Upload
others
View
4
Download
0
Embed Size (px)
Citation preview
ENVIRONMENTAL IMPACT ASSESSMENT
REPORT
FOR THE
PROPOSED CONSTRUCTION OF HIGH LEVEL BRIDGE ACROSS
PULICAT LAKE CONNECTING 0/4 OF CHENNAI � PULICAT ROAD
TO PASIYAVARAM ROAD
By
GOVERNMENT OF TAMILNADU HIGHWAYS
DEPARTMENT
Towards
Coastal Regulation Zone Clearance under CRZ Notification 2011
TABLE OF CONTENTS
1.0 GENERAL ........................................................................................................................................ 1
1.1 ABOUT THE PROJECT ...................................................................................................................... 1
2.0 BACKGROUND AND NECESSITY OF THE PROJECT .......................................................................... 2
2.1 BACKGROUND OF THE PROJECT .................................................................................................... 2
2.2 PLANT DESCIRPTION ...................................................................................................................... 9
2.3 PRESENT STATUS OF THE PROJECT ................................................................................................ 9
2.4 PROPOSAL DETAILS ........................................................................................................................ 9
2.4 NEED FOR EIA ............................................................................................................................... 11
3.0 EXISTING ENVIRONMENTAL STATUS ................................................................................ 12
3.1 OBJECTIVE .................................................................................................................................... 12
3.2 SCOPE OF THE STUDY ................................................................................................................... 12
3.3 METHODOLOGY ........................................................................................................................... 12
3.3.1 EXISTING ENVIRONMENTAL STATUS ......................................................................................... 12
3.4 ENVIRONMENTAL COMPONENT .................................................................................................. 13
3.5 SAMPLING LOCATIONS ................................................................................................................. 13
3.6 MICROMETEOROLOGY ................................................................................................................. 13
3.6.1 Temperature ............................................................................................................................. 17
3.6.2 Rainfall....................................................................................................................................... 17
3.6.3 Wind Speed ............................................................................................................................... 17
3.7 AMBIENT AIR QUALITY ................................................................................................................. 19
3.7.1 AMBIENT AIR QUALITY STANDARDS ......................................................................................... 19
3.7.2 SELECTION OF SAMPLING LOCATION ........................................................................................ 22
3.7.3 PARTICULATE MATTER (PM10 and PM2.5) .................................................................................. 22
3.7.4 SULPHUR DIOXIDE (SO2) ............................................................................................................ 22
3.7.5 OXIDES OF NITROGEN (NO2) ..................................................................................................... 22
3.8 Noise Environment ....................................................................................................................... 26
3.8.1 Ambient Noise Standards .......................................................................................................... 28
3.8.2 Identification of Sampling Locations ......................................................................................... 28
3.9 WATER QUALITY ........................................................................................................................... 29
3.10 SOIL QUALITY ............................................................................................................................. 31
3.10.1 Data Generation ...................................................................................................................... 31
3.10.2 BASELINE SOIL STATUS ............................................................................................................ 32
3.12.1 BIOLOGICAL ENVIRONMENT ASSESSMENT ........................................................................... 37
3.12.2 SURVEY METHODOLOGY ........................................................................................................ 38
3.12.3 Baseline Status-Fauna ............................................................................................................. 40
3.12.4 TERRESTRIAL ECOLOGY ........................................................................................................... 47
3.14 BASELINE STATUS SUMMARY .................................................................................................... 53
4.0 ANTICIPATED IMPACTS AND MITIGATION MEASURES ................................................ 54
4.1 INTRODUCTION ............................................................................................................................ 54
4.2 IMPACT ASSESSMENT MATRIX ..................................................................................................... 54
4.3 GENERAL ...................................................................................................................................... 55
4.4 IMPACTS AND MITIGATION MEASURES DUE TO PROJECT SITING ............................................... 55
4.5 IMPACTS AND MITIGATION MEASURES DURING CONSTRUCTION PHASE .................................. 55
4.5.1 LAND DISTURBANCE .................................................................................................................. 56
4.5.2 AIR IMPACT ............................................................................................................................... 56
4.5.3 NOISE IMPACT ........................................................................................................................... 56
4.5.4 WATER IMPACT ......................................................................................................................... 56
4.5.5 ECOLOGICAL IMPACT ................................................................................................................ 57
4.5.6 SOCIO-ECONOMIC IMPACT ....................................................................................................... 57
4.6 IMPACTS AND MITIGATION MEASURES DURING OPERATIONAL PHASE ..................................... 57
4.6.1 AIR QUALITY .............................................................................................................................. 57
4.6.2 WATER QUALITY ........................................................................................................................ 57
4.6.3 NOISE IMPACT ........................................................................................................................... 58
4.6.4 NOISE MODELING...................................................................................................................... 58
4.6.5 SOLID WASTE............................................................................................................................. 58
4.6.6 SOCIO-ECONOMIC IMPACT ....................................................................................................... 58
4.6.7 ECOLOGY AND SENSITIVE LOCATIONS ...................................................................................... 59
4.6.9 RAINWATER HARVESTING ......................................................................................................... 61
5.0 ENVIRONMENTAL MITIGATION ACTION PLAN ............................................................... 62
6.0 GENERAL ...................................................................................................................................... 76
7.0 ADDITIONAL STUDIES ................................................................................................................... 81
7.1 RISK ASSESSMENT ........................................................................................................................ 81
7.1.1 HAZARD IDENTIFICATION USING PHA TECHNIQUES ................................................................. 82
7.1.2 BASED ON FIRE & EXPLOSION INDEX ........................................................................................ 82
7.1.3 HAZOP STUDIES ......................................................................................................................... 83
7.1.4 PROBABILITY OF OCCURRENCE ................................................................................................. 83
7.2 DISASTER MANAGEMENT PLAN ................................................................................................... 83
7.2.1 EMERGENCY PLANNING FOR DISASTER .................................................................................... 83
7.2.3 ONSITE EMERGENCY PLAN ........................................................................................................ 83
7.2.4 OFFSITE EMERGENCY PLAN ....................................................................................................... 86
8.0 PROJECT BENEFITS ....................................................................................................................... 87
8.1 GENERAL ...................................................................................................................................... 87
8.2 BENEFITS OF PROJECT .................................................................................................................. 87
8.3 CONSTRUCTION PHASE ................................................................................................................ 87
9.0 COST ESTIMATE ............................................................................................................................ 88
9.1 EMAP COST ESTIMATE ................................................................................................................. 88
10.0 ENVIRONMENTAL MANAGEMENT PLAN ........................................................................ 90
10.1 INTRODUCTION .......................................................................................................................... 90
10.2 MITIGATION MEASURES AND ITS IMPLEMENTATION SCHEDULE.............................................. 90
11.0 FINDINGS AND RECOMMENDATIONS .............................................................................. 92
11.1 FINDINGS .................................................................................................................................... 92
10.0 CONCLUSION .............................................................................................................................. 94
ENVIRONMENTAL IMPACT ASSESSMENT REPORT
1
CHAPTER 1 1.0 GENERAL
The proposed bridge is situated on the back waters of Pulicat Lake and Buckingham canal which is
near to the coast of Bay of Bengal. The bridge will connect a lot of fishermen hamlets and is expected
to serve as life line for more than 1,00,000 fisherman. The Government of Tamil Nadu has accorded
administrative sanction of Rs. 1500.00 Lakhs under Tsunami Rehabilitation Program (TRP) FOR THE
YEAR 2007-08 Vide G.O. No. 401 Revenue (MC III (2) ) AND (Chief Engineer's Lr No:24683/Salai /2006
Dt 01.08.07. Revised administrative sanction for Rs. 1820.00 lakhs was accorded, as per G.O.MS No.
315 / Revenue / DM (IV.1) / Department, dated 31.08.2015. The Government of Tamil Nadu has
proposed to construct High Level Bridges (HLB) in Tsunami affected areas on Government roads and
village roads, for which detailed engineering study will be undertaken through qualified and
experienced consultants adopting the Procurement Guidelines of ADB. The Project consists mainly of
Construction of HLB with Approach Roads in accordance with the IRC standards in Tsunami Affected
areas to meet the requirements of the local public. The proposed bridge is very useful as escape root
for those reside in the island (18,000 people) as well transporting emergency response operations
required for humanitarian aid, personnel and equipment to the affected site.
The State Government of Tamil Nadu has engaged M/s Turret & Alps, as a consultant to assist the
Highways Department in all aspects of the Project Preparation up to preparation of document related
to EIA, EMP, RAP and Bid Document.
The proposed bridge located at km 0/4 of Chennai - Pulicat Road to Pasiyavaram Road (Panchayat
Road) branch at Km24/10(RS) of Chennai Pulicat road and the road is a major link to Chennai and
Andhra Pradesh.
1.1 ABOUT THE PROJECT
The proposed High Level Bridge Construction is across the Pulicat Lake along with the
approach roads on both sides of the Lake. The start of approach road is on Pulicat Village
and end approach road is on Pasiyavaram Village. The proposed Right of Way for the
approach roads on the Pulicat Village and Pasiyavaram is 25m. While in case of the Pulicat
Lake, the propose RoW is 16m for the bridge portion.
The alignment of the bridge is taken along the existing road and it is branching along the
existing road towards Pasiyavaram Village. Lesser land acquisition is involved in the main
land due to the presence of existing road.
ENVIRONMENTAL IMPACT ASSESSMENT REPORT
2
CHAPTER 2
2.0 BACKGROUND AND NECESSITY OF THE PROJECT
2.1 BACKGROUND OF THE PROJECT
PASIYAVARM is an island in Pulicat Lake near Pazhaverkadu. Pazhaverkadu remains as a market
center and commercial hub for the local fishing community. Pazhaverkadu is also a place of tourist
attraction well connected to main land. PAZHAVERKADU is connected with bus services from Chennai
and some towns of Andhra Pradesh. Pasiyavaram though very near to PAZHAVERKADU is not
connected with any roads Pasiyavaram has around 50 old settlements houses and newly built
Tsunami housing. Residents of Pasiyavaram use boats or wade through water for their daily
essentials. People face maximum difficulty during rainy season and high tide times to cross the water.
So it is essential for the Island people to have an permanent remedy in the way of a bridge. The total
population around this location is about 50000 and their main occupation is fishing in the Bay of
Bengal and in the Pulicat Lake. At present, the people living in these kuppams have to go to Ponneri
town and Pulicat village for day - to - day activities by using boats. The depth of water during normal
period is noted to be about 2.0m. During monsoon period, water spread is about 500m. As per PWD,
the maximum depth of flow is reported to be 3.73m from the bed level of the Buckingham canal. Due
to raised water level in the lake, the villagers find it very difficult to cross this lake. The fishermen
experience much hardship to market their catches in the nearby town. Moreover it is found that
materials are conveyed through bullock carts and the carts with loads are drawn in the standing
water. Therefore it is absolutely necessary to construct a high level bridge across the Pulicat Lake.
S.No. Particulars Details
1. Plant Location Palaverkadu VILLAGE, Ponneri Taluk,
Thiruvallur District.
2. General Elevation 6.7 m from Mean Sea Level
3. Nearest Indian Meteorological centre Nungambakkam
4. Maximum temperature 39.3⁰C
5. Minimum temperature 21.0⁰C
6. Nearest highway The Nearest highway NH 16 is 20 km away
from the project site.
ENVIRONMENTAL IMPACT ASSESSMENT REPORT
3
7. Nearest railway station Ponneri Railway Station
The Nearest railway station is 15 km away
from the Project site.
8. Nearest Airport Anna International Airport, Chennai
The Nearest Airport is 55 km away from the
project site.
9. Nearest Major Water Bodies Pulicat lake is adjacent from the project site
10. Nearest Town/ City Ponneri Town
State of Tamilnadu
ENVIRONMENTAL IMPACT ASSESSMENT REPORT
4
Figure.2.1. Location of the Proposed Site at Thiruvallur District, Tamil Nadu
ENVIRONMENTAL IMPACT ASSESSMENT REPORT
5
Figure 2.2 Satellite Image of the Project Site
Proposed Site
ENVIRONMENTAL IMPACT ASSESSMENT REPORT
6
Figure 2.3 Terrain Map of Project Site
Proposed Site
ENVIRONMENTAL IMPACT ASSESSMENT REPORT
7
Figure 2.4 Topo Map (10 km Radius)
SITE
ENVIRONMENTAL IMPACT ASSESSMENT REPORT
8
SITE PLAN
ENVIRONMENTAL IMPACT ASSESSMENT REPORT
9
2.2 PLANT DESCIRPTION
PASIYAVARM is an island in Pulicat Lake near Pazhaverkadu. Pazhaverkadu remains as a market
center and commercial hub for the local fishing community.
Pazhaverkadu is also a place of tourist attraction well connected to main land. PAZHAVERKADU is
connected with bus services from Chennai and some towns of Andhra Pradesh.
Pasiyavaram though very near to PAZHAVERKADU is not connected with any roads Pasiyavaram has
around 50 old settlements houses and newly built Tsunami housing. Residents of Pasiyavaram use
boats or wade through water for their daily essentials. People face maximum difficulty during rainy
season and high tide times to cross the water. So it is essential for the Island people to have an
permanent remedy in the way of a bridge.
The total population around this location is about 50000 and their main occupation is fishing in the
Bay of Bengal and in the Pulicat Lake. At present, the people living in these kuppams have to go to
Ponneri town and Pulicat village for day - to - day activities by using boats. The depth of water during
normal period is noted to be about 2.0m. During monsoon period, water spread is about 500m. As per
PWD, the maximum depth of flow is reported to be 3.73m from the bed level of the Buckingham
canal.
Due to raised water level in the lake, the villagers find it very difficult to cross this lake. The fishermen
experience much hardship to market their catches in the nearby town. Moreover it is found that
materials are conveyed through bullock carts and the carts with loads are drawn in the standing
water. Therefore it is absolutely necessary to construct a high level bridge across the Pulicat Lake.
2.3 PRESENT STATUS OF THE PROJECT
At present there is no bridge to link Chennai-Pulicat road and the Pasiyavaram Island, and the people
use boats to commute between the main land and the island and they cross the river by walk. During
emergency situations like cyclone, storm and Tsunami, boats could not be used and the island will be
completely cut off from the mail land. The people coming from Chennai or other parts of the cities get
down at Pulicat and they have to travel by the boats to reach their destinations in the Pasiyavaram
Village. There is no existing road in the island along the existing alignment. The following figures show
the conditions of the Project location.
2.4 PROPOSAL DETAILS
The zero chainage of the alignment starts at Km 0/4 i.e. 400m away from Pulicat Chennai Highways.
Further, the alignment continues in a straight line and-the bridge portion starts at chainage 268 m
ENVIRONMENTAL IMPACT ASSESSMENT REPORT
10
and ends at 658 m. Again the alignment continues in a straight line and ends at chainage 974m in
Pasiyavaram Village.
The bridge consists of 20 spans of 21.6m centre to center and 1 navigation span 21.8 m. The central
span is raised over the other spans with a road level of+10.755m. The spans on pulicat side are in a
gradient of 1 in 96.7 m and on Pasiyavaram side 1 in 36. The road level at the abutment on pulicat
side is +8.302m.
2.4.1 SITE AND ITS ALIGNMENT
The existing horizontal alignment will be straight avoiding horizontal curves and vertical alignment of
the approach roads to the bridge will have to be maintained as per the bridge alignment. A vertical
clearance of 3.09m above HFL is provided for the navigation purpose. The alignment is proposed such
that no significant land acquisition/environmental concerns are involved.
2.4.1 NEED FOR PROJECT
There is no direct link or indirect link to Pasiyavaram village. 19 villages will get benefits after the
proposal. Depth of water level will be 0.5 � 2.0 m, during the monsoon period the water depth will
raise to 3.73 m and water spread will increase to 500 m as per PWD record. SO people and students
cannot cross the lake. This island suffered maximum casualties in the Tsunami 2004.
Following are the vehicle movement at Pulicat & Pasiyavaram road
Fast Moving Vehicles Slow mowing
Vehicles
2 W
hee
ler
3 W
hee
ler
Car
/ je
ep /
Van
LC
V
Bus
Tru
ck
3 Axle
Multi Axle
Ag
ri t
ract
or
Cyc
le
Cyc
le
Ric
ksh
aw
An
imal
D
raw
n
Han
d C
art
Ped
estr
ian
PCU
167 0 30 0 0 0 0 0 0 67 0 0 0 1026 147
143 0 28 0 0 0 0 0 0 46 0 0 0 955 123
139 0 23 0 0 0 0 0 0 36 0 0 0 924 111
123 0 21 0 0 0 0 0 0 35 0 0 0 830 100
152 0 28 0 0 0 0 0 0 46 0 0 0 1016 127
129 0 28 0 0 0 0 0 0 46 0 0 0 981 116
192 0 36 0 0 0 0 0 0 68 0 0 0 1035 166
ENVIRONMENTAL IMPACT ASSESSMENT REPORT
11
2.4 NEED FOR EIA
As per the Coastal Regulation Zone Notification 1991 and its subsequent and extraordinary Gazette
Notification and its amendment up to the year 2002, CRZ clearance is required as per the conditions and
guidelines of Department of Environment, Government of Tamil Nadu and Ministry of Environment &
Forest, Government of India. For getting the consent to establish the proposed High Level Bridge
project, the clearance from Tamil Nadu Pollution Control Board is required. Prior approvals for tree
felling are to be sought from the District Collector/RDO. EIA report is mandatory for getting CRZ
clearance.
The objective of EIA is to foresee the potential environmental problems that would arise out of a
proposed development and address them in the project's planning and design stage. The EIA process
should then allow for the communication of this information to:
(a) The project proponent;
(b) The regulatory agencies; and,
(c) All stakeholders and interest groups.
EIA integrates the environmental concerns in the developmental activities right at the time of initiating
for preparing the feasibility report. In doing so it enables the integration of environmental concerns and
mitigation measures in project development. EIA can often prevent future liabilities or expensive
alterations in project design.
The project proposed by the Proponent requires clearance as per the Coastal Regulation Zone
Notification, 2011 under sub-section (1) of section and clause (V) of subsection (2) of section 3 of the
Environment (Protection) Act, 1986. As it involves construction of bridge in the area classified as CRZ I.
DESCRIPTION OF PROPOSAL
S.No Description Details
1 Type of Bridge High Level Bridge (Square Bridge)
2 Number of Spam 20
3 Oveall width of the bridge 8.5 m
4 Carriage Way 7.5 m
5 Length of Bridge 432 m
6 Seismic Zone Zone � III
7 Type of Foundation Pile Foundation (1000 mm Dia)
ENVIRONMENTAL IMPACT ASSESSMENT REPORT
12
CHAPTER 3
3.0 EXISTING ENVIRONMENTAL STATUS
3.1 OBJECTIVE
The objective of the study is to carry out Environmental Impact Assessment (EIA) considering the
proposed bridge.
3.2 SCOPE OF THE STUDY
The scope of the EIA study is as follows:
Assessment of baseline environmental conditions for terrestrial environment within the study
area based on results of primary surveys carried out and other relevant secondary published
data.
Identification and prediction of significant impact on the physical environment considering
meteorological conditions, air, noise, water, soil, biotic environment, socio economic
environment, geological and hydro geological conditions within the study area.
3.3 METHODOLOGY
Considering the environmental setting of the project, project activities and their interaction,
environmental regulations and standards, following Environmental attributes have been included for
the EIA study. Study Area will be covering 10 km Radius from project boundary.
Site specific micrometeorological data for the parameters Wind Speed & direction, Temperature,
Humidity and Rainfall.
Ambient Air Quality (at 8 locations) for the parameters: PM10, PM2.5, SO2, NO2.
Noise Level Measurements at 8 Locations for both Leq-Day and Leq-Night values.
Water Quality - Surface Water (2 Locations) and Ground Water (6 Locations) for IS:10500 Norms.
Soil Quality (6 Locations) for Textural & Physical Parameters, Nutrients, etc.
Biotic Attributes: Flora & Fauna - Core zone & Buffer zone-Diversity Index.
Socio-Economic Profile (2011 Census): Total Population, Household Size, Age, Gender Composition,
SC/ST, Literacy Level, Occupational Structure, etc.
3.3.1 EXISTING ENVIRONMENTAL STATUS
With rapid strides in economic development, particularly in urban areas, the need for
rationalizing and upgrading the infrastructure is imperative. In the process of development,
there has been intensive use of natural resources. Very often the process of development
has adversely affected the environment, leading to ecological imbalances. The importance of
conserving and enhancing the environmental assets has assumed urgency. Apart from land
ENVIRONMENTAL IMPACT ASSESSMENT REPORT
13
use, conservation of flora and fauna and planning, meeting demand & supply ends and
infrastructural development is an important aspect of sustainable growth. The compilation
of environmental baseline data is essential to assess the impact on environment due to the
project activities. The physical environment mainly includes water, land, air, noise, ecology
and socio � economic issues. The information presented in the chapter has been collected
from desk research, other secondary sources and field studies. Majority of data on water
quality, soil quality, air and noise quality was collected during field studies in March to May
2015.
3.4 ENVIRONMENTAL COMPONENT
Considering the environmental setting of the project, project activities and their interaction,
environmental regulations and standards, following Environmental attributes have been included for
the EIA study. Study Area will be covering 10 km Radius from project boundary.
Site specific micrometeorological data for the parameters Wind Speed & direction, Temperature,
Humidity, Cloud Cover and Rainfall.
Ambient Air Quality (at 8 locations) for the parameters: PM10, PM2.5, SO2, NO2, CO, HC &
Particulate Lead.
Noise Level Measurements at 8 Locations for both Leq-Day and Leq-Night values.
Water Quality-both Surface Waters (8 Locations) and Ground Waters (8 Locations) for IS: 10500
Norms.
Soil Quality (8 Locations) for Textural & Physical Parameters, Nutrients, etc.
Present & Post-project Land Use Pattern based on Satellite Imagery.
Biotic Attributes: Flora & Fauna -Core zone & Buffer zone-Diversity Index.
Socio-Economic Profile (2011 Census): Total Population, Household Size, Age, Gender
Composition, SC/ST, Literacy Level, Occupational Structure, etc.
3.5 SAMPLING LOCATIONS
Locations of sampling stations for micrometeorology, air, noise, water and soil quality are
presented in Fig 3.1 - 3.3 respectively.
3.6 MICROMETEOROLOGY
As a part of the study, the micrometeorology and microclimatic parameters were recorded by
installing a weather monitoring station at the Plant site at 10 m height. Data of wind velocity, wind
direction, ambient temperature, relative humidity, cloud cover and atmospheric pressure were
recorded at hourly intervals along with rainfall for 24 hours throughout the monitoring period.
ENVIRONMENTAL IMPACT ASSESSMENT REPORT
14
Micrometeorological Data of the project area for the period between April and June 2016 is
presented in the tables below.
Table 3.1 Meteorological Data-Project Site
For the month of April 2016
S.No. Date Temperature (oC) Relative Humidity Wind
Direction From-->To
Wind Velocity (Km/hr)
Rain Fall in mm Max Min Max % Min %
1 1-Apr-16 34.2 24.2 76 49 NW -SE 5.1 0
2 2-Apr-16 35.6 25.1 74 44 NW -SE 6.4 0
3 3-Apr-16 35.1 25.6 72 41 NW -SE Calm 4
4 4-Apr-16 35.1 25.4 70 53 NW -SE 4.6 2
5 5-Apr-16 35.2 24.3 71 58 NW -SE 5.2 0
6 6-Apr-16 34.9 26.3 76 59 W - E Calm 0
7 7-Apr-16 34.8 24.1 75 64 W - E Calm 5
8 8-Apr-16 34.9 23.6 74 56 SE - NW 6.8 6
9 9-Apr-16 34.6 22.9 73 58 SE - NW 5.6 0
10 10-Apr-16 34.2 23.6 74 52 SE - NW 4.1 7
11 11-Apr-16 33.2 24.6 75 48 SE - NW 7.2 4
12 12-Apr-16 33.6 25.7 69 49 S - N 4.2 0
13 13-Apr-16 35.6 26.4 67 42 S - N 2.8 4
14 14-Apr-16 35.1 27.1 75 38 S -N Calm 0
15 15-Apr-16 35.3 27.3 74 46 S -N 3.2 0
16 16-Apr-16 35.4 26.8 73 38 SW - NE 2.6 5
17 17-Apr-16 35.2 26.7 72 38 SW - NE 5.6 0
18 18-Apr-16 34.6 26.5 74 40 S - N calm 0
19 19-Apr-16 34.7 26.4 70 45 S - N 9.5 2
20 20-Apr-16 34.6 26.4 72 49 SW - NE calm 0
21 21-Apr-16 35.2 26.9 78 49 SW - NE 7.6 0
22 22-Apr-16 35.3 27.3 73 53 SW - NE calm 0
23 23-Apr-16 35.4 25.8 70 39 SW - NE 6.4 0
24 24-Apr-16 36.1 25.9 74 36 S - N 5.4 0
25 25-Apr-16 36.3 25.5 73 38 SW - NE 7.8 0
26 26-Apr-16 36.1 25.4 73 39 SW - NE 7.2 0
27 27-Apr-16 35.9 23.6 68 37 SW - NE 8.1 0
28 28-Apr-16 35.7 23.6 70 42 SW - NE 6.9 0
29 29-Apr-16 36.3 26.5 72 39 S - N 10.5 0
30 30-Apr-16 36.2 25.6 71 46 S -N 9.7 0
ENVIRONMENTAL IMPACT ASSESSMENT REPORT
15
Table 3.2 Meteorological Data-Project Site
For the month of May 2016
S.No. Date Temperature (oC) Relative Humidity
Wind Wind
Velocity
(Km/hr)
Rain Fall
in mm Direction
Max Min Max % Min % From-->To
1 1-May-16 35.8 25.9 73 48 N - S 7 0
2 2-May-16 36.4 24.2 76 52 N - S 5 0
3 3-May-16 34.1 27.4 73 43 NE - SW 5 0
4 4-May-16 35.8 26 72 47 N - S 7 0
5 5-May-16 35.3 25.7 74 42 NE - SW 6 0
6 6-May-16 35.9 25.8 76 48 NE - SW 11 6
7 7-May-16 34.4 26.4 75 48 N - S 7 0
8 8-May-16 35.5 24.7 74 52 NE - SW 7 0
9 9-May-16 36.7 26.2 73 44 NE - SW 5 1
10 10-May-16 35.4 24.2 74 53 NE - SW 6 0
11 11-May-16 34.1 24.3 75 56 NE - SW 8 0
12 12-May-16 35.4 27.8 72 46 NE - SW 7 0
13 13-May-16 34.5 27.4 73 44 NE - SW 8 0
14 14-May-16 34.2 26.2 75 43 NE - SW 6 0
15 15-May-16 35.2 25.3 74 48 NE - SW 9 0
16 16-May-16 35.7 27.1 76 45 E - W 6 0
17 17-May-16 34.8 27.6 75 45 NE - SW 7 0
18 18-May-16 35.4 24.2 74 54 N - S 5 0
19 19-May-16 35.7 27.3 75 55 N - S calm 6
20 20-May-16 35.2 27.5 76 39 NE - SW 8 0
21 21-May-16 35.6 25.6 75 52 NE - SW 6 0
22 22-May-16 34.8 26.2 73 47 NE - SW 6 0
23 23-May-16 35.9 26.4 72 47 N - S 7 0
24 24-May-16 34.8 26.3 74 49 N - S 5 0
25 25-May-16 34.6 25.2 73 49 NE - SW 6 0
26 26-May-16 35.9 24.7 73 52 NE - SW 2 0
27 27-May-16 34.5 25.8 70 48 N - S 8 0
28 28-May-16 35.7 26.7 72 42 N - S 7 0
29 29-May-16 34.2 26.1 74 51 N - S 6 0
30 30-May-16 35.3 25.3 76 46 N - S calm 15
31 31-May-15
ENVIRONMENTAL IMPACT ASSESSMENT REPORT
16
Table 3.3 Meteorological Data-Project Site
For the month of June 2016
S.No. Date
Temperature (oC) Relative Humidity
Wind Wind
Velocity
(Km/hr)
Rain
Fall in
mm
Direction
Max Min Max % Min % From-->To
1 1-June-16 34.9 26 71 50 S - N calm 0
2 2- June-16 34.6 24.7 68 53 S - N 11 3
3 3- June-16 35.7 25.2 70 55 SW - NE calm 0
4 4- June-16 36.8 24.1 69 61 SW - NE 8 0
5 5- June-16 37.1 26.3 70 56 S - N 7 0
6 6- June-16 37.1 25.9 73 63 N - S 8 0
7 7- June-16 36.2 24 71 51 NE - SW 8 0
8 8- June-16 36.5 25.7 68 57 N - S 9 0
9 9- June-16 36.2 25.2 70 55 N - S 8 0
10 10- June-16 35.4 26.8 69 51 NE - SW 8 0
11 11- June-16 35.2 25.6 70 56 N - S 12 2
12 12- June-16 35.8 24.2 69 57 NE - SW 10 0
13 13- June-16 34.4 27.6 71 52 NE - SW 10 0
14 14- June-16 36.3 26.2 73 50 N - S 8 0
15 15- June-16 35.3 26.1 68 54 NE - SW 12 0
16 16- June-16 35.3 24.4 68 60 NE - SW 8 0
17 17- June-16 35.9 25.4 72 57 NE - SW 11 1
18 18- June-16 35.7 25.3 70 55 NE - SW calm 0
19 19- June-16 36.5 24.2 69 56 N - S 10 0
20 20- June-16 34.7 24.3 72 50 N - S 10 6
21 21- June-16 37.6 24.2 70 62 N - S 10 6
22 22- June-16 36.2 25.8 68 52 N - S 9 0
23 23- June-16 37.8 25.5 71 58 N - S 8 0
24 24- June-16 33.8 25.4 69 44 NE - SW 11 0
25 25- June-16 36 26.9 73 53 NE - SW 7 13
26 26- June-16 35.8 26.1 71 58 NE - SW 8 0
27 27- June-16 34.6 26.7 69 44 NE - SW 10 0
28 28- June-16 37.4 24.2 72 62 NE - SW 8 0
29 29- June-16 36.7 24.1 69 63 NE - SW 8 0
30 30- June-16 35.3 24.8 71 55 NE - SW 11 0
31 31- June-16 37.4 25.6 70 59 N - S 8 0
ENVIRONMENTAL IMPACT ASSESSMENT REPORT
17
3.6.1 TEMPERATURE
The average daily maximum and minimum temperature for each of the 12 months for the
period of 2009-2013 recorded at Nungambakkam has been furnished in the Table 3.2. June
is the hottest month with maximum temperature of 39.30C. January is the coolest month
with minimum temperature of 21.00C.
3.6.2 RAINFALL
The rainfall data collected for the period from 2009 to 2013 are presented in Table 3.2.
While the predominant rainy season is the north-east monsoon (Oct � Dec), the region is
also influenced to some extent by south-west monsoon (June - Sep). While maximum rainfall
of 968.4 mm is received during the month of October 2011, minimum traces are received
during February (0.0 mm). Monthly average rain fall and yearly average rainfall are shown in
Table 3.2
3.6.3 WIND SPEED
The minimum average speed was 0.0 km/h and the maximum average speed was 15 km/h is
presented in Table 3.2. The Pasquill stability class for wind speed is given in Table 3.1.
Table 3.4 Pasquill Stability Class
Surface Wind
Speed (m/s)
(at 10m)
Day Night
Incoming Solar Radiation
Strong Moderate Slight Thinly overcast or ≥4/8 low cloud
≤ 3/8 cloud
< 2 A A-B B E F
2-3 A-B B C E F
3-5 B B-C C D E
5-6 C C-D D D D
> 6 C D D D D
Note: A = extremely unstable, B = moderately unstable, C = slightly unstable, D = neutral, E
= slightly stable, F = moderately stable. Neutral class D should be assumed for overcast
conditions during day or night.
ENVIRONMENTAL IMPACT ASSESSMENT REPORT
18
Table 3.5 Meteorological Data
STATION: NUGAMBAKKAM PERIOD : 2009- 2013
Year Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
I. MONTHLY AVERAGE WIND SPEED , 24 HRS, (KMPH)
2009 5 5 6 8 9 9 9 7 6 6 3 5
2010 6 4 5 6 7 6 5 5 4 4 4 5
2011 13 12 5 6 7 8 7 7 5 6 6 8
2012 8 8 5 6 7 8 7 7 6 6 7 7
2013 6 6 5 6 7 9 7 7 6 6 7 8
II. MONTHLY MEAN RH AT 0830 HRS IST (%)
2009 82 82 79 73 68 55 58 70 73 73 85 87
2010 84 82 79 72 71 75 79 79 81 80 87 86
2011 82 81 77 75 64 72 73 78 81 83 85 86
2012 83 77 76 72 65 56 68 73 76 83 80 84
2013 88 84 80 77 73 61 80 83 82 86 86 80
III. MONTHLY MEAN RH AT 1730 HRS IST (%)
2009 62 58 61 63 62 54 45 65 66 62 79 77
2010 68 65 68 69 69 72 74 71 71 71 79 76
2011 60 61 59 65 58 54 68 74 75 78 76 81
2012 47 26 40 60 34 41 39 40 49 51 52 68
2013 60 46 52 65 54 39 59 60 60 61 69 55
IV. MONTHLY TOTAL RAINFALL (mm)
2009 34.2 0.0 2.1 0.0 40.3 16.1 68.4 143.5 182.3 43.1 646.1 214.9
2010 5.2 0.4 0.0 0.0 204.0 136.7 155.5 235.8 120.1 195.7 274.0 287.1
2011 10.8 88.9 0.0 12.1 76.5 61.3 146.2 225.8 115.3 968.4 876.5 188.1
2012 16.3 0.0 1.6 2.0 0.0 24.7 79.9 89.5 214.1 422.6 47.0 125.5
2013 Trace 14.3 11.9 3.6 3.6 34.0 146.6 195.1 240.1 157.2 193.7 85.9
V. MONTHLY MEAN MAX. TEMP (0C)
2009 30.1 32.2 34.1 36.3 38.4 39.3 37.8 35.7 35.0 34.3 30.4 29.0
2010 29.9 31.3 33.9 35.4 36.6 35.3 33.7 33.6 33.0 33.4 30.7 28.7
2011 29.9 30.9 32.9 35.1 37.5 38.3 36.4 35.3 34.7 33.2 30.3 29.4
2012 29.6 30.9 33.6 34.6 38.6 38.8 35.4 34.9 34.0 32.2 31.0 29.6
2013 29.9 30.7 32.6 34.8 37.7 37.5 34.3 34.2 33.5 33.2 31.0 29.5
VI. MONTHLY MEAN MIN. TEMP (0C)
2009 21.1 21.7 23.8 26.5 27.7 28.1 27.7 26.1 25.7 25.2 23.9 22.3
2010 21.2 21.8 24.0 26.9 26.8 25.5 24.7 26.1 25.7 25.5 23.9 22.0
2011 21.1 21.3 23.5 26.5 27.2 28.6 26.4 26.1 25.7 24.6 23.1 22.2
2012 21.2 21.5 25.1 27.6 29.4 29.0 26.8 26.1 25.6 25.1 22.8 22.6
2013 21.0 22.5 24.1 27.6 28.7 28.3 26.0 26.1 25.9 25.9 24.3 22.1
* Data not available, *** Data not issued
ENVIRONMENTAL IMPACT ASSESSMENT REPORT
19
3.7 AMBIENT AIR QUALITY
The ambient air quality with respect to the study zone of 10 km radius around the project
site forms the baseline information. The prime objective of the baseline air quality study
was to assess the existing air quality of the area. This will also be useful for assessing the
conformity to standards of the ambient air quality during the operation of the proposed
project. The study area represents partly residential and industrial environment. This
section describes the selection of sampling locations, methodology adopted for sampling,
analytical techniques and frequency of sampling. The results of monitoring carried out for
study period of April to June 2016 is represented in the tables below.
3.7.1 AMBIENT AIR QUALITY STANDARDS
Ambient Air Quality standards has been notified by the MoEF vide Gazette Notification
dated 18th November 2009 are presented in Table 3.6.
ENVIRONMENTAL IMPACT ASSESSMENT REPORT
20
Table 3.6: National Ambient Air Quality Standards
ENVIRONMENTAL IMPACT ASSESSMENT REPORT
21
ENVIRONMENTAL IMPACT ASSESSMENT REPORT
22
3.7.2 SELECTION OF SAMPLING LOCATION
The baseline status of the ambient air quality has been assessed through a scientifically
designed ambient air quality monitoring network. The design of monitoring network in the
air quality surveillance program has been based on the following considerations:
Meteorological conditions of synoptic scale
Topography of the study area
Representative of regional background air quality for obtaining baseline status
Representatives of likely impact areas
Ambient Air Quality Monitoring (AAQM) stations were set up at eight locations with due
consideration to the above mentioned points. The AAQM locations are depicted in Figure
3.1.
3.7.3 PARTICULATE MATTER (PM10 AND PM2.5)
The PM10 and PM2.5 among the eight sampling stations covering the study region varied from
36 to 46 µg/m3and 17 to 23 µg/m3 respectively. These results are presented in Table 3.7 and
3.8
3.7.4 SULPHUR DIOXIDE (SO2)
Sulphur dioxide (SO2) concentration recorded was ranging from 7.0 to 10.7 µg/ m3 presented
in Table 3.9.
3.7.5 OXIDES OF NITROGEN (NO2)
Nitrogen dioxide was in the range of 6 to 9 µg/ m3presented in Table 3.10.
ENVIRONMENTAL IMPACT ASSESSMENT REPORT
23
Figure 3.1 (Air Sampling Locations)
S.No. Location
AAQ 1 Pulicat
AAQ 2 Kolathumedu
AAQ 3 Andikuppam
AAQ 4 Arangankuppam
AAQ 5 Vairavankuppam
AAQ 6 Pazhaverkadu
AAQ 7 Pulicat -1
AAQ 8 Pulicat - 2
1
2 5
4
6
3
7 8
ENVIRONMENTAL IMPACT ASSESSMENT REPORT
24
Table 3.7�Ambient Air Quality Status (PM10) � (April to June 2016)
Averaging Time: 24 Hrs Unit: µg/m3
SA.
No. Sampling Station Bearing*
Distance*
(KM) Min Max
Arithmetic
Mean
Standard
Deviation 98th Percentile
SA1 Pulicat -- -- 42 46 44 2.83 45.8
SA2 Kolathumedu NW 1.0 41 45 43 2.83 44.9
SA3 Andikuppam N 1.3 39 43 41 2.83 42.8
SA4 Arangankuppam NE 1.5 38 42 40 2.83 41.8
SA5 Vairavankuppam E 1.6 38 41 39.5 2.12 40.8
SA6 Pazhaverkadu SE 0.8 36 40 38 2.83 39.8
SA7 Pulicat -1 S 0.6 41 45 43 2.83 44.8
SA8 Pulicat - 2 SW 0.5 40 44 42 2.83 43.8
*- With respect to project site
Permissible limit for industrial, Residential, Rural and other area 100 µg/m3
Table 3.8�Ambient Air Quality Status (PM2.5) � (April to June 2016)
Averaging Time: 24 Hrs Unit:µg/m3
SA.
No. Sampling Station Bearing*
Distance*
(KM) Min Max
Arithmetic
Mean
Standard
Deviation
98th
Percentile
SA1 Pulicat -- -- 20 23 21.5 2.12 22.8
SA2 Kolathumedu NW 1.0 19.5 22.5 21 2.12 22.3
SA3 Andikuppam N 1.3 19 20 19.5 0.71 19.8
SA4 Arangankuppam NE 1.5 18 21 19.5 2.12 20.8
SA5 Vairavankuppam E 1.6 18.5 20 19.25 1.06 19.8
SA6 Pazhaverkadu SE 0.8 17 20 18.5 2.12 19.9
SA7 Pulicat -1 S 0.6 19.5 22 20.75 1.77 21.8
SA8 Pulicat - 2 SW 0.5 19 21 20 1.41 20.8
*- With respect to project site
Permissible limit for industrial, Residential, Rural and other area 60 µg/m3
ENVIRONMENTAL IMPACT ASSESSMENT REPORT
25
Table 3.9 � Ambient Air Quality Status (SO2) - (April to June 2016)
Averaging time: 24 hrs. Unit : µg/m3
SA.
No. Sampling Station Bearing*
Distance*
(KM) Min Max
Arithmetic
Mean
Standard
Deviation 98th Percentile
SA1 Pulicat -- -- 8.2 10.7 9.45 1.77 10.5
SA2 Kolathumedu NW 1.0 8.1 10.1 9.1 1.41 10
SA3 Andikuppam N 1.3 7.9 9.5 8.7 1.13 9.3
SA4 Arangankuppam NE 1.5 7.4 9.4 8.4 1.41 9.2
SA5 Vairavankuppam E 1.6 7.7 9.2 8.45 1.06 9.1
SA6 Pazhaverkadu SE 0.8 7.5 9.3 8.4 1.27 9.2
SA7 Pulicat -1 S 0.6 7 9.8 8.4 1.98 9.7
SA8 Pulicat - 2 SW 0.5 7.1 9.4 8.25 1.63 9.3
* With respect to project site
Permissible limit of SO2 for Industrial, Residential, Rural and other area = 80 µg/m3
Table 3.10 � Ambient Air Quality Status (NO2) - (April to June 2016)
Averaging Time: 24 hrs. Unit: µg/m3
SA.
No. Sampling Station Bearing*
Distance*
(KM) Min Max
Arithmetic
Mean
Standard
Deviation 98th Percentile
SA1 Pulicat -- -- 7 8 7.5 0.71 8
SA2 Kolathumedu NW 1.0 6 7 6.5 0.71 7
SA3 Andikuppam N 1.3 5 6 5.5 0.71 6
SA4 Arangankuppam NE 1.5 8 9 8.5 0.71 9
SA5 Vairavankuppam E 1.6 7 8 7.5 0.71 8
SA6 Pazhaverkadu SE 0.8 6 7 6.5 0.71 7
SA7 Pulicat -1 S 0.6 7 8 7.5 0.71 8
SA8 Pulicat - 2 SW 0.5 8 9 8.5 0.71 9
* With respect to project site
Permissible limit of NO2 for Industrial, Residential, Rural and other area =80 µg/m3
ENVIRONMENTAL IMPACT ASSESSMENT REPORT
26
3.8 NOISE ENVIRONMENT
Figure 3.2 (Noise Sampling Locations)
S.No. Location
SN 1 Pulicat
SN 2 Kolathumedu
SN 3 Andikuppam
SN 4 Arangankuppam
SN 5 Vairavankuppam
SN 6 Pazhaverkadu
SN 7 Pulicat -1
SN 8 Pulicat - 2
1
2 5
4
6
3
7 8
ENVIRONMENTAL IMPACT ASSESSMENT REPORT
27
The noise monitoring has been conducted for the determination of noise levels at eight
locations around the study area. Levels of noise have been monitored during 6am to 10pm
and night levels during 10 pm to 6 am. In the residential cum rural areas equivalent day
night noise levels ranges from 59.2 to 67.2 dB (A). The details of sampling locations with
respect to the plant site and the equivalent day night levels are tabulated in Table 3.11.
Table 3.11 � Equivalent Day-Night Noise Level Details
SA. No. Sampling Stations BEARING
*
DISTANCE
*
Equivalent Levels dB(A)
Day Time Night Time
SN1 Pulicat -- -- 69.5 57.4
SN2 Kolathumedu NW 1.0 66.3 64.8
SN3 Andikuppam N 1.3 67.3 65.2
SN4 Arangankuppam NE 1.5 60.2 59.4
SN5 Vairavankuppam E 1.6 60.5 58.4
SN6 Pazhaverkadu SE 0.8 59.2 67.2
SN7 Pulicat -1 S 0.6 65.5 63.5
SN8 Pulicat - 2 SW 0.5 62.4 59.5
Day Night
Permissible limit for Industrial Area - 75 70
Permissible limit for Rural Area - 55 45
ENVIRONMENTAL IMPACT ASSESSMENT REPORT
28
3.8.1 AMBIENT NOISE STANDARDS
Ambient Noise level standards have been notified by the MoEF vide Gazette Notification dated
26th December 1989 and also in the Schedule III of the Environmental (Protection) Rules 1986.
It is based on the �A� weighted equivalent noise level (Leq). These are presented in Table 3.12
Table 3.12: National Ambient Noise Standards
Category of Zones
Leq in dB(A)
Day * Night *
INDUSTRIAL 75 70
COMMERCIAL 65 55
RESIDENTIAL 55 45
SILENCE ZONE ** 50 40
Source: Central Pollution Control Board
Note:-
1. Day time shall mean from 6.00 a.m. to 10.00 p.m.
2. Night time shall mean from 10.00 p.m. to 6.00 a.m.
3. Silence zone is an area comprising not less than 100 metres around hospitals, educational
institutions, courts, religious places or any other area which is declared as such by the
competent authority. Use of vehicle horn, loudspeaker and bursting of crackers is banned in
these zones.
4. Mixed categories of areas may be declared as one of the four above mentioned categories by
the competent authority and the corresponding standards shall apply
3.8.2 IDENTIFICATION OF SAMPLING LOCATIONS
A preliminary reconnaissance survey has been undertaken to identify the major noise
generating sources in the study area. Noise at different noise generating sources have been
identified based on the activities in the surrounding area, ambient noise due to small scale
industries, traffic and noise at sensitive areas like hospitals and schools.
ENVIRONMENTAL IMPACT ASSESSMENT REPORT
29
3.9 WATER QUALITY The water samples were collected from eight locations in the study area. We have submitted
the permissible limit for the drinking purposes as well as the permissible limits in the
absence of alternative sources. Generally, the desirable limit is obtained by the river water
only, whereas we have received the water samples from bore well & open wells. The water
from sampled location falls in the range mentioned for drinking water when there is no
alternative source.
Figure 3.3 (Water Sampling Locations)
S.No. Location S.No. Location S.No. Location
GW 1 Pulicat GW 4 Arangankuppam SW 7 Kolathumedu Lake
GW 2 Pasiyavaram GW 5 Vairavankuppam SW 8 Kosasthalaiyar River
GW 3 Andikuppam SW 6 Pulicat Lake
1
2
5
4
6
3
7
8
ENVIRONMENTAL IMPACT ASSESSMENT REPORT
30
Table 3.13 � Water Analysis Results
S.No PARAMETERS UNITS SAMPLING SITES & RESULTS
GW - 1 GW - 2 GW - 3 GW - 4 GW - 5 SW - 6 SW - 7 SW - 8
1 Calcium (Ca) mg/l 49 44 50 43 46 1000 956 103
2 Chlorides (Cl) mg/l 152 148 150 142 145 18800 17500 225
3 Colour (Visual) Hazen < 1.0 < 2.0 < 1.0 < 1.0 < 1.0 < 1.0 < 1.0 45
4 Electrical Conductivity --- 821 720 832 740 840 45600 35650 1123
5 Fluorides (F) mg/l 0.2 0.24 0.3 0.2 0.26 1.22 1.1 0.2
6 Iron (Fe) mg/l 0.08 0.12 0.05 0.09 0.1 0.18 0.15 <0.01
7 Magnesium (Mg) mg/l 17 19 18 16 20 1080 1050 30
8 Nitrates (NO3) mg/l 0.1 0.1 0.12 0.14 0.13 1.13 1.1 < 1.0
9 Odour --- Agreeable Agreeable Agreeable Agreeable Agreeable No offensive odour
Agreeable Dis Agreeable
10 pH@250C No. 7.4 7.69 7.5 7.6 7.45 7.96 7.0 7.6
11 Sulphates (SO4) mg/l 52 46 48 43 45 2600 105 106
12 Total Alkalinity
(CaCo3) mg/l 96 90 93 91 95 130 125 73
13 Total dissolved solids mg/l 529 480 501 485 490 36800 35500 730
14 Total hardness (CaCo3) mg/l 190 160 175 180 165 7000 6500 378
15 Turbidity (NTU) NTU 0.9 1.2 1.0 1.0 1.1 3.5 <0.5 30
S.No. Location S.No. Location S.No. Location S.No. Location
GW 1 Pulicat GW 3 Andikuppam GW 5 Vairavankuppam SW 7 Kolathumedu Lake
GW 2 Pasiyavaram GW 4 Arangankuppam SW 6 Pulicat Lake SW 8 Kosasthalaiyar River
ENVIRONMENTAL IMPACT ASSESSMENT REPORT
31
3.10 SOIL QUALITY
It is essential to determine the potential of soil in the area and identify the impacts of
urbanization and industrialization on soil quality. Accordingly, a study of assessment of the soil
quality has been carried out.
3.10.1 DATA GENERATION
For studying soil profile of the region, sampling location was selected to assess the existing soil
condition in and around the plant representing various land use conditions. The physical,
chemical and heavy metal concentrations were determined. The samples were collected by
ramming a core-cutter into the soil up to a depth of 90 cm. Simultaneously, in-situ infiltration
test using double ring infiltrometer was carried out at all location to determine the
permeability.
The present study on the soil profile establishes the baseline characteristics and identifies the
incremental concentrations if any, due to the existing and proposed activities.
The sampling locations have been identified with the following objectives:
To determine the baseline soil characteristics of the study area;
To determine the impact on soil more importantly from agricultural productivity point of
view.
Eight locations within the study area of the plant site were selected for soil sampling. At each
location, soil samples were collected from three different depths viz 30 cm, 60 cm, and 90 cm
below the surface and homogenized. The homogenized samples were taken during April � June
2016 period to identify soil conditions.
The details of the sampling location are given in Table � 3.14 and are shown in Figure � 3.4.
ENVIRONMENTAL IMPACT ASSESSMENT REPORT
32
3.10.2 BASELINE SOIL STATUS
It has been observed that the texture of soil is mostly �Clayey Sand� in the area. The common
color of the soil ranged from light brown. It has been observed that the pH of the soil quality
ranged from 7.6 to 8.2 indicating that the soil is usually neutral to slightly basic in nature.
The electrical conductivity was observed to be in the range of 0.2 to 0.4 µmhos/cm, the
Nitrogen values ranged between < 0.1 to 0.1 kg/acre. The phosphorous value ranges between
0.1 to 0.2 kg/acre. Potassium value ranges between 174 to 190 Mg/kg indicating that the soils
in that the surrounding area having very rich quantity of potassium. The standard of soil
classification is given in Table 3.15.
ENVIRONMENTAL IMPACT ASSESSMENT REPORT
33
Table 3.14 � Soil Quality
S.No PARAMETERS UNITS RESULTS
SA-1 SA-2 SA- 3 SA- 4 SA- 5 SA - 6 SA-7 SA-8
1 pH No. 7.9 7.6 7.8 8.2 8.1 7.8 7.7 8.0
2 EC µmhos/cm 0.2 0.4 0.3 0.3 0.2 0.4 0.4 0.2
3 Texture --- Clayey sand
Clayey Silty sand
Clayey Silty fine sand
Clayey Silty sand
Clayey sand
Clayey sand
Clayey sand
Fine sand
Macro Nutrients:
4 Nitrogen Kg/Ac 0.1 0.1 < 0.1 < 0.1 0.1 < 0.1 < 0.1 0.1
5 Total Phosphorus % 0.1 0.1 0.1 0.1 0.1 0.1 0.2 0.1
6 Potassium Mg/kg 181 185 190 180 175 185 189 174
Micro Nutrients:
7 Iron mg/Kg 1452 1521 1542 1463 1552 1582 1545 1485
8 Manganese mg/Kg 52 53 55 54 50 56 54 52
9 Zinc mg/Kg 21 19 18 20 22 21 20 18
10 Copper mg/Kg 35 38 37 36 34 35 33 34
ENVIRONMENTAL IMPACT ASSESSMENT REPORT
34
Figure 3.4 (Soil Sampling Locations)
S.No. Location
SN 1 Pulicat
SN 2 Kolathumedu
SN 3 Andikuppam
SN 4 Arangankuppam
SN 5 Vairavankuppam
SN 6 Pazhaverkadu
SN 7 Pulicat -1
SN 8 Pulicat - 2
1
2 5
4
6
3
7 8
ENVIRONMENTAL IMPACT ASSESSMENT REPORT
35
Table � 3.15 � Standards of Soil Classification
S.No. Soil Test Classification
1. pH
<4.5 Extremely acidic
4.51 � 5.00 Very strongly acidic
5.51 � 6.0 moderately acidic
6.01 � 6.50 slightly acidic
6.51 � 7.30 Neutral
7.31 � 7.80 slightly alkaline
7.381 � 8.50 moderately alkaline
8.51 � 9.0 strongly alkaline
9.01 very strongly alkaline
2. Salinity Electrical
Conductivity (mmhos/cm)
Up to 1.00 Average
1.01 � 2.00 Harmful to germination
2.01 � 3.00 Harmful to crops (Sensitive to salts)
3. Organic Carbon
Upto 0.2 : Very less
0.21 � 0.4 : Medium,
0.51 � 0.8 : On an average sufficient
0.81 � 1.0 : Sufficient
> 1.0 : More than sufficient
4. Nitrogen (kg/ha)
Up to 50 : Very less
51 � 100 : Less
101 � 150 : Good
151 � 300 : Better
> 300 : Sufficient
5. Potash (kg/ha)
0 - 120 Very less
120 � 180 Less
181 � 240 Medium
241 � 300 Average
301 � 360 better
> 360 More than sufficient
ENVIRONMENTAL IMPACT ASSESSMENT REPORT
36
3.11 PULICAT LAKE
The proposed Bridge is to be constructed across Pulicat Lake. This lake is in Buckingham canal at
about 5 km from its confluence point with Bay of Bengal. There is a huge waterfront of the
Buckingham Canal with a vast spread of over flown tidal waters from the lake, in the North. This
Pulicat Lake is a saltwater lagoon. It is the second largest backwater lake in India. It is located
between 13°26' and 13°43'N latitude and 80°03' and 80°18' E longitude lying almost parallel to
the Bay of Bengal, It is extending over the Ponneri and Gummidipundi taluk of Thiruvallur
district in Tamilnadu and Sulurpet and Tada Taluk of Nellore district in Andhra Pradesh and
covers an area of about 461 square km. Table 3.10. Shows the aerial extent of various wetland
classes in Pulicat area. The lake extends to about 59km in the northern sector of the lake, The
lake at its southern end, near north of Pulicat town open into the Bay of Bengal by narrow pass
into the sea. The lagoon has a high water spread area of 460 square km and low floodwater
spread area of 250 square km. There is always fluctuation of the tidal seawater that changes the
pattern of the water in the Pulicat Lake. This Pulicat Lake is one of the important wetlands, in
Tamilnadu.
The lake as its southern end, near north of Pulicat town opens into Bay of Bengal by a narrow
pass into the sea. According to Paul Raj 1976, from March till September, the mouth gets silted
and reduced in width and depthVas/it shifts position, simultaneously from south to north. The
mouth normally gets completely closed once in above five years or even little more frequently if
there is no monsoon flood in any particular year.
Table 3.16 Arial extent of various Wetland classes in Pulicat area
Salt Marsh in
square Km
Mud Flat in square
Km
Sait Pan in Square
Km
Lake Party in
Square Km
26.80 0.356 0.257 252.040
ENVIRONMENTAL IMPACT ASSESSMENT REPORT
37
3.12 BIOLOGICAL ENVIRONMENT
3.12.1 BIOLOGICAL ENVIRONMENT ASSESSMENT
A habitat or an area comprises of different kinds of plants and animals within its boundary. The
distribution of flora and fauna in the given area represents the biological environment. The
biological portion of the environment includes, what is present in the study area, its values, and
its responses to impacts description of community uniqueness, the dominant species, and an
evaluation of rare or endangered species. Natural vegetation is scanty and the bio-diversity of
the area is low and it forms a part of deciduous area. Species diversity and food web index of
the surrounding area will be negligible. Considering this particulate project this is construction
of bridge, so there will not be any major impacts for us.
Flora-fauna: An ecological survey of the study area was conducted particularly with reference
to recording the existing biological resources. The objectives of the survey were intended to:
Generate baseline data from field observations from various terrestrial ecosystems,
Collect secondary data from Government records,
Compare the data so generated with authentic past records to understand changes,
Understand the impact of the proposed activity on vegetation structure in the site.
To accomplish the above objectives, a general ecological survey covering an area of 10 km
radius area was conducted. The locations were identified for phyto-sociological aspects to
assess the current status. Phyto-sociological studies were carried out by using least count
quadrant method. Trees species were surveyed by taking quadrates of 100 m x 10 m distributed
randomly. Shrub species were surveyed by taking quadrates of 10 m x 10 m. Herb species were
surveyed by taking quadrates of 1 m x 1 m. The data obtained was further used to estimate
Relative Dominance, Relative Density (RD), Relative Frequency (RF) and Importance Value Index
(IVI) as per the formula. Faunal survey covers the Terrestrial Fauna, Avian Fauna and Aquatic
Fauna. The survey was based on Personal observation, Enquiry with local population and
Records available. This survey will include identification of endangered and rare species as per
Red Book.
ENVIRONMENTAL IMPACT ASSESSMENT REPORT
38
3.12.2 SURVEY METHODOLOGY
An ecological survey of the study area was conducted particularly with reference to recording
the existing biological resources. The objectives of the survey were intended to:
Generate baseline data from field observations from various terrestrial ecosystems,
Collect secondary data from Government records,
Compare the data so generated with authentic past records to understand changes,
Understand the impact of the proposed activity on vegetational structure in the site.
To accomplish the above objectives, a general ecological survey covering an area of 10 km
radius area was conducted. The locations were identified for phyto-sociological aspects to
assess the current status. Phyto-sociological studies were carried out by using least count
quadrate method. Trees species were surveyed by taking quadrates of 100 m x 10 m distributed
randomly. Shrub species were surveyed by taking quadrates of 10 m x 10 m. Herb species were
surveyed by taking quadrates of 1 m x 1 m. The data obtained was further used to estimate
Relative Dominance, Relative Density (RD), Relative Frequency (RF) and Importance Value Index
(IVI) as per the formula. Faunal survey covers the Terrestrial Fauna, Avian Fauna and Aquatic
Fauna. The survey was based on Personal observation, Enquiry with local population and
Records available. This survey will include identification of endangered and rare species as per
Red Book. The flora and fauna studies were carried out in the entire study area of 10 km
radius around the proposed site. The diversified plant genera distributed in this area. The
natural vegetation of the study area had more population with variety of species. Many varieties
of plant species were growing naturally. The overall aerial and close observations lead to the
conclusion that the diversity of plant species was more in the buffer zone.
Aquatic Flora
The Pulicat Lake harbors a variety of aquatic vegetation. However to know the actual status of
the phytoplankton, sampling has been done as per IS: 7967 Phytoplankton samples are
collected using Phytoplankton net with mouth area of 0.25 m2 and mesh size of 64 urn was
towed between 0 and 0.5m depth from the water surface for five minutes and the collected
samples are immediately preserved. Depending upon the biomass concentration, sub-samples
are taken to study the whole species diversity. Organisms are identified up to genus level under
microscope using standard identification key and counted using a Sedgwick rafter counting
chamber. The biomass concentration of phyto plankton is calculated from the displacement
volume of water.
ENVIRONMENTAL IMPACT ASSESSMENT REPORT
39
Flora
The Study of flora involved intensive sample survey of vegetation in the project site and other
locations applying standard methods (e.g., Greig-Smith 1983, Caustan 1988). To examine the
trees and shrubs, quadrants of 25 x 25 m and for herbs 2 x 2 m were laid. In each of the larger
quadrants (i) Species (ii) their number, and (iii) Girth at Breast Height (GBH), were measured.
(Chaturvedi and Khanna,1982). The species of vegetation found in each station were identified
and listed according to their families, both in dicotyledons and monocotyledons of the plant
kingdom. The plant species were classified as per the classifications of �Bentham and Hooker�
and identified by using Gambles book on �Flora of Madras Presidency� and Mathew�s book on
�Flora of the Tamil Nadu Carnatic�.
Aquatic Fauna
There are many varieties of aquatic fauna that take shelter in the Pulicat Lake. The aquatic
fauna covering fish, prawns, crabs etc. have been covered in the Section 3.13. However, to
know the present status of the zooplanktons, samplings have been done as per the Standards of
IS:7967.
Zooplankton samples are collected at 8 locations. Zooplankton net with mouth area of 0.25 m2
and mesh size of 300 um is towed between 0 and 0.5 m depth for live minutes. Organisms are
identified up to genus level under microscope using standard identification key and counted
using a Sedgwick rafter counting chamber. The biomass concentration of zooplankton was
calculated from the displacement volume of water.
Fauna:
Both direct and indirect observation methods were used to survey the fauna. Visual encounter
(search) method was employed to record vertebrate species. Additionally survey of relevant
literature was also done to consolidate the list of vertebrate fauna distributed in the area
(Smith 1933-43, Ali and Ripley 1983, Daniel 1983, Prater 1993, Murthy and Chandrasekhar1988).
Since birds may be considered as indicators for monitoring and understanding human impacts
on ecological systems (Lawton, 1996) attempt was made to gather quantitative data on the
group. Point Survey Method: Observations were made in each site for 15 minutes duration. Road
Side Counts: The observer traveled from site to site, all sightings were recorded (this was done
both in the day and night time). An index of abundance of each species was also established.
Pellet and Track Counts: All possible animal tracks and pellets were identified and recorded
ENVIRONMENTAL IMPACT ASSESSMENT REPORT
40
(South Wood, 1978). Based on the Wildlife Protection Act, 1972 (WPA 1972, Anonymous 1991,
Upadhyay 1995, Chaturvedi and Chaturvedi 1996) species were short-listed as Schedule II or I
and considered herein as endangered species. Species listed in Ghosh (1994) are considered as
Indian Red List species.
3.12.3 BASELINE STATUS-FAUNA
The list of Flora & Fauna is given below:
Table 3.17 LIST OF FLORA IN THE STUDY AREA
Scientific Name Family Distribution
Anacardium occidentale Anacardiaceae Moderate
Cassia grandis Caesalpiniaceae Moderate
Polyalthia pendula Annonaceae Moderate
Polyalthia longifolia Annonaceae Moderate
Abrus precatorius Fabaceae Moderate
Rhynchosia suaveolens Fabaceae Moderate
Ampelocissus indica Vitaceae Moderate
Antigonon leptopus Polygonaceae Moderate
Asparagus racemosus Asparagaceae Low
Basella rubra basellaceae Moderate
Vanilla planifolia Orchidaceae Moderate
Wattakaka volubilis Asclepiadaceae Abundant
Vanda testaceae Orchidaceae Moderate
Annona reticulate Annonaceae Low
Citrus aurantium Rutaceae Low
Citrus limon Rutaceae Low
Michelia champaca Magnoliaceae Moderate
Abelmoschus moschatus Malvaceae Abundant
Abutilon indicum Malvaceae Abundant
Acalypha indica Euphorbiaceae Abundant
ENVIRONMENTAL IMPACT ASSESSMENT REPORT
41
Achyranthes aspera Amaranthaceae Abundant
Aerva lanata Amaranthaceae Abundant
Aeschynomene aspera Fabaceae Abundant
Aeschynomene indica Fabaceae Abundant
Ageratum conyzoides Compositae Abundant
Alysicarpus monilifer Fabaceae Abundant
Delonix regia Fabaceae Moderate
Poinciana regia Fabaceae Moderate
Butea monosperma Fabaceae Moderate
Amaranthus spinosus Amarathaceae Abundant
Ammania baccifera Lythraceae Abundant
Andrographis echioides Acanthaceae Moderate
Andrographis echioides Acanthaceae Moderate
Andrographis paniculata Acanthaceae Abundant
Argemone mexicana Papaveraceae Abundant
Biophytum sensitivum OxalidaceAE Abundant
Bacopa monieri Scrophulariaceae Moderate
Boerhavavi diffusa Nyctaginaceae Moderate
Boerhavaia erecta Nyctaginaceae Moderate
Brassica juncea Brassicaceae Moderate
Celosia cristata Amaranthaceae Abundant
Chrozophora prostrate Euphorbiaceae Abundant
Chrozophora rottleri Euphorbiaceae Abundant
Cleome aspera Capparidaceae Abundant
Cleome monophylla Capparidaceae Abundant
Areca catechu Areaceae Low
Borassus flabellifer Areaceae Low
Caryota urens Areaceae low
Cocos nucifera Areaceae Moderate
ENVIRONMENTAL IMPACT ASSESSMENT REPORT
42
Phoenix sylvestris Areaceae Low
Cocos nucifera Palmaceae Low
Salix alba Salicaceae Low
Salix floridana Salicaceae Moderate
Salix cordata Salicaceae Moderate
Agave Americana Agavaceae Low
Agavee angustifolia Agavaceae Moderate
Asphodelaceae Aloe vera Moderate
Anisomeles indica Labiateae Abundant
Cajanus cajan Fabaceae Low
Acacia Fabaceae Low
Breynia vitis-idaea Euphorbiaceae Abundant
Jatropha curcas Euphorbiaceae Abundant
Casuarina cunninghamiana Casuarinaceae Moderate
Casuarina equisetifolia Casuarinaceae Abundant
Cassia fistula ceasalpinaceae Moderate
Cassia javanica ceasalpinaceae Low
Cleistanthus collinus Euphorbiaceae Moderate
Cordia domestica Boraginaceae Low
Capparis grandis Capparidaceae Moderate
Albizia amara Mimosaceae Low
Albizia lebbeck Mimosaceae Low
Acacia planifrons Mimosaceae Moderate
Acacia tomentosa Mimosaceae Moderate
Neptunia prostrate Mimosaceae Low
Neptunia triquetra Mimosaceae Low
Mimosa pudica Mimosaceae Low
Barringtonia acutangula Barringtoniaceae Abundant
Bauhinia purpurea Caesalpiniaceae Low
ENVIRONMENTAL IMPACT ASSESSMENT REPORT
43
Bauhinia racemosa. Caesalpiniaceae Low
Ficus hispida Moraceae Moderate
Ficus mollis Moraceae Low
Memecylon edule Melastomataceae Abundant
Madhuca indica Sapotaceae Low
Manilkara zapota Sapotaceae Moderate
Casurina equiselifolia Casuarinaceae Low
Jatropha indica Euphorbiaceae Moderate
Tamarindus indicus Fabaceae Moderate
Hibiscus micranthus Malvaceae Abundant
Gynandropsis gynandra Malvaceae Abundant
Malachra capitata Malvaceae Moderate
Thespesia populnea Malvaceae Moderate
Ludwigia perennis Onagraceae Abundant
Azadirachta indica Meliaceae Moderate
Terminalia catappa Rosaceae Low
Terminalia arjuna Combretaceae Moderate
Cyathea dealbata Cyatheaceae Moderate
Andrographis paniculata Acanthaceae Moderate
Streblus asper Moraceae Low
Streblus taxoides Moraceae Moderate
Millingtonia hortensis Bignoniaceae Low
Dolichandrone falcate Bignoniaceae Low
Tectona grandis Lamiaceae Low
Tectona hamiltoniana Lamiaceae Low
Tectona philippinensis Lamiaceae Moderate
Tamarix aphylla Tamaricaceae Abundant
ENVIRONMENTAL IMPACT ASSESSMENT REPORT
44
The list of few animals is given below:
Table 3.18 Fauna of the Study area
Zoological Name Family
Ardea Ardeidae
A. alba modesta
Egretta intermedia
Psittacula krameri manillensis Pasirracida
Clamator coromandus
Eudynamus scolopaceae
Coracias bengalensis Coraidae
Upupa epops ceylonensis Upupidae
Dinopium bengalense puncticolle Picidae
Sturnus pagodarum Sturnidae
Acridotheres tristis tristis
Corvus splendens spendens Corvidae
Corvus macrorhynchos
Passer domesticus Passeriformes
Ploceus phillipinus phillipinus
Petronia xanthocollis
Copsychus saularis
Acrocephalus stentoreus
Coracina melanoptera sykesi
Acridotheres tristiris
Coturnix coturnix Galliformes
Perdicula argoondah
Naja naja Squamata
Bungarus coeralus
Calotes versicolor
Hemidactylus frenatus
Eryx johni
ENVIRONMENTAL IMPACT ASSESSMENT REPORT
45
Zoological Name Family
Macropisthodon plumbicolor
Lycodon aulicus
Argyrogena fasciolatus
Nerodia piscator
Geochelone elegans Testudina
Ratus ratus Muridae
Pteropus spp. Chiroptera
Felis chaus Felidae
Capra aegagrus hircus Bovidae
Canis lupus familiaris -
Bos Taurus Bos
Bufo melanosticus Anura
Polypetadus maculates
Euphlyctis cyanophlyctics
Vegetation Cover
There are about 26 trees coming within the Right of Way of the proposed High Level Bridge
with approach roads. Out of 26 trees, only 3 trees of Babul species are coming within the RoW
on the mainland before the Lake water on Jetty side. Rest of the trees about 2.3 tress mostly
palm are coming within the Row on Island portion of the Light House Kuppam. Before the
construction work starts, many of them will have to be felled for the proposed Project. The
extent of the trees to be felled is to be determined during the detail design stage. Most of the
trees within the right of way do not have any significant ecological and/or commercial value but
are planted at random in privately owned areas.
3.12.4 FOREST AREA
The Row and the corridor of impact of the proposed project of the Bridge has no Forest Area.
The only forest area, which is having its East side boundary to the Bay of Bengal up to the
Village limits of Puliat, wherein the Department of Forests, Government of Tamil Nadu, has
established a Bird Sanctuary. The Pulicat Bird Sanctuary is outside and away from the project
site.
ENVIRONMENTAL IMPACT ASSESSMENT REPORT
46
The Department of Forest, Government of Tamil Nadu has established the Pulicat Bird
Sanctuary long ago on the Pulicat lagoon primarily to conserve the terrestrial as well as aquatic
birds and to tempt the migratory birds which take the Pulicat Lake as a route to stop for a
break.
The Pulicat lagoon is the third most important wetland for the migratory shore birds on the
eastern seaboard of India and is protected as a Bird Sanctuary because of its rich biodiversity.
The lake is important area for a variety of resident and migratory birds like waterfowl, pelicans,
herons, egrets, storks, flamingos, ducks, gulls and terns. It boasts 65 different species of fish, 30
varieties of terrestrial and aquatic birds and a host of small mammals and reptiles. Flamingos
are the most frequent visitors to the lake, about 15,000 of them visit every year. Pelicans,
Kingfishers, Herons, Painted Storks, Spoonbills and Ducks are some of the other birds that show
up at Pulicat Lake in the bird sanctuary every year.
3.13 FISHERIES AND FISH HABITAT
The proposed bridge will be constructed across the Pulicat Lake but fish catching zone is far
away from the project area, it will not get influenced by the project construction. The major
business in the project region is of fishing only. The local economy of the Pulicat Village and
Light House Kuppam depends on the fishing activity. The Pulicat Lake is a very good habitat of
fisheries which can sustain fisheries business throughout the year. This big reservoir of Pulicat is
stocked with different types of commercial fisheries like Rohu, Mrigal, Katla, Ayla, Kingfish,
Tuna, Mullet, Pamphret, Mayle, Kota, Jelly fish, Mathi, Keluthi, Parrai, Valai, and Ladyfinger etc.
Occasionally the fishermen of the Pulicat Village get the shark fish which fetch the good
amount. Apart from fish, the other marine features which occupy major source of income are
prawns and Crabs providing a better business for the fishermen.
3.14 QUALITY OF LIFE VALUES
3.14.1 ARCHAEOLOGICAL/HISTORICAL MONUMENTS
The Corridor of impact/ RoW of the proposed project do not have ant protected / declared
archaeological. / Historical monuments.
3.14.2 TEMPLES/SHRINES/IDOLS/STATUES
The corridor of impact does not have any temple, shrine or any structure of religious
importance.
ENVIRONMENTAL IMPACT ASSESSMENT REPORT
47
3.14.3 CULTURAL HERITAGE/SENSITIVE/CRITICAL/NATURAL HABITATS
There are no cultural heritage sites, sensitive and/or critical natural habitats, national parks,
wild life sanctuaries, sacred groves, protected natural reserves falling within corridor of
impact/RoW of the proposed project. The Pulicat Bird Sanctuary covering most of the Pulicat
Lake is beyond the right of way.
3.12.4 TERRESTRIAL ECOLOGY
The study of terrestrial ecology within the study area of 10 km radius has been carried out
through field investigation and satellite imagery data. The area can be classified into the
following ecological zone.
i. Scrub Eco-system (dry evergreen vegetation)
This type of ecosystem is dominated by Phoenix sylvestris species. Apart from typical scrub
jungle species, a few salt tolerant species were also recorded, probably because of the
proximity to the sea and the estuary.
ii. Tidal Eco-system
The plant growing in this area are salt tolerant as they are covered by the saline water during
high tides. The species like Arthrocnemum indicum, Suaeda Maritima are dominating species in
this ecosystem.
iii. Mangrove Eco-system
This type of ecosystem existed in western bank of the river Korattailar. This is dominated by
Avicinnia marine. Sesuvium Portulacastrum & Suaeda Maritima. These plants are periodically
washed by the tides and as result in some areas quick sands are noticed.
iv. Marsh Eco-system
The marshes are essentially fresh water supporting variety of plant. Acacia nilotica and
Azadirachata indica are the common species of the study area.
v. Agro Ecosystem
Rice and banana species of plant are the main species of this ecosystem.
ENVIRONMENTAL IMPACT ASSESSMENT REPORT
48
vi. Flora
The field investigation and satellite imagery data show, that the study area is a mixture of
agricultural, wasteland and get irrigated by the tanks and tube wells.
The dry tropical vegetation is observed within the study area. The experimental finding of the
pre monsoon season shows the dominance of grasses like Cyanodon followed by Parthenium
hysterophorous, Croton sparsiflorus & Odina odiya and trees like Acacia nilotica, Azadirechta
indica, Anona squamosa, Delonix regia, Ficus benghalensis within the study area.
vii. Fauna
Domestic:
The domestic animals are mainly mammals. The domestic animals present in the study area are
listed.
viii. Wild Animal
Since the natural forests constitute negligible of the forest area and since they are in isolated
pockets, the wild life does not offer a wide spectrum of species. Wild animals are rarely seen
due to absence of natural dense forest and land occupied by human being. The wild animals like
Nilgai, Jackals, Fox and Rabbit have drastically reduced due to increase in human population
and clearance of wild flora for making residential and commercial land. Other than these, some
reptiles and amphibians can also be seen with a number of bird species.
A list of birds, reptiles, amphibians and rodents based on information gathered from local
inquiries is presented.
3.12.5 AQUATIC ECOLOGY
The specific biological species (Fishes, Phytoplankton, Zooplankton etc.) for a particular
environmental condition are the best indicators of environmental conditions are the best
indicators of environmental quality. Information on the environmental stress due to the
impacts of any industrial activities on the community structure serves as inexpensive and
efficient early warning and control system to check the effectiveness of the measures to
prevent damage to a particular ecosystem.
ENVIRONMENTAL IMPACT ASSESSMENT REPORT
49
a. Planktons
Phytoplankton and Zooplankton are indicators of environmental stress. The quality and quality
of such biological species in a particular environmental largely depends on various
physicochemical characteristics of water such as pH, Conductivity, nutrients, BOD, alkalinity etc.
b. Fishes
The fishes/ aquatic fauna of the study area is reported based on the field sampling and
confirmed by the local people and secondary data provided by Thiruvallur district office is listed.
The fishes like Chirocenttrus, Lesser Sardines, Thriossocles, Anchoviella, Flying Fish, Sciaenids,
Caranx, Meckerel, Seer, Crabs found in good number in the study area.
Table 3.19 List of Zooplankton identified within the Study Area
S.No Zooplankton 1. Favella species 2. Tintinnopsis species 3. Globigerina Species 4. Acartia donae 5. Acartia erythraca 6. Acartia clansi 7. Calanns finrnarchicns 8. C furcatns 9. Paracalanus parvus 10. Microsetella norvegica 11. Microsetella rosea 12. Capilla Vitrea 13. Corycaeus danae 14. Oithona rigida 15. Oncacea venusta 16. Gastropod veliger 17. Barochinnous Unceolaris 18. Barochinnous Candatns 19. Monostyla bulla 20. Nancocalanus minor 21. Paracalanus parvus 22. Labidocera acuta 23. Euterpina acutifrous 24. Microsetella norvegica 25. Microsetella gracilis 26. Metis jousseaumei 27. Copilia vitrea 28. Corycaeus danae
ENVIRONMENTAL IMPACT ASSESSMENT REPORT
50
29. Oithona bervicornis 30. Oithona rigida 31. Oncacea venusta 32. Bivalve veliger 33. Gastropod veliger 34. Copepod nauplius
3.13 SOCIOECONOMIC ENVIRONMENT
Socio-economic condition of the area was studied and has been described in this section. In
2011, Ponneri Taluk had population of 389862 of which male and female were 195181 and
194681 respectively. In 2001 census, Thiruvallur had a population of 946949 of which males
were 1876062 and remaining 1852042 were females.
Average literacy of Thiruvallur in 2011 were 2791721 of which male 1495711 and female were
1296010.
In census enumeration, data regarding children under 0-6 years of age is also collected for all
districts including Thiruvallur. There were total 405669 children under age of 0-6. Of total
405669 male and female were 208449 and 197220 respectively.
ENVIRONMENTAL IMPACT ASSESSMENT REPORT
51
Table 3.20 Population Status Of Nearest Towns (As Per 2011 Census)
S.N
o
Name of the
Villages
No. of
House
Holds
Total Male Femal
e
0 - 6 SC Population ST
Population Literates Cultivators
Male Female Male Female Male Female Male Female Male Female
1. Ponneri
Town 100866 389862 195181 194681 21900 20936 61814 62280 3946 3996 149414 126595 6129 1509
2. Minjur
Town 7048 28337 14168 14169 1579 1381 4627 4747 24 34 11813 10488 159 34
3. Padianallur
Town 5912 23819 12043 11776 1380 1222 995 999 33 35 10040 9132 81 11
4. Nallur
Town 4887 19595 9843 9752 1152 1166 1062 1082 121 122 7991 6945 13 2
5. Arani Town 3328 12833 6392 6441 678 694 985 1035 193 177 5066 4174 53 21
6. Edayanchav
adi Toewn 3142 12119 6042 6077 567 584 707 695 3 2 4969 4371 14 0
7. Athipattu
Town 2762 11034 5623 5411 677 580 2251 2254 147 152 4454 3751 6 4
8. Alamathi
Town 1894 7424 3790 3634 445 443 1166 1077 35 27 2923 2421 27 11
ENVIRONMENTAL IMPACT ASSESSMENT REPORT
52
Table 3.21 Population Status of nearest Villages (As per 2011 Census)
S.No Name of the Villages
No. of
House
Holds
Male Female Total Literates Cultivators
Agriculture
Labours SC Population ST Population
Male Female Male Female Male Female Male Female Male Female
1 Nalur 1655 6238 3146 3092 355 329 1427 1367 42 11 2452 2079 239 117
2 Nandiambakkam 1511 6268 3156 3112 359 360 1034 1014 280 269 2542 2275 78 11
3 Neithavayal 1400 5525 2777 2748 308 292 1773 1780 67 70 2109 1804 43 12
4 Pulicat 4619 17925 8915 9010 1160 1036 1157 1236 536 580 6320 5650 53 22
5 Sholavaram 2432 9397 4662 4735 534 536 1569 1555 153 156 3642 3329 137 58
6 Thangalperumbalam 573 2095 1083 1012 136 128 240 214 0 0 744 549 25 6
7 Thatchoor 1700 6584 3298 3286 406 377 669 665 41 44 2463 2137 150 23
8 Vallur 2993 11935 6089 5846 663 646 3958 3845 14 15 5040 4061 48 29
9 Vichoor 1437 5765 2868 2897 311 289 1443 1482 5 4 2211 1896 209 34
10 Voyalur 781 3114 1566 1548 152 158 751 723 37 38 1103 855 52 22
53
3.14 BASELINE STATUS SUMMARY
The findings of baseline environmental status of the study area are summarized below:
The monitored ambient air quality in the study area was found to be in compliance with the
National Ambient Air Quality (NAAQ) Norms of 100 µg PM10/m3, 60 µg PM10/m3, 80 µg
SO2/m3 and 80 µg NO2/m3 for Residential, Rural and other areas.
Ambient equivalent noise levels (Leq) during day and night times were found to be well
within the MoEF Norms.
The water quality of surface waters was found to be in compliance with CPCB norms.
The ground water quality was found to be in compliance with the IS:10500 Norms.
The absence of Oil & Grease, Phenols, Cyanides, low BOD & COD levels, trace metals below
their detectable limits, etc. confirm the fact that the water quality in the vicinity was not
getting polluted due to any industrial activity.
The soil in the study area would very well support vegetation after amending it suitably.
Presence of number of phanerophytes (shrubs and trees) and therophytes (annuals)
indicates semiarid vegetation structure in the study area.
There is no Wild Life Sanctuary or National Park or Biosphere or Hotspots within the study
area of 10 km.
Domesticated animals and common fauna only exist in the study area.
The area is thinly populated. All the villages are electrified, road connected and provided
with water supply. The basic amenities are there almost at all villages.
Thus, there is adequate buffer for the proposed Project in the physical, biological and edaphic
environments of the study area.
The project is proposed in an industrially backward area. There are significant numbers of non-
workers in the area and the project would provide direct or indirect job opportunities to them. Also,
there will be some migration of labour force from outside also during construction phase which may
result in social stress on the local settlements. However, this impact is envisaged to be marginal and
temporary in nature.
Thus, the overall impact on environment during construction phase due to the proposed Project
would be short term and insignificant.
54
CHAPTER 4
4.0 ANTICIPATED IMPACTS AND MITIGATION MEASURES
4.1 INTRODUCTION
Impact assessment describes identification and appraisal of various impacts due to the proposed
project.
"Environmental Impact" can be defined as any alteration of environmental conditions or creation of
a new set of environmental conditions, adverse or beneficial, caused or induced by the action or set
of actions under consideration. Generally, the environmental impacts can be categorized as either
primary or secondary.
Primary impacts are those, which are attributed directly by the project
Secondary impacts are those, which are indirectly induced and typically include the
associated investment and changed patterns of social and economic activities by the
proposed action.
The proposed bridge project will improve the natural and social environment if proper mitigation
measures are adopted in the design phase, construction phase and operation phase. The potential
impacts due to bridge will be minor and for well be limited to construction phase only. The
environmental scenario in the entire sketch described in earlier chapters has revealed that there are
certain environmental issues, which may cause adverse impact.
The construction works for the project comprise the construction of the bridge across waterways of
the Pulicat Lake, construction of the additional paved and unpaved approach roads to the bridge,
carriageway and rehabilitation of existing structures and construction of road safety and
appurtenance works. These activities are expected to contribute to enhancement in transport
capacity, speed, connectivity between the kuppams on seaside and the main route to the Chennai.
The most important utility of the proposed bridge is very useful as an escape root for those reside in
the island kuppams as well as transporting emergency response operations required for
humanitarian aid, personnel and equipment to the affected site and thus it gives the transport
safety. Among other factors which lead to the economic growth of the island kuppams due to the
connectivity the potential impacts due to the proposed project of the bridge construction are
summarized hereunder along with the mitigation measures.
4.2 IMPACT ASSESSMENT MATRIX
From the Table-4.1 significant impacts are identified.
55
TABLE 4.1 IMPACT IDENTIFICATION MATRIXES
Activities ENVIRONMENTAL ATTRIBUTES
Air Noise Water Land & soil Ecology Socio Economics Aesthetics
Site Clearing & Leveling
√ √ √
Construction & Erection of Plant
√ √ √ √ √
Operation √ √
Development of Greenbelt
√ √
Employment Generation
√
4.3 GENERAL
In this chapter, anticipated environmental impacts and proposed mitigation measures for the
proposed bridge has been elaborated. Impact prediction is a way of mapping the environmental
consequences of significant aspects of the proposed plant.
4.4 IMPACTS AND MITIGATION MEASURES DUE TO PROJECT SITING
The project site is located in the premises. And so it does not involve land acquisition or revamping
activities. Further the land falls under non-planning area.
The existing roads will be used for transportation during construction phase.
4.5 IMPACTS AND MITIGATION MEASURES DURING CONSTRUCTION PHASE
Use of the existing roads for hauling is to be avoided. If unavoidable, the roads are to be first
strengthened and/or widened so that the present users can continue to use the road and not
severely affected by the hauling operations. Alignment of the haul roads is to avoid agricultural lands
to the extent to the extent possible. In unavoidable circumstance, suitable compensation is to paid
to the people whose land will be temporarily acquired for the duration of the operations. The
compensation is to cover for loss of income for the duration of temporary acquisition and land
restoration. Prior to the construction of haul roads, topsoil is to be preserved and may be used for
tuning of the embankment. Water tankers with suitable sprinkling system are to be deployed along
the haulage roads. Water shall be sprinkled regularly to suppress the airborne dust due to the
dumper/truck movement. The required frequency is to be determined as per site conditions.
Truck/dumpers deployed for the material transportation are to be spillage proof In any case, all haul
roads are to be inspected at least once daily to clear accidental spillage, if any Material stacking sites
56
are to be access controlled for unauthorized entry people grazing cattle and stray animals; Haulage
roads are to be restored with a wearing coat after completion of the operations. The restoration
shall be conforming to the MOST specifications and left for the use by local communities. The
impacts of the construction phase of the project on the environment are as follows:
4.5.1 LAND DISTURBANCE
The present project does not involve any removing of vegetation and reshaping topography as the
land is vacant and leveled.
4.5.2 AIR IMPACT
The major source of air pollution during construction period is from the movement of vehicles for
construction activity. The emissions are from the stationary sources like generator sets during
emergency service only, and air borne dust emissions from cutting and filling of soil and vehicular
movements. The exhaust emission along with the dust emissions resulting from vehicles operating at
site will also add to air impact. Dust suppression by spraying of water will reduce these impacts
considerably. The emission from vehicles will depend on the type and capacity of the vehicles used.
The impact due to additional vehicles plying during the construction period is of temporary nature
and their impact on air quality will not be significant.
4.5.3 NOISE IMPACT
The major sources of noise pollution due to construction activity is from leveling and compacting,
trucks for transportation of construction materials, concrete mixers, asphalt mixing and laying
equipment all add to the general noise level. The noise generated from all construction activities will
be restricted to daytime working hours. Generally the noise will be limited very much within the site
boundary except noise of piling work for pile foundation, the trucks entering and leaving the site.
Hence, noise impact is expected to be minimal. Further the noise impact during construction will be
temporary in nature. The noise level will drop down to the acceptable level, once construction
period will be over.
4.5.4 WATER IMPACT
The impacts on water quality during construction phase mainly arise due to site cleaning,
leveling, excavation, storage of construction material, etc. Ground water will be used for
construction work. The construction phase of the proposed construction will have impact on
ground water. But after construction phase there will not be any water requirement.
57
4.5.5 ECOLOGICAL IMPACT
The proposed High Level Bridge with approach roads will only involve the felling of about 26 trees within the
Row. Out of 26 trees, only 3 trees of Babul species are coming within the Row on the mainland before the Lake
water on Jetty side. Rest of the trees which are mostly palm trees are coming within the Row on island portion
of the Light House Kuppam. Before the construction work starts, many of them will have to be felled for the
proposed Project. The extent of the trees to be felled is to be determined during the detail design stage.
During the detail design stage, the design-construction contractor has to explore all possible options to keep
the number of trees to be felled to a bare minimum keeping the objectives of the proposed project. Most of
the trees within the right of way do not have any significant ecological and/or commercial value but are
planted at random.
The clearing operations of the right of way will not have any other impact on the environmental
attributes as the number of trees to be felled is meager in quantity.
4.5.6 SOCIO-ECONOMIC IMPACT
The construction workers will be mainly employed from the adjacent villages. There will be
considerable beneficiary impact on social life of the people around the site. Displacement of the
people is not required, as site is free of habitation. Therefore, livelihood of the people will not alter.
Hence rehabilitation & resettlement (R&R) is not required.
4.6 IMPACTS AND MITIGATION MEASURES DURING OPERATIONAL PHASE
4.6.1 AIR QUALITY
The proposed desalination plant will not have any pollutant emission in form of SO2, NOx, and SPM
as there is no fuel involved in the process.
4.6.2 WATER QUALITY
Water supply will be expected to fulfill the entire requirement; however, it is also proposed to
design a sewage treatment plant in such a way that sewage can be recycled for green belt
development and toilet flushing. Effluent generated will be
Generated waste water shall be treated to meet the liquid waste discharge limit. All plant process
drains and plant surface drains after suitable treatment. The waste water generated from the blow
down, bleed off and regeneration will be sent to the effluent treatment plant. The treated water will
be used for dust suppression and greenbelt development.
58
4.6.3 NOISE IMPACT
The exact noise level generation from working place will be identified only after commissioning of
the plant. The operational noise levels of the plant will be measured once the operation of the plant
starts. All units would be housed in closed buildings, which would considerably nullify any
transmission of noise to the outside environment. Maintenance and operating personnel working
within the plant would be provided with adequate personal protection against noise. All the
equipments in the plant are designed/operated to have the noise level not exceeding 85-90 dB(A)
measured at a distance of 1.5 m from the equipment. Also, all the measures would be taken to limit
the noise levels at the plant boundary within stipulated limits.
4.6.4 NOISE MODELING
Noise modeling is done based on the wave divergence formula. Based on this, the sound pressure
level generated by a noise source decreases with increasing distance from the sound source due to
wave divergence. The basic formula for the noise reduction is given below:
Lp2 = Lp1 � 20 log (r2/r1) where,
Lp2 = Sound pressure level in dBA at receptor at r2 from the source
Lp1 = Sound pressure level in dBA at a distance of r1 from the source
Noise level at the plant boundary is calculated considering the natural attenuation. This calculation
was done based on the divergence formula. The noise impact of the proposed desalination plant is
negligible and the impact can be considered as insignificant.
4.6.5 SOLID WASTE
No much solid waste will be generated from the proposed desalination plant. Any minimum waste
generated shall be disposed off through authorized recyclers or to authorized buyers adhering to
Polluters Pays Principle. Proper disposal of solid waste and its management will not pose any
contamination problem to the surrounding environment. No impacts are envisaged due to disposal
of solid waste.
4.6.6 SOCIO-ECONOMIC IMPACT
Proposed site has no inhabitation, permanent structure, vegetation and wildlife. Hence
rehabilitation issues are not involved that could alter the existing socio-economic pattern. Most of
the people around the site have an income directly or indirectly from the proposed project.
Secondary employment will also be generated due to this project, which will enhance the income of
surrounding population.
59
4.6.7 ECOLOGY AND SENSITIVE LOCATIONS
There are no National Park, Sanctuary, Elephant/Tiger Reserve, migratory routes/wildlife corridor
within 10 Km of the project site. The predicted background pollutant concentrations are expected to
be within NAAQS limit. Hence this will not cause any adverse impact on flora and fauna of the
surrounding area. Additional plantation will be done in the area earmarked for greenbelt. This will
improve the aesthetic look of the surrounding area. Neither liquid effluents nor air emissions would
be causative for any adverse impact on flora and fauna.
Greenbelt is developed inside the factory premises covering a total area of about 2.83 Acres. The
unit will also develop the nearby area around the industry for greenbelt. The inter-spaces are laid
with shrubs. The inter-space between trees planted is about 5m. It is proposed to double the tree density in
future.
4.6.8 NOISE & VIBRATION
Both the construction and operation of the proposed high level bridge induce noise impacts. While
the noise impacts during the construction stage can be largely controlled, operation stage impacts
are generally beyond the purview of the department of highway authorities. The sources that cause
much of the noise are the vehicular noise and the noise generated by the construction equipments
4.7 IMPACT MITIGATION
Noise induced by the construction activities is generally intermittent and depends on the type of
specific operation, location, function, equipment usage cycles and attenuates quickly with distance.
Impacts of noise during the construction activities can be largely controlled by the following
measures.
All equipment vehicles deployed for the construction activities shall not be older than 3 years and
regularly maintained.
Work force likely to be exposed to noise leves beyond the theshould limits is to be provided with
protective gears like ear plugs, ear muffs etc. Rotation of personnel which get exposed to noisy
environment, every four hours should be considered as a supplement measure.
Limiting the operations to daytime only particularly in the human settlement areas.
60
Due to the proposed project, the existing settlements near the project site will be exposed to
reatively lower vehicular noise as compared to the present situation due to the smooth traffic flow.
Improved geometries and existing road conditions of the Project will contribute to the reduction of
noise levels.
The Project design characteristics will ensure a more uniform speed as compared to the present
situation. Frequent acceleration/deceleration of the vehicles contributes to increased noise levels.
No blasting work will be carried out for the proposed project work.
4.8 AQUATIC FLORA AND FAUNA
4.8.1 POTENTIAL IMPACTS
The aquatic flora, fauna and the sediment quality are going to affect moderately. The food chain of
bottom dwelling organisms, particularly small fish or prawns moving in and out of the lake water
may get affected during this recuperation period. The construction debris may cover the bottom
dwelling organisms and disturb the food chain.
4.8.2 Impact Mitigation
The benthic flora and fauna in the lake water should be least disturbed. Sediment quality with
respect to the heavy metals is to be watched during the post development stage which is of concern
to the contamination of the lake water in the construction zone.
4.9.0 Fisheries Resources
4.9.1 Potential Impacts
Although the fish spawing grounds and fish catching areas are far away from the project site, there
will migration of some of the marine fisheries that take shelter in and around the project site
especially during the construction period.
4.9.2 Mitigation Measures
Construction operations should be carried out properly with at most care during the breeding
seasons of fishes (July - September). Furthermore dumping of construction waste in the lake water
will be strictly avoided and will be disposed in safe manner at appropriate locations considering the
consequences of the proposed activity. The objective would be to ensure clear of lake water from
any potential contamination arising from the waste due to the construction.
61
4.6.9 RAINWATER HARVESTING
Rain Water Harvesting:
Source: Rain water from open areas
RWH system includes:
Storm water manholes/channels
Sumps
a) Change in surface permittivity and grading
Construction of bridge and roads will change the natural characteristic of the surface. Addition
of impervious surface could add to marginal increase in runoff, which in turn could lead to soil
erosion in case that soil is improperly vegetated.
.
62
CHAPTER 5
5.0 ENVIRONMENTAL MITIGATION ACTION PLAN
5.1 GENERAL
The IEE of the proposed project of High Level Bridge proposal has identified the broad Impacts and
their mitigation measures. An environmental mitigation action plan (EMAP) has been drawn up for
implementing the mitigation measures. The EMAP is presented in Tables 5.1. The IEE report along
with EMAP are to be appended to the construction contracts to do so that the prospective
contractor is clearly aware of the environmental requirements of the proposed project works and
accordingly provide for the same in their bids.
5.2 ENVIRONMENTAL MITIGATION ACTION PLAN
The EMAP broadly comprise;
� Identification of the project action(s) and the environmental attributes those are likely to be
impacted.
� Appropriate mitigation and/or environmental enhancement measures
� Responsible agency for the implementation of the mitigation measures.
� Environmental management and monitoring plan.
5.2.1 ISSUES/PROJECT ACTIONS/ENVIRONMENTAL ATTRIBUTES:
The project actions, which generally induce environmental Impacts, are clearing operations of the
ROW, temporary traffic diversions during construction period, construction of campsite, haulage
roads, quarry and broowing operations, hauling construction materials, construction of foundation,
substructure and super structure, air and noise pollution at all operational areas from the
construction equipment, plant and machinery, effects on aquatic flora and fauna, sanitation in
workforce camps and plant sites among others.
5.2.2 MITIGATION MEASURES
Appropriate mitigation and/or environmental enhancement measures have been identified for the
different environmental attributes, which are likely to be impacted upon.
63
5.2.3 RESPONSIBILITY FOR IMPLEMENTATION
The EMAP is to be appended to the construction contracts so that the prospective contractor should
aware of the environmental requirements of the proposed construction of the High Level Bridge and
accordingly provide for the same in their bids. The implementation of the EMAP by the contractor is
to be monitored by the Project Implementation Unit (PIU). The concerned Officer(s) under PIU will
oversee and monitor the implementation of EMAP on a day to day basis.
The institutional arrangements for implementation of EMAP are described under Chapter 6.0.
5.2.4 ENVIRONMENTAL MANAGEMENT MONITORING FREQUENCY
A Monitoring mechanism in the form of a control matrix has been framed for overseeing the
implementation of the EMAP. The control matrix is presented in Table 5.2.
5.3 TECHNICAL SPECIFICATIONS AND CONDITIONS OF CONTRACT
The proposed project of the High Level Bridge will adhere to the Technical Specifications based on
the Ministry of Road Transport and Highways Specifications for Road and Bridge Works{1995) and
the conditions of contract. Provisions for protection of environment are included in these
documents, The Specification has, for instance a number of clauses relevant or environmental
concerns. Clause 111 (Precautions for strengthening the Environment) has general requirements for
borrow-pit location, quarry operations control of erosion and pollution, as well as hazardous
substances. The Scope of works (clause 105) specifies attention to first
aid, adequate sanitary arrangements, and regular clearance of rubbish and clearing-up and
restoration of site. Clause 201 on site clearance has requirements to preserve the roadside trees, for
monuments not to be disturbed and for control of erosion and water pollution. It also provides for
removal of roots, overhanging trees and wastes. Clause 306 (Soil Erosion and Sedimentation Control)
provides for provision of terms, sediment basins, fibre mats, mulches grasses, slope drains and other
devices to be specified, or directed. It also provides for minimization of areas opened and corrective
actions at Contractor's expense.
64
TABLE 5.1: ENVIRONMENTAL MIGRATION ACTION
Project Actions / Environmental Attributes
Mitigation Measures Responsibilities
ENVIRONMENTAL MITIGATION PLAN FOR CONST RUCTION STAGE
Setting out and
clearing operations
of ROW
� A two-mom school building and compound
wall of the hospital are to be
constructed/relocated to adjacent locations
in close consultation with local community
leaders.
� Re-location of utilities to adjoining areas of
the Proposed Project.
� Permission for tree felling is to be obtained
from the concern tree cutting authorities or
Department of Forests, Government of
Tamil Nadu.
During right of way clearing operations, any
treasure trove, slabs with epigraphically
evidence or edicts, sculptural or any
material are found and appear to have
historical importance, it should be brought
to the notice of Department of Archaeology,
Government of Tamil Nadu.
The Project implementation
Unit (Highways Department,
Government of Tamil Nadu)
will be required to initiate the
actions for seeking the
permission of tree felling and
re-location of the public
structures/public utilities
within the corridor of Impact.
PI U will co-ordinate and
ensure implementation and
ensure adequacy &
appropriate implementation.
Diversion of traffic Appropriate traffic diversion schemes shall
be implemented so as to avoid
inconvenience due to project
operations to present road users,
particularly during right time.
Proper diversion schemes will ensure
smooth traffic flow which minimizes
accidents, traffic snirl ups, and
commotion.
The diversion / Warming Precautionary
signs should be bold and clearly visible
particularly at night.
Diversion schemes particularly near lake
water (Jetty) should consider the ferrying
of the boats on either side of the lake.
Contractor is responsible for
implementation under
approval from PIU.
PIU will co-ordinate and
ensure implementation and
ensure adequacy & appropriate
implementation
65
� All project operations shall have proper
cladding wherever necessary.
Construction The construction campsite is to be located
away from any local human settlements
and preferably located on lands, which
are not productive presently. The camp
shall have adequate water supply,
sanitation and all requisite infrastructure
facilities. This would minimize
dependence of construction personnel on
outside resources, presently being used
by local populace and minimize
undesirable social friction thereof. The
water supplied to the construction camps
shall be free from Arsenic contamination.
All facilities are to be planned
and implemented by the
contractor under approval by
PIU.
PIU will monitor and ensure
appropriate implementation.
The concerned PIU
personnel will visit the camp
sites at least once in a week for
inspection and compliance.
Camp Sites
� The camp shall have septic tank pit of
adequate capacity so that it can function
property for the entire duration of its use.
� The construction camp shall have rationing
facilities particularly for kerosene/LPG so
that dependence on firewood for cooking is
avoided completely to the extent possible.
The construction camp shall have health
care facilities for adults, pregnant women
and children. All construction personnel
shall be subjected to vaccinations and other
preventive/healthcare measures.
Haulage roads � The alignment of haulage roads (in case of
new ones) transportation link shall be
finalized to avoid the regular routes to the
extent possible. In unavoidable
circumstances, suitable compensation may
be paid to the people whose land will be
temporarily acquired for the duration of
operations. The compensation shall cover
for the loss of income for the duration of
the acquisition and land restoration.
Prior to construction of the approach roads
/ Bridge, topsoil if found suitable and free
The planning, design and
construction / up-gradation of
the existing roads to be used as
haulage roads are
responsibilities of contractor
under approval by PIU.
The concerned PIU
personnel will regularly
monitor and ensure
appropriate implementation.
The PIU personnel will co-
ordinate regularly with the
66
from the adequate silt, shall be preserved
or at least shall be used for any other
useful purposes rather than allowing its
loss by construction activities.
villagers to ensure that their
interests are protected and no
social resentment sets in.
Water tankers with suitable sprinkling
system are to be deployed along the
transportation links. Water, may be
sprinkled with required frequency as per
site conditions all along the site to suppress
the airborne dust due to the truck
movement particularly on unpaved roads.
Roads, which are subjected for huge
material movement, provision for sprinkles
can be made which may become
economical as compared to water
sprinkling by tankers.
The vehicles deployed for material
transportation shall be spillage proof to
avoid or minimize the spillage of the
material during transportation. In any case,
the transportation like are to be inspected
at least twice daily to clear accidental
spillage, if any
The borrow and material dumping sites
must be access controlled to keep away
unauthorized entry of people, grazing cattle
and any other stray animals.
Use of the existing roads should be avoided
for h hauling of materials. If unavoidable,
roads are to first properly strengthen and
for widened so that existing users can also
continue to same road alongside in
dedicated tracks.
After completion of hauling, wearing coat
must be replenished and roads handed
over to local use.
Work sites � All personnel in the work site shall have
protective gears like helmets, boots etc.
so that injuries to the personnel are
All facilities are to be planned
and implemented by the
contractor under approval by
67
minimized.
Children and pregnant women shall not
be allowed to work under any
circumstances.
No personnel shall be allowed to work at
site for more than 10 hours per day.
Personnel who are likely to be exposed
to noise levels beyond stipulated limits
shall be provided with protective gears
like ear plugs etc. and regularly rotated.
Regular water sprinkling of water shall
be ensured so that dust levels are kept
to minimum
PIU.
�
PIU personnel will monitor and
ensure appropriate
� Implementation.
Construction
Equipment and
Vehicles
� All equipment�s / vehicles deployed for
construction activities shall be regularly
maintained and not older than 3 years.
� Vehicles / equipment�s deployed for
construction activities shall be regularly
maintained for smooth operation, a
measure contributing to air quality and
noise levels.
� Vehicles / equipment�s shall be regularly
subjected for emission tests and shall have
valid POLLUTION UNDER CONTROL
certificates. Revalidation of certificates
shall be done once in a month.
� All vehicles deployed for material
movement shall be spill proof to the extent
possible.
In any case all material movement routes
shall be inspected daily twice to clear off
any accidental spills.
Contractor is responsible for
ensuring provision of facilities
under approval by PIU.
The concerned PIU personnel
and other team members of
the PI U will monitor and
ensure appropriate
implementation.
Water Quality &
Drainage Pattern
Impacts arising out of the construction of
the High Level Bridge across the Pulicat
Lake are not likely to impact drainage
pattern of the water.
Adequate precaution is to be taken to
prevent oil / lubricant / hydrocarbon
The planning and construction
of new chute drainage
structures along the approach
roads are responsibilities of the
contractor under approval by
PIU.
The concerned PIU personnel
68
contamination of lake water beds.
Spillage if any shall be immediately
cleared with utmost caution to leave no
traces.
� Channel beds are to be cleaned up and
restores to its previous state after
completion of construction but prior to
onset of monsoon.
The sections on both the sides of the
proposed construction site are to be
improved up to a distance of at least 100
m on either side to ease the water
passage in consultation with the PWD,
Government of Tamil Nadu.
Adopting mitigate measures like cessation
of operations intermittently for limiting
turbidity, limiting hours of operation to
day time hence recuperation of
turbidity, strict prohibition of disposal of
solid and liquid waste disposal into waters
etc. Good sanitary and hygiene practices
on Lake Waterbeds etc. can largely
minimize Impacts on water quality during
the construction of bridge across the Lake
water. In any case such impacts will be
short term and transitory in nature.
will regularly monitor and
ensure appropriate
implementation.
Borrow areas � Prior approval of all the borrow areas must
be taken from Local concerned regulatory
authorities.
Borrow areas are to be demarcated with
signboards. All operational areas are to be
access controlled particularly for locals and
for gazing cattle.
� The top soil recovered from borrow areas
are to be restored or to be used for turfing
of embankment of the approach road
� All equipment deployed for excavation
shall have appropriate monitoring and
control facilities to improve accuracy of
Sourcing of borrowing
materials and all related
activities like planning and
deployment of the most
optimum number of vehicles
without disregarding the
existing uses in case of exist
linkages and construction/up
gradation of existing / new
haulage roads under approval
by PIU
The concerned personnel lof
69
positioning and excavating depths.
� Scrapping & tamping of the borrowed
areas shall be carried out to minimize
localized depressions & render a smooth
profile.
� Limit operations to day house only.
Rotation of personnel should be
considered to minimize exposure of noise
levels beyond limits.
� Provide protective gear like ear plugs if
necessary to operating personnel which
are likely to be exposed to noise levels
beyond threshold limits.
� All equipment deployed shall be well-
maintained and meet emission norms of
diesel vehicles.
� Demarcate areas identified for operations
and install signboards in regional language
prohibiting unauthorized movement of
locas, similarly personnel / labour
operation on borrow areas shall be
restrained to move in areas which are not
under operation. Movement it warranted
can be only with authorization.
� No labour camps shall be allowed either in
desilting/borrow areas or any other
location which is not authorized.
All borrow areas are to be re-vegetated
with a drainage facility connected to
nearby watercourses to avoid formation of
cesspools during/after monsoon, the side
walls shall have gentle slope.
the PIU will monitor and
ensure appropriate
implementation.
Air Quality & Noise
Level
� All operational areas under project
development like borrow area, jaulage
roads, work sites, construction camp site,
etc are to be regularly monitored (at least
once in a week) for air quality parameters
such as SPM, RPM, SO2, NOX, HC, CO, Pb
etc.,
Contractor is responsible for
ensuring the occupationally
healthy environment for all
personnel irrespective of
category under approval of
PIU.
70
� This will ensure identification of
operations/areas of concern with regard to
air pollution and mitigation measures such
as water sprinkling for dust suppression,
permitting construction equipment /
vehicles having pollution under control
certificates will reduce work area
concentration for air pollutants like RPM,
SO2, NOX, HC, CO, etc. and therefore does
not contribute to build up of pollutants.
� Like for air quality, all operational areas
under project development shall be
monitored for noise levels representing all
hours of a typical work shift.
This will ensure identification of
operations/areas of concern with regard to
noise pollution, Operational areas include,
work sites, haulage roads, quarries, borrow
sites etc.
Mitigation measures such as provision of
ear plugs, rotation of personnel, ensuring
regular maintenance/lubrication, limiting
operations to day time etc. will contain
noise levels to permissible/threshold
limits.
The concerned PIU personnel
will independently monitor
these parameters at least once
a month with a staggered
schedule as that of contractor.
The PIU will have requisition
services of private or
governmental agencies for
undertaking periodic
environmental monitoring if
necessary to ensure
compliance of contractor in this
regard.
Soil erosion and Measures to ensure embankment
stabilization including selection of less
erodable material, good compaction, re-
vegetation, placement of fabions /riprap or
any suitable measures around bridges and
culverts etc. are included in technical
specifications and contract documents.
The engineering measures for countering
soil erosion, slope protection, drainage
wherever required considered for the
proposed project and detailed in the
project design documents.
� Many of impacts on soil can be significantly
Erosion control/embankment
protection measures as
governed by local site
conditions shall be prepared by
contractor under approval of
PIU
The concerned personnel of
the PIU will monitor and
ensure appropriate
implementation.
conservation
71
mitigated by some of the following
measures.
a) Minimising area of ground clearance only
to the extent required.
b) Balancing the filling and cutting of earth to
the extent possible
c) Avoiding creation of cut slopes and
embankments which are of an angle
greater than natural angle of repose for
locally available soil type.
d) Replanting disturbed area(s) immediately
after disturbance due to construction has
stopped and NOT after construction has
been completed.
Wet Mix Plants � Wet mix plants shall be at least 500m away
from any human settlements and
preferably located on leeward side.
As mentioned elsewhere under this section
all such plant/sites shall be located on
barred/uncultivable lands. Diversion of
cultivable/agricultural lands, even
preferred by local people for economic
gain shall not be allowed unless otherwise
warranted by specific local conditions.
Contractor is responsible for
ensuring an occupationally
healthy and hazard free
environment for all personnel
irrespective of category
under approval areas.
PIU will monitor and ensure
appropriate Implementation.
Loss of Top soil � Clearing operations within the right of way
and at all places of operational areas like
borrow areas, work sites, labour camps,
construction of new/up-gradation of
existing to new haulage roads, wet mix
plants, storage areas etc. shall consider
preservation of top soil to the extent
possible.
The topsoil can be restored to its initial
place after the specific activity is
completed for which the area was vacated,
or for enriching some other place like
embankment slopes for (erosion protective
Contractor is responsible for
ensuring a proper utilization of
fertile top soil under approval
of PIU.
The PIU will monitor and
ensure appropriate
implementation.
72
measure. The topsoil can also be used for
supporting re-plantation activities within
right of way.
Loss of
access
The construction works may often lead to
Temporary loss of the routine access from
one side of the lake to the other side
especially boat ferrying activities.
Efforts shall be directed for minimizing
such situations or suggest and provide the
alternative routes.
The local people shall be taken into
confidence through opening up of the
communication with local populace and
or community leaders.
Contractor is responsible for
ensuring the minimum
disturbance to local populace
due to operations and
provides alternatives wherever
access is lost due to operations
and restores it as soon as
possible under approval of PIU.
The concerned personnel of
the PIU will monitor and
ensure appropriate
implementation.
Location of The location of campsite, storage depots
shall preferably on unproductive lands.
Use of agricultural/cultivable lands shall
not be allowed under any circumstances.
All fuel loading, unloading, storage areas
shall be spill proof, leakage proof and
carried out on impervious/paved areas.
The site shall have suitable system to
drain storm water, sanitary facilities and
should not contaminate Lake Water.
The site shall also have a system for
handling any emergency situation like
fire, explosion etc.
The Contractor is
Campsite,
storage
responsible for ensuring the
depots suggested actions under
approval of PIU.
The concerned personnel of
the PIU will monitor and
ensure appropriate
implementation.
Storage of The areas intended for storage of
hazardous materials shall be
quarantined and provided with
adequate facilities to combat
emergency situations complying all
applicable statutory stipulations.
The personnel in charge of such areas
shall be properly trained, licensed and
Contractor is responsible for
ensuring an occupational
healthy and hazard free
environment for all personnel
also for communities in and
around all operational areas
under approval of PIU
The concerned personnel of
the PIU will monitor and
hazardous
materials (if
required)
73
with sufficient experience.
� The areas shall be access controlled and
entry shall be allowed only under
authorization.
ensure appropriate
implementation.
Tree plantation The tree plantation is to be
implemented for the proposed project for
the retrieval of green cover.
According to the concern tree cutting
authority, such re-plantation should be
implemented.
Along the approach roads near the lake
water or the appropriate location as per
the tree cutting authority instructions,
trees may be planted.
The project implementing
agency High ways Department
will be required to initiate
consultation with the
concerned authorities for
Seeking tree felling permission
and re-plantation plan shall
cover for the maintenance of
the saplings for at least two
years.
The concerned personnel of
PIU will co-ordinate and
ensure implementation of
tree plantation plan during the
implementation period.
Aquatic Flora and � Sediment quality with respect to the heavy
metals is to be watched during the post
development stage which is of concern to
the contamination of the lake water in the
construction zone.
The construction work of the High Level
Bridge should be carried out in a proper
fashion which tends to reduce the
disturbance to the surrounding
environment especially lake water and it
inhabitants i.e. benthic flora and fauna
The concerned personnel of
the PIU will monitor and
ensure appropriate
implementation.
Fauna
74
Project Actions / Environmental Attributes
Mitigation Measures Responsibilities
ENVIRONMENTAL MITIGATION PLAN FOR CONSTRUCTION STATE
Air Quality & Noise
Level
� The major human settlements along the
proposed project which are adjacent to
the project are to be regularly monitors for
air quality parameters such as SPM, RPM,
SO2, NOX, HC, CO, Pb etc.
� The monitoring will determine the extent
of the improvement / deterioration due to
project operation and also ensure
identification of operations / areas of
concern with regard to air pollution.
� Like for air quality, selected sensitive areas
along project corridor like hospitals,
schools, human settlements which were
considered under baseline monitoring
during IEE studies may be monitored for
noise level both during day time and night
level.
� The monitoring may be carried out at least
ONCE in THREE months, each monitoring
lasting for full 24 hours covering both day
and night time.
The monitoring will enable to determine
either improvement/deterioration of noise
level due to operation of the proposed
project and also identify areas which are
experiencing high noise levels as compared
to present situation and necessity of any
noise mitigation measures.
The PIU will take care for the
environmental management
and environmental monitoring
on quarterly basis.
The concerned personnel of
PIU will have to take care of
the monitoring of the air
quality and noise parameters at
least once in three months.
The PUI will have requisition
services of private /
governmental agencies for
undertaking periodic
environmental monitoring.
The PIU is to be responsible for
regular monitoring and
quarterly environmental status
reports.
The tree plantation
within the project
corridor
The green cover of the proposed project
shall be maintained and regularly watered
as per the schedule.
The PIU will have to monitor
the maintenance and upkeep
of vegetation for at least two
years.
75
Lake & Ground
Water Quality
� Monitor water quality for Physico-
chemical parameters as per IS:7961 after
completion of operations and to check the
status of the water quality.
� The monitoring of the lake water may be
carried out at least ONCE in THREE months
for the period of two years
In case of the ground water in settlement
areas near to the project site, sampling will
be done for pre monsoon and post
monsoon seasons for the period of two
years.
The PIU will have to take the
monitor water quality
parameters for at least two
years after the construction
stage.
Aquatic Flora &
Fauna
Aquatic flora and fauna i.e.
phytoplankton�s and zooplanktons will be
monitored of their status after completing
the construction stage of the proposed
project as per IS:7967
The PIU will take care of the
monitoring of the aquatic flora
and fauna.
76
CHAPTER 6
6.0 GENERAL
6.0 INSTITUTIONAL REQUIREMENTS
The institutional requirements for implementation of environmental mitigation action plan are
presented in this section.
6.1 INSTITUTIONAL SETUP AND CO ORDINATION
The monitoring and evaluation of the EMAP is critical activity in ascertaining the effectiveness of
mitigation measures and controlling the adverse environmental impact of the project.
The project implementation Unit (PIU) Department of Highways has the responsibility in
implementing the environmental mitigation measures. The responsibility also includes the notifying
the affected parties, their relocation and notifying the utility departments such as telephones, water
supply, electricity etc. which use the approach roads for providing the utility services.
PIU will get the EMAP implemented by incorporating EMAP requirements in the contractual
agreement along with the provision of penalties to be levied if the contractor fails to comply with
the prescribed conditions.
6.1.1 DEPARTMENT OF HIGHWAYS (DOH)
DOH shall initiate coordination process among the concerned organizations for EMAP
implementation. DOH shall take lead in:
� Reviewing the progress of the projects and plans particularly in respect of the EMAP.
� Reviewing and discussing the salient features of the quarterly environmental status reports
prepared by the concerned authorities.
� Organizing and coordinating training programs for all the PIU and related organizations.
� The PIU (DOH) is responsible for both environmental planning and management. It will also be
responsible for coordinating the environmental related works and ensuring preparation and
implementation of sectoral and project level EMAP for the Proposed Bridge projects.
77
6.1.2 PROJECT IMPLEMENTATION AGENCY / UNIT (PIA / PIU)
The responsibility of implementing the various environmental mitigation measures lies with DOH as
PIU. The responsibility included various tasks such as notifying various affected persons (informal
vendors in this case), utility departments-government and private. Which use road/bridge for
providing utilities.
6.1.3 ENVIRONMENTAL MANAGEMENT & CAPACITY BUILDING
DOH will take initiative at implementation stage for Environment Management & Capacity Building
(EMCB). PIU shall be responsible for:
Review institutional capacity of PIU vis-a-vis environmental management in general and
addressing environmental issues of TEAP in particular.
Identify organizational needs in terms of structure, resources {facilities, and staff), roles and
responsibilities in DOH.
Develop and plan training programme including:
Identification of different training modules covering various courses at different
levels {initial and recurring)
Identification of trainers.
Development of training programs for each module
Development of training material for each module (slides, videos and
information support material)
Planning a training schedule
Development of a mechanism for training feedback assessment.
Conduct or organise training program according to the above program and provide feedback
on the effectiveness of the training.
Coordinate the monitoring and supervision in coordination with ADB in relation to
environmental issues during project implementation by:
Helping to develop uniform codes of practice for construction management that integrate all
relevant environmental concerns upstream in subprojects (based on a review of what
currently exists within the PIU's)
Assisting in supervision of studies to be undertaken under the project, for example study on
noise levels along the project road to be undertaken in order to map the noise levels w.r.t.
sensitive receptors with a view to recommend adequate mitigation measures.
78
6.1.4 PROJECT CONTRACTOR
The project contractor is the lower most agency in the multi-level institutional arrangement. The
contractor shall implement the EMAP measures, enhancement measures and measures as directed
by PIU. The responsibility on the contractor for implementing the EMAP measures shall be built into
contractual agreement that the contractor has with PIU. The PIU shall review and approve the ECR
submitted by the contractor. After approval PIU will forward ECR to ADB. This after review and
monitoring will be submitted to IPM for confirmation to implement of environmental mitigation
measures. Then accordingly report will be submitted to the Asian Development Bank.
6.2 INSTITUTIONAL STRENGTHENING
The implementation of an environmentally sound transport strategy involves a number of
institutions/organizations at various levels, with each organization having a distinct role to play.
Introducing environmental dimensions in formulating and implementing a transport strategy would
require these institutions should have additional responsibilities for ensuring that the strategy does
not result in any significant adverse environmental Impacts.
In order to examine the existing capacities and identify the additional responsibilities that the
concerned Organizations/Institutions shall take up to address environmental issues.
DOH is the apex organization and being the regional planning authority has to be regular interactions
with various concerned Agencies. The existing capabilities of these organization/agencies for
environmental management have been carefully assessed. The envisaged roles and responsibilities
of these organization�s and additional strengthening requirements to meet the environmental
obligations are given in Table 6.1.
79
Organization Roles & Responsibilities Strengthening Required
DOH/ADB Review the implementation of
EMAP
Facilitate implementation of policy
directives/emission laws etc. for
pollution prevention/mitigation by
interacting with various Govt.
Department viz., Environment, PCB
and PWD etc.,
Review the environmental
management capabilities of
implementation contractors to assist
them in developing their capabilities.
Obtain and analyze environmental
information generated by
organizations like TNPCB, or private
agencies etc.
Enhance the capabilities of the
PIU by out sourcing whenever
required. Training coordinated
by DOH to support the
EMCB programme on
� Environmental assessment
� Appreciation of
environmental Impacts and
procedures and
responsibilities for EMAP
implementation,
monitoring & reporting etc.
DOH/ Monitoring of ambient air quality,
noise level, surface and
underground water quality and
aquatic flora and fauna at existing
project locations. Extending
monitoring for post project
monitoring.
Regular report to DOH to enable
enviornmental planning
The contractor will monitor and
ensure appropriate
implementation during the
project construction stage.
DOH will have to operate air
quality, noise level, water
sampling, aquatic flora & fauna
monitoring programme during
post project through the state
PCB or private monitoring
agency which has already have
trained personnel. Training &
relation to Quality Assurance
and dissemination and other
issues as suggested in the
report.
Contractor
80
6.2.1 ROLE OF IMPLEMENTING AUTHORITIES IN CONSTRUCTION PHASE
MITIGATION
Implementing Organizations for construction Stage mitigation
The project implementing authorities like DOH has major role in enforcement mitigation of
measures during construction phase. These measures can be taken care by the contractors assigned
the project under supervision of implementation authorities.
Mechanisms for implementing Mitigation
The project implementing agency shall include a section in their tender document for the project,
which is aimed at getting the mitigation measure implemented during construction stage. Various
points recommended for incorporation as:
� Construction should be scheduled in such a manner that excaved site does not remain exposed
during monsoons.
� Construction should be taken up stage wise to reduce inconvenience to users.
� Covering trucks carrying construction sites for the reasons of public safety, containment of dust
and aesthetics.
� Specifications of noise level for construction equipment. Values recommended are
Drilling 75 dB (A)
Vibrato 75 dB (A)
Dumper 75 dB (A)
Assurance from the Contractor that noise level shall not be exceeded the ambient noise standards of
50 dB (A) during day time and 40 dB (A) as project site is sensitive receptor which includes hospital
and school. Specifications for operating construction equipment away from sensitive receptor,
unless it is not feasible, in which case temporary noise shield to be used.
Specification for the sites to be used for the disposal of the excavated material at the DOH specified
sites.
81
CHAPTER 7
7.0 ADDITIONAL STUDIES
7.1 RISK ASSESSMENT
Any new proposal activity involving any hazardous chemical named or classified in the various
schedules under the Environment (Protection) Act, 1986/Hazardous Waste (Management and
Handling) Rules 1989 attracts compliance with the rules. Though there is no handling of any
hazardous chemicals in this project, a brief risk assessment study was undertaken for the proposed
project.
The major elements of the Risk Assessment include:
Hazard & Operability (HAZOP) Studies for identification of hazards and vulnerable sections of the
storage,
Consequence Analysis for various release scenarios,
Presentation of damage contour for worst damage from fire or explosion
Risk Assessment and
Provision of guidelines for emergency preparedness based on the findings of the risk analysis.
The details of the present study are:
1) Hazard Identification and Visualization of Credible Accident Scenarios
Identification of hazards,
Analysis of past accident data to develop the credibility of worst accident scenarios and
Visualization of Credible Accident scenarios (CAS).
2) Analysis of CAS
Analysis of identified CAS and quantification of effects pertaining to the cases of:
Outflow and releases
Heat radiation
Explosion
Application of damage criteria for heat radiation and explosion.
Presentation of damage contours for worst damages from fire or explosion.
Effect of the proposed project on neighboring areas (including cascade effects if any).
3) Risk Assessment based on the individual Risk Contour Plots and
4) Guidelines for emergency planning and other safety recommendations based on the studies.
82
7.1.1 HAZARD IDENTIFICATION USING PHA TECHNIQUES
This is a construction of bridge project. Hence the corrosive hazard, fire hazard, toxic hazard and
explosive hazard will not be generated in the above project. Hence the risk is not generated in any
area till the work complete.
As per NFPA rating system it has been characterized by the �Diamond Shape� that is actually a
�Square on point� shape. It identifies the hazards of a material and the degree of severity of the
health, flammability, and instability hazards. Hazard severity is indicated by a numerical rating that
ranges from zero (0) indicating a minimal hazard, to four (4) indicating severe hazard. The hazards
are arranged spatially as follows: health at nine o'clock position, flammability at twelve o�clock
position, and instability at three o'clock position. In addition to the spatial orientation that can be
used to distinguish the hazards, they are also color‐coded as follows: blue for health, red for
flammability, and yellow for instability. The six o'clock position on the symbol represents special
hazards and has a white background. The special hazards in use are W, which indicates unusual
reactivity with water and is a caution about the use of water in either firefighting or spill control
response, and OX, which indicates that the material is an oxidizer.
7.1.2 BASED ON FIRE & EXPLOSION INDEX
The next stage of hazard identification involves the estimation of Fire & Explosion Indices for the
project in the facility to give the relative severity of the project from the fire angle. These are
evaluated from the knowledge of the Material Factor, General Process Hazard (GPH) and Special
Process Hazard (SPH) factors. Material Factor (MF) is the measure of the energy potential of a
particular chemical or its mixture with other chemicals. GPH and SPH are evaluated by taking into
account the exotherm or endotherm of a reaction, material handling and transfer hazards,
accessibility, severity of process conditions and possibilities, dust and other explosions, inventory
level of flammable material, etc. The F&EI value is then calculated as the product of MF, GPH and
SPH. Detailed fire and explosion indexing were carried out for the major sections of the proposal.
Fire & Explosion Indices (F&EI) for the entire storage unit in the Plant have been estimated to give
the relative degree of severity of the units using the criteria given below:
83
Index Range Degree of Hazard
1-60 Light
61- 96 Moderate
97-127 Intermediate
128-158 Heavy
>159 Severe
7.1.3 HAZOP STUDIES
Hazard and Operability Study (HAZOP) is a powerful tool for identifying hidden design inadequacies
and understanding operational mistakes that may lead to incidents or accidents. This will, in turn,
help in taking suitable remedial measures.
The principle of HAZOP is that accidents occur when operations are conducted under conditions that
deviate from the desired intentions. Therefore, HAZOP starts by understanding the design intentions
of a particular line or a vessel and finds out meaningful deviations that can occur in the process. The
process then is to understand these deviations and the consequences of these deviations, and
detect which of these consequences will result in a major hazard.
7.1.4 PROBABILITY OF OCCURRENCE
The overall probability of occurrence was found to be extremely low (10-7).
7.2 DISASTER MANAGEMENT PLAN
7.2.1 EMERGENCY PLANNING FOR DISASTER
A major disaster that can be expected in project might be due to cyclones and rare occasion of
Tsunami also. More over Thiruvallur area comes under heavy rainfall area and the flooding of rivers.
7.2.3 ONSITE EMERGENCY PLAN
To meet any major emergency during the construction , the following on site plan are laid down.
Emergency personnel�s responsibilities during normal working hours are as follows:
84
Site controller:
He will retain overall responsibility of the factory and its personnel. As soon as he is informed of the
emergency he shall proceed to the control room and meet the communication officer. His duties
are:
Assess the magnitude of situation and decide for evacuation of staff etc. from their assembly
points.
Direct operational control over areas other than those affected.
Maintain continuous review of possible development and assess in consultation with the
incident controller and other responsible persons for further actions.
Contact senior officers of Fire Bridge, police, medical and factory inspector etc.
Issues authorized statements to news media and ensure that evidence is preserved for
enquiries.
Incident controller:
On hearing of the emergency he will rush to the scene of the occurrence and take over all charge
and report to site controller.
He will:
Direct all operations within the affected area with priorities for safety of personnel,
minimum damage to plant, property environment and minimize loss of materials.
Pending arrival of site controller assume the duties of his part and in particular direct
shutting down, evacuation of plant, areas, ensure that all key personnel and outside help is
called in Report all the significant developments to the site controller.
Fire and Security officer:
He is responsible for fighting. On hearing the alarm he will reach at the site immediately and advise
fire and security staff in the factory in the incidence zone. He will also contact immediately and
advise fire and security staff in the factory in the incidence zone. He will also contact immediately
through telephone or messenger the incident and site controllers that an incident has occurred in
such and such zone. He will open the nearby gate of incidence area and standby to direct the
emergency.
Departmental Heads:
They will report to incident controller and provide assistance as required. They will decide which
member of their staff, they require at the scene.
85
Engineer in-charge and Electricians:
They will report to the site of incident and close down the services as requested by the incident
Controller.
Shift in-charge:
Immediately after he becomes aware of the emergency and its location, he will assess the scale of
the incident and direct all operations within the affected areas with following properties:
Minimize damage, environment, minimize loss of materials
Inform other engineers, assistants as to what services will or will not be required.
Hand over charge of operations to the incident controller when he arrives on scene.
Fire and security officer:
On hearing the alarm, he shall rush to the gate, advise the fire and security staff of the incident zone
and cancel the alarm and on advice of the shift in-charge inform the local fire brigade. He will
through messengers / runner/ telephone (if working) on advise shift in-charge tell the staff to
evacuate the assembly points open the gate nearest to incident site and standby to direct the
emergency. He shall also call out the responsible persons.
First Aid Team:
Member of the first aid team is report to the shift in-charge /incident controller on hearing the
alarm. The first aider shall inform the shift executive in-charge, giving the name of the patient and
destination i.e. the hospital of doctor�s room and request the incident / shift controller to inform the
destination (hospital etc.) advising them about the casualties reaching there.
Fire fighting with Fire Extinguishers:
To deal with fires other than carbonaceous fires which can be dealt with by water suitable fire
extinguishers are required to do the job effectively. It is, therefore, necessary adequate numbers of
extinguishers are kept in readiness at easily approachable places.
Adequate numbers of �fire station� are established, which house and keep in readiness of the
following types of equipment and arrangements:
CO2 Extinguishers
Dry Powder Chemical Extinguishers
Foam Extinguishers
Fire buckets
50mm spray hoses upto 150 m length.
86
Appropriate types of fire extinguishers are provided at conveyor drive heads, crusher house, control
rooms, in machines like stacker, reclaimer, electrical yard, sub-station and other infrastructural
facilities within the premises In the transformer yard, automatic fire detecting and quenching system
are provided for each transformer. This system will come into operation whenever the temperature
of surrounding air exceeds 800oC and spray water over the transformer to prevent spreading of fire
and quench the same. In order to avoid fire in cable galleries, all the power and control cables of
FRLS type (Fire Resistant Low Smoke) are used. In addition fire detecting and fire alarm systems are
installed in the cable galleries.
Inspection:
Fire alarm panel (electrical) would cover the entire plant. Fire Extinguishers in Fire Stations and
machines and other places are periodically inspected by the inspection group.
Emergency telephone number boards are displayed at vital points by the groups. General
inspections for fire are being regularly carried out by the group.
7.2.4 OFFSITE EMERGENCY PLAN
Since it is close to the coastal area and Thiruvallur is more bourne to cyclone and rare occasion of Tsunami
also. More over Thiruvallur area comes under heavy rainfall area and the flooding of rivers, so off site
emergency plan is necessary for the bridge. When the disaster like cyclone or Tsunami it is necessary to involve
Govt. resources to control such emergency.
Probability for OffSite Emergency
S.No Scenario
1. Cyclone
2. Tsunami
87
CHAPTER 8
8.0 PROJECT BENEFITS
8.1 GENERAL
This chapter includes the benefits accruing to the locality, neighborhood, region and nation as a
whole. It should bring out details of benefits by way of:
By constructing the bridge people and students living in the island gets benefit, they can
cross the water by their own.
Improvements in the physical infrastructure by way of addition of project infrastructure
Improvements in the social infrastructure like roads, railways, townships, housing, water
supply, electrical power, drainage, educational institutions, hospitals, effluent treatment
plants, improved waste disposal systems, improved environmental conditions, etc.
8.2 BENEFITS OF PROJECT
In tsunami this area affected lot and people living in the area don�t have facility to escape from
there, so decided to construct a bridge , it will help the people to transport their basic needs from
one side to other side easily. By constructing the bridge the basic needs of all people will be
obtained.
8.3 CONSTRUCTION PHASE
The community structure will be benefited by generation of employment during construction phase.
This particulate project will require more man power to construct the bridge. The local people will
get the employment.
88
CHAPTER 9
9.0 COST ESTIMATE
9.1 EMAP COST ESTIMATE
The broad Cost estimates of the environmental mitigation measures works out to some 13 lakhs.
The construction works of the proposed High Level Bridge have been estimated at about 15 crores
and the estimate is some 1 % of the investment cost of the proposed project. The EMAP cost
estimate along with its breakup is presented in Table 9.1.
Table 9.1: EMAP Cost Estimate
Sl.
No.
Item no. Assumption Rate
Adopted (in Rs.)
Total Cost
(in Rs.)
Construction Phase
1 Air Quality
Monitoring
One representative sample for 24
hours for each location (2x6) samples
for a period of 18 months for two
representative locations.
10,000/-per
sample
1,20,000
2 Noise Monitoring One representative sample for 24
hours for each location (2x6) samples
for a period of 18 months for two
representative locations
1,500/-per day 18,000
3 Water quality
monitoring
Two representative samples that
include one surface water and one
ground water sample Surface Water
(1 x 6) for a period of 18 months
Underground Water (1 x 6) for a
period of 18 months
1000/-per
sample
6,000
6,000
12,000
4 Monitoring of
Aquatic flora and
fauna
1 representative sample along with
its location for aquatic flora and
fauna for a period of 18 months
(1x1x6)
1500/- per
location
9,000
5 Tree Felling
plantation and
26 nos 1400/tree 36,400
89
maintenance for a
period of 2 years
6 Sewage / Effluent
disposal and waste
disposal during
construction
LS 50,000 /- 50,000
7 Dust suppression
Measures
18 months 50,000 per
month
9,00,000
11,45,4 0 Contingencies @ 5% 57,270
Total Amount 12,02,67 0
Operational Phase 1 Air Quality
Monitoring
One representative sample for 24
hours (1x8) samples for a period of 2
years
10,000/- per
sample
80,000
2 Noise Monitoring One representative sample for 24
hours (1x8) samples for a period of 2
years
1,500/-per
day
12,000
3 Water quality
monitoring
Two representative samples that
include one surface water and one
ground water sample Surface
Water (1x8) for a period of 2 years
8,000
Underground Water (1 x 4) for a
period of 2 years
4,000
12,000
4 Monitoring of
Aquatic flora and
fauna
1 representative sample along with
its location for aquatic flora and
fauna for a period of 2 years (1x1x8)
1500/- per
location
12,000
Total 1,16,000 Contingencies @ 5% 5,800
Total /Amount 1,21, 800 GRAND TOTAL 13,24,470
90
CHAPTER 10
10.0 ENVIRONMENTAL MANAGEMENT PLAN
10.1 INTRODUCTION
An Environmental Management brings upon continuity to the EIA Process and helps optimization of
environmental benefits at each stage of project development. Environmental Management Plan
(EMP) is required to ensure sustainable development in the area of proposed project. Hence it needs
to be an all-encompassing plan for which the project, Governing bodies and Regulating agencies like
the Central/ State Pollution Control boards and for the most part the public of the region need to
extend their cooperation and contribution.
Overall, through impact assessment it has been identified that the project area will not be affected
significantly. Mitigation measures at the source level and an overall Management Plan at the site is
elicited in order to maintain and enhance the exiting environment.
In order to keep in line with the social and economic development of the project area, a set of
mitigation measures are recommended towards protecting and conserving the environment.
Construction phase impacts are primarily short spanned and restricted to the proposed project area
and is not to be envisaged to a larger scale.
However, an EMP is delineated on the following;
Mitigation measures for each of the causing the environmental impact,
Monitoring plan for checking activities and environmental parameters and monitoring
responsibilities.
10.2 MITIGATION MEASURES AND ITS IMPLEMENTATION SCHEDULE
Each of the activities during construction and operational phases are considered and suitable
mitigation measures have been suggested.
The below Table elaborates on the mitigation measures for the activities considered to be causing
environmental impact.
91
Activity Environmental Impacts Mitigation Measures
Site Clearing & Construction Air
Land
Water
Noise
Socio economy
Water Spraying during earth work
for dust suppression
Well maintained vehicles will be
used for transportation and
movement of material
Metaled road for Vehicle
movement
Top soil excavated will be
conserved and utilized for
Landscaping and Gardening
Site barricading will be done
during construction
Well maintained equipment will
be utilized to prevent noise
generation
Personal Protective Equipment
will be used by all workers
Labour force will be sourced
locally
92
CHAPTER 11
11.0 FINDINGS AND RECOMMENDATIONS
11.1 FINDINGS
The following are the findings of the IEE of the proposed High Level Bridge across the Pulicat Lake to
Pasiyavaram Village.
� The IEE of the proposed project indicates an economic investment and is beneficial for the local
economy of the Kuppams and villages. In fact the proposed project on the bridge has been earlier
identified as high priority project under the prioritization study and investment plan of the Tamil
Nadu Government.
� The Project is largely confined to the minimum right of way in the lake water. The land acquisition
will be restricted to minimum in waterway as well as on the land. As per the Coastal Regulated Zone
Notification, the proposed will require the CRZ clearance from the Department of Environment,
Government of Tamil Nadu / MoEF, Government of India as per the regulations and their
requirements. Consent for establishment is also required from Tamil Nadu Pollution Control Board,
Government of Tamil Nadu.
� The corridor of Impact/right of way of the proposed bridge project does not traverse through
sanctuary area, reserve forests and sensitive natural habitats.
� The corridor of Impact does not have any historical/archeologically important monuments and
heritage sites.
� The proposed project will involve clearing of a very small number of trees (about 26 in number)
within the RoW. Although the loss of trees due to the proposed project will be apparent on short
term, impacts will not-be significant on long term. As per the stipulations of the Concerned Tree
Cutting Authority, it is mandatory to seek prior permission for tree felling and accordingly saplings
are to be planted for every tree felled during/after the project. The replanted saplings are to be
maintained for at least two years and funded by the project authorities, Department of Highways,
Government of Tamil Nadu.
� The water requirements for construction will be largely met through the water tankers sourced
from outside of the project region.
93
� Project specific haulage roads are to be built and will be replenished with wearing coat after the
completion of hauling. During the hauling operations, measures will be enforced to ensure the
environment protection, namely, sprinkling of water to contain dust, spillage-proof vehicles for
hauling, regular maintenance of vehicles and monthly re-validation of vehicle emission test
certificate. In case, existing road network is to be used, the roads are to be upgraded widened /
strengthened as required so that movement of haulage vehicles will not affect the existing
users/local communities.
� Work force camp for the construction works is to be provided with adequate water supply, septic
tank with soak away pits, health care facilities and rationing of LPG to negate dependence on fuel
wood.
� The IEE has identified likely impacts and has defined mitigation measures in the form of an
environmental mitigation action plan (EMAP). These mitigation measures are to be implemented
and monitored. A control matrix showing responsibilities and monitoring frequency of mitigation
measures is defined. The IEE is to be included in the construction contract provisions so that the
prospective contractors are aware of the environmental requirements of the proposed project and
accordingly provide for in their bids.
� A project implementation Unit (PIU) is required for the implementation of the EMAP. The PIU will
manage and oversee the implementation of the EMAP by the contractors. The environmental
monitoring will be executed by a competent agency on the approved list of the Central Pollution
Control Board, Government of India or Tamil Nadu.
� Provision has been made in the project cost estimate for the implementation of the environmental
mitigation / enhancement measure for both/construction and initial 2-year operation period.
8.2 Recommendations
The environmental attributes likely to be impacted due to the project have been identified, assessed
and appropriate mitigation measures have defined to negate or limit the impacts. An Environmental
Mitigation Action Plan has been suggested for implementation. Therefore, the construction of the
proposed High Level Bridge across Pulicat Lake in Chennai-Pulicat Lake Road to Pasiyavaram in
Ponneri taluk of Thiruvallur district is unlikely to have any long-term impacts. Consequently no
further detailed environmental Impact assessment studies are required as per present and likely
future environmental scenario of the proposed project.
94
CHAPTER 10
10.0 CONCLUSION
The overall assessment shows that the adverse effects on environment are insignificant in comparison to their
benefits and advantages through its proposed activity.
In the light of all the discussions and findings in the preceding sections, it can be concluded that the
construction of the proposed High Level Bridge across Pulicat Lake to Pasiyavaram in Ponneri taluk of
Thiruvallur district will not have any adverse impacts and will be an environmentally beneficial
option contributing to uplift of the economy of the kuppams on the Pasiyavaram side and is very
useful as an escape root for those reside in the island as well transporting emergency response
operations required for humanitarian aid, personnel and equipment to the affected site.