
Page 16
REF: COMMITMENT COMPLIANCE FINDING RECOMMENDATION
Sasol monitors both surface and groundwater to ensure there is no
contamination. Surface water and the borehole monitoring points
are indicated in the IWWMP. Two of the monitoring boreholes
adjacent to this site (REGM-128 and REGM-129) with groundwater
considered to be within quality requirements, with no actions
required and no exceedances observed.
Evidence:
— IWWMP SIC 2015 Final_2018-05-15
— GWMonitor Report May 2018 Final_Prj6164rev-01_2018-11-
20
3.23 The applicant must comply with Major Hazard Installation
Regulation (regulation 5(5) of the Occupation Health and
Safety Act (Act No. 85 of 1993).
N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None
3.24 All vehicles, equipment and machinery must be maintained in
good condition such that they do not leak oil and any other
petroleum products onto the soil.
C The site is mainly unmanned and operated from the control room.
Consequently, there is little to no traffic movement on the site for
the most part as the process is mainly automated. The site is
concreted and there were no signs of leaks observed during the site
walk therefore, indicating little to no risk of soil contamination.
Evidence:
None
ENVIRONMENTAL AUTHORISATION AND ENVIRONMENTAL MANAGEMENT PROGRAMME COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL SYNFUELS OPERATIONS: WATER AND ASH
WSP June 2019
Page 17
REF: COMMITMENT COMPLIANCE FINDING RECOMMENDATION
Impermeable surface
3.25 All waste (general and hazardous) generated during
construction of the plant must be disposed of at an appropriate
licensed waste disposal sites.
N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None
3.26 Any complaints received from the public during construction
and operational phases of the activity must be attended to as
soon as possible and addressed to the satisfaction of all
concerned.
C The complaints register was reviewed and there were no complaints
regarding the flaring system related to this EA. Sasol provides
feedback on all complaints as observed in the complaints register.
Evidence:
— Environmental Complaints Register (2008-2019)
None
ENVIRONMENTAL AUTHORISATION AND ENVIRONMENTAL MANAGEMENT PROGRAMME COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL SYNFUELS OPERATIONS: WATER AND ASH
WSP June 2019
Page 18
REF: COMMITMENT COMPLIANCE FINDING RECOMMENDATION
GENERAL
3.27 A copy of this authorisation must be kept at the property
where the activities will be undertaken. The authorisation
must be produced to any authorised official of the Department
who requests to see it and must be available for inspection by
any employee or agent of the holder of the authorisation who
works or undertakes work at the property.
C Sasol keeps all authorisations and permits at the SHE department on
the SAP system and on SharePoint and are available upon request.
All environmental aspects are shared to site personnel during
induction. Sasol provided the auditor with the evidence that the
responsible persons, Rakesh Durjan (Senior Manager of Process
Water Area) and Simon Baloyi (legal appointee of Water & Ash),
were made aware of the EA on in September / October 2016.
Evidence:
— EA_EX Handover_SSO_WA-Process Water;
— EA_EX Handover_SSO_WA-Process Water_Amend VP
None
3.28 Where any of the applicant’s contact details change, including
the name of the responsible person, the physical or postal
address and / or telephonic details; the applicant must notify
the Department as soon as the new details become known to
the applicant.
C A name change application was lodged on 29 March 2017 from
Sasol Synfuels (Pty) ltd to Sasol South Africa (Pty) Limited. This
was captured in the amended EA issued in March 2016.
Evidence:
— EA Name Change applications_Transmittal_2017-03-
29_signed
None
3.29 The holder of the authorisation must notify the Department,
in writing and within 24 (twenty-four) hours, if conditions of
this authorisation are not adhered to. Any notification in terms
of this condition must be accompanied by reasons for the non-
compliance
C No non-compliances were observed over the course of this audit. None
3.30 Non-compliance with a condition of this authorisation may
result in criminal prosecution or other actions provided for in
the National Environmental Management Act, 1998 and the
regulations.
N/A Noted. None
ENVIRONMENTAL AUTHORISATION AND ENVIRONMENTAL MANAGEMENT PROGRAMME COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL SYNFUELS OPERATIONS: WATER AND ASH
WSP June 2019
Page 19
Table 3: Audit Findings – Environmental Management Plan
REF: COMMITMENT COMPLIANCE FINDING RECOMMENDATION
4 CONSTRUCTION PHASE
4.1 EMPLOYMENT, AWARENESS AND SKILLS DEVELOPMENT
Appointment of contractor, temporary labour
4.1.1 Local labour and contractors must be used wherever possible. N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None
4.1.2 Basic skills development and capacity building must be
incorporated. N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None
4.1.3 Sasol must ensure that this EMP forms part of any contractual
agreements with a Contractor(s) and sub-contractors for the
execution of the proposed project.
N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None
4.1.4 Sasol and the Contractor must comply with the relevant
provisions of the EMP, environmental authorisation, by-laws,
applicable environmental legislation and associated
regulations promulgated in terms of these laws.
N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None
4.1.5 Construction staff must be adequately educated by the Sasol
Technology EIA Specialist or the Project Manager as to the
provisions included in the EMP and general environmentally
friendly practice.
N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None
ENVIRONMENTAL AUTHORISATION AND ENVIRONMENTAL MANAGEMENT PROGRAMME COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL SYNFUELS OPERATIONS: WATER AND ASH
WSP June 2019
Page 20
REF: COMMITMENT COMPLIANCE FINDING RECOMMENDATION
4.2 SITE ESTABLISHMENT AND MANAGEMENT (CONSTRUCTION CAMP)
Site Establishment
4.2.1 The site selected for the construction camp should ensure
potential environmental impacts are kept to a minimum. N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None
4.2.2 The construction area must be clearly demarcated on a site
plan, and all other areas must be considered no-go areas for
the construction personnel.
N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None
4.2.3 Only designated areas may be used for the storage of
construction material, topsoil, machinery, equipment and
establishment of site offices.
N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None
4.2.4 The following activities must be prohibited at site camp(s),
and by the construction staff in general: N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None
4.2.4.1 The irresponsible use of welding equipment, oxy-acetylene
torches and other naked flames which could result in fires or
constitute a hazard.
N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None
4.2.4.2 Burning of any type of waste material. N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None
4.2.4.3 The use of rivers, streams, dams or any watercourses/surface
water for washing or recreational purposes. N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None
4.2.4.4 Entering areas outside of the demarcated construction area
without relevant permissions. N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None
ENVIRONMENTAL AUTHORISATION AND ENVIRONMENTAL MANAGEMENT PROGRAMME COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL SYNFUELS OPERATIONS: WATER AND ASH
WSP June 2019
Page 21
REF: COMMITMENT COMPLIANCE FINDING RECOMMENDATION
Personal Protective Equipment (PPE)
4.2.5 No person is allowed to enter the site without Sasol Business
Unit (SBU) approved (SANS approved) PPE. N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None
4.2.6 Strict non-compliance measures must be administered to any
employees not complying with the use of PPE. N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None
4.2.7 The contractor must ensure that the company logo is displayed
and company personnel re easily identifiable. N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None
4.2.8 PPE minimum requirement notice boards shall be placed at
the entrance to the construction site. N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None
Generation and indiscriminate disposal of domestic waste
4.2.9 All construction waste will be placed in provided waste bins. N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None
4.2.10 Waste will be separated into different types and placed into
separate waste containers. N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None
4.2.11 The Contractor should ensure that sewerage waste is routed
accordingly and does not drain into the nearby stormwater
system.
N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None
Spillage of petroleum products
4.2.12 All diesel generators will be equipped with drip trays. N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None
ENVIRONMENTAL AUTHORISATION AND ENVIRONMENTAL MANAGEMENT PROGRAMME COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL SYNFUELS OPERATIONS: WATER AND ASH
WSP June 2019
Page 22
REF: COMMITMENT COMPLIANCE FINDING RECOMMENDATION
4.2.13 All petroleum products will be kept in a properly bunded area. N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None
4.2.14 Refuelling of machinery/vehicles will take place in a properly
bunded area. N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None
4.2.15 Contaminated soil will be properly removed and sent to the
Waste Recycling Facility (WRF). N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None
Sanitation
4.2.16 Use of any ablution facility other than those provided is
strictly prohibited. N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None
4.2.17 Contractor will be responsible for providing and maintaining
own toilet facilities. N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None
4.3 SITE CLEARING
Erosion
4.3.1 Areas susceptible to erosion should be protected by installing
the necessary temporary and/or permanent drainage works as
soon as possible and by taking other measures necessary to
prevent surface water from being concentrated in streams and
from scouring slopes, banks or other areas.
N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None
4.3.2 Any runnels or erosion channels developed during the
construction period shall be backfilled and compacted, and the
areas restored to an acceptable condition.
N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None
ENVIRONMENTAL AUTHORISATION AND ENVIRONMENTAL MANAGEMENT PROGRAMME COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL SYNFUELS OPERATIONS: WATER AND ASH
WSP June 2019
Page 23
REF: COMMITMENT COMPLIANCE FINDING RECOMMENDATION
4.3.3 Blocking of stormwater drainage systems must be prevented
and stormwater must be managed to prevent soil erosion. N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None
Existing Earth Dams (two)
4.3.7 Concrete slabs will be demolished and disposed off at a
regular disposal site approved by Sasol. N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None
4.3.8 After demolition of the slabs, mass excavations (~3m) and
backfilling (ash/dolerite) shall take place over the entire plot
space to provide a terraced plot. It might be possible that some
piling of heavy equipment may occur.
N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None
4.4 PLANT CONSTRUCTION
Calibration of monitoring equipment
4.4.1 Calibration of equipment will be done as required. N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None
Domestic waste
4.4.2 All construction waste to be disposed off in waste bins
provided. Waste will be separated into different types and
placed in separated waste containers.
N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None
Grinding
4.4.3 All construction waste to be disposed off in waste bins
provided. Waste will be separated into different types and
placed in separated waste containers.
N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None
ENVIRONMENTAL AUTHORISATION AND ENVIRONMENTAL MANAGEMENT PROGRAMME COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL SYNFUELS OPERATIONS: WATER AND ASH
WSP June 2019
Page 24
REF: COMMITMENT COMPLIANCE FINDING RECOMMENDATION
Insulation material
4.4.4 All construction waste to be disposed off in waste bins
provided. Waste will be separated into different types and
placed in separated waste containers.
N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None
Mixing of concrete
4.4.5 All construction waste to be disposed off in waste bins
provided and disposed off according to the Sasol Waste
Management Procedure (Document still in draft format -
SGR-GEN-000002).
N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None
Other waste
4.4.6 All construction waste to be disposed off in waste bins
provided. Waste will be separated into different types and
placed in separated waste containers.
N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None
Packaging material
4.4.7 All construction waste to be disposed off in waste bins
provided. Waste will be separated into different types and
placed in separated waste containers.
N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None
Painting
4.4.8 Potential spillages:
— All paints will be kept in a well bunded area.
— Soil contaminated by paint will be removed and sent to
the WRF.
N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None
ENVIRONMENTAL AUTHORISATION AND ENVIRONMENTAL MANAGEMENT PROGRAMME COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL SYNFUELS OPERATIONS: WATER AND ASH
WSP June 2019
Page 25
REF: COMMITMENT COMPLIANCE FINDING RECOMMENDATION
4.4.9 Paint cans left on site:
— All construction waste to be disposed off in waste bins
provided.
N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None
Storage of cement/grease, oils, paints and chemicals
4.4.10 All products that have a potential of contaminating the soil
will be kept in a well protected/bunded area. N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None
Welding
4.4.11 All construction waste to be disposed off in waste bins
provided. Waste will be separated into different types and
placed in separated waste containers.
N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None
4.5 SITE PREPARATION ACTIVITIES
Removal of contaminated rainwater from foundations
4.5.1 All contaminated water will be disposed off into the correct
sewer systems. N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None
Use of electricity/diesel generators - Noise
4.5.2 All generators will comply to the noise limit of 85dB.
N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None
ENVIRONMENTAL AUTHORISATION AND ENVIRONMENTAL MANAGEMENT PROGRAMME COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL SYNFUELS OPERATIONS: WATER AND ASH
WSP June 2019
Page 26
REF: COMMITMENT COMPLIANCE FINDING RECOMMENDATION
Use of electricity/diesel generators - smoke
4.5.3 Electricity generators used by the Contractor should be in
good working condition. N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None
Use of electricity/diesel generators - leaks
4.5.4 Electricity generators used by the contractor should be in good
working condition and not leak oil. N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None
4.5.5 All generators will be furnished with drip trays. N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None
4.5.6 In the instance of spillages, clean-up measures should be
executed in order to contain the pollution and remediation
should be carried out.
N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None
Use of construction vehicles/machinery – Borrow pits
4.5.7 Only licenced borrow pits may be used. N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None
Use of construction vehicles/machinery – Spent engine oil
4.5.8 In a case of spillages, contaminated soil will be removed and
disposed off properly. N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None
4.5.9 Clean-up measures must be in place when spillages occur. N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None
ENVIRONMENTAL AUTHORISATION AND ENVIRONMENTAL MANAGEMENT PROGRAMME COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL SYNFUELS OPERATIONS: WATER AND ASH
WSP June 2019
Page 27
REF: COMMITMENT COMPLIANCE FINDING RECOMMENDATION
Use of construction vehicles/machinery – Fuel storage and refuelling leading to spillages
4.5.10 All fuels will be stored at a designated storage facility outside
the construction site and no refuelling will be allowed on site
unless done on a properly bunded area or using a drip tray.
N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None
Use of construction vehicles/machinery – Dust
4.5.11 Dust must be suppressed on access roads and construction
sites during dry periods by the regular application of water.
Water used for this purpose must be used in quantities that
will not result in the generation of run-off.
N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None
4.5.12 Dust dispersion from construction activities, unsurfaced
roads, spoil dumps and other construction locations will be
limited and suppressed to the maximum extent practical.
N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None
4.5.13 Spoil dumps will be positioned such that they are not
vulnerable to wind erosion. N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None
Use of construction vehicles/machinery – Noise
4.5.14 All construction vehicles will comply to the noise limit of
85dB. N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None
Use of construction vehicles/machinery – Excavated material not used for backfill left on site
4.5.15 Rock and other material from the excavation process will be
disposed of in a way that does not have a negative impact on
the aesthetics of the environment and that blends in with the
rehabilitation process.
N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None
ENVIRONMENTAL AUTHORISATION AND ENVIRONMENTAL MANAGEMENT PROGRAMME COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL SYNFUELS OPERATIONS: WATER AND ASH
WSP June 2019
Page 28
REF: COMMITMENT COMPLIANCE FINDING RECOMMENDATION
4.5.16 Any redundant excavated material will be disposed off at
Charlie 1 general waste site. N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None
Use of construction vehicles/machinery – Contaminated excavated material not used for backfill left on site
4.5.17 Contaminated excavated material will be disposed of at the
WRF for treatment. N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None
Use of construction vehicles/machinery – Building rubble left on site
4.5.18 Rock and other material from the excavation process will be
disposed of in a way that does not have a negative impact on
the aesthetics of the environment and that blends in with the
rehabilitation process.
N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None
4.5.19 Any redundant excavated material will be disposed off at
Charlie 1 general waste site. N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None
Use of construction vehicles/machinery – Contaminated building rubble left on site
4.5.20 Contaminated building rubble will be disposed of at the WRF
for treatment. N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None
Removing redundant/contaminated equipment and not disposed of correctly
4.5.21 Redundant equipment will be sent to the reclamation yard. N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None
4.5.22 Contaminated equipment will be cleaned prior to being sent
to the reclamation yard. N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None
ENVIRONMENTAL AUTHORISATION AND ENVIRONMENTAL MANAGEMENT PROGRAMME COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL SYNFUELS OPERATIONS: WATER AND ASH
WSP June 2019
Page 29
REF: COMMITMENT COMPLIANCE FINDING RECOMMENDATION
Backfill with dolerite/ash for foundation
4.5.23 Dolerite will be sourced from licenced sellers. N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None
Backfill with dolerite/ash for foundation purposes & Ash heaps resulting in dust
4.5.24 Dust suppressing measures will be established. N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None
4.6 HYDROLOGY
Stormwater management
4.6.1 Adequate measures will be put into place to control surface
water flows across and around all construction sites. N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None
4.6.2 Ensure that no pollution enters surface water or has the
potential to pollute groundwater by ensuring that there is
containment of spillages and that there is an emergency plan
in place to deal with accidental spillage.
N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None
4.6.3 Ensure that no stormwater is discharged to the working areas
and further ensuring that the stormwater leaving the footprint
of the proposed development areas is not contaminated by any
substance, whether that substance is solid, liquid, vapour or
any combination thereof.
N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None
4.6.4 The quantity of uncontaminated stormwater entering cleared
areas will be minimised by appropriate site design and by
installation of control structures and drains which direct such
N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None
ENVIRONMENTAL AUTHORISATION AND ENVIRONMENTAL MANAGEMENT PROGRAMME COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL SYNFUELS OPERATIONS: WATER AND ASH
WSP June 2019
Page 30
REF: COMMITMENT COMPLIANCE FINDING RECOMMENDATION
flows away from cleared areas and slopes to stable (vegetated)
areas.
4.7 TRASNPORTATION OF EQUIPMENT BY ROAD/RAILWAYS/PIPELINES
Overloading capacity of existing infrastructure
4.7.1 Drivers will comply with Sasol Internal as well as the South
African Traffic rules. N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None
Spillages
4.7.2 A Transport Risk Assessment will be conducted and
recommendations will be implemented. N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None
5 PRE-COMMISSIONING PHASE
5.1 CLEANING OF EQUIPMENT
Chemicals used for cleaning/pickling/passivation
5.1.1 Ensure that the chemicals are disposed of at a permitted site. N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None
5.1.2 Proper disposal methods should be used. Chemicals will be
disposed off by the responsible Contractor/s.
N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None
ENVIRONMENTAL AUTHORISATION AND ENVIRONMENTAL MANAGEMENT PROGRAMME COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL SYNFUELS OPERATIONS: WATER AND ASH
WSP June 2019
Page 31
REF: COMMITMENT COMPLIANCE FINDING RECOMMENDATION
Water used for cleaning of steam/condensate system
5.1.3 Water will be routed through to the proper sewer system. N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None
Water used for cleaning/flushing of plant equipment
5.1.4 Water will be routed through to the proper sewer system. N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None
5.2 LOADING OF SLUDGE INTO THE REACTORS
Spillage of the sludge while loading
5.2.1 Loading must take placed on the paved area. N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None
5.2.2 Contaminated soil will be sent to the WRF. N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None
5.3 STORAGE OF CHEMICALS FOR CLEANING/PICKLING/PASSIVATION
Spillage of hazardous substance when storing
5.3.1 The Contractor will be responsible for safe storage of
chemicals and will compile and keep all the emergency
response plans and MSDSs.
N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None
ENVIRONMENTAL AUTHORISATION AND ENVIRONMENTAL MANAGEMENT PROGRAMME COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL SYNFUELS OPERATIONS: WATER AND ASH
WSP June 2019
Page 32
REF: COMMITMENT COMPLIANCE FINDING RECOMMENDATION
5.4 TESTING OF EQUIPMENT: HYDRAULIC TESTING
Management of used water
5.4.1 Water will be routed through to the proper sewer system. N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None
5.5 TRANSPORTATION OF CHEMICALS OF CLEANING/PICKLING/PASSIVATION
Spillage of hazardous substance when transporting
5.5.1 Contractor will be responsible for safe transportation of
chemicals and will compile and keep all the emergency
response plans and MSDSs.
N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None
5.6 WET RUN (CIRCULATION): WATER USED FOR CIRCULATION
Management of used water
5.6.1 Water will be routed through to the proper sewer system. N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None
6 START-UP AND SHUTDOWN PHASE
6.1 DRAINING OF VESSELS DURING SHUT DOWNS
Incorrect disposal of effluents
6.1.1 Drain to the correct sewers/sumps. C All WRG operations follow the issued SOP, which all responsible
personnel and contractors have access to. The effluent is drained to
None
ENVIRONMENTAL AUTHORISATION AND ENVIRONMENTAL MANAGEMENT PROGRAMME COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL SYNFUELS OPERATIONS: WATER AND ASH
WSP June 2019
Page 33
REF: COMMITMENT COMPLIANCE FINDING RECOMMENDATION
the correct sewers/sumps according to Section 5.6 (specifically step
1 of 5.6.1 of the SOP) when vessels are shut down. The SOP was
reviewed and indicated that the lines are flushed and drained to the
sewer and then the relevant sump as required.
Evidence:
— 3.19_EA_SAS-579A WRG SOP rev 0 (3) July 2018
6.2 FILLING UP OF VESSELS
Displacement of air/nitrogen etc.
6.2.1 The biogas will be routed to the flare. C All WRG operations follow the issued SOP, which all responsible
personnel and contractors have access to. The biogas is drained to
flare according to Section 5.6 (specifically step 5 of 5.6.17 of the
SOP) when vessels are shut down. The SOP was reviewed and
indicated that the biogas is routed to the flare as required.
Evidence:
— 3.19_EA_SAS-579A WRG SOP rev 0 (3) July 2018
None
6.3 FLARING
Flare
6.3.1 Flaring systems shall be designed such that there is no flaring
visible or audible to the surrounding communities and general
public, except for provable process or plant emergencies.
C Sasol uses enclosed or ground based flares rather than elevated
flares. The flares used reduce noise, luminosity and heat radiation.
Furthermore, the system used provides wind protection and
effective emission monitoring.
The complaints register was reviewed and there were no complaints
regarding the flaring system related to this EA.
Evidence:
— Environmental Complaints Register (2008-2019)
None
ENVIRONMENTAL AUTHORISATION AND ENVIRONMENTAL MANAGEMENT PROGRAMME COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL SYNFUELS OPERATIONS: WATER AND ASH
WSP June 2019
Page 34
REF: COMMITMENT COMPLIANCE FINDING RECOMMENDATION
6.3.2 Ensure that Best Available Techniques (BAT) technical flare
design criteria are applied. N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None
6.3.3 Eliminate / reduce / minimise the need to continuously
“destroy” flare gases through optimal: technology selection;
plant design and flare gas recovery.
N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None
6.4 FLUSHING, DRAINING AND DISPOSAL OF OILS
Oils not disposed of correctly
6.4.1 Oil will be removed by the contractor. C The driver collects all the oil collected in the sumps from the Waste
Recycling Facility (WRF) adjacent to the WRG plant who also
collects used oil from all other Sasol Secunda facilities including the
mining operations. All the oil is taken to the WRF before contractors
for recycling collect it.
None
6.5 PROCESSING OF FEED: OFF-SPEC MATERIAL
Management of off-spec material: Incorrect disposal of non-recyclable material
6.5.1 The off-spec reaction water will go to the current system.
C All WRG operations follow the issued SOP, which all responsible
personnel and contractors have access to. Off-spec water on the site
is taken to the current system to be treated so that it can then be re-
used as process water again.
Evidence:
— 3.19_EA_SAS-579A WRG SOP rev 0 (3) July 2018
None
ENVIRONMENTAL AUTHORISATION AND ENVIRONMENTAL MANAGEMENT PROGRAMME COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL SYNFUELS OPERATIONS: WATER AND ASH
WSP June 2019
Page 35
REF: COMMITMENT COMPLIANCE FINDING RECOMMENDATION
7 OPERATION AND MAINTENANCE PHASE
7.1 ADDITIONAL PERMANENT EMPLOYMENT
Employment and skills development
7.1.1 Local labour and contractors must be used wherever possible. C Sasol uses trained personnel and contractors for operation and
maintenance. All site personnel that work on the WRG undergo
SHE induction to ensure that they are familiar with the site’s SHE
aspects and requirements. All of Sasol’s training is carried out
through the regional SHE learning and development academy. The
induction presentation and the SOP for the site were available for
review.
Evidence:
— Induction Modules
— 3.19_EA_SAS-579A WRG SOP rev 0 (3) July 2018
None
7.1.2 Basic skills development and capacity building must be
incorporated. C All site personnel that work on the WRG undergo SHE induction to
ensure that they are familiar with the site’s SHE aspects and
requirements. All of Sasol’s training is done through the regional
SHE learning and development academy. The induction
presentation and the SOP for the site were available for review.
Evidence:
— Induction Modules
— 3.19_EA_SAS-579A WRG SOP rev 0 (3) July 2018
— SA Regional Procedure - Generic SHE Training.docx Rev.01
July 2018
None
7.1.3 Employees will be trained as required. C All site personnel that work on the WRP undergoes Safety, Health
and Environment (SHE) induction to ensure that they are familiar
with the site’s SHE aspects and requirements. All of Sasol’s training
is done through the regional SHE learning and development
None
ENVIRONMENTAL AUTHORISATION AND ENVIRONMENTAL MANAGEMENT PROGRAMME COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL SYNFUELS OPERATIONS: WATER AND ASH
WSP June 2019
Page 36
REF: COMMITMENT COMPLIANCE FINDING RECOMMENDATION
academy. Site personnel are trained on the WRG SOP on how the
site operates. The induction presentation and the SOP for the site
were available for review.
Evidence:
— Induction Modules
— 3.19_EA_SAS-579A WRG SOP rev 0 (3) July 2018
— SA Regional Procedure - Generic SHE Training.docx Rev.01
July 2018
7.2 CLEANING OF EQUIPMENT
Chemicals used for cleaning/pickling/passivation, etc.
7.2.1 Water will be routed to the correct sewer system according to
the Synfuels Water Management Procedure. C According to the IWWMP and the SOP, all water that falls within
contaminated areas including bunds is channelled in the dirty
stormwater system and taken away to the effluent collection sumps.
Any spillages in the chemical bunded and off-loading area first need
to be neutralised before being released to the effluent sump. If lime
is spilled, it can be diluted with plant water before being routed to
the oily water system. The acid sump level must also be monitored
to prevent any potential spillages and is pumped out completely
when required.
Evidence:
— 3.19_EA_SAS-579A WRG SOP rev 0 (3) July 2018
— SIC IWWMP Appendix 1 - WRG 2017 Rev 1
None
Water used for cleaning of steam/condensate system
7.2.2 Water will be routed to the correct sewer system according to
the Synfuels Water Management Procedure. C According to the IWWMP and the SOP, all water that falls within
contaminated areas including bunds is channelled in the dirty
stormwater system and taken away to the effluent collection sumps.
None
ENVIRONMENTAL AUTHORISATION AND ENVIRONMENTAL MANAGEMENT PROGRAMME COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL SYNFUELS OPERATIONS: WATER AND ASH
WSP June 2019
Page 37
REF: COMMITMENT COMPLIANCE FINDING RECOMMENDATION
The sump is operated as empty as possible at all times to prevent
any overflow to the clean stormwater sewer.
Evidence:
— 3.19_EA_SAS-579A WRG SOP rev 0 (3) July 2018
— SIC IWWMP Appendix 1 - WRG 2017 Rev 1
Water used for cleaning/flushing of plant equipment
7.2.3 Water will be routed to the correct sewer system according to
the Synfuels Water Management Procedure. C According to the IWWMP and the SOP, all water that falls within
contaminated areas including bunds is channelled in the dirty
stormwater system and taken away to the effluent collection sumps.
The sump is operated as empty as possible at all times to prevent
any overflow to the clean stormwater sewer.
Evidence:
— 3.19_EA_SAS-579A WRG SOP rev 0 (3) July 2018
— SIC IWWMP Appendix 1 - WRG 2017 Rev 1
None
7.3 COOLING TOWER DRIFT
Liquid fall out
7.3.1 Drift eliminators will be installed to minimise liquid fall out. C During the site walk over, it was confirmed that drift eliminators
were installed to minimise liquid fall out as required.
Evidence:
— Personnel Communication
None
ENVIRONMENTAL AUTHORISATION AND ENVIRONMENTAL MANAGEMENT PROGRAMME COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL SYNFUELS OPERATIONS: WATER AND ASH
WSP June 2019
Page 38
REF: COMMITMENT COMPLIANCE FINDING RECOMMENDATION
7.4 EMERGENCY AND RISK
Safety risks and emergency plan
7.4.1 Process Hazard Analysis and HAZOPs and training of
personnel will be conducted. C Sasol conducts risk assessments on the processes conducted on the
site based on risk assessment procedure (SGI-SHE-000014).
Several scenarios are covered during risk assessments to ensure safe
operation of the site.
All site personnel that work on the WRP undergoes SHE induction
to ensure that they are familiar with the site’s SHE aspects and
requirements. All of Sasol’s training is done through the regional
SHE learning and development academy. The induction
presentation was available for review.
Sasol have an environment emergency procedure (SGR-
SHE000023) that covers different scenarios on the site as well as an
environmental incident procedure process flow that indicates steps
taken when an incident occurs. Furthermore, the
WRG has its own specific emergency procedure that was available
for review
Evidence:
— SGI-SHE-000014 rev 6 - Minimum requirements for
ERA_Published
— IMS_Occupational Safety_2019-01-09
— Induction_Mod4_ProcessSafetyManagement
— Induction_Mod5_WorkPlaceSafety
— Induction_Mod7_Occupational
— Environment emergency procedure_SGR-
SHE000023_rev6_2015-11
— 3.21_EA_Emergency Procedure WRG
None
ENVIRONMENTAL AUTHORISATION AND ENVIRONMENTAL MANAGEMENT PROGRAMME COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL SYNFUELS OPERATIONS: WATER AND ASH
WSP June 2019
Page 39
REF: COMMITMENT COMPLIANCE FINDING RECOMMENDATION
7.4.2 Emergency plan must be in place before the commissioning
of the plant. C Sasol have an environment emergency procedure (SGR-
SHE000023) that covers different scenarios on the site as well as an
environmental incident procedure process flow that indicates steps
taken when an incident occurs. Furthermore, WRG has its own
specific emergency procedure that was available for review.
Evidence:
— Environmental emergency procedure (Rev 6): SGR-
SHE000023
— 3.21_EA_Emergency Procedure WRG
None
7.4.3 Safety features that are intrinsic (built-in) rather than extrinsic
(added-on) to the basic design - this philosophy and the use of
high-integrity equipment and piping, provide the first lines of
defence against the dramatic and often catastrophic effects of
an overpressure and subsequent rupture, explosion or fire.
C The auditor was informed that the site equipment came with intrinsic
safety features to help prevent potential incidents. Furthermore,
additional safety features are installed around the facility to assist.
Features used on the facility include level controls linked to pumps,
pressure sensors, trip systems and alarms monitored in the control
room. All these are used to prevent site incidents.
Evidence:
— 3.19_EA_SAS-579A WRG SOP rev 0 (3) July 2018
None
7.4.4 Reduction of the probability of occurrence of an event by
considering the integrity of equipment and safe guards in
place to prevent failure of equipment should be addressed
during Basic Engineering.
C The auditor was informed that the site equipment came with intrinsic
safety features to help minimise the probability of occurrence of an
event. Furthermore, additional safe guards are installed around the
facility to prevent failure of equipment. Features used on the facility
include level controls linked to pumps, pressure sensors, trip
systems and alarms monitored in the control room. All these are
used to prevent site incidents.
Evidence:
— 3.19_EA_SAS-579A WRG SOP rev 0 (3) July 2018
None
7.4.5 New storage tanks will be designed with floating roofs and the
deck fittings and rim seals will be in accordance with
international standards to minimise evaporative losses.
N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
No new tanks have been added since construction was completed.
None
ENVIRONMENTAL AUTHORISATION AND ENVIRONMENTAL MANAGEMENT PROGRAMME COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL SYNFUELS OPERATIONS: WATER AND ASH
WSP June 2019
Page 40
REF: COMMITMENT COMPLIANCE FINDING RECOMMENDATION
7.4.6 Storage and liquid impoundment areas for fuels, raw material
and in-process materials, solvents, wastes and products shall
be designed with secondary containment measures and hard
surfaces, suitable subsurface lining and leak detection
systems, pressure relief valves and high level alarms to
prevent spills and contamination of soil, groundwater and
surface water.
C All storage tanks are within concreted bunds that contain any
potential leaks. This was observed during the site walk and indicated
in the photo taken and referenced in Table 2. Furthermore, all the
tanks as well as the process are monitored in the control room to see
if there are any leaks, pressure build-up as well as potential changes
to levels within the tanks. The contained spillages are channelled
towards the sumps and are to be reworked back to the system.
The site is completely concreted, with stormwater channels that lead
to the out-sump. This water is then channelled back to the system to
be reworked. Furthermore, all the tanks with reagents used in the
process are bunded and contained to help prevent any flow of
contaminated stormwater to the surrounding environment. The
sumps which collect contaminated water are monitored for both the
quality and level so to prevent an overflow into the surrounding
environment.
Sasol monitors both surface and groundwater to ensure there is no
contamination. Surface water and the borehole monitoring points
are indicated in the IWWMP. Two of the monitoring boreholes
adjacent to this site (REGM-128 and REGM-129) with groundwater
considered to be within quality requirements, with no actions
required and no exceedances observed.
Soil pollution monitoring is conducted as part of contaminated land
management. Phase 1 (December 2015) and Phase 2 (August) land
monitoring reports have been conducted for the Synfuels site as a
whole by Geo Pollution Technologies. Recommendations from each
report are marked down for implementation as required.
Contaminated land is managed within legal requirements and
incident registers are maintained in order to monitor any
contamination events.
Evidence:
— IWWMP SIC 2015 Final_2018-05-15
— GWMonitor Report May 2018 Final_Prj6164rev-01_2018-11-
20
None
ENVIRONMENTAL AUTHORISATION AND ENVIRONMENTAL MANAGEMENT PROGRAMME COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL SYNFUELS OPERATIONS: WATER AND ASH
WSP June 2019
Page 41
REF: COMMITMENT COMPLIANCE FINDING RECOMMENDATION
— Phase 1_Contaminated Land
Assessment_November_2015_Final 1.0
— Secunda Contaminated Land Phase 2 Report_Final v1 part 1 of
2_2018-08-28
7.4.7 The safety, health and environmental objectives of the plant
layout are to minimise the potential for injuries, overall
property and environmental damage, and related business
interruption. Measures should be taken during the site layout
to minimise the incident size and impact.
N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None
7.4.8 Where possible new process units, storage tanks, control
building, occupied buildings and other facilities shall be
separated to minimise the effect of fires, explosions, radiant
heat, spills, etc., in one area onto adjacent areas (domino
effect).
N/A No new process units installed since the plant was commissioned in
2013.
None
7.4.9 Occupational health practices and operating procedures
currently conducted will be maintained and continually
improved in keeping with the current approach. Requirements
of the OHS Act (85 of 1993) and its Regulations, Sasol SH&E
Minimum Requirements, the requirements of the International
Risk Control Africa (IRCA) Occupational Health auditing
system, principles of the OHSAS 18000 standard, World
Health Organisation (WHO) guidelines and practices
currently embedded in the Synfuels Occupational Health
system will apply to the proposed project.
C Sasol maintain and continually improve their operational
occupational health and safety practices as required in terms of the
OHS Act (85 of 1993) and its Regulations. All health and safety
documentation is kept on the IMS system and the appointed safety
officers are displayed in the control room as was confirmed during
the site walk. All the relevant documentation was indexed on the
IMS system.
All site personnel that work on the WRG project undergo Safety,
Health and Environment (SHE) induction to ensure that they are
familiar with the site’s SHE aspects and requirements. All of Sasol’s
training is done through the regional SHE learning and development
academy. The induction modules for process safety management,
workplace safety and occupational health and safety were all
available for review.
The Synfuels facility is an ISO 18000 certified facility and the
relevant certificate was available for review which was issued on 24
August 2018 and will expire on 11 March 2021.
None
ENVIRONMENTAL AUTHORISATION AND ENVIRONMENTAL MANAGEMENT PROGRAMME COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL SYNFUELS OPERATIONS: WATER AND ASH
WSP June 2019
Page 42
REF: COMMITMENT COMPLIANCE FINDING RECOMMENDATION
Evidence:
— Induction_Mod4_ProcessSafetyManagement
— Induction_Mod5_WorkPlaceSafety
— Induction_Mod7_Occupational
— SSO_BSOHSAS18001_IQNet_2018-08-24
7.5 FEED TO PLANT: TRANSPORTATION
Incidents during transportation
7.5.1 The feed to the plant will be by pipeline. A Transport Risk
Assessment will be conducted and is applicable during start-
up.
C According to Section 5.7 of the WRG SOP, inspections are carried
out according to the pre-commissioning checklist. The sequence
involved is:
— Clearance for operation certificate
— Permits signed off
— MOC completed
— Alarms and trip systems checked
— Emergency and safety equipment checks
— Lock out system enforced
This is also monitored in the control room. after all checks are done
and there are no issues, the feed can be started.
Evidence:
— 3.19_EA_SAS-579A WRG SOP rev 0 (3) July 2018
None
ENVIRONMENTAL AUTHORISATION AND ENVIRONMENTAL MANAGEMENT PROGRAMME COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL SYNFUELS OPERATIONS: WATER AND ASH
WSP June 2019
Page 43
REF: COMMITMENT COMPLIANCE FINDING RECOMMENDATION
7.6 FIRE WATER: ROUTING OF FIRE WATER
Water used to extinguish a fire not routed/disposed of correctly
7.6.1 Existing WRF fire system will be used. C The auditor was informed that the WRF fire system is used for any
potential fires that may arise on the WRG site. This is stipulated in
the WRG SOP.
Evidence:
— 3.19_EA_SAS-579A WRG SOP rev 0 (3) July 2018
None
7.7 FLARE
Emissions to the atmosphere
7.7.1 Flare only to be used during emergencies and start-up
conditions. C The flare is used as required. During the site walk, the flare system
was not in use and the auditor was informed that it is only used as
and when required.
Evidence:
— Personnel communication
None
7.8 INCINERATOR
Emissions to the atmosphere
7.8.1 Make use of existing incinerators. C The sludge produced in the process is sent to the two incinerators on
the site. This was as confirmed in the SOP. The use of the site
biosludge incinerators is licensed in the AEL (under subcategory 8.1
- thermal treatment of general and hazardous waste), which was
provided for review.
Evidence:
None
ENVIRONMENTAL AUTHORISATION AND ENVIRONMENTAL MANAGEMENT PROGRAMME COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL SYNFUELS OPERATIONS: WATER AND ASH
WSP June 2019
Page 44
REF: COMMITMENT COMPLIANCE FINDING RECOMMENDATION
— 3.19_EA_SAS-579A WRG SOP rev 0 (3) July 2018
— AEL Sasol Synfuels 0016-2018-F03 (2018)
7.9 MAINTENANCE REPLACE OLD EQUIPMENT
Removing redundant/contaminated equipment and not disposed of correctly
7.9.1 Redundant equipment will be sent to the Reclamation yard. N/A Noted. No equipment has been made redundant since
commissioning was completed.
None
7.10 NITROGEN BLANKETING IN TANKS
Continuous venting of VOCs saturated in Nitrogen to the atmosphere
7.10.1 Nitrogen will be routed to the biogas system and then to the
flare. C Any venting of nitrogen is routed according to the condition, and is
confirmed in the SOP (which was available for review).
Evidence:
— 3.19_EA_SAS-579A WRG SOP rev 0 (3) July 2018
None
7.11 PRODUCTION OF PRODUCT/BY-PRODUCT
Off-spec product and/or by-product not disposed of/routed correctly
7.11.1 Off-spec product will be circulated within the system. C All off-spec product is circulated within the system, as was
confirmed in the SOP.
Evidence:
— 3.19_EA_SAS-579A WRG SOP rev 0 (3) July 2018
None
ENVIRONMENTAL AUTHORISATION AND ENVIRONMENTAL MANAGEMENT PROGRAMME COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL SYNFUELS OPERATIONS: WATER AND ASH
WSP June 2019
Page 45
REF: COMMITMENT COMPLIANCE FINDING RECOMMENDATION
7.12 RELIEVE VALVES BIOGAS SYSTEM
Emissions to atmosphere
7.12.1 Routed to flare.
C Any venting of emissions to the atmosphere are routed according to
the condition which is confirmed in the SOP, which was available
for review.
Evidence:
— 3.19_EA_SAS-579A WRG SOP rev 0 (3) July 2018
None
7.13 STORMWATER MANAGEMENT: CONTAMINATED STORMWATER
Contaminated stormwater not disposed of/routed correctly
7.13.1 Stormwater contaminated by foam will go to the stormwater
dams. C According to the IWWMP and the WRG SOP, runoff from
contaminated areas drains to a sump, from where the water is
pumped back into the process circuit of WRG after passing through
the stormwater dams as required before that water is then treated and
sent back as process water.
Evidence:
— IWWMP SIC 2015 Final_2018-05-15
— 3.19_EA_SAS-579A WRG SOP rev 0 (3) July 2018
None
7.14 STORMWATER MANAGEMENT: UNCONTAMINATED STORMWATER
Uncontaminated stormwater not disposed of/routed correctly
7.14.1 Uncontaminated stormwater will be routed to the existing
stormwater system. C According to the IWWMP and the SOP, all stormwater runoff from
areas of the WRG plant where no pollution is expected drains
None
ENVIRONMENTAL AUTHORISATION AND ENVIRONMENTAL MANAGEMENT PROGRAMME COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL SYNFUELS OPERATIONS: WATER AND ASH
WSP June 2019
Page 46
REF: COMMITMENT COMPLIANCE FINDING RECOMMENDATION
directly to the environment. The water is routed via a canal to the
south of the WRG site from where it drains to the Bossiespruit.
Evidence:
— SIC IWWMP Appendix 1 - WRG 2017 Rev 1
— 3.19_EA_SAS-579A WRG SOP rev 0 (3) July 2018
7.15 TESTING OF EQUIPMENT: HYDRAULIC TESING
Management of used water
7.15.1 Water will be routed to the correct sewer system according to
the Synfuels Water Management Procedure. C As indicated before and according to the IWWMP, water is
channelled into the stormwater system that surrounds the site and is
taken to the same stormwater system as contaminated water. This
leads to stormwater dams as required before that water is then
treated and sent back as process water.
Evidence:
— IWWMP SIC 2015 Final_2018-05-15
— 3.19_EA_SAS-579A WRG SOP rev 0 (3) July 2018
None
7.16 WASTE GENERATED IN THE PROCESS: SLUDGE
Sludge not disposed of correctly
7.16.1 Sludge will be incinerated. C The sludge produced in the process is sent to the two incinerators on
the site. This was as confirmed in the SOP. The use of the site
biosludge incinerators is licensed in the AEL under subcategory 8.1
(thermal treatment of general and hazardous waste) that was
provided for review as required.
Evidence:
— 3.19_EA_SAS-579A WRG SOP rev 0 (3) July 2018
None
ENVIRONMENTAL AUTHORISATION AND ENVIRONMENTAL MANAGEMENT PROGRAMME COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL SYNFUELS OPERATIONS: WATER AND ASH
WSP June 2019
Page 47
REF: COMMITMENT COMPLIANCE FINDING RECOMMENDATION
— AEL Sasol Synfuels 0016-2018-F03 (2018)
7.17 WASTE GENERATED IN THE PROCESS: SOLID WASTE
Solid waste generated in the process not disposed of correctly
7.17.1 The slurry resulting from the project will be sent to
incinerators. C The auditor was informed that the slurry produced is sent to the
biosludge incinerators as required. This was confirmed following a
review of the SOP.
Evidence:
— 3.19_EA_SAS-579A WRG SOP rev 0 (3) July 2018
None
ENVIRONMENTAL AUTHORISATION AND ENVIRONMENTAL MANAGEMENT PROGRAMME COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL SYNFUELS OPERATIONS: WATER AND ASH
WSP June 2019
Page 48
5 SUMMARY OF THE AUDIT FINDINGS
5.1 ENVIRONMENTAL AUTHORISATION
The audit findings have been summarised into the following categories: compliance, non-compliance and not
applicable. The overall audit findings concerning compliance to the EA conditions are as listed in Table 4 below.
Table 4: Summary of EA Compliance Audit Findings
SECTION OF THE EA NO. COMMITMENTS C NC N/A
SCOPE OF AUTHORISATION 6 3 0 3
APPEAL OF AUTHORISATION 4 0 0 4
MANAGEMENT AND MONITORING OF THE ACTIVITY 2 2 0 0
COMMISSIONING AND OPERATION OF THE ACTIVITY 21 11 0 10
GENERAL 4 8 0 1
Total Count 37 19 0 18
Total Percentage 51% 0% 49%
Percentage Compliance with Applicable Conditions 100%
ENVIRONMENTAL AUTHORISATION AND ENVIRONMENTAL MANAGEMENT PROGRAMME COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL SYNFUELS OPERATIONS: WATER AND ASH
WSP June 2019
Page 49
Figure 5-1 illustrates the number/count contribution of the findings of the EA per section while Figure 5-2
presents the total proportion of compliance for the facility.
Figure 5-1: Number/Count contribution of findings made to the EA conditions per Section
Figure 5-2: Overall count findings on compliance to the EA conditions
0
5
10
15
20
25
Scope ofAuthorisation
Appeal ofAuthorisation
Management andMonitoring of the
Activity
Commissioningand Operation of
the Activity
General
Sectional Count Contribution
C
NC
N/A
19
0
18
Total Compliance
C
NC
N/A
ENVIRONMENTAL AUTHORISATION AND ENVIRONMENTAL MANAGEMENT PROGRAMME COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL SYNFUELS OPERATIONS: WATER AND ASH
WSP June 2019
Page 50
Figure 5-3 illustrates the percentage contribution of the findings of the EA conditions. Figure 5-4 presents the
total percentage compliance for the facility.
Figure 5-3: Percentage contribution of findings made to the EA conditions per Section
Figure 5-4: Overall percentage findings on compliance to the EA conditions
0102030405060708090
100
Scope ofAuthorisation
Management andMonitoring of the
Activity
Commissioningand Operation of
the Activity
General
Sectional Percentage Contribution
C
NC
N/A
51%
0%
49%
Total Percentage Compliance
C
NC
N/A
ENVIRONMENTAL AUTHORISATION AND ENVIRONMENTAL MANAGEMENT PROGRAMME COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL SYNFUELS OPERATIONS: WATER AND ASH
WSP June 2019
Page 51
5.2 ENVIRONMENTAL MANAGEMENT PLAN
The audit findings have been summarised into the following categories: compliance, non-compliance and not
applicable. The overall audit findings concerning compliance to the EMPr conditions are as listed in Table 5
below.
Table 5: Summary of EMPr Compliance Audit Findings
SECTION OF THE EMPR NO. COMMITMENTS C NC N/A
CONSTRUCTION PHASE 72 0 0 72
PRE-COMMISSIONING PHASE 10 0 0 10
START-UP AND SHUTDOWN PHASE 7 5 0 2
OPERATION AND MAINTENANCE PHASE 29 25 0 4
Total Count 118 30 0 88
Total Percentage 25% 0% 75%
Percentage Compliance with Applicable Conditions 100%
ENVIRONMENTAL AUTHORISATION AND ENVIRONMENTAL MANAGEMENT PROGRAMME COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL SYNFUELS OPERATIONS: WATER AND ASH
WSP June 2019
Page 52
Figure 5-5 illustrates the number/count contribution of the findings of the EMPr per section while Figure 5-6
presents the total proportion of compliance for the facility.
Figure 5-5: Number/Count contribution of findings made to the EMPr conditions per Section
Figure 5-6: Overall count findings on compliance to the EMPr conditions
0
10
20
30
40
50
60
70
80
Construction Phase Pre-CommissioningPhase
Start-Up andShutdown Phase
Operation andMaintenance Phase
Sectional Count Contribution
C
NC
N/A
30
0
88
Total Compliance
C
NC
N/A
ENVIRONMENTAL AUTHORISATION AND ENVIRONMENTAL MANAGEMENT PROGRAMME COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL SYNFUELS OPERATIONS: WATER AND ASH
WSP June 2019
Page 53
Figure 5-7 illustrates the percentage contribution of the findings of the EMPr conditions. Figure 5-8 presents the
total percentage compliance for the facility.
Figure 5-7: Percentage contribution of findings made to the EMPr conditions per Section
Figure 5-8: Overall percentage findings on compliance to the EMPr conditions
0102030405060708090
100
Construction Phase Pre-CommissioningPhase
Start-Up and ShutdownPhase
Operation andMaintenance Phase
Sectional Percentage Contribution
C
NC
N/A
25%
0%
75%
Total Percentage Compliance
C NC
N/A
ENVIRONMENTAL AUTHORISATION AND ENVIRONMENTAL MANAGEMENT PROGRAMME COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL SYNFUELS OPERATIONS: WATER AND ASH
WSP June 2019
Page 54
5.2.1 EFFECTIVENESS OF THE EMPR
Section 34 and Appendix 7 of the EIA Regulations 2014 (as amended) requires an assessment of the adequacy
and effectiveness of the EMPr as part of the audit scope, as follows:
— Assess the extent to which the avoidance, management and mitigation measures provided for in the EMPr,
achieve the objectives and outcomes laid out in these documents;
— Identify and assess any new impacts and risks that result from undertaking the activity;
— Critically evaluate the effectiveness of the EMPr;
— Identify shortcomings in the EMPr; and
— Identify the need for any changes to the avoidance, management and mitigation measures provided for in
the EMPr.
The EMPr compliance audit has identified that approximately 70% of the listed measures are no longer applicable,
as these mostly related to the construction phase and pre-commissioning phase only. The original EMPr document
was designed pre-operation principally to govern these construction phase impacts, and has been superseded
during the operational phase by Sasol Business Unit-specific risk assessments; compliance with the EA, relevant
WUL and AEL; and through Sasol’s choice to comply with the ISO 14001 Environmental Management
international standard.
The EIA Regulations 2014 (as amended) requires that the EA and EMPr is audited only at least every five years,
and Sasol has systems in place which are considered to be more robust for monitoring compliance and
implementing changes than through the EMPr audits; including the annual audit of each business unit to meeting
ISO 14001 standards.
New impacts and risks are continually identified and assessed by Sasol by its Governance SHE Risk and
Assurance department; which assesses environmental risks and drives improvement implementation. The SHE
Environment department facilitates Environmental Risk Assessments per business entity to ensure that gaps are
addressed through implementation of mitigation measures via the Integrated Management System. Sasol further
addresses all Key Undesirable Events (KUEs) from a group perspective. Risk documentation is hosted on Sasol’s
Information Management System.
In conclusion, WSP considers that for the duration that Sasol continues to operate each business unit under ISO
14001 standards and meet licence compliance (EA, WUL, AEL), this is effective as mitigation against any gaps
in the EMPr and as a means to regularly identify new impacts and risks. In the event that Sasol elects to no longer
comply with ISO standards, an alternative system must be implemented. Such an alternative may involve updates
to the EMPr and regular (annual) audits against these updates.
APPENDIX
A ENVIRONMENTAL AUTHORISATION
(17/2/2/1(e) MP-04)