ER420QP-QP(S) Monthly Report No: 03 (May 2013)
ER420-130611-6006-CV-Monthly Report No.03 (May 2013) 1
Client Land Transport Authority
Reference ER420-130611-6006-CV-Monthly Report No: 03 (Ending 31st
May 2013)
Submitted by C & V Engineering Pte Ltd
00 31st
May
2013
3rd
issue Alfredo A. Claro, Jr. Cheng Kim Hua
Rev Date Notes /Description Prepared by Reviewed/Approved
by
C & V ENGINEERING PTE LTDContract ER420QP
Qualified Person (Supervision) for Contract No: ER420QP
For Proposed New Link Between Upper Changi Road and
Upper Changi Road East
QP(S) Monthly Report No: 03 (Ending May 2013)
7/28/2019 ER420-130611-6006-CV-Monthly Report No 03 (May 2013) (3)
2/17
ER420QP-QP(S) Monthly Report No: 03 (May 2013)
ER420-130611-6006-CV-Monthly Report No.03 (May 2013) 2
Contents
1.0 Summary ........................................................................................................................................... 4
1.1 Introduction ... .................................................................................................................................. 4
1.2 Status of Main Contractor works ..................................................................................................... 4
1.3 QP(S) Works ...................................................................................................................................... 5
2.0 Scope of Main Contract and QP(S) Works ...................................................................................... 5
2.1 Main Contract Works ........................................................................................................................ 5
2.2 QP(S) Works ...................................................................................................................................... 6
3.0 Transmittals ...................................................................................................................................... 8
3.1 Letters to LTA on Main contractors matter ..................................................................................... 8
3.2 Letters to LTA on matters other than Main Contractors issue ........................................................ 8
3.3 Letters received from LTA /other Authorities ................................................................................... 9
4.0 Construction Drawings .................................................................................................................... 10
5.0 Meetings, inspections and coordination ........................................................................................ 10
5.1 Meetings and coordination ............................................................................................................. 10
5.2 Inspections carried out ................................................................................................................... 11
6.0 Main contractor construction works, safety and monitoring and areas of concern ...................... 11
6.1 Main contractor construction works .............................................................................................. 11
6.2 Safety and monitoring work ........................................................................................................... 12
6.3 Area of concern ............................................................................................................................... 12
7.0 Contractors Programme and Method Statements ........................................................................ 12
8.0 QP(S) matters QP(S) Manpower Deployment ............................................................................. 12
8.1 QP(S) Manpower Deployment ........................................................................................................ 12
7/28/2019 ER420-130611-6006-CV-Monthly Report No 03 (May 2013) (3)
3/17
ER420QP-QP(S) Monthly Report No: 03 (May 2013)
ER420-130611-6006-CV-Monthly Report No.03 (May 2013) 3
Table 8.1 - Summary of staff mobilised (as at 1st
May 2013) ............................................................... 12
9.0 QP(S) Progress Photographs for the month of May 2013 ......................................................... 14
List of Appendixes
Ref Title
1A QP(S) Scope of works
2A Letter to LTA - Review of Main Contractors submission
3A Letter to LTA and Authorities except on Contractors
submission/issues
3B Letter from LTA/other Authorities
3C BCA Authority Submission Monitoring Table
4A List of Construction Drawings
5A List of Meetings Held/Attended
5B List of Inspections
7A Status of review of Method Statements as at 31 May 2013
8A QP(S) Staffing
9A Monthly Progress Photographs (Month of May 2013)
7/28/2019 ER420-130611-6006-CV-Monthly Report No 03 (May 2013) (3)
4/17
ER420QP-QP(S) Monthly Report No: 03 (May 2013)
ER420-130611-6006-CV-Monthly Report No.03 (May 2013) 4
1.0 Summary1.1 Introduction
The Contract ER420QP is for the provision of Qualified Person(Supervision)Services
for the main contract ER420 - which was awarded to ULT Corporation Pte., Ltd. in 15
October 2012 . ER420QP services commenced on 01st
Mach 2013 and due to complete
by 30th
Nov 2013, to be followed by a 12 months servicing of the contractors defect
liability period.
The ER420QP Contract reference is as follows:
Main contract Duration 9 calendar Months + 12 months defect liability period
Main contract commencement
date
15th
October 2012
Main contract completion date 24th
August 2013 (9 months)
ER420QP Commencement date 01st
March 2013
ER420QP Completion date Nov 2013
% of time lapsed (ER420QP) 33.33% ( 3 out of 9 months)
1.2 Status of Main Contractor works
a) The Contractor has carried out the following works in May 2013:--
i. The Contractor carried out Earth Cutting and Soil Disposal
( To date 1,467 truck loads of soil disposal had been done).
ii. First Batch were Tested for Welded Wire Mesh
( Size B8 and B6, to test B10 subsequently)
iii. Soil Samples were tested.
iv. Geo-Technical Instrumentations were installed on site:
New Road Link Slope Area 1 - Inclinometer
1 - Piezometer
5 - Settlement Markers
1,500mm Wide Drain 2 - Inclinometer
2 - Piezometer
6 - Settlement Markers
1 - Vibration Meter
7/28/2019 ER420-130611-6006-CV-Monthly Report No 03 (May 2013) (3)
5/17
ER420QP-QP(S) Monthly Report No: 03 (May 2013)
ER420-130611-6006-CV-Monthly Report No.03 (May 2013) 5
v. Water Absorption Test done for 900mm wide Drain.
vi. The Contractor casted the slab and wall of 900 mm wide RC Drain at Upper
Changi Road MCO2 West Bound which is approximately 45 Linear meters.
vii. The Contractor casted the slab and wall of 900 mm wide RC Drain at New Road
Road MCO1 North Bound which is approximately 65 Linear meters.
viii.Concrete cube samples were tested for this month of May for Grade 30
Concrete and Grade 40 N Concrete.
ix. Sheet Piling works started on 26 April 2013 for 1,500mm Wide Drain
( Area 1 - CH60 to CH96).
x. Excavation works started at 1,500mm wide RCU Drain at Sheet Piling Area
( Area 1 - CH60 to CH96).
xi. 1,400mm wide x 1380mm deep RCBC Base Foundation started casting on
25 May 2013.
1.3 QP(S) Worksa) QP(S) -C&V Engineering PTE. LTD. Commence QP service on 1st March 2013.
b) QP(S) supervised /observed/reported on the following : --
i. Inspection for Casting of 900mm wide RCU Drain.
ii. Inspection for Casting of 1400mm wide RCBC Drain.
iii. Delivery of 1,500mm wide PC RCU Drain.iv. Delivery of 1,200mm wide PC RCU Drain.
v. Inspection for Earth Works.
vi. Inspection for Sheet Piling Works.
vii.Witness Geotechnical Instrumentation Installation and Monitoring.
viii.Review Method of Statements/Test Reports submitted by Contractor.
ix. Safety and Quality of Works within the project site. (Prevention of
Mosquito Breeding on site).
2.0 Scope of Main Contract and QP(S) Works
2.1 Main Contract Works
The Main Contract ER420 had been awarded to ULT Corporation Pte Ltd in January 2013.
The Main Contract works consists of :
Construction of New Road Between Upper Changi Road and Upper Changi RoadEast.
Construction of New Junctions in the Upper Changi Road and Upper Changi RoadEast.
7/28/2019 ER420-130611-6006-CV-Monthly Report No 03 (May 2013) (3)
6/17
ER420QP-QP(S) Monthly Report No: 03 (May 2013)
ER420-130611-6006-CV-Monthly Report No.03 (May 2013) 6
Construction of Rigid Pavements at the Junctions.
Road Widening a Part of Upper Changi Road.
Milling and Patching works in Upper Changi Road and Upper Changi Road East.
Construction of RCU Drains, RC Box Culverts and RC Sumps.
Construction of Two Bus Bays and Bus Shelters Slabs.
Installation of railings.
Miscellaneous works.
All temporary and monitoring works related to the projects.
2.2 QP(S) Works
The Contract ER420QP is for the provision of Qualified Person(Supervision) Services for
the main contract ER420 - The scope of works is shown in Appendix 1A - QP(S) scope
of works.
QP(S) services include the provision of Professional Engineering Supervision services as
required under the Authoritys requirements and /or the requirements of other authorities
and agencies and to comprise:
Provide qualified site supervision staff as required under the Building Control Act tosupport the QP(S);
Ensure that the construction works are carried out in a safe manner in
accordance with best construction practices; and
Any other professional engineering services as set out in the scope of Services.
7/28/2019 ER420-130611-6006-CV-Monthly Report No 03 (May 2013) (3)
7/17
ER420QP-QP(S) Monthly Report No: 03 (May 2013)
ER420-130611-6006-CV-Monthly Report No.03 (May 2013) 7
APPENDIX 1A - QP(S) Scope of Works
QP(S) is to provide the required Qualified Person (Supervision) [QP(S)] to
a) provide professional engineering supervision services as required under the Authoritysrequirements and /or the requirements of other authorities and agencies;
b) provide qualified site supervision staff as required under the Building Control Act to
support the QP(S);
c) ensure that the construction works is carried out in a safe manner in accordance with
best construction practices; and
d) Any other professional engineering services as set out in the scope of Services.
QP(S)s primarily role is to ensure safety and quality construction by the main contractor andserve as the technical advisor to LTA on the matter of supervision . As no formal contract exists
between The Main contractor and QP(S) , all dealing are through LTA and no changes in the
design is to be accepted during the supervision stage , unless the QP(Design ) and LTA have
approved it.
As the main contract is a Design and Build contract , the main contractor has engaged the design
firm (NBH Consultant) to undertake the full design based on LTAs tender development drawings
and also based on further data/information collected by the main contractor.
The main contractor had also engaged Er. Ng Boon Hoo as PE for temporary works as well as PE(TERS) for temporary earth retaining structures .
At the same time , LTA has also engaged Accredited Checker ( AC) namely ECAS-EJ Consultants
Pte Ltd to provide the required check on permanent design of the works, as well as for the
checking of the AIP documents. Where necessary, an AC will also be engaged by LTA.
QP(S) role is mainly to carry out supervision duties and checking services for method statements
and other proposals submitted by ULT Corporation Pte Ltd. The temporary works which are not
deemed to be checked by an AC are also to be checked by QP(S). However, the permanent
design check , obtainment of the permit to carry out structural works from the BCA, and
modifications, if any, at construction stage are to be handled by the QP(D) .
The full scope of works for QP(S) is as described in the contract document for ER420QP
7/28/2019 ER420-130611-6006-CV-Monthly Report No 03 (May 2013) (3)
8/17
ER420QP-QP(S) Monthly Report No: 03 (May 2013)
ER420-130611-6006-CV-Monthly Report No.03 (May 2013) 8
3.0 Transmittals
3.1 Letters to LTA on Main contractors matter
The list of letters to LTA related to Main contractor is as shown in Appendix 2A (Review ofMain Contractors submissions).
APPENDIX 2A
Letters to LTA - Review of Main Contractor's Submission
Date ReceivedULT REF
No.Subject
Reply/Review
Status
Date
RepliedC & V Ref No.
1 20-May-13 C060/L
Method Statement for Tree
Cutting along Upper Changi
Road
Approved with
Comments21-May-13 5013
S/No
ULT Incoming Letters C & V Engineering Pte Ltd
3.2 Letters to LTA on matters other than Main Contractors issue
The list of letters to LTA on issues other than those linked to Main contractor s
submission are as shown in Appendix 3A (Letters to LTA , except on Main Contractors
submission/ issues ).
APPENDIX 3ALetters to LTA except on Main Contractor's submission/ issues
Date Subject Letter Reference No. Letter Ref. No.
1 5-May-13Monthly Report for
April 2013ER420-130505-6004 6004
2 28-May-13Drainworks Progress
as at 28 May 2013ER420-130528-6005 6005
S/NoC & V Engineering Pte Ltd
Status/ Remarks
7/28/2019 ER420-130611-6006-CV-Monthly Report No 03 (May 2013) (3)
9/17
ER420QP-QP(S) Monthly Report No: 03 (May 2013)
ER420-130611-6006-CV-Monthly Report No.03 (May 2013) 9
3.3 Letters received from LTA /other Authorities
The list of letters from LTA is as shown in Appendix 3B (Letters from LTA/other
Authorities).
No outstanding letters
APPENDIX 3B
Letters incoming from LTA / other Authorities
DateLTA Letter REF
No.Subject
Status /
Remarks
C & V
Ref. No.
1
2
3
4
5
S/No
3.4 Letters received from LTA /other Authorities
The list of letters from BCA and other Authorities is as shown in Appendix 3C (BCA
Authority Approval Status)
APPENDIX 3CBCA Authority Approval status monitoring Table as of May 2013
1
ST01 - ERSS Design calculation for
construction of New Drain from MCO2 CH 030
to MCO1 CH 030
20/3/2013 26/3/2013 __
2ST02 - ERSS Calculation for construction of
New Link Road20/3/2013 23/3/2013 __
S/No Permit To WorkDate of SubmissionSubject BCA Approval date
7/28/2019 ER420-130611-6006-CV-Monthly Report No 03 (May 2013) (3)
10/17
ER420QP-QP(S) Monthly Report No: 03 (May 2013)
ER420-130611-6006-CV-Monthly Report No.03 (May 2013) 10
4.0 Construction Drawings
The construction drawings list is as shown in Appendix 4A (List of Construction Drawings).
APPENDIX 4A
Lists of Construction Drawings
S/No Date Received Drawing Title Drawing Number Revision Number Received from
1 4 March, 2013DRAWING LIST / GENERAL
INFORMATIONL/ER420/RR/GI/0001 ---- ULT
2 4 March, 2013SETTING-OUT PLAN / TRAFFIC
LAYOUT PLANL/ER420/RR/TRF/0001 ---- ULT
3 4 March, 2013 SITE PLAN L/ER420/RR/WS/0001 ---- ULT
4 4 March, 2013 SITE PLAN AND DETAILS L/ER420/RR/WS/0002 ---- ULT
5 4 March, 2013 LONGITUDINAL SECTIONS L/ER420/RR/CLS/0001 ---- ULT
6 4 March, 2013 TREES AFFECTED PLAN L/ER420/RR/WSCL/0001 ---- ULT
7 4 March, 2013 UTILITIES PLAN L/ER420/RR/UT/0001 ---- ULT
8 4 March, 2013 UTILITIES PLAN L/ER420/RR/UT/0002 ---- ULT
9 4 March, 2013 TOPOGRAPHICAL PLAN L/ROAD/SL/SV/1530 ---- ULT
10 4 March, 2013 TOPOGRAPHICAL PLAN L/ROAD/SL/SV/1531 ---- ULT
11 4 March, 2013 SITE PLAN NBH/UPPER CHANGI/ST01 ---- ULT
12 4 March, 2013 SECTION 1-1 TO 3-3 DETAIL A AND B NBH/UPPER CHANGI/ST02 ---- ULT
5.0 Meetings, inspections and coordination
5.1 Meetings and coordination
The list of meetings held in this month is as shown in Appendix 5A (list of Meetings held
/attended).
7/28/2019 ER420-130611-6006-CV-Monthly Report No 03 (May 2013) (3)
11/17
ER420QP-QP(S) Monthly Report No: 03 (May 2013)
ER420-130611-6006-CV-Monthly Report No.03 (May 2013) 11
APPENDIX 5A
List of Meetings held / attended for the month of May
S/No Date Technical Meeting LTA QP(S)/RTO ULT
1 25-May-13
Meeting with PUB- Discussion
with PUB regarding the existing pipe culvert
across Upper Changi Road and Proposal to
maintain the pipe culvert and construct new
sump and box culvert at the existing
Discharge Point.
5.2 Inspections carried out
Inspections carried out for this month are summarised in Appendix 5B (List of Inspections).
S/N No. Form No. Date Inspection Type Location/Chainage Approved Rejected Remarks
1 RC-008 3 May 2013900MM WIDE RCU DRAIN SLAB CONCRETING
WORKSMC02-CH172-CH 143
2 RC-009 10 May 2013900MM WIDE RCU DRAIN WALL CONCRETING
WORKS
MC02-CH32 -CH 49
3 RC-010 13 May 2013900MM WIDE RCU DRAIN SLAB CONCRETING
WORKSMC02-CH49 -CH 65
4 RC-011 21 May 2013900MM WIDE RCU DRAIN SLAB CONCRETING
WORKSMC01-CH49 -CH 65
5 PLT-012 22 May 2013 PLATE LOAD TEST FOR RCBC 1400 X 1380 MC01-CH49 -CH 66
6 RC-012 23 May 2013900MM WIDE RCU DRAIN WALL CONCRETING
WORKSMC01-CH65 -CH 82
7 RC-013 28 May 2013900MM WIDE RCU DRAIN WALL CONCRETING
WORKSMC01-CH49 -CH65.5
8 RC-014 29 May 20131400MM WIDE RCBC BASE FOUNDATION
CASTINGMC01-CH30
9 RC-015 31 May 2013900MM WIDE RCU DRAIN WALL CONCRETING
WORKSMC01-CH92 -CH108
10 RC-016 31 May 20131400MM WIDE RCBC BASE FOUNDATION
CASTINGMC01-CH32
Appendix 5B List of Inspections
6.0 Main contractor construction works, safety and monitoring
and areas of concern
6.1 Main contractor construction works
a) Earth Works, Soil Cutting and Soil Disposal, Sheet Piling Works, Excavation works for
1500mm wide RCU Drain, Casting of 900mm wide RCU Drain, casting of 1400mm wide
RCBC Base Foundation,(Excavation, Installation, C5 Benching Works)
7/28/2019 ER420-130611-6006-CV-Monthly Report No 03 (May 2013) (3)
12/17
ER420QP-QP(S) Monthly Report No: 03 (May 2013)
ER420-130611-6006-CV-Monthly Report No.03 (May 2013) 12
6.2 Safety and monitoring work
a) No non-conformity notice ( NCN) were issued.
b) It is intended to initiate SQN( Safety and Quality Notice) for minor safety and
quality infringements for this project. As of today no SQN were issued aswell.
c) The safety and quality matters were mostly taken up during the PGI and other
routine work walk around.
d) The Contractor doing Safety Tool Box meeting on a daily basis and Sheet Pile Workers
were informed to be very careful whenever working closer to an existing PUB water
line which is a 500mm diameter Asbestos Pipe located along the existing Foot Path at
Upper Changi Road.
6.3 Area of concern
a) SAFETY REVIEW - We have frequently reminded ULT Corporation Pte Ltd that safety
matters particularly at Sheet Piling Area are always top of concerns. So far there
were no incidents reported.
b) INTERNAL PROCEDURES - The Contractor has been reminded to ensure that Method
Statements are submitted at least 28 days before commencement of construction
activities to give sufficient time for the Method Statement to be reviewed. This is
because there are always comments from the LTA and QP(S) which needs to be
addressed before the Contractor is allowed to commence works.
c) UNAUTHORISED WORKS None to report for the month of May of 2013.
7.0 Contractors Submission : Method Statements
For the Complete List of Method of Statement please refer to Appendix 7A .
APPENDIX 7A
Status of review of Method Statements until May 2013
S/NoULT REF
No.Subject
Date
Received
C & V Reply
Date
C & V Ref
No.Reply by C & V
1 C036/L ERSS Submission for New Road Link 7-Mar-13 3-May-13 5012 Accepted
2 C060/LMethod Statement- Tree Cutting
along Upper Changi Road20-May-13 21-May-13 5013
Approved with
comments
8.0 QP(S) matters QP(S) Manpower Deployment
8.1 QP(S) Manpower Deployment
The manpower deployment is shown in Appendix 8A -List of Staff
So far the 1 full time RTO have been deployed , please see Table 8.1
7/28/2019 ER420-130611-6006-CV-Monthly Report No 03 (May 2013) (3)
13/17
ER420QP-QP(S) Monthly Report No: 03 (May 2013)
ER420-130611-6006-CV-Monthly Report No.03 (May 2013) 13
Table 8.1 - Summary of staff mobilised (as at 1st May 2013)
Ref Position Contract
required
number
Mobilised
number for the
month of May
2013
Mobilised
number for the
month of May
2013
Part time
QP(S) Qualified Person
(Supervision)
1 1 1
Full time
RTO Resident Technical
Officer
1 1 1
Total full
time staff
RTOs 1 1 1
Note : * The Duties of RTO 1 has been Resumed from 1st
May 2013.
7/28/2019 ER420-130611-6006-CV-Monthly Report No 03 (May 2013) (3)
14/17
ER420QP-QP(S) Monthly Report No: 03 (May 2013)
ER420-130611-6006-CV-Monthly Report No.03 (May 2013) 14
9.0 QP(S) Progress Photographs for the month of
May 2013
Please see Appendix 9A attached.
7/28/2019 ER420-130611-6006-CV-Monthly Report No 03 (May 2013) (3)
15/17
ER420QP-QP(S) Monthly Report No: 03 (May 2013)
ER420-130611-6006-CV-Monthly Report No.03 (May 2013) 15
7/28/2019 ER420-130611-6006-CV-Monthly Report No 03 (May 2013) (3)
16/17
ER420QP-QP(S) Monthly Report No: 03 (May 2013)
ER420-130611-6006-CV-Monthly Report No.03 (May 2013) 16
7/28/2019 ER420-130611-6006-CV-Monthly Report No 03 (May 2013) (3)
17/17
ER420QP-QP(S) Monthly Report No: 03 (May 2013)
ER420-130611-6006-CV-Monthly Report No.03 (May 2013) 17
`