37
EPRI’s Buried Pipe Initiative Industry/NRC Meeting on Buried Pipe October 22, 2009 Bo Clark EPRI, BOP Corrosion Program Manager

EPRI’s Buried Pipe Initiative · 2012-12-02 · EPRI’s Buried Pipe Initiative • 2007 – Nuclear Power Council expresses concern • March 2008 - 1016276, “An Assessment of

  • Upload
    others

  • View
    9

  • Download
    0

Embed Size (px)

Citation preview

Page 1: EPRI’s Buried Pipe Initiative · 2012-12-02 · EPRI’s Buried Pipe Initiative • 2007 – Nuclear Power Council expresses concern • March 2008 - 1016276, “An Assessment of

EPRI’s Buried Pipe Initiative

Industry/NRC Meeting on Buried Pipe

October 22, 2009

Bo Clark

EPRI, BOP Corrosion Program Manager

Page 2: EPRI’s Buried Pipe Initiative · 2012-12-02 · EPRI’s Buried Pipe Initiative • 2007 – Nuclear Power Council expresses concern • March 2008 - 1016276, “An Assessment of

EPRI’s Buried Pipe Initiative

• 2007 – Nuclear Power Council expresses concern

• March 2008 - 1016276, “An Assessment of Industry Needs for Control of Degradation in Buried Pipe”

– Gap Analysis Identified needs for:

• 1) Guidelines to Control Degradation

2© 2009 Electric Power Research Institute, Inc. All rights reserved.

) Gu de es to Co t o eg adat o

• 2) Risk Ranking Method for buried pipe

• 3) Technical Resources document for buried pipe

• 4) Dedicated test facility

• 5) Experience sharing

• 6) Assess and Develop Inspection Tools

• 7) Training

Page 3: EPRI’s Buried Pipe Initiative · 2012-12-02 · EPRI’s Buried Pipe Initiative • 2007 – Nuclear Power Council expresses concern • March 2008 - 1016276, “An Assessment of

EPRI’s Buried Pipe Strategic Activities

3© 2009 Electric Power Research Institute, Inc. All rights reserved.

Page 4: EPRI’s Buried Pipe Initiative · 2012-12-02 · EPRI’s Buried Pipe Initiative • 2007 – Nuclear Power Council expresses concern • March 2008 - 1016276, “An Assessment of

Program Guidance

4© 2009 Electric Power Research Institute, Inc. All rights reserved.

Page 5: EPRI’s Buried Pipe Initiative · 2012-12-02 · EPRI’s Buried Pipe Initiative • 2007 – Nuclear Power Council expresses concern • March 2008 - 1016276, “An Assessment of

Program Guidance

• 1016456, Recommendations for an Effective Program to Control the Degradation of Buried Pipe

– Rev. 1 in progress

– Discussed in depth later

• Training for Buried Pipe Program Owners

5© 2009 Electric Power Research Institute, Inc. All rights reserved.

a g o u ed pe og a O e s

– June 2-4, 2009

– Sept 9-11, 2009

– November 10-12, 2009, Dallas

Page 6: EPRI’s Buried Pipe Initiative · 2012-12-02 · EPRI’s Buried Pipe Initiative • 2007 – Nuclear Power Council expresses concern • March 2008 - 1016276, “An Assessment of

Program Guidance (continued)

• NRC/NEI/INPO Interface

– INPO uses “Recommendations” document as a basis for BP program evaluation

• Program feedback

– Met with NEI/NRC on Aug 19-20, 2009 on Buried Pipe

6© 2009 Electric Power Research Institute, Inc. All rights reserved.

et t / C o ug 9 0, 009 o u ed peand ASME Code Case N-755 on HDPE

Page 7: EPRI’s Buried Pipe Initiative · 2012-12-02 · EPRI’s Buried Pipe Initiative • 2007 – Nuclear Power Council expresses concern • March 2008 - 1016276, “An Assessment of

Risk Ranking Software

7© 2009 Electric Power Research Institute, Inc. All rights reserved.

Page 8: EPRI’s Buried Pipe Initiative · 2012-12-02 · EPRI’s Buried Pipe Initiative • 2007 – Nuclear Power Council expresses concern • March 2008 - 1016276, “An Assessment of

Risk Ranking Software

• Risk Ranking - used to prioritize the selection of inspection locations.

– Correlates the likelihood of failure against the consequences of failure.

Risk = Likelihood X Consequences

8© 2009 Electric Power Research Institute, Inc. All rights reserved.

• BPWORKS V1.0a

– Open Database being developed in V2.0

– Other commercially available tools also exist

– Training - BPWORKS Software

Risk Likelihood X Consequences

Page 9: EPRI’s Buried Pipe Initiative · 2012-12-02 · EPRI’s Buried Pipe Initiative • 2007 – Nuclear Power Council expresses concern • March 2008 - 1016276, “An Assessment of

Buried Pipe Integrity Group (BPIG)

9© 2009 Electric Power Research Institute, Inc. All rights reserved.

Page 10: EPRI’s Buried Pipe Initiative · 2012-12-02 · EPRI’s Buried Pipe Initiative • 2007 – Nuclear Power Council expresses concern • March 2008 - 1016276, “An Assessment of

Buried Pipe Integrity Group (BPIG)

• Buried Pipe Integrity Group (BPIG) formed in 2008 – In 2010, all US Utilities will be members– Meets two times/year

• Provides:– Forum for plant owners to discuss buried pipe issues

10© 2009 Electric Power Research Institute, Inc. All rights reserved.

p p pand exchange experiences (OE Sharing)

– Forum to obtain a consensus on industry issues– Technical support on buried pipe issues, as well as

support for related products– Related training– Interface with Vendor Support

• Sponsor related R&D

Page 11: EPRI’s Buried Pipe Initiative · 2012-12-02 · EPRI’s Buried Pipe Initiative • 2007 – Nuclear Power Council expresses concern • March 2008 - 1016276, “An Assessment of

Condition Assessment of Pipe O.D. Coatings

11© 2009 Electric Power Research Institute, Inc. All rights reserved.

Page 12: EPRI’s Buried Pipe Initiative · 2012-12-02 · EPRI’s Buried Pipe Initiative • 2007 – Nuclear Power Council expresses concern • March 2008 - 1016276, “An Assessment of

Condition Assessment of Pipe O.D. Coatings

• Indirect Inspection Methods Used in Pipeline Industry

• Pipe-to-Soil potential• Direct Current Voltage Gradient (DCVG)• Pearson survey

12© 2009 Electric Power Research Institute, Inc. All rights reserved.

Pearson survey• AC Current Attenuation• Close Interval Potential Survey• Area Potential Earth Current (APEC)

• Application challenges

– Congested Plant Piping

Page 13: EPRI’s Buried Pipe Initiative · 2012-12-02 · EPRI’s Buried Pipe Initiative • 2007 – Nuclear Power Council expresses concern • March 2008 - 1016276, “An Assessment of

Condition Assessment of Pipe O.D. Coatings

• Briefly Covered in Training for Buried Pipe Program Owners

• Discussed in

13© 2009 Electric Power Research Institute, Inc. All rights reserved.

• Discussed in depth in Cathodic Protection / Indirect Inspection Training

Page 14: EPRI’s Buried Pipe Initiative · 2012-12-02 · EPRI’s Buried Pipe Initiative • 2007 – Nuclear Power Council expresses concern • March 2008 - 1016276, “An Assessment of

Cathodic Protection

14© 2009 Electric Power Research Institute, Inc. All rights reserved.

Page 15: EPRI’s Buried Pipe Initiative · 2012-12-02 · EPRI’s Buried Pipe Initiative • 2007 – Nuclear Power Council expresses concern • March 2008 - 1016276, “An Assessment of

Cathodic Protection (CP)

• O.D. Coating - First Line of Defense against external corrosion

– Cathodic Protection - Backup Defense for areas of damaged coating

• CP Training

15© 2009 Electric Power Research Institute, Inc. All rights reserved.

• CP Training

– NMAC’s CP Workshop

– BP Program Owners’ Training

– CP Field Training Covered in Cathodic Protection / Indirect Inspection Course

Page 16: EPRI’s Buried Pipe Initiative · 2012-12-02 · EPRI’s Buried Pipe Initiative • 2007 – Nuclear Power Council expresses concern • March 2008 - 1016276, “An Assessment of

Condition Assessment of Pipe

16© 2009 Electric Power Research Institute, Inc. All rights reserved.

Page 17: EPRI’s Buried Pipe Initiative · 2012-12-02 · EPRI’s Buried Pipe Initiative • 2007 – Nuclear Power Council expresses concern • March 2008 - 1016276, “An Assessment of

Condition Assessment of Buried Pipe

• Ongoing Research

– Internal Pipe NDE Inspection Vehicles

– Guided Wave NDE

– Buried Pipe Mockups

17© 2009 Electric Power Research Institute, Inc. All rights reserved.

• Proposed/Planned Research

– 10” & smaller internal vehicles

– Buried pipe location & mapping

Page 18: EPRI’s Buried Pipe Initiative · 2012-12-02 · EPRI’s Buried Pipe Initiative • 2007 – Nuclear Power Council expresses concern • March 2008 - 1016276, “An Assessment of

In-Line Instrumented Vehicles

• There are commercial offerings that offer in-line inspections of pipe wall thickness (pigs)

• Limitations:

– In-ability to go through elbows, tees, valves, elevation changes

18© 2009 Electric Power Research Institute, Inc. All rights reserved.

g

– Require dedicated launch and retrieval stations

– Require 1/8” liftoff for accurate detection & sizing of pits

• Since 2004 EPRI has been developing vehicles and sensors suited for power plant piping (1” liftoff to accommodate pipe crud)

Page 19: EPRI’s Buried Pipe Initiative · 2012-12-02 · EPRI’s Buried Pipe Initiative • 2007 – Nuclear Power Council expresses concern • March 2008 - 1016276, “An Assessment of

Vehicle for Large Diameter Pipe Inspection

• ‘Proof of Concept’ of EPRI vehicle for very large diameter buried pipe (36” < D < 12’) completed in 2008

• Detect

− Internal and external pits

− Circumferential weld

Exciter Array

19© 2009 Electric Power Research Institute, Inc. All rights reserved.

degradation

− Longitudinal weld degradation

• Install through 24” diameter man way

• Can disassemble to pass through elbows

Detector Array

Page 20: EPRI’s Buried Pipe Initiative · 2012-12-02 · EPRI’s Buried Pipe Initiative • 2007 – Nuclear Power Council expresses concern • March 2008 - 1016276, “An Assessment of

Vehicle for Intermediate Diameter Pipe

• “Proof of Concept” -facilitate pipe inspection (12” to 30” diameter)

• Pulls itself along a guide wire

• 1” of radial clearance to allow for d t b l ti t

Instrument Modules

20© 2009 Electric Power Research Institute, Inc. All rights reserved.

mud, tubercles, coatings, etc

• Can traverse

– Change of elevations

– Branches, tees

– Multiple elbows (at least 6)

• Field testing in 2010

Spring Loaded Wheels

Sensors

Page 21: EPRI’s Buried Pipe Initiative · 2012-12-02 · EPRI’s Buried Pipe Initiative • 2007 – Nuclear Power Council expresses concern • March 2008 - 1016276, “An Assessment of

Project Timeline

Deliverable Title Scheduled DateCondition Assessment of buried Piping of Intermediate diameter

12/31/2009

Condition Assessment of Buried Piping of Intermediate Diameter-Field Trial

12/31/2010

21© 2009 Electric Power Research Institute, Inc. All rights reserved.

Condition Assessment of Buried Piping that Cannot be Drained-Engineering Design

12/31/2011

Condition Assessment of Buried Piping that cannot be drained-Manufacturing and Lab evaluation

12/30/2012

Condition Assessment of Buried Piping that cannot be drained-Field Trial

12/30/2013

Page 22: EPRI’s Buried Pipe Initiative · 2012-12-02 · EPRI’s Buried Pipe Initiative • 2007 – Nuclear Power Council expresses concern • March 2008 - 1016276, “An Assessment of

Guided Wave Ultrasonics

• Guided Wave ultrasonics is an existing technology that is being extended to inspect buried pipe

22© 2009 Electric Power Research Institute, Inc. All rights reserved.

Page 23: EPRI’s Buried Pipe Initiative · 2012-12-02 · EPRI’s Buried Pipe Initiative • 2007 – Nuclear Power Council expresses concern • March 2008 - 1016276, “An Assessment of

Guided Wave Ultrasonics

– 100% volumetric coverage over length of exam

– Screens for change in cross section area; can be focused

• Multiple sensors are wrapped around pipe and send signals both directions. Provides

23© 2009 Electric Power Research Institute, Inc. All rights reserved.

section area; can be focused on a specific area

– Ability to inspect under coatings, in inaccessible areas, and without complete excavation

– Length of exam limited by coatings, ground compaction, elbows Piezoelectric Sensors

Page 24: EPRI’s Buried Pipe Initiative · 2012-12-02 · EPRI’s Buried Pipe Initiative • 2007 – Nuclear Power Council expresses concern • March 2008 - 1016276, “An Assessment of

Guided Wave Variables

Guided wave technology for buried pipe examination is:

• Relatively new and is emerging

– Capabilities and limitations are not well known/documented

Flaw characterization is currently limited

24© 2009 Electric Power Research Institute, Inc. All rights reserved.

Several complex factors affect successful application

– Piping geometry

– Coating type and thickness

– Flaw shape and depth

– Surface conditions

– Multiple flaws

– Inspection distance

Page 25: EPRI’s Buried Pipe Initiative · 2012-12-02 · EPRI’s Buried Pipe Initiative • 2007 – Nuclear Power Council expresses concern • March 2008 - 1016276, “An Assessment of

Guided Wave Pipe Mock-ups

EPRI is building two piping mock-ups• 24” diameter 0.375” thick carbon steel

– Most common based on industry survey

• Un-coated Mock-up status

– Welded together

25© 2009 Electric Power Research Institute, Inc. All rights reserved.

– Flaw implant scheduled to start in October

• Coated mock-up status

– Piping has been coated and ready to ship

– Construction scheduled for 4th quarter

– Flaw implant to begin after studies on un-coated mock-up are complete

Page 26: EPRI’s Buried Pipe Initiative · 2012-12-02 · EPRI’s Buried Pipe Initiative • 2007 – Nuclear Power Council expresses concern • March 2008 - 1016276, “An Assessment of

Un-coated Mock-up

Purpose • Study guided wave

– Interaction on multiple flaw shapes independent of coating variables

– Response through elbow • Process and technology development

26© 2009 Electric Power Research Institute, Inc. All rights reserved.

Process and technology development• Develop training and test specimen• Validation of computer modeling• Identify appropriate flaw characteristics for buried mock-

up

Page 27: EPRI’s Buried Pipe Initiative · 2012-12-02 · EPRI’s Buried Pipe Initiative • 2007 – Nuclear Power Council expresses concern • March 2008 - 1016276, “An Assessment of

Un-coated Mock-up

• Guide wave collar

27© 2009 Electric Power Research Institute, Inc. All rights reserved.

Page 28: EPRI’s Buried Pipe Initiative · 2012-12-02 · EPRI’s Buried Pipe Initiative • 2007 – Nuclear Power Council expresses concern • March 2008 - 1016276, “An Assessment of

Coated Mock-up

Purpose

• Identify Gaps

• Develop advanced GW techniques

– Improve detection (including around elbows)

Improve flaw characterization

28© 2009 Electric Power Research Institute, Inc. All rights reserved.

– Improve flaw characterization

– Focusing

– Signal processing

• Benchmark technologies

• Study effects of coating on GW (attenuation)

• Develop/validate modeling

• Not intended as a qualification mock-up

Page 29: EPRI’s Buried Pipe Initiative · 2012-12-02 · EPRI’s Buried Pipe Initiative • 2007 – Nuclear Power Council expresses concern • March 2008 - 1016276, “An Assessment of

Coated Mock-up (continued)

Variables within mockup

• Multiple coatings – coal tar enamel and coal tar epoxy

• Multiple flaw shapes and sizes

• Multiple data acquisition locations

29© 2009 Electric Power Research Institute, Inc. All rights reserved.

Vendor Capability Demonstrations

• Invite NDE Services vendors to perform blind demonstrations; publish the results

Page 30: EPRI’s Buried Pipe Initiative · 2012-12-02 · EPRI’s Buried Pipe Initiative • 2007 – Nuclear Power Council expresses concern • March 2008 - 1016276, “An Assessment of

EPRI Buried Pipe Mockup Layout

5

6 7 8 9 10

1113B

1 2 3 4

12A

13A

20

’30© 2009 Electric Power Research Institute, Inc. All rights reserved.

Coal Tar Enamel

Coal Tar Epoxy

Access Point

Backfill

QUANTITIES

10 – 20’ 24” OD .375” Wall CS Pipe Sections

5 – CT Enamel A106B

5 – CT Epoxy A106B

3 – 10’ 24” OD .375” Wall CS Pipe Sections A106B

3 - No coating

4 – 90 elbows

1 – 45 bend

1 - Tee

Page 31: EPRI’s Buried Pipe Initiative · 2012-12-02 · EPRI’s Buried Pipe Initiative • 2007 – Nuclear Power Council expresses concern • March 2008 - 1016276, “An Assessment of

Schedule

Uncoated Mock-up

• Fabrication complete

– Flaws to be inserted 4th quarter of 2009

Coated Mock-up

• Coating complete

31© 2009 Electric Power Research Institute, Inc. All rights reserved.

• Coating complete

• Fabrication to be completed during 4th quarter of 2009

• Flaws to be inserted 1st quarter of 2010

• Backfill to occur after initial R&D and evaluation of inserted flaws

Page 32: EPRI’s Buried Pipe Initiative · 2012-12-02 · EPRI’s Buried Pipe Initiative • 2007 – Nuclear Power Council expresses concern • March 2008 - 1016276, “An Assessment of

Future Vision

• Potential use for demonstration or qualification of vendor capabilities– Use of NDE data to produce Virtual Pipe Specimens

• Two possibilities– Embed recorded flaw data into data files obtained

from clean pipes

32© 2009 Electric Power Research Institute, Inc. All rights reserved.

from clean pipes– Use models to develop NDE responses to known

flaws, embed into clean pipe data– Enables preparation of unlimited varieties of

specimens for blind demonstrations or qualifications• Varied flaw types, locations, configurations (elbows,

for example), test conditions (soils, coatings, temperature, …)

Page 33: EPRI’s Buried Pipe Initiative · 2012-12-02 · EPRI’s Buried Pipe Initiative • 2007 – Nuclear Power Council expresses concern • March 2008 - 1016276, “An Assessment of

Repair / Replacement

33© 2009 Electric Power Research Institute, Inc. All rights reserved.

Page 34: EPRI’s Buried Pipe Initiative · 2012-12-02 · EPRI’s Buried Pipe Initiative • 2007 – Nuclear Power Council expresses concern • March 2008 - 1016276, “An Assessment of

Repair / Replacement

Cured-in-Place Pipe (CIPP)

• ASME Code Case N589-1 provides rules for cured-in-place pipe (CIPP) to be used to repair Class 3 piping

34© 2009 Electric Power Research Institute, Inc. All rights reserved.

– However, R.G. 1.193 did not approve its use

• Although the CIPP products have many limitations, there are many applications where they are useful Insertion of an Inverted Liner

Page 35: EPRI’s Buried Pipe Initiative · 2012-12-02 · EPRI’s Buried Pipe Initiative • 2007 – Nuclear Power Council expresses concern • March 2008 - 1016276, “An Assessment of

Repair / Replacement

High Density Polyethylene (HDPE)• Considered to be an attractive option for replacements of

degraded pipe

• Extensive effort underway to support ASME to revise and

35© 2009 Electric Power Research Institute, Inc. All rights reserved.

obtain approval for Code Case N-755

• Details of R&D activities on HDPE were discussed with NRR during public meeting on August 20, 2009

Page 36: EPRI’s Buried Pipe Initiative · 2012-12-02 · EPRI’s Buried Pipe Initiative • 2007 – Nuclear Power Council expresses concern • March 2008 - 1016276, “An Assessment of

Buried Pipe Strategic Activities

36© 2009 Electric Power Research Institute, Inc. All rights reserved.

Page 37: EPRI’s Buried Pipe Initiative · 2012-12-02 · EPRI’s Buried Pipe Initiative • 2007 – Nuclear Power Council expresses concern • March 2008 - 1016276, “An Assessment of

Together…Shaping the Future of Electricity

37© 2009 Electric Power Research Institute, Inc. All rights reserved.