Upload
others
View
24
Download
0
Embed Size (px)
Citation preview
EC&PP⇒Lecture 1
1
Mr. Sanjeet Sahoo
Assistant Professor
Department of Civil Engineering
Estimating, costing and professional Practice
Subject Code:- CE40102
Credit-03
Prerequisites: The students have knowledge of
1. Studying and interpreting drawings.
Course Outcome:
CO1. Able to understand principle of estimation, method and units of different
items of work and ideas to measure the quantity of different types of work
for building.
CO2. Able to gain ideas to measure the quantity of different type of culvert and
bridges.
CO3. Able to gain knowledge about the specification for various types of
construction works.
CO4. Able to analyze the rate of different types of construction works.
CO5. Able to understand the network techniques, CPM/PERT method and their
use in project planning.
Course Details:
Unit1:
U1.1: Introduction and principle of estimation, methods of building estimate –
long wall short wall method and centerline method.
U 1.2: Units of different items of work, Estimation of quantity of different
materials in building –estimation of single room building, estimation of
two room building with front verandah.
Unit2:
U 2.1: Different parts of culverts, calculation of quantity for abutment and wing
wall, arch culvert, slab culvert, pipe culvert and bridges
Unit3:
U 3.1:Introduction to specification, principle of general specification, general
specification of different class of building and principle of detailed
specification for various type of works.
Unit 4:
U.4.1Analysis of rate, description, prime cost, schedule rate, cost of different
material and labour, analysis of rates for various types of works like-
plastering, rcc work, mortar work, earth work, brick work , concrete work
etc.
EC&PP⇒Lecture 1
2
Mr. Sanjeet Sahoo
Assistant Professor
Department of Civil Engineering
Unit 5:
U.5.1: Network techniques, introduction to CPM/PERT methods, critical path
calculation, float and slack calculation, EOT,LOT calculation and their use
in project planning construction schedules for jobs, materials equipments,
labour and finance.
Text books:
• 1. Estimating and costing in civil engineering theory and practice, B.N
Dutta, UBS Publishers.
• 2. PERT and CPM, L.S Sreenath, East west press.
• 3. Civil engineering contracts and estimates by B.S Patil, University press
ESTIMATION
Definition:-
• Estimation is the technique of calculating the various quantities and the
expected expenditure to be incurred on a particular work or project.
Before sanction or approval of any project or work, its estimated cost is
worked out and necessary funds are sanctioned by the competent
authority. In case funds available are less than the estimated cost, the
work is done in part or by reducing it or specifications are altered so that
the work can be completed within available funds.
• The primary object of the estimate is to enable one to know beforehand
cost of the work (buildings, structures etc.). Accurate estimate is prepared
by detailed estimated cost.
ACTUAL COST:
• The actual cost of work is known after the completion of work. The
actual cost should not differ much from the estimated cost worked out
at the beginning.
EC&PP⇒Lecture 1
3
Mr. Sanjeet Sahoo
Assistant Professor
Department of Civil Engineering
DETAILED ESTIMATE:
• Preparation of detailed estimate consists of working out the quantity of
different items of work and then working out the cost. It is prepared in two
states.
(i) Detail of measurement and calculation of quantity:
➢ The whole work is divided into different item of works like earthwork,
concrete, brickwork etc.
Sl
no
Description
Or
Particulars
No Length Breadth Height Quantity Remark
1 Earthwork
in
excavation
x
2 DPC work y
n Brick work z
(ii) Abstract of estimated cost:
➢ The cost under each item of work is calculated from the quantity already
computed at workable rate, and the total cost is workout in a prescribed
form. A percentage of 3% to 5% is added for contingencies (unforeseen
expenditure, change in design, change in rates etc.).
➢ A percentage of 1.5% to 2% is also added to meet the expenditure of work
charge establishment (chowkidar, guard etc.).
Item
no
Description
Or
Particulars
Quantity Unit Rate Amount
1 Earthwork
in
excavation
x
2 DPC work y
n Brick work z
EC&PP⇒Lecture 1
4
Mr. Sanjeet Sahoo
Assistant Professor
Department of Civil Engineering
NEED FOR ESTIMATION AND COSTING:
• Estimate gives an idea of the cost of the work and hence its feasibility can
be determined that is whether the project could be taken up in the fund
available or not.
• Estimate gives an idea of time required for the completion of work.
• Estimate is also required to control the expenditure during the execution of
work.
RULES FOR MEASUREMENT
The rules for measurement of each item are invariably described in IS- 1200.
However some of the general rules are listed below.
1. Measurement shall be made for finished item of work and description of each
item shall include materials, transport, labour, fabrication tools and plant and all
types of overheads for finishing the work in required shape, size and
specification.
2. In booking, the order shall be in sequence of length, breadth and height or
thickness.
3. All works shall be measured subject to the following tolerances.
I. linear measurement shall be measured to the nearest 0.01m.
II. Areas shall be measured to the nearest 0.01 sq.m
III. Cubic contents shall be worked-out to the nearest 0.01 cum
4. Same type of work under different conditions and nature shall be measured
separately under separate items.
5. The bill of quantities shall fully describe the materials, proportions,
workmanships and accurately represent the work to be executed.
EC&PP⇒Lecture 1
5
Mr. Sanjeet Sahoo
Assistant Professor
Department of Civil Engineering
6. In case of masonry (stone or brick) or structural concrete, the categories shall
be measured separately and the heights shall be described:
a) From foundation to plinth level
b) From plinth level to first floor level
c) From Fist floor to second floor level and so on.
REQUIREMENTS OF ESTIMATION AND COSTING
1. Estimate gives an idea of the cost of the work and hence its feasibility can be
determined i.e. whether the project could be taken up with in the funds available
or not.
2. Estimate gives an idea of time required for the completion of the work.
3. Estimate is required to invite the tenders and Quotations and to arrange
contract.
4. Estimate is also required to control the expenditure during the execution of
work.
5. Estimate decides whether the proposed plan matches the funds available or
not.
PROCEDURE OF ESTIMATING OR METHOD OF ESTIMATING.
Estimating involves the following operations
1. Preparing detailed Estimate.
2. Calculating the rate of each unit of work
3. Preparing abstract of estimate
EC&PP⇒Lecture 1
6
Mr. Sanjeet Sahoo
Assistant Professor
Department of Civil Engineering
DATA REQUIRED TO PREPARE AN ESTIMATE
1. Drawings i.e. plans, elevations, sections etc.
2. Specifications.
3. Rates.
DRAWINGS
If the drawings are not clear and without complete dimensions the preparation
of estimation become very difficult. So, it is very essential before preparing an
estimate.
SPECIFICATIONS:
General Specifications: This gives the nature, quality, class and work and
materials in general terms to be used in various parts of wok. It helps no form a
general idea of building. Detailed Specifications: These gives the detailed
description of the various items of work laying down the Quantities and
qualities of materials, their proportions, the method of preparation workmanship
and execution of work.
RATES
For preparing the estimate the unit rates of each item of work are required.
1. for arriving at the unit rates of each item.
2. The rates of various materials to be used in the construction.
3. The cost of transport materials.
4. The wages of labor, skilled or unskilled of masons, carpenters, Amador, etc.,
EC&PP⇒Lecture 1
7
Mr. Sanjeet Sahoo
Assistant Professor
Department of Civil Engineering
Different Parts of building
Basic components a building structure:-
1. Roof
2. Parapet
3. Lintels
4. Beams
5. Columns
6. Damp proof course (DPC)
7. Walls
8. Floor
9. Stairs
10. Plinth Beam
11. Foundation
12. Plinth
EC&PP⇒Lecture 1
8
Mr. Sanjeet Sahoo
Assistant Professor
Department of Civil Engineering
1. Roof
The roof forms the topmost component of a building structure. It covers the top
face of the building. Roofs can be either flat or sloped based on the location and
weather conditions of the area.
2. Parapet
Parapets are short walls extended above the roof slab. Parapets are installed for
flat roofs. It acts as a safety wall for people using the roof.
3. Lintels
Lintels are constructed above the wall openings like Doors, windows, Shelves,
etc. These structures support the weight of the wall coming over the opening.
Normally, lintels are constructed by reinforced cement concrete. In residential
buildings, lintels can be either constructed from concrete or from bricks.
4. Beams and slabs
Beams and slabs form the horizontal members in a building. For a single storey
building, the top slab forms the roof. In case of a multi-storey building, the
beam transfers the load coming from the floor above the slab which is in turn
transferred to the columns. Beams and slabs are constructed by reinforced
cement concrete (R.C.C).
5. Columns
Columns are vertical members constructed above the ground level. Columns
can be of two types: Architectural columns and structural columns.
Architectural columns are constructed to improve the building’s aesthetics
while a structural column takes the load coming from the slab above and
transfers safely to the foundation.
6. Damp Proof Course (DPC)
DPC is a layer of waterproofing material applied on the basement level to
prevent the rise of surface water into the walls. The walls are constructed over
the DPC.
EC&PP⇒Lecture 1
9
Mr. Sanjeet Sahoo
Assistant Professor
Department of Civil Engineering
7. Walls
Walls are vertical elements which support the roof. It can be made from stones,
bricks, concrete blocks, etc. Walls provide an enclosure and protect against
wind, sunshine, rain etc. Openings are provided in the walls for ventilation and
access to the building(Door, Window,etc).
8. Floors
The floor is the surface laid on the plinth level. Flooring can be done by a
variety of materials like tiles, granites, marbles, concrete, etc. Before flooring,
the ground has to be properly compacted and levelled.
9. Stairs
A stair is a sequence of steps that connects different floors in a building
structure. The space occupied by a stair is called as the stairway. There are
different types of stairs like a wooden stair, R.C.C stair, metal stairs, etc.
10. Plinth Beam
Plinth beam is a beam structure constructed either at or above the ground level
to take up the load of the wall coming over it.
11. Plinth
The plinth is constructed above the ground level. It is a cement-mortar layer
lying between the substructure and the superstructure.
12. Foundation
The Foundation is a structural unit that uniformly distributes the load from the
superstructure to the underlying soil. This is the first structural unit to be
constructed for any building construction. A good foundation prevents
settlement of the building.
EC&PP⇒Lecture 1
10
Mr. Sanjeet Sahoo
Assistant Professor
Department of Civil Engineering
Unit of different items of works
Serial no Particulars of item Units in MKS
1 Earthwork in excavation in ordinary soil, hard soil,
mixed soil with kankar, bajri etc
Cu m
2 Rock excavation Cu m
3 Earthwork in excavation of foundation and sand
filling
Cu m
4 Quarrying of stone Cu m
5 Cutting of tree Nos
6 Earthwork in cutting, banking, in road and irrigation
canal
Cu m
7 Cement concrete in foundation Cu m
8 RCC work Cu m
9 Lime concrete in foundation Cu m
10 Precast cement concrete Cu m
11 DPC(Thickness specified) Sq m
12 Brickwork in foundation, plinth, superstructure and
arches
Cu m
13 Reinforced brick work Cu m
14 Thin partition wall Sq m
EC&PP⇒Lecture 1
11
Mr. Sanjeet Sahoo
Assistant Professor
Department of Civil Engineering
15 Stone work in wall facing(thickness specified) Sq m
16 Wood work, door and window frame or chowkath,
roof trusses etc
Cu m
17 Door and window shutter Sq m
18 Wood work in partition, ply wood, etc Sq m
19 Steel work(rolled steel joist,, angle, etc) quintal
20 Steel reinforcement bar quintal
21 Cast iron pipe(diameter specified) meter
22 Threading of iron cm
23 Boring holes in iron Nos
24 Cutting of iron joist, channels cm
25 Flooring Sq m
26 Roofing- tile, asbestos, etc.. Sq m
27 RCC roof Cu m
28 Plastering- cement plaster, lime plaster, mud,
etc.(thickness and proportion specified)
Sq m
29 Pointing Sq m
30 Dado(thickness specified) Sq m
31 White washing, colour washing and distempering Sq m
32 Pipe(Rain water, sanitary, waste water pipes) meter
33 Fixing door and windows Nos
34 Lining of irrigation Canal Sq m
35 Bituminous road surfacing Sq m
36 Water closet, wash basin Nos
37 Fan, plug point Point
38 Dismantling of brickwork Cu m
39 Explosive for blasting Kg
40 Supply of bitumen Ton
41 Supply of bare electric wire quintal
42 Paint Litre
Q. Calculate different items of work like, earthwork in excavation of
foundation, cement concrete in foundation, brickwork in superstructure, plinth
and footing work, DPC work and both side (no side and top wall)plastering
and colouring work of a single wall.
EC&PP⇒Lecture 1
12
Mr. Sanjeet Sahoo
Assistant Professor
Department of Civil Engineering
Sl no Description Nos Length(m) Breadth(
m)
Height(m) Quantity Remark
1 Earthwork in
excavation of
foundation
1 6 0.8 0.9 4.32 cu
m
2 Cement concrete in
foundation
1 6 0.8 0.3 1.44 cu
m
3 Brickwork in
plinth and footing
• 1st footing
• 2nd footing
• Plinth wall
1
1
1
6
6
6
0.6
0.5
0.4
0.2
0.2
0.8
0.72cu m
0.60cu m
1.92cu m
4 2.5 cm DPC work 1 6 0.4 ----- 2.4 sq m
5 Brickwork in
superstructure
1 6 0.3 3.5 6.3 cu m
6 Plastering
• Inside
• outside
1
1
6
6
--
--
3.5
4.2
21sq m
25.2 sqm
3.5+0.6+0.1
(10 cm
below G.l)
7 Colouring
• Inside
• outside
1
1
6
6
--
--
3.5
4.1
21sq m
24.6 sqm
3.5+0.6
EC&PP⇒Lecture 1
13
Mr. Sanjeet Sahoo
Assistant Professor
Department of Civil Engineering
Methods of Building Estimation
1. Long wall – Short wall Method. • In Long wall – Short wall method of estimation, the external wall along
the length of the room is intended to be Long wall while the wall
perpendicular to the long wall is stated to be a Short wall.
• To get the length of the long wall or short wall, calculate first the
centerline lengths of the particular wall.
• Then the length of the long wall, (out to out) may be measured after
adding half breadth at each end to its centerline length.
• Thus, the length of short wall measured into in and may be found by
deducting half breadth from its centerline length at each end.
• The length of the short wall usually increases from earthwork to
brickwork in superstructure while the long wall decreases.
• These lengths are then multiplied by depth and breadth to get quantities.
• In short wall and long wall method, the wall along the length of the room
is considered to be a long wall, while the wall perpendicular to a long
wall is known to be a short wall.
• This method is also called separate or individual wall method. This is
simplest method of calculation with minimum error.
Note:-
➢ Long wall out-to-out= c/c length of long wall+ 1 width
➢ Short wall in-to-in== c/c length of short wall- 1 width
2. Center Line Method.
• In Center Line method of estimation, measurements of the wall are taken
up-to center. Internal measurements are generally taken.
• The thickness of half wall from one side and thickness of half wall from
another side in internal measurements are added in order to determine the
length of Center Line of room walls.
• If all of the steps are symmetrical in cross-section of the wall, then the
total length of the Center Line will be uniform for all items of the wall.
• If these steps are not symmetrical, then the length will be determined
separately for each step.
• Despite, if the design of walls is same throughout in building then it is
quite easy to find the length of Center Line.
EC&PP⇒Lecture 1
14
Mr. Sanjeet Sahoo
Assistant Professor
Department of Civil Engineering
• Center Line method is employed easily in circular and polygonal shaped
buildings.
• Despite, this method is also suitable to use in small buildings with few
rooms.
• Wall having different thickness and different foundation details are
difficult to find the quantity in this method.
3. PARTLY CENTRE LINE AND PARTLY CROSS WALL METHOD
• This method is adopted when external (i.e., around the building) wall is of
one thickness and the internal walls having different thicknesses. In such
cases, centre line method is applied to external walls and long wall-short
wall method isused to internal walls.
• This method suits for different thicknesses walls and different level of
foundations. Because of this reason, all engineering departments are
practicing this method.
Q. Calculate different items of work like, earthwork in excavation of
foundation, cement concrete in foundation, brickwork in superstructure, plinth
and footing work, Dpc work of a single room building by both the methods and
compare their quantity.
EC&PP⇒Lecture 1
15
Mr. Sanjeet Sahoo
Assistant Professor
Department of Civil Engineering
➢ Long wall short wall method:
Sl.
no
Description Nos Length(
m)
Breadth
(m)
Height(
m)
Quanti
ty
Rema
rk
1 Earthwork in excavation of
foundation
➢ Long wall
➢ Short wall
2
2
6.2
3.4
0.9
0.9
0.9
0.9
10.04c
um
5.51cu
m
5.3+0.
9
4.3-0.9
2 Cement concrete in
foundation
➢ Long wall
➢ Short wall
2
2
6.2
3.4
0.9
0.9
0.3
0.3
3.35cu
m
1.83cu
m
3 Brickwork in plinth and
footing
➢ Long wall
• 1st footing
• Plinth wall
➢ Short wall
• 1st footing
• Plinth wall
2
2
2
2
5.9
5.8
3.7
3.8
0.6
0.5
0.6
0.5
0.3
0.3
0.3
0.3
2.13cu
m
1.74cu
m
1.33cu
m
1.14cu
m
4 2.5 cm DPC work
➢ Long wall
➢ Short wall
2
2
5.8
3.8
0.5
0.5
--
--
5.8sqm
3.8sqm
5 Brickwork in
superstructure
➢ Long wall
➢ Short wall
2
2
5.6
4
0.3
0.3
3.5
3.5
11.76c
um
8.40cu
m
EC&PP⇒Lecture 1
16
Mr. Sanjeet Sahoo
Assistant Professor
Department of Civil Engineering
➢ Centreline Method:
Total centreline= 5.3+4.3+5.3+4.3=1.2m
Sl.
no
Description Nos Length(
m)
Breadt
h(m)
Heigh
t(m)
Quan
tity
Rem
ark
1 Earthwork in
excavation of
foundation
1 19.2 0.9 0.9 15.55
cum
2 Cement concrete in
foundation
1 19.2 0.9 0.3 5.18c
um
3 Brickwork in plinth
and footing
• 1st
footing
• Plinth
wall
1
1
19.2
19.2
0.6
0.5
0.3
0.3
3.46c
um
2.88c
um
4 2.5 cm DPC work
1 19.2 0.5 --
9.6sq
m
5 Brickwork in
superstructure
1 19.2 0.3 3.5 20.16
cum
Q. Calculate different items of work like, earthwork in excavation of foundation,
cement concrete in foundation, brickwork in superstructure, plinth and footing
work, dpc work, RCC work and plastering work of a single room building by
long-wall and short-wall method.
Data:
Thickness of lintel is 10 cm, foundation depth is 10 cm for staircase and length
of staircase is 1.5m(R=10cm, T=30cm),roof slab projection is 10cm on each
side and thickness is 15cm,chajja thickness 5cm.
EC&PP⇒Lecture 1
17
Mr. Sanjeet Sahoo
Assistant Professor
Department of Civil Engineering
EC&PP⇒Lecture 1
18
Mr. Sanjeet Sahoo
Assistant Professor
Department of Civil Engineering
Sl.no Description No
s
Length(
m)
Breadth(
m)
Height(
m)
Quantity Remar
k
1 Earthwork in excavation
of foundation
➢ Long wall
➢ Short wall
Staircase
2
2
1
6.2
3.4
1.5
0.9
0.9
0.6
0.9
0.9
0.1
.04cum
5.51cum
0.09cum
5.3+0.9
4.3-0.9
2 Cement concrete in
foundation
➢ Long wall
➢ Short wall
Staircase
2
2
1
6.2
3.4
1.5
0.9
0.9
0.6
0.3
0.3
0.1
3.35cum
1.83cum
0.09cum
3 Brickwork in plinth and
footing
➢ Long wall
• 1st footing
• Plinth wall
➢ Short wall
• 1st footing
• Plinth wall
2
2
2
2
5.9
5.8
3.7
3.8
0.6
0.5
0.6
0.5
0.3
0.3
0.3
0.3
2.13cum
1.74cum
1.33cum
1.14cum
4 2.5 cm DPC work
➢ Long wall
➢ Short wall
➢ Deduction door
sill
2
2
1
5.8
3.8
1.2
0.5
0.5
0.5
--
--
--
5.8sqm
3.8sqm
.72sqm
5 Brickwork in
superstructure
➢ Long wall
➢ Short wall
Staircase
Step-1
Step-2
Deduction
Door opening
Window opening
Lintel over window
Lintel over door
and window
2
2
1
1
1
2
1
1
5.6
4
1.5
1.5
1.2
1
1.4
2.55
0.3
0.3
0.60
0.30
0.3
0.3
0.3
0.3
3.5
3.5
0.10
0.10
2.1
1.5
0.10
0.10
11.76cum
8.40cum
0.09cum
0.045cum
0.756cum
0.9cum
0.042cum
0.072cum
10cm
bearing
6 RCC work
➢ Roof slab
room(15cm)
➢ Chajja projection
Front
Side
1
1
1
4.8
3
1.2
5.8
0.45
0.45
0.15
0.05
0.05
4.176cum
0.0675cu
m
0.027cum
EC&PP⇒Lecture 1
19
Mr. Sanjeet Sahoo
Assistant Professor
Department of Civil Engineering
7 Plastering work
Inside
➢ Long wall
➢ Short wall
Outside
➢ Long wall
➢ Short wall
➢ Plinth side out
Deduction
➢ Door
➢ Window
2
2
2
2
1
1
2
5
4
5.6
4.6
19.2(5.6+
5.6+4+4)
1.2
1
--
--
--
--
---
3.5
3.5
3.9
3.9
0.10
2.1
1.5
36sqm
28sqm
43.68sqm
35.88sqm
1.92sqm
2.52 sq m
3 sq m
3.5+0.3
+0.1(10
cm
inside
bearing
into
ground
)
Q. Assignment:-
EC&PP⇒Lecture 1
20
Mr. Sanjeet Sahoo
Assistant Professor
Department of Civil Engineering