Upload
others
View
20
Download
0
Embed Size (px)
Citation preview
ESS Beam
Diagnostics
Overview
Andreas Jansson, ESS/BI Group
IBIC12, Tsukuba, Japan
2012-10-3
2
Overview
• Overview of ESS Project
• Baseline diagnostics layout
• “Bread-and-butter” diagnostics systems
• Some particular challenges
Berkeley 37-inch cyclotron
350 mCi
Ra-Be source
Chadwick
1930 1970 1980 1990 2000 2010 2020
105
1010
1015
1020
1
ISIS
Pulsed Sources
ZINP-P
ZINP-P/
KENS WNR
IPNS
ILL
X-10
CP-2
Steady State Sources
HFBR
HFIR NRU MTR
NRX
CP-1
1940 1950 1960
Effective therm
al neutr
on f
lux n
/cm
2-s
(Updated from Neutron Scattering, K. Skold and D. L. Price, eds., Academic Press, 1986)
Evolution of the performance of neutron sources
FRM-II
SINQ
SNS
ESS - the neutron source for tomorrow
ESS
Why Neutrons?
Cs Zr Mn S O C Li H
X-rays
Neutrons
- Thermal neutrons have a wavelength (2 Å) similar to inter-atomic distances, and an energy (20 meV) similar to elementary excitations in solids.
- Simultaneous information on the structure and dynamics of materials.
- Cross section varies between elements and even between different isotopes of the same element.
- In particular, hydrogen has a large neutron cross section, different from deuterium.
- Neutrons probe the bulk of the sample, and not only its surface.
- Since neutrons penetrate matter easily, neutron scattering can be performed
with samples stored in all sorts of sample environment: Cryostats, magnets, furnaces, pressure cells, etc.
- The neutron magnetic moment makes neutrons scatter from magnetic structures or magnetic field gradients.
From K. Lefmann
5
Details/Resolution
Intensity opens new possibilities
Complexity/ Count-rate
ESS intensity allows studies of
– complex materials
– weak signals
– important details
– time dependent phenomena
Sweden, Denmark and Norway
cover 50% of construction cost
Remaining 50% from European
partners
Letters of intent from 17 European states
Multilateral MoU for pre-construction
signed in Paris 11 Feb 2012
International Collaboration
Where is ESS?
Where is ESS?
Particle species p Energy 2.5 GeV Current 50 mA Average power 5 MW Peak power 125 MW Pulse length 2.86 ms Rep rate 14 Hz Max cavity surface field 40 MV/m Operating time 5200 h/year Reliability (all facility) 95%
FDSL_2012_05_15
ESS Linac Parameters
Cold neutrons – Long Pulse
• Up to 90% of neutron experiments use cold neutrons
• Pulsed cold neutrons always come as long pulses as a result of the
moderation process
• No compressor ring required, major difference from earlier ESS proposal
F. Mezei, NIM A, 2006
Lab Eout (MeV) Betaout Length (m) Temp (K) Freq (MHz)
Ion source + LEBT Catania 0.075 0.01 4.6 300 -
RFQ Saclay 3 0.08 5.0 300 352.21
MEBT Bilbao 3 0.08 3.5 300 352.21
DTL Legnaro 79 0.39 32.5 300 352.21
Spoke cavities Orsay 201 0.57 58.6 2 352.21
Medium-beta ellipticals Saclay 623 0.80 113.9 2 704.42
High-beta ellipticals Saclay 2500 0.96 227.9 2 704.42
HEBT Aarhus 2500 0.96 159.2 300 -
Spoke resonators Medium-beta ellipticals High-beta ellipticals
Cells per cavity 3 5 5
Cavities per cryomodule 2 4 4
Number of cryomodules 14 15 30
Linac Layout
ESS Linac Optics
13
Linac Component Designs
LNL – 6 September 2012Paolo MEREU – DTL Meeting
DTL
Spoke Cryomodule
Elliptical Cavity Cryomodule
Warm Quad
Doublet Unit
14
Tunnel & RF Gallery Layout
Frequency (MHz)
No. of couplers
Max power (kW)
RFQ 352.21 1 900
DTL 352.21 4 2150
Spokes 352.21 28 280
Medium betas 704.42 60 560
High betas 704.42 129 850
Decision to have a single
integrated control system
for ESS:
- EPICS-based
- ITER control-box
concept
Two hardware prototyping
platforms selected:
• cPCIe
• uTCA.4
Integrated Control System
ESS Master Schedule
200
9
201
0
201
1
201
2
201
3
201
4
201
5
201
6
201
7
201
8
201
9
202
0
202
1
202
2
202
3
202
4
202
5
ESS Program
Phases, Gates and
Milestones
Program level
Accelerator
Target
Instruments
Conventional
Facilities
Program
Initiation Program Set-up Delivery of Contsruction phase
PG 3
PG 2
PG 1
PG 4
Full beam power
on target
Design Update
Prepare to Build
Construction
Technical Design Report
Design Update
Prepare to Build
Construction
Concepual Design
Installation 1-22
Installation
Design Update
Site preparation
Construction
# 7
List
Ground Break
Pre-construction phase
Operations
Installation
Design and Manufacturing 22 instruments
Construction
First Building
First Neutrons
to Instruments
losure
Pre Construction Report
The ESS Site Today
The ESS Site Today
The ESS Site Today
The ESS Site Today
17
New CEO, announced today
James Yeck
Most recently:
Assistant Project Director for Conventional Construction at NSLS-II
and Director of IceCube,
previously Project Director for US-LHC, and
DOE Project Manager for RHIC construction project
Starting at ESS January 1, taking over as CEO March 1
18
… and now, to the diagnostics part…
19
LEBT
2 BCMs
1 Slit + 2 H/V Grids
1 Faraday Cup
Viewports (for profile)
20
MEBT
6 BPMs
4 BCMs (2 fast, 2 slow)
1 Slit + 1 H/V Grid
1 Faraday Cup
4 Wire Scanners
2 Non-invasive profile devices (viewports w camera)
2 Halo Monitors
21
DTL
LNL – 6 September 2012Paolo MEREU – DTL Meeting
12 BLMs (4 ICs, 4 Fast BLMs, 4 Neutron Detectors)
8 BPMs
6 BCMs (5 slow, 1 fast)
4 Faraday Cups
4 Wire Scanners
4 Non-invasive profile devices (viewports w camera)
1 BSM
1 Halo Monitor
22
Cold Linac and upgrade space
3 BLMs per cell
1 BPM per quadrupole
1 BCM per transition between main sections
4 Wire-scanners co-located with non-invasive profile monitors at each transition
4 BSMs at each transition
Example:Spoke Section
23
Target and Dump lines
BLM and BPM at most quads
BCMs to verify beam destination
WS and non-invasive profile at octupoles
Redundant target profile diagnostics
Accelerator to Target Line 25 mm
200 mm
• Simulation with 500,000 particles
Simulation data: Aarhus
Target Diagnostics Layout
• Upstream wire scanners to measure emittance (not shown here)
• BCM above:
– Used to normalize beam density measurements
– Beam accounting (power on target, total energy delivered, etc)
• Redundant measurements at proton beam window and target:
– Halo: Halo monitoring via thermocouple assemblies
– Img: Imaging (luminescent coatings on Proton Beam Window and Target)
– NPM: Non-Invasive Profile monitor (He gas luminescence)
– Grid: SEM in vacuum and ionization in Helium
He at ~1 atm vacuum
Layout of Target Monolith
Target shaft
Target
diagnostics
(no details yet)
Target wheel
Beam Instrumentation Plug
• Optics (upstream,
downstream, H and V)
• H and V grid
• halo
PBW:
Coating (~100 C)
H and V grid
halo
PBW
plug
He-valve
plug
Access to water
cooled
shielding blocks
(if necessary)
Coating on
target (<200 C) 4.4
meters
Optical and
signal path
Drawing: FZ Jülich
Beam Loss
If lost in one spot, the beam can
melt steel in a few microseconds
BLM system needs to detect large
losses in 2us (10us in cold linac)
For small continuous losses, BLMs should
have sensitivity to detect losses leading
to activaton of 1% of the hand-on limit
(~0.01W/m)
Ionization Chamber will be main detector type.
(LHC or SNS type could be used)
Some fast monitors (scintillator, diamond) and
neutron detectors will be used
Beam Loss
• Simulations ongoing to optimize exact detector location
• Have Marie Curie Fellow (through oPAC network) to work on this
Loss location = middle of first quadrupole
Loss angle = 1.5 mrad
Loss intensity = 10^12 protons/sec
28
Beam Current
• Plan to use mainly ACCTs, with some FCTs for bunch studies
• Beam current should be measured to 1%.
• Differential BCM measurements will be used to complement BLMs for
beam loss in the low energy section -> same response time
requirements as BLMs
BPMs
• Need a sensitvity of <0.1mm for
position and 1 degree for
phase.
• Plan to use mostly buttons,
similar to those in E-XFEL
• SNS-like stripline in DTL
• Prototyping electronics in
uTCA.4 (one of two prototyping
platforms agreed on with
Controls Group).
BPMs
• Need a sensitvity of <0.1mm for
position and 1 degree for
phase.
• Plan to use mostly buttons,
similar to those in E-XFEL
• SNS-like stripline in DTL
• Prototyping electronics in
uTCA.4 (one of two prototyping
platforms agreed on with
Controls Group).
BPM Signals
Preliminary studies (using E-XFEL button size) show that button signal gives
adequate sensitivity for production and diagnostics beam for nominal bunch length.
During tune-up of the cold linac, beam will be transported long distances without
longitudinal focussing. The BPM system should be able to provide some position
information to allow to center debunched beam. May need larger buttons for this.
BPM Signals
Preliminary studies (using E-XFEL button size) show that button signal gives
adequate sensitivity for production and diagnostics beam for nominal bunch length.
During tune-up of the cold linac, beam will be transported long distances without
longitudinal focussing. The BPM system should be able to provide some position
information to allow to center debunched beam. May need larger buttons for this.
BPM Signals
Preliminary studies (using E-XFEL button size) show that button signal gives
adequate sensitivity for production and diagnostics beam for nominal bunch length.
During tune-up of the cold linac, beam will be transported long distances without
longitudinal focussing. The BPM system should be able to provide some position
information to allow to center debunched beam. May need larger buttons for this.
• Preliminary ANSYS simulations studies show that
the LEBT slits can be used with the full production
beam.
• TZM, graphite, tungsten are possible materials.
For MEBT slits, beam pulse must be reduced to 50 μs
Short available drift space leads to challenging SEM wire pitch (0.1mm).
Maximum temperature on a graphite slit for different slit angle and
pulse length, the mechanical limits of graphite is around 1600K
Emittance Measurement
• Carbon (33 μm) is the primary choice for wire scanner in
warm linac
In MEBT, beam pulse has to
reduced to 50 μs in order to
avoid thermionic emission and
wire damages
In the DTL the stopping power
is lower and a pulse length of
100 μs can be used.
Maximum temperature on a carbon wire during the slow tuning
mode (1Hz, 50 mA, 100 μs) at the exit of the first DTL tank (beam
sizes are 2 mm in both planes).
Maximum temperature on a carbon wire installed in
the MEBT (1Hz, 50 mA, 50 μs) .
Warm Linac Wire Scanners
Cold Linac Wire Scanners
• Carbon wires are not allowed in cold linac!
• 20 μm tungsten wires are considered.
• Expect no issue with temperature in the cold linac
Estimation of the temperature has been done
assuming σx=σy= 2 mm, with a beam energy of
80 MeV (no acceleration from the
superconducting cavity)
At around 2 GeV, the stopping power reaches its
minimum, assuming the same beam sizes, the
expected temperature are:
• 850 K during the fast tuning mode
• 950 K during the slow tuning mode
Maximum temperature during the fast tuning mode
Maximum temperature during the slow tuning mode
Wire Scanner signal
• Below the pion production threshold: measure secondary emission
– low level of signal above 100 MeV
• Above threshold, detect shower with scintillator
– the geometry of the detector can affect the beam profile reconstruction
• SCL Wire scanner will be used with care, for initial commissioning and for calibration of non-invasive method
Maximum expected current on the wire in function of the beam energy
in SEM mode for carbon wire (black line), tungsten wire (red line) and
in shower mode (blue dots).
Scintillator geometry, in green the
scintillator with the light guide (black
line) .and in grey the beam pipe
Energy deposition on the 4 scintillators in function of the wire
position (E=1GeV)
Non-invasive profile
• Want non-invasive monitor of beam
profile during neutron production
– Co-located with WS for cross-
calibration
• No sync light, and lasers don’t work
on protons …
• Methods under consideration
– Luminescence
– Ionization profile
– Electron/Ion beam scanner
• Recently started tests of luminesce
yield in the SNS HEBT
• Candidate Halo Methods:
– Wire Scanner
• can be used only at low energy where
the secondary emission signal is high
– Wire Scanner with telescope
• can be used only in the HEBT due to
the lake on space in the Linac
– Diamond
• The radiation could be an issue
– Cherenkov fiber scanner
• The radiation could be an issue
• MEBT Scrapers and collimators will also be
instrumented
• Thermocouples at windows and target
Diamond based detector used at spring8
for halo measurement (more detail in
TUPB24, DIPAC09, Basel)
Principe of the telescope in counting mode
Halo Measurement
Bunch Length
• Bunch length measurement in proton linacs is
challenging (short bunch, low beta).
• Feschenko style monitors will be used (several
versions has been proposed and developed)
• Plan topical workshop at ESS in Lund (tentatively
week of January 14th).
Downloaded 01 Dec 2009 to 130.199.3.130. Redistribution subject to AIP license or copyright; see http://proceedings.aip.org/proceedings/cpcr.jsp
Target monitoring
• Plan to use coat target and
window as at SNS
• Proton Beam Window is the
most critical
– Highest current density
• Also the most challenging
– Very thin, SNS style
luminescent coating
would add significant
mass
– Need coating R&D 39
96 CHAPTER 4. ACCELERATOR
Figure 4.132: Particle density plots on the PBW and the target. Notice also the horizontal and verticalbeam profi les on a linear scale.
target will nominally be exposed to a peak current density of 52 µA/cm 2 , whereas the PBW will be hitby a maximum current density of 84 µA/cm 2 , in both cases scaled to an average beam current of 2 mA.As a reference, a peak current density of 250 µA/cm 2 would result from a Gaussian beam without anyflattening. The fixed collimator will in the present scenario intercept 8.3 kW of beam power.
L osses and ap er tu res.
Tails in the beam may lead to losses unless the apertures are sufficiently large. On the other hand, magnetapertures drive the cost and have to be optimized. I n Fig. 4.133 the transverse power loss isocontours inboth planes together with the apertures in the magnets and vacuum chambers are shown. W e observe theabsence of beam losses, which with the present statistics correspond to power levels of less than 10 W .Notice in particular the very large aperture needed in front of the fixed collimator. Furthermore weobserve the reduced apertures in the octupoles as compared to the quadrupoles in general. F inally, thelast quadrupole triplet will have even larger apertures due to the expansion of the beam on the target.
B eam l in es for tu n in g b eam dum ps.
During initial setting-up of the ESS accelerator, and also during startup after shutdowns, a straightbeamline following the S1 line will transport the beam to a commissioning beam dump. This dump isdesigned for 50 kW , and a quadrupole doublet will expand the beam to 12.5 mm RMS on the dump. Inparticular during the initial commissioning of the linac with many phase scans of the cavities, this beamwill impinge on the target with varying energies and energy spreads.
A diagnostic line will transport the beam to a second tuning beam dump. The beamline is designedwith a large ratio between dispersion and betafunction, and hence the energy spread of the beam can bemeasured directly using profi le monitors. Such measurements are otherwise not available. The line willalso include a quadrupole expansion of the beam to the planned 50 kW beam dump. A beam plug (gammablocker) will be inserted in front of the dumps during maintenance personnel access to the linac tunnel.
4.6.2 Col l im ation
Comprehensive simulations of the beam transport from the linac to the target have been performed, butclearly some contingency has to be added in the present technical design of the components. In particular
96
Figure 4.128: Particle density plots on the PBW and the target. Notice also the horizontal and verticalbeam profi les on a linear scale.
Notice in particular the very large aperture needed in front of the fixed collimator. Furthermore weobserve the reduced apertures in the octupoles as compared to the quadrupoles in general. F inally, thelast quadrupole triplet will have even larger apertures due to the expansion of the beam on the target.
B eam l in es for tu n in g b eam dum ps.
During initial setting-up of the ESS accelerator, and also during startup after shutdowns, a straightbeamline following the S1 line will transport the beam to a commissioning beam dump. This dump isdesigned for 50 kW , and a quadrupole doublet will expand the beam to 12.5 mm RMS on the dump. Inparticular during the initial commissioning of the linac with many phase scans of the cavities, this beamwill impinge on the target with varying energies and energy spreads.
A diagnostic line will transport the beam to a second tuning beam dump. The beamline is designedwith a large ratio between dispersion and betafunction, and hence the energy spread of the beam can bemeasured directly using profi le monitors. Such measurements are otherwise not available. The line willalso include a quadrupole expansion of the beam to the planned 50 kW beam dump. A beam plug (gammablocker) will be inserted in front of the dumps during maintenance personnel access to the linac tunnel.
4.6.2 Col l im ation
Comprehensive simulations of the beam transport from the linac to the target have been performed, butclearly some contingency has to be added in the present technical design of the components. I n particularthe power content of the tails of the beam is vital as too much beam power might damage componentsand make maintenance difficult.
Two collimator systems will be installed in the HEBT . The fi rst, as a precaution, will be able to capturelarge-amplitude particles in beam with a system of transverse movable collimators. Two systems with anappropriate phase advance (of around 90 degrees for halo particles) between are needed to perform aneffective collimation. Each system will be designed to capture a few kW of beam power with a collimationefficiency in the order of % . The other system will be a fixed collimator. As described above, the octupolesin the S3 section will produce a flat beam distribution at the expense of sending large-amplitude haloparticles to even larger amplitudes. Hence a fixed collimator is designed to capture particles outside thebeam footprint on the PBW . The collimator will be designed for a power of 25 kW , although lower powersare expected.
• ESS project is ramping up!
– TDR being finalized
– Local organization is growing (and will
continue to grow)
– Expect to formally enter construction phase
next year.
• Baseline diagnostics suite defined. Many
diagnostics systems planned
– Some particular challenges include target
monitoring, bunch length and noninvasive
profile and halo
• Expect many more papers at coming IBICs…
Summary
41
ESS/AD ESS Accelerator Divison (+guests), December 2011
41
ESS/AD
We are hiring! Check out http://www.esss.se/jobs
ESS Accelerator Divison (+guests), December 2011
Recent newcomers!
42
Welcome to Lund, Sweden