evaluación multicriterios de plantas de tratamiento de agua

Embed Size (px)

Citation preview

  • 7/29/2019 evaluacin multicriterios de plantas de tratamiento de agua

    1/13

    Multi-criteria evaluation of wastewater treatment plant

    control strategies under uncertainty

    Xavier Flores-Alsinaa,b, Ignasi Rodrguez-Rodaa,*, Gurkan Sinb, Krist V. Gernaeyb

    aLaboratory of Chemical and Environmental Engineering, University of Girona, Montilivi Campus s/n 17071, Girona, SpainbCenter for BioProcess Engineering, Department of Chemical and Biochemical Engineering, Technical University of Denmark, Building 229,

    DK-2800 Kgs. Lyngby, Denmark

    a r t i c l e i n f o

    Article history:

    Received 24 January 2008

    Received in revised form

    13 May 2008

    Accepted 29 May 2008

    Published online 24 June 2008

    Keywords:

    Wastewater treatment

    Control

    Benchmarking

    Multi-criteria decision analysisUncertainty

    Monte Carlo simulation

    a b s t r a c t

    The evaluation of activated sludge control strategies in wastewater treatment plants

    (WWTP) via mathematical modelling is a complex activity because several objectives; e.g.

    economic, environmental, technical and legal; must be taken into account at the same

    time, i.e. the evaluation of the alternatives is a multi-criteria problem. Activated sludge

    models are not well characterized and some of the parameters can present uncertainty,

    e.g. the influent fractions arriving to the facility and the effect of either temperature or

    toxic compounds on the kinetic parameters, having a strong influence in the model

    predictions used during the evaluation of the alternatives and affecting the resulting rank

    of preferences. Using a simplified version of the IWA Benchmark Simulation Model No. 2 as

    a case study, this article shows the variations in the decision making when the uncertainty

    in activated sludge model (ASM) parameters is either included or not during the evaluation

    of WWTP control strategies. This paper comprises two main sections. Firstly, there is theevaluation of six WWTP control strategies using multi-criteria decision analysis setting the

    ASM parameters at their default value. In the following section, the uncertainty is intro-

    duced, i.e. input uncertainty, which is characterized by probability distribution functions

    based on the available process knowledge. Next, Monte Carlo simulations are run to

    propagate input through the model and affect the different outcomes. Thus (i) the variation

    in the overall degree of satisfaction of the control objectives for the generated WWTP

    control strategies is quantified, (ii) the contributions of environmental, legal, technical and

    economic objectives to the existing variance are identified and finally (iii) the influence of

    the relative importance of the control objectives during the selection of alternatives is

    analyzed. The results show that the control strategies with an external carbon source

    reduce the output uncertainty in the criteria used to quantify the degree of satisfaction of

    environmental, technical and legal objectives, but increasing the economical costs and

    their variability as a trade-off. Also, it is shown how a preliminary selected alternative withcascade ammonium controller becomes less desirable when input uncertainty is included,

    having simpler alternatives more chance of success.

    2008 Elsevier Ltd. All rights reserved.

    * Corresponding author. Tel.: 34 972 418281; fax: 34 972 418150.E-mail addresses: [email protected], (X. Flores-Alsina), [email protected] (I. Rodrguez-Roda), [email protected] (G. Sin),

    [email protected] (K.V. Gernaey).

    A v a i l a b l e a t w w w . s c i e n c e d i r e c t . c o m

    j o u r n a l h o m e p a g e : w w w . e l s e v i e r . c o m / l o c a t e / w a t r e s

    0043-1354/$ see front matter 2008 Elsevier Ltd. All rights reserved.

    doi:10.1016/j.watres.2008.05.029

    w a t e r r e s e a r c h 4 2 ( 2 0 0 8 ) 4 4 8 5 4 4 9 7

    mailto:[email protected]:[email protected]:[email protected]:[email protected]://www.elsevier.com/locate/watreshttp://www.elsevier.com/locate/watresmailto:[email protected]:[email protected]:[email protected]:[email protected]
  • 7/29/2019 evaluacin multicriterios de plantas de tratamiento de agua

    2/13

    1. Introduction

    Nowadays, evaluation of the feasibility of wastewater

    treatment plant (WWTP) design, operation and control

    strategy alternatives is to a large extent based on simulation

    of mechanistic models. Computer codes implementing the

    International Water Association (IWA) activated sludge

    model (ASM) family (Henze et al., 2000) are employed to

    support decision making on implementation of different

    technological alternatives such as: controllers (Stare et al.,

    2007), reactor volume and configuration (Yuan et al., 2000;

    Flores et al., 2005) and recycle streams (Salem et al., 2002).

    The recent developments in the WWTP modelling field for example the release of the Anaerobic Digestion Model No.

    1 (ADM1, Batstone et al., 2002), the development of model

    interfaces coupling the ASM and ADM models (Nopens et al.,

    submitted for publication) have allowed the construction of

    plant-wide WWTP models. The latter models combine sub-

    models for primary (Otterpohl et al., 1994) and secondary

    settlers (Takacs et al., 1991), activated sludge reactors,

    anaerobic digesters, dewatering units, etc., which are linked

    together by a number of recycles and bypasses. Thus, apart

    from studying the performance of individual WWTP unit

    processes it is nowadays also possible to investigate the

    interactions amongst such processes. Some applications of

    this approach can be found already, for example comparingtechnologies to treat rejected water streams (Volcke et al.,

    2006), evaluating the effect of a control strategy on a long-term

    basis (Vrecko et al., 2006; Jeppsson et al., 2007) or analyzing the

    simulation results by multivariable analysis (Flores et al.,

    2007a)

    Uncertainty is a central concept when dealing with biolog-

    ical systems like activated sludge systems, which inherently

    are subjected to large natural variations. However, tradition-

    ally WWTP process simulators assume constant rather than

    variable model parameters, and are thus not capable to take

    into account the inherent randomness. Indeed, the activated

    sludge process cannot be considered as a well characterized

    process and some activated sludge model parameters areuncertain. Examples are the parameters describing the

    influent COD fractionation, or the parameters describing the

    effect of temperature or toxic compounds on the model

    kinetics, which will both have a significant influence on the

    model predictions. Hence, the assessmentand presentation of

    uncertainty is widely recognized as an important part of the

    analysis of complex water systems (Beck, 1987).

    The Monte Carlo simulation technique is a practical way of

    imitating the inherent randomness in biological systems

    using deterministic models. Monte Carlo simulation is based

    on a probabilistic sampling method of input uncertainties

    followed by determination and analysis of the propagation of

    input uncertainty to model outputs (Helton and Davis, 2003).Some authors have used the Monte Carlo simulation tech-

    nique in the water research field, for example addressing the

    design and upgrade of a WWTP under uncertainty balancing

    effluent costs and risk of effluent standards exceedance

    (Benedetti et al., 2006), predicting the disinfection perfor-

    mance of a full scale reactor in drinking water treatment

    (Neumann et al., 2007), generating different wastewater

    influent compositions for posterior process performance

    evaluation (Martin et al., 2007), or also as a pragmatic proce-

    dure to automate the calibration of ASM models ( Sin et al.,

    2008).

    It is important to emphasize that several types of objec-

    tives (economic environmental, legal and technical), must be

    Nomenclature

    AD anaerobic digester

    ADM1 Anaerobic Digestion Model No. 1

    AER aerobic reactor

    Aj alternative to be evaluated

    ANOX anoxic reactor

    ASM activated sludge model

    BOD5 biochemical oxygen demand (g COD m3)

    BSM2 Benchmark Simulation Model No. 2

    C uncertainty class

    COD chemical oxygen demand (g CODm3)

    D probability distribution

    DH dewatering unit

    DO dissolved oxygen

    EQ effluent quality index (kg pollution day1)

    IWA International Water Association

    KLa oxygen transfer coefficient (day1)

    Kp proportional gain (units depend on context)

    np

    number of evaluation criteria applied to

    quantify the degree of satisfaction for OBJknt total number of evaluation criteria

    OBJk control objective

    PI proportional integral

    PRIM primary clarifier

    Qcarb external carbon source (ANOX1) (m3 day1)

    Qintr internal recycle (from AER3 to ANOX1)

    (m3 day1)

    Qr external recycle (from SEC to ANOX1)

    (m3 day1)

    s(Aj) weighted sum for an alternative j

    SNH ammonium concentration (g N m3)

    SNO

    nitrate concentration (g N m3)

    SO dissolved oxygen concentration (g (-COD) m3)

    ST storage tank

    THK sludge thickener

    Ti integral time constant (days)

    TIV time in violation (days)

    TN total nitrogen (g N m3)

    TSS total suspended solids (gTSSm3)

    Tt anti-windup constant (days)

    U uncertainty factor

    v(Xj) value function for a criterion j

    v(xj,i) normalized value i for a given alternative j

    wk weights applied to control objectives

    wi weights applied to criteriaWWTP Wastewater Treatment Plant

    Xi evaluation criteria

    xi* best situation for a criterion i

    xi* worst situation for a criterion i

    xj,i quantified criterion i for a given alternative j

    w a t e r r e s e a r c h 4 2 ( 2 0 0 8 ) 4 4 8 5 4 4 9 74486

  • 7/29/2019 evaluacin multicriterios de plantas de tratamiento de agua

    3/13

    taken into account simultaneously during the evaluation of

    design/control alternatives, i.e. the evaluation of the

    competing alternatives is a multi-criteria problem (Vincke,

    1992; Belton and Stewart, 2002). The main limitation of

    previously published works is the lack of systematic

    approaches to support decision making when such multi-

    criteria problems arise. Moreover, despite the importance of

    considering uncertainty during simulation-based WWTPperformance evaluation, multi-criteria evaluation under

    uncertainty has only been treated sparsely in the wastewater

    engineering field. Clearly, there is a need to fill this gap by

    providing technologies to support the decision makers that

    have to deal with this type of multi-criteria problems in the

    wastewater treatment field.

    The objective of this paper is therefore to demonstrate the

    influence of considering uncertainty in activated sludge

    model parameters on the decision making process during the

    multi-criteria evaluation of WWTP control strategies. A plant-

    wide WWTP model is used as a case study. First a reference

    case will be presented, by evaluating and comparing several

    WWTP control strategies based on the traditional way, i.e. byusing the default (deterministic) values of model parameters.

    Secondly, the WWTP control strategies are compared while

    considering uncertainty in the ASM parameters. Hence input

    uncertainties are propagated to the set of applied plant

    performance evaluation criteria, and as a consequence the

    influence of input uncertainty during multi-criteria decision

    making can be investigated. To this purpose, input uncer-

    tainty is quantified by assuming probability distributions for

    each parameter based on the available process knowledge.

    The WWTP model is then coupled to a Monte Carlo engine

    that randomly samples parameters from the previously

    defined probability distributions, thus solving the model and

    quantifying the evaluation criteria foreach parameter sample.

    2. Methods

    2.1. Wastewater treatment plant (WWTP) under study

    The WWTP under study has the same layout as the IWA

    Benchmark Simulation Model No. 2 (BSM2) proposed by

    Jeppsson et al. (2007). The activated sludge unit is a modified

    LudzackEttinger configuration consisting of 5 tanks in series.

    Tanks 1 (ANOX1) and 2 (ANOX2) are anoxic with a total volume

    of 2000 m3, while tanks 3 (AER1), 4 (AER2) and 5 (AER3) are

    aerobic with a total volume of 3999 m3. The circular secondarysettler (SEC) has a surface area of 1500 m2 with a total volume

    of 6000 m3. The BSM2 plant furthercontains a primary clarifier

    (PRIM), a sludge thickener (THK), an anaerobic digester (AD),

    a storage tank (ST) and a dewatering unit (DH). Further

    information about the BSM2 layout and the description of the

    process models can be found in Jeppsson et al. (2007).

    Plant performance evaluation has been reduced from 1-

    year simulation to 1 week in order to reduce the computa-

    tional burden of the whole study. The default wastewater to

    be treated has a dry weather flow rate of 18446 m3 day1 with

    a carbon and nitrogen load of 12228 kgCODday1 and

    1025 kgN day1, respectively. The wastewater influent is the

    same as for the Benchmark Simulation Model No. 1 (Copp,

    2002), but increasing the concentrations of particulate carbon

    and nitrogen in order to take into account the effect of the

    primary clarifier.

    2.2. Implemented control strategies

    Five control strategies were implemented to a default open

    loop case (A1). The operational settings of the open loop basecase considered in this case study were slightly modified

    compared to the BSM1 (Copp, 2002). The constant waste

    sludge flow rate was reduced from 385 m3 day1 to

    300 m3 day1 and the constant oxygen transfer coefficient

    (KLa) for the third aerobic reactor (AER3) was increased from

    84 day1 to 240 day1. The values for other manipulated vari-

    ables (Qintr 55,338 m3 day1, Qr 18,446 m

    3 day1 and

    Qcarb 0 m3 day1) remained at the default BSM1 values. The

    control strategies A {A2,.,Aj,.,A6}, summarized in Table 1,

    were applied to the activated sludge reactor section. The

    simulation results (open loop 5 control strategies) are the

    starting point for the work presented in this paper.

    The dissolved oxygen (DO) sensor was assumed to be idealwithout noise or delay. The nitrate (SNO) and ammonium (SNH)

    sensors had a time delay of 10 min, with zero mean white

    noise (standard deviation of 0.1 g N m3). All the dynamic

    simulations were preceded by a steady state simulation to

    ensure an appropriate starting point for the dynamic simu-

    lations and to eliminate bias due to the selection of the initial

    conditions on the dynamic modelling results (Copp, 2002).

    Even though the length of the dynamic influent file used to

    carry out the simulations was 28 days, only the data generated

    during the last 7 days were used to evaluate the plant

    performance.

    The control strategies presented in this study assume

    constant rather than variable set points.Previous studies havedemonstrated that different set points might lead to different

    conclusions (see, e.g. Flores et al., 2007b). However, the

    selected operational settings of the controllers (set points, Kp,

    Tt) are reasonable values that will lead to an acceptable plant

    performance, since the operational settings have been

    extracted from the literature and were for a large part defined

    by the IWA Task Group on Benchmarking of Control Strategies

    for WWTPs (www.benchmarkwwtp.org). The literature refer-

    ences mentioned in Table 1 can be consulted for further

    details about the controllers.

    2.3. Objectives, criteria and evaluation procedure

    Environmental, economical, technical and legal objectives

    were taken into account [OBJ OBJ1,.,OBJk,.,OBJp] during

    the evaluation procedure (hence p 4). The degree of satis-

    faction of the defined control objectives OBJ1, OBJ2, OBJ3 and

    OBJ4 was quantified by a set [n n1,.,nk,.,np] of 1, 1, 1 and 4

    criteria, respectively Pp

    k1 nk nt 7. Weight factors

    [w w1,.,wk,.,wp] are then assigned to each objective (k).

    The relative importanceof the objectives is normalized to sum

    1, orPp

    k1 wk 1. For each control objective, the criteria used

    to evaluate the degree of satisfaction of that objective are

    weighted equally. Thus, the weight factor applied to each

    evaluation criterion (wi, i 1,2,.,nt) is obtained by dividingwk

    by the number of evaluation criteria nk belonging to a specific

    w a t e r r e s e a r c h 4 2 ( 2 0 0 8 ) 4 4 8 5 4 4 9 7 4487

    http://www.benchmarkwwtp.org/http://www.benchmarkwwtp.org/
  • 7/29/2019 evaluacin multicriterios de plantas de tratamiento de agua

    4/13

    control objective. The effluent quality index (EQ, Copp, 2002)

    was the single criterion (X1) used to evaluate the accom-

    plishment of OBJ1 (minimize the environmental impact). The

    operational cost index (X2) proposed by Vrecko et al. (2006)was applied for evaluating the accomplishment of objective

    OBJ2 (minimize economic cost). The risk for occurrence of

    microbiology-related solids separation problems (X3) was

    used to evaluate the technical reliability of the controllers

    (OBJ3). The risk for occurrence of separation problems (Comas

    et al., 2006) was assessed by punishing control strategies that

    create operation conditions that potentially can drive the

    plant to bulking (X31), foaming (X32) and rising sludge (X33).

    Finally the percentage of time that the plant violates the legal

    effluent limits (OBJ4) was quantified using the time plant in

    violation index (Copp, 2002) for the different pollutants, i.e.

    total suspended solids (X4, TSS), chemical oxygen demand (X5,

    COD), biochemical oxygen demand (X6, BOD5) and total

    nitrogen (X7, TN). Compared to OBJ4, OBJ1 provides additional

    information about the impact on water by the treated effluent,

    since the contribution of each pollutant is weighted differ-

    ently to calculate the value of OBJ1 (Copp, 2002). It couldindeed happen that scenarios providing the same degree of

    satisfaction of the legal requirements (OBJ4) will have different

    potential impacts on the receiving water (OBJ1).

    All criteria [X] were quantified based on dynamic simula-

    tions. The quantification of an option Aj with respect to crite-

    rion Xi is indicated as xj,i. Thus, each option under evaluation

    can be formulated as a vector of scores and represented as a n-

    dimensional performance score profile Aj xj;i;.; xj;nt .

    Value functions [v(Xi)] map the score profiles of all options into

    a value v(xj,i) normalized from 0 to 1. The 0 and 1 values were

    associated with the worst (xi*) and the best (xi*) situation,

    respectively, whilst a mathematical function was used to

    evaluate the intermediate effects. The collection of the best

    Table 1 Main features of the control strategies evaluated in this case study

    Oxygen controller in the aerated section (AER1, 2 and 3) ( Vanrolleghem and Gillot, 2002)

    Controller type PI with anti-windup Units

    Proportional gain (Kp) 100 m3 (g (-COD))1 days1

    Integral time constant (Ti) 0.01 days

    Anti-windup constant (Tt) 0.01 days

    Controlled variable SO in AER1, 2 and 3Set point 2 g (-COD) m3

    Manipulated variable (MV) KLa days1

    Maximum value of MV 360 days1

    Implemented in alternatives A2, A3, A4, A5 and A6

    Nitrate controller in the anoxic section (ANOX2) (Copp, 2002)

    Controller type PI with anti-windup Units

    Proportional gain (Kp) 10,000 m3(gN)1 days1

    Integral time constant (Ti) 0.04 days

    Anti-windup constant (Tt) 0.04 days

    Controlled variable SNO in ANOX2

    Set point 1 g N m-3

    Manipulated variable (MV) Qintr m3 days1

    Maximum value of MV 92,336 m3 days1

    Implemented in alternatives A3 and A5

    Nitrate controller in the anoxic section (ANOX2) (Gernaey et al., 2007)

    Controller type PI with anti-windup Units

    Proportional gain (Kp) 1 m3(gN)1 days1

    Integral time constant (Ti) 0.1 days

    Anti-windup constant (Tt) 0.1 days

    Controlled variable SNO in ANOX2

    Set point 1 g N m3

    Manipulated variable (MV) Qcarb m3 days1

    Maximum value of MV 5 m3 days1

    Implemented in alternatives A4 and A6

    Ammonium controller in the aerated section (AER3) (Gernaey et al., 2007)

    Controller type Cascaded PI Units

    Proportional gain (Kp) 1 m3(gN)1 days1

    Integral time constant (Ti) 0.2 days

    Anti-windup constant (Tt) 0.2 days

    Controlled variable SNH in AER3

    Set point 1 g N m3

    Manipulated variable (MV) SO set point in AER3, 4 and 5 g (-COD) m3

    Maximum value of MV 4 g (-COD) m3

    Implemented in alternatives A5 and A6

    w a t e r r e s e a r c h 4 2 ( 2 0 0 8 ) 4 4 8 5 4 4 9 74488

  • 7/29/2019 evaluacin multicriterios de plantas de tratamiento de agua

    5/13

    x x1;.; xnt

    and the worst x x1;.; xnt scores for all

    criteria determined the best vx vx1;.; vxnt

    1 and

    the worst profiles vx vx1;.; vxnt 0. Finally,

    a multi-objective function was calculated to obtain a unique

    value for each alternative (Eq. (1)). The multi-objective function

    is presented as a weighted sum and calculated by summing up

    the product of each normalized criterion v(xj,i) with its corre-

    sponding weight (wi). Theoptions were rankedaccording to theobtained scores. The alternativewith the highest score was the

    one that was considered to give the higher degree of satisfac-

    tion of the considered objectives, and thus corresponds to the

    recommended alternative for implementation (Flores et al.,

    2007b).

    s

    Aj

    v

    xj;1$w1 . v

    xj;i

    wi . v

    xj;nt

    wnt Xn

    i1

    v

    xj;i

    wi

    (1)

    3. Multi-criteria evaluation of WWTP controlstrategies without uncertainty

    In this section the deterministic multi-criteria evaluation of

    WWTP control strategies is presented. WWTP control strate-

    gies defined in Table 1 were tested and evaluated using multi-

    criteria decision analysis for default values of the activated

    sludge model parameters. Table 2 summarizes the score

    profile for each evaluated alternative. Note that the criteria X4,

    X5 and X6 had identical values for each tested control strategy

    in this case study, and thus these criteria were not useful to

    discriminate the competing alternatives.

    It should be emphasized that results of this base case

    analysis depend strongly on the model selection prior toperforming the simulations. When modelling activated sludge

    plants, there is often disagreement on the best model to apply

    for a given case. The representation of biomass decay (Siegrist

    et al., 1999), the modelling of nitrogen removal (Gujer et al.,

    1999) and the oversimplification of the settling models (i.e.

    non-reactive in most cases, despite the fact that a significant

    amount of biomass is often stored at the bottom of the

    secondary clarifier, e.g. Gernaey et al., 2006) are key issues that

    are still under discussion.

    To compare the effects of the different criteria during the

    evaluation procedure, it is necessary to map these score

    profiles into normalized values because all those criteria are

    measured in different units. Value functions award values

    from 0 to 1 to the worst and the best situation considered,

    respectively, whilst a mathematical function is proposed to

    evaluate the intermediate effects. The extreme profiles (based

    on expert judgment) are summarized in the following lines.

    [(xi*) (x1* 60935 kg pollution day1, x2* 15,000, x31*

    100%, x32* 100%, x33* 100%, x4* 100%, x5* 100%, x6*

    100%, x7* 100%)] and[(xi*) (x1* 0 kg pollutionday

    1, x2* 7500, x31* 0%, x32*

    0%, x33* 0%, x4* 0%, x5* 0%, x6* 0%, x7* 0%)].

    A linear model was applied between these extreme values

    to calculate the intermediate effects (e.g. for criterion X2 the

    value function is v(X2) 0.000113X2 2). Finally, a multi-

    objective function calculated as a weighted sum (Eq. (1)) was

    applied in order to obtain a single value for all the alternatives

    which were then ranked according to the scores obtained,

    with the final decision as to which alternative is best in ful-

    filling the evaluation criteria resting on the decision maker. As

    weight assessment is not a central topic in this paper, equal

    importance for all the objectives is assumed wp 0.25. The

    results of the weighted sum lead us to the following conclu-sion: in accordance with the control objectives, alternative A5with a scores (A5) of 0.75 is the selected, while A1, A2, A3, A4and A6 with a score in theweighted sum of 0.68,0.72, 0.72,0.63

    and 0.66, respectively, are rejected.

    Despite the fact that this control strategy shows a higher

    risk of favouring formation of rising sludge, alternative A5 is

    the most favourable mainly because this alternative showed

    the lowest scores in OBJ2 (minimize economic costs). The

    latter result is basically attributed to an efficient use of

    the aeration energy in this control strategy, providing just the

    sufficient quantity of oxygen to maintain a reasonable effluent

    ammonium concentration. Also, it is important to mention

    that alternative A5 performed well in both environmental(OBJ1) and legal (OBJ4) objectives, because this control strategy

    improves the overall nitrification efficiency.

    4. Multi-criteria evaluation of controlstrategies under uncertainty

    This section of the manuscript provides details of the proce-

    dure followed to evaluate the WWTP control strategies under

    uncertainty: first, the quantification of the input uncertainty

    of the ASM model parameters is presented; then the set-up of

    Table 2 Score profiles for the six evaluated control strategies without uncertainty

    A1 A2 A3 A4 A5 A6 Units

    X1 8114.10 7770.90 7784.70 5879.90 7108.70 5824.90 g pollution m3

    X2 10682 9853 9787 13551 9187 12746

    X31 78.89 78.00 78.08 80.79 77.93 80.33 %

    X32 77.94 77.94 77.75 81.94 77.73 81.05 %

    X33 86.32 94.37 91.01 91.25 97.67 85.05 %

    X4 0.00 0.00 0.00 0.00 0.00 0.00 %

    X5 0.00 0.00 0.00 0.00 0.00 0.00 %

    X6 0.00 0.00 0.00 0.00 0.00 0.00 %

    X7

    44.79 15.18 18.01 0.00 6.85 0.00 %

    w a t e r r e s e a r c h 4 2 ( 2 0 0 8 ) 4 4 8 5 4 4 9 7 4489

  • 7/29/2019 evaluacin multicriterios de plantas de tratamiento de agua

    6/13

    the Monte Carlo simulations is explained, and finally multi-

    criteria evaluation of the simulation results is presented and

    discussed in detail.

    4.1. Identification and quantification of the input

    uncertainty of the ASM model

    The BSM2 is an integrated model that contains several sub-models, i.e. influent, model interfaces, settling tanks, aeration

    tanks, digesters, controllers, etc. For the scope of this study, it

    was decided to frame the uncertainty analysis to consider

    only the uncertainty in the biokinetic parameters and the

    influent fractions of the ASM1 model. All other potential

    sources of uncertainty, e.g. model structure (settlers,

    hydraulics, controllers, etc.) are fixed and assumed known as

    defined by BSM2. This framing of uncertainty is simple.

    However, it was felt necessary (if not essential) to avoid

    getting involved into discussing solely the uncertainty of the

    BSM2 model which is not the prime purpose of this study.

    To carry out this analysis, the uncertainty associated to the

    ASM parameters [U U1,.

    ,Uy,.

    U32] wascharacterized by a setof probability distributions [D D1,.,Dy,.D32]. These distri-

    butions were assumed to characterize a degree of belief with

    respectto where theappropriate values for theelements of [U]

    are located for usein thesimulation ofthe BSM2. Whenusedin

    this manner, these distributions are providing a quantitative

    representation of what is referred as subjective or epistemic

    uncertainty (Helton and Davis, 2003). In this case study those

    distributions were developed through interpretation of avail-

    able process knowledge. Three uncertainty classes were

    distinguished [C C1, C2, C3] to allow presentation of the

    parameteruncertaintyin a structuredway,and each uncertain

    parameter Uy included in theanalysiswas assigned to a certain

    class Cc depending on the extent of knowledge available in the

    literature about this specific parameter value. The first class

    was assigned to low uncertainty and included mostly stoi-

    chiometric parameters. In this class (C1), the parameters were

    assumed to have a 5% upper and lower bounds around their

    default values [U1,.

    ,U10]. The second class (C2), correspondedto medium uncertainty and involved kinetic parameters such

    asthe maximum specificgrowth rate andthe affinity constants

    [U11,.,U24]. In this class, 25% upper and lower bounds around

    the default values were assumed. For simplification, all the

    kinetic and stoichiometric parameters were supposed to be

    independent although the authors are aware of possible

    correlations amongst several parameters, e.g. the maximum

    specific growth rate and the half saturation constants. Table 3

    summarizes these parameters, the classes to which they

    belong and the range of evaluated parameters.

    Finally, the third class of uncertainty (C3) corresponded to

    high uncertainty and included the influent fraction related

    parameters, assuming upper and lower bounds equal to 50%of the default parameter values. Several class 3 uncertainty

    factors were applied to the default stoichiometric coefficients

    used to calculate the different ASM1 influent organic carbon

    related state variables [U25,.,U28] such as the soluble

    biodegradable substrate (SS) or the particulate biodegradable

    substrate (XS) concentration from the influent COD load,

    resulting in a range of treatment plant influents to be applied

    in the simulations. A similar method was applied to influent

    nitrogen [U29,.,U32], where the fraction coming from partic-

    ulate products and biomass was removed first, to finally

    Table 3 Parameter distributions used for the Monte Carlo simulation including default parameter values, assignedparameter class and variation range for class 1 and 2 parameters

    Uncertainty parameter (Up, K&S) Symbol Default value Class Range Units

    Autotrophic yield YA 0.67 1 0.067 g COD g N1

    Heterotrophic yield YH 0.24 1 0.024 g COD g COD1

    Fraction of biomass to particulate products fP 0.08 1 0.008 Dimensionless

    Fraction of nitrogen in biomass iXB 0.08 1 0.008 g N(g COD) in biomass

    Fraction of nitrogen in particulate products iXP 0.06 1 0.006 g N(g COD) in XpConversion from COD to inert particulates XI2TSS 0.75 1 0.075 g TSS g COD

    1

    Conversion from COD to inert particulates XS2TSS 0.75 1 0.075 g TSS g COD1

    Conversion from COD to inert particulates XBH2TSS 0.75 1 0.075 g TSS g COD1

    Conversion from COD to inert particulates XBA2TSS 0.75 1 0.075 g TSS g COD1

    Conversion from COD to inert particulates XU2TSS 0.75 1 0.075 g TSS g COD1

    Maximum specific heterotrophic growth rate mH 4.00 2 2.00 day1

    Half saturation (heterotrophic growth) KS 10.00 2 5.00 g COD m3

    Half saturation (heterotrophic oxygen) KOH 0.20 2 0.10 g COD m3

    Half saturation (nitrate) KNO 0.50 2 0.25 g N m3

    Heterotrophic specific decay rate bH 0.30 2 0.15 day1

    Maximum specific autotrophic growth rate mA 0.50 2 0.25 day1

    Half saturation (autotrophic growth) KNH 1.00 2 0.50 g N m3

    Half saturation (auto. oxygen) KOA 0.40 2 0.20 g COD m3

    Autotrophic specific decay rate bA 0.05 2 0.025 day1

    Anoxic growth rate correction factor hg 0.80 2 0.40 Dimensionless

    Amonification rate ka 0.05 2 0.025 m3(gCODday)1

    Maximum specific hydrolysis rate kh 3.00 2 1.50 g Xs(g Xbh CODday)1

    Half saturation (hydrolysis) KX 0.10 2 0.05 g Xs(g Xbh COD)1

    Anoxic hydrolysis rate correction factor nyh 0.80 2 0.40 Dimensionless

    w a t e r r e s e a r c h 4 2 ( 2 0 0 8 ) 4 4 8 5 4 4 9 74490

  • 7/29/2019 evaluacin multicriterios de plantas de tratamiento de agua

    7/13

    obtain the inorganic (ammonium, SNH) and organic influent

    nitrogen compound concentrations (either soluble or partic-

    ulate, SND and XND).

    It is important to point out that despite of the apparent

    advantages of a formal assessment of uncertainty, one should

    be aware that the conclusions arising from this case study

    considering uncertainty can always only be as good as the

    underlying assumptions. Thus, the results of the uncertaintyanalysis will to a large extent depend on the characteristics of

    the defined distributions, similar to the base case perfor-

    mance where the obtained results will depend on the model

    selection, as indicated earlier.

    4.2. Monte Carlo simulations

    The input uncertainty space is sampled using the Latin

    hypercube method (McKay et al., 1979; Iman et al., 1981). In

    this study, 1000 samples [Uy Uy,1,.,Uy,f,.,Uy,1000] are gener-

    ated to make sure that the input uncertainty space is covered

    uniformly. Each Latin hypercube sample contains onerandomly selected value Uy,f from each of the previously

    defined probability distributions Dy. The Monte Carlo simula-

    tions are performed by evaluating the BSM model for each one

    of the generated Latin hypercube samples, solving the entire

    model and quantifying the defined criteria [X] for each tested

    alternative [A]. The solution of the model for each parameter

    combination results in a distribution of possible values for the

    desired performance criteria, whose distributions reflect the

    possible variation of the performance criteria taking into

    account the input uncertainty. Both interpretation and

    representation of the results of the Monte Carlo simulations is

    subsequently carried out using descriptive statistical tech-

    niques such as multiple box plots, error bar charts, threedimensional representations of the inter-quartile range, etc.

    4.2.1. Environmental objectives (OBJ1)

    According to the previous section, a single criterion (X1) is

    used to quantify the degree of satisfaction of objective OBJ1(minimize environmental impact). Fig. 1 shows the results of

    the Monte Carlo simulations in a box plot fashion (Hair et al.,

    1998). The different box plots illustrate that there is a clear

    pattern: all the control strategies including an external carbon

    source addition (A4 and A6) result in lower values in both

    average effluent quality index terms and in effluent quality

    index variability, i.e. the range between the first and the third

    quartile is smaller compared to the other control strategies.

    This differentiation between the control strategies can be

    explained by the lack of soluble biodegradable carbon in theinfluent and the low hydraulic retention time in the biological

    reactor, resulting in poor denitrification rates as long as no

    external carbon source is dosed. The external carbon source

    addition acts as an extra electron donor enhancing the total

    nitrogen removal by improving the reduction of the produced

    nitrate to nitrogen gas and decreasing the impact of the

    nitrate term in the effluent quality index. Also, this input

    increases the robustness of the denitrification because this

    process now no longer depends on the organic substrate

    contents in the influent. Instead, the controller is now

    supplying the necessary biodegradable carbon to maintain the

    nitrate concentration in the second anoxic reactor (ANOX2) at

    the desired set point.It is also important to point out the effect of the SNH

    cascade controller (A5, A6) in the propagation of the uncer-

    tainty when it is compared to other control strategies, e.g.

    the open loop controller (A1) and the DO controller (A2, A3and A4). The SNH controller with its DO set point that varies

    as a function of the ammonium concentration in the last

    aerated tank improves the nitrification efficiency of the

    whole plant and reduces its variability. A constant aeration

    flow rate or dissolved oxygen set point results in situations

    where there is either lack or excess of dissolved oxygen to

    nitrify all the ammonium entering the plant. The improve-

    ment of the aeration system obtained by introducing the

    cascade controller reduces the percentage of time whenthe aeration flow is not adequate, e.g. due to differences of

    the influent load during daytime and night, thus reducing

    the overall variability of effluent total Kjeldahl nitrogen

    (TKN) as shown in the frequency histograms of Fig. 2.

    Nevertheless, Fig. 1 reveals that alternative A5 is the alter-

    native with a larger variation in terms of effluent quality

    index mainly due to an increase of the uncertainty in the

    denitrification efficiency. This plot elucidates the trade-off

    that has to be made between improvements of nitrification

    efficiency on the one hand and the overall effluent quality

    index variation on the other hand. Regarding the other

    scenarios (A1, A2 and A3), it is just worth mentioning that

    there the controllers do not have a clear effect in botheffluent quality and variability reduction.

    4.2.2. Economic objectives (OBJ2)

    The plant operational costs (X2) are used to evaluate the

    degree of satisfaction of OBJ2 (minimize economic costs). In

    Table 4 the mean and the standard deviation of the break-

    down of the operational costs used to evaluate the economic

    feasibility of the controllers can be found.

    The values in Table 4 again demonstrate a clear differ-

    ence between the control strategies with and without

    external carbon source addition. The periodic purchase of an

    external carbon source (X24) implies a subsequent increase

    of both quantity and variability of the sludge production

    Alternative

    X1(kgPollution.day

    -1)

    2000

    4000

    6000

    8000

    10000

    12000

    14000

    A1 A2 A3 A4 A5 A6

    Fig. 1 Effluent quality index (X1) variation using a multiple

    box plot representation.

    w a t e r r e s e a r c h 4 2 ( 2 0 0 8 ) 4 4 8 5 4 4 9 7 4491

  • 7/29/2019 evaluacin multicriterios de plantas de tratamiento de agua

    8/13

    (X21), aeration energy (X22), heating energy (X26) and the

    overall operating cost index (X2), although it should be

    mentioned that there also is an increase in the methane

    production (X27). The inclusion of carbon source dosage in

    the control strategy does not have any effect on mixing

    energy (X25) and pumping energy (X23). Hence, it can be

    concluded that the addition of external carbon source

    reduces the impact on water (X1) and its variability as

    a trade-off to an increase of the operating costs (X2) and their

    variability.

    gN.m-3

    gNm-3

    1 2 3 4 5 6 7 8

    gN.m-3

    1 2 3 4 5 6 7 8

    Count

    0

    20

    40

    60

    80

    100

    120

    140

    160

    180

    Co

    unt

    0

    20

    40

    60

    80

    100

    120

    140

    160

    180

    Co

    unt

    0

    20

    40

    60

    80

    100

    120

    140

    160

    180

    Alternative A1 Alternative A2

    Alternative A5 Alternative A6

    a

    Count

    0

    20

    40

    60

    80

    100

    120

    140

    160

    b

    0 2 4 6 8

    gNm-3

    0 2 4 6 8

    c d

    Fig. 2 Histograms of the effluent TKN variation when alternative (a) A1, (b) A2, (c) A5 and (d) A6 are evaluated under ASM

    parameters uncertainty.

    Table 4 Mean and standard deviation of the operational cost breakdown for the different generated alternatives underuncertainty

    A1 A2 A3 A4 A5 A6 Units

    xj,21 Mean 2652.56 2654.65 2653.00 2825.55 2653.88 2816.98 kg TSS day1

    Standard deviation 336.15 336.36 336.12 371.70 336.11 383.29 kg TSS day1

    xj,22 Mean 8548.40 7685.97 7751.88 8164.18 7699.25 8547.70 kwh day1

    Standard deviation 0.00 622.03 638.14 670.05 1710.82 2138.73 kwh day1

    xj,23 Mean 396.47 396.47 250.24 396.71 282.03 396.64 kwh day1

    Standard deviation 0.11 0.11 42.25 0.13 68.33 0.15 kwh day1

    xj,24 Mean 0.00 0.00 0.00 997.43 0.00 827.00 kg COD day1

    Standard deviation 0.00 0.00 0.00 345.35 0.00 478.75 kg COD day1

    xj,25 Mean 648.00 648.00 648.00 648.00 648.00 648.00 kwh day1

    Standard deviation 0.00 0.00 0.00 0.00 0.00 0.00 kwh day1

    "xj,26 Mean 3854.48 3854.72 3854.27 3940.95 3854.49 3916.35 kwh day1

    Standard deviation 41.79 41.79 41.70 48.59 41.65 55.11 kwh day1

    xj,27 Mean 1659.76 1659.55 1659.39 1715.41 1659.66 1702.79 m3 CH4 day

    1

    Standard deviation 140.84 140.77 140.75 144.89 140.79 144.54 m3 CH4 day1

    xj,2 Mean 10682.08 9824.52 9740.82 13563.42 9721.67 13468.58

    Standard deviation 1490.13 1087.08 1083.81 1724.57 1999.21 3801.00

    w a t e r r e s e a r c h 4 2 ( 2 0 0 8 ) 4 4 8 5 4 4 9 74492

  • 7/29/2019 evaluacin multicriterios de plantas de tratamiento de agua

    9/13

    Alternatives with a DO controller (A2, A3, A4, A5 and A6) are

    characterized by having a larger variation in the aeration costs

    (see values of Xj,22) when they are compared to the plant

    running in open loop regime (A1). The effect of the cascade

    ammonium controller can be noticed clearly from the results

    ofTable 4 in both alternatives A5 and A6: a large variation in

    operational costs can be observed mainly due to variation in

    the aeration energy cost (see values of X5,22 and X6,22). Thisfact is attributable to the dynamics of the cascade controller

    which introduces a variable DO set point instead of the

    permanent DO set point (2 g (-COD) m3) that is applied for the

    alternatives A2, A3 and A4.

    Control strategies A3 and A5 have lower average values and

    higher variability in pumping energy (X23) because the

    controller manipulates the internal recycle in order to main-

    tain the nitrate concentration in ANOX2 to the desired set

    point of 1 g N m3.

    4.2.3. Technical objectives (OBJ3)

    The risk of occurrence of separation problems (X3) is used to

    evaluate the technical reliability (OBJ3) of the proposed controlstrategies. As mentioned earlier the risk of microbiology-

    related solids separation problems is evaluated by deter-

    mining the operating conditions that potentially can drive the

    plant to bulking (X31), foaming (X32) and rising sludge (X33).

    The uncertainty in these indices is represented using the

    inter-quartile range the differencebetween the third quartile

    and the first quartile. The higher the value of the inter-quartile

    range, the higher the uncertainty on the index is. That said,

    the inter-quartile range for these three indices of settling

    problems are plotted against each other in a three dimen-

    sional graph for all the scenarios (Fig. 3). The main objective of

    Fig. 3 is not representing the precise values of the six evalu-

    ated alternatives, but showing the main differences betweenalternatives. Hence, at first sight, the results presented in this

    figure lead to the following conclusions: alternatives A4 and A6

    (in white) are clearly different from the rest of the evaluated

    alternatives. In terms of reduction of the rising risk variability

    (X33) alternatives with an external carbon source controller

    present the lowest uncertainty. This is because this type of

    controller results in a rather low and constant effluent nitrate

    level (see in Fig. 3 the large distance along the Z axis between

    A1, A2, A3, A5. on the one hand and A4, A6 on the other hand)

    where the presence of high nitrate levels in the settler andthus the effluent is the main factor contributing to the

    occurrence of rising sludge (Comas et al., 2006).

    It is important to also highlight the low variation in terms

    of bulking and foaming risk from one alternative to another.

    Only the controllers with an external carbon source addition

    result in a marginal reduction in risk for bulking (X31) and

    foaming (X32) uncertainty. Again this fact is appreciated in

    Fig. 3 with the small separation between A4, and A6 and the

    rest of the evaluated alternatives on the X and the Yaxes. The

    lower risk for bulking and foaming for controllers with

    external carbon source addition is mainly due to the fact that

    the food to microorganism ratio (Comas et al., 2006) is more

    constant for such scenario due to the external carbon sourceaddition. Indeed, the external carbon source addition will in

    fact do nothing else than compensate for low influent

    concentrations of readily biodegradable substrate, for

    example during night time. On the other hand, again, the

    external carbon source increases the concentration of solids

    in the reactor, thus reducing the food to microorganism ratio

    and increasing the risk of bulking and foaming

    4.2.4. Legal objectives (OBJ4)

    Finally, the percentage of time that the plant is in violation of

    the legal effluent discharge limits for the different pollutants

    (X4X7) forms the set of criteria to evaluate the accomplish-

    ment of OBJ4 (comply with legal effluent discharge limits). Forthis case study criteria X4, X5 and X6 are always below the

    limits without any variation, and as a consequence they are

    not useful in discriminating between the competing alterna-

    tives. Fig. 4 shows that control strategies A4 and A6 present

    a lower risk of not complying with the effluent standards. This

    4

    6

    8

    10

    12

    14

    16

    18

    20

    22

    24

    13,8

    14,2

    14,6

    15,0

    15,4

    15,8

    15,015,5

    16,016,5

    17,017,5

    Q3-Q1for

    X3-3

    (%)

    Q3-Q

    1forX3-2(%)

    Q3-Q1forX3

    -1(

    %)

    Alternative A1

    Alternative A2

    Alternative A3

    Alternative A4

    Alternative A5

    Alternative A6

    Fig. 3 Risk of occurrence of separation problems (X3), 3-D

    representation of the inter-quartile range (Q3Q1) for all the

    evaluated control strategies under ASM parameters

    uncertainty.

    Alternative

    X8timeinviolationforTN(%)

    0

    20

    40

    60

    80

    100

    A1

    A2

    A3

    A4

    A5

    A6

    Fig. 4 Error bar chart of criterion X7 (TIVTN) for the

    generated control strategies under ASM parameters

    uncertainty.

    w a t e r r e s e a r c h 4 2 ( 2 0 0 8 ) 4 4 8 5 4 4 9 7 4493

  • 7/29/2019 evaluacin multicriterios de plantas de tratamiento de agua

    10/13

    is mainly due to the fact that those strategies are character-

    ized by high denitrification rates because the external carbon

    source enhances the nitrate reduction to nitrogen gas, and as

    a consequence the effluent nitrate concentration is continu-

    ously below the limits and with less variation as shown by

    the dynamic profiles in Fig. 5. With respect to the rest of the

    controllers it can in general be concluded that as long as the

    level of plant instrumentation increases (more on-line sensorsand control) the percentage of the time that the plant is in

    violation and its uncertainty will decrease.

    4.3. Decision procedure

    The multi-objective function defined in the previous section

    (Eq. (1)) is used as a metric to quantify the overall degree of

    satisfaction of the control objectives for the different gener-

    ated alternatives. This metric is calculated for all 1000 simu-

    lations that were performed for each alternative, where each

    simulation is based on one of the parameter combinations

    resulting from the Latin hypercube sampling method

    described in the previous section. In this case, the mostdesirable alternative has the highest mean and lowest stan-

    dard deviation in terms of the multi-objective function. A

    practical wayto see this relationship is by using the coefficient

    of variation (see Table 5).

    From the results of the previous analyses it is possible to

    know the contributions of environmental, economic, legal and

    technical objectives to the variance in the control objectives

    overall degree of satisfaction. In this way, alternatives A4 and

    A6 are the least favoured alternatives because they have the

    lowest scores in objective OBJ2 (minimize economic costs); i.e.

    high absolute value and high variability in plant operating

    cost. This is mainly due to the extra cost of the carbon source

    and additional sludge production that is induced by applying

    this strategy. Nevertheless, it must be pointed out that these

    two alternatives provide the best accomplishment and the

    lowest variation in objectives OBJ1 (minimize environmentalimpact) and OBJ4 (comply with legal effluent discharge limits).

    Alternative A1 is also rejected because of the bad scores in

    operational costs (OBJ2), environmental (OBJ1) and legal

    objectives (OBJ4). The lack of instrumentation in this strategy

    makes the operation really unfeasible, because the plant is

    always running under the same operating conditions and is

    not capable to adapt to the different perturbations caused by

    influent composition and flow rate variations.

    It is important to point out that the results of Table 5

    demonstrate that when uncertainty in the ASM model inputs

    is considered, then the decision to implement alternative A5that was derived from the (deterministic) base case evaluation

    might be questioned. Despite the fact that alternative A5obtained good scores in some of the criteria used to quantify

    the degree of satisfaction of the considered objectives, it can

    also be concluded that its performance strongly depends on

    the selection of the model inputs, i.e. kinetic and stoichio-

    metric parameters, and influent fractions. If those inputs are

    changed from the default values, as is done when performing

    the Monte Carlo simulations, the same level of accomplish-

    ment of the plant objectives can no longer be ensured. For this

    t (days)

    8 10 12 14

    t (days)

    8 10 12 14

    t (days)

    8 10 12 14

    t (days)

    8 10 12 14

    gNm-3

    5

    10

    15

    20

    25

    30

    gNm-3

    5

    10

    15

    20

    25

    30

    gNm-3

    5

    10

    15

    20

    25

    30

    gNm-3

    5

    10

    15

    20

    25

    30

    5th Percentile

    95th Percentile

    5th Percentile

    95th Percentile

    5th Percentile

    95th Percentile

    5th Percentile

    95th Percentile

    a b

    c d

    Fig. 5 Dynamic uncertainty ranges for TN during the evaluation of alternative (a) A2, (b) A3, (c) A4 and (d) A6 under ASM

    parameters uncertainty. The 5th and the 95th percentile TN profile resulting from the Monte Carlo simulations are shown.

    w a t e r r e s e a r c h 4 2 ( 2 0 0 8 ) 4 4 8 5 4 4 9 74494

  • 7/29/2019 evaluacin multicriterios de plantas de tratamiento de agua

    11/13

    reason, when considering uncertainty on model inputs alter-

    native A3 comes out as the most desirable alternative that has

    a higher chance of success, since A3 has good scores in all the

    objectives and can thus be considered as the most balanced of

    the alternatives. Also, the good value in terms of multi-

    objective mean and standard deviation ensures the robust-

    ness of the decision. Hence it cannot be said that alternative

    A5 is better than A3, as was concluded in the deterministic

    case. Instead, it is now probable that alternative A3 is better

    than A5. This analysis including uncertainty thus brings

    about a better documented decision about which alternative

    to choose, since balancing the accomplishment of the objec-tives is combined with taking into account the deviations

    created by the input uncertainties that are considered.

    It should be emphasized that the use of multi-criteria

    decision analysis inherently implies a certain degree of

    subjectivity. Indeed, the selection of criteria, the definition of

    the extreme profiles before the normalization and the relative

    weight given to the control objectives are important factors

    affecting the scores. Nevertheless, the main focus of the study

    was not on the subjectivity (i.e. the choices mentioned before)

    involved in the construction of a multi-objective function.

    Rather the main focus was to study how the uncertainty

    involved in quantifying different objectives of the multi-

    objective function (assuming the multi-objective function isconstructed) influences the decision making. For this study,

    the multi-objective function was defined in an explicit and

    transparent way by using equal weights for all the objectives.

    The key to solving this multi-criteria decision making

    problem is not easily found, and the solution is based on

    realizing that different process alternatives have many

    uncertainties in common. For example, all the generated

    WWTP control strategies are subjected to identical uncertain

    influent fractions and kinetic and stoichiometric parameters,

    but depending on the evaluated alternative, the uncertainty

    will be propagated in a different way. Assuming that the

    decision maker is particularly interested in a control strategy

    that promises the lowest environmental impact, then theselected alternative would be A4. On the other hand, if

    a compromise between operation costs and risk wants to be

    ensured that controller should be A3. The preferences of the

    decision maker can be considered in the analysis by adjusting

    the weights wk such that they reflect the importance given by

    the decision maker to each objective (see also below).

    5. Scenario analysis and final discussion

    The scenario analysis of the weights applied to the multi-

    objective function (Eq. (1)) presented in this last part of the

    paper is intended to contribute to clarifying how the selected

    alternative resulting from the multi-criteria decision making

    procedure under activated sludge model input uncertainties

    will vary when the relative importance of the different

    objectives expressed by the weights wk is changed. The

    weights represent the desires or preferences of the decision

    makers to obtain an alternative that maximises the degree of

    satisfaction and reduces variability for one or several specifc

    objectives.

    The first example consists of a simplified analysis amongst

    objectives OBJ1 (minimize environmental impact), OBJ2(minimize economical costs) and OBJ3 (maximize technical

    reliability). The results are presented in a bi-plot fashion,where the changes in the selected alternative (different type

    of symbol and colour) are represented when the relative

    importance amongst objectives OBJ1 (X axis) and OBJ2 (Yaxis)

    is modified. The values of OBJ3 are omitted because we do not

    have a third dimension, but they can be easily found as (0.75

    minus the sum of OBJ1 and OBJ2). The importance of the fourth

    objective (comply with the legal effluent discharge limits,

    OBJ4) remains constant, i.e. w4 0.25 in order to maintain the

    previously established condition that the sum of the weights

    wk should be 1.

    From the results ofFig. 6 it can be noticed that high values

    of OBJ1 clearly favour alternative A4 above the other alterna-

    tives. This is mainly due to the fact that the addition ofexternal carbon source in this strategy will reduce the impact

    on water by improving the overall nitrogen removal efficiency

    while simultaneously reducing the variability in the effluent

    quality as shown in Figs. 1, 4 and 5. Nevertheless, as w2increases in value the most desirable alternative changes

    w1

    0,0 0,2 0,4 0,6

    w2

    0,0

    0,2

    0,4

    0,6

    Alternative A1

    Alternative A2

    Alternative A3

    Alternative A4

    Alternative A5

    Alternative A6

    Fig. 6 Scenario analysis of the weights of the OBJ1

    (minimize environmental impact), OBJ2 (minimize

    operating cost) and OBJ3 (maximize technical reliability).

    Table 5 Mean, standard deviation and coefficient of variation of the multi-objective function for the different controlstrategies under uncertainty

    s(Aj) A1 A2 A3 A4 A5 A6

    Mean 0.68 0.71 0.72 0.63 0.71 0.64

    Standard deviation 0.04 0.03 0.02 0.04 0.06 0.10

    CV 17.00 24.73 36.00 15.75 11.83 6.40

    w a t e r r e s e a r c h 4 2 ( 2 0 0 8 ) 4 4 8 5 4 4 9 7 4495

  • 7/29/2019 evaluacin multicriterios de plantas de tratamiento de agua

    12/13

    from A4 to A3 because alternative A3 presents lower operating

    costs and variability as shown in Table 4. It is important to

    mention that all the alternatives with an ammonium

    controller (A4, A6), although having the lowest values in

    operating costs, are anyhow not selected when the economic

    objectives are prioritized. This is mainly due to the high

    sensitivity of the ammonium controller to the input uncer-

    tainty, increasing the variance of the multi-criteria index andthus reducing the coefficient of variation. Finally when

    objective OBJ3 is prioritized, the selected alternative depends

    on the relative contribution of OBJ1 and OBJ2 because both

    alternatives satisfy OBJ3 in a similar way. Again, it can be said

    that alternative A4 improves the coefficientof variation of OBJ1(minimize environmental impact) at the expense of sacrificing (to

    an extent) its economical variability (OBJ2).

    This analysis opens the door to a number of discussions.

    One can note in this example that the preliminary selected

    alternative A5 is no longer selected as the best for any of the

    possible combinations of weights. The considered input

    uncertainties had a large impact on the behaviour of this

    controller (cascade ammonium), where in some cases thiscontroller was not capable to compensate for the different

    disturbances. After this analysis, it was possible to conclude

    that this alternative was only the best for a limited range of

    conditions. Thus, when considering uncertainty in the multi-

    criteria decision making it is possible to answer questions

    such as: What would happen if there is a change in the

    influent composition? What are the expected effects of either

    temperature changes or toxic spills and how can the

    controller handle them? Secondly, this type of representa-

    tions clearly distinguishes the different processes and their

    more important features, while at the same time it highlights

    their main weaknesses. Finally, it is highly encouraged to

    perform this type of analysis because it can better guidedecision makers on such important questions as whether to

    go ahead with the implementation of a controller and what is

    the potential risk of failures in the event of the selection of an

    alternative.

    6. Conclusions

    This paper has demonstrated a method to consider the

    influence of activated sludge input uncertainty in the decision

    making process during the multi-criteria evaluation of control

    strategies in a WWTP. In the first section several WWTP

    control strategies were tested and evaluated using standarddeterministic multi-criteria decision analysis using a modified

    version of the BSM2 as a case study. In the second part, the

    uncertainty in those parameters was quantified by means of

    model input probability distributions that were based on the

    available knowledge about the different parameters. Next the

    plant mechanistic model was coupled to a Monte Carlo engine

    that randomly selected parameters from the previously

    defined distributions using Latin hypercube sampling, i.e.

    input uncertainty, solving the model for each set of model

    inputs. Such approach gave a range of possible solutions for

    the desired WWTP performance criteria representing their

    possible variation. The results were analyzed using several

    descriptive statistical tools and it was possible to see how

    these input uncertainties were propagated through the model

    and affected the different outcomes.

    From the evaluated controllers, alternatives with an

    external carbon source (alternatives A4 and A6) reduced the

    uncertainty in the degree of satisfaction of environmental,

    legal and technical objectives but increasing the economical

    costs and its variability as a trade-off. The alternatives with

    DO and SNO controller (A2 and A3) reduced operational costswhile at the same time improving the effluent quality. Finally,

    it was shown how the preliminary selected alternative

    A5 resulting from a deterministic multi-criteria decision

    analysis became less desirable when the input uncertainty

    was considered. When considering uncertainty, a simpler

    controller structure (A3) was evaluated to have a larger chance

    of success.

    The relative importance of the control objectives (weights)

    on the selection of alternatives was investigated. One one

    hand it was possible to discover the affinity of alternative A4for objectives OBJ1 and OBJ4. On the other hand the scenario

    analysis revealed that when OBJ2 was favoured alternative A3

    would be selected.Finally, it should be emphasized that this type of analysis

    results in a more transparent decision making process, since

    the uncertainty analysis contributes to developing an

    improved understanding on the process and the trade-offs

    between different objectives. Practically, the uncertainty

    analysis allows identification of potential WWTP problems

    early on and reduces the risk of controller failures.

    Acknowledgments

    The authors gratefully acknowledge financial support from

    the Spanish Ministerio de Ciencia y Tecnologa projects:

    DPI2006-15707-C02-01, 018/SGTB/2007/3.1 and NOVE-

    DAR_Consolider. Gurkan Sin also wishes to acknowledge his

    post-doctoral scholarship of the Hans Christian Oersted

    Postdoc Programme at DTU.

    r e f e r e n c e s

    Batstone, D.J., Keller, J., Angelidaki, I., Kayuznyi, S.V.,

    Pavlostathis, S.G., Rozzi, A., Sanders, W.T.M., Siegrist, H.,Vavilin, V.A., 2002. Anaerobic Digestion Model No. 1. IWAScientific and Technical Report No. 13. IWA Publishing,London, UK.

    Beck, M.B., 1987. Water quality modelling: a review of the analysisof uncertainty. Water Resour. Res. 23 (8), 13931442.

    Belton, V., Stewart, T.J., 2002. Multiple Criteria Decision Analysis:an Integrated Approach. Kluwer Academic Publishers,Dordrecht,.

    Benedetti, L., Bixio, D., Vanrolleghem, P.A., 2006. Assessment ofWWTP design and upgrade options: balancing costs and risksof standards exceedance. Wat. Sci. Technol. 54 (67), 371378.

    Comas, J., Rodriguez-Roda, I., Poch, M., Gernaey, K.V., Rosen, C.,Jeppsson, U., 2006. Extension of the IWA/COST simulationbenchmark to include expert reasoning for system

    performance evaluation. Wat. Sci. Technol. 53 (45), 331339.

    w a t e r r e s e a r c h 4 2 ( 2 0 0 8 ) 4 4 8 5 4 4 9 74496

  • 7/29/2019 evaluacin multicriterios de plantas de tratamiento de agua

    13/13

    Copp, J.B., 2002. The COST Simulation Benchmark: Descriptionand Simulator Manual. Office for Official Publications of theEuropean Community, Luxembourg.

    Flores, X., Bonmat, A., Poch, M., Rodriguez-Roda, I., Banares-Alcantara, R., 2005. Selection of the activated sludgeconfiguration during the conceptual design of activated sludgeplants using multcriteria analysis. Ind. Eng. Chem. Res. 44 (10),35563566.

    Flores, X., Comas, J., Rodriguez-Roda, I., Jimenez, L., Gernaey, K.V.,2007a. Application of multivariable statistical techniques inplant-wide WWTP control strategies analysis. Wat. Sci.Technol. 56 (6), 7583.

    Flores, X., Poch, M., Rodrguez-Roda, I., Banares-Alcantara, R.,Jimenez, L., 2007b. Systematic procedure to handle criticaldecisions during the conceptual design of activated sludgesystems. Ind. Eng. Chem. Res. 46 (17), 56005613.

    Gernaey, K.V., Jeppsson, U., Batstone, D.J., Ingildsen, P., 2006.Impact of reactive settler models on simulated WWTPperformance. Wat. Sci. Technol. 53 (1), 159167.

    Gernaey K., Vrecko D., Rosen C., Jeppsson U. 2007. BSM1 versusBSM1_LT: is the control strategy performance rankingmaintained? In: Proceedings of the Seventh International IWASymposium on Systems Analysis and Integrated Assessment

    in Water Management, Washington DC, USA, 7th9th May2007.

    Gujer, W., Henze, M., Mino, T., van Loosdrecht, M.C.M., 1999.Activated sludge model no. 3. Wat. Sci. Technol. 39 (1),183193.

    Hair, J.F., Andersen, R.E., Tatham, R.L., Black, W.C., 1998.Multivariable Data Analysis, fifth ed. Prentice-Hall, London,UK.

    Helton, J.C., Davis, F.J., 2003. Latin hypercube sampling methodand the propagation of uncertainty in analyses of complexsystems. Reliab. Eng. Syst. Saf. 81 (1), 2369.

    Henze, M., Gujer, W., Mino, T., van Loosdrecht, M.C.M., 2000.Activated Sludge Models ASM1, ASM2, ASM2d and ASM3. IWAScientific and Technical Report No. 9. IWA Publishing, London,UK.

    Iman, R.L., Helton, J.C., Campbell, J.E., 1981. An approach tosensitivity analysis of computer models, Part 1. Introduction,input variable selection and preliminary variable assessment.

    J. Qual. Technol. 13 (3), 174183.Jeppsson, U., Pons, M.N., Nopens, I., Alex, J., Copp, J.B., Gernaey, K.

    V., Rosen, C., Steyer, J.P., Vanrolleghem, P.A., 2007. BenchmarkSimulation Model No 2 general protocol and exploratory casesudies. Wat. Sci. Technol. 56 (8), 287295.

    Martin, C., Eguinoa, I., McIntyre, N.R., Garca-Sanz, M. and Ayesa,E., 2007. ARMA models for uncertainty assessment of timeseries data: application to Galindo-Bilbao WWTP. In:Proceedings of the Seventh International IWA Symposium on

    Systems Analysis and Integrated Assessment in WaterManagement, Washington DC, USA, 7th9th May 2007.

    McKay, M.D., Conover, W.J., Beckman, R.J., 1979. A comparison ofthree methods for selecting values of input variables in theanalysis of output from a computer code. Technometrics 21,239245.

    Neumann, M.B., von Gunten, U., Gujer, W., 2007. Uncertainty inprediction of disinfection performance. Wat. Res. 41 (11),

    23712378.Nopens, I., Batstone, D., Copp, J.B., Jeppsson, U., Volcke, E., Alex, J.,

    Vanrolleghem, P.A.A newinterface forASMADM foruse in theBenchmark Simulation Model No. 2. Water Res., submitted forpublication.

    Otterpohl, R., Raak, M., Rolfs, T. 1994. A mathematical model forthe efficiency of the primary clarification. In: Proceedings ofthe 17th IAWQ Biennial Conference on Water Quality,Budapest, Hungary, July 1994.

    Salem, S., Berends, D., Heijnen, H.J., van Loosdrecht, M.C.M., 2002.Model-based evaluation of a new upgrading concept for N-removal. Wat. Sci. Technol. 45 (6), 169177.

    Siegrist, H., Brunner, I., Koch, G., Con Phan, L., Van Chieu, L., 1999.Reduction of biomass decay under anoxic and anaerobicconditions. Wat. Sci Technol. 39 (1), 129137.

    Sin, G., De Pauw, D.J.W., Weijers, S., Vanrolleghem, P.A., 2008. Anefficient approach to automate the manual trial and errorcalibration of activated sludge models. Biotechnol. Bioeng. 100(3), 516528.

    Stare, A., Vrecko, D., Hvala, N., Strmcnik, S., 2007. Comparison ofcontrol strategies for nitrogen removal in an activated sludgeprocess in terms of operating costs: a simulation study. Wat.Res. 41 (9), 20042014.

    Takacs, I., Patry, G.G., Nolasco, D., 1991. A dynamic model of theclarification thickening process. Wat. Res. 25 (10), 12631271.

    Vanrolleghem, P., Gillot, S., 2002. Robustness and economicmeasures as control benchmark performance criteria. Wat.Sci. Tech 45 (4/5), 117126.

    Vincke, P., 1992. Multicriteria Decision-Aid. John Wiley & Sons,Chichester, UK.

    Volcke, E.I.P., Gernaey, K.V., Vrecko, D., Jeppsson, U., vanLoosdrecht, M.C.M., Vanrolleghem, P.A., 2006. Plant-wide(BSM2) evaluation of reject water treatment with a SHARON-Anammox process. Wat. Sci. Technol. 54 (8), 93100.

    Vrecko, D., Gernaey, K.V., Rosen, C., Jeppsson, U., 2006.Benchmark Simulation Model no. 2 in Matlab-Simulink:towards plant-wide WWTP control strategy evaluation. Wat.Sci. Technol. 54 (8), 6572.

    Yuan, Z., Boagert, H., Leten, J., Verstraete, W., 2000. Reducing thesize of the nitrogen removal activated sludge plant byshortening the retention time of the inert solids via sludgestorage. Wat. Res. 34 (2), 539554.

    w a t e r r e s e a r c h 4 2 ( 2 0 0 8 ) 4 4 8 5 4 4 9 7 4497