ETCS Report

Embed Size (px)

Citation preview

  • 8/13/2019 ETCS Report

    1/34

    Implementingthe European Train Control System

    Cost/Benefit analysis

    ETCS migration strategies oncorridors and at national level

  • 8/13/2019 ETCS Report

    2/34

    Contents

    Foreword . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3

    Executive summary . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5

    1. Objectives and Scope . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8

    2. Data available . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9

    3. Methodology to assess Traction Units associated with

    corresponding Corridors . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 12

    4. International Rail Corridor analysis . . . . . . . . . . . . . . . . . . . . . . . . . . 17

    5. Analysis of Results in the context of an accelerated

    programme on International corridors . . . . . . . . . . . . . . . . . . . . . . . 23

    6. National Migration Strategies . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 25

    7. Global Assessment of Cost of Migration . . . . . . . . . . . . . . . . . . . . . 28

    8. Other Economic Global Factors . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30

    9. Conclusions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 33

    Appendix A: SWOT analysis from the document prepared

    in connection with UIC ERTMS Conference Leipzig 10-11 December 2003. . . . . . . . . . . . . . . . . . . . . . . . . 35

    Appendix B: Corridor analysis of additional costs for faster ETCS

    migration and associated on-board savings . . . . . . . . . . . . . . . . 39

    Appendix C: ETCS migration from a practical perspective . . . . . . . . . . . . . 53

    Appendix D: Global assessment of cost of migration . . . . . . . . . . . . . . . . . . 59

    Acronymes and Abbreviations: . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 79

  • 8/13/2019 ETCS Report

    3/34

    Foreword

    The theme of this years UIC ERTMS Conference, Managing the Migration, has been chosen because it

    serves to highlight that the progressive introduction of ERTMS over the coming years in Europe will need to be

    effectively managed to ensure that optimum benefits are realised from the sizeable investment, at the earliest

    opportunity. It also focuses attention on the national and international aspects of achieving an interoperable

    European railway network, within a reasonable time horizon, which will facilitate an expansion of rail traffic.

    At last years Conference at Leipzig, UIC presented participants with a report and survey of current ETCS

    implementation plans in Europe in order to stimulate the decisionmaking process for the future (entitled:

    Implementing the European Train Control System Opportunities for European rail Corridors).This years

    Conference report, prepared during the course of 2004, builds on the previous work and further explores the

    business cost/benefits of ETCS Migration strategies, from the perspective of the railway organisations within theUIC. In this respect, it is complementary to the macro-economic perspective undertaken in the recent cost/benefit

    analysis carried out by AEIF, as part of the economic appraisal accompanying the control, command and signalling

    elements of the Technical Standard for Interoperability for Conventional Rail.The UIC report has been prepared

    with the assistance of a number of its Members and the input of CER and EIM.

    From the railway actors perspective, it is generally accepted that ETCS is the right long term technical solution,

    but that the migration from existing national systems will be difficult and costly. Its implementation will necessitate

    sizeable financial assistance from Member states and the European Union to enable this transition to be made

    without overburdening the debt on the railway operators and infrastructure managers, who will have to bear the

    burden of the costs in the medium term before the long term benefits from a standardised signalling system are

    realised.The UIC study has examined five differential cost scenarios, using four different financial discounting rates,

    over a forty year period covering an expanded Trans European Network area, inclusive of New Members States

    and pending accession countries.The most probable scenario postulates that the net extra cost to the railways,

    expressed in Net Present Value, could be 12.5 billion Euros.While this is a substantial additional sum, on top of

    other investment priorities, it has to be viewed within the context of other macro-economic parameters and

    decisions that embrace future transport sustainability, quality of life and connectivity within a rapidly changing

    European landscape.

    Another aspect of this report is its analysis of the strategy of migration, based on unifying the signalling systems

    along important corridors. In this respect the relationship between trackside and on-board investment is examined.

    The conclusion, of this part of the report, is that there is a need to be selective in the choice of corridors and in

    the concentration of investment to ensure the earliest realisation of track-side and on-board savings.This arises

    from the fact that, to achieve a reduction in the number of signalling systems along any particular corridor, there

    must be a long-term co-ordinated parallel strategy of trackside and on-board investment, starting as early as

    possible, to reap the benefits in 10 - 20 years time. It is clear that such a long range investment commitment

  • 8/13/2019 ETCS Report

    4/34

    from the railway actors will only be achieved if the vision is shared and confidently underpinned by the character

    of decision making at Member State and European level. It is also necessary to correlate other investment

    requirements with the decision making process relating to ERTMS, as part of a full analysis of corridor

    development needs.

    It is therefore satisfying to report that in the period between the last UIC Conference in Leipzig and todays

    conference in Rome we have experienced a positive engagement between the Member States, the European

    Commission, the railway actors and the supply industry to plan a realistic course for ERTMS deployment on a

    backbone of important economic corridors, which will, in time, link each Member state and new accession

    countries along an interoperable railway network. Reaching final agreement, to commonly aspire to this vision, will

    facilitate development at national level and stimulate the prospect of new business ventures based on the

    exploitation of the potential of the international rail business.The fruits of this engagement should result in thesigning of a Memorandum of Understanding between the parties to constructively develop an ERTMS migration

    approach based on a sound business perspective, underpinned by solid commitments on funding.

    UIC will continue to contribute to the development of such a comprehensive approach and will actively assist in

    promoting a wider understanding of the technical issues involved. It is anticipated that by the time of our next

    ERTMS Conference, planned for the spring of 2006, we will be able to offer further insights into this challenging

    project.

    In parallel with this exciting opportunity in Europe, UIC has, through its activities at a World level, engaged in a

    broadening of the horizon toward the East and West through its promotion of new freight transit corridors,

    reinforcing Europes links with North America and Asia. It is indeed a welcome addition to our Conference that we

    will have speakers on the platform from India and China, which demonstrates the broadening interest in ERTMS

    beyond the borders of the European Community.

    The location of the 2004 UIC ERTMS Conference in Rome and the enthusiasm, pride and generosity shown by

    our host Rete Ferroviaria Italiana (RFI), in making the experience of 300km/h running with ETCS Level 2 on the

    new high speed line between Rome and Naples an attractive part of the conference programme, attests to their

    confidence in this new technology.

    I hope that you enjoy the Conference and find the subject matter of this report stimulating.

    Philippe Roumegure

    UIC Chief Executive

    15 December 2004

  • 8/13/2019 ETCS Report

    5/34

    Executive summary

    The TSIs for High speed and Conventional rail (pending) prescribe the implementation

    of ETCS as a common signalling system in Europe to enhance interoperability between

    rail networks in the future.

    It is generally accepted that ETCS is the right long term technical solution, but that the

    migration from existing national systems will be difficult and costly and many networks

    are questioning whether the net commercial result will be positive.

    This study takes, as its starting point, the assumption that the force of the EU

    Directives precludes any consideration of non-compliance while, at the same time,

    appreciating the position held by certain railways with regard to economic viability.

    Accordingly, the assessment is limited to the following boundary conditions: Establishing whether there are benefits (or less cost) involved in proceeding with a

    more co-ordinated and integrated approach along particular international corridors

    to mitigate system wide costs and reduce operational hindrance.

    Examining whether there is a financial/economic case for justifying a faster rate than

    might be otherwise planned or required by minimalist compliance with the Directives.

    Assessing the appropriate combination of on-board and track-side migration towards

    ETCS having regard to the normal pattern of replacement of life-expired assets which

    must, in any event, be planned to maintain the integrity of the rail system.

    Quantifying the order of magnitude of the costs involved in the migration process as

    a basis of a case for special EU support during the transition period.

    The report starts by examining 10 corridors covering 30,563 equivalent single track km

    and representing about 12% of the overall combined total network length of the

    countries covered by the corridors.These corridors represent a correspondingly higher

    proportion of the TEN network, of the order of 20%, and thus provides a good cross-

    section of the entire pan-European network.

    The additional cost of installing ETCS, in an accelerated programme, in parallel to

    existing national systems, is quantified.This strategy would close many of the gaps in the

    10 selected corridors, where some ETCS is already planned for completion by the end

    of 2008.The study reveals that the cost would be of the order of 638 M on the

    track-side. This cost is over and above the cost of the investment, in the current

    national (or bilateral) plans that have already been approved, or are on the point of

    approval.This extra cost works out at an average of 46.6 k per additional equivalent

    single track km (93.2 k per double track km) for the sections studied.

    5

  • 8/13/2019 ETCS Report

    6/34

    The cost of converting on-board equipment, in such an accelerated programme, would

    be of the order of 8.8 billion for the entire fleet using the 10 corridors

    studied. This would equip about 13,650 traction units (28% of the national fleet in the

    same networks). It is estimated that approximately 1500 of these (11%) would be

    involved in international cross border operations.The cost of only converting this

    reduced fleet would be 1 bil lion .

    The conclusion drawn from this part of the study is that, in general, the cost of

    accelerating the ETCS Programme, by parallel installation on the track-side, will not be

    covered by the savings on international on-board systems.Therefore the pace of

    migration, in the immediate future, will more likely be dictated by national perspectives

    based on life expiry rates of assets and considerations of safety and capacity

    improvement.A global cost benefit analysis, based on a phased programme of ETCS Migration,

    synchronised with replacement of life expired assets and traction overhaul intervals, is

    then carried out.This analysis assesses the difference in the costs and benefits which

    would result from a decision to unilaterally implement ETCS over the entire TEN

    network.The potential global impact on the railway infrastructure Managers and

    Undertakings (i.e. the internal railway system) is determined in Net Present Value

    terms.The analysis restricts itself to the potential direct impact of ETCS and does not

    include general macro-economic and societal benefits, which might ensue from

    interoperability and modal shift.The latter are more speculative and could not be

    attributed to ETCS alone.Therefore the report quantifies the net cost of migration to

    the railway companies so as to determine the funding support that would be required

    to flow from Members States and the EU towards the rail system.

    A number of scenarios are projected over a 40-year time horizon.The probable

    scenario suggests that the implementation of ETCS would result in a negative Net

    Present Value (NPV at 6%) of 12.5 billion . On this basis, the railways within an

    expanded European network of 27 Member State, plus neighbouring networks, would

    need an injection (funding) of this amount of money purely to maintain commercial

    equilibrium with to-days position.

    Taking the broader economic factors into consideration, the study considers that the

    greatest benefits (or least cost) are likely to arise from an integrated strategy involving:

    no further development of national systems;

    focusing on the busiest corridors and the laying of ETCS in parallel to national

    systems on the sections of smallest extent;

    6

  • 8/13/2019 ETCS Report

    7/34

    7

    systematically reducing of the number of on-board systems;

    creating a mass market for ETCS and enhancing rail safety through replacement of

    life expired or obsolete national systems;

    setting a realistic programme of traction fleet conversions to the ETCS C/C system.

    Acknowledging that each network is in the process of elaborating its own national

    rollout out strategy for ETCS migration, the report suggests that the following

    provisions may be considered as a prudent approach to migration:

    order new rolling stock equipped with ETCS or at least prepared for ease of fitment,

    and equip or prepare existing fleet at major overhaul;

    roll out an ETCS programme for track side migration at least in line with the life

    expiry of the signalling system.

    However, it is unlikely that this approach will be sufficient, both on track-side and on-board, for the highly integrated networks, or portions of networks, and a faster path

    will be appropriate.

    The report concludes by observing that the cost of accelerating the ETCS programme,

    by parallel installation on the track-side, will not generally be covered by the savings on

    international on-board systems and so other considerations need to be taken into

    account. However, it considers that the strategy of migration to ETCS is correct from a

    business and technical perspective as it unlocks individual networks from the technical

    perpetuation of bespoke systems and lays the basis for a common safety signalling

    standard for the future.

    It also concludes that the broader economic benefits will not be maximised by an

    apathetic uncoordinated approach to ETCS and that the railway companies must review

    the current situation constructively and prepare, in a united fashion, for the appropriate

    engagement with industry and the EC in relation to the ETCS migration programme,

    system specification and interchangeability issues and cost.

  • 8/13/2019 ETCS Report

    8/34

    1. Objectives and Scope

    The Technical Standards for Interoperability (TSIs) for High speed and Conventional rail,

    have, as an objective, the implementation of ETCS (European Train Control System) as a

    common signalling system in Europe to enhance interoperability between rail networks

    in the future. It is also anticipated that wider benefits will include reduced specification

    cost, speedier cross acceptance and economies of scale in procurement.The increased

    safety and capacity potential of ETCS will also be an important factor, especially for

    networks with less modern signalling systems.

    It is generally accepted that ETCS is the right long term technical solution, especially

    where an effective cost relationship to route benefit can be demonstrated. However,

    the migration from existing national systems will be difficult and costly and many

    networks are questioning whether the net commercial result will be positive.The speedwith which networks progress towards ETCS implementation will be conditioned by

    the persuasiveness of the financial appraisal for their respective businesses.

    This study takes, as its starting point, the assumption that the force of the EU

    Directives precludes any consideration of non-compliance while, at the same time,

    appreciating the position held by certain railways.Accordingly, the assessment is limited

    to the following boundary conditions:

    Establishing whether there are benefits (or less cost) involved in proceeding with a

    more co-ordinated and integrated approach along particular international corridors

    to mitigate system wide costs and reduce operational hindrance.

    Examining whether there is a financial/economic case for justifying a faster rate than

    might be otherwise planned or required by minimalist compliance with the Directives.

    Assessing the appropriate combination of on-board and track-side migration towards

    ETCS having regard to the normal pattern of replacement of life-expired assets which

    must, in any event, be planned to maintain the integrity of the rail system.

    Quantifying the order of magnitude of the costs involved in the migration process asa basis of a case for special EU support during the transition period.

    To achieve these aims it has been considered appropriate to:

    Examine a fast/integrated ETCS migration scenario.

    Analyse the cost implications of the fast/integrated migration.

    Substantiate the corridor philosophy and identify corridors where a faster ETCS

    migration strategy could be the correct decision on the balance of financial cost.

    Examine the least cost/disruptive opportunities for national migration towards ETCS,

    afforded by the replacement of assets and the upgrading of the traction fleet at major

    overhaul.

    8

  • 8/13/2019 ETCS Report

    9/34

  • 8/13/2019 ETCS Report

    10/34

    10

    Table A

    Control/Command Systems overview per country

  • 8/13/2019 ETCS Report

    11/34

    11

    Table Asuite

  • 8/13/2019 ETCS Report

    12/34

    12

    3. Methodology to assess Traction Units

    associated with corresponding Corridors

    Detailed data is currently unavailable to accurately determine the total amount of

    traction units, which would be affected by a decision to introduce a new signalling

    system (such as ETCS), on a particular corridor.Therefore it has been necessary to

    devise a methodology to calculate this figure with sufficient accuracy and confidence for

    use in a global business case scenario.The following approach has been taken:

    a) The total number of traction units per equivalent single-track km has been calculated

    for each country.This ratio (last column in table A)

    ] combined with a global perspective of the network

    concerned, offers an empirical indication of the overall network characteristic.

    A low value of indicates: peripheral/dedicated network traffic (0.05< 0.15).

    A medium value of indicates: intermediate network traffic (0.15< 0.25).

    A high value of indicates: highly integrated network traffic (0.25< 0.36).

    The following table B has been created on this basis:

    Table B

    total number traction units

    total length single track=[

  • 8/13/2019 ETCS Report

    13/34

    13

    It should be noted that large networks, such as in Germany, France, Great Britain and

    Italy will display all three characteristics in different parts of their networks, however

    their national averages tend to be consistently in the low to medium range.

    b) It is then necessary to assess how the systematic introduction of a new signalling

    system influences the amount of traction units, which have to be converted, in

    relation to the national average per km.The general assumption is that the

    introduction of ETCS will have the same repercussion on rolling stock (in terms of

    number of traction units to be equipped) as the systematic introduction of new

    signalling systems in the network had in the recent past.To determine this general

    relationship for ETCS, the amount of actual conversions made in a sample of

    representative railways, associated with their own national signalling systems, hasbeen reviewed in order to derive the multiple factor - (above the national

    average) for the three types of network characteristics outlined above at each stage

    of track conversion.Therefore actual figures, for other systems, have been used to

    plot a range of curves, which are utilised in the ETCS study.

    In this way the graph multiple factor vs.% of track converted to ETCS has been

    created as a best fit compromise using selected information from table A (see

    Graph 1 below).

    In accordance with the multiple factor definition, the percentage of traction units

    converted is calculated with respect to the percentage of track converted for each

    multiple factor curve.

    In this way the graph percentage of traction units converted to ETCS vs.% of track

    converted to ETCS has been created (see Graph 2 below).

    For a given percentage of track converted to ETCS three different percentages of

    traction unit conversion is reported depending on which type of network is being

    considered.

  • 8/13/2019 ETCS Report

    14/34

    14

    Graph 1

    Multiple Factor

    Graph 2

    ETCS Conversion

  • 8/13/2019 ETCS Report

    15/34

    Graph n. 1 is consistent with intuitive understanding. It shows that at the early stage of

    a new signalling system (ETCS in this case) a higher number of traction units per km

    needs to be converted than the national average.This reduces towards the national

    average figure as more of the system is converted.The actual multiple is significantly

    affected by the network traffic characteristic and so three curves are drawn, which can

    then be appropriately utilised for the analysis on each specific corridor.

    For obvious and intuitive reasons when plotting the three best fit curves an asymptote,

    whose equation is the line =1, has been imposed. In fact the multiple factor cannot

    assume values less that 1.

    Graph n. 2 is derived in correspondence with Graph n. 1 by calculating the % of total

    fleet converted, resulting from the application of the multiple factor.This also offers abalancing check on the appropriateness of the multiple factor curves since the inverse

    graphs of cumulative fleet conversion display a characteristic, which is again consistent

    with intuition.

    In this case, also, some restrictions have been placed on the best fit curves.The three

    curves are bounded by the horizontal asymptote line v=100 and they start from the

    point v0 (0;7); that is to say that a minimum of 7% of traction units is necessary from

    the very beginning (track length tending to zero).

    It is important to point out that the two graphs represent a distillation of information

    drawn from a number of networks, with different levels of advancement of national C/C

    systems.This has been used to plot a common set of curves for use in studying the

    migration of the on-board C/C system in a broad economic business case scenario for

    ETCS. It is accepted that, in the case of a stand alone national project involving, say, the

    first 100 km of ETCS, a specific analysis of the percentage of the fleet to be converted

    would be necessary. In this regard it can be speculated that the first step towards ETCS

    on the trackside will necessitate a certain proportion of fleet conversion, possibly of

    the order of 5-10%. However, this specific national aspect has no significant impact on

    the global model in this analysis.

    c) A third step in determining the cost/benefits associated with the timing of the ETCS

    trackside installation and on-board equipment is to estimate the proportion of the

    fleet which operates on the corridor and crosses national boundaries. Potential

    savings in the cost of future on-board C/C equipment could be anticipated on the

    international fleet arising from a unified signalling system.

    To assess this figure, in the absence of specific data, it has been necessary to examine

    national and international traffic-kms (passenger and freight) in each network and

    15

  • 8/13/2019 ETCS Report

    16/34

    16

    propose a relationship between the traction units utilised for freight and passenger

    traffic.The data have been extrapolated from UIC statistics using certain assumptions

    as to fleet distribution.The resulting table C is shown below.

    Table C

    Network international traffic factor

    Note: Network International Traffic Factor = 0.25 Freight ratio + 0.75 Passenger ratio

  • 8/13/2019 ETCS Report

    17/34

    4. International Rail Corridor analysis

    The 10 corridors outlined in the document: Implementing the European Train Control

    System - Opportunities for European Corridors, presented at the UIC ERTMS

    Conference held in Leipzig on 10-11 December 2003, have been taken as the basis of

    this analysis.The ETCS projects on those corridors, where decisions have already been

    made, or are in the process of been taken, have been noted.The financial cost/benefits

    of implementing an accelerated track side programme over and above these plans has

    been examined.The 10 corridors cover 30,563 equivalent single track km and thus

    represent about 12% of the overall combined total network length of the countries

    covered by the corridors.They represent a correspondingly higher proportion of the

    TEN network, of the order of 20%, and thus provide a good cross-section of the entire

    pan-European network.For each corridor a spreadsheet has been produced showing information on

    infrastructure and estimates of ETCS track-side and on-board costs.These costs have

    been mainly obtained by UIC either directly from members or from AEIF.Where

    neither was available an estimate has been made within the range of the figures that

    have been supplied.This has allowed an overall estimate to be made of the additional

    financing cost of advancing the track-side migration in comparison with the potential

    on-board savings on C/C equipment on the international fleet.

    The investment cost of rolling out a GSM-R network has been largely excluded from

    the analysis for the following reasons:

    a) Modern Telecommunications systems are, today, considered as an essential part of

    the basic infrastructure of many railways. Future reliance on such systems will

    transcend ETCS applications.

    b) The additional investment to support data transmission for ETCS levels 2 and 3

    should be somewhat off-set, in the future, by reduced track-side equipment, such as

    the elimination of line-side signalling. However, the exact relationship between the

    costs and benefits will be a function of the extent of commercial exploitation of

    GSM-R and the actual reduction in the signalling equipment.

    c) Many networks intend to use their GSM-R platform to leverage safety and

    productivity gains in other non-signalling related area.

    Accordingly, having regard to the complexity of assigning an appropriate proportion of

    GSM-R investment cost to ETCS, it has been decided to avoid a discussion on the relative

    merits and savings of various levels of ETCS and their dependency or otherwise on GSM-R.

    The results of all the individual corridor sheets (see Appendix B to this document) are

    17

  • 8/13/2019 ETCS Report

    18/34

    18

    brought forward to two summary tables D1 and E1 where a complete analysis has

    been performed per corridor and per country respectively. Each spreadsheet was

    mutually electronically connected forming a unique tool described in figure 1. A

    reduced subset,

    involving a re-analysis

    of four corridors,

    which offer the most

    potential, is also

    shown in tables D2

    and E2.These latter

    corridors were first

    examined as part ofglobal proportion

    (20%) of the TEN

    network and later re-viewed on a specific individual corridor basis.

    A higher proportion of rolling stock (i.e. highly integrated network traffic multiple

    factors) has been assigned in the re-analysis to assess the sensitivity of this on the

    results.

    The working method was iterative: hypotheses agreed at the ETCS migration strategy

    group meetings were implemented in the model, the

    model run and the results evaluated until a final and

    definitive agreement was reached (see the

    following figure 2).

    Fig.1The migration tool

    Fig.2

  • 8/13/2019 ETCS Report

    19/34

    19

    Table

    D

    1

    Corr

    idorsanalysisofadditionalcostsforfas

    terETCS

    migrationand

    associatedon-board

    savings

  • 8/13/2019 ETCS Report

    20/34

    20

    Table

    E

    1

    PerCountry

    analysisofaddition

    alcosts

    forfasterETCSm

    igration

  • 8/13/2019 ETCS Report

    21/34

    21

    Table

    D

    2

    4-Corrido

    rre-analysisofadd

    itionalcostsforfasterETCS

    migrationandassociatedon-board

    savings

  • 8/13/2019 ETCS Report

    22/34

    22

    Table

    E

    2

    PerCo

    untry(relatedtoth

    e4corridors)re-analysisof

    additionalcos

    tsforfasterETCSm

    igration

  • 8/13/2019 ETCS Report

    23/34

  • 8/13/2019 ETCS Report

    24/34

    no financial benefits from an accelerated programme purely on the basis of savings of

    on-board equipment of the international fleet.This means that, as a general

    philosophy, unilateral premature replacement or parallel installation of track-side

    equipment will not be an optimum financial choice.

    b) Corridor 3:PBKAL (fig. 4) displays the most immediate potential for considering an

    accelerated migration programme, especially if the figures estimated for the number

    of international traction units and

    on/board cost savings are

    substantiated. It should be noted that

    the European Commission has also

    expressed an interest in examining thiscorridor.They have sought to establish

    the cost of closing all remaining gaps

    (including TVM areas, which were not

    considered in the UIC study to date).

    A more detailed analysis of the rolling

    stock savings need to be made,

    especially the specific units operating

    between Brussels and Paris.

    c) Three other corridors should be further evaluated in more detail as the international

    component may still represent a strong factor when considered in conjunction with

    any other national benefits.A co-ordinated strategy along all, or part, of these routes

    in the future could present the opportunity to reduce the overall cost of ETCS

    migration for each of the adjoining networks,

    especially if additional national projects result in

    increasing the length of ETCS installed in each

    network, thus reducing the cost of closing the

    remaining gaps.These corridors are (fig. 5):

    Paris-Mannheim-Zurich (corridor 2)

    Rotterdam-Milan-Genoa (corridor 5)

    Antwerp-Bettembourg-Metz-Basle (corridor 6).

    Two general observations support this

    contention.

    Firstly, it can be seen from the summary table

    24

    Fig. 53 promising corridors

    Fig. 4PBKAL corridor

  • 8/13/2019 ETCS Report

    25/34

    of the 10 corridors, aggregated on a national basis (Table E1), that countries such as

    Belgium, Luxembourg and The Netherlands could benefit from an integrated

    approach. Secondly, the results of the market study of the Eurailinfra project (UIC

    Infrastructure Commission) indicate strong future international traffic relationships

    between the countries involved, which offer the prospect to increase the amount of

    international traffic on the corridors in question.

    d) The remaining corridors do not appear to offer an immediate benefit from an

    accelerated integrated ETCS programme along the entire length of the corridor.The

    reason for this is due to insufficient international traction units operating over the

    entire corridor and/or the absence of existing national plans, at this point in time,

    which would provide a sufficient foundation to make the additional filling ofoutstanding gaps an attractive financial proposition.Therefore, there is a need to re-

    examine whether a less extensive proposal on a bilateral or tri-lateral basis between

    some networks, covering a smaller extent of the corridor, would offer a better

    proposition.

    6. National Migration Strategies

    The analysis in the previous section strongly indicates that the pace of ETCS migration

    will be driven more by national perspectives and the age and condition of current

    infrastructure and traction units, than by the attraction of reduced on- board costs of

    the international fleet. Each network is currently in the process of elaborating their

    national rollout strategies for ETCS Migration.These strategies will be influenced by the

    factors outlined in section 1 and in the SWOT analysis in Appendix A.

    It is worth observing that the on-going requirement to replace assets offers an

    opportunity to consider an optimised transition path towards ETCS. In such

    circumstances, the decision is not whether there is financial case for pre-mature

    replacement or parallel installation of equipment, but more a question of assessing how

    ETCS can be introduced instead of like for like replacement of existing systems.

    Compliance with the European Directives has also to be factored into this decision.The

    tables in Appendix C approach the migration to ETCS from this practical perspective.

    Table C1.1 demonstrates that, based on a conservative assessment of the life cycle of

    signalling equipment, there should be a need to replace 4,000 equivalent single track

    kms on the TEN network of an enlarged European Union on an annual basis.This figure

    25

  • 8/13/2019 ETCS Report

    26/34

    26

    rises to 6,400 km per year if one takes the entire enlarged European rail network into

    account. In simple terms this means that there is an opportunity to make progress

    towards ETCS at a regular rate each year.The following steps appear to represent a

    prudent approach to migration:

    1) Define a roll out programme for track side migration at least in line with life expiry

    of the existing signalling systems. Based on an average life of forty years this suggests

    that the European network should be at least 35% converted to ETCS on the track-

    side by 2020. Based on the analysis in section 2 (see Graph 2, in particular) this

    track-side renewal would necessitate an associated proportion of the national fleet

    to be fitted with a compatible on-board ETCS system.The minimum percentage of

    the national fleet to be converted can be estimated from Graph 2, depending on thenetwork characteristic. Knowing the injection of annual new fleet enables one to

    calculate the balance of fleet conversions to be carried on the existing fleet (see

    Table C1.2).

    2) Order new rolling stock equipped with ETCS or at least prepared for ease of

    fitment subsequently for ETCS (Eurocabs, DMI, Odometry etc.) and equip or carry

    out remaining preparation of existing fleet at major overhaul.This would represent

    the least disruptive on-board conversion programme and should minimise or

    eliminate the additional out of service cost for workshop fitment at other non-

    scheduled times. Even at a steady replacement rate of traction units on a forty year

    cycle (average of TEN network fleet assumed to be 30 years in this exercise) and a

    10 year overhaul frequency (fitting only the 10 and 20 year old fleet each year) this

    should see the European fleet pre-fitted by 2020 (see Table C1.3).

    3) In overall terms the above strategy may be sufficient to cover the networks which

    have been described as peripheral or intermediate in this report.The likelihood is

    that some initial injection of fleet conversion will be necessary before settling into a

    national pattern.This is likely to be about 5-10% of current fleet size and is displayed

    at an average of 7% on the curves in Graph 2. However, it is unlikely that the above

    minimalist approach will be sufficient, both on track-side and on-board, for the highly

    integrated networks, or sections of networks around busy hubs, and a faster path

    will be necessary.The aspect can be seen from a comparison of the required

    programme suggested by Table C1.2 and the least disruptive programme suggested

    by Table C1.3.These two tables are combined and shown in Graph 3 (below and in

    appendix C).This shows that while the overall rate of conversion by 2020 should be

  • 8/13/2019 ETCS Report

    27/34

    adequate in all cases there would be a need for more accelerated fitment

    programme in the earlier years on the highly integrated networks, which could be

    compensated by a reduced programme in later years.

    4) The difference in cost between the selected ETCS Migration programme and the

    normal steady state replacement and upgrading of assets can be quantified.This

    amount should represent the additional funding support sought from the EU towards

    ETCS Migration.A global cost benefit analysis has been carried out to assess the

    order of magnitude of the total cost difference for UIC member railways in an

    expanded EU of 27 Member states, plus the neighbouring networks.This is discussed

    in the next Section.

    Graph 3

    Traction fleet conversion to E TCS per network type

    27

  • 8/13/2019 ETCS Report

    28/34

    7. Global Assessment of Cost of Migration

    The study of the 10 selected corridors has revealed that, the cost of closing many of

    the gaps in the overall corridor length, by overlaying ETCS in parallel to existing

    national systems, would be of the order of 638 M.This cost is over and above the

    cost of the investment, in the current national (or bilateral) plans that have already

    been approved, or are on the point of approval.This extra cost works out at an average

    of 46.6 k per additional equivalent single track km (93.2 k per double track km) for

    the sections studied.This serves as a useful global indicator of the extra cost provision

    that would have to be made in the future to roll out a faster strategy on the TEN

    network, than appears to be covered by current national priorities or the needs to

    replace life expired equipment.The global study also reveals that the cost of the on-board Eurocab equipment would

    be of the order of 8.8 billion for the entire fleet using the 10 corridors

    studied. This is to equip about 13,650 traction units (28% of the national fleet in the

    same networks). It is estimated that approximately 1500 of these (11%) would be

    involved in international cross border operations.The cost of only equipping this

    reduced fleet would be 1 bil lion .

    If one adopts the slower migration

    approach, in line with the replacement

    rate of lifeexpired assets, it will be

    possible to optimise the financial costs

    by avoiding the overlay costs of ETCS in

    areas where there is no obvious

    financial benefits from saving of on-

    board equipment. It will also be possible

    to consider a migration of the on-board

    equipment based on an injection of new

    fleet in combination with a less disruptive

    conversion programme of the existing fleet, in accordance with planned overall

    schedules. Such a scenario has been chosen as the basis for a global cost benefit

    analysis to establish the order of magnitude of the total differential cost of migration

    for an expanded Trans European Network area, inclusive of New Members States and

    pending accession countries (fig. 6) , taking the following expenditure elements into

    account:

    a) The difference in signalling replacement cost, and subsequent maintenance, between

    28

    Fig. 6Trans European rail network in a EU of 27 Member

    States

  • 8/13/2019 ETCS Report

    29/34

    ETCS and like for like replacement.

    b) The difference in fleet replacement cost and maintenance, including the on-board

    equipment, with a European ETCS programme compared with continuing with

    installation of national C/C systems.

    c) The cost of converting the on-board systems of a proportion of the existing fleet

    until 2020 to keep pace with the track-side installation of ETCS.

    The differential cost of migration to ETCS for the European Railways Companies

    concerned (Infrastructure Managers and Railway Undertakings) has been calculated.This

    is based on a 40 year time horizon, applying a range of discount factors (0%, 4%, 6% and

    8%) to the annual estimated difference in anticipated expenditure in order to arrive at a

    Net Present Value (NPV). In addition to assessing the difference in investment cost and

    savings, an attempt has been made to place a monetary value on other potentialincremental benefits arising from the uniform adoption of ETCS - such as gain in track

    capacity and savings arising from a reduction in rail fatalities and injuries.The analysis,

    however, does not consider other more general macro-economic and societal benefits,

    which might ensue from interoperability and modal shift.The latter are more

    speculative and could not be attributed to ETCS alone.Therefore the study

    concentrates on quantifying the net cost of migration to the railway companies so as to

    determine the funding support that would be required to flow from Member States and

    the EU towards the rail system.

    Furthermore, at this stage of early development of ETCS, and without a strong

    indication and commitment of industry, it is not possible to attribute potential benefits

    or cost savings in spare parts or other procurement benefits due to economies of

    scale. It might also be reasonable to anticipate savings related to reduced training for

    drivers, maintenance and operational staff due to the adoption of a unique CC system

    in the long term. However, the study considered that the cost/benefit would be broadly

    neutral during the time horizon of the analysis due to higher potential costs in the early

    stage being compensated by benefits of the unique system in the long term.

    The full calculations are contained in Appendix D, and a summary of the results is

    29

  • 8/13/2019 ETCS Report

    30/34

    30

    shown below.

    Differential cost of migration to E TCS(Billion )

    The probable scenario suggests that the implementation of ETCS would result in a

    negative Net Present Value (NPV at 6%) of 12.5 billion . On this basis, the railways

    within an expanded European network of 27 Member State, plus neighbouring

    networks, would need an injection (funding) of this amount of money purely to

    maintain commercial equilibrium with to-days position.

    This figure correlates well with the cost elements (both on-board and track side)

    calculated in a separate AEIF study, taking into account the fact that the study is based

    on migration costs within the EU 15 member states.

    8. Other Economic Global Factors

    Overall, this analysis has been concerned with the optimisation, mainly in terms of

    financial cost/benefit, of the ETCS migration strategy. However, assuming that the

    financial imbalances are addressed in discussions with the EC and Member States, and

    taking the broader economic horizon into account, the greatest benefits are likely to

    arise from the following strategy:

    1) No further development of national systems so as to:

    effectively concentrate the attention of the signalling industry to the more rapid

    development and support of ETCS, to include finalisation of specifications and

    progress on interchangeable supplier equipment;

    begin to gain benefits through economies of scale procurement and reduced cross

    acceptance costs;

    de-risk the transfer of specialist signalling system principles and knowledge to

  • 8/13/2019 ETCS Report

    31/34

    31

    manufacturers and outside industry, having regard to the trend of reducing in-house

    expertise within many networks.

    2) The least cost route to an accelerated migration at international level, and towards

    meeting the goal of interoperability, will be achieved by focussing on the busiest

    corridors and considering laying ETCS in parallel to national systems on the sections

    of smallest extent.

    3) Systematically reducing the number of on-board systems will bring benefits for train

    operators in time. In this regard there are over twenty European signalling systems.

    By 2010, ETCS will be, at least, the fifth most extensive signalling system with over

    16,000 equivalent single track kms installed, based on current commitments alone

    (see table F below for plans to 2008).

    Table FThis will establish it as a dominant system and will leave only PZB, Crocodile, KVB,

  • 8/13/2019 ETCS Report

    32/34

    ATP/TPWS systems with a greater coverage, predominantly in Germany, France & UK

    (see Table G).

    Table GThe extent of such systems means that on-board parallel equipment will still be

    required on many international routes crossing these networks for many years.This

    study shows that there is a weak financial case for accelerating the migration of track

    side equipment. However, if it can be shown that there are wider economic or practical

    technical benefits, by minimising the amount of international foreign trains requiring

    such additional on-board equipment, an accelerated programme of ETCS implemented

    in important transit corridors such as from Belgium,The Netherlands, crossing North

    and Eastern France and South-Western and Eastern Germany to Switzerland, Italy and

    Austria would seem to be the best place to start.

    4) As a general observation it may be stated that the installation of ETCS in peripheral

    networks, outside of the central European corridor areas, is unlikely to be financially

    justifiable based purely on interoperability benefits. However, the installation of

    ETCS, consistent with national plans, will be an important contributor to enhancing

    rail safety and will create the mass market for ETCS through replacement of life

    expired or less modern national systems.

    5) The underlying rate at which existing national systems can be eliminated will be

    largely determined by the pace of traction fleet conversion to ETCS C/C system.

    While the parallel fitting of ETCS on the track-side can reduce pressure on national

    fleet conversions, this will not be a substitute for a well organised long term strategy

    for on-board equipment. Failure to recognise this could result in severe restrictions

    32

  • 8/13/2019 ETCS Report

    33/34

    on fleet operations and high out-of-service time if programmes have to be

    implemented at short notice due to sudden obsolescence, unsustainable maintenance

    cost or life expiry of the predominant national system. It is important to recognise

    that it can take up to forty years of gradual replacement, in normal steady state

    conditions, to replace/upgrade an entire national system or fleet. It is also evident

    that by about 2015, few of the existing systems may be supported by the

    manufacturers.

    9. Conclusions

    This report has examined the cost/benefits of ETCS Migration strategies from a

    financial, economic and organisational perspective. It is clear that the cost ofaccelerating the ETCS Programme, by parallel installation on the track-side, will not be

    covered by the savings on international on-board systems.Therefore the pace of

    migration, in the immediate future, will be dictated by national perspectives based on

    life expiry rates and considerations of safety and capacity improvement.

    Nevertheless the broader economic benefits, outlined in the report, will not be

    maximised by an apathetic uncoordinated approach to ETCS.There is technical

    consensus around the ETCS solution for the long-term and the force of EC Directives

    will ensure the future evolution in this direction. It is reasonable to assume that a

    unified signalling system will bring economies of scale in an area which is fragmented

    and specialised.

    Therefore, for the long-term, the strategy of migration to ETCS is correct from a

    business and technical perspective as it unlocks individual networks from the technical

    perpetuation of bespoke systems and lays the basis for a common safety signalling

    standard for the future.These are important issues for companies with aspirations

    towards commercialisation and public accountability.

    Accordingly, there is a need to consider ETCS as the next generation signalling system

    and in accordance with any replacement strategy, railways will need to plan in such a

    manner so as to ensure the continuity of their future operations in the light of future

    signalling market conditions.

    Ambiguity will only be a feeding ground for indecision and will result in a lack of real

    commitment from industry to make the necessary steps to advance rapidly with

    reliable, safe and economical solutions, including interfacing with existing systems and

    inter-change between supplier products.

    Therefore the railway companies must consider ETCS in the context of a more global

    economic perspective and prepare, in a united fashion, for the appropriate engagement

    33

  • 8/13/2019 ETCS Report

    34/34

    34

    with industry and the EC in relation to the migration programme and the practical

    resolution of concerns such as the stabilisation of specifications, interchangeability of

    supplier equipment, funding and cost.

    It is reassuring to report that such discussions have commenced and should shortly

    Fig. 7Relevant corridors