Upload
andrew-ryan
View
217
Download
0
Tags:
Embed Size (px)
Citation preview
ERCOT Emergency Load Response
Sam Jones Paul WattlesSteve Krein
PUC Demand Response Workshop
Sept. 15, 2006
2PUCT Workshop9/15/2006 2
Load Response at ERCOT
• Background– Under normal circumstances, adequate resources are on line or
available to deal with most situations (RRS, NSRS, RPRS) – Historical need for additional resources due to abnormal events
(usually weather related)• Cold weather events can lead to abnormally high load combined
with fuel curtailments (Feb. 2003)
• Shoulder month events caused by unusual weather at unexpected times (100º weather in April with 20% of capacity offline for seasonal maintenance)
– When abnormal events occur, additional ERCOT tools could reduce the possibility of a need for firm load shedding
– Shrinking reserve margins place the system at greater risk
3PUCT Workshop9/15/2006 3
0%
5%
10%
15%
20%
25%
30%
35%
40%
1999
2000
2001
2002
2003
2004
2005
2006
2007
2008
2009
2010
2011
12.5%
Reserve Margins 1999-2011
Percentage difference between peak load forecast and available generation/resources
12.5% is the target minimum reserve margin established by ERCOT stakeholders and Board
*1,100 MW of mothballed units have been returned to service
Over 26,000 MW of new generation added after passage of Senate Bill 7
Since 1999:• 2,800 MW retired • 8,700 MW mothballed*
Future generation is officially counted only if interconnection agreement completed
Announced generation without interconnection agreements (excludes wind)
2008 is a major concern
4PUCT Workshop9/15/2006 4
Peak Load Variability (Highly Weather Sensitive)
• Swing of ~3500 MW in Peak Load from an “Average” Year to high and low• Represents about 5% of current Peak Capacity
• Load forecasts used for reserve margin calculations are based on average temperatures
Normalized Peak Load Duration
45000
47500
50000
52500
55000
57500
60000
0 5 10 15 20 25 30 35 40 45 50
Hours at Load Level
Lo
ad
(M
W)
1998
1999
2000
2001
2002
2003
2004
Average
ERCOT Peak Load Duration Data Normalized for Economic & Population Growth, 1998-2004
5PUCT Workshop9/15/2006 5
Increasing Demand for Power
• Region-wide demand is growing at an average of 2.3% per year
• Per-home energy consumption has doubled since 1980, despite appliance efficiency gains– Many more
devices in use • 60% of new homes
have ceilings of 9 ft. or higher
• 100% of new homes in southern U.S. have A/C So, what happens when all else fails?
6PUCT Workshop9/15/2006 6
ERCOT Emergency Operations
Operating Procedures scheduled for Board approval on 9/19/06
Event/Action Trigger
Operating Condition Notice Physical responsive reserve below 3300 MW
ADVISORY Physical responsive below 3000 MW
ALERT: Start RMR units, suspend unit testing, deploy RPRS & NSRS
Physical responsive below 2500 MW
Emergency Electric Curtailment Plan
Step 1: Dispatch all generation, public media appeal, DC Ties
Physical responsive below 2300 MW
Step 2: Deploy LaaRs Physical responsive below 1750 MW
Step 3: Instruct transmission operators to shed firm load
Frequency below 59.8 hz
7PUCT Workshop9/15/2006 7
April 17, 2006: 4-5 p.m.
• Additional load resources deployed shortly after 1600 could have averted the need for firm load shedding
0
100
200
300
400
500
600
700
800
900
1000
1100
1200
1300
1400
1500
16:00:00 16:05:00 16:10:00 16:15:00 16:20:00 16:25:00 16:30:00 16:35:00 16:40:00 16:45:00 16:50:00 16:55:00 17:00:00
59.76
59.78
59.80
59.82
59.84
59.86
59.88
59.90
59.92
59.94
59.96
59.98
60.00
60.02
60.04
60.06
REGULATION RESPONSIVE NSRS DEPLOYED FREQUENCY
4 Unit Trips
Graph represents post-LaaR deployment
(instruction issued 15:34)
Firm Load Shed (instruction issued 16:13)
8PUCT Workshop9/15/2006 8
ERCOT Emergency Operations
A proposed new tool for the ERCOT toolbox
Event/Action Trigger
Operating Condition Notice Physical responsive reserve below 3300 MW
ADVISORY Physical responsive below 3000 MW
ALERT: Start RMR units, suspend unit testing, deploy RPRS & NSRS
Physical responsive below 2500 MW
Emergency Electric Curtailment Plan
Step 1: Dispatch all generation, public media appeal, DC Ties
Physical responsive below 2300 MW
Step 2: Deploy LaaRs Physical responsive below 1750 MW
Step 3: Instruct transmission owners to shed firm load
Frequency below 59.8 hz
New Step: Deploy EMERGENCY INTERRUPTIBLE LOAD
9PUCT Workshop9/15/2006 9
Emergency Interruptible Load Response at ERCOT
• Proposal for an Emergency Interruptible Load Response Program – Loads would respond:
• After all regular emergency resources (NSRS and RRS) have been deployed• Under low frequency conditions• Prior to shedding firm load
– Quantity would be based on averting historical firm load shedding events which have occurred in winter peak or shoulder months
• 1000 MW based on history
– Quantity could be adjusted based on projected reserve margins for the following year
– Expected deployment of these load resources would be infrequent • 1 or 2 events in 10 years
– An “event” could entail deployment over several consecutive days (due to an extreme heat wave for example)
– Customers making up these load resources should be prepared for interruption and would replace firm customers who are not prepared
10PUCT Workshop9/15/2006 10
Emergency Interruptible Load Response at ERCOT
• Advantages of an Emergency Interruptible Load Program:– Backstop in times of tight supply– Shedding voluntary and prepared end use customer load is
preferred over involuntary unprepared firm load shedding– Shedding load is 100% effective for balancing to available
generation– Societal cost should be lower than the cost of shedding firm load– Capital cost should be much lower than adding peak generation
capacity
11PUCT Workshop9/15/2006 11
Emergency Interruptible Load Response at ERCOT
• Potential Program Characteristics– Procurement/Payment
• Loads, through their QSEs, would competitively bid to provide service (similar to Black Start)
• 2-year contract term• Initial start-up payment at time of contract award• Pay for performance based on actual load response• End of contract term payment based on availability• Consider a price cap for total compensation
12PUCT Workshop9/15/2006 12
Emergency Interruptible Load Response at ERCOT
• Potential Program Characteristics – Dispatching and Operations
• Dispatched By ERCOT thru QSEs• Would be deployed as a single block after all existing
generation resources: under low frequency conditions but before any firm load shedding
• Needs to be quick responding (10 minute or less response time)
• Require IDR metering for measurement and verification – But no telemetry
• Limit number of hours to be curtailed in any given year
13PUCT Workshop9/15/2006 13
Emergency Interruptible Load Response at ERCOT
•Potential Program Participants–Large Commercial and Industrial Accounts –Government and Municipal Facilities–Retail Chains–Others???
Program should be open to QSEs serving both competitive and NOIE load
14PUCT Workshop9/15/2006 14
Emergency Interruptible Load Response at ERCOT
• A potential issue relating to customer performance:– Prospective customers may already participate in bilateral price
responsive load programs and/or 4CP load adjustments• Payment for emergency interruption thus should be based on
performance, tracked through IDR meter data
Transmission Connected Loads
3000
3200
3400
3600
3800
4000
4200
4400
4600
4800
5000
12:00 13:00 14:00 15:00 16:00 17:00 18:00
Time
Lo
ad
(M
W)
June 1, 2006 June 13, 2006 (4CP)
Gap of 600MW on a probable 4CP day
15PUCT Workshop9/15/2006 15
Summary
Proposed Emergency Interruptible Load Program• ERCOT takes advocacy positions on policy issues when grid
reliability is affected– Proposed emergency interruptible load is a reliability tool
• Emergency interruptible load is needed ASAP– Region will be near or below minimum reserve levels in 2007 and
2008 (and possibly beyond), depending on weather extremes– ERCOT strongly recommends enabling by Spring ’07 shoulder
months• PUC action is crucial
– Stakeholders cannot be expected to develop a program in time, based on history of demand-side initiatives
• Fast-track authorization or commendation from commissioners will be necessary
16PUCT Workshop9/15/2006 16
Questions?