ENVIRONMENTAL STATEMENT
Non-Technical Summary
Delph Lane North
Residential Development
Full Application
June 2014
Delph Lane North Residential Development, Daresbury Full Application
Environmental Statement Non-Technical Summary
Delph Lane North Residential Development, Daresbury
Full Application
Environmental Impact Assessment
Environmental Statement
Non-Technical Summary
June 2014
Prepared by
TEP
Genesis Centre
Birchwood Science Park
Warrington
WA3 7BH
Tel: 01925 844004
Fax: 01925 844002
e-mail: [email protected]
for
Redrow Homes (NW) Ltd.
Redrow House
St. David’s Park, Ewloe Flintshire,
CH5 3RX
Tel: 01244 545655
Delph Lane North Residential Development, Daresbury Full Application
Environmental Statement Non-Technical Summary
I.0 Non-Technical Summary
i.1 Introduction
i.1.1 This Environmental Statement accompanies a full planning application for consent
under the Town and Country Planning Act (1990) (as amended) for a residential
development of up to 295 dwellings between the West Coast Main Line and the
Chester to Warrington Regional Railway, as shown in Inset i.1. Proposals also
include a network of pedestrian and cycle greenway routes. Consent is also being
sought for the creation of a new spine road south from the A558 through the new
development up to the Chester-Warrington rail line.
Inset i.1 Proposed Development Site Aerial Context
i.1.2 Full details of the effects of the Proposed Development are contained within the
Environmental Statement under the Town and Country Planning Act (1990) (as
amended).
i.1.3 The Environmental Statement provides details of the proposed works and an
assessment of the potential environmental effects arising from construction and
operation as required under the Town and Country Planning (Environmental
Impact Assessment) (England and Wales) Regulations 2011 (EIA Regulations).
i.1.4 This document provides a Non-Technical Summary of the predicted effects on the
environment of the Proposed Development.
Delph Lane North Residential Development, Daresbury Full Application
Environmental Statement Non-Technical Summary
i.2 Background
i.2.1 The site of the Proposed Development is within Daresbury Strategic Site (Inset
i.2), as defined in the adopted Halton Borough Council’s Core Strategy, which
forms part of the wider East Runcorn Key Area of Change.
i.2.2 The Core Strategy allocates land for specific uses within the Strategic Site
including land for residential development, a local centre and employment.
i.2.3 Under this Key Area of Change the Daresbury Strategic Site will deliver:
26ha of expansion for B1 science, high tech and research development at
Daresbury SIC;
40ha of land for the expansion of office and knowledge based facilities at
Daresbury Park;
Phased delivery of 1,400 dwellings brought forward in 3 phases; and
A mixed use neighbourhood centre including a marina.
Inset i.2: Daresbury Strategic Site (Cource: Halton Core Strategy Policy CS11)
Delph Lane North Residential Development, Daresbury Full Application
Environmental Statement Non-Technical Summary
i.2.4 This Proposed Development of up to 800 dwellings, commercial land and a
marina aims to delivering the residential and commercial objectives for Daresbury
Strategic Site, on land specially allocated for this purpose.
i.3 Environmental Impact Assessment Process
i.3.1 The EIA Regulations require that before consent is sought for certain types of
development, an Environmental Impact Assessment (EIA) must be undertaken.
i.3.2 The Regulations set out the forms of development which must always be subject
to Environmental Impact Assessment (Schedule 1 development) and other
developments which may require assessment (Schedule 2 development).
i.3.3 The Council formed a ‘Screening Opinion’ (dated 13th November 2012) stating that
the proposed development comprises EIA development under the Regulations,
falling within Schedule 2, specifically category 10(b) ‘Infrastructure Projects’.
i.4 Consultation
i.4.1 Redrow Homes (NW) Ltd. has engaged with key stakeholders including Halton
Borough Council officers, Daresbury Parish Council, local residents and local
councillors during the development of design proposals for the Site. Details of this
consultation process, including the methods used and findings are represented in
the ‘Statement of Community Involvement’, which accompanied the Planning
Application.
i.5 Content of the Environmental Statement
i.5.1 The ES contains the following information:
A description of the Proposed Development and an outline of the alternatives
considered;
A description of the likely significant effects of the Proposed Development on
the following environmental topics:
o Ecology;
o Geology;
o Hydrology and Flood
Risk;
o Air Quality;
o Historic Environment;
o Landscape and Views;
o Traffic and Transport;
o Socio-Economics;
o Land Use
o Waste; and
o Climate Change.
A description of measures proposed to prevent, reduce or where possible off-
set any significant adverse effects on the environment.
Delph Lane North Residential Development, Daresbury Full Application
Environmental Statement Non-Technical Summary
i.6 Project Proposals
Alternatives
i.6.1 The Daresbury Strategic Site was subject to consideration as far back as during
the production of the Unitary Development Plan, which was adopted following
public inquiry in 2005. Following this, Halton Borough Council included Daresbury
Strategic Site in its consideration of spatial options for its Core Strategy. After
significant public consultation and a further sustainability appraisal of the options,
Halton Council concluded that the Daresbury Strategic Site would be taken
forward into the Core Strategy.
i.6.2 Following a subsequent, more detailed, sustainability appraisal and examination in
public, the Halton Core Strategy (now known as its Local Plan) was adopted in
April 2013.
i.6.3 Policy CS11 of the Local Plan makes specific reference to the Proposed
Development as part of the area required to help deliver up to 1400 dwellings.
i.6.4 In summary, Halton Borough Council has considered alternative locations for
residential development and alternative uses for this site, and has concluded that
on the basis of evidence, the site is appropriately allocated for residential
development of the type proposed. A full description of the reasons why the Site is
allocated is set out in the preamble to policy CS11 in Halton’s Local Plan.
i.6.5 Alternatives have also been considered during the design phases of the Proposed
Development, with iterations of the masterplan for the site in recent months,
following consultations with stakeholders and initial environmental assessment
findings. Alternative designs have considered housing density, layout, access
arrangements, massing and appearance in addition to the extent of provision of
green space, pedestrian routes and cycleways.
i.7 Summary of Environmental Effects
i.7.1 The following section summarises the predicted effects of the construction and
operation of the Proposed Development on the environment.
Ecology
i.7.2 This chapter assesses the effects on wildlife of the Proposed Development. In
particular, it describes the potential loss, disturbance or damage to wildlife as
result of the Proposed Development.
i.7.3 The Proposed Development does not have any protected areas for wildlife,
however a number of habitats and animals were included in the assessment
including arable field margins, hedgerows, ponds, badgers, bats and breeding
birds.
Delph Lane North Residential Development, Daresbury Full Application
Environmental Statement Non-Technical Summary
i.7.4 There is potential for minor adverse effects during the construction phase on most
of these, from habitat loss and disturbance. Construction-phase measures are
proposed that will reduce the effects, such as careful timing and programming of
the works to ensure that wildlife such as nesting birds are not disturbed by
construction activity. The Construction Environmental Management Plan would
also minimise impacts on wetlands, specifically including pollution prevention
measures.
i.7.5 The new landscape, including new hedgerows, wetlands and green buffer zones
alongside road, rail and development boundaries will provide green infrastructure
that, over time will remove adverse effects for all receptors affected by this
application.
i.7.6 Increases in certain bird species such as song thrush, house sparrow, dunnock,
reed bunting are expected.
i.7.7 There will be additional benefits to the water environment from the use of ponds,
ditches and reedbeds to control surface water from the site.
i.7.8 The new landscapes will be subject to long-term management which will benefit
most of the habitats and animals assessed.
Geology
i.7.9 This chapter provides a description of the physical environment (soils, geology
and hydrogeology) within the site of the Proposed Development. It identifies and
assesses the potential activities associated with the Proposed Development that
could impact upon, and result in contamination of, soils and/or groundwater.
Where necessary, measures are proposed, to avoid or reduce effects.
i.7.10 A summary of the remaining effects, after such measures are implemented, is
shown in Table i.7.
Table i.7 Residual Effects
Potential Impact Significance
of Impact
Mitigation measures Residual Effect
Construction
Contamination of soil and
groundwater resulting
construction (e.g. from
storage and use of
hazardous materials)
Moderate Detailed site investigation and
risk assessment to provide a
remediation strategy for
construction activities
Implementation of Pollution
Prevention Plan and
Emergency Response Plan
Not Significant
Delph Lane North Residential Development, Daresbury Full Application
Environmental Statement Non-Technical Summary
Potential Impact Significance
of Impact
Mitigation measures Residual Effect
Operation
Contamination of
groundwater aquifers via
existing pathways
Minor Detailed foundation risk
assessment to mitigate
potential pathways
Drainage designed to intercept
sediment / silt
Not Significant
i.7.11 The risk to the ground and groundwater environment is assessed as ‘not
significant’ as any risks can be controlled through specific activities to avoid or
reduce the risk.
Hydrology and Flood Risk
i.7.12 The Proposed Development site lies solely within Flood Zone 1 and is
approximately 17.2 ha in size.
i.7.13 The site is mainly undeveloped land surrounding ‘Delph Lane’ in Daresbury
Halton, and the identified water bodies within the vicinity are:
Keckwick Brook;
Bridgewater Canal;
Poplar Farm Coarse Fishery; and
Further pond and drainage ditch features within the boundaries of site.
i.7.14 This chapter considers the effects of the development on water quality and flood
risk within the Poplar Farm Coarse Fishery pond and the Keckwick Brook.
Water Quality
i.7.15 Environment Agency water quality results for the Keckwick Brook varied from
moderate to high. Samples taken at Poplar Farm pond results showed that it
water quality was as would be expected for still water body.
i.7.16 The construction impacts identified included input of soil and mobilisation of fine
sediment; and accidental spillage of pollutants such as fuel. It is considered that
with appropriate controls there would be no significant adverse effects. The pond
would be de-silted and the coarse fish removed which would have a long term
minor beneficial effect on water quality within the pond.
i.7.17 The potential impacts following completion of the houses were identified as being
associated with the altered site drainage, causing the potential for greater
variation in flows and reduced water quality (into the pond and Keckwick Brook
Delph Lane North Residential Development, Daresbury Full Application
Environmental Statement Non-Technical Summary
only). Also, both waterbodies could be affected by increased recreational pressure
(with increased potential for litter or bird feeding by residents and visitors causing
greater nutrient input). However, with the use of ponds and reedbeds to improve
water quality, education boards to reduce litter/bird feeding, and facilities to
manage litter no significant adverse effects are expected.
i.7.18 There will be additional benefits to the water environment from the use of ponds,
ditches and reedbeds to control surface water from the site.
Flood Risk
i.7.19 A detailed Flood Risk Assessment has been carried out examining all the sources
of flood risk both to and from the Proposed Development site including; fluvial,
tidal, pluvial, groundwater, sewers and flooding from artificial sources.
i.7.20 Following consultation with various parties and review of Halton Borough
Council’s Preliminary Flood Risk Assessment and Strategic Flood Risk
Assessment it was concluded that the site has not historically had any instances
of flooding that the surrounding areas has.
i.7.21 The development site is considered to have a low risk of flooding therefore the
principle focus of the Flood Risk Assessment was on effective surface water
management.
i.7.22 The existing drainage situation is understood to drain via an informal drainage
solution at present; this includes a variety of boundary drainage ditches, pond
features and through infiltration (in some areas).
i.7.23 Following development; surface water run-off generated by the development will
discharge to Keckwick Brook (as existing) through a variety of drainage features
including the existing boundary drainage ditches, the pond features and infiltration
(where possible). Multiple surface water sewers will be required within the broader
system due to the topographic constraints of the development site.
i.7.24 It will be necessary to restrict the surface water discharge generated by the
development proposals to the pre-development greenfield rates of run-off. Further
restrictions may be required following investigation into the existing culverts
should capacity issues arise.
i.7.25 ‘Sustainable drainage systems’ of ponds, ditches and reedbeds are proposed to
manage the surface water wherever possible; the existing fishery will remain post
development following enhancement; providing storage and water improvement
prior to discharge into the watercourse. The existing drainage ditches are
proposed to be improved; increasing biodiversity and capacity, and soak-aways
are proposed in the north-eastern areas to reduce surface water run-off generated
by the proposals.
Delph Lane North Residential Development, Daresbury Full Application
Environmental Statement Non-Technical Summary
Air Quality
11.1.1 This chapter assesses the likely effects of the Proposed Development on dust
emissions during construction and air quality from the exhausts of road vehicles
following completion. The proposed development is not in an Air Quality
Management Area declared by Halton Borough Council.
11.1.2 In addition to dust generated during the construction phase, the key pollutants that
were assessed were nitrogen dioxide (NO2) and fine particulate matter (PM10).
Effects were assessed in relation to an opening year of 2021, which is the likely
opening year of the Proposed Development.
11.1.3 Set in the context of existing conditions, the increase in exhaust emissions
associated with road traffic movements during the construction phase, over what
would be a relatively short period of time, would be not significant. The Site was
defined as ‘medium risk’ for each of the construction related activities and
associated dust generation. However, though the use of best-practice measures
suitable for a ‘medium risk’ site, and the temporary nature of the works, the effects
of construction dust can be successfully reduced.
11.1.4 The assessment of effects on emissions following completion of the Proposed
Development showed that, in 2021, changes in pollutant concentrations were
expected to be ‘imperceptible’. The Site was also deemed to be suitable for its
proposed use, with none of the air quality objectives predicted to be exceeded at
the relevant locations of new exposure. Overall, the air quality effects from road
traffic associated with the operation of the Development were therefore said to be
not significant.
Heritage
i.7.26 Baseline conditions identified 31 designated heritage assets within 2km of the
Proposed Development site; the development does not adversely affect any of the
positive contribution made by the setting of these assets to their significance.
i.7.27 Baseline conditions identified 10 non-designated heritage assets within the area of
search, of which two assets are within the Proposed Development site and would
be directly affected. These assets are both of low heritage significance and
although the magnitude of effect would be high, measures are proposed to record
any disturbed archaeological evidence and thus mitigate the predicted adverse
effect. The proposed archaeological investigation could be secured by a condition
of planning consent. After the implementation of the proposed archaeological
investigation, the predicted residual effect in relation to these two non-designated
heritage assets is negligible.
Delph Lane North Residential Development, Daresbury Full Application
Environmental Statement Non-Technical Summary
Landscape and Visual Impact
i.7.28 The site lies in the Moore Village and Keckwick Brook Valley landscape character
area, as identified by Halton Borough Council. The Site is not the subject of
landscape designations and is not visible from the Daresbury Village Conservation
Area.
i.7.29 The significance of effects on landscape character resulting from construction
activity is anticipated to be moderate adverse. In operation, the Proposed
Development would result in a moderate adverse significance of effect on the
landscape within the area defined by the Daresbury Strategic Site Allocation.
Residual effects long-term 15 years completion of all phases of the development
would reduce to minor adverse significance due to trees on site reaching maturity
and giving the development a ‘greener’ impression. This would help to create a
development similar in character and appearance to existing development to the
west.
i.7.30 The principal public views of medium sensitivity are experienced by users of
Delph Lane and Keckwick Lane. The significance of effects on public views is
anticipated to range from moderate adverse to negligible, depending on distance
from the new buildings and the degree to which the site forms part of the existing
view.
i.7.31 The principal private views of medium sensitivity are experienced by residents of
properties along Delph Lane and Village Farm (north of the Chester to Warrington
Line) surrounded by the site and residents of Poplar Farm (a farmhouse adjoining
the site). The significance of effects on private views is anticipated to range from
major adverse to minor adverse.
i.7.32 Measures have been incorporated into the Proposed Development design and
layout proposals to reduce effects on landscape and views on completion of the
proposed development.
i.7.33 The new spine road will be subject to roadside planting and, coupled with
additional planting in the public open spaces within the development, over time
the character of the residential landscape will look like housing within a wooded
setting, as occurs in development at Norton, on the western flanks of the
Keckwick Brook Valley.
i.7.34 The Site is on the side of a low lying shallow river valley next to the settlements of
Norton and Sandymoor and close to SciTech Daresbury. Consequently there are
limited potential visual receptors. Only properties along Delph Lane north of the
Chester to Warrington Line would have a high level of change and effects of major
adverse significance within the assessment. Taking into account the design and
layout of the Proposed Development the visual residual effects are reduced to
moderate adverse. Visual residual effects are generally recorded as minor
adverse and negligible.
Delph Lane North Residential Development, Daresbury Full Application
Environmental Statement Non-Technical Summary
Traffic and Transport
i.7.35 This chapter assesses the potential effects of the Proposed Development on
Traffic and Transport.
i.7.36 The Proposed Development would provide homes close to expanding
employment areas. This enables many work trips to be made on foot or by cycle.
The development is also providing several new walk and cycle routes enabling
these modes to become important. The new routes also connect with Sandymoor
enabling these modes to be much more important for travel to work and school
from this expanding residential area.
i.7.37 The Proposed Development will facilitate the improvement in bus service
provision, providing new services.
i.7.38 A portion of new spine road will provide direct access to the A558 providing a
ready access route and enabling impacts on Sandymoor and existing residents
along Delph Lane to be minimised.
i.7.39 The Proposed Development will have a Minor Adverse impact on the A558 but is
funding over £3 million on road infrastructure.
i.7.40 The Proposed Development is but one of a number of developments in the area
which, between them (and with public sector funding), are providing a wide range
of infrastructure and service improvements.
i.7.41 During the construction period some impacts are inevitable, but by considerate
management of activities, these will be managed to minimise the extent and
duration of impacts on adjacent householders and those using the road network in
the area
Socio-Economics
i.7.42 This chapter provides an assessment of the socio-economic and community
impacts of the proposed development and includes the following:
A socio-economic baseline assessment for the borough of Halton, focusing on
the characteristics of the local population and economy;
Quantification of the full range of economic impacts, both direct and indirect,
that the proposed development will generate; and
A detailed assessment of the local social and community infrastructure in the
vicinity of the site and its capacity to serve the increased population arising
from the Proposed Development.
i.7.43 The assessment distinguishes between the effects of the development during the
construction stage and during the operational stage. The assessment of impacts
is based on an assumed construction programme between 2015 and 2022 and
assumes a fully occupied development.
Delph Lane North Residential Development, Daresbury Full Application
Environmental Statement Non-Technical Summary
i.7.44 In summary, the Proposed Development is expected to deliver a number of
positive impacts for Halton:
An increase in the local resident population of 850 people, 66% of which will
be of working age and can help to redress the widening imbalance in the
population of Halton. It is important to maximise retention of the working age
population in order to strengthen the local labour market;
A temporary increase in construction jobs over the estimated 6 year build
period, amounting to c.110 employment opportunities;
A permanent increase in local employment opportunities through the
increased household expenditure in the local economy. This could create up
to 20 new jobs. The building of new homes in the Proposed Development
could help to address local unemployment in the industry, and provide
apprenticeship and training opportunities for young unemployed people;
A permanent increase in the supply of skilled labour which could help to
address skill gaps and increase the productivity of local employers; and
The Proposed Development will place demands on the existing social and
community infrastructure but the assessment shows there is sufficient capacity
to meet these demands. The delivery of additional primary school capacity at
Sandymoor, as set out in our analysis, would also provide additional capacity
that can be utilised.
Land Use
i.7.45 This chapter examines the effects associated with the proposed residential
development on existing and future land use interests.
i.7.46 The assessment considers the potential permanent and temporary effects that the
Proposed Development may have on existing and future land use and identifies
measures to avoid, reduce or offset potential adverse effects, or enhance potential
beneficial effects on land use.
i.7.47 Predicted land use effects for the residential development would mainly relate to
the construction phase; as ‘allocated land’ in Halton Borough Council’s Core
Strategy, the Proposed Development site has been identified for housing for many
years.
i.7.48 Construction effects on land use will be localised, temporary and of minor
significance. These include effects associated with the restriction of access, such
as the down grading of local routes, which may temporarily restrict access to
properties and businesses whilst re-surfacing and other works are being
undertaken, and may cause traffic disturbance associated with the increase in
construction traffic movements.
i.7.49 The only significant effects which relate to the operation of the Proposed
Development relate to other environmental disciplines such as those associated
Delph Lane North Residential Development, Daresbury Full Application
Environmental Statement Non-Technical Summary
with increased traffic movements and noise, which are considered elsewhere
within this Non Technical Summary.
Noise
i.7.50 This chapter assesses the noise impact of the Proposed Development on existing
noise-sensitive receptors in the area. In particular, it considers minimising
potential impact of construction noise and assessing any additional traffic noise
generated on the local highway network as a result of the completed
development.
i.7.51 The impact of existing noise sources in the area (i.e. railway noise and road traffic
noise from the A558) on the proposed residential development itself is not a
requirement of the EIA Regulations. However, a separate technical noise report
on this aspect has been prepared for submission with the planning application and
is included as Appendix 14a.This report includes baseline noise survey data for
the development.
i.7.52 The method for assessing noise impacts of the temporary construction phase of
the Proposed Development has by necessity been qualitative rather than
quantitative. This is because at this stage (i.e. planning application stage) a
contractor has not been appointed and there is no detailed information available
regarding the type of construction plant to be used. The assessment has therefore
focussed on the need to mitigate construction noise as far as is reasonably
practicable.
i.7.53 It has been concluded that, without the implementation of appropriate noise
mitigation measures, construction site noise may give rise to short-term noise
impacts of up to Moderate Adverse during periods where the noisiest activity is
taking place at the closest points to nearby noise-sensitive receptors. Therefore,
there is a need to reduce construction noise, as far as is possible, by using ‘best
practice’ guidance. With the implementation of these measures the residual noise
impact at any one location from construction works is likely to be no more than
Minor Adverse, and for a temporary period only.
i.7.54 For the operational phase, potential long term traffic noise impacts resulting from
operation of the completed development have been assessed using a
comparative approach. This has involved investigating the difference between
calculated traffic noise levels for the ‘without development’ and ‘with development’
scenarios, based upon the anticipated future traffic flows. Noise impacts have
been evaluated for existing noise sensitive receptors located on or near a sample
of roads nearest to the development site. The calculated increases in traffic noise
on main roads equates to Negligible Impact. Taking account of traffic likely to be
generated by relevant committed development in the wider area, the calculated
increases in traffic noise on main roads equates to Negligible to Minor Adverse
impact. Traffic is forecast to reduce on Delph Lane and Keckwick Lane and thus
Delph Lane North Residential Development, Daresbury Full Application
Environmental Statement Non-Technical Summary
traffic noise (due solely to the change in traffic on those lanes) has been
calculated to reduce for dwellings alongside these lanes, resulting in at least a
Minor Beneficial impact.
Waste
i.7.55 The potential effects of waste arising from the Proposed Development, both
during construction and operation, have been assessed at a strategic level, using
Redrow Homes (NW) Ltd.’s past projects to determine likely construction waste
arisings and sub-regional statistics from Halton and Merseyside to estimate
operational waste arisings.
i.7.56 Waste generated from construction activity would result in a negligible impact on
the waste management capacity of Halton and neighbouring authorities. Site
Waste Management Plans would be adopted, under planning conditions imposed
by Halton Borough Council. The Site Waste Management Plans would promote
re-use and recycling of construction waste and ensure off-site disposal did not
result in contamination or nuisance to the environment and surrounding
communities.
i.7.57 Waste generated during the occupation of the development would result in a
minor adverse significance effect on the waste management capacity of Halton
and neighbouring authorities.
i.7.58 Redrow Homes (NW) Ltd’s designs allow for appropriate internal recyclable waste
storage located within kitchen units. The garden layouts also include suitable
hard-standing areas for the siting of waste containers which are provided by Local
Authorities. Where apartment buildings are built, their design includes for
dedicated refuse storage areas. These design measures would enable personal
and Local authority-led initiatives to re-use and recycle materials that would
otherwise be treated as waste.
Climate Change
i.7.59 Annual Local Authority greenhouse CO2 estimates are produced by the
Department of Energy and Climate Change. The July 2013 statistical release
provides the following information with respect to Halton Borough Council:
Total CO2 emissions have fallen between 2005 and 2011 by 16% reduction;
Domestic emissions have fallen by 18%;
Transport emissions have fallen by7%;
The population of Halton has increased in this time period by 4% increase;
Per capita emissions have fallen from by 19% reduction; and
Domestic emissions represented 18% of total emissions in the borough.
Delph Lane North Residential Development, Daresbury Full Application
Environmental Statement Non-Technical Summary
i.7.60 A quantitative study was carried out on the likely CO2 emissions arising from the
Proposed Development.
i.7.61 There would be a temporary increase in CO2 emissions from construction traffic,
plant and machinery during the construction phase. The relatively low levels of
these emissions and their short term nature mean that these would be not
significant.
i.7.62 The estimated total, annual, CO2 emissions from the dwellings in the Proposed
Development equates to a 0.3% increase in annual CO2 emissions for Halton
Borough Council. This effect would be not significant. In addition, based on SAP
(energy efficiency) calculations, the annual CO2 emissions from the Proposed
Development would be an improvement on the Building Regulations target rate for
this number of dwellings, of 0.56kT per year.
i.7.63 A worst case scenario increase of transport emissions in CO2 from the Proposed
Development would represent an increase of 0.3% on the emissions of CO2 from
transport in the borough of Halton. This effect would be not significant.