25
EURO EURO A High Intensity Neutrino Oscillation Facility in Europe Introduction What EUROnu is doing Next step Input to the Strategy Review Future of EUROnu Conclusions On behalf of the EUROnu Consortium

EURO

  • Upload
    toki

  • View
    24

  • Download
    0

Embed Size (px)

DESCRIPTION

EURO . A High Intensity Neutrino Oscillation Facility in Europe. Introduction What EUROnu is doing Next step Input to the Strategy Review Future of EUROnu Conclusions. On behalf of the EUROnu Consortium. EUROnu. FP7 Design Study - PowerPoint PPT Presentation

Citation preview

Page 1: EURO

EUROEUROA High Intensity Neutrino Oscillation Facility in

Europe

• Introduction

• What EUROnu is doing

• Next step

• Input to the Strategy Review

• Future of EUROnu

• Conclusions

On behalf of the EUROnu Consortium

Page 2: EURO

EUROnuEUROnu

• FP7 Design Study

• Due to limited funds: focus on possible “next” generationneutrino oscillation facilities in Europe

• Do:

Conceptual designs of accelerators

Performance of baseline detectors

Physics performance

Approximate costs

• Project started: 1st September 2008

• Duration: 4 years – completion in August 2012

→ → Almost finished & much work doneAlmost finished & much work done→ → Ideal timing for Strategy ReviewIdeal timing for Strategy Review

Page 3: EURO

EUROnu WorkEUROnu Work

• Three facilities

• CERN to Frejus Superbeam:

Based on 4 MW SPL

Targets, horns, integration and target station

Beam preparation for targets

Performance

MEMPHYS detector at Frejus

• Much of the work is generic Marcos Dracos, Marco Zito, et al

Page 4: EURO

Super-BeamSuper-Beam

Page 5: EURO

Super-BeamSuper-Beam

To minimise extrapolation from working facilities:

4 targets and horns

Page 6: EURO

Super-BeamSuper-Beam

Page 7: EURO

Super-BeamSuper-Beam

Page 8: EURO

Neutrino FactoryNeutrino Factory

• Close collaboration with IDS-NF

• EUROnu: target to muon acceleration

• Aim: Reference Design Report

• Detectors: MIND + near detector(s)

• Baseline redefined following θ13: 10 GeV instead of 25 GeV

cheaper

easier to build

Juergen Pozimski, Ken Long, et al

Page 9: EURO

Neutrino FactoryNeutrino Factory

Towards a Low Energy

Neutrino FactoryLENF

Page 10: EURO

Neutrino FactoryNeutrino Factory

Page 11: EURO

Neutrino FactoryNeutrino Factory

Page 12: EURO

Beta-BeamBeta-Beam

• Main issue in EUROnu: maximise ion flux in SR

• Studied:

new ion species

alternative production methods

collective effects

collection

bunching

acceleration

storage

• 2 ion options considered: - 6He & 18Ne → from EURISOL - 8Li & 8B

→ from C. Rubbia et al

Elena Wildner, et al

Page 13: EURO

Beta-BeamBeta-Beam

Decay Ring: B ~ 500 Tm, B = ~7 T, C = ~6900 m, Lss= ~2500 m, = 100, all ionsDecay Ring: B ~ 500 Tm, B = ~7 T, C = ~6900 m, Lss= ~2500 m, = 100, all ions

CERN Specific, Beta Beam favored by 13 results

Page 14: EURO

Beta-BeamBeta-Beam

Collection device tests

INFN, Legnaro

6Li (3He,n) 8B

ECR source tests

Experiment on direct production

of 18Ne at ISOLDE

Page 15: EURO

DetectorsDetectors

• Limited funding: only performance and cost

• Concentrate on baseline detectors

Magnetised Iron Neutrino Detector - NF

Large water cherenkov – SB and BB

Near detectors

• Extrapolations from existing technology, not new

Paul Soler, Anselmo Cervera,

et al

Page 16: EURO

PhysicsPhysics

• Physics performance determination

• Done independently of facilities, as it should be

• As far as possible

everything done in a consistent manner

including systematics

migration matrices

• First comparison from Enrique Fernandez-Martinez & Pilar Coloma

Pilar Hernandez, Andrea Donini, et

al

Page 17: EURO

PhysicsPhysics

LENF: 1.4x1021 decays per year, 100 kt mass MIND at 2000 kmBB100: gamma=100, with 1.3/3.5x1018

decays for Ne/He, 10-2

atmospheric background suppression, 500 kt WC detectorSPL: 4 MW proton driver, 500 kt WC

detectorCN2GS: 0.8 MW, 500 kt WC detector at

GS (730 km)CN2PY: 0.8 MW,100 kt LAr at 2300 km

- 10 years total running- 5%/10% systematics for signal/backgrd- 095.02sin 13

2

Page 18: EURO

PhysicsPhysics

Page 19: EURO

CostingCosting

• Doing the best we can with limited resources

• Using CERN costing tool – developed for CLIC

• Using as much existing knowledge as possible

• Being done in a consistent manner: - Same assumptions - Same costs, where possible

• Using CERN as the location

• Civil engineering is a significant component

• All facilities have been laid out at CERN

Ilias Efthymiopoulos, Elena Wildner, et al

Page 20: EURO

CostingCosting

Super Beam

Page 21: EURO

CostingCosting

Neutrino Factory

Page 22: EURO

Beta Beam

Page 23: EURO

Next StepsNext Steps

• EUROnu finishes in 3.5 months

• FP7 final reports are limited

• Special EUROnu edition of:Physical Review Special Topics: Accelerators & Beams

• Papers:- Introduction- Overview of each facility & detectors -

Special papers on specific work

• Introduction – EUROnu summary for Strategy Review?

• Deadline for Overview papers: 31st July!

Page 24: EURO

Input to Strategy ReviewInput to Strategy Review

• Date of EUROnu annual meeting: 12th-15th June

• Fixed and announced about a year ago

• First and only opportunity for EUROnu to discuss SR

• Fortunately: 6 weeks to submission deadline

• EUROnu future:

Aim: proponents of future facilities working together

Has worked well

Would like to continue

Depends to some extent on new CERN Strategy

Appropriate programme in Horizon 2020 (~FP8)

Page 25: EURO

ConclusionsConclusions

• EUROnu has been running for almost 4 years

• Much detailed work done

• Physics parameters much more reliable and defendable now

• What needs to be done after EUROnu is known

• Work coming to an end

• Main things still to be done:

Complete modifications for large θ13

Complete costing

Write everything up

Decide on future

• It has been a pleasure to coordinate the project!