1
EOG OILBIRD PROJECT POST CONSTRUCTION ANALYSIS REF. PHASE MAN HOURS LABOR COST MATERIAL ESTIMATE ACTUAL ESTIMATE ACTUAL ESTIMATE ACTUAL 1 ENGINEERING - - $36,000 $39,550 - - 2 STRICTURAL 7800 13,645 $178,200 $318,250 $165,000 $215,460 4 BLAST & PAINT 3000 2800 $62,600 $58,558 $27,000 $36,297 5 OUTFITTING 7900 8136 $155,800 $193,472 $216,700 $210,347 7 PLUMBING 2000 1165 $40,500 $18,628 $32,100 $54,877 8 ELECTRICAL 2800 2780 $59,300 $59,532 $72,200 $47,083 9 HVAC - - - - $83,000 $81,000 11 FIRE, GAS & GAITRONICS 285 $6,000 $74,300 $66,196 12 3000 $59,300 $29,000 13 EQUIPMENT - - - - $43,000 $72,717 14 MISC. $12,866 $88,011 NOTES: 1. TOTAL ESTIMATED COST IS $1,340,000. 2. TOTAL ACTUAL COST IS $1,572,844. UNDER ELEC. UNDER ELEC. WEIGH BLDG, CHECK C.G., LOUDOUT AND TIEDOWN

Eog Analysis(1)

Embed Size (px)

DESCRIPTION

process

Citation preview

Sheet1REF.PHASEMAN HOURSLABOR COSTMATERIALESTIMATEACTUALESTIMATEACTUALESTIMATEACTUAL1ENGINEERING--$36,000$39,550--2STRICTURAL780013,645$178,200$318,250$165,000$215,4604BLAST & PAINT30002800$62,600$58,558$27,000$36,2975OUTFITTING79008136$155,800$193,472$216,700$210,3477PLUMBING20001165$40,500$18,628$32,100$54,8778ELECTRICAL28002780$59,300$59,532$72,200$47,0839HVAC----$83,000$81,00011FIRE, GAS & GAITRONICS285UNDER ELEC.$6,000UNDER ELEC.$74,300$66,19612WEIGH BLDG, CHECK C.G., LOUDOUT AND TIEDOWN3000$59,300$29,00013EQUIPMENT----$43,000$72,71714MISC.$12,866$88,011NOTES:1. TOTAL ESTIMATED COST IS $1,340,000.2. TOTAL ACTUAL COST IS $1,572,844.

&C&12EOG OILBIRDPROJECT POST CONSTRUCTION ANALYSIS

Sheet2

Sheet3