Upload
miles-ball
View
212
Download
0
Embed Size (px)
Citation preview
Evaluation of the SEND Pathfinder Programme: Early Findings
June 2012
Outline
The findings reported Are based on the first monitoring returns provided by all
Pathfinder sites Are sites own perceptions of progress
Cover the period to the end of March 2012 Are based around the Common Delivery Framework (CDF),
which sets out a series of themes and elements which it was anticipated each Pathfinder would need to address
Will be updated quarterly based on future monitoring submissions
2
=Development not yet begun
=Early stage
development=
Partial development
=Full
implementation
=Already in place
prior to the Pathfinder
Movement left to right within the diagrams indicates increasing
progress
Pathfinder progress setting up governance structures by end of March 2012
3
Quarter 4
Quarter 3
Quarter 4
Quarter 3
Quarter 4
Quarter 3
A c
lea
r se
t of o
bje
ctiv
es
ha
ve b
ee
n a
gre
ed
0 5 10 15 20 25
Development not yet begun Early stage development Partial development Full implementation Already in place prior to becoming a Pathfinder
Number of Pathfinder areas
Substantial progress setting up governance structures Three quarters of areas (22) had their board or governance
structure fully in place Two thirds (19) had agreed a clear set of Pathfinder objectives
Stakeholder engagement4
There is a group of stakeholders that are common to almost all sites
…but also some less represented than might expect – but may reflect local
focus / circumstances
Good progress on staffing… but more mixed on other developments
Almost all areas had a designated Pathfinder lead in place, and three quarters had a nominated project manager
Wider restructuring had caused issues in some areas
Leads and Project Managers most often from education or a multiagency background
Most areas reported that they had at least partially developed commitment from education (28), social care (25) and health (25) to share resources signalling some collective responsibility
Far fewer had secured resource for the resultant service provision
Most of the Pathfinder areas had started to consider the development of their approaches to change management, market development and the local
… but many still perceived themselves to be in the early stages of developing these elements
5
Parent-carer and VCS involvement in the development of the Pathfinder
6
Pathfinder areas had made good progress in terms of engaging the VCS and parent/carers in the development of the Pathfinder
Although the majority of areas were still in the early stages (or had not yet begun) engaging children and young people in this development
Quarter 4
Quarter 3
Quarter 4
Quarter 3
Quarter 4
Quarter 3
Enga
gem
ent
of p
aren
t ca
rers
in t
he d
evel
opm
ent
of t
he P
athfi
nder
0 5 10 15 20 25
Development not yet begun Early stage development Partial development Full implementation Already in place prior to becoming a Pathfinder
Number of Pathfinder areas
Overall it is a mixed picture across the areas7
19 judged at least a third of the 16 progress measures to be fully in place 13 were still in the early stages of developing (or had not yet begun) a third of
their progress measures
Progress engaging and involving families and young people to participate in the Pathfinder
Most had begun to consider raising awareness with families and young people
… but few had done soAs a result the numbers recruited to the end of March
were very smallBy early June the number recruited had risen to 129 –
but heavily dependent on one siteThe vast majority of those recruited were already in
receipt of SEN support… and 80% receiving specialist health support
8
Progress setting up the Pathfinder infrastructure
By the end of March 2012 all Pathfinder areas had begun to develop their assessment and single plan pathway
Around half of the areas had reached ‘partial development’ of the assessment pathway and were considering A set of assessments (by different agencies) being brought together – 12 of 14
areas Single assessment episode supplemented by ad hoc specialist assessments – 8
of 14 areas
The most common planning approaches being considered by the 14 areas were Single planning events The use of a planning coordinator to create the plan with the family and liaise
with professionals from relevant agencies to obtain their input
Relatively few had progressed personal budgets, information sharing or risk management
9
Key conclusions and implications10
• IMPLICATIONSCONCLUSIONS
•How to engage the stakeholders that have proven to be more difficult to engage or that may not be linked to the immediate target group, but will play a part in the development of a 0-25 yrs approach•How to ensure accountability of the resource that is required for the service packages
All areas had set up a Project Board/Governance structure,
which included engagement from the following stakeholders
•The extent to which operational staff had been actively engaged in the development of the Pathfinders was unclear•Change management of operational staff will be crucial, and needs progressed to fit with family recruitment
The majority of areas had a designated Lead and a Project Manager in post
•How areas can scale up their developing approach for the whole 0-25 yrs and for existing and new cases post the Pathfinder•To date most recruitment has been of families already in receipt of services•There is less progress on personal budgets and information sharing
Around half of the areas reporting they had at least
reached the partial development stage of their assessment and
single plan pathway
11
Contact
Graham Thom
Director
SQW
t. 07766 916897
w. www.sqw.co.uk
Meera Prabhakar
Senior Consultant
SQW
t. 07715 071574
w. www.sqw.co.uk