Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
Document Number: ETS 05-0301
Version: 2.0
Date: 14/12/2017
TH
IS IS
AN
UN
CO
NT
RO
LL
ED
DO
CU
ME
NT
, T
HE
RE
AD
ER
MU
ST
CO
NF
IRM
IT
S V
AL
IDIT
Y B
EF
OR
E U
SE
ENGINEERING TECHNICAL SPECIFICATION
ETS 05-0301
BLACK START CONTROLLER FOR GRID AND PRIMARY SUBSTATION BATTERY CHARGER SYSTEMS
Network(s): EPN, LPN, SPN
Summary:
This standard applies to both new trip/close battery installations and the upgrade of existing trip/close and intertripping battery charger systems in Grid and Primary sites across the UK Power Networks licence area.The Black Start Controller unit has been developed by UK Power Networks in conjunction with established substation battery and charger suppliers and complies with ENA Recommendation (ENA ER G91), approved by OFGEM. Document is to be used in conjunction with ETS 05-0300.
Author: John Moutafidis Date: 14/12/2017
Approver: Paul Williams Date: 15/12/2017
This document forms part of the Company’s Integrated Business System and its requirements are mandatory throughout UK Power Networks. Departure from these requirements may only be taken with the written approval of the Director of Asset Management. If you have any queries about this document please contact the author or owner of the current issue.
Applicable To
UK Power Networks External
☒ Asset Management ☒ G81 Website
☒ Capital Programme ☐ UK Power Networks Services
☐ Connections ☐ Contractors
☐ Health & Safety ☒ ICPs/IDNOs
☐ Legal ☐ Meter Operators
☐ Network Operations
☐ Procurement
☐ Strategy & Regulation
☐ Technical Training
Black Start Controller for Grid and Primary Substation Battery Charger Systems
Document Number: ETS 05-0301
Version: 2.0
Date: 14/12/2017
© UK Power Networks 2017 All rights reserved 2 of 18
Revision Record
Version 2.0 Review Date 02/01/2019
Date 20/12/2017 Author John Moutafidis
Reason for update: Periodic review
What has changed: Changed process flow diagram in Appendix B. added definition for “Sacrificial” and “Reserved”. Re-numbered from EDS 03-0030
Version 1.0 Review Date 25/09/2017
Date 04/07/2014 Author Seán Stack
New Document: Written to meet the requirements with regard to substation protection battery resilience in Black Start situations as specified by Ofgem.
Black Start Controller for Grid and Primary Substation Battery Charger Systems
Document Number: ETS 05-0301
Version: 2.0
Date: 14/12/2017
© UK Power Networks 2017 All rights reserved 3 of 18
Contents
1 Introduction ............................................................................................................. 5
2 Scope ....................................................................................................................... 5
3 Definitions ................................................................................................................ 5
4 General Requirements ............................................................................................ 6
5 Functions of the Equipment ................................................................................... 6
5.1 Controller Operation .................................................................................................. 6
5.1.1 Battery String 2 Disconnection Due to Loss of AC Supply ......................................... 6
5.1.2 Low Voltage Disconnection ....................................................................................... 7
5.1.3 SCADA Controls ........................................................................................................ 7
5.1.4 Bypass Contactor ...................................................................................................... 7
5.2 Configuration with Existing Equipment....................................................................... 7
5.2.1 Grid Site with a Newly Installed (n+1 dual string) Battery Charger System ................ 7
5.2.2 Grid or Primary Site with an Installed Dual Separate (LPN Design) Battery Charger System ........................................................................................................ 8
5.2.3 Grid or Primary Site with a Recently Installed Single String Battery Charger System ...................................................................................................................... 8
5.2.4 Grid or Primary Site with a Traditional Single String (Plante Cell) Battery Charger System ...................................................................................................................... 8
5.2.5 Auxiliary Wiring .......................................................................................................... 8
5.2.6 SCADA Battery Charger Systems ............................................................................. 8
5.2.7 Intertripping Battery Charger Systems ....................................................................... 8
5.3 System Environment ................................................................................................. 9
5.4 Environment .............................................................................................................. 9
6 Technical Requirements ......................................................................................... 9
6.1 System Monitoring ..................................................................................................... 9
6.2 Connections to Telecontrol ........................................................................................ 9
6.3 Controller ................................................................................................................. 10
6.4 Maintenance ............................................................................................................ 11
7 Testing ................................................................................................................... 11
8 Training .................................................................................................................. 11
9 Installation and Commissioning ........................................................................... 11
10 Drawings and Documentation .............................................................................. 11
11 Delivery .................................................................................................................. 11
12 References ............................................................................................................. 12
13 Dependent Documents.......................................................................................... 12
Appendix A - Specific Requirements for Black Start Controllers .................................. 13
Black Start Controller for Grid and Primary Substation Battery Charger Systems
Document Number: ETS 05-0301
Version: 2.0
Date: 14/12/2017
© UK Power Networks 2017 All rights reserved 4 of 18
Appendix B - Flow Diagram of Black Start Controller Processes ................................. 14
Appendix C - Operation in a Black Start or Prolonged Outage Scenario ...................... 15
Black Start Controller for Grid and Primary Substation Battery Charger Systems
Document Number: ETS 05-0301
Version: 2.0
Date: 14/12/2017
© UK Power Networks 2017 All rights reserved 5 of 18
1 Introduction
This standard details the design requirements of UK Power Networks for the Black Start Controller functionality required on Grid and Primary trip/close and upgraded Intertripping batteries charger systems. This will allow existing UK battery charger systems to be upgraded where necessary as per OFGEM recommendations and new installations to be specified cost effectively without 72 hour resilient battery packs.
OFGEM’s recommendation states that each DNO ensures that SCADA control and tripping batteries (including Intertripping systems) in all Grid and Primary substations are serviceable after a period of Black Start recovery. This period is estimated by OFGEM to be 72 hours.
2 Scope
This standard applies to both new Trip/Close battery installations and the upgrade of existing Trip/Close and Intertripping battery charger systems in Grid and Primary sites across the UK Power Networks licenced areas.
This document is to be used in conjunction with UK Power Networks Battery and Charger Specification, ETS 05-0300.
The Black Start Controller unit has been developed by UK Power Networks in conjunction with established substation battery and charger suppliers and complies with ENA Recommendation (ENA ER G91), approved by OFGEM.
3 Definitions
‘Black Start’ A “Black Start” is the carefully co-ordinated restoration of generation and network demand following a partial or complete shutdown of supplies affecting all or part of the National Grid (NG) system. It results from the disconnection of generation sets frofffm all or parts of the country’s 400kV and 275kV systems rendering the affected system effectively “dead”.
‘Supplier’ Refers to a manufacturer or other organisation supplying equipment for use on UK Power Networks’ distribution systems.
‘East of England Network’ (EPN) refers to the distribution network for which UK Power Networks is the licence holder.
‘Southeast Network’ (SPN) refers to the distribution network for which UK Power Networks is the licence holder.
‘London Network’ (LPN) refers to the distribution network for which UK Power Networks plc is the licence holder.
Black Start Controller for Grid and Primary Substation Battery Charger Systems
Document Number: ETS 05-0301
Version: 2.0
Date: 14/12/2017
© UK Power Networks 2017 All rights reserved 6 of 18
4 General Requirements
The Black Start Controller functionality will be incorporated into all UK Power Networks battery charger systems which have battery resilience of less than 72 hours and are deemed critical in a Black Start situation. By definition this refers to existing Intertripping (where applicable) and Trip/Close and new Trip/Close battery charger systems in Grid and Primary substations across the UK Power Networks licenced areas (SPN, LPN and EPN).
5 Functions of the Equipment
The following section describes the operation UK Power Networks have specified for the Black Start controller installed in a dual string battery charger system. A simplified battery schematic with the Black Start controller is shown Appendix A.
5.1 Controller Operation
The controller has multiple functions:
Disconnect battery string 2 due to loss of AC supply.
Disconnect battery string 1 due to battery low volts detection.
Disconnect/Re-connect either battery string with SCADA interface.
Interface with SCADA and manual controls.
These functions are described in more details below and are shown in flowchart format in Appendix B.
5.1.1 Battery String 2 Disconnection Due to Loss of AC Supply
1. In the event of a sustained loss of AC power supply to battery charger system, the
contactor in series with battery string 2 will be opened after a configurable time delay (0 -
120min), which can be overridden via SCADA.
2. When a sustained AC power supply is restored for a configurable time (0 - 10min), the
string 2 contactor will be closed.
3. If the AC power supply is then lost again within a configurable time (0 - 30min) the
string 2 contactor will be reopened immediately.
4. Step 2 and 3 above will repeat unless the AC power supply is sustained for longer than
the delay above (0 - 30min). The system will then return to its normal state and a further
supply failure will result in string 2 disconnection as per step 1 above.
Black Start Controller for Grid and Primary Substation Battery Charger Systems
Document Number: ETS 05-0301
Version: 2.0
Date: 14/12/2017
© UK Power Networks 2017 All rights reserved 7 of 18
5.1.2 Low Voltage Disconnection
To prevent irreparable damage to the batteries when used to supply to the load for prolonged time without AC power supply present, a low voltage disconnection (LVD) scheme is to be used to monitor and disconnect battery string 1 independently. In the event of AC power supply failure, the logic used by the LVD scheme shall be:
1. If the voltage on battery string 1 falls below a configurable pre-set level, the contactor in
series with battery string 1 will be opened. This contactor will reclose on restoration of
AC power.
2. If the voltage on battery string 2 falls below a configurable pre-set level, the contactor in
series with battery string 2 will remain closed and allow the battery to be sacrificed to
maintain the DC load.
5.1.3 SCADA Controls
The controller shall interface and facilitate the control of the Battery String Contactors (BSC1 and BSC2) via SCADA. These controls shall take precedence over the manual and automatic controls.
The preference will be for the controller to communicate directly with the SCADA RTU. If this is not possible, 6 interposing relays will be needed (shown in blocks of 2):
Auto / SCADA Control.
Battery String 1 Contactor Open / Close.
Battery String 2 Contactor Open / Close.
5.1.4 Bypass Contactor
The Black Start controller shall be equipped with a local manual latching contactor. This will be used to bypass Battery String 2 Contactor (BSC2) via local control in the event of controller failure with the BSC2 open. The bypass facility will also allow site personnel to work on the battery charger system, local LV supply or Black Start controller without compromising the site protection scheme.
The Bypass Contactor shall be controlled locally via a latching switch/button and contactor.
5.2 Configuration with Existing Equipment
In all situations the resilience of the current battery systems will be considered prior to undertaking any work. This will provide an indication of the level of battery system upgrade/modification required to meet the requirements.
The standards specified in ETS 05-0300 shall be adhered to (unless specified in this document) for all equipment required to provide the Black Start controller functionality.
5.2.1 Grid Site with a Newly Installed (n+1 dual string) Battery Charger System
At these sites the existing battery charger unit shall be modified to replicate the described operation.
Black Start Controller for Grid and Primary Substation Battery Charger Systems
Document Number: ETS 05-0301
Version: 2.0
Date: 14/12/2017
© UK Power Networks 2017 All rights reserved 8 of 18
5.2.2 Grid or Primary Site with an Installed Dual Separate (LPN Design) Battery Charger
System
At this site one of the complete charging units will be fitted with a Black Start controller between the common bus and battery output. This shall operate as per specification in the event of a supply failure and leave one of the units supplying the standing load with the other unit in reserve. When required, the contactor would be closed via SCADA to restore supplies as per the operation described above.
5.2.3 Grid or Primary Site with a Recently Installed Single String Battery Charger System
For this system a second charging unit will be required and the battery bank will require re-configuration to form two separate strings. The Black Start controller with the described functionality will be added either internal or external to the charger system enclosure. If this is not feasible or financially practical this site’s battery system will be upgraded with a modern system complete with Black Start functionality.
5.2.4 Grid or Primary Site with a Traditional Single String (Plante Cell) Battery Charger
System
This is the more typical legacy battery and charger solution found in the EPN and SPN areas. At this site a dual string of batteries may be required and the existing charger unit will be modified to include the N+1 charging facility and Black Start controller. If this is not feasible or financially practical then this site’s battery system will be upgraded with a modern system complete with Black Start functionality.
5.2.5 Auxiliary Wiring
The need for additional signal wiring between the Trip/Close and SCADA/Telecontrol battery charger system is expected to be identified prior to the commissioning stage. The installer will be required to connect and test these additional signal cores and present the cores in an acceptable manner at the SCADA RTU cabinet.
5.2.6 SCADA Battery Charger Systems
At each instance of a Trip/Close battery system modification the SCADA system will be upgraded as per the requirements, to give greater than 72 hour resilience.
A facility shall also be provided to enable an additional SCADA battery voltage alarm to be flagged both locally and remotely when a voltage threshold is reached. This threshold shall be more sensitive than the traditional volts low alarm if present on the charger system.
5.2.7 Intertripping Battery Charger Systems
Intertripping batteries will require a site by site analysis, depending on function, to decide how the requirements can be met efficiently. It will be decided to upgrade these systems either as the trip/close or SCADA battery charger systems. Alternatively it may be decided that these systems do not require any upgrade/modification.
Black Start Controller for Grid and Primary Substation Battery Charger Systems
Document Number: ETS 05-0301
Version: 2.0
Date: 14/12/2017
© UK Power Networks 2017 All rights reserved 9 of 18
5.3 System Environment
For the purposes of upgrading the existing systems the Black Start controller and required battery upgrades shall be installed within the existing battery charger enclosure, if this is not feasible the controller shall be fabricated to be wall mounted with a minimal horizontal and vertical footprint.
Black Start controller, battery system modification works shall be carried out in a manner so as not to void warranty and/or service agreements associated with the battery charger. Interference of internal hardware, wiring and software of battery systems manufactured by companies other than those carrying out the Black Start upgrades shall be avoided. All interconnection between the Black Start controller and existing battery systems shall be made external to the battery charger, via the distribution panel where possible.
The controller and additional batteries will be incorporated into the charger and battery arrangement of new equipment being installed on the network.
5.4 Environment
The equipment shall be suitable for operation under Ambient Class I conditions to ENA TS 50-18 and 48-5. No special anti-pollution measures are required.
6 Technical Requirements
6.1 System Monitoring
The Black Start Controller will require the following alarms in addition to those specified in ETS 05-0300, the Battery and Charger Specification.
Black Start controller status alarm - This will provide the control engineer with a status of
the Black Start controller, the two Battery String Contactors and the Bypass Contactor.
Voltage analogue - This shall provide an indication to the control engineer of the exact
battery voltage of each string of the 110V installation. Alarms shall have adjustable
threshold limits. The settings and range of the above shall take account of hysteresis,
maximum and minimum conditions. Alarm levels shall be in line with battery and charger
recommendations.
6.2 Connections to Telecontrol
For a connection outline from the Black Start controller to the telecontrol cubicle, please see the following table:
Black Start Controller for Grid and Primary Substation Battery Charger Systems
Document Number: ETS 05-0301
Version: 2.0
Date: 14/12/2017
© UK Power Networks 2017 All rights reserved 10 of 18
CORE
No.
COLOUR FERRULE
No.
FROM
TERM
(PB Unit)
FROM
TERM
(PE Unit)
TO
TERM
1 RED W145A B-7 6/7 1 Battery string 1 contactor trip pos Reserved
2 BLUE W146A B-8 6/8 2 Battery string 1 contactor trip neg Reserved
3 GREEN W147A B-9 6/5 3 Battery string 1 contactor close pos Reserved
4 YELLOW W148A B-10 6/6 4 Battery string 1 contactor close neg Reserved
5 WHITE W145B A-7 6/11 5 Battery string 2 contactor trip pos Sacrificial
6 BLACK W146B A-8 6/12 6 Battery string 2 contactor trip neg Sacrificial
7 BROWN W147B A-9 6/9 7 Battery string 2 contactor close pos Sacrificial
8 VIOLET W148B A-10 6/10 8 Battery string 2 contactor close neg Sacrificial
9 ORANGE X1 A-23 7/1 9 Indication common
10 PINK X137A B-26 7/2 10 Battery string 1 contactor open Reserved
11 TURQ. X139A B-24 7/3 11 Battery string 1 contactor closed Reserved
12 GREY X137B A-26 7/4 12 Battery string 2 contactor open Sacrificial
13 RED/BLU X139B A-24 7/5 13 Battery string 2 contactor closed Sacrificial
14 GRN/RED X601 A-12 8/1 14 Alarm common
15 YEL/RED X689 A-22 8/2 15 Manual Bypass closed (NC)
16 WHI/RED X687A B-17 8/3 16 Battery string 1 controller faulty Reserved
17 RED/BLK X687B A-17 8/4 17 Battery string 2 controller faulty Sacrificial
18 RED/BRN X691 A-11 8/5 18 Battery string 2 disconnect in progress Sacrificial
19 YEL/BLU X693 A-14 8/6 19 Battery string 2 disconnect overridden Sacrificial
20 WHI/BLU --- --- 20 Spare
21 BLU/BLK --- --- 21 Spare
22 ORA/BLU XM11A B-1 6/19 22 Battery string 1 volts 24V SCADA Reserved
23 GRN/BLU XM12A B-2 6/20 23 Battery string 1 volts 0-20mA output Reserved
24 GRY/BLU XM11B A-1 6/21 24 Battery string 2 volts 24V SCADA Sacrificial
25 YEL/GRN XM12B A-2 6/22 25 Battery string 2 volts 0-20mA output Sacrificial
N.B. Some cable suppliers use this alternative colour code
23 YEL/GRN 23
24 WHI/GRN 24
25 ORA/GRN 25
DESCRIPTION
Battery string 1 indicated “Reserved” because at the end of a Black Start event it shall be serviceable. Battery string 2 indicated “Sacrificial” because at the end of a Black Start event it might be dead, if the voltage has dropped beyond serviceable level.
6.3 Controller
The Black Start controller shall be microprocessor based with suitable redundancy and self-monitoring. It shall be re-configurable with regard to function and output signals during its lifetime.
The Battery String 1 Contactor and Battery String 2 Contactor shall be of the bi-stable type, mechanically or magnetically latched and fully rated to make and break the rated DC current of the charger system.
Black Start Controller for Grid and Primary Substation Battery Charger Systems
Document Number: ETS 05-0301
Version: 2.0
Date: 14/12/2017
© UK Power Networks 2017 All rights reserved 11 of 18
6.4 Maintenance
Should the Black Start controller require changing during normal operation it will be possible to carry out this operation while the system is live.
The Black Start controller will have the ability to carry out a self-check operation which will be operated locally (only when the bypass function is activated) and will test the system including the condition of the supply failure low voltage disconnect and SCADA contactors and their operational speeds.
Periodic Maintenance shall be in accordance with ETS 05-0300 and will coincide with maintenance schedule for Grid and Primary Substations. The manual By-pass button on the Controller shall be used in this case to prevent any operation of the device while work is being carried out’.
7 Testing
Testing of the Black Start controller shall be carried out in accordance to ETS 05-0300 and EDS 05-9006.
8 Training
As per ETS 05-0300, Battery and Charger Specification.
9 Installation and Commissioning
Installation and commissioning will be carried out in accordance to UK Power Network’s approved procedures and the Distribution Safety Rules. Contracted personnel shall be approved to work on UK Power Networks operational sites and hold the required accreditations. Consideration at all times must be given to UK Power Networks Outage Planning, Network Control and emergency fault restoration works.
Post installation the equipment details will be recorded in UK Power Networks EDS 12-0202e, Asset Register Amendment Form: Battery / Charger.
10 Drawings and Documentation
As per ETS 05-0300, Battery and Charger Specification.
11 Delivery
As per ETS 05-0300, Battery and Charger Specification.
Black Start Controller for Grid and Primary Substation Battery Charger Systems
Document Number: ETS 05-0301
Version: 2.0
Date: 14/12/2017
© UK Power Networks 2017 All rights reserved 12 of 18
12 References
ETS 05-0300 Equipment Technical Specification, Charger and Battery Specification
EDS 05-9006 Equipment Design Specification, Telecoms Hardware for Operational Sites.
Black Start Recovery –Substation and SCADA Resilience.
Report by the Electricity Task Group (ETG) of the Energy Emergencies Executive Committee (E3C) – July 2010.
Black Start Resilience, Grid and Primary Substations (Regulated) Strategy Paper v4.3
UK Power Networks Internal document.
ENA TS 50-18 Application of Ancillary Electrical Equipment
13 Dependent Documents
The documents below are dependent on the content of this document and may be affected by any changes.
ETS 05-0300 Charger and Battery Specification.
Black Start Controller for Grid and Primary Substation Battery Charger Systems
Document Number: ETS 05-0301
Version: 2.0
Date: 14/12/2017
© UK Power Networks 2017 All rights reserved 13 of 18
Appendix A - Specific Requirements for Black Start Controllers
Simplified Schematic Battery String Disconnection System
Charging Units (N+1) Battery String 1
Load
Distribution Board
BSC1
(SCADA / Test /
LVD)
Battery String 2
Manual
Bypass
BSC2
(AC / SCADA /
Test)
Deterministic Testing
Black Start Controller for Grid and Primary Substation Battery Charger Systems
Document Number: ETS 05-0301
Version: 2.0
Date: 14/12/2017
© UK Power Networks 2017 All rights reserved 14 of 18
Appendix B - Flow Diagram of Black Start Controller Processes
Black Start Controller Process
Charger LV Supply Present
Normal ModeDual String S/S T&CDC
supply to protection and CB.
Disconnect Mode
Control will see alarms and indication
String 1 Battery Voltage >
97.75V (110dc)
Black Start ModeDisconnect Battery
String 1. S/S DC system dead
No
Yes
Delay On Timer
(120 Min)
Bypass ModeOn?
Yes
No
Bypass ModeOn?
Yes
No
Charger LV Supply Present
No
No
Delay On Timer(5 Min)
Yes
No
Yes
String 2 Off ModeBattery String 1
remains connected to the DC load.
Yes
Bypass ModeOn?
Yes
Charger LV Supply Present
Delay On Timer(5 Min)
No
Yes
Delay On Timer
(30min)
No
Yes
Yes
No
No
Yes
Charger LV Supply Present
Delay On Timer(5 Min)
Yes
Yes
No
Bypass ModeOn?
Recovery ModeReconnect
Battery String 2 to reconfigure
S/S
Yes
No
No Delay On Timer(5 Min)
Charger LV Supply Present
Yes
No
No
End of Life ModeBattery String 2 passed
point of recovery. Battery String 1 servicable.
Arrange for generator.
Monitor ModeControl to monitor
Battery Voltages. Both strings must be > 97.75V
String 2 Battery Voltage >
97.75V (110dc)
Yes
Yes
Charger LV Supply Present
No
No
Delay On Timer(5 Min)
Yes
Yes
Close String 1
Contactor
OpenString 1
Contactor
Open Battery String 1
Contactor(BSC1)
Close Battery String 1
Contactor(BSC1)
OpenString 2
Contactor
Close String 2
Contactor
Close Battery String 2
Contactor(BSC2)
Open Battery String 2
Contactor(BSC2)
Automatic Control
SCADA Control
Manual /SCADA Bypass
No
Black Start Controller for Grid and Primary Substation Battery Charger Systems
Document Number: ETS 05-0301
Version: 2.0
Date: 14/12/2017
© UK Power Networks 2017 All rights reserved 15 of 18
Appendix C - Operation in a Black Start or Prolonged Outage Scenario
Throughout this scenario, SCADA control will be available to disconnect each battery string to preserve battery charge or to reconnect each string in the DC power was required.
Normal Condition Prior to Outage
The chargers supply the load and keep the batteries charged up.
Figure C.1 below shows the single line representation of the Black Start controller in
normal mode.
Charging Units (N+1) Battery String 1
Load
Distribution Board
BSC1
(SCADA / Test /
LVD)BSC2
(AC / SCADA /
Test / LVD)Battery String 2
Manual
Bypass
Deterministic Testing
Figure C.1 – Trip/Close Battery Charger System in Normal Operation
Note: The Charger is an N+1 unit and not N+N, meaning that an extra module within the charging unit is needed, not two chargers.
Black Start Controller for Grid and Primary Substation Battery Charger Systems
Document Number: ETS 05-0301
Version: 2.0
Date: 14/12/2017
© UK Power Networks 2017 All rights reserved 16 of 18
After Supply Failure
In the event of a loss of AC power supply to battery charger system, the batteries will
continue to supply the load.
If the loss of AC is sustained, the contactor in series with battery string 2 (BSC2) will be
opened after a configurable time delay (0-120min), string 2 will be isolated from the
standing load.
Battery string 1 remains in service with the current being supplied to the standing load
through the series contact of BSC1 shown in Figure C.2.
When the battery string 1 is drained, the voltage will fall below a configurable
predetermined level. This is the Low Voltage Disconnect (LVD) function and the
contactor (BSC1) will open to prevent irreparable damage to the batteries.
All power to the load will be lost.
Charging Units (N+1)Battery String 1
Load
Distribution Board
BSC2
(AC / SCADA /
Test / LVD)Battery String 2
Manual
Bypass
BSC1
(SCADA / Test /
LVD)
Deterministic Testing
Figure C.2 – Trip/Close Battery Charger System after Mains Supply Failure
Black Start Controller for Grid and Primary Substation Battery Charger Systems
Document Number: ETS 05-0301
Version: 2.0
Date: 14/12/2017
© UK Power Networks 2017 All rights reserved 17 of 18
Restoration of DC Power Prior to Network Supply Restoration
Presuming battery string 1 is drained and is disconnected from the load, the Control
Engineer will issue a command to close battery string 2 contactor (BSC2).
Battery string 2 will supply the load.
After a short time delay the Control Engineer can check the availability of the protection
system and reconfigure the network as necessary.
Providing that the charge on battery string 2 has not been drained, and assuming that
battery string is sized for 6 hours resilience, it should be possible to maintain the load
without the presence of AC supply for approximately 5 hours.
Charging Units (N+1) Battery String 1
Load
Distribution Board
BSC2
(AC / SCADA /
Test / LVD)Battery String 2
Manual
Bypass
BSC1
(SCADA / Test /
LVD)
Deterministic Testing
Figure C.3 – Trip/Close Battery Charger System Prior to AC Supply Restoration
Black Start Controller for Grid and Primary Substation Battery Charger Systems
Document Number: ETS 05-0301
Version: 2.0
Date: 14/12/2017
© UK Power Networks 2017 All rights reserved 18 of 18
After Restoration of AC Supply
When the AC supply is restored the charger will take over supplying the load.
Contactor in series with battery string 1 (BSC1) will close (if it was open) and the
batteries will start recharging.
If the AC supply is maintained for a configurable time (0 - 10min), the string 2 contactor
(BSC2) will close (if it was open) and the batteries will start recharging.
If the AC supply is then lost again within a configurable time (0 - 30min) the string 2
contactor (BSC2) will be reopened immediately.
If the AC supply remains for a time greater than the delay above (0 - 30min) the system
is returned to its normal state.
In the undesired event of a restoration of the AC supply via network reconfiguration with
both battery strings disconnected, the same logic as above will apply. This could
however have disastrous consequence due to the lack of availability of electronic
protection for a short period of time after energisation and therefore must be avoided. In
this situation Control will be aware of the battery status and an appropriate response
shall be initiated.