21
Evaluation Phase Overview

Evaluation Phase Overview. 2 2.01 Evaluation Phase Overview Plan Decision Board Project Team Frame Alter- natives The third step in the IMSCG decision

Embed Size (px)

Citation preview

Page 1: Evaluation Phase Overview. 2 2.01 Evaluation Phase Overview Plan Decision Board Project Team Frame Alter- natives The third step in the IMSCG decision

Evaluation Phase Overview

Page 2: Evaluation Phase Overview. 2 2.01 Evaluation Phase Overview Plan Decision Board Project Team Frame Alter- natives The third step in the IMSCG decision

22.01 • Evaluation Phase Overview

Plan

Decision Board

Project Team

FrameAlter-

natives

The third step in the IMSCG decision process evaluates the alternatives to identify sources of value and risk.

EvaluatedAlternatives

Spreadsheet ModelA B C

1

2

3

4

5Tornado Diagram

Decision Tree

Probability Distributions

The goals of the phase are understanding, insight, and communication.

Assessed Probabilities

Page 3: Evaluation Phase Overview. 2 2.01 Evaluation Phase Overview Plan Decision Board Project Team Frame Alter- natives The third step in the IMSCG decision

32.01 • Evaluation Phase Overview

The deliverables of the evaluation phase illustrate the implications of choosing one alternative over another.

$

1 2 3 4

• Base case evaluation of alternatives

Why?• Sources of value

• Sources of risk

• Probabilistic analysis

The level of analysis varies with the complexity and importance of the decision. Evaluation stops if the best choice is clear, based on sources of value or sensitivity analysis.

Page 4: Evaluation Phase Overview. 2 2.01 Evaluation Phase Overview Plan Decision Board Project Team Frame Alter- natives The third step in the IMSCG decision

42.01 • Evaluation Phase Overview

Assess Situation

Develop Alternatives

Evaluate Alternatives

Plan for Implementation

Project Team

Dialogue Decision Process

Specific steps provide a logical approach for conducting the evaluation phase.

DecisionStructure

DeterministicAnalysis

ProbabilisticAnalysis

Insight Generation

InitialSituation

These steps will allow us to organize our discussion in the evaluation phase.

Page 5: Evaluation Phase Overview. 2 2.01 Evaluation Phase Overview Plan Decision Board Project Team Frame Alter- natives The third step in the IMSCG decision

52.01 • Evaluation Phase Overview

A deterministic model has single-valued inputs and outputs; probabilistic analysis addresses uncertainty.

Deterministic Analysis

ModelC = A + B

A

B39

47C

86

• One variable value for each input

• “Assumes away” uncertainty

Probabilistic Analysis

ModelC = A + B

A

BC

• Probability distribution for each uncertain input variable

• Explicitly analyzes uncertainty

Page 6: Evaluation Phase Overview. 2 2.01 Evaluation Phase Overview Plan Decision Board Project Team Frame Alter- natives The third step in the IMSCG decision

62.01 • Evaluation Phase Overview

Strategy Table

Several tools provide insight throughout the evaluation phase.

DecisionStructure

DeterministicAnalysis

ProbabilisticAnalysis

InsightGeneration

Initial

Situation

Iteration

InfluenceDiagram

1

2

3

4

5

DeterministicModel

A B C

TornadoDiagram

DecisionTree

ProbabilityDistributions

Decision Quality

Page 7: Evaluation Phase Overview. 2 2.01 Evaluation Phase Overview Plan Decision Board Project Team Frame Alter- natives The third step in the IMSCG decision

7

We break down our discussion of the evaluation phase into the following topics.

2.01 • Evaluation Phase Overview

12345

A B C

• The art of spreadsheet modeling

• Base case and sensitivity analysis

• Introduction to probabilistic analysis

• Probability assessment and biases

• Structuring decision trees

Page 8: Evaluation Phase Overview. 2 2.01 Evaluation Phase Overview Plan Decision Board Project Team Frame Alter- natives The third step in the IMSCG decision

8

Appendix

2.01 • Evaluation Phase Overview

Page 9: Evaluation Phase Overview. 2 2.01 Evaluation Phase Overview Plan Decision Board Project Team Frame Alter- natives The third step in the IMSCG decision

92.01 • Evaluation Phase Overview

We will introduce the main concepts to be used during the evaluation phase.

•Evaluation Phase Overview

•Net Present Value Review

Page 10: Evaluation Phase Overview. 2 2.01 Evaluation Phase Overview Plan Decision Board Project Team Frame Alter- natives The third step in the IMSCG decision

102.01 • Evaluation Phase Overview

…it’s all about the time-value of money!

• If I were to give you a $100k gift, would you prefer to receive it today or in a year from now?

− What about $100k today or $120k a year from now?

• If the lottery announces a $25 million prize, why does the winner get ~$14 million when he goes to collect it?

Page 11: Evaluation Phase Overview. 2 2.01 Evaluation Phase Overview Plan Decision Board Project Team Frame Alter- natives The third step in the IMSCG decision

112.01 • Evaluation Phase Overview

NPV is a simple, accurate, easy-to-interpret measure for financial analysis.

• NPV is a measure of wealth creation that incorporates time-value of money− It represents the net amount generated by an investment expressed in

today’s dollars.

• NPV is easy to calculate and interpret. − If an investment has a positive NPV, it creates wealth. − If an investment has a negative NPV, it consumes wealth - and

should be rejected.

• NPV allows for easy comparison between investments.− The maximum NPV is preferred. − The NPV of a sum of independent projects is the sum of their NPVs.

• NPV is clear and straightforward compared with old methods of investment appraisal, such as IRR and profitability index.

• NPV is widely used and understood by the business community.

Page 12: Evaluation Phase Overview. 2 2.01 Evaluation Phase Overview Plan Decision Board Project Team Frame Alter- natives The third step in the IMSCG decision

122.01 • Evaluation Phase Overview

To illustrate the use of NPV when making investment decisions, consider the situation facing Acme Corporation*.

• Acme wishes to expand capacity by modifying an existent plant or by building a new plant.

* This example is based on R. A. Brealey, S. C. Myers, Principles of Corporate Finance.

We will use NPV to help Acme make the right choice.

Modify Plant

Initial Investment: $ 4M

Build New Plant

Initial Investment: $ 7M

Page 13: Evaluation Phase Overview. 2 2.01 Evaluation Phase Overview Plan Decision Board Project Team Frame Alter- natives The third step in the IMSCG decision

132.01 • Evaluation Phase Overview

Step 1: We shall compute cash flows in each year—“cash in minus cash out.”

Capital Investment ($M)Sales

Cost of Goods SoldSalvage Value

Net Cash Flow ($M)

0–4

–4.0

1

4–3

1

2

4–3

1

3

4–3

1

4

4–3

1

5

4–3

1

6

4–3

1

7

4–3

1

8

4–3

1

9

4–3

1

10

4–3

0.61.6

Modify PlantYear

Capital Investment ($M)Sales

Cost of Goods SoldSalvage Value

Net Cash Flow ($M)

0–7

-7.0

1

4–2.4

1.6

2

4–2.4

1.6

3

4–2.4

1.6

4

4–2.4

1.6

5

4–2.4

1.6

6

4–2.4

1.6

7

4–2.4

1.6

8

4–2.4

1.6

9

4–2.4

1.6

10

4–2.40.81.6

Build Plant Year

The initial investment is done at “time 0” or

today

Based on Acme’s assumptions,the new plant will not impact sales,

though it will reduce production costs and have a higher salvage value

All other cash flows are assumed to happen at the end of each

period

Page 14: Evaluation Phase Overview. 2 2.01 Evaluation Phase Overview Plan Decision Board Project Team Frame Alter- natives The third step in the IMSCG decision

142.01 • Evaluation Phase Overview

Cash flow after taxes is the proper basis for calculation.

• Depreciation itself is not a cash flow. Depreciation only affects cash flows through tax effects. − Only tax savings due to the tax deductibility of depreciation are a cash

flow.

• Interest and dividends are not cash flows. − They are taken into account by discounting.

• Only Overhead generated by the project should be included. Beware of allocated overhead.

• Include working capital cash flows – they must be financed.

Page 15: Evaluation Phase Overview. 2 2.01 Evaluation Phase Overview Plan Decision Board Project Team Frame Alter- natives The third step in the IMSCG decision

152.01 • Evaluation Phase Overview

Only incremental cash flows matter.

• Forget sunk costs.− Do not include past expenditures. No project should be kept going just

because a lot of money has already been spent on it (valid also for relationships).

• Include opportunity cost.− E.g.: Using land has an opportunity cost. It is not free.

• Include terminal value – any residual value past the timeframe of the model− More applicable to company valuations than product valuations.− Usually estimated through a multiple or a perpetuity

• Include the financial impact of all side effects (impact on other parts of the business).− E.g.: Learning from new technology, environmental savings, etc.

Page 16: Evaluation Phase Overview. 2 2.01 Evaluation Phase Overview Plan Decision Board Project Team Frame Alter- natives The third step in the IMSCG decision

162.01 • Evaluation Phase Overview

Be consistent in the treatment of inflation.

• Use nominal discount rates with nominal cash flows.− The actual number of dollars and the actual interest rates.

− The preferred way in the US, Europe and Japan

• Use real discount rates with real cash flows.− Taking into account inflation – so the numbers represent what would have

happened in the absence of inflation.

− The preferred way in high inflation countries

• Different cash flows have different inflation rates (tax shields do not inflate; labor tends to be higher than CPI).

Page 17: Evaluation Phase Overview. 2 2.01 Evaluation Phase Overview Plan Decision Board Project Team Frame Alter- natives The third step in the IMSCG decision

172.01 • Evaluation Phase Overview

Step 2: We shall calculate the “discounted value” or “present value” of each cash flow.

Capital Investment ($M)Sales

Cost of Goods SoldSalvage Value

Net Cash Flow ($M)Discounted Cash Flow

0–4

–4.00

1

4–3

10.91

2

4–3

10.83

3

4–3

10.75

4

4–3

10.68

5

4–3

10.62

6

4–3

10.56

7

4–3

10.51

8

4–3

10.47

9

4–3

10.42

10

4–3

0.61.6

0.62

Modify Plant Year

The discounted or present value is the amount of money in today’s dollars that is equivalent to the cash flow in a particular year.

This is calculated as: Cash flow in Year i

(1 + discount rate)i

Capital Investment ($M)Sales

Cost of Goods SoldSalvage Value

Net Cash Flow ($M)Discounted Cash Flow

0–7

–7.00

1

4–2.4

1.61.46

2

4–2.4

1.61.32

3

4–2.4

1.61.20

4

4–2.4

1.61.09

5

4–2.4

1.60.99

6

4–2.4

1.60.90

7

4–2.4

1.60.82

8

4–2.4

1.60.75

9

4–2.4

1.60.68

10

4–2.40.81.6

0.93

Build Plant Year

Page 18: Evaluation Phase Overview. 2 2.01 Evaluation Phase Overview Plan Decision Board Project Team Frame Alter- natives The third step in the IMSCG decision

182.01 • Evaluation Phase Overview

The tricky part is to select the appropriate Discount Rate.

•Any use of capital imposes an opportunity cost to a firm – funds are diverted from earning a return on another investment.

− Uses of capital must be benchmarked against capital market investment options - only those that can earn in excess of its cost of capital create value for investors.

•The Discount Rate to use is the organization’s weighted average cost of capital (WACC)

− The WACC is the weighted average of the cost of individual sources of capital employed in the company:

WACC= KEquity* WEquity + (1-tax rate)*Kdebt * Wdebt

K = Component cost of capital W = weight of component as a % of total capital

• In most cases, as consultants, we will use the corporate Discount Rate – computed and provided by our client’s Finance department.

Page 19: Evaluation Phase Overview. 2 2.01 Evaluation Phase Overview Plan Decision Board Project Team Frame Alter- natives The third step in the IMSCG decision

192.01 • Evaluation Phase Overview

Step 3: The NPV is the sum today’s cash flow plus all future discounted cash flows.

Capital Investment ($M)Sales

Cost of Goods SoldSalvage Value

Net Cash Flow ($M)Discounted Cash Flow

NPV (at 10%)

0–4

–4.00$2.4M

1

4–3

10.91

2

4–3

10.83

3

4–3

10.75

4

4–3

10.68

5

4–3

10.62

6

4–3

10.56

7

4–3

10.51

8

4–3

10.47

9

4–3

10.42

10

4–3

0.61.6

0.62

Modify Plant Year

Capital Investment ($M)Sales

Cost of Goods SoldSalvage Value

Net Cash Flow ($M)Discounted Cash Flow

NPV (at 10%)

0–7

–7.00$3.1M

1

4–2.4

1.61.46

2

4–2.4

1.61.32

3

4–2.4

1.61.20

4

4–2.4

1.61.09

5

4–2.4

1.60.99

6

4–2.4

1.60.90

7

4–2.4

1.60.82

8

4–2.4

1.60.75

9

4–2.4

1.60.68

10

4–2.40.81.6

0.93

Build Plant Year

Σ

Σ

Page 20: Evaluation Phase Overview. 2 2.01 Evaluation Phase Overview Plan Decision Board Project Team Frame Alter- natives The third step in the IMSCG decision

202.01 • Evaluation Phase Overview

Plotting NPV versus discount rate avoids the difficulty of choosing a single discount rate.

• For Acme Corporation, we find that Build Plant is better than Modify Plant for any discount rate less than 15 percent.

0 5 10 15 20 25–2

–10

1

23

4

5

6

7

8

9

10

Discount Rate (%)

NP

V (

$ m

illio

ns)

Modify Plant

Build Plant

Key

Page 21: Evaluation Phase Overview. 2 2.01 Evaluation Phase Overview Plan Decision Board Project Team Frame Alter- natives The third step in the IMSCG decision

212.01 • Evaluation Phase Overview

NPV is the value measure of choice for investment valuation.

• A cash flow can have only one NPV.

• NPV distinguishes good (NPV+) from bad (NPV-) projects.

− A higher NPV represents higher value creation.

• NPV is able to handle changing discount rates.− This is useful for changing inflation and different long-term versus

short-term rates.

• NPV can be extended to include uncertainty.

NPV

$600K

$200K

$700K

Expected NPV = $400K

High-Yield Improvement

Low-Yield Improvement

($2,000K)

$585K

($2,000K)

.5

.5