Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
European Network Code
Implementation Overview
Wednesday 3 May 2017
Background and purpose
More detail on: Connection Codes – Requirements for Generators
Operational Codes
Balancing Codes
Implementation Progress
Get involved/Keep informed
2
EU Code Implementation Overview
European Network Code
Implementation Overview
Rob Wilson
Technical Codes Development Manager
European 3rd package drivers
4
The key players in ENC Development
5
European Network Codes
Development Process
6
What are the codes and what do they do?
7
Markets
Establishes a platform for managing capacity and flow around the
interconnected system to facilitate the setup of a single EU market
Capacity Allocation
& Congestion
Management
(“CACM”)
Forward Capacity
Allocation (“FCA”)
Electricity
Balancing
Guideline
(“EBGL”)
System
Operation
Harmonises the processes Transmission System Operators have to
manage their systems, including system restoration
(Transmission) System
Operation Guideline (“TSOG”)
Emergency & Restoration
(“ER”)
Grid
Connection
Sets consistent technical requirements across EU for new
connections of user equipment (e.g. generation/interconnectors)
Requirements for
Generators (“RfG”)
High Voltage Direct
Current (“HVDC”)
Demand
Connection (Code)
(“DCC”)
More detail on:
EU Connection Codes
9
Overview of the EU Connection codes
Requirements for Generators (RfG)
Entry Into Force: 17th May 2016
Applies to: New generation connections (800 Watts capacity and up) to Distribution and Transmission systems
From: 17th May 2018 onwards
Demand Connection Code (DCC)
Entry Into Force: 7th September 2016
Applies to: New Transmission-connected Demand connections; and new equipment providing Demand Side Response
From: 7th September 2018
High Voltage Direct Current (HVDC)
Entry Into Force: 29th September 2016
Applies to: New Transmission-connected Demand connections,, and new equipment providing Demand Side Response
From: 7th September 2018
More detail on RfG – Generator Banding
Technical requirements in RfG are arranged into x4 Types based
on a user’s connection voltage and MW capacity
Type A - B requirements are close to a product standard
Type C - D requirements need active user management
GB levels will apply consistently across Scotland and England +
Wales. The local TSO (NGET) will make a proposal for the levels -
this is then ratified via industry consultation and regulatory approval
Maximum RfG banding levels permitted for GB:
Type Connection
Voltage Capacity
A < 110kV 800 W – 1 MW
B < 110kV 1 MW – 50 MW
C < 110kV 50 MW – 75 MW
D > 110kV 75 MW +
Current GB Levels:
Generator
Size SHET SPT NGET
Small <10MW <30MW <50MW
Medium 50-100MW
Large >10MW >30MW >100MW
More detail on RfG – Requirements per Type
11
Technical Requirements Type A Type B Type C Type D
Operation across a range of frequencies ● ● ● ●
Limits on active power output over frequency range ● ● ● ●
Rate of change of frequency settings applied (likely to be at least 1Hz/sec) ● ● ● ●
Logic interface (input port) to cease active power output within 5 secs ● ● ● ●
Ability to automatically reduce power on instruction ● ● ●
Control schemes, protection and metering ● ● ●
Fault Ride Through requirements ● ● ●
Ability to reconnect ● ● ●
Reactive capability ● ● ●
Reactive current injection ● ● ●
Active power controllability ● ●
Frequency response ● ●
Monitoring ● ●
Automatic disconnection ● ●
Optional Black start ● ●
Stable operation anywhere in operating range ● ●
Pole slipping protection ● ●
Quick resynchronisation capability ● ●
Instrumentation and monitoring requirements ● ●
Ramp rate limits ● ●
Simulation models ● ●
Wider Voltage ranges / longer minimum operating times ●
Synchronisation on instruction ●
Enhanced Fault Ride through ●
More detail on:
Transmission System
Operation Guideline
Rob Selbie
EU Codes Development Manager
Overview of the EU System Operation codes
13
Emergency & Restoration Code (E&R):
Harmonisation of system defence and restoration procedures during severe events
Transmission System Operation Guideline (TSOG): system security, operational planning and frequency management standards
Operational
Security • Data Exchange
• System States
• System
Management
Operational
Planning • Regional security
coordination
• Outage
coordination
• Adequacy
Load
Frequency
Control &
Reserves • Operational
agreements
• Quality targets
Harmonises the processes TSO have to manage their systems, including
system operation
So am I impacted?
TSOs
More transparency
in system operation
Operational security analysis
Cross-border processes
Generators
New data exchange
requirements
Including for distribution connected
SGUs
Distribution Network
Operators
New data exchange
requirements and outage coordination
responsibilities
Interconnectors
Facilitation of exchange of A/S
Including agreements for
cross-border processes
14
More detail on:
Electricity Balancing
Guideline; TERRE
Overview of the European MARKET codes
16
Early Implementation – Project TERRE
Pan-EU Balancing
Energy Market
• Development of pan-EU platforms
for the exchange of standard
balancing energy products
• 6 year implementation period
• Replacement Reserves (RR)
• Manual Frequency Restoration
Reserves (mFRR)
• Specific products retained
nationally
Harmonisation of Market
Design & Settlement
• Harmonised Gate Closure Time for
standard products
• Harmonisation of ISP at Synchronous
Area level
• Harmonisation of imbalance
arrangements (preference for single
imbalance pricing)
• Harmonisation of reserve procurement
arrangements
Cross Zonal Capacity
Reservation (CZC)
• Opens the possibility for TSOs to
reserve XB capacity for the
exchange of balancing energy
• Co optimisation with market
timeframes
• TSOs to develop detailed
methodologies
Overview of the European Market codes
17
TSOs: Access to a wider pool of flexibility EU Platforms procurement closer to real time
Balancing Service Providers: New standard products; Access to EU market; Level playing field
Balance Responsible Parties: Harmonised imbalance settlement; Imbalance Adjustment; More accurate price signals
Interconnectors: Facilitation of exchange of A/S; More variability
Implementation Progress
ENC implementation approach
(multiple interactions to manage!)
20
1 Grid Code - RfG Banding and Fast Fault Current Injection, RfG and HVDC Fault Ride Through Grid Code National Grid GC0048 May-2017 17/05/2018Consolidated mod - dependencies between banding
and fault ride through parameters
2 Distribution Code - RfG Banding and Fast Fault Current Injection, RfG and HVDC Fault Ride Through Distribution Code ENA TBC 17/05/2018Consolidated mod - dependencies between banding
and fault ride through parameters
3 Grid Code - RfG and HVDC Voltage/Reactive and Frequency Response requirements Grid Code National Grid GC0048 May-2017 17/05/2018
4 Distribution Code - RfG and HVDC Voltage/Reactive and Frequency Response requirements Distribution Code ENA TBC 17/05/2018
5 Grid Code - Compliance and System Management Grid Code National Grid GC0048 Jun-2017 17/05/2018
6 Distribution Code - Compliance and System Management Distribution Code ENA TBC 17/05/2018
7 Grid Code - DCC Technical & Demand Side Response Requirements Grid Code National Grid GC0091 Jun-2017 07/09/2018
8 Distribution Code - DCC Technical & Demand Side Response Requirements Distribution Code ENA TBC Jun-2017 07/08/2018
9 Grid Code – to enable data provision between NGET and other TSOs Grid Code National Grid TBC Apr-2017 Q2 2018 Common Grid Model Project
10 Grid Code – to enable interconnector data provision to NGET after GB gate closure Grid Code National Grid TBC Apr-2017 Q1 2019 (TBC)
11 EB GL - General Compliance (BSC) BSC Elexon TBC Q3 2017 Q3 2018
12 EB GL - General Compliance (Grid Code) Grid Code National Grid TBC Q3 2017 Q3 2018
13 EB GL - General Compliance (Distribution Code) Distribution Code ENA TBC Q3 2017 Q3 2018
14 BSC - Publication of information BSC Elexon TBC Q3 2017 Q4 2018 Project TERRE
15 BSC - Assignment Elexon Tasks BSC Elexon TBC Apr-2017 Q3 2017
16 BSC - Replacement Reserves BSC Elexon P344 Q2 2016 Q4 2018 Project TERRE
17 Grid Code - Replacement Reserves Grid Code National Grid GC0097 Q1 2017 Q4 2018 Project TERRE
18 CUSC - Replacement Reserves CUSC National Grid TBC Q4 2017 Q4 2018 Project TERRE
19 Grid Code - manual Frequency Restoration Reserves Grid Code National Grid TBC Q1 2020 Q3 2021 mFRR Project
20 BSC - manual Frequency Restoration Reserves BSC Elexon TBC Q1 2020 Q3 2021 mFRR Project
21 CUSC - manual Frequency Restoration Reserves CUSC National Grid TBC Q3 2020 Q3 2021 mFRR Project
22 BSC - Imbalance Settlement Harmonisation BSC Elexon TBC Q1 2019 Q3 2020
23 STC - Multi TSO Training Cooperation STC National Grid TBC Q3 2017 Q3 2018
24 SQSS - Determination of Minimum required Inertia SQSS National Grid TBC Q3 2018 Q3 2019
25 Grid Code - TSOG requirements for data exchange Grid Code National Grid TBC Q3 2017 Q3 2018
26 D-Code - TSOG requirements for data exchange Distribution Code ENA TBC Q3 2017 Q3 2018
27 STC - TSOG requirements for data exchange STC National Grid TBC Q3 2017 Q3 2018
28 Grid Code - Regional Outage Coordination and Security Analysis Grid Code National Grid TBC Q1 2018 Q4 2018
29 D-Code - Regional Outage Coordination and Security Analysis Distribution Code ENA TBC Q1 2018 Q4 2018
30 SQSS - Regional Outage Coordination and Security Analysis SQSS National Grid TBC Q1 2018 Q4 2018
31 STC - Regional Outage Coordination and Security Analysis STC National Grid TBC Q1 2018 Q4 2018
32 Grid Code - TSOG requirements in relation to reserve providers and operational agreements Grid Code National Grid TBC Q1 2018 Q4 2018
33 SQSS - TSOG requirements in relation to reserve providers and operational agreements SQSS National Grid TBC Q1 2018 Q4 2018
34 Grid Code - System Defence & Restoration Plans Grid Code National Grid TBC Q3 2017 Q3 2018
35 BSC - Market Suspension BSC National Grid TBC Q3 2017 Q3 2018
36 Grid Code - Market Suspension Grid Code National Grid TBC Q3 2017 Q3 2018
Planned
Date to
Raise at
Code Panel
Op
era
tio
nal
Co
des
TSOG (EIF - 01/07/2017 Expected)
E&R (EIF - Q3 2017 Expected)
Required
Compliance
Date
DependenciesC
on
necti
on
Co
des
Requirements for Generators (EIF - 17/05/2016) & HVDC (EIF - 29/09/2016)
DCC (EIF - 07/09/2016)
Mark
et
Co
des
CACM (EIF - 14/08/2015)
EB GL (EIF - Q3 2017 Expected)
EU
Code
Family
Ref Modification DescriptionWhich GB Code
To be Applied
Code
Administrator
Modification
Reference
Markets & Balancing Development
GB Code Modifications
Where can I
find out more?
For more information/how to get involved
Joint European Stakeholder Group:
A monthly meeting covering all European legislation issues
(supported by BEIS, Ofgem, National Grid amongst others)
Weekly Email Newsletter Update
For more information contact:
Implementation Workgroups (Grid Code):
RfG Implementation Workgroup – GC0048
RfG Frequency Response provisions - GC0087
HVDC Implementation Workgroup - GC0090
DCC Implementation Workgroup - GC0091
TSOG Implementation Workgroup - GC0095
TERRE Implementation Workgroup – GC0097
For more information contact: [email protected]
22
Fact sheets
Fact sheets providing an overview on each EU code are
available on our website: http://www2.nationalgrid.com/UK/Industry-information/Electricity-
codes/European-network-code/Development-process-and-code-
information/
23
Back-up content
Where to find info on SO Ancillary Services
Our Balancing Services web page provides information on
commercial opportunities:
www2.nationalgrid.com/uk/services/balancing-services/
More detail on these services is set out in a range of guides available
at this link:
http://www2.nationalgrid.com/UK/Services/Balancing-
services/Service-Guides/
25
For more information
please contact:
commercial.operation
@nationalgrid.com
Update: Review of transmission charging
In light of significant change in recent years, e.g. decentralisation,
decarbonisation and new technologies; we believe Transmission
charging and commercial arrangements need holistic review
This was supported by feedback from two dedicated charging
seminars held in July (outputs here: Charging Review Website)
Feedback from these seminars has informed the scope and
approach of a review. At TCMF on 08/12/16 we presented further
thoughts on the next steps. These are grouped in three areas…
1. Quick wins – a number of activities are progressing, including
CUSC mods on half hourly charging (CMP266), a policy paper on
storage (early 2017) and improvements to tariff forecasting.
2. Holistic review – we want to work with Ofgem to ensure their
areas of work around embedded generation are comprehensive,
particularly with regards to flexibility.
3. Stakeholder forum – we want to establish a forum to discuss
broader industry reform and develop a route-map for change 26
Other Grid Code mods
GC0096 – Storage is a new workgroup kicking off
in early 2017
In conjunction with the BEIS/Ofgem call for
evidence on Flexibility, it will define (Electricity)
Storage in the Grid Code, and make clear what
technical requirements are required for:
Stand-alone Storage connections, and...
Storage configured with existing generation or
demand units
For more details on how to get involved please
email [email protected] 27
Market Design
Capacity Allocation & Congestion Management
(CACM) Guideline
• Implicit Day Ahead & Intraday cross border trading
• Bidding zone reporting process and subsequent review
Forward Capacity Allocation (FCA) Guideline
• Long term transmission rights;
-Physical Transmission Rights (PTRs) with Use It or
Sell It (UIOSI)
- Financial Transmission Rights (FTR) options
-FTR obligations
• Single Allocation Platform with Harmonised Allocation
Rules
Regional Capacity Calculation
• CACM and FCA both increase regional TSO
coordination with capacity calculation used to determine
interconnector capacities
• Calculation underpinned by a pan- EU Common Grid
Model (CGM)
It establishes a platform for managing capacity & flow around the
interconnected system to facilitate a single EU market
Overview of the European MARKET codes
CACM and FCA have been published and
become law within the UK;
- CACM entry into force 14 Aug 2015
- FCA entry into force 17 Oct 2016CACM
and FCA now requires T
TSOs, NEMOs to draft, consult, and submit
proposals to regulators on detailed design
aspects.
CACM proposals largely complete by end
of 2018, FCA by end of 2019.
Any changes to GB codes to implement
CACM and FCA will be raised and consulted
on through the normal GB code governance
routes
TSO = Transmission System Operator
NEMO= Nominated Electricity Market
Operator
Overview of the European MARKET codes
NG and other TSOs will develop new processes to increase
regional coordination
Trading Interconnector capacity in the forwards markets trading
cross border energy in the day-ahead & intraday timeframes
Generators and demand to provide information on which TSO
decisions are made on a regional basis (see Common Grid Model)
Power exchanges (in their new role as NEMOs) will develop new
processes to deliver a pan-EU marketplace
Interconnector owners (current and future) will operate under new
rules, including new requirements on interconnector firmness
Overview of the European MARKET codes
CGM built
at D-2
CGM built
at D-1
Common Grid Model (CGM)
• A European-wide network model assembled from each TSO’s individual grid model (IGM)
• Realistic and accurate representation of the Transmission & Distribution networks
• One scenario for each market time unit (1 hour)
• Built to a common standard with a harmonised modelling approach
• Used as a key tool for many new coordinated European processes – incl. capacity calculation
Each TSO’s IGM is built
using the latest available
data from market
participants for specific
delivery times
Rolling Daily Process that supports target
model
TSO A
IGM
Overview of the European MARKET codes
TSO B
IGM
TSO C
IGM
Overview of the European MARKET codes
32
Obligations Q2 Q3 Q4
2016
Q1 Q2 Q3 Q4
2017
Q1 Q2 Q3
2018
ENC
deadlines
CGM
Methodology
GLDP
Methodology
Early testing
and parallel
run of CGM
process
NR
A
ap
pro
va
l DA & ID CGM
Requirements
(for CACM)
delivered
Update CGMM
& GLDPM for
FCA (Long-
term
timescales)
FC
A E
IF
TS
OG
EIF
DA & ID data
requirements for
CACM) delivered
Update
CGMM &
GLDPM for
TSOG
CGM process fully
operational
NR
A
ap
pro
va
l TSO develop
IGM
capability
TSOs
publish list
of parties
required to
provide data
Data Provision process
fully operational
CA
CM
EIF
Au
g 2
01
5
So when does it come into effect?
Deadline Proposal Project Key
Overview of the Joint European stakeholder group
33
The Joint European Stakeholder Group is a
GB Stakeholder forum which will
cover the development, Comitology process and implementation of
European Network Codes (ENC), which provides a single group for GB
stakeholder
to engage on all aspects of European Policy
Want to get Involved?
WebEx/teleconference facilities available
Weekly update – sign up on feedback form
Monthly meetings – come along, held at Exelon offices, London
Next meeting: 13th December 2016 – EID discussions.
Come and talk at lunch should you want to know anymore
Barbara Vest
Director of
Generation
(Chair)
Chrissie Brown
NETSO Code
Administration
(Technical Secretary)