75
Environmental Representative Monthly Report 12 - August 2018 Eden Breakwater Wharf Extension 7 September 2018 Level 17, 141 Walker St North Sydney NSW 2060 Australia 301311-13734-EN-REP-0036 www.advisian.com

Environmental Representative Monthly Report 12 - August 2018 · Environmental Representative Monthly Report 12 - August 2018 Eden Breakwater Wharf Extension 7 September 2018 Level

  • Upload
    others

  • View
    4

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Environmental Representative Monthly Report 12 - August 2018 · Environmental Representative Monthly Report 12 - August 2018 Eden Breakwater Wharf Extension 7 September 2018 Level

Environmental Representative Monthly Report 12 - August 2018 Eden Breakwater Wharf Extension 7 September 2018

Level 17, 141 Walker St North Sydney NSW 2060Australia

301311-13734-EN-REP-0036

www.advisian.com

Page 2: Environmental Representative Monthly Report 12 - August 2018 · Environmental Representative Monthly Report 12 - August 2018 Eden Breakwater Wharf Extension 7 September 2018 Level

NSW Department of Industry Environmental Representative Monthly Report 12 - August 2018Eden Breakwater Wharf Extension

Synopsis

The Environmental Representative Report has been prepared to provide details of the actions and decisions on matters for which the Environmental Representative was responsible under the terms of the State Significant Infrastructure (SSI) Approval granted under the Environmental Planning & Assessment Act 1979 for the Eden Breakwater Wharf Extension (the Project).

Specifically, this Report has been prepared to address the requirements in Conditions A16(l) of the Infrastructure Approval (SSI 7734).

Disclaimer Advisian operates as an independent business line of the WorleyParsons Group. This report hasbeen prepared on behalf of and for the exclusive use of NSW Department of Industry, and is subject to and issued in accordance with the agreement between NSW Department of Industry andWorleyParsons.

Advisian accepts no liability or responsibility whatsoever for it in respect of any use of or reliance upon this report by any third party.

Copying this report without the permission of NSW Department of Industry and Advisian is not permitted.

Project No: 301311-13734-EN-REP-0036 – Environmental Representative Monthly Report 12 - August 2018: Eden Breakwater Wharf Extension

Advisian Rev Description Author Review Approval Date

Rev 0 Issued for review

G Thomson S Mason-Jones

7 Sep 18

S Wakefield /S Mason-Jones

Advisian ii

Page 3: Environmental Representative Monthly Report 12 - August 2018 · Environmental Representative Monthly Report 12 - August 2018 Eden Breakwater Wharf Extension 7 September 2018 Level

NSW Department of Industry Environmental Representative Monthly Report 12 - August 2018Eden Breakwater Wharf Extension

Table of Contents 1 Introduction............................................................................................................................... 1

1.1 Purpose and Content of this Report ................................................................. 1

1.2 Project Description ................................................................................................... 1

1.3 Project Status.............................................................................................................. 2

2 Review and Amendments to the CEMP or Approvals .............................................. 4

2.1 CEMP amendments .................................................................................................. 4

2.2 Infrastructure Approval Amendments .............................................................. 4

3 Environmental Performance ............................................................................................... 5

3.1 Environmental Issues ............................................................................................... 5

3.1.1 Minor Hydraulic Oil Leak.................................................................................... 5

3.1.2 Use of Cordless Hammer Drill .......................................................................... 5

3.2 Weekly Observations ............................................................................................... 6

4 Environmental Monitoring Summary .............................................................................. 7

4.1 Noise and Vibration Monitoring ......................................................................... 7

5 Environmental Incidents / Complaints ........................................................................... 8

Tables Table 3-1: Weekly Environmental Observations ........................................................................................................ 6

Figures Figure 1-1: Piling progress ................................................................................................................................................. 3

Appendices Appendix A: Whale Register ............................................................................................................................................. 9

Appendix B: Piling Construction Noise Monitoring Report (ERM, 2018) .................................................... 10

Advisian iii

Page 4: Environmental Representative Monthly Report 12 - August 2018 · Environmental Representative Monthly Report 12 - August 2018 Eden Breakwater Wharf Extension 7 September 2018 Level

NSW Department of Industry Environmental Representative Monthly Report 12 - August 2018Eden Breakwater Wharf Extension

Acronyms and Terms Acronym/Term

BVSC

Definition Bega Valley Shire Council

CEMP Construction Environmental Management Plan Consistency assessment An assessment of whether a proposed activity for the purpose of

the SSI is consistent with the terms of approval

Construction

Includes all physical work required to construct the SSI, otherthan the following low impact work:

a. Survey works including carrying out general alignment survey, installing survey controls (including installation of global positioning system (GPS)), installing repeater stations, carrying out survey of existing and future utilities and building and road dilapidation surveys, and hydrographic survey;

b. Background and/or baseline monitoring works; c. Investigations including investigative drilling and

excavation; d. Establishment of ancillary facilities in approved locations

or in locations meeting the criteria identified in Conditions A9 and Condition A11 of the approvalincluding constructing ancillary facility access roads and providing utilities to the facility;

e. Operation of ancillary facilities if the ER has determined the operational activities will have minimal impact on the environment and community;

f. Minor clearing and relocation of native vegetation, as identified in the EIS/Submissions Report;

g. Installation of mitigation measures including erosion and sediment controls, temporary exclusion fencing forsensitive areas and acoustic treatments;

h. Relocation and connection of utilities where the relocation or connection does not present a significantrisk to the environment as determined by the ER;

i. Archaeological testing under the Code of practice for archaeological investigation of Aboriginal objects in NSW (DECCW 2010) or archaeological monitoring undertaken in association with [a]-[i] above to ensure that there is no impact on heritage items;

j. Other activities determined by the ER to have minimal environmental impact which may include construction of minor access roads, temporary relocation of pedestrian and cycle paths and the provision of property access; and

Advisian iv

Page 5: Environmental Representative Monthly Report 12 - August 2018 · Environmental Representative Monthly Report 12 - August 2018 Eden Breakwater Wharf Extension 7 September 2018 Level

NSW Department of Industry Environmental Representative Monthly Report 12 - August 2018Eden Breakwater Wharf Extension

Acronym/Term Definition k. Maintenance of existing buildings and structures

required to facilitate the carrying out of the SSI. However, where heritage items, or threatened species, populations or ecological communities (within the meaning of the EP&A Act) are affected or potentially affected by any low impact work, that work is construction, unless otherwise determined by the Secretary in consultation with OEH or DPI Fisheries (in the case of impact upon fish, aquatic invertebrates or marine vegetation). The low impact work described in this definition becomes construction with the approval of a Construction Environmental Management Plan.

DoEE Commonwealth Department of the Environment and Energy DP&E NSW Department of Planning and Environment DPI – Fisheries NSW Department of Primary Industries – Fisheries

Dumping Activities

Defined in the Sea Dumping Permit Variation as: means all activities associated with the dumping permitted under this permit, including:

(i) the loading for the purpose of dumping of dredged material;

(ii) the dumping of the material at the prescribed disposal site

ER The Environmental Representative for the SSI IMC Intermediate Bulk Container

Incident

An occurrence or set of circumstances that: Causes, or threatens to cause, material harm to the

environment, community or any member of the community,being actual or potential harm to the health or safety of human beings or to threatened species, endangered ecological communities or ecosystems that is not trivial; or

Results in non-compliance with the approval. Note: this meaning of “material harm” applies for the purpose of the approval only

Marine Species Means all whales, dolphins and marine turtles listed under the Environment Protection and Biodiversity Conservation Act 1999

MMO Marine Mammal Observer Monitoring zone

The area within a 300 metre radius of the (dredging disposal) vessel

Observation zone During September, October and November a horizontal

radius determined from the piling equipment of 2.2 kilometres

Advisian v

Page 6: Environmental Representative Monthly Report 12 - August 2018 · Environmental Representative Monthly Report 12 - August 2018 Eden Breakwater Wharf Extension 7 September 2018 Level

NSW Department of Industry Environmental Representative Monthly Report 12 - August 2018Eden Breakwater Wharf Extension

Acronym/Term Definition During January, February, March, April, May, June, July

August and December a horizontal radius determined from the piling equipment of 1.5 kilometres

Proponent The person identified as such in Schedule 1 of the SSI approvaland any other person carrying out any part of the SSI from time to time

Sea Dumping PermitVariation

Sea Dumping Permit (SD2015/3102) Variation issued by DoEE under the Environment Protection (Sea Dumping) Act 1981, dated 27 April 2017

Secretary Secretary of the NSW Department of Planning and Environment(or nominee, whether nominated before or after the date in which the SSI approval was granted)

Sensitive receivers

Includes residences, educational institutions (includingpreschools, schools, universities, TAFE colleges), health carefacilities (including nursing homes, hospitals), religious facilities (including churches), child care centres, passive recreation areas (including outdoor grounds used for teaching), active recreation areas (including parks and sports grounds), commercial premises(including film and television studios, research facilities ,entertainment spaces, temporary accommodation such as caravan parks and camping grounds, restaurants, office premises, retail spaces and industrial premises), and others asidentified by the Secretary

Shut-down zone

During September, October and November a horizontal radius determined from the piling equipment of 1.3 kilometres

During January, February, March, April, May, June, JulyAugust and December a horizontal radius determined from the piling equipment of 1 kilometre

SSI The State Significant Infrastructure, as generally described inSchedule 1 (SSE 7734), the carrying out of which is approved under the terms of the approval

Whales Species listed under the Environment Protection Biodiversity Conservation Act 1999 (EPBC Act)

Advisian vi

Page 7: Environmental Representative Monthly Report 12 - August 2018 · Environmental Representative Monthly Report 12 - August 2018 Eden Breakwater Wharf Extension 7 September 2018 Level

NSW Department of Industry Environmental Representative Monthly Report 12 - August 2018Eden Breakwater Wharf Extension

1 Introduction The Eden Breakwater Wharf Extension Project (the Project) includes the extension of the existing Eden Breakwater Wharf and associated dredging.

The Infrastructure Approval (SSI Approval No. 7734) was granted for the Project by the Executive Director, Priority Projects Assessment (as delegate of the Minister for Planning) on 5 July 2017.

The Construction Environmental Management Plan (CEMP) and CEMP Sub-plans have been prepared, approved by the Secretary of the Department of Planning and Environment (the DP&E) on the 22 August2017, and implemented. Revised CEMP and CEMP Sub-plans relevant to Stage 21 of the Project were updated and subsequently approved by DP&E on 28 February 2018.

This Environmental Representative (ER) Report (Report) addresses Condition A16(l) of the Infrastructure Approval. This Report provides an update on the environmental and social performance of the Project’s construction.

1.1 Purpose and Content of this Report

Condition A16(l) of the Infrastructure Approval requires an ER Report to be prepared and submitted to the Secretary for information each month. This will be submitted within seven days following the end of eachmonth for the duration of Construction of the Project or as otherwise negotiated with the Secretary. The report details the actions and decisions on matters for which the ER was responsible in the preceding month.

Further, Condition C16 requires the results of the Construction Monitoring Programs be submitted to the Secretary and relevant regulatory agencies, for information at the frequency identified in the relevant Construction Monitoring Program. As these reports will be monthly, relevant information will be contained and submitted along with this report.

Construction of Stage 1 commenced on 4 September 2017, as marked by the arrival of the tugs, split-hopper barges and the dredge. Construction of Stage 2 commenced on 13 April 2018, as marked by the commencement of survey for scour protection removal in anticipation of pile installation. This report covers construction activities from 1 August 2018 to 31 August 2018.

1.2 Project Description The Project is located in Snug Cove, Eden, New South Wales and comprises the extension of the existing Eden Breakwater Wharf and dredging of the approach channel and berth pocket with offshore disposal, to accommodate the berthing of cruise ships of up to 325m in length.

1 Stage 2 is outlined in the Project Staging Report (Advisian 2017, as submitted to the Secretary 24 July 2017 in accordance with Condition A37 of the Infrastructure Approval)

Page 8: Environmental Representative Monthly Report 12 - August 2018 · Environmental Representative Monthly Report 12 - August 2018 Eden Breakwater Wharf Extension 7 September 2018 Level

NSW Department of Industry Environmental Representative Monthly Report 12 - August 2018Eden Breakwater Wharf Extension

Key features of the Project include:

Extension of the existing wharf by approximately 95m, including 78 piles to support the extension

Installation of three mooring dolphins and two berthing dolphins, including 30 piles Installation of new landside bollards to restrain the ship’s bow, including 18 piles Dredging of 210,148m³ of in-situ material (including over-dredging allowance) Transport and placement of the dredge material at an offshore disposal site

Installation of minor services (lighting, power, potable water and emergency water) Installation of navigational aids.

1.3 Project Status During the period covered by this report (1 August 2018 to 31 August 2018), the following key activities wereundertaken and milestones achieved relating to the Project:

On-site noise monitoring is ongoing

Piling works are ongoing (refer to Figure 1-1), 78 wharf piles (56 complete and 22 partially complete) and nine onshore bollard piles have been completed

Dolphin topside fabrication is ongoing (off-site fabrication) Precast concrete deck plank fabrication is complete and Silane treatment commenced Precast concrete headstock troughs fabrication is ongoing, 18 have been poured One headstock installed on the wharf Temporary works have commenced for transition wharf Trimming piles is ongoing

Removal of rock amour and pile gate poured for navigational aid/tower.

Advisian 2

Page 9: Environmental Representative Monthly Report 12 - August 2018 · Environmental Representative Monthly Report 12 - August 2018 Eden Breakwater Wharf Extension 7 September 2018 Level

NSW Department of Industry Environmental Representative Monthly Report 12 - August 2018Eden Breakwater Wharf Extension

Note: Red flagged piles are complete. However 22 piles are still to be “drilled and driven” or “rock socketed”.

Figure 1-1: Piling progress

Advisian 3

Page 10: Environmental Representative Monthly Report 12 - August 2018 · Environmental Representative Monthly Report 12 - August 2018 Eden Breakwater Wharf Extension 7 September 2018 Level

NSW Department of Industry Environmental Representative Monthly Report 12 - August 2018Eden Breakwater Wharf Extension

2 Review and Amendments to the CEMP or Approvals

2.1 CEMP amendments The CEMP and CEMP Sub-plans for Stage 1 of the Project were formally approved by the Secretary on 22 August 2017.

The CEMP and CEMP Sub-plans for Stage 2 of the Project were prepared and submitted to DP&E for approval. The CEMP and CEMP Sub-plans were approved by the Secretary on 28 February 2018.

During the period covered by this report, there were no reviews or minor amendments made to the CEMP and/or CEMP Sub-plans.

2.2 Infrastructure Approval Amendments Consultation is ongoing with DP&E and the Community Consultation Committee (CCC) regarding a potential modification to operational conditions concerning the environmental management of noise amenity and airquality (E17, E18, E20, and E22). Written comments have been received regarding the potential amendments, some comments support the changes and some comments raise concerns.

A Modification Request was formally submitted to DP&E on the 04 July 2018. The DP&E placed themodification request on public exhibition from 13 July to Friday 27 July 2018.

On the 03 August 2018, the DP&E provided a letter requesting a response to the issues raised in submissionsand requested additional information to support the proposed modifications. The Department received a total of 18 submissions on the Modification Request, including:

Five regulatory agencies (NSW Office of Environment and Heritage, NSW Environment Protection Authority, NSW Department of Industry, Transport for NSW and Bega Valley Shire Council)

Four organisations (Cat Balou Cruises, Bega Valley Shire Residents and Ratepayers Association Inc, Eden Tourism Incorporated and Sapphire Coast Buslines)

Nine private stakeholders. Of the 18 submissions, only one objected to the Modification Request related to the proposed modification of Conditions E20 and E22 (related to air quality). A Response to Submissions Report was submitted to the Department on the 03 September 2018 for assessment and a decision

Advisian 4

Page 11: Environmental Representative Monthly Report 12 - August 2018 · Environmental Representative Monthly Report 12 - August 2018 Eden Breakwater Wharf Extension 7 September 2018 Level

NSW Department of Industry Environmental Representative Monthly Report 12 - August 2018Eden Breakwater Wharf Extension

3 Environmental Performance Environmental performance was measured through observation of construction activities and identification of continual improvement opportunities.

3.1 Environmental Issues For this reporting period, two environmental performance issues occurred on-site.

3.1.1 Minor Hydraulic Oil Leak On 23 August 2018, the Pilequip ICE 44B Vibro Hammer was laid on the wharf, with the hydraulic hose lines secured and capped, awaiting repair of a coupling seal failure on the main hose. On 24 August 2018 it was relocated on the wharf for space utilisation and production reasons. While stored on the wharf, a leak developed and oil spilled on the ground. The spill was noticed on arrival on site and walk around on 27 August 2018, after the weekend. Spill pads were deployed and the hammer elevated to stop the spill. Indiscussion with the hydraulic fitter it was found that the Pilequip ICE 44B Vibro Hammer is required to bestored on an angle to prevent the hydraulic sump stored fluid level from covering the Thermo Relief valve opening. Once the issue was identified the hammer was repositioned to clean up the spill. The hammer was stored on an incline to ensure the free fluid in the sump did not cover the valve. No further spill has occurred.

An incident report was prepared and it was noted that there was no impact to the environment and the report was closed out. An upright storage frame will be implemented to prevent a reoccurrence.

3.1.2 Use of Cordless Hammer Drill On 29 August 2018, the Proponent advised that the preparation of the surface profile on the fender headstocks currently on the barge, were not prepped to the correct profile, as per the specification andrequested approval from the ER to scabble the pockets on the barge using a Milwaukee cordless hammer drill. The contractor provided an outline of the required works, environmental control and monitoring measures, the duration and timing of works and community engagement activities.

On 29 August 2018 and having reviewed to the CEMP, the description of required works and environmental control measures, the ER advised that the works required to be carried out are generally in accordance withthe Infrastructure Approval terms and intent of the CEMP. Their impact is also consistent with the existingenvironmental risk assessment for this stage.

The work was carried out on 31 August 2018. For the remainder of construction, green cutting of the construction joints will be carried out in accordance with the CEMP.

Advisian 5

Page 12: Environmental Representative Monthly Report 12 - August 2018 · Environmental Representative Monthly Report 12 - August 2018 Eden Breakwater Wharf Extension 7 September 2018 Level

NSW Department of Industry Environmental Representative Monthly Report 12 - August 2018Eden Breakwater Wharf Extension

3.2 Weekly Observations

Table 3-1 provides a list of actions and close out from the weekly observations inspections and daily site visits.

Table 3-1: Weekly Environmental Observations

Date raised Action identified Action undertaken Date closed

2-Aug-18

2-Aug-18

30-Aug-18

Hazardous waste bund to be pumped out

Subcontractor PFD's to be included on WWC register

Repairs to concrete washout area

Pumped out organisedand undertaken during site inspection

Sub contractors that do not currently have aninternal register have been included on the WWC register

Sighted during dailyinspection

02-Aug-18

02-Aug-18

01-Sep-18

30-Aug-18 Reinstate the timber sign on bin Sighted during daily inspection

01-Sep-18

30-Aug-18 Concrete spills at rear of wharf to be cleaned up and investigated

30-Aug-18 Firefighting equipment to be made more accessible at the front of the elevated platform for welders undertaking work on the fender section of the headstock

Advisian 6

Page 13: Environmental Representative Monthly Report 12 - August 2018 · Environmental Representative Monthly Report 12 - August 2018 Eden Breakwater Wharf Extension 7 September 2018 Level

NSW Department of Industry Environmental Representative Monthly Report 12 - August 2018Eden Breakwater Wharf Extension

4 Environmental Monitoring Summary Monitoring for Stage 2 activities included observations on aquatic ecology, water quality and air quality, and site-based monitoring for noise amenity and vibration. No observations have identified any adverse environmental impacts due to the Project.

Marine Mammal Observer (MMO) trained personnel were onsite conducting observations during piling works in line with the requirements of the EPBC Act Referral Decision Notice conditions. The following was noted during this reporting period:

No incidents involving marine mammals have occurred

Whales have been sighted within Twofold Bay, with one observed in the Observation Zone during the reporting period. To date there have been no sightings of whales within the shut-down zone (refer to Appendix A for the Whale Register.

The Observation and Shut down zones were increased on the 30 August to 2.2km and 1.3km (respectively) to cater for the whale migration and as prescribed in the EPBC referral (EPBC2016/7828).

4.1 Noise and Vibration Monitoring Noise and vibration monitoring equipment was installed on the 27 April 2018 prior to the commencement of piling on the 28 April 2018. The vibration monitoring equipment was in place for two weeks and has now been removed, and noise monitoring equipment will remain in place for during of piling to monitor any adverse impacts. No noise or vibrations incidents or non-conformances have been raised during this reporting period.

A Piling Construction Noise Monitoring report dated 06 September 2018, has been developed by ERM and is attached at Appendix B. This report has been prepared in accordance with the Noise and Vibration CEMP Sub-plan and outlines the results for the continuous monitoring period from 01 – 31 August 2018. Weeklystatistics are provided in the reports since the commencement of piling.

The results of the monitoring were compared to the predicted noise levels outlined in the EIS and the Noise and Vibration CEMP Sub-plan for the Project. Based on continuous monitoring and identified periods of piling activity, it is evident that while site activities are audible and contribute to the noise environment at the identified sensitive receivers, noise impacts are below Approved Noise Levels during identified periods of piling activities. Noise levels at both logging locations were found to be heavily influenced by prevailing wind conditions.

The report recommended that ongoing noise monitoring be maintained as per the program, and noise impacts be reviewed where any significant changes to piling equipment or operation occurs, particularly once dolphin piling works commence.

Advisian 7

Page 14: Environmental Representative Monthly Report 12 - August 2018 · Environmental Representative Monthly Report 12 - August 2018 Eden Breakwater Wharf Extension 7 September 2018 Level

NSW Department of Industry Environmental Representative Monthly Report 12 - August 2018Eden Breakwater Wharf Extension

5 Environmental Incidents / Complaints Zero environmental incidents occurred on the Project.

Zero community complaints have been received regarding the Project.

Advisian 8

Page 15: Environmental Representative Monthly Report 12 - August 2018 · Environmental Representative Monthly Report 12 - August 2018 Eden Breakwater Wharf Extension 7 September 2018 Level

NSW Department of Industry Environmental Representative Monthly Report 12 - August 2018Eden Breakwater Wharf Extension

Appendix A: Whale Register

Advisian 9

Page 16: Environmental Representative Monthly Report 12 - August 2018 · Environmental Representative Monthly Report 12 - August 2018 Eden Breakwater Wharf Extension 7 September 2018 Level

WHALE REGISTER Date Time Location Action undertaken Species Number Comments

1/05/2018 16:16 Observation zone Nil - continued piling as softstart already underway and mammal did not enter shutdown zone

Whale 1

25/05/2018 8:55 Outside Observation Zone Piling delayed for >1.5hrs Whale 2 Whale in observation zone between 8:55 and 9:25. Piling

commenced at 11:07.

15/06/2018 12:00 Outside Observation Zone Nil Whale 3

9/07/2018 12:05 Observation zone Nil Whale 1 Whale in observation zone between 12:05 and 12:15 - during barge relocation and pile setup. Pre piling observations were undertaken from 13:15 to 13:45. Piling commenced at 13:45.

24/07/2018 - Outside Observation Zone Nil Whale 1

26/07/2018 8:10 Outside Observation Zone Nil Whale 2 Located 300m - 400m from yellow buoys

2/08/2018 8:15 Outside Observation Zone Nil Whale 1 Inbetween Nth and Sth Head appro. 2-3kms off obser. Zone

2/08/2018 9:12 Outside Observation Zone Nil Whale 4 1km south of Nth Head

2/08/2018 10:50 Outside Observation Zone Nil Whale 6 or 7 Travelling from Nth Head to Sth Head

8/08/2018 9:43 Observation zone Nil - no piling being undertaken Whale 1 Sighted at location 2 heading south - last sighted at 9:47

24/08/2018 - Outside Observation Zone Nil - no piling being undertaken Whale 1 Sighted near Navy Wharf

Page 17: Environmental Representative Monthly Report 12 - August 2018 · Environmental Representative Monthly Report 12 - August 2018 Eden Breakwater Wharf Extension 7 September 2018 Level

NSW Department of Industry Environmental Representative Monthly Report 12 - August 2018Eden Breakwater Wharf Extension

Appendix B: Piling Construction Noise Monitoring Report (ERM, 2018)

Advisian 10

Page 18: Environmental Representative Monthly Report 12 - August 2018 · Environmental Representative Monthly Report 12 - August 2018 Eden Breakwater Wharf Extension 7 September 2018 Level

Robert Davis

Project Manager

Waterway Constructions Pty Ltd

[email protected]

6 September 2018

Dear Robert,

Port of Eden Project – Piling Construction Noise Monitoring – Continuous Monitoring 1st to 31st August 2018

ERM was engaged by Waterway Constructions Pty Ltd (Waterway) to complete ongoing noise

monitoring as part of Stage 2 of the Eden Breakwater Wharf Extension. Noise monitoring is

required as part of the Noise and Vibration CEMP Sub-plan for the works, and as a requirement

of Infrastructure Approval (SSI 7734, July 2017), stated by the Department of Planning and

Environment (DP&E).

The attached document is an assessment of noise impacts from piling for the period 1st to 31st

August 2018.

Please contact ERM if you require any further information.

Yours sincerely

Aaron McKenzie

Principle Consultant

Enclosure

ERM Sydney ABN: 86 127 101 642

Level 15, 309 Kent Street www.erm.com

Sydney NSW 2000 Ph: +61 2 8584 8888

Page 19: Environmental Representative Monthly Report 12 - August 2018 · Environmental Representative Monthly Report 12 - August 2018 Eden Breakwater Wharf Extension 7 September 2018 Level

1 Introduction

The monitoring scope included long term unattended monitoring at two locations after the

commencement of piling activities. This report outlines the results for the period 1st to 31st August

2018. Weekly statistics have been presented for Weeks 15 to 19 in this report, being the weeks

since the commencement of piling and monitoring.

This document references the following documents:

Noise and Vibration CEMP Sub-plan Eden Breakwater Wharf Extension - Stage 2 (Advisian,

February 2018).

Port of Eden Air Quality and Noise Assessment (Pacific Environment 2016).

This monitoring report has been prepared with reference to the following policy and guidance:

Interim Construction Noise Guideline (DECCW 2009);

Construction Noise Strategy (TfNSW 2012);

Australian Standard AS1055.1:1997: Description and Measurement of Environmental Noise.

A glossary of the acoustic terms used in this report are presented in Attachment A.

2 Monitoring Locations and Approved Noise Levels

2.1 Sensitive Receivers and Monitoring Locations

Individual receiver locations and addresses are indicated in the Air Quality and Noise

Assessment (PEL 2016a), and reproduced in Attachment B. Monitoring locations are presented in

Attachment B and Figure 2-1.

Location L1 was required for monitoring as part of Stage 1 of the Eden Breakwater Extension, but

is not required as part of Stage 2, however naming has been maintained for the remaining sites

for consistency with previous reports.

ERM Sydney www.erm.com 2 Level 15, 309 Kent Street Ph: +61 2 8584 8888

Sydney NSW 2000

Page 20: Environmental Representative Monthly Report 12 - August 2018 · Environmental Representative Monthly Report 12 - August 2018 Eden Breakwater Wharf Extension 7 September 2018 Level

Table 2.1: Noise Monitoring Locations, MGA Zone 55

Location ID NCA Address Suburb Easting (m) Northing (m)

L3 1 17 Victoria Terrace Eden 758415 5893428

L2 2 8 By St Eden 758733 5892986

Source: Air Quality and Noise Assessment (Pacific Environment, 2016)

Figure 2-1: Site Location, Noise Catchment Areas and Noise Monitoring Locations

ERM Sydney www.erm.com 3 Level 15, 309 Kent Street Ph: +61 2 8584 8888

Sydney NSW 2000

Page 21: Environmental Representative Monthly Report 12 - August 2018 · Environmental Representative Monthly Report 12 - August 2018 Eden Breakwater Wharf Extension 7 September 2018 Level

2.2 Approved Noise Management Levels

The noise limits for the project are stated in the CEMP and are based on noise predictions from

the Air Quality and Noise Assessment (Pacific Environment, 2016). Model Scenario 3 includes

impact piling at the port, and a situation where piling equipment is relocated to the wave

attenuator. Noise levels have been presented at the receivers adjacent the noise loggers, being

SR43 at By Street (L2) and SR21 Victoria Terrace (L3). These are reproduced in Table 2-3.

Noise levels have been presented with the magnitude of noise exceedances as per Table 2.2,

with the results applied in subsequent table. Red background indicates noise levels in

exceedance of the highly noise affected criteria.

Table 2.2: Presentation of Results and Exceedances

Description Exceedance above

Criteria, dB(A)

Predicted noise level,

dB(A)

Colour scheme

Noticeable 0 – 10 dB(A) -

Clearly audible 10 – 20 dB(A) -

Moderately intrusive 20 – 30 dB(A) -

Highly intrusive > 30 dB(A) -

Highly Noise Affected - > 75 dB(A)

Source: PEL 2016.

Table 2-3: Predicted Construction Noise from Piling

Predicted Noise Level LAeq,15min dB(A)

Criteria LAeq,15min Scenario 3

Receiver ID NCA Day Eve Night Day/Port Day Atten

SR21 NCA 1 43 37 37 75 77

77 72SR43 NCA 2 47 40 40

Source: PEL 2016.

ERM Sydney www.erm.com 4 Level 15, 309 Kent Street Ph: +61 2 8584 8888

Sydney NSW 2000

Page 22: Environmental Representative Monthly Report 12 - August 2018 · Environmental Representative Monthly Report 12 - August 2018 Eden Breakwater Wharf Extension 7 September 2018 Level

3 Noise Monitoring

3.1 Equipment Failure

Due to ongoing issues with the noise monitors modems failing to consistently connect to the mobile

phone network, and subsequent data loss, replacement monitors were swapped over to allow for

testing by the equipment manufacturer. The following instruments were in place:

Location L2, By Street – swapped to logger serial number 8780A2 on 31st of July, and

subsequently a replacement battery installed on the 7th of August.

Location L3 Victoria Terrace swapped to logger serial number 8780A3 on 8th of August.

3.2 Monitoring Methodology

Continuous unattended noise monitoring was completed with Class 1 noise loggers with reference

to AS1055.1:1997. Instrumentation calibrated by a NATA testing laboratory with in field checks of

instrument calibration. Noise loggers were set to record A-weighted noise levels every 15 minutes

and set to ‘fast’ response time. Calibration was checked monthly with no significant drift observed.

All logging equipment carry current NATA calibration certificates (Attachment D).

Noise logging graphs and daily summaries for location L2 and L3 between the 1st and 31st August

2018 are summarised in Attachment C. The existing noise environment was influenced by

prevailing wind conditions and sea swell.

With regard to the approved noise levels (Table 2-3), piling noise levels are to comply with

77 dB(A) at L2 and 75 dB(A) at L3. It is noted that these levels are based on 15 minute

assessment periods.

The instantaneous maximum piling noise impact can generally be approximated from the

maximum noise levels recorded in the daily logger graphs (Attachment C) when piling is being

undertaken.

Weekly statistics for location L2 and L3 are discussed in the following sections for the period of

continuous data collection.

4 Results

4.1 Week 15 – 1st to 31st August 2018

During Week 15, piling only occurred on 1st August 2018 between 07:30 and 12:46; on 2nd August

2018 between 08:23 and 16:55; and on 7th August 2018 between 09:17 and 17:11.

ERM Sydney www.erm.com 5 Level 15, 309 Kent Street Ph: +61 2 8584 8888

Sydney NSW 2000

Page 23: Environmental Representative Monthly Report 12 - August 2018 · Environmental Representative Monthly Report 12 - August 2018 Eden Breakwater Wharf Extension 7 September 2018 Level

4.1.1 Location L2, 8 By Street Due to equipment error, data was not captured for 6th and 7th August 2018 at Location L2.

Average noise level (LAeq) varied from 39 dB(A) to 64 dB(A) during the day time period. The

maximum noise levels (LMax) ranged from 52 dB(A) to 85 dB(A) during the day time period.

During Week 15, piling LAeq noise levels were measured from 46 to 64 dB(A). Lmax levels during

these periods ranged between 55 to 80 dB(A). Lmax peaks were typically between 70 to 77 dB(A),

with a single peak event of 80 dB(A) recorded on 2nd August.

LAeq 15 minute average noise levels during the day time period did not exceed 77 dB(A).

4.1.2 Location L3, 17 Victoria Terrace Due to equipment error, data was not captured at Location L3 for Week 15 of the monitoring

program.

4.2 Week 16 – 8th to 14th August 2018

During Week 16, piling was undertaken on 8th August 2018 between 08:03 to 17:04; on 9th August

2018 between 08:15 to 15:07; and on 10th August 2018 between 08:37 and 11:30.

4.2.1 Location L2, 8 By Street The average noise level (LAeq) varied from 38 dB(A) to 66 dB(A) during the day time period. The

maximum noise level (LMax) varied from 50 dB(A) to 86dB(A) during the day time period.

During Week 16, piling LAeq noise levels were measured from 40 to 63 dB(A). Lmax levels during

these periods ranged between 57 to 77 dB(A). Lmax peaks were typically between 65 to 75 dB(A).

LAeq 15 minute average noise levels during the day time period did not exceed 77 dB(A), except on

8th August where the measurements were influenced by equipment calibration checks and

maintenance activity, occurring between 16:30 and 17:00.

4.2.2 Location L3, 17 Victoria Terrace The average noise level (LAeq) varied from 36 dB(A) to 68 dB(A) during the day time period. The

maximum noise levels (LMax) ranged from 52 dB(A) to 87 dB(A) during the day time period.

At L3, piling LAeq noise levels were measured from 44 to 68 dB(A). Lmax levels during these periods

ranged between 60 to 80 dB(A). Lmax peaks were typically between 60 to 77 dB(A).

LAeq 15 minute average noise levels during the day time period did not exceed 75 dB(A).

4.3 Week 17 - 15th to 21st August 2018

No piling was undertaken during Week 17.

ERM Sydney www.erm.com 6 Level 15, 309 Kent Street Ph: +61 2 8584 8888

Sydney NSW 2000

Page 24: Environmental Representative Monthly Report 12 - August 2018 · Environmental Representative Monthly Report 12 - August 2018 Eden Breakwater Wharf Extension 7 September 2018 Level

4.3.1 Location L2, 8 By Street The average noise level (LAeq) varied from 37 to 65 dB(A) during the day time period. The maximum

noise level (LMax) varied from 52 dB(A) to 89 dB(A) during the day time period.

LAeq 15 minute average noise levels during the day time period did not exceed 77 dB(A).

4.3.2 Location L3, 17 Victoria Terrace The average noise level (LAeq) varied from 36 to 61 dB(A) during the day time period. The maximum

noise levels (LMax) ranged from 53 dB(A) to 85 dB(A) during the day time period.

At L3 during Week 17, noise levels were measured between 50 to 65 dB(A). As no piling was

undertaken during Week 12, recorded noise levels can be attributed to existing environmental

noise.

LAeq 15 minute average noise levels during the day time period did not exceed 75 dB(A).

4.4 Week 18 – 22nd to 28th August 2018

No piling was undertaken during Week 18.

4.4.1 Location L2, 8 By Street The average noise level (LAeq) varied from 39 dB(A) to 68 dB(A) during the day time period. The

maximum noise level (LMax) varied from 53 to 89 dB(A) during the day time period. As no piling was

undertaken during Week 18, recorded noise levels can be attributed to existing environmental

noise.

4.4.2 Location L3, 17 Victoria Terrace The average noise level (LAeq) varied from 40 dB(A) to 62 dB(A) during the day time period. The

maximum noise levels (LMax) ranged from 57 dB(A) to 85 dB(A) during the day time period. As no

piling was undertaken during Week 12, recorded noise levels can be attributed to existing

environmental noise.

4.5 Week 19 – 29th to 31st August 2018

During Week 19, piling was undertaken on 30th August between 07:30 to 14:15.

4.5.1 Location L2, 8 By Street The average noise level (LAeq) varied from 42 dB(A) to 66 dB(A) during the day time period. The

maximum noise level (LMax) varied from 49 to 96 dB(A) during the day time period.

ERM Sydney www.erm.com 7 Level 15, 309 Kent Street Ph: +61 2 8584 8888

Sydney NSW 2000

Page 25: Environmental Representative Monthly Report 12 - August 2018 · Environmental Representative Monthly Report 12 - August 2018 Eden Breakwater Wharf Extension 7 September 2018 Level

During Week 19, piling LAeq noise levels were measured from 46 to 56 dB(A). Lmax levels during

these periods ranged between 66 to 82 dB(A). Lmax peaks were typically between 75 to 80 dB(A).

LAeq 15 minute average noise levels during the day time of the period 29th to 31st August did not

exceed 77 dB(A).

4.5.2 Location L3, 17 Victoria Terrace The average noise level (LAeq) varied from 40 to 60 dB(A) during the day time period. The maximum

noise levels (LMax) ranged from 56 dB(A) to 84 dB(A).

At L3, piling LAeq noise levels were measured from 44 to 59 dB(A). Lmax levels during these periods

ranged between 59 to 78 dB(A). Lmax peaks were typically between 70 to 75 dB(A).

LAeq 15 minute average noise levels during the day time of the period 29th to 31st August did not

exceed 75 dB(A).

4.6 Statement of Compliance

Based on continuous monitoring and identified periods of piling activity, it is evident that while site

activities are audible and contribute to the noise environment at the identified sensitive receivers,

noise impacts are below Approved Noise Levels during identified periods of piling activities.

For weeks 15 to 19, measured LAeq average noise levels during the daytime period at location L2

(By St) did not exceed 77 dB(A).

For Weeks 15 to 19, LAeq average noise level noise levels during the daytime at location L3 (Victoria

Terrace) did not exceed 75 dB(A).

At both monitoring locations, instantaneous maximum noise levels were estimated at being above

70 dB(A) at several short interval events throughout the monitoring period, however these levels

were not sustained and did not result in exceedance of the approved LAeq 15minute noise levels.

Noise levels were found to be impacted by prevailing wind conditions. As noted during previous

attended monitoring campaigns, winds tend to be elevated during the daytime period, which

results in increased noise levels received at the logging locations.

5 Conclusion

ERM has completed ongoing noise monitoring as part of Stage 2 of the Eden Breakwater Wharf

Extension. Noise monitoring is required as part of the Noise and Vibration CEMP Sub-plan for the

works, and as a requirement of Infrastructure Approval (SSI 7734, July 2017), stated by the

Department of Planning and Environment (DP&E).

This report presents noise impacts from piling for the period 1st to 31st August 2018 for Weeks 15

to 19 of the monitoring schedule.

ERM Sydney www.erm.com 8 Level 15, 309 Kent Street Ph: +61 2 8584 8888

Sydney NSW 2000

Page 26: Environmental Representative Monthly Report 12 - August 2018 · Environmental Representative Monthly Report 12 - August 2018 Eden Breakwater Wharf Extension 7 September 2018 Level

The results of monitoring were compared to the Project Approval limits. Measured noise levels

have been below the Approval limits referred to in the Infrastructure Approval. Noise levels at

both logging locations were found to be heavily influenced by prevailing wind conditions.

It is recommended that ongoing noise monitoring be maintained as per the program, and noise

impacts be reviewed where any significant changes to piling equipment or operation occurs,

particularly once dolphin piling works commence.

References

Advisian, February 2018. Noise and Vibration CEMP Sub-plan Eden Breakwater Wharf Extension

- Stage 2.

Australian Standard (AS) 1055.1:1997 Description and Measurement of Environmental Noise.

British Standards Institute (2008). BS 6472-1:2008 Guide to evaluation of human exposure to

DECC (2009). NSW Interim Construction Noise Guidelines (ICNG).

Department of Planning and Environment (DP&E) (2017). Infrastructure Approval (SSI 7734, July

2017).

Pacific Environment (2016a). 20910 RHDHV Eden Air Quality and Noise Assessment D3.

TfNSW (2012). Construction Noise Strategy 7TP-ST-157/2.0

Attachment A – Glossary of terms

Attachment B – Sensitive Receivers

Attachment C - Daily Logger Graphs

Attachment D – Instrument Calibration Certificates

ERM Sydney www.erm.com 9 Level 15, 309 Kent Street Ph: +61 2 8584 8888

Sydney NSW 2000

Page 27: Environmental Representative Monthly Report 12 - August 2018 · Environmental Representative Monthly Report 12 - August 2018 Eden Breakwater Wharf Extension 7 September 2018 Level

Attachment A: Glossary of Terms

Term Description

Weather conditions that affect noise measurements (wind, rain and temperature inversions) that occur at a particular site for a significant period of time. The

Adverse weather maximum wind speed allowed during acoustics measurements is 5m/s. No rain is allowed.

The all-encompassing noise environment at a given location, comprising sources in Ambient noise

the near and far field.

Assessment The period in a day over which assessments are made.

period

Adjustment made to a noise level based on international standards. Approximates a A-weighting

human’s hearing response to frequency at lower sound levels.

Background noise is the term used to describe the underlying level of noise present in an area, measured in the absence of any extraneous noise. Typically when

Background noise measured with a sound level meter is measured statistically as the A-weighted noise level exceeded for ninety percent of a sample period (LA90,T).

dB Decibel, the logarithmic ratio of a given sound pressure to a reference pressure.

dB(A) A-weighted decibels.

Free-field A sound field where the effects of reflection are negligible in the region of interest.

The number of cycles per unit of time. It is measured with cycles per second (cps) or Frequency the interchangeable Hertz (Hz). Frequency can be associated as a synonymous to

pitch.

Level that drops to the background noise level several times during the period of Intermittent noise

observation.

LA1,T The noise level exceeded for 1% of the time period, T.

LA10,T The noise level exceeded for 10% of the time period, T.

The noise level exceeded for 90% of the time period, T. Commonly referred to as the LA90,T background noise level.

The equivalent average noise level of the time period, T. It represents in a single LAeq,T number, the energy of the actual fluctuating noise level over the period.

LAmax,T The maximum noise level measured during the period, T.

Rating Background Level. The background noise level as defined by the NSW RBL Industrial Noise Policy (EPA, 2000). It is calculated by the taking the median value of

the lowest 10th percentile LA90 measurements in any day, evening or night period.

Is the difference between the pressure produced by a sound wave and the Sound Pressure

barometric (ambient) pressure at the same point in space. Typically expressed in Level (SPL)

decibels, as measured by a standard sound level meter with a microphone.

ERM Sydney www.erm.com 10 Level 15, 309 Kent Street Ph: +61 2 8584 8888

Sydney NSW 2000

Page 28: Environmental Representative Monthly Report 12 - August 2018 · Environmental Representative Monthly Report 12 - August 2018 Eden Breakwater Wharf Extension 7 September 2018 Level

Attachment B: Sensitive Receivers

ERM Sydney www.erm.com 11 Level 15, 309 Kent Street Ph: +61 2 8584 8888

Sydney NSW 2000

Page 29: Environmental Representative Monthly Report 12 - August 2018 · Environmental Representative Monthly Report 12 - August 2018 Eden Breakwater Wharf Extension 7 September 2018 Level

Figure B1: Noise sensitive receivers immediately adjacent to Snug Cove (Source: PEL 2016a)

ERM Sydney ABN: 86 127 101 642

Level 15, 309 Kent Street www.erm.com

Sydney NSW 2000 Ph: +61 2 8584 8888

Page 30: Environmental Representative Monthly Report 12 - August 2018 · Environmental Representative Monthly Report 12 - August 2018 Eden Breakwater Wharf Extension 7 September 2018 Level

Attachment C: Continuous Monitoring Graphs

ERM Sydney ABN: 86 127 101 642

Level 15, 309 Kent Street www.erm.com

Sydney NSW 2000 Ph: +61 2 8584 8888

Page 31: Environmental Representative Monthly Report 12 - August 2018 · Environmental Representative Monthly Report 12 - August 2018 Eden Breakwater Wharf Extension 7 September 2018 Level

Attachment C: Continuous Monitoring Graphs

Unattended Noise Monitoring Graphs

1st to 31st August 2018

s

ERM Sydney www.erm.com 15 Level 15 | 309 Kent Street | Ph: +61 2 8584 8888

Sydney NSW 2000

Page 32: Environmental Representative Monthly Report 12 - August 2018 · Environmental Representative Monthly Report 12 - August 2018 Eden Breakwater Wharf Extension 7 September 2018 Level

- -

1st – 31st August 2018

Table 1: L2 - By Street Daily Statistics – Week 15

Location ID Ambient Noise Level, Leq(period)

Day Maximum Noise Levels, Lmax

Day

Ave Min Max Ave Min Max

Wednesday

01/08/2018 56 42 64 70 58 80

Thursday

02/08/2018 54 44 62 67 56 80

Friday

03/08/2018 52 44 60 67 57 85

Saturday

04/08/2018 49 39 54 67 52 83

Sunday

05/08/2018 46 40 54 65 52 81

Monday

06/08/2018 - - - - - -

Tuesday

07/08/2018 - - - - - -

ERM Sydney www.erm.com 16 Level 15 | 309 Kent Street | Ph: +61 2 8584 8888

Sydney NSW 2000

Page 33: Environmental Representative Monthly Report 12 - August 2018 · Environmental Representative Monthly Report 12 - August 2018 Eden Breakwater Wharf Extension 7 September 2018 Level

- -

Table 2: L3– Victoria Terrace Daily Statistics – Week 15

Location ID Ambient Noise Level, Leq(period)

Day Maximum Noise Levels, Lmax

Day

Ave Min Max Ave Min Max

Wednesday

01/08/2018 - - - - - -

Thursday

02/08/2018 - - - - - -

Friday

03/08/2018 - - - - - -

Saturday

04/08/2018 - - - - - -

Sunday

05/08/2018 - - - - - -

Monday

06/08/2018 - - - - - -

Tuesday

07/08/2018 - - - - - -

ERM Sydney www.erm.com 17 Level 15 | 309 Kent Street | Ph: +61 2 8584 8888

Sydney NSW 2000

Page 34: Environmental Representative Monthly Report 12 - August 2018 · Environmental Representative Monthly Report 12 - August 2018 Eden Breakwater Wharf Extension 7 September 2018 Level

L2 - By St – 1st August 2018

L3 – Victoria Terrace - 1st August 2018

No data available on this day.

Key Leq Lmax L95 L90 L50 L10 L5 Battery Temperature Overload

ERM Sydney www.erm.com 18 Level 15 | 309 Kent Street | Ph: +61 2 8584 8888

Sydney NSW 2000

Page 35: Environmental Representative Monthly Report 12 - August 2018 · Environmental Representative Monthly Report 12 - August 2018 Eden Breakwater Wharf Extension 7 September 2018 Level

L2 – By St – 2nd August 2018

L3 – Victoria Tce - 2nd August 2018

No data available on this day.

Key Leq Lmax L95 L90 L50 L10 L5 Battery Temperature Overload

ERM Sydney www.erm.com 19 Level 15 | 309 Kent Street | Ph: +61 2 8584 8888

Sydney NSW 2000

Page 36: Environmental Representative Monthly Report 12 - August 2018 · Environmental Representative Monthly Report 12 - August 2018 Eden Breakwater Wharf Extension 7 September 2018 Level

L2 – By St – 3rd August 2018

L3 –Victoria Tce – 3rd August 2018

No data available on this day.

Key Leq Lmax L95 L90 L50 L10 L5 Battery Temperature Overload

ERM Sydney www.erm.com 20 Level 15 | 309 Kent Street | Ph: +61 2 8584 8888

Sydney NSW 2000

Page 37: Environmental Representative Monthly Report 12 - August 2018 · Environmental Representative Monthly Report 12 - August 2018 Eden Breakwater Wharf Extension 7 September 2018 Level

L2 – By St – 4th August 2018

L3 – Victoria Tce – 4th August 2018

No data available on this day.

Key Leq Lmax L95 L90 L50 L10 L5 Battery Temperature Overload

ERM Sydney www.erm.com 21 Level 15 | 309 Kent Street | Ph: +61 2 8584 8888

Sydney NSW 2000

Page 38: Environmental Representative Monthly Report 12 - August 2018 · Environmental Representative Monthly Report 12 - August 2018 Eden Breakwater Wharf Extension 7 September 2018 Level

L2 – By St – 5th August 2018

L3 – Victoria Tce – 5th August 2018

No data available on this day.

Key Leq Lmax L95 L90 L50 L10 L5 Battery Temperature Overload

ERM Sydney www.erm.com 22 Level 15 | 309 Kent Street | Ph: +61 2 8584 8888

Sydney NSW 2000

Page 39: Environmental Representative Monthly Report 12 - August 2018 · Environmental Representative Monthly Report 12 - August 2018 Eden Breakwater Wharf Extension 7 September 2018 Level

L2 – By St – 6th August 2018

No data available on this day.

L3 – Victoria Tce – 6th August 2018

No data available on this day.

Key Leq Lmax L95 L90 L50 L10 L5 Battery Temperature Overload

ERM Sydney www.erm.com 23 Level 15 | 309 Kent Street | Ph: +61 2 8584 8888

Sydney NSW 2000

Page 40: Environmental Representative Monthly Report 12 - August 2018 · Environmental Representative Monthly Report 12 - August 2018 Eden Breakwater Wharf Extension 7 September 2018 Level

L2 – By St – 7th August 2018

No data available on this day.

L3 – Victoria Tce – 7th August 2018

No data available on this day.

Key Leq Lmax L95 L90 L50 L10 L5 Battery Temperature Overload

ERM Sydney www.erm.com 24 Level 15 | 309 Kent Street | Ph: +61 2 8584 8888

Sydney NSW 2000

Page 41: Environmental Representative Monthly Report 12 - August 2018 · Environmental Representative Monthly Report 12 - August 2018 Eden Breakwater Wharf Extension 7 September 2018 Level

- -

8th to 14th August 2018

Table 3: L2 - By Street Daily Statistics – Week 16

Location ID Ambient Noise Level, Leq(period)

Day Maximum Noise Levels, Lmax

Day

Ave Min Max Ave Min Max

Wednesday

08/08/2018 71 41 79 77 50 103

Thursday

09/08/2018 53 40 63 69 57 86

Friday

10/08/2018 52 45 59 69 53 81

Saturday

11/08/2018 54 46 58 68 60 79

Sunday

12/08/2018 51 38 58 66 53 79

Monday

13/08/2018 56 39 66 68 53 84

Tuesday

14/08/2018 50 41 57 67 58 82

Note: 1. Peak affected by instrument calibration.

ERM Sydney www.erm.com 25 Level 15 | 309 Kent Street | Ph: +61 2 8584 8888

Sydney NSW 2000

Page 42: Environmental Representative Monthly Report 12 - August 2018 · Environmental Representative Monthly Report 12 - August 2018 Eden Breakwater Wharf Extension 7 September 2018 Level

- -

Table 4: L3 – Victoria Terrace Daily Statistics – Week 16

Location ID Ambient Noise Level, Leq(period)

Day Maximum Noise Levels, Lmax

Day

Ave Min Max Ave Min Max

Wednesday

08/08/2018 48 40 51 68 56 82

Thursday

09/08/2018 57 38 68 70 60 87

Friday

10/08/2018 55 39 65 68 57 81

Saturday

11/08/2018 48 43 52 64 52 78

Sunday

12/08/2018 49 36 53 65 54 76

Monday

13/08/2018 53 37 63 68 53 82

Tuesday

14/08/2018 49 39 53 69 60 80

ERM Sydney www.erm.com 26 Level 15 | 309 Kent Street | Ph: +61 2 8584 8888

Sydney NSW 2000

Page 43: Environmental Representative Monthly Report 12 - August 2018 · Environmental Representative Monthly Report 12 - August 2018 Eden Breakwater Wharf Extension 7 September 2018 Level

L2 – By St – 8th August 2018

L3 – Victoria Terrace – 8th August 2018

1 Note: Data valid from 17:30 only on this date.

Key Leq Lmax L95 L90 L50 L10 L5 Battery Temperature Overload

ERM Sydney www.erm.com 27 Level 15 | 309 Kent Street | Ph: +61 2 8584 8888

Sydney NSW 2000

Page 44: Environmental Representative Monthly Report 12 - August 2018 · Environmental Representative Monthly Report 12 - August 2018 Eden Breakwater Wharf Extension 7 September 2018 Level

L2 – By St – 9th August 2018

L3 - Victoria Terrace – 9th August 2018

Key Leq Lmax L95 L90 L50 L10 L5 Battery Temperature Overload

ERM Sydney www.erm.com 28 Level 15 | 309 Kent Street | Ph: +61 2 8584 8888

Sydney NSW 2000

Page 45: Environmental Representative Monthly Report 12 - August 2018 · Environmental Representative Monthly Report 12 - August 2018 Eden Breakwater Wharf Extension 7 September 2018 Level

L2 – By St – 10th August 2018

L3 - Victoria Terrace – 10th August 2018

Key Leq Lmax L95 L90 L50 L10 L5 Battery Temperature Overload

ERM Sydney www.erm.com 29 Level 15 | 309 Kent Street | Ph: +61 2 8584 8888

Sydney NSW 2000

Page 46: Environmental Representative Monthly Report 12 - August 2018 · Environmental Representative Monthly Report 12 - August 2018 Eden Breakwater Wharf Extension 7 September 2018 Level

L2 – By St– 11th August 2018

L3 – Victoria Terrace – 11th August 2018

Key Leq Lmax L95 L90 L50 L10 L5 Battery Temperature Overload

ERM Sydney www.erm.com 30 Level 15 | 309 Kent Street | Ph: +61 2 8584 8888

Sydney NSW 2000

Page 47: Environmental Representative Monthly Report 12 - August 2018 · Environmental Representative Monthly Report 12 - August 2018 Eden Breakwater Wharf Extension 7 September 2018 Level

L2 – By St – 12th August 2018

L3 - Victoria Terrace– 12th August 2018

Key Leq Lmax L95 L90 L50 L10 L5 Battery Temperature Overload

ERM Sydney www.erm.com 31 Level 15 | 309 Kent Street | Ph: +61 2 8584 8888

Sydney NSW 2000

Page 48: Environmental Representative Monthly Report 12 - August 2018 · Environmental Representative Monthly Report 12 - August 2018 Eden Breakwater Wharf Extension 7 September 2018 Level

L2 – By St – 13th August 2018

L3 - Victoria Terrace– 13th August 2018

Key Leq Lmax L95 L90 L50 L10 L5 Battery Temperature Overload

ERM Sydney www.erm.com 32 Level 15 | 309 Kent Street | Ph: +61 2 8584 8888

Sydney NSW 2000

Page 49: Environmental Representative Monthly Report 12 - August 2018 · Environmental Representative Monthly Report 12 - August 2018 Eden Breakwater Wharf Extension 7 September 2018 Level

L2 – By St – 14th August 2018

L3 – Victoria Terrace – 14th August 2018

Key Leq Lmax L95 L90 L50 L10 L5 Battery Temperature Overload

ERM Sydney www.erm.com 33 Level 15 | 309 Kent Street | Ph: +61 2 8584 8888

Sydney NSW 2000

Page 50: Environmental Representative Monthly Report 12 - August 2018 · Environmental Representative Monthly Report 12 - August 2018 Eden Breakwater Wharf Extension 7 September 2018 Level

- -

15th to 21st August 2018

Table 5: L2 - By Street Daily Statistics – Week 17

Location ID Ambient Noise Level, Leq(period)

Day Maximum Noise Levels, Lmax

Day

Ave Min Max Ave Min Max

Wednesday

15/08/2018 57 40 65 70 55 82

Thursday

16/08/2018 51 41 55 68 57 80

Friday

17/08/2018 50 41 59 67 52 89

Saturday

18/08/2018 52 37 65 68 53 86

Sunday

19/08/2018 58 46 65 68 56 80

Monday

20/08/2018 52 41 59 67 55 82

Tuesday

21/08/2018 55 41 64 69 54 82

Note: 1. Peak affected by instrument calibration

ERM Sydney www.erm.com 34 Level 15 | 309 Kent Street | Ph: +61 2 8584 8888

Sydney NSW 2000

Page 51: Environmental Representative Monthly Report 12 - August 2018 · Environmental Representative Monthly Report 12 - August 2018 Eden Breakwater Wharf Extension 7 September 2018 Level

- -

Table 6: L3 – Victoria Terrace Daily Statistics – Week 17

Location ID Ambient Noise Level, Leq(period)

Day Maximum Noise Levels, Lmax

Day

Ave Min Max Ave Min Max

Wednesday

15/08/2018 53 36 61 66 56 83

Thursday

16/08/2018 49 39 54 67 57 77

Friday

17/08/2018 49 36 60 66 57 80

Saturday

18/08/2018 49 41 57 65 53 76

Sunday

19/08/2018 55 45 60 68 58 85

Monday

20/08/2018 51 42 57 67 60 73

Tuesday

21/08/2018 51 40 55 68 59 75

ERM Sydney www.erm.com 35 Level 15 | 309 Kent Street | Ph: +61 2 8584 8888

Sydney NSW 2000

Page 52: Environmental Representative Monthly Report 12 - August 2018 · Environmental Representative Monthly Report 12 - August 2018 Eden Breakwater Wharf Extension 7 September 2018 Level

L2 – By St – 15th August 2018

L3 - Victoria Terrace – 15th August 2018

Key Leq Lmax L95 L90 L50 L10 L5 Battery Temperature Overload

ERM Sydney www.erm.com 36 Level 15 | 309 Kent Street | Ph: +61 2 8584 8888

Sydney NSW 2000

Page 53: Environmental Representative Monthly Report 12 - August 2018 · Environmental Representative Monthly Report 12 - August 2018 Eden Breakwater Wharf Extension 7 September 2018 Level

L2 – By St – 16th August 2018

L3 - Victoria Terrace – 16th August 2018

Key Leq Lmax L95 L90 L50 L10 L5 Battery Temperature Overload

ERM Sydney www.erm.com 37 Level 15 | 309 Kent Street | Ph: +61 2 8584 8888

Sydney NSW 2000

Page 54: Environmental Representative Monthly Report 12 - August 2018 · Environmental Representative Monthly Report 12 - August 2018 Eden Breakwater Wharf Extension 7 September 2018 Level

L2 – By St – 17th August 2018

L3 - Victoria Terrace – 17th August 2018

Key Leq Lmax L95 L90 L50 L10 L5 Battery Temperature Overload

ERM Sydney www.erm.com 38 Level 15 | 309 Kent Street | Ph: +61 2 8584 8888

Sydney NSW 2000

Page 55: Environmental Representative Monthly Report 12 - August 2018 · Environmental Representative Monthly Report 12 - August 2018 Eden Breakwater Wharf Extension 7 September 2018 Level

L2 – By St – 18th August 2018

L3 - Victoria Terrace – 18th August 2018

Key Leq Lmax L95 L90 L50 L10 L5 Battery Temperature Overload

ERM Sydney www.erm.com 39 Level 15 | 309 Kent Street | Ph: +61 2 8584 8888

Sydney NSW 2000

Page 56: Environmental Representative Monthly Report 12 - August 2018 · Environmental Representative Monthly Report 12 - August 2018 Eden Breakwater Wharf Extension 7 September 2018 Level

L2 – By St – 19th August 2018

L3 - Victoria Terrace – 19th August 2018

Key Leq Lmax L95 L90 L50 L10 L5 Battery Temperature Overload

ERM Sydney www.erm.com 40 Level 15 | 309 Kent Street | Ph: +61 2 8584 8888

Sydney NSW 2000

Page 57: Environmental Representative Monthly Report 12 - August 2018 · Environmental Representative Monthly Report 12 - August 2018 Eden Breakwater Wharf Extension 7 September 2018 Level

L2 – By St – 20th August 2018

L3 - Victoria Terrace - 20th August 2018

Key Leq Lmax L95 L90 L50 L10 L5 Battery Temperature Overload

ERM Sydney www.erm.com 41 Level 15 | 309 Kent Street | Ph: +61 2 8584 8888

Sydney NSW 2000

Page 58: Environmental Representative Monthly Report 12 - August 2018 · Environmental Representative Monthly Report 12 - August 2018 Eden Breakwater Wharf Extension 7 September 2018 Level

L2 – By St – 21st August 2018

L3 - Victoria Terrace – 21st August 2018

Key Leq Lmax L95 L90 L50 L10 L5 Battery Temperature Overload

ERM Sydney www.erm.com 42 Level 15 | 309 Kent Street | Ph: +61 2 8584 8888

Sydney NSW 2000

Page 59: Environmental Representative Monthly Report 12 - August 2018 · Environmental Representative Monthly Report 12 - August 2018 Eden Breakwater Wharf Extension 7 September 2018 Level

- -

22nd to 28th August 2018

Table 7: L2 - By Street Daily Statistics – Week 18

Location ID Ambient Noise Level, Leq(period)

Day Maximum Noise Levels, Lmax

Day

Ave Min Max Ave Min Max

Wednesday

22/08/2018 52 41 61 69 58 88

Thursday

23/08/2018 51 42 57 69 60 89

Friday

24/08/2018 50 43 59 68 54 84

Saturday

25/08/2018 51 43 62 66 53 84

Sunday

26/08/2018 46 39 54 68 53 80

Monday

27/08/2018 57 44 66 71 59 80

Tuesday

28/08/2018 58 43 68 69 59 81

ERM Sydney www.erm.com 43 Level 15 | 309 Kent Street | Ph: +61 2 8584 8888

Sydney NSW 2000

Page 60: Environmental Representative Monthly Report 12 - August 2018 · Environmental Representative Monthly Report 12 - August 2018 Eden Breakwater Wharf Extension 7 September 2018 Level

- -

Table 8: L3 – Victoria Terrace Daily Statistics – Week 18

Location ID Ambient Noise Level, Leq(period)

Day Maximum Noise Levels, Lmax

Day

Ave Min Max Ave Min Max

Wednesday

22/08/2018 50 45 53 67 57 77

Thursday

23/08/2018 50 44 54 68 59 81

Friday

24/08/2018 51 40 62 68 61 84

Saturday

25/08/2018 49 44 55 69 61 81

Sunday

26/08/2018 48 42 55 68 58 85

Monday

27/08/2018 53 45 60 67 60 76

Tuesday

28/08/2018 53 43 58 66 60 74

ERM Sydney www.erm.com 44 Level 15 | 309 Kent Street | Ph: +61 2 8584 8888

Sydney NSW 2000

Page 61: Environmental Representative Monthly Report 12 - August 2018 · Environmental Representative Monthly Report 12 - August 2018 Eden Breakwater Wharf Extension 7 September 2018 Level

L2 – By St – 22nd August 2018

L3 - Victoria Terrace – 22nd August 2018

Key Leq Lmax L95 L90 L50 L10 L5 Battery Temperature Overload

ERM Sydney www.erm.com 45 Level 15 | 309 Kent Street | Ph: +61 2 8584 8888

Sydney NSW 2000

Page 62: Environmental Representative Monthly Report 12 - August 2018 · Environmental Representative Monthly Report 12 - August 2018 Eden Breakwater Wharf Extension 7 September 2018 Level

L2 – By St – 23rd August 2018

L3 - Victoria Terrace – 23rd August 2018

Key Leq Lmax L95 L90 L50 L10 L5 Battery Temperature Overload

ERM Sydney www.erm.com 46 Level 15 | 309 Kent Street | Ph: +61 2 8584 8888

Sydney NSW 2000

Page 63: Environmental Representative Monthly Report 12 - August 2018 · Environmental Representative Monthly Report 12 - August 2018 Eden Breakwater Wharf Extension 7 September 2018 Level

L2 – By St – 24th August 2018

L3 - Victoria Terrace – 24th August 2018

Key Leq Lmax L95 L90 L50 L10 L5 Battery Temperature Overload

ERM Sydney www.erm.com 47 Level 15 | 309 Kent Street | Ph: +61 2 8584 8888

Sydney NSW 2000

Page 64: Environmental Representative Monthly Report 12 - August 2018 · Environmental Representative Monthly Report 12 - August 2018 Eden Breakwater Wharf Extension 7 September 2018 Level

L2 – By St – 25th August 2018

L3 - Victoria Terrace – 25th August 2018

Key Leq Lmax L95 L90 L50 L10 L5 Battery Temperature Overload

ERM Sydney www.erm.com 48 Level 15 | 309 Kent Street | Ph: +61 2 8584 8888

Sydney NSW 2000

Page 65: Environmental Representative Monthly Report 12 - August 2018 · Environmental Representative Monthly Report 12 - August 2018 Eden Breakwater Wharf Extension 7 September 2018 Level

L2 – By St – 26th August 2018

L3 - Victoria Terrace – 26th August 2018

Key Leq Lmax L95 L90 L50 L10 L5 Battery Temperature Overload

ERM Sydney www.erm.com 49 Level 15 | 309 Kent Street | Ph: +61 2 8584 8888

Sydney NSW 2000

Page 66: Environmental Representative Monthly Report 12 - August 2018 · Environmental Representative Monthly Report 12 - August 2018 Eden Breakwater Wharf Extension 7 September 2018 Level

L2 – By St – 27th August 2018

L3 - Victoria Terrace – 27th August 2018

Key Leq Lmax L95 L90 L50 L10 L5 Battery Temperature Overload

ERM Sydney www.erm.com 50 Level 15 | 309 Kent Street | Ph: +61 2 8584 8888

Sydney NSW 2000

Page 67: Environmental Representative Monthly Report 12 - August 2018 · Environmental Representative Monthly Report 12 - August 2018 Eden Breakwater Wharf Extension 7 September 2018 Level

L2 – By St – 28th August 2018

L3 - Victoria Terrace – 28th August 2018

Key Leq Lmax L95 L90 L50 L10 L5 Battery Temperature Overload

ERM Sydney www.erm.com 51 Level 15 | 309 Kent Street | Ph: +61 2 8584 8888

Sydney NSW 2000

Page 68: Environmental Representative Monthly Report 12 - August 2018 · Environmental Representative Monthly Report 12 - August 2018 Eden Breakwater Wharf Extension 7 September 2018 Level

- -

- -

29th to 31st August 2018

Table 9: L2 - By Street Daily Statistics – Week 19

Location ID Ambient Noise Level, Leq(period)

Day Maximum Noise Levels, Lmax

Day

Ave Min Max Ave Min Max

Wednesday

29/08/2018 59 47 66 72 62 83

Thursday

30/08/2018 51 42 56 69 49 82

Friday

31/08/2018 58 42 65 71 60 96

Table 10: L3 – Victoria Terrace Daily Statistics – Week 19

Location ID Ambient Noise Level, Leq(period)

Day Maximum Noise Levels, Lmax

Day

Ave Min Max Ave Min Max

Wednesday

29/08/2018 55 47 59 66 62 76

Thursday

30/08/2018 50 40 59 66 56 78

Friday

31/08/2018 50 42 60 67 56 84

ERM Sydney www.erm.com 52 Level 15 | 309 Kent Street | Ph: +61 2 8584 8888

Sydney NSW 2000

Page 69: Environmental Representative Monthly Report 12 - August 2018 · Environmental Representative Monthly Report 12 - August 2018 Eden Breakwater Wharf Extension 7 September 2018 Level

L2 – By St – 29th August 2018

L3 - Victoria Terrace – 29th August 2018

Key Leq Lmax L95 L90 L50 L10 L5 Battery Temperature Overload

ERM Sydney www.erm.com 53 Level 15 | 309 Kent Street | Ph: +61 2 8584 8888

Sydney NSW 2000

Page 70: Environmental Representative Monthly Report 12 - August 2018 · Environmental Representative Monthly Report 12 - August 2018 Eden Breakwater Wharf Extension 7 September 2018 Level

L2 – By St – 30th August 2018

L3 – Victoria Terrace – 30th August 2018

Key Leq Lmax L95 L90 L50 L10 L5 Battery Temperature Overload

ERM Sydney www.erm.com 54 Level 15 | 309 Kent Street | Ph: +61 2 8584 8888

Sydney NSW 2000

Page 71: Environmental Representative Monthly Report 12 - August 2018 · Environmental Representative Monthly Report 12 - August 2018 Eden Breakwater Wharf Extension 7 September 2018 Level

L2 – By St – 31st August 2018

L3 – Victoria Terrace – 31st August 2018

Key Leq Lmax L95 L90 L50 L10 L5 Battery Temperature Overload

ERM Sydney www.erm.com 55 Level 15 | 309 Kent Street | Ph: +61 2 8584 8888

Sydney NSW 2000

Page 72: Environmental Representative Monthly Report 12 - August 2018 · Environmental Representative Monthly Report 12 - August 2018 Eden Breakwater Wharf Extension 7 September 2018 Level

Attachment D: Calibration Certificates

ERM Sydney www.erm.com

Level 15, 309 Kent Street Ph: +61 2 8584 8888

Sydney NSW 2000

Page 73: Environmental Representative Monthly Report 12 - August 2018 · Environmental Representative Monthly Report 12 - August 2018 Eden Breakwater Wharf Extension 7 September 2018 Level

ERM Sydney www.erm.com

Level 15, 309 Kent Street Ph: +61 2 8584 8888

Sydney NSW 2000

Page 74: Environmental Representative Monthly Report 12 - August 2018 · Environmental Representative Monthly Report 12 - August 2018 Eden Breakwater Wharf Extension 7 September 2018 Level

ERM Sydney www.erm.com

Level 15, 309 Kent Street Ph: +61 2 8584 8888

Sydney NSW 2000

Page 75: Environmental Representative Monthly Report 12 - August 2018 · Environmental Representative Monthly Report 12 - August 2018 Eden Breakwater Wharf Extension 7 September 2018 Level

ERM Sydney www.erm.com

Level 15, 309 Kent Street Ph: +61 2 8584 8888

Sydney NSW 2000