31
EQUIPMENT CAPABILITES Type of equipment Average Capabilities 1. Bulldozer (D8) a.) Clearing 500 sq.m./hr. b.) Stripping 200 sq.m./hr c.) Excavation 1.) Common Soil 45 cu.m/hr. 2.) Slightly hard Materials 25 cu.m./hr. d.) Quarrying 107 Common Materials 50 cu.m./hr. 108 Aggregates 40 cu.m./hr. Boulders 15 cu.m./hr. 200 Needs Screening e.) Pushing 3 cu.m./hr. 2. Road Grader a.) Sub grading 300 cu.m./hr. b.) Spreading 50 cu.m./hr. 3. Payloader Loading 30 cu.m./hr. 4. Crane Shovel Loading 35 cu.m./hr. 5. Sheep Foot Roller a.) Static Rolling 15 cu.m./hr.

EQUIPMENT CAPABILITES

Embed Size (px)

Citation preview

Page 1: EQUIPMENT  CAPABILITES

EQUIPMENT CAPABILITES

Type of equipment Average Capabilities

1. Bulldozer (D8) a.) Clearing 500 sq.m./hr. b.) Stripping 200 sq.m./hr

c.) Excavation 1.) Common Soil 45 cu.m/hr. 2.) Slightly hard Materials 25 cu.m./hr.

d.) Quarrying 107 Common Materials 50 cu.m./hr. 108 Aggregates 40 cu.m./hr. Boulders 15 cu.m./hr. 200 Needs Screening e.) Pushing 3 cu.m./hr.

2. Road Grader a.) Sub grading 300 cu.m./hr. b.) Spreading 50 cu.m./hr.

3. Payloader Loading 30 cu.m./hr.

4. Crane Shovel Loading 35 cu.m./hr.5. Sheep Foot Roller a.) Static Rolling 15 cu.m./hr.

(12 passes – 15 cm. lift) b.) Vibratory Rolling 135 cu.m./hr. (6 passes – 20 cm. lift)

6. 3 – Wheel Road Roller a.) Static Rolling 24 cu.m./hr. (6 passes – 20 cm. lift)

7. Tractor Drawn Roller a.) Vibratory Rolling 24 cu.m./hr. (6 passes – 20 cm. lift)

8. Tandem Roller a.) Static Rolling 24 cu.m./hr. (6 passes – 20 cm. lift)

b.) Vibratory Rolling 72 cu.m./hr. (6 passes – 60 cm. lift)

9.) 6 – T Dump Truck a.) Hauling Common Borrow 3.5 cu.m./hr. Base Course b.) Hauling Selected Borrow 5.0 cu.m./hr. c.) Hauling Concrete Batch 2 Batch/trip ‘Class A’

10. 2 ½ T – Dump Truck a.) Hauling Common Borrow 2.5 cu.m./trip Base Course b.) Hauling Selected Borrow 4.0 cu.m./trip Base Concrete Batch 1.0 Batch/trip ‘ Class A ‘

11. Buggy a.) Hauling Concrete Mix 0.17 cu.m./trip

Page 2: EQUIPMENT  CAPABILITES

12. Wheel Borrow a.) Hauling Aggregates 0.17 cu.m./trip b.) Hauling Concrete Mix 0.05 cu.m./trip

13. Water Truck a.) Watering 1000 sq.m./trip14. Concrete Mixer a.) Mixing Concrete 9 cu.m./hr.15. Rock Crusher a.) Crushing Mix sand & Gravel 30 cu.m./hr.16. Concrete Vibrator a.) Vibrating Concrete Mix 40 cu.m./hr.17. Concrete Floor Finisher a.) Finishing Concrete Floor 140 cu.m./hr.18. Percussion Drilling a.) Drilling Hard Rock 0.23 m./hr. b.) Drilling Loose Rock 0.30 m./hr. c.) Drilling Lime Stone 0.38 m./hr. d.) Drilling Sticky Clay 0.49 m./hr. e.) Drilling Loose Clay 0.70 m./hr.

TASK RATES FOR LABOR-BASED PROJECTS

I. For Item 100 – Clearing and GrubbingActivity: Productivity 1.) Bush Clearing sq.m./man-day Bush Type a.) Light Bush 200 b.) Medium Bush 100 c.) Dense Bush 502.) Tree and Stump Removal One (1) man-day per cm. of trunk diameter at Base of tree3.) Grubbing Vegetation Type a.) Dense vegetation in firm soil covering 80 the whole area b.) Spaced vegetation in loose soil 250

II. For Item 105 – Excavation for Roadway & Drainage Activity Productivity

1.) Excavation Cu.m./man-day (throwing distance in m.) Soil Type 0 – 4 m. 4 – 6 m. 6 – 8 m. a.) Loose, rot sticky soil 5.0 - 6.0 4.5 – 5.5 3.5 – 4.5 b.) Firm Soil 3.5 – 4.5 3.4 – 4.0 2.5 – 3.5 c.) Very hared soil, hard soil mixed 2.0 – 3.0 1.8 – 2.5 1.7 – 2.5 with stones2.) Loading Cu.m./man-day Type of Soil a.) Loose 4.5 – 5.5 b.) Firm 2.5 – 4.0 c.) Hard 1.5 – 2.5

Excavation combined with loading of soil can be effectively carried out by laborers up to a loading height of about 1.00 e.g. into wheel borrow or head baskets.

Page 3: EQUIPMENT  CAPABILITES

Above that height, it is preferable to have a separate group of leaders whose output must be matched with that of the excavators.

Necessary output for the Loading ActivitySoil Type Loading Height Productivity cu.m./man-daya.) Loose 0.1 m. 12 – 15b.) Loose 1 – 2 m. 7 – 10c.) Loose Over 2 m. 4 – 5

III. For Item 106 – Excavation for Structures Activity Productivity1.) Excavation Depending on the type of soil There use similar productivity Data as those used for Excavation In Item 105

IV. For Item 110 – Foundation Fill Activity Productivity1.) Backfilling and Tamping 3 cu.m./man-day

V. For Item 108 – Aggregate Sub – Base CourseActivity Productivity1.) Quarrying (Excavation & Gravel) 0.50 – 2.0 cu.m./man-day2.) Loading 7 – 10 cu.m./man-day3.) Spreading 8 – 12 cu.m./man-day4.) Compacting 8 – 12 cu.m./man-day5.) Hauling activity should be considered in this item, hence, hauling distance has an important bearing on the cost of the gravelling operation, the maximum acceptable. Hauling distance has to be considered from case to case.

VI For Item 200 - Aggregate Base CourseActivity Productivity1.) Quarrying 0.50 – 2.0 cu.m./man-day2.) Loading 7 – 10 cu.m./man-day3.) Spreading 8 – 12 cu.m./man-day4.) Compacting 8 – 12 cu.m./man-day5.) Hauling – please refer to activity no. 5 of Item 1086.) Screeping 3 – 5

VII. For Item 413 – Reinforced Concrete Pipe Culvert Activity Productivity1.) Crushing of stone for aggregate 0.20 cu.m./man-day2.) Casting of culvert rings 2 man-days/ring3.) Laying of standard culvert (24 in. diameter) Refer culvert laying data below Or 0.60 m. dia., length 6.00 m.,

Page 4: EQUIPMENT  CAPABILITES

Excavation, culvert bad and Backfill4.) Building of headwalls with masonry blocks 10 man-days/2 head walls

If the length of the culvert exceeds 6 meters, the number of man-days has to be increased accordingly.

Culvert laying – this task consist of the excavation of the trench preparing the bed, laying o culvert, backfilling and compaction. Number of man-days required varies with the volume of the excavation and the soil type.

FACTORS TO BE MULTIPLIED TO DETERMINE THE REQUIRED QUANTITY OF EACH MATERIAL

CONCRETE (BASED) on the 88 pounds (lbs.) bag of cement

CLASS “A” CONCRETE (3000 psi)Cement – 9.08 Bags/cu.m. of concrete + 3 - 5 % wastageSand – 0.58 cu.m./cu.m. of concrete + 8 – 10% wastageGravel – 0.77 cu.m./cu.m. of concrete + 8 – 10 % wastage

CLASS “B” CONCRETE (2500 psi)Cement – 8.38 bgs/cu.m. of concrete + 3 – 5% wastageSand – 0.45 cu.m./cu.m. of concrete + 8 – 10% wastageGravel – 0.82 cu.m./cu.m. of concrete + 8 – 10% wastage

CLASS “C” CONCRETE (3500 psi)Cement – 9.77 bags/cu.m. of concrete + 3 – 5% wastageSand – 0.53 cu.m./cu.m. of concrete + 8 – 10% wastageGravel – 0.70 cu.m./cu.m. of concrete + 8 -10% wastage

CLASS “D” CONCRETE (4000 psi)Cement – 11.17 bags/cu.m. of concrete + 3 – 5% wastageSand – 0.44 cu.m./cu.m. of concrete + 8 – 10% wastageGravel – 0.68 cu.m./cu.m. of concrete + 8 – 10% wastage

FOR BRIDGE ESTIMATELumber for false work - 60 bd.foot/cu.m. of concreteNails - 2 kilos/cu.m. of concreteTie wires - 1.1 kilos/cu.m. of concretePainting structural steel - 3 galloons per ton

Page 5: EQUIPMENT  CAPABILITES

AVERAGE FUEL CONSUMPTION PERDAYFUEL ENGINE GEAR GREASE OIL#10 OIL OILCrane, 140 liters(diesel) 4 liters 1 liter 2 lbs. –Diesel Hammer, 20 liters - - - 1 literBulldozer, 200 liters (Diesel) 3 liters 1 liter 1 lb. 1 literPayloader, 100 liters (Diesel) 3 liters 1 liter 1 lb. 1 literGrader, 120 liters (Diesel) 3 liters 1 liter 1 lb. 1 literRoller, 60 liters (Diesel) 2 liters 1 liter/wk. 2 lbs./wk. 1 literDump Truck, 60 liters (Diesel) 1 liter 2liters/wk. 1 lb. 1 literMixer (1-bagger), 40 liters (gas.) - - 0.5 lb. –Vibrator, 15 liters (gasoline) - - - -One Bagger Mixer – 100 bags/dayCrane – minimum of 2 piles/day (16 m. length including spotting)

VOLUME OF TRENCH CU.M.

Soil Type 7 7 – 8 10 -13

In these cases, the work split over two or more days. First the trench should be excavated and then the preparation of the bed, the laying, backfilling and compaction is done. Therefore the volume of the excavation to be limited following rates and then applicable:Soil Type Productivitya.) Hard Soil 3.50 cu.m./man-dayb.) Very hard, stony 2.00 cu.m./man-day

After completion of the trench approximately 4 man – days are needed to lay 6 rings, backfill and compact to finish road level.

I. MECHANIZED ASPECTA. CLEARING AND GRUBBING Dozer Production Horse Power Dense of Vegetation (No. of Trees/Hectare) 0 – 50 51 – 100 101 – 200 201 – 250 250 above 120 360 250 190 160 130 140 420 290 220 185 150 160 480 330 255 210 170 180 540 375 285 240 195 200 600 420 310 265 215

Page 6: EQUIPMENT  CAPABILITES

B. EXCAVATION (Common Materials)B.1 Crane Tonnage Capacity (cu.m./hr.) Bank Volume Canal Structure Creek 15 15 10 10 20 20 15 15 25 25 20 20 30 30 25 25B.2 Dozer Dozer Production (cu.m./hr.) Bank Volume

Horse Power Canal Structure 120 30 15 140 35 20 160 40 25 180 45 30 200 50 35 B.3 Backhoe

Bucket (cu.m.) Production (cu.m./hr.) Bank Volume Canal Structure Creek

0.50 20 15 15 0.75 30 20 20 1.00 40 30 30 1.25 50 40 40 1.50 60 45 45 C. QUARRYING

Dozer Production (cu.m./hr.) Bank Volume Horse Power Common Aggregate Cobbles/Boulders 140 55 60 27 160 60 65 29 180 65 70 31 200 70 75 33J. AVERAGE SPEED OF DUMP TRUCK Type of Road Kilometer per hour With Load Without Load Concrete/Asphalt Road 35 45 Good Maintained Gravel Road 30 35 Poorly Maintained Gravel Road 20 25K. DEMOLITION OF CONCRETE

160 CFN Compressor & two (2) Jack HammerCapacity – 8.00 cu.m./day for massive concrete 12.00 cu.m./day for slab & wall

L. DRIVING OF PILESSteel Pipes: Crane 25 tons with 2 – tons drop hammer, Capacity = 8 L.M./Hr.

Concrete Piles: Crane 25 tons with 2500 kgs. Pile Hammer, Capacity = 2.00 L.M. L.M. per hour, 4.00 L.M.per hour, for thick and thin concrete piles

Page 7: EQUIPMENT  CAPABILITES

MANUAL ASPECT

A. Excavation:A.1 Common Materials Capacity (cu.m./day)Bank Volume & Depth of Excavation Type of Work (meter) Farm Ditchs 3.00 2.50 2.00 Canal 2.50 2.00 1.75 Structure 2.00 1.75 1.50

A.2 Slight Hard Materials (Ind.) Type of Work Capacity (cu.m./man-day) Bank Volume

Canal 1.00 Structure 0.75

B. LOADING CAPABILITIES OF FIVE (5) LABORERS Sand & Common Cobbles Boulders Cement R.S. Bars Lumber Plywood Gravel Cu.m./hr cu.m./hr. cu.m./hr. cu.m./hr. bags/hr kgs/hr. bd.ft./hr. pcs./hr. 4 5 3.5 3 3 6,000 4,000 2.5

C. UNLOADING CAPABILITIES OF FIVE (5) LABORERS Sand & Common Cobbles Boulders Cement R.S. Bars Lumber Plywood Gravel Cu.m./hr cu.m./hr. cu.m./hr. cu.m./hr. bags/hr kgs/hr. bd.ft./hr. pcs./hr.

6 6 5 4 300 7,000 4,000 2.5

D. CUT, BEND & PLACE RSBStructure 1 Steelman & 1 Helper with bar cutterCanal & others 80 kgs./day

E. QUARRYINGCapability cu.m./man-daySand & Gravel Cobbles Boulders 3.50 2.50 2.00

F. DEMOLITION OF CONCRETESlab and Wall 0.50 cu.m./man-dayMassive Concrete 0.20 cu.m./man-day

G. SCREENING OF AGGREGATESGravel 4.00 cu.m./man-daySand 6.00 cu.m./man-day

Page 8: EQUIPMENT  CAPABILITES

H. MANUAL BACKFILLCapacity : 3.00 cu.m./man-day

I. LAYING OF MATERIALS (cu.m./man-day)Cobbles - 2.00Boulders - 1.50

J. SPREADING OF AGGREGATECapacity - 2.50 cu.m./man-day

K. RUBBLE MASONRY (Concreting)Crew: 1 – Foreman, 2 – Mason, 10 – Laborers, 1 – Light Equip. Oper.Capacity: 6.00 cu.m./day

L. GROUTED RIPRAP Crew: 1 – Foreman, 2 – Mason, 10 – Laborers, 1 – Light Equip. Oper.

Capacity: 7.50 cu.m./day

M. CONCRETE HALLOW BLOCK: Setting Capacity sq.m./dayCrew: 1 – Mason, 2 - Laborers Fence Building4” CHB 14 106” CHB 10 8

N. CONCRETE LININGCrew: 1 – Foreman, 2 – Mason, 1 – Light Equipt. Oper. 10 – Laborers with one bagger mixerCapacity: 4.50 cu.m./day

O. INSTALLATION OF STEEL GATESCrew: 1 – Mason & 5 – Laborers 16 X 16 to 24 X 24 2 assy/day Above 24 X 24 1 assy/day

P. CONCRETE WORKS P.1 Fabrication, Placing & Dismantling of Forms Crew: 2 – Carpenters, 4 – Laborers, Capacity: 3.50 cu.m./day for 3000psi Crew: 1 – Carpenter, 1 – Laborer, Capacity: 4.50 cu.m./day canal lining P.2 Concreting and Curing Capability P.2.a. With concrete mixer Crew: 1 – Foreman, 2 – mason, 1 – L.E. Operator, 8 – Laborers Class “A” : 3.50 cu.m./day Class “B” : 3.70 cu.m./day Class “C” : 3.50 cu.m./day Lean Concrete : 4.50 cu.m./day

Page 9: EQUIPMENT  CAPABILITES

Q. PLASTERING OF CHB WALLCrew: 2 – Masons, 2 – LaborersCapability: 12 sq.m./day (One side only)

R. REINFORCED CONCRETE PIPESCrew Capability Diameter Inch Cm. Fabrication Installation1 – Foreman 12 30 15 161 – Mason 18 46 11 111 – Carpenter/Steelman 24 61 9 1212 – Laborers with 30 76 6 101 – Bagger Mixer 36 91 5 8 48 122 3 6

42 4 7

NOTE: TIME OF MIXING = BAGS OF CEMENT/DAY X 10 MIN./BAG 60 MINUTES/HOUR

III. MATERIAL ASPECTClass Strength Max. Aggre. Cement Sand Gravel Boulder Size, inch. Bags/cu.m cu.m./cu.m.A. Concretea. 211 kgs. 1.50 9.00 0.45 0.90 -b. 200 kgs. 2.00 7.00 0.50 1.00 - Canal Lining 200 kgs 1.00 7.50 0.48 0.96 -B. Rubble Masonry w/ 211 kgs. - 4.50 0.225 0.45 0.75C. Grouted Riprap - 4.20 0.35 0.05 1.00 Plain Riprap - - - 0.10 1.00 D. Lean Concrete - 5.00 0.50 1.00 -

1000 psi E. Gravel Blanket - - - 1.00 - F. Filter Drain - - - - -

OTHER MATERIALS Class Type of Strength F. Lumber 1/2”Plywd. Tie Wire Nails Structure Kgs. bd.ft./cu.m. pcs./cu.m. kgs/cu.m kgs/cu.m A Bridge/Flume 211 40 1.00 1.25%RSB 2.50 A Siphon/Box Cul 211 25 1.25 1.20%RSB 2.00 A Other Struc.@inc 211 25 1.25 1.10%RSB 2.00 A 211 5 0.10 - 0.50 B 200 5 - - 0.25 A 211 15 0.40 1.00%RSB 1.50 B 200 5 0.10 1.00%RSB 0.50

Page 10: EQUIPMENT  CAPABILITES

A 211 5 - - 0.25

REINFORCE CONCRETE PIPES Diameter Fabrication Materials per piece Cement Sand Gravel G.I. F. Lumber Tie Wire CW Nails Sheet Inches Bag Cu.m. Cu.m. Pc. Bd.ft. Kgs. Kgs. 12 0.58 0.02 0.05 0.12 0.34 9.28 0.10 18 1.22 0.05 0.10 0.19 0.36 7.72 0.20 24 1.82 0.08 0.15 0.24 0.48 9.75 0.30 30 2.56 0.11 0.21 0.30 0.60 23.22 0.40 36 3.33 0.14 0.28 0.34 0.72 50.43 0.50 42 4.26 0.18 0.36 0.40 0.84 60.84 0.60

INSTALLATION OF R.C. PIPES Diameter Cement Sand Gravel R.S.B. F. Lumber Tie Wire CW Nails Inches Bag Cu.m. Cu.m. Kgs. Bd.ft. Kgs. Kgs. 12 0.21 0.01 0.02 - 2.00 0.20 0.20 18 0.45 0.02 0.04 3.65 2.00 0.20 0.20 24 0.72 0.03 0.06 4.52 3.00 0.30 0.30 30 0.93 0.04 0.08 5.26 3.00 0.30 0.30 36 1.11 0.05 0.10 6.01 4.00 0.40 0.40 42 1.32 0.06 0.12 6.79 4.00 0.40 0.40

PLASTERING C.H.B. BLOCK Size Materials per sq.m. for two (2) sides Sand Cement 4” X 6” 0.034 0.41

G.I. LAYING OF C.H.B. Size Cement Sand Bags/sq.m. Cu.m./sq.m. 4” 0.55 0.046 6” 1.07 0.089

Page 11: EQUIPMENT  CAPABILITES

ACEL RATE 1998

Operated Equipment Description Rate per Day (PhP)Bulldozer Komatsu, D80A-12DD 180Hp 9,160.00Payloader 75 TCM,Clark, 1.53 cu.m. 10,010.00 Capacity, 151 HpRoad Grader Mitsubishi MG 500 170 Hp 8,808.00Dump Truck Japan & other Make, 9,016.00 10 cu.m. CapacityRoad Roller Ingersoll Rand SP48 MI Tons 8,701.00Crane All models, Truck mounted, 11,296.00 Standard mechanically operated 31 – 35 Tons Backhoe Komatsu PC 120, Capacity 90 Hp 9,656.00Transit Mixer Japan Make 3.8 cu.m., 46 cu.m 8,528.00 Capacity 175 HpAir Compressor Gas/Diesel Engine, CFM 20 Hp 1,376.00Plate Compactor 12 Hp Engine Driven 1,648.00Asphalt Paver Worthington 34 (Basic Equipment Only) 3,320.00Asphalt Distributor Little Ford Sprasmaster 5,784.00

Bare Equipment Description Rate per Day (PhP)Pile Hammer (w/o crane) Domag D8 – 22 5,067.00Drop Hammer (w/o crane) Two Tons w/ Pile Hammer 100.00Jack Hammer Stanley, hydraulic w/o power unit 294.00Welding Machine Gas/Diesel Driven 250 Amps., 185 Hp 300.00Concrete Mixer 1 – Bagger 298.00Concrete Vibrator Gas/Diesel Driven 341.00Chainsaw Husquama, 2100 CD w/o Blade 180.00Water Truck All makes, 500 - 1000 gals. 1,773.00Water Pump All models 3.5” – 4” size 119.00Concrete Batch Plant With Cement Silo Manual 5,113.00 /mo. X rated cap. In Cu.m./hour

LABOR OUTPUT CAPABILITIESREMOVAL EXISTING STRUCTURE:

Lumpsum:Installations:Timber:Girts and Girder 0.10 – 0.15 cu.m./man-dayFloor Joist 150 L.M man-daysFlooring Boards 15 – 18 sq.m./man-daysPost 0.14 cu.m./man-days

Page 12: EQUIPMENT  CAPABILITES

Walling/Sliding: Covering 30 sq.m./man-daysFraming, Studs 12 cu.m./man-days(Multiply by the no. of days Double Walling)

Ceiling Joist and Hangers 16 sq.m./man-daysCeiling Boards (4’X8’ Plywood) 30 sq.m./man-daysWindow sashes:

Jamb Fabrication 4 sq.m./man-daysFrames Fabrication 2 sq.m./man-daysJambs Installation 14 sq.m./man-daysFrames Installation 10 sq.m./man-days

Doors:Jambs Fabrication/Installation 2.5 sq.m./man-daysDoor Fabrication/Installation 1 panel/man-days

Paintings:Paint Rollers 125 sq.m./man-daysPaint Brush 50 sq.m./man-daysNeutralizer 100 sq.m./man-days

Truss Fabrication: 0.25 truss/man-daysPurlins Installation 125 sq.m./man-daysFascia Board 0.05 cu.m./man-dayRoof Coverings (GI Sheets) 35 pcs./man-days

Concrete Works:Concrete Pouring 0.30 pcs./man-daysRebars 20 – 30 kgs./man-daysFinishingRough Finish 10 sq.m./man-daysPlain/Fine Finish 8 sq.m./man-days

CHB Filling/LayingA. Cement Mortar

Table 1. Quantity of Cement and Sand for CHB Mortar per square meter wallSize of CHB No. per sq.m. 40 Kg. Mixture Cement Bags A B C Sand4”X8”X16” 12.5 0.525 0.394 0.328 0.04386”X8”X16” 12.5 1.013 0.759 0.633 0.08448”X8”X16” 12.5 1.500 1.125 0.938 0.1250

B. Mortar for PlasteringTable 2. Quantity of Cement and Sand for Plastering per square meter 40 kg. Cement BagMixture Class 16 mm thick 20 mm thick 25 mm thick A 0.288 0.360 0.450 B 0.192 0.240 0.300

C 0.144 0.180 0.225 D 0.120 0.150 0.188 Sand 0.016 0.020 0.025

Page 13: EQUIPMENT  CAPABILITES

1. Find the area of the wall (two faces)Area = 3.00 X 4.00 X 2 facesArea = 24 sq.m.

2. Refer to Table 2 under 16 mm thick plaster Class “B” mixture: Multiply:Cement = 24 X 0.192 = 4.6 bagsSand = 24 X 0.016 = 0.384 cu.m.

C. CHB Footing

Table 3. Quantity of Cement, Sand and Gravel for CHB Footing per square meter Length

Dimension Cement in Bags Class Mixture AggregateCentimeters 40 kgs Cement Sand Gravel Thick Width A B cu.m. cu.m. 10 30 0.270 0.225 0.015 0.030 10 35 0.315 0.263 0.018 0.035 10 40 0.360 0.300 0.020 0.040 10 50 0.450 0.380 0.020 0.050 15 40 0.540 0.450 0.030 0.060 15 45 0.608 0.506 0.034 0.068 15 50 0.675 0.563 0.038 0.075 15 60 0.810 0.675 0.045 0.090 20 40 0.720 0.600 0.040 0.080 20 50 0.900 0.750 0.050 0.100 20 60 1.080 0.900 0.060 0.120

1. Solve for the net length of the CHB wallNet Length = 40 m – (0.25 X 11 post) = 37.25 meters

2. Refer to Table 3 along the 15 X 50 cm footing dimensions 40 kgs. cement Class “A”Mixture; Multiply:Cement = 37.25 X 0.675 = 25.14 say 26 bagsSand = 37.25 X 0.038 = 1.4 say 1.50 cu.m.Gravel = 37.25 X 0.075 = 2.8 say 3.00 cu.m.

MAINTENANCE BY CONTRACT (MBC)METHODS OF CONSTRUCTION

1. PATCHING POTHOLES – should be done to the areas specified by the contracts and plans duly approved by the Engineer Materials to be used must be suitable to acquire best result when compacted. SCHEDULE OF WORKS: MONTHLY

2. RESHAPING - should also be done to areas required in the plan and contracts. All works should conform to what will be described in the specification. SCHEDULE OF WORKS: QUARTERLY

Page 14: EQUIPMENT  CAPABILITES

3. VEGETATION CONTROL AND CLEANING DITCHES – All objects subject for the obstruction of the designed areas should be removed and cleared. SCHEDULE OF WORK: TWICE A YEAR

4. REGRAVELLING - All materials shall consist of hard, durable particles or fine divided mineral matter that can be compacted reaching for stable sub-base. Using especially equipped vehicles materials should be distributed in a continuous uniform layer. The uniform thickness of sub-base materials shall be adjusted prior to the compaction by watering or by drying as required in order to obtain the required compaction. Compaction shall continue until a field density of at least 100 (%) percent of the maximum dry density. SCHEDULE OF WORKS – ANNUALAL

5. BLADING/GRADING – All unstable materials should be removed in areas subject for blading/grading. These areas should be brought to a grade required in the plan and contracts. Compaction will follow using heavier compacting units until required density can be attained.

Page 15: EQUIPMENT  CAPABILITES
Page 16: EQUIPMENT  CAPABILITES
Page 17: EQUIPMENT  CAPABILITES
Page 18: EQUIPMENT  CAPABILITES
Page 19: EQUIPMENT  CAPABILITES