84

EXECUTIVE SUMMARY...Contract 1001 – Yau Ma Tei to Whampoa Tunnels and Ho Man Tin Station 5 Contract 1002 – Kwun Tong Line Extension Whampoa Station and Overrun Tunnel 1.3 Coverage

  • Upload
    others

  • View
    8

  • Download
    0

Embed Size (px)

Citation preview

  • 1

    EXECUTIVE SUMMARY

    The Kwun Tong Line Extension (KTE) Project was awarded to the respective contractors in lateMay 2011. The EM&A programme for the Kwun Tong Line Extension (KTE) Projectcommenced on 20 June 2011, the commencement date of construction of the Project. This is the15th monthly Environmental Monitoring and Audit (EM&A) Report for Kwun Tong LineExtension (KTE) Project. The Report presents the results of EM&A works and the impactmonitoring for the construction works undertaken during the period of 1 September 2012 to 30September 2012. The major construction activities in the reporting period included utility anddrainage diversions, temporary road & traffic diversion, piling works, bulk excavation, shaft andadit excavation, soil nailing and ground improvement works.

    Impact monitoring for air quality and noise were conducted in accordance with the EM&AManual in the reporting period.

    No exceedance on noise and dust monitoring was recorded.

    No environmental notification of summon and prosecution were received in the reporting period.

    One environmental complaint on emission of dark smoke referred from EPD on 28 September2012 and they was classified as invalid complaints after investigation by EPD, ET and theContractors.

    Regular joint site inspections, led by the ER with the presence with representatives from theContractors and Environmental Team, were conducted on a weekly basis to monitor Contractors’performance on environmental management and implementation of environmental pollutioncontrol and mitigation measures for the Project. No non-conformance was identified in thereporting period. Some environmental concerned items raised during the site inspections havebeen followed up the respective contractors in a responsible manner.

    The Environmental Permit (EP-399/2010/B) dated on 7 June 2012 is being used for the KTEProject.

  • 2

    EXECUTIVE SUMMARY

    1 INTRODUCTION1.1 Project Background1.2 Project Programme1.3 Coverage of the EM&A Report

    2 PROJECT INFORMATION2.1 Project Management Organization and Contact Details2.2 Project Works Areas and Environmental Monitoring Locations2.3 Summary of EM&A Requirements2.4 Implementation of Environmental Mitigation Measures2.5 Construction Activities in the Reporting Month2.6 Construction Activities for the Coming Month

    3 IMPACT MONITORING3.1 Air Quality3.2 Noise3.3 Action taken in Event of Exceedance

    4 LANDSCAPE AND VISUAL4.1 Monitoring Requirements4.2 Audit Results4.3 Action Taken in Event of Non-Conformance

    5 WASTE MANAGEMENT

    6 WATER QUALITY

    7 RECORD OF ENVIRONMENTAL COMPLAINTS

    8 RECORD OF NON- COMPLIANCES

    9 NOTIFICATION OF SUMMONS AND PROSECUTIONS

    10 STATUS OF STATUTORY SUBMISSIONS10.1 Submissions required under Environmental Permits10.2 Statutory Permits and Licenses

    11 SITE INSPECTIONS11.1 Observations11.2 Other Notable Events

    12 FUTURE KEY ISSUES12.1 Key Issues for the Coming Month12.2 Effectiveness and Efficiency of Mitigation Measures

    13 CONCLUSIONS

  • 3

    List of Appendices

    Appendix A Figures

    Appendix B Environmental Quality Performance Limits

    Appendix C Event Action Plans

    Appendix D Implementation of Environmental Mitigation Measures

    Appendix E Calibration Details

    Appendix F Impact Monitoring Graphical Plots

    Appendix G Monitoring Schedule for the Present and Next Reporting Period

  • 4

    1 INTRODUCTION

    1.1 Project Background

    MTR Corporation Limited (MTRCL) proposes to build a new railway line, the KwunTong Line Extension (KTE), otherwise referred to as ‘the Project’, which is an extensionof the existing Kwun Tong Line from Yau Ma Tei Station to Whampoa area. The routelength of the fully underground KTE is approximately 2.6 km with two new stationsnamely Ho Man Tin Station (HOM) and Whampoa Station (WHA), and a new ancillaryventilation building at Wylie Road.

    1.2 Project Programme

    The Kwun Tong Line Extension (KTE) Project was awarded to the respective ContractorsNishimatsu Construction Co. Ltd (NCC) and Chun Wo-Hip Hing Joint Venture (CHJV)for construction in late May 2011. The commencement of construction was on 20 June2011. The commencement of operation of the Project is scheduled to be in 2015.Contractors’ summary programme for Contract 1001 and Contract 1002 are presentedbelow.

    NCC, as the Contractor of Contract 1001, is responsible for the construction of alignmentlink from the existing Yau Ma Tei Station to Wuhu Street at Whampoa and the new HoMan Tin Station as well as the ancillary ventilation building at Wylie Road. CHJV, asthe Contractor of Contract 1002, is responsible for the construction of the undergroundWhampoa Station and a platform & overrun tunnel.

    Contract 1001 – Yau Ma Tei to Whampoa Tunnels and Ho Man Tin Station

  • 5

    Contract 1002 – Kwun Tong Line Extension Whampoa Station and Overrun Tunnel

    1.3 Coverage of the EM&A Report

    The EM&A programme for the Kwun Tong Line Extension (KTE) Project commenced on20 June 2011. This is the 15th Monthly Environmental Monitoring and Audit (EM&A)Report for the Project. The Report presents the results of EM&A works and the impactmonitoring for the construction works undertaken by respective Contractors during theperiod of 1 September 2012 to 30 September 2012.

    2 PROJECT INFORMATION

    2.1 Project Management Organization and Contact Details

    The KTE Project organization chart is presented in Figure 1. Contacts of keyenvironmental personnel of the Project are shown in Tables 1a, 1b and 1c respectively.

    Figure 1. Project Organization

  • 6

    Table 1a Contact List of Key Personnel for Project Management

    Organization Name TelephoneEngineer’s Representative

    Project Manager James Chow 2163 6283

    Construction Manager Kenny Kong 3441 3101

    Construction Manager Nelson Yeung 3940 3398

    Independent Environmental Checker

    Consultant – Arup Jacky Chan 3447 6051

    Environmental Team

    Environmental Team Leader Richard Kwan 2688 1179

    Contact 1001 Contractor

    Project Manager Colin Birkby 9641 2485

    Environmental Officer Ricky Tse 9221 0368

    Contact 1002 Contractor

    Project Manager Eric Wu 2743 3711

    Senior Environmental Engineer Louie Chan 9270 1390

    Table 1b Contact List of Environmental AuthorityOrganization Name TelephoneEnvironmental Protection Department

    Sr Env Protection Offr(Metro Assessment) 2 Colin Keung 2835 1125

    Sr Env Protection Offr(Regional E) 6 C L Wong 2150 8002

    Sr Env Protection Offr(Regional E) 5 Warren Wong 2117 7538

    Sr Env Protection Offr(Regional E) 4 Louis Chan 2117 7502

  • 7

    2.2 Project Works Sites and Areas and Environmental Monitoring Locations

    The KTE Project works sites and areas are summarized in Table 2 below and shown inAppendix A Figures 1 to 8. The locations of environmental monitoring stations areindicated in Appendix A Figures 2 to 8. Table 3 shows the details of the activemonitoring stations as reported in Sections 3.1 and 3.2.

    Table 2 Summary of KTE Project Works Sites and AreasContract 1001 Works Sites and Areas

    Works Site A Gascoigne Road Rest Garden

    Works Site B Underground Tunnel between Yau Ma Tei Station and WylieRoad Ancillary Building

    Works Site C Wylie Road Ancillary Building

    Works Site D Underground Tunnel between Wylie Road Ancillary Buildingand Ho Man Tin Station

    Works Site E Ho Man Tin Station

    Works Site F Fat Kwong Street Playground

    Works Site G Underground Tunnel between Ho Man Tin Station andWhampoa Station

    Works Area J Finger Pier Barging Point

    Works Area K Tseung Kwan O Area 137 Magazine Site

    Contract 1002 Works Sites and Areas

    Works Site H Whampoa Station West Concourse

    Works Site I Whampoa Station East Concourse

    Works Area L Hung Lok Road Site Office

    Table 3 Summary of impact air quality and noise monitoring stationsID Monitoring StationAirCD1 Queen Elizabeth Hospital – Specialist ClinicCD2 Yee Fu BuildingCD3a No. 238 Chatham Road NorthCD4a Ka Fu Building, Whampoa EstateCD5 Fung Kei Millennium Primary SchoolCD6a Site boundary of Finger Pier adjacent to Harbourfront HorizonNoiseCN1 Alhambra BuildingCN2 Methodist CollegeCN3 Queen Elizabeth Hospital – Specialist ClinicCN4 Yee Fu BuildingCN5* Caritas Bianchi College of CareersCN6 Lok Do Building

  • 8

    ID Monitoring StationCN7 Block Y, Ki Fu Building, Whampoa EstateCN8 Block I, Lok Wah Building, Whampoa EstateCN9 Block 13, Bauhinia Mansions, Whampoa Garden Site 11CN10 Block 1, Oak Mansions, Whampoa Garden Site 5CN11 Fung Kei Millennium Primary SchoolCN12 GCEPSA Whampoa Primary School

    Note: Alternative monitoring locations were proposed in the Alternative Proposal whichwas submitted on 14 Apr 2011 and agreed by the Environmental Protection Departmenton 29 Apr 2011. The noise monitoring location at Caritas Bianchi College of Careers,which has been relocated to Tiu Keng Leng with the original premise unoccupied andinaccessible, is suspended until the premises are occupied by similar educational use.No noise monitoring will be conducted for CN5.

    2.3 Summary of EM&A Requirements

    The EM&A programme mainly requires environmental monitoring for air quality, noise,landscape and visual, water quality and waste management as specified in the EM&AManual.

    A summary of impact EM&A requirements as applicable to this EM&A Report ispresented in Table 4 below.

    Table 4 Summary of impact EM&A RequirementsParameters Descriptions Locations Monitoring

    FrequenciesDuration

    Air Quality 24-hr TSP Shown in Table 3 Once per 6 days Constructionstage

    Noise Leq(30min) Shown in Table 3 Once a weekConstructionstage

    Landscapeand visual On-Site Audit Active Works Sites Bi-weekly

    Constructionstage

    Waste On-Site Audit Active Works Sites Weekly Constructionstage

    Wastewater On-Site Audit Active Works SitesWeekly and inaccordance to thedischarge licences

    Constructionstage

    General SiteConditions

    EnvironmentalSite Inspection Active Works Sites Weekly

    Constructionstage

    Environmental Quality Performance Limits for air quality and noise are shown inAppendix B. The Event Action Plan for air quality and noise are shown in Appendix C.

  • 9

    2.4 Implementation of Environmental Mitigation Measures

    The KTE Civil Works Contractors are required to implement the mitigation measures asspecified in the EP, EIA Report and EM&A Manual. During the regular environmental siteinspections, the Contractors’ implementation of mitigation measures were inspected andreviewed. A schedule of the implementation of mitigation measures identified in the KTEEIA is given in Appendix D.

    2.5 Construction Activities in the Reporting Month

    Major construction activities carried out by the respective KTE Civil Works Contractorsduring the reporting period include:

    Contract 1001 - Works Sites and Areas

    Works Site A (Gascoigne Road Rest Garden) Cable tunnel enlargement YMT platform modification works

    Works Site B (Underground Tunnel betweenYau Ma Tei Station and Wylie Road Ancillary Building) Nil

    Works Site C (Wylie Road Ancillary Building) Shaft excavation Rock blasting

    Works Site D (Underground Tunnel betweenWylie Road Ancillary Building and Ho Man Tin Station) Nil

    Works Site E (Ho Man Tin Station) Bulk excavation Rock blasting Installation of soil nailing Shotcreting works for slope protection

    Works Site F (Fat Kwong Street Playground) Adit excavation Rock blasting

    Works Site G (Underground Tunnel betweenHo Man Tin Station and Whampoa Station) Nil

    Works Area J (Hung Hom Barging Point) Nil

    Works Area K (Tseung Kwan O Area 137 Magazine Site) Nil

  • 10

    Contract 1002 - Works Sites and Areas

    Works Site H (Whampoa Station West Concourse) Diversion of utilities and drain pipes Temporary traffic management implementation Ground instrument installation work Predrilling, grouting and pipe piling works Deck beam and traffic deck installation at Entrance B

    Works Site I (Whampoa Station East Concourse) Trial Excavation Pre-drilling works Pipe piling works Grouting works Rock drilling and shaft excavation at ventilation shaft Traffic deck installation at Shung King Street

    Works Area L (Hung Lok Road Site Office) Nil

    2.6 Construction Activities for the Coming Month

    According to the construction programme for the Civil Works Contracts, the scheduledmajor construction activities in the next reporting month are as follows:

    Contract 1001 - Works Sites and AreasWorks Site A (Gascoigne Road Rest Garden) Cable tunnel enlargement YMT platform modification works

    Works Site B (Underground Tunnel between Yau Ma Tei Station and Wylie RoadAncillary Building) Nil

    Works Site C (Wylie Road Ancillary Building) Shaft excavation Rock blasting

    Works Site D (Underground Tunnel between Wylie Road Ancillary Building and HoMan Tin Station) Nil

    Works Site E (Ho Man Tin Station) Bulk excavation Rock blasting Installation of soil nailing Shotcreting works for slope protection

    Works Site F (Fat Kwong Street Playground) Adit excavation Rock blasting

  • 11

    Works Site G (Underground Tunnel between Ho Man Tin Station and Whampoa Station) Nil

    Works Area J (Hung Hom Barging Point) Nil

    Works Area K (Tseung Kwan O Area 137 Magazine Site) Nil

    Contract 1002 - Works Sites and AreaWorks Site H (Whampoa Station West Concourse) Diversion of utilities and drain pipes Temporary traffic management implementation Ground instrument installation work Pre-drilling and pipe piling works Underpinning Man Siu Street Footbridge Installation of pumping wells, observation wells and recharge wells Grouting work Deck beam and traffic deck installation

    Works Site I (Whampoa Station East Concourse) Utilities diversion and ground instrument installation work Temporary drainage diversion along Tak On Street, Shung King Street and Tak

    Ting Street Pre-drilling works Traffic deck installation Pipe piling works continue along Tak On Street, Shun King Street and Tak Ting

    Street Rock Excavation for ventilation Shaft at Wan Hoi Street Noise panel installation for erection of noise enclosure at Wan Hoi Street

    Works Area L (Hung Lok Road Site Office) Nil

    3 IMPACT MONITORING

    3.1 Air Quality

    24-Hour TSP Levels Monitoring

    The sampling procedure follows that described in the App. B of Pt 50 in 40CFR Ch.1 (U.S.Environmental Protection Agency). TSP is sampled by drawing air through aconditioned, pre-weighed filter paper inside the high volume sampler at a controlled rate.After 24-hour sampling the filter paper with retained particles is collected and returned tothe laboratory for drying in a desiccator followed by weighing. TSP levels are calculatedfrom the ratio of the mass of particulate retained on the filter paper to the total volume ofair sampled.

  • 12

    The samplers should be properly maintained. Prior to dust monitoring commencing,appropriate checks should be made to ensure that all equipment and necessary powersupply are in good working condition.

    Calibration Requirements

    The flow rate of the high volume sampler with mass flow controller will be calibratedusing an orifice calibrator. Initial calibration (five points) will be conducted uponinstallation and prior to commissioning. Calibration will be carried out every six months.Calibration certificates are attached in Appendix E.

    To examine the construction dust levels, 24-hour TSP monitoring was undertakenaccording to the EM&A Manual. The dust monitoring locations are shown in theSection 2.2 above. Monitoring results are presented in the following table and AppendixF for graphical plot. The 24-hour TSP monitoring results in the range from 28.5 to 109.1ug/m3 recorded in the monitoring period shows that the dust levels generated by theactive construction activities were within the Action Levels with no exceedance. Thisindicates that the construction activities did not have a noticeable adverse effect on thegeneral air quality for the works areas.

    CD1 Queen Elizabeth Hospital – Special Clinic

    Date TSP(µg/m3)

    Action Level(µg/m3)

    Limit Level(µg/m3)

    Compliance(Yes /No)

    WeatherCondition

    05/09/2012 28.5 171 260 Yes Cloudy

    10/09/2012 36.7 171 260 Yes Sunny17/09/2012 89.1 171 260 Yes Sunny

    20/09/2012 78.2 171 260 Yes Rainy

    26/09/2012 45.3 171 260 Yes CloudyCD2 Yee Fu Building

    Date TSP(µg/m3)

    Action Level(µg/m3)

    Limit Level(µg/m3)

    Compliance(Yes /No)

    WeatherCondition

    05/09/2012 36.2 183 260 Yes Cloudy

    10/09/2012 37.1 183 260 Yes Sunny17/09/2012 102.9 183 260 Yes Sunny

    20/09/2012 95.8 183 260 Yes Rainy

    26/09/2012 75.8 183 260 Yes CloudyCD3a No.238 Chatham Road North

    Date TSP(µg/m3)

    Action Level(µg/m3)

    Limit Level(µg/m3)

    Compliance(Yes /No)

    WeatherCondition

    05/09/2012 32.5 192 260 Yes Cloudy10/09/2012 39.5 192 260 Yes Sunny

    17/09/2012 109.1 192 260 Yes Sunny20/09/2012 75.4 192 260 Yes Rainy

    26/09/2012 66.7 192 260 Yes Cloudy

  • 13

    CD4a Ka Fu Building, Whampoa Estate

    Date TSP(µg/m3)

    Action Level(µg/m3)

    Limit Level(µg/m3)

    Compliance(Yes /No)

    WeatherCondition

    03/09/2012 39.3 187 260 Yes Cloudy

    10/09/2012 82.8 187 260 Yes Sunny15/09/2012 102.5 187 260 Yes Sunny

    21/09/2012 54.6 187 260 Yes Rainy

    27/09/2012 89.7 187 260 Yes SunnyCD5 Fung Kei Millennium Primary School

    Date TSP(µg/m3)

    Action Level(µg/m3)

    Limit Level(µg/m3)

    Compliance(Yes /No)

    WeatherCondition

    03/09/2012 40.0 168 260 Yes Cloudy

    10/09/2012 36.2 168 260 Yes Sunny

    15/09/2012 53.8 168 260 Yes Sunny21/09/2012 53.8 168 260 Yes Rainy

    27/09/2012 81.1 168 260 Yes SunnyCD6a Site boundary of Finger Pier adjacent to Harbourfront Horizon

    Date TSP(µg/m3)

    Action Level(µg/m3)

    Limit Level(µg/m3)

    Compliance(Yes /No)

    WeatherCondition

    05/09/2012 32.3 182 260 Yes Cloudy

    10/09/2012 33.8 182 260 Yes Sunny17/09/2012 87.1 182 260 Yes Sunny

    20/09/2012 73.0 182 260 Yes Rainy

    28/09/2012 97.6 182 260 Yes Cloudy

    3.2 Noise

    B&K 2250 sound level meters which complied with the International ElectrotechnicalCommission Publication 651:1979 (Type 1) and 804:1985 (Type 1), specification asreferred to in the Technical Memoranda to the NCO were used for the construction noiseimpact monitoring. The B&K sound level meters and B&K 4231 calibrator are verifiedby the certified laboratory or manufacturer once every two years to ensure they perform tothe same level of accuracy as stated in the manufacturer’s specifications. In thisreporting period, two sound level meters with serial number 2731886 and 2741136 wereused. All relevant calibration certificates are attached in Appendix E.

    Immediately prior to and following each set of measurements at any NSR, the accuracy ofthe sound level meter was checked using an acoustic calibrator generating a known soundpressure level at a known frequency. If the calibration levels before and after themeasurement differs by more than 1.0dB the measurement shall be repeated to obtain areliable result. Periods of prolonged or repeated overloading of the sound level meterdetector were avoided by setting the meter with adequate headroom prior to commencingmeasurements. Measurements were recorded to the nearest whole dB, with values of 0.5

  • 14

    or more being rounded up.

    Impact noise monitoring of LAeq(30min) was undertaken to measure construction noiselevels in accordance with the EM&A Manual. The noise monitoring locations are shownin Section 2.2 above.

    The monitoring results corrected to the baselines in the range from 60 to 75 dBA arepresented in the following table and Appendix F for graphical plot.

    CN1- Alhambra buildingDate Time Measured

    Leq(dBA)BaselineLeq(dBA)

    CorrectedLeq(dBA)#

    LimitLevel(dBA)

    Exceedanceof LimitLevel

    ResidualLevel(dBA)##

    Exceedanceof ResidualLevel

    03/09/2012 8:30 69 71 *** 75 No - -13/09/2012 15:00 70 71 *** 75 No - -19/09/2012 9:00 69 71 *** 75 No - -25/09/2012 14:30 71 71 *** 75 No - -

    CN2- Methodist CollegeDate Time Measured

    Leq(dBA)BaselineLeq(dBA)

    CorrectedLeq(dBA)#

    LimitLevel(dBA)

    Exceedanceof LimitLevel

    ResidualLevel(dBA)##

    Exceedanceof ResidualLevel

    03/09/2012 9:00 74 75 *** 70 No 75 No13/09/2012 14:00 75 76 *** 70 No 75 No19/09/2012 9:30 73 75 *** 70 No 75 No25/09/2012 14:00 75 76 *** 70 No 75 No

    CN3- Queen Elizabeth Hospital – Specialist ClinicDate Time Measured

    Leq(dBA)BaselineLeq(dBA)

    CorrectedLeq(dBA)#

    LimitLevel(dBA)

    Exceedanceof LimitLevel

    ResidualLevel(dBA)##

    Exceedanceof ResidualLevel

    03/09/2012 9:30 68 63 66 75 No - -13/09/2012 13:00 67 64 64 75 No - -19/09/2012 10:30 65 63 60 75 No - -25/09/2012 13:00 66 64 62 75 No - -

    CN4- Yee Fu BuildingDate Time Measured

    Leq(dBA)BaselineLeq(dBA)

    CorrectedLeq(dBA)#

    LimitLevel(dBA)

    Exceedanceof LimitLevel

    ResidualLevel(dBA)##

    Exceedanceof ResidualLevel

    06/09/2012 15:30 77 70 75 75 No 77 No12/09/2012 16:30 76 70 75 75 No 77 No18/09/2012 17:30 76 70 75 75 No 77 No25/09/2012 16:30 75 70 74 75 No 77 No

    CN6- Lok Do BuildingDate Time Measured

    Leq(dBA)BaselineLeq(dBA)

    CorrectedLeq(dBA)#

    LimitLevel(dBA)

    Exceedanceof LimitLevel

    ResidualLevel(dBA)##

    Exceedanceof ResidualLevel

    06/09/2012 15:00 75 71 73 75 No - -12/09/2012 16:00 73 71 69 75 No - -18/09/2012 17:00 76 71 74 75 No - -25/09/2012 17:30 74 71 70 75 No - -

    CN7- Block Y, Ki Fu Building, Whampoa EstateDate Time Measured

    Leq(dBA)BaselineLeq(dBA)

    CorrectedLeq(dBA)#

    LimitLevel(dBA)

    Exceedanceof LimitLevel

    ResidualLevel(dBA)##

    Exceedanceof ResidualLevel

    07/09/2012 9:00 75 72 73 75 No 83 No12/09/2012 16:00 74 71 71 75 No 83 No

  • 15

    18/09/2012 9:00 73 72 69 75 No 83 No28/09/2012 13:00 73 71 68 75 No 83 No

    CN8- Block I, Lok Wah Building, Whampoa GardenDate Time Measured

    Leq(dBA)BaselineLeq(dBA)

    CorrectedLeq(dBA)#

    LimitLevel(dBA)

    Exceedanceof LimitLevel

    ResidualLevel(dBA)##

    Exceedanceof ResidualLevel

    07/09/2012 9:30 74 70 72 75 No 81 No12/09/2012 14:30 76 69 75 75 No 81 No18/09/2012 9:30 75 70 74 75 No 81 No28/09/2012 11:00 69 70 *** 75 No 81 No

    CN9- Block 13, Bauhinia Mansions, Whampoa Garden Site 11Date Time Measured

    Leq(dBA)BaselineLeq(dBA)

    CorrectedLeq(dBA)#

    LimitLevel(dBA)

    Exceedanceof LimitLevel

    ResidualLevel(dBA)##

    Exceedanceof ResidualLevel

    07/09/2012 10:00 71 69 66 75 No 79 No12/09/2012 13:30 77 70 75 75 No 79 No18/09/2012 10:00 71 69 66 75 No 79 No28/09/2012 13:30 73 70 70 75 No 79 No

    CN10- Block 1, Oak Mansions, Whampoa Garden Site 5Date Time Measured

    Leq(dBA)BaselineLeq(dBA)

    CorrectedLeq(dBA)#

    LimitLevel(dBA)

    Exceedanceof LimitLevel

    ResidualLevel(dBA)##

    Exceedanceof ResidualLevel

    07/09/2012 10:30 71 66 70 75 No 82 No12/09/2012 14:00 70 69 66 75 No 82 No18/09/2012 10:30 74 66 73 75 No 82 No28/09/2012 11:30 76 66 75 75 No 82 No

    CN11- Fung Kei Millennium Primary SchoolDate Time Measured

    Leq(dBA)BaselineLeq(dBA)

    CorrectedLeq(dBA)#

    LimitLevel(dBA)

    Exceedanceof LimitLevel

    ResidualLevel(dBA)##

    Exceedanceof ResidualLevel

    07/09/2012 11:30 68 64 65 70 No 78 No12/09/2012 15:00 70 66 68 70 No 78 No18/09/2012 12:00 63 64 *** 70 No 78 No28/09/2012 10:30 68 66 65 70 No 78 No

    CN12- GCEPSA Whampoa Primary SchoolDate Time Measured

    Leq(dBA)BaselineLeq(dBA)

    CorrectedLeq(dBA)#

    LimitLevel(dBA)

    Exceedanceof LimitLevel

    ResidualLevel(dBA)##

    Exceedanceof ResidualLevel

    07/09/2012 11:00 71 65 70 70 No 76 No12/09/2012 16:30 71 64 70 70 No 76 No18/09/2012 11:00 67 65 62 70 No 76 No28/09/2012 9:30 70 64 69 70 No 76 No

    Notes:

    It is noted that all noise monitoring were not undergone in the raining period. The weather condition is fine and with wind speed < 2m/s.

    Decimal point of measured and baseline monitoring data is used to calculate the corrected noise level.

    # The Measured Leq is corrected against the corresponding Baseline Level.

    *** Refers to the Measured Leq is lower than the Baseline Level.

    ## Residual Level refers to the maximum predicted construction noise levels in the EIA report when residual impact is anticipated.

    3.3 Action taken in Event of Exceedance

    No exceedance on noise and dust monitoring was recorded. Therefore, no action shall betaken.

    4 LANDSCAPE AND VISUAL

  • 16

    4.1 Monitoring Requirements

    Monitoring of the implementation of the landscape and visual mitigation measures duringconstruction phase was conducted in accordance with the requirements as stipulated inthe EM&A Manual.

    The landscape and visual monitoring and audit will be conducted once every two weeksthroughout the construction stage.

    4.2 Audit Results

    Monitoring and audit was undertaken in accordance with the EM&A Manual.

    Tree Felling at Contract 1001 Works Sites / Areas

    No tree related to KTE project was felled during this reporting month.

    Tree Felling at Contract 1002 Works Sites / Areas

    No tree related to KTE project was felled during the reporting month.

    Tree Transplantation in this reporting period for Contract 1001

    No tree related to KTE project was transplanted during the reporting month.

    Tree Transplantation in this reporting period for Contract 1002

    No tree related to KTE project was transplanted during the reporting month.

    Bi-weekly inspection

    The Registered Landscape Architect of Environmental Team or his representativesconducted inspections and audits and the tree protection works being planned andimplemented by the respective contractors of Contract 1001 and 1002 were in progress.No non-conformance was identified in the reporting period.

    4.3 Action Taken in Event of Non-Conformance

    No actions on landscape and visual were required to be taken in this reporting period.

    5 WASTE MANAGEMENT

    Mitigation measures on waste management have been implemented in accordance withthe requirements of the EM&A Manual. Suitable C&D materials were reused on-site orat other projects such as Andersen Road Quarry while the remaining C&D materials andnon-inert wastes were disposed at the public filling reception facilities and the landfillsrespectively. The quantities disposed in the reporting period are summarized in thefollowing table:

  • 17

    Amount of Construction Wastes DisposedReporting Period Inert C&D

    Materials toPublic Fill(m3)

    Inert C&DMaterialsReused (m3)

    Non-inertWaste toLandfill (m3)

    Chemical Wasteto designatedtreatment facility(trips)

    Contract 1001June – July 2011 588 0 66 0August 2011 78 0 156 0September 2011 960 0 78 0October 2011 4542 0 54 0November 2011 13842 2676 114 0December 2011 8680 22092 246 0January 2012 1882 43572 192 0February 2012 2365 37874 174 0

    March 2012 4331 47353 84 1April 2012 3597 44308 108 0May 2012 1102 31228 108 0June 2012 2308 33080 240 0July 2012 1623 27177 108 0August 2012 2570 36569 108 0September 2012 2730 33111 90 0Subtotal 51199 359040 1926 1

    Contract 1002June – July 2011 534 0 0 0August 2011 602 0 5 0

    September 2011 283 0 0 0

    October 2011 854 0 0 0November 2011 663 0 2 0December 2011 101 0 2 0

    January 2012 50 0 18 0February 2012 443 10 12 1March 2012 532 0 30 0April 2012 488 5 36 0May 2012 1081 18 18 1

    June 2012 1048 5 6 0July 2012 1493 5 18 0August 2012 1496 5 12 1September 2012 2784 5 24 0Subtotal 12452 53 183 3

    Overall Total 63651 359093 2109 4

  • 18

    6 WATER QUALITY

    Monitoring of the implementation of the water quality mitigation measures duringconstruction phase was conducted in accordance with the requirements as stipulated inthe EM&A Manual.

    Weekly site inspection will be conducted throughout the construction stage covering theentire project site areas to ensure the recommended mitigation measures are properlyimplemented.

    In the reporting period, the water quality mitigation measures were implemented inaccordance with the requirements as stipulated in the EM&A Manual and found in anacceptable manner.

    Water sample tests were conducted for Works Sites C and F. Analytical results will bereported in accordance to the WPCO licenses.

    7 RECORD OF ENVIRONMENTAL COMPLAINTS

    One environmental complaint was referred from EPD and it was classified as invalidafter investigation by EPD, ET team and the Contractor. On 28 September 2012, EPDreferred a public complaint on dark smoke emission from generator from MTRconstruction site at Chatham Road North. The inspection conducted by EPD did notreveal any emission of dark smoke from generator. Nevertheless, MTR has passed thecomplaint case to contractor for attention.

  • 19

    Invalid Complaint Valid ComplaintReportingPeriod Frequency Nature Status Frequency Nature StatusJune 2011 0 N/A N/A 0 N/A N/A

    July 2011 0 N/A N/A 0 N/A N/A

    August 2011 0 N/A N/A 0 N/A N/A

    September 2011 1 Noise Closed 0 N/A N/A

    October 2011 0 N/A N/A 0 N/A N/A

    November 2011 0 N/A N/A 1 Dust Closed

    December 2011 1 Water Closed 0 N/A N/A

    January 2012 0 N/A N/A 0 N/A N/A

    February 2012 1 Noise Closed 1 Noise Closed

    March 2012 2 Noise & Dust Closed 2 Noise Closed

    April 2012 1 N/A N/A 1 Noise Closed

    May 2012 1 Water Closed 0 N/A N/A

    June 2012 3 Noise & Dust Closed 3 Noise Closed

    July 2012 0 N/A N/A 0 N/A N/A

    August 2012 2 Noise & Odor Closed 0 N/A N/A

    September 2012 1 Air Closed 0 N/A N/A

    Cumulative 13 N/A N/A 8 N/A N/A

    8 RECORD OF NON-COMPLIANCES

    There was no non-compliance identified in the reporting period.

    9 NOTIFICATION OF SUMMONS AND SUCCESSFUL PROSECUTIONS

    No summon or prosecution related to environmental issue was recorded in the reportingperiod. A summary of environmental prosecution since commencement of constructionis shown below:-

    Reporting Period Frequency Cumulative Nature StatusJune – December 2011 0 0 N/A N/AJanuary – June 2012 0 0 N/A N/AJuly 2012 0 0 N/A N/AAugust 2012 0 0 N/A N/ASeptember 2012 0 0 N/A N/ACumulative 0 0 N/A N/A

    10 STATUS OF STATUTORY SUBMISSIONS

    10.1 Submissions required under Environmental Permit

    A summary of the status of submissions required under the KTE Environmental Permitas of 30 September 2012 is shown below:

  • 20

    EP-399/2010/A Part CClause No.

    Description Status

    1.12 1 Notification of commencement of construction Submitted on 17 May 20112.1 2 Establishment of ET with ET Leader Submitted on 1 April 2011

    2.1 3 Establishment of Registered Landscape Architect Submitted on 14 April 2011

    2.2 4 Employment of IEC Submitted on 1 April 2011and 7 July 2011

    2.3 5 Notification of the management organization of main constructioncompanies and/or any form of JV

    Submitted on 19 May 2011

    2.4 6 Layout drawings with explanatory statement, showing Projectboundary, alignment and associated work areas and works siteslocations

    Submitted on 10 June 2011and 13 July 2011

    2.5 7 Notification of setting up hotline to service complaints, comments,suggestions or requests for information

    Submitted on 12 May 2011

    3.7 8 Report any contamination hotspot(s) identified from thereconnaissance site visit to the kerosene store at Chung Hau Street

    Submitted on 25 July 2011

    5.3 9 Submission of Baseline Monitoring Report Submitted on 4 May 2011 and8 July 2011

    6.2 10 Notification of Internet address to place EM&A data Submitted on 1 August 20115.4 11 Monitoring Report for July 2011 Submitted on 12 August 2011

    5.4 12 Monitoring Report for August 2011 Submitted on 15 September2011

    5.4 13 Monitoring Report for September 2011 Submitted on 17 October2011

    4.1 14 Review Plan for Operational Groundborne Noise Submitted on 28 October2011

    5.4 15 Monitoring Report for October 2011 Submitted on 14 November2011

    5.4 16 Monitoring Report for November 2011 Submitted on 14 December2011

    5.4 17 Monitoring Report for December 2011 Submitted on 16 January2012

    5.4 18 Monitoring Report for January 2012 Submitted on 14 February2012

    4.1 19 Review Plan for Operational Groundborne Noise Submitted on 29 February2012

    5.4 20 Monitoring Report for February 2012 Submitted on 14 March 2012

    5.4 21 Monitoring Report for March 2012 Submitted on 17 April 2012

    4.1 22 Review Plan for Operational Groundborne Noise Submitted on 27 April 2012

    5.4 23 Monitoring Report for April 2012 Submitted on 15 May 2012

    3.7 24 Further Inspection to the Kerosene Store Submitted on 8 Jun 2012

    5.4 25 Monitoring Report for May 2012 Submitted on 14 Jun 2012

    2.4 26 Update of Layout drawings with explanatory statement, showingProject boundary, alignment and associated work areas and workssites locations

    Submitted on 13 Jul 2012

    5.4 27 Monitoring Report for Jun 2012 Submitted on 16 Jul 2012

    5.4 28 Monitoring Report for Jul 2012 Submitted on 14 Aug 2012

    4.9 29 Landscape and Visual Plan Part 1: Tseung Kwan O Area 137Magazine Site

    Submitted on 27 Aug 2012

    5.4 30 Monitoring Report for Aug 2012 Submitted on 14 Sep 2012

  • 21

    10.2 Statutory Permits and Licenses

    A summary of the status of all relevant environmental permits and licenses as of 30September 2012 is shown below:

    Description License/ Permit Reference Issue Date Expired Date

    Environmental PermitEnvironmental Permit for KwunTong Line Extension Project(EP-399/2010)

    (EP-399/2010) (supersededby EP-399/2010/A)

    27 September 2010 NA

    Variation of EnvironmentalPermit for Kwun Tong LineExtension Project

    (EP-399/2010/A) )(superseded byEP-399/2010/B)

    1 December 2010 NA

    Variation of EnvironmentalPermit for Kwun Tong LineExtension Project

    (EP-399/2010/B) 7 June 2012 NA

    Contract 1001Wastewater Discharge License WT00009504-2011 (Works

    Site C),

    WT00009582-2011 (WorksSite F),

    WT00009608-2011 (WorksSite A),

    WT00009611-2011 (WorksArea J)

    WT00012298-2012 (WorksSite E)

    14 July 2011

    27 July 2011

    1 August 2011

    9 August 2011

    19 April 2012

    31 July 2016

    31 July 2016

    31 August 2016

    31 August 2016

    31 July 2016

    Registration as a ChemicalWaste Producer

    5213-226-N2206-22(Works Site A)

    5213-226-N2206-23(Works Site C)

    5213-237-N2454-04(Works Site E)

    5213-243-N2454-03(Works Site F)

    1 August 2011

    1 August 2011

    11 August 2011

    11 August 2011

    NA

    NA

    NA

    NA

    Disposal of Construction Waste Billing Account no.7012910 activated

    26 May 2011 NA

    Construction Noise Permit GW-RE0461-12(Works Site A)

    GW-RE0799-12(Works Site C)

    GW-RE0786-12(Works Site E)

    GW-RE0531-12(Works Site F)

    18 June 2012

    27 September 2012

    19 September 2012

    28 June 2012

    Valid from 19 Jun2012 to 30 Nov 2012

    Valid from 29 Sep2012 to 28 Feb 2013

    Valid from 24 Sep2012 to 16 Mar 2013

    Valid from 30 Jun2012 to 30 Nov 2012

  • 22

    Contract 1002Wastewater Discharge License WT00009415-2011 (Site

    office)

    WT00010827-2011

    11 July 2011

    8 December 2011

    30 Sep2016

    31 Oct 2016

    Registration as a ChemicalWaste Producer

    Waste Producer No.5213-245-C3672-01

    16 June 2011 NA

    Disposal of Construction Waste Billing Account No.7012934 activated

    31 May 2011 NA

    Construction Noise Permit GW-RE0706-12Tak On Street betweenShung King Street and TakTing Street

    24 August 2012 Valid from 30August 2012 to 29September 2012

    11 SITE INSPECTIONS

    11.1 Observations

    Regular site inspections led by the Engineer’s Representative and anticipated by ET andrespective Contractors were undertaken in accordance with the EM&A Manual in thereporting period. The contractors' performance on environmental matters were assessedand found in an acceptable manner. The inspection findings and the associatedrecommendations on improvement to the environmental protection and pollution controlworks were raised to the contractors for reference and/ or action.

    Observations against the implementation of the mitigation measures recommended in theEP/EIA are summarized as follows:

    Item Description Follow-upStatus

    Contract 10011 The contractor is reminded to clean the oil stain left on the ground

    at Works Site C.Completed

    2 The contractor was reminded to carry out vehicle washing at theenclosure entrance at Works Site C.

    Ongoing

    Contract 10021 Surface runoff should be collected and discharged properly to

    prevent flowing into public areaOngoing

    2 The contractor should cover the air compressor by acoustic blanketentirely according to EP’s requirement.

    Completed

    3 Drip trap should be provided for chemical containers. Completed

    The respective contractors have followed most of concerned items raised during theinspections for rectification in a responsible manner.

    11.2 Other Notable Events

    IEC Site Inspections

    The IEC conducted site inspections for Works Areas on 18 and 12 September 2012 forContract 1001 and 1002 respectively. Some observations including improving effluent

  • 23

    control measures, enhancing noise and dust suppression measures were noted during thesite inspections and the respective Contractors had followed up the issues as identified inthe site inspections in a responsible manner.

    EPD Inspection

    EPD conducted inspection for contract 1002 on 14 September 2012 for the noisemitigation measures and site water discharge condition. EPD reminded the contractor tospeed up the installation of noise enclosure at Wan Hoi Street and provide sufficient sitewater treatment facilities if required.

    12 FUTURE KEY ISSUES

    12.1 Key Issues for the Coming Month

    Future key issues envisaged in the coming month include the followings: Noise impact from operating equipment from site construction activities, e.g. pile/

    sheet piling and rock breaking works; Fugitive dust impact from cement mixing activities and rock breaking works; Effluent discharge generated from various construction works; Tree protection.

    12.2 Effectiveness and Efficiency of Mitigation Measures

    Based on the environmental monitoring results of the reporting period, the effectivenessand efficiency of the mitigation measures implemented were found to be satisfactory. Therespective contractors were reminded to carry out their future construction activities tocomply with the requirements of the EP and the relevant contract requirements.

    13 CONCLUSIONS

    The Report presents the results of EM&A works and the impact monitoring for theconstruction works undertaken during the period of September 2012. The majorconstruction activities in the reporting period included utility and drainage diversions,temporary road & traffic diversion, piling works, bulk excavation, shaft and aditexcavation, soil nailing and ground improvement works.

    No exceedance on noise and dust monitoring was recorded.

    One invalid environmental complaints on dark smoke emission was referred by EPD andno valid complaint was received.

    No notification of summon and prosecution were received in the reporting period.

    Regular site inspections led by the Engineer’s Representative and anticipated by therepresentatives from ET and the respective Contractors’ Team were conducted on aweekly basis to monitor the implementation of environmental pollution control andmitigation measures for the Project. No non-conformance to the environmentalrequirements was identified by the Environmental Team in the reporting period. Theperformances of the respective contractors on site environmental management werefound in a responsible manner in this reporting period.

  • 24

    It is concluded from the environmental monitoring and audit works for the Kwun TongLine Extension Project were undertaken in a responsible manner. The environmentalprotection and pollution control measures provided by respective contractors of Contract1001 and 1002 were generally acceptable apart from some minor irregularities whichwere rectified timely by the respective civil works contractors.

  • Appendix A

    Figures

  • Figure 1. KTE Project Works Area

    Figure 2. Location of Dust Monitoring Stations (CD1)

    Works Site A

    Works Site D(Underground Tunnel)

    Works Site B(Underground Tunnel)

    Works Site C

  • Figure 3. Location of Dust Monitoring Stations (CD2 and CD3a)

    Figure 4. Location of Dust Monitoring Stations (CD4a and CD5)

    Works Site D(Underground Tunnel)

    Works Site E

    Works Site F

    Works Site G(Underground Tunnel)

    Works Site H

    Works Site I

    Works Site G(Underground Tunnel)

  • Figure 5. Location of Dust Monitoring Stations (CD6a)

    Figure 6. Location of Noise Monitoring Stations (CN1, CN2 and CN3)

    Works Area J

    Works Site A

    Works Site B(Underground Tunnel)

    Works Site C

    Works Site D(Underground Tunnel)

  • Figure 7. Location of Noise Monitoring Stations (CN4 and CN6)

    Figure 8. Location of Noise Monitoring Stations (CN7 to CN12)

    Works Site D(Underground Tunnel)

    Works Site E

    Works Site F

    Works Site G(Underground Tunnel)

    Works Site G(Underground Tunnel)

    Works Site H

    Works Site I

  • Figure 9. Location of Tseung Kwan O Area 137 Magazine Site

    Figure 10. Location of Hung Lok Road Site Office

    Works Area K

    Works Area L

  • Appendix B

    Environmental Quality Performance Limits

  • Action and Limit Levels for 24-hour TSP

    Monitoring Station Action Level (µg/m3) Limit Level (µg/m3)CD1 171 260CD2 183 260CD3a 192 260CD4a 187 260CD5 168 260CD6a 182 260

    Action and Limit Levels for 1-hour TSP for Complaint Handling

    Monitoring Station Action Level (µg/m3) Limit Level (µg/m3)CD1 310 500CD2 301 500CD3a 311 500CD4a 303 500CD5 309 500CD6a 316 500

    Action and Limit Levels for Construction Noise

    Time Period Action Level Limit Level (dB(A)),Leq(30min)

    0700-1900 hr on normalweekdays

    When one documented complaintis received

    75*

    * Limit for school is 70 dB(A) and 65 dB(A) during school examination periods.

  • Appendix C

    Event Action Plans

  • Appendix D

    Implementation of Environmental Mitigation Measures

  • Kwun Tong Line ExtensionConsultancy Agreement No. NEX/2207Environmental Impact Assessment (EIA) Study for KTEEM&A Manual

    June 2012 Page 1

    Appendix 1.1 Implementation Schedule for Environmental Mitigation MeasuresImplementation

    StagesEIAReference

    EM&AManualReference

    Environmental Protection Measures Objectives of Measuresand Main Concern toAddress

    Location ImplementationAgent

    RelevantStandard orRequirement D C O

    MaintenanceAgent Implementation

    status

    Miscellaneous3.4.2.1 WSD Fresh Water Service Reservoir

    Undertake an independent study of theeffects of the drill and blast tunnelling on thereservoir to the satisfaction of WSD.

    Ensure stability of thereservoir duringconstruction

    WSD Fresh WaterService Reservoir

    MTR Corporation/Main Contractor -

    n/a

    To beimplemented asper construction

    programmeLandscape and Visual5.12.1.2 Reuse of Existing Topsoil

    Existing topsoil shall be re-used for newplanting areas within the project. TheContractor’s construction plan shall considerusing the soil removed for backfilling.Suitable storage ground, gathering groundand mixing ground shall be set up ifnecessary.

    Conservation of valuablenatural landscaperesources

    Gascoigne RoadRest Garden,Hill slopes aboveChatham RoadNorth,Roadside plantersat Hung HomRoad

    MTR Corporation/Main Contractor

    EIArecommendation

    MTRCorporation /

    LandsD, LCSD/ HyD

    Implemented

    5.12.1.2 Tree TransplantationTransplantation is proposed for a number oftrees which are generally able to providehigh amenity value and are likely to survivethe transplantation process.

    Conservation of valuablenatural landscaperesources

    Gascoigne RoadRest Garden,HOM Station,Yan Fung StreetRest GardenSlopessurrounding FatKwong StreetPlayground,WHA Station

    MTR Corporation/Main Contractor/Detailed DesignConsultant

    Alltransplantationwill be carriedout inaccordancewith ETWBTCW No.3/2006.

    MTRCorporation /

    LandsD / HyD /LCSD / AFCD

    Implemented

    5.12.1.2 Erection of Decorative HoardingsTemporary decorative screen hoardings shallbe designed and erected to be compatiblewith the existing urban context, eitherbrightly and imaginatively or with visuallyunobtrusive design and colours where moreappropriate. All works sites and works areasshall be surrounded by such hoardings,which shall be removed at projectcompletion.

    Visual screening of workssite during construction

    All works sitesand TemporaryWorks Areas

    MTR Corporation/Main Contractor/Detailed DesignConsultant

    EIArecommendation

    Contractor Implemented

    5.12.1.2 Control of night-time lighting glareAll security floodlights for construction sitesand temporary works areas shall be equippedwith adjustable shield, frosted diffusers andreflective covers, and be carefully controlled

    Restricting light pollutionto nearby receivers

    All works sitesand TemporaryWorks Areas

    Main Contractor EIArecommendation

    Contractor

    To beimplemented asper construction

    programme

  • Kwun Tong Line ExtensionConsultancy Agreement No. NEX/2207Environmental Impact Assessment (EIA) Study for KTEEM&A Manual

    June 2012 Page 2

    ImplementationStages

    EIAReference

    EM&AManualReference

    Environmental Protection Measures Objectives of Measuresand Main Concern toAddress

    Location ImplementationAgent

    RelevantStandard orRequirement D C O

    MaintenanceAgent Implementation

    status

    to minimize light pollution and night-timeglare to nearby receivers.

    5.12.1.2 Re-provision of Public Open SpacesEvery effort should be made to minimise useof public open spaces, however if affected bythe Project they shall be re-provisioned to anequal or improved standard at completion ofthe project. Sensitive design andreinstatement of the affected Public OpenSpaces (Gascoigne Road Rest Garden, YanFung Street Rest Garden, Fat Kwong StreetPlayground) shall be made, incorporatingreplacement facilities to those currentlyprovided and using materials of qualitysuitable for long term use and acceptable tothe relevant government departmentsincluding LCSD and PlanD, who shall beconsulted on the design of the reinstatedpublic open spaces at an early stage of thedesign process.

    Replacement of loss ofresources

    Gascoigne RoadRest Garden,Yan Fung StreetRest Garden,Fat Kwong StreetPlayground,

    MTR Corporation/ Main Contractor/Detailed DesignConsultant

    EIArecommendation

    LCSD

    To beimplemented asper construction

    programme

    5.12.1.2 Compensatory Tree PlantingSuitable land pockets within the project areawill be used for the implementation ofcompensatory mitigation to offset the netloss of key landscape resources and improvevisual amenity.A compensatory tree planting proposalincluding locations of tree compensation willbe submitted separately to seek relevantgovernment department’s approval, inaccordance with ETWB TCW No. 3/2006.

    Replacement of loss ofresources andEnhancement of visualamenity

    Gascoigne RoadRest Garden,Yan Fung StreetRest Garden,Fat Kwong StreetPlayground,WAB,HOM StationWHA Station

    MTR Corporation/ Main Contractor/Detailed DesignConsultant

    ETWB TCWNo. 3/2006.WBTC 7/2002

    MTRCorporation /

    LandsD/HyD/LCSD/AFCD

    To beimplemented asper construction

    programme

    5.12.1.2 Horizontal and Slope Greening

    Shotcreting of cut rock slopes shall beavoided and greening applications employedthroughout the project.

    At HOM Station the backfill slopes shall behydroseeded and native seedling treesplanted. The station roof shall be temporarilygreened should there be no further on-sitedevelopment within 1 year of completion of

    Mitigation of loss ofresources andEnhancement of visualamenity

    Gascoigne RoadRest Garden,Yan Fung StreetRest Garden,Fat Kwong StreetPlayground,WAB,HOM Station

    MTR Corporation/Main Contractor/Detailed DesignConsultant

    WBTC 25/93WBTC 17/2000

    MTRCorporation /

    LandsD

    To beimplemented asper construction

    programme

  • Kwun Tong Line ExtensionConsultancy Agreement No. NEX/2207Environmental Impact Assessment (EIA) Study for KTEEM&A Manual

    June 2012 Page 3

    ImplementationStages

    EIAReference

    EM&AManualReference

    Environmental Protection Measures Objectives of Measuresand Main Concern toAddress

    Location ImplementationAgent

    RelevantStandard orRequirement D C O

    MaintenanceAgent Implementation

    status

    KTE, until permanent measures areundertaken under the proposed propertydevelopment stage.

    Parapets at WAB and HOM Station shall beprovided with internal permanent planterboxes.

    The roof at WAB shall be greened toimprove visual amelioration fromsurrounding high level viewers

    Station entrances at HOM and WHA shallutilise shrub planting areas to providelocalised greening

    WHA Station

    5.12.1.2 PlantingVertical greening / climbers shall be appliedto all above ground structures againstexposed walls where appropriate. Furthersuch localised planting systems shall beinstigated subject to technical operationaland maintenance constraints.

    Mitigation of loss ofresources andEnhancement of visualamenity

    WAB,HOM Station

    MTR Corporation/Main Contractor/Detailed DesignConsultant

    EIArecommendation

    MTRCorporation

    To beimplemented asper construction

    programme

    5.12.1.2 Architectural Design Aesthetics for the WABat Club de RecreioThe emergency access and ventilationbuilding shall be designed in a way so as toensure the form, material and surfacedetailing of this structure can fitsympathetically into the local context. Theform shall consider the Cultural Heritage ofthe Club de Recreio site as well as otherproximate buildings. The structure shallincorporate vertical greening / climbers.

    Enhancement of visualamenity

    WAB MTR Corporation/Main Contractor/Detailed DesignConsultant

    EIArecommendation

    MTRCorporation

    To beimplemented asper construction

    programme

    5.12.1.2 Architectural Design Aesthetics forAbove-Ground Structures at HOM StationAll station entrances, vent shafts, chillers andother above-ground structures shall bedesigned in accordance with the standardisedMTR Corporation architectural theme for theKTE and other current rail projects. Howeverspecific attention shall be undertaken toensure the form, material and surfacedetailing of these structures is considered to

    Enhancement of visualamenity

    HOM Station MTR Corporation/Main Contractor/Detailed DesignConsultant

    EIArecommendation

    MTRCorporation

    To beimplemented asper construction

    programme

  • Kwun Tong Line ExtensionConsultancy Agreement No. NEX/2207Environmental Impact Assessment (EIA) Study for KTEEM&A Manual

    June 2012 Page 4

    ImplementationStages

    EIAReference

    EM&AManualReference

    Environmental Protection Measures Objectives of Measuresand Main Concern toAddress

    Location ImplementationAgent

    RelevantStandard orRequirement D C O

    MaintenanceAgent Implementation

    status

    fit into the local context in terms of thearchitectural character of the site.

    5.12.1.2 Architectural Design Aesthetics forAbove-Ground Structures at WHA StationThese shall be designed in accordance withthe standardised MTR Corporationarchitectural theme for the KTE and othercurrent rail projects. However specificattention shall be undertaken to ensure theform, material and surface detailing of thesestructures is considered to fit into the localcontext in terms of the architecturalcharacter of the site.

    Enhancement of visualamenity

    WHA Station MTR Corporation/Main Contractor/Detailed DesignConsultant

    EIArecommendation

    MTRCorporation

    To beimplemented asper construction

    programme

    Air QualityS.6.7.1.7 &S.6.9.2.3

    Cut-and-Cover areas in the vicinity of aditsand shafts (if applicable):- Heavy construction activities and wind

    erosion at the cut-and-cover areas,active areas for heavy constructionactivities:- Watering every hour at exposed soil.

    Trucks for transportation of materials:- Wheel washing facilities should be

    provided at all site exits. Vehiclesshould be washed before leavingworks sites. Spoil on trucks shouldbe well covered before leaving workssites to minimise the generation ofdusty materials.

    - Haul roads within works sites shouldbe paved and water spraying wouldbe provided to keep the wetcondition.

    To minimise dust impacts All relevant workssites

    MTR Corporation/Main Contractor/Detailed DesignConsultant

    Air PollutionControlOrdinance

    Implemented

    S.6.7.1.7&S.6.9.2.3

    Barging point at Hung Hom Finger Pier: For haul roads within the area of

    barging point for transportation of spoil,all road surfaces should be paved andhourly water spraying should beprovided to keep the wet condition asfar as practical.

    The spoil unloading process should be

    To minimise dust impacts Barging Point atHung Hom FingerPier

    MTR Corporation/MainContractor/Detailed DesignConsultant

    Air PollutionControlOrdinance

    Implemented

  • Kwun Tong Line ExtensionConsultancy Agreement No. NEX/2207Environmental Impact Assessment (EIA) Study for KTEEM&A Manual

    June 2012 Page 5

    ImplementationStages

    EIAReference

    EM&AManualReference

    Environmental Protection Measures Objectives of Measuresand Main Concern toAddress

    Location ImplementationAgent

    RelevantStandard orRequirement D C O

    MaintenanceAgent Implementation

    status

    undertaken within an enclosed tippinghall. Water spraying and 3-sided screenwith top should be provided at thedischarge point for dust suppression.

    Vehicle wheel washing facilities shouldbe provided at the exits of the bargingpoint.

    S.6.7.1.5&S. 6.7.1.8

    Rock crushing equipment at HOM Stationand barging point at Hung Hom Finger Pierif operated during construction: A dust enclosure with fabric

    baghouse/cartridge filter type dustextraction and collection system orequivalent system with 99% or moredust removal efficiency for the rockcrushing equipment, haul road andunloading location; and

    Watering of paved roads within the areaof the rock crushing facility as good sitepractice.

    To minimise dust impacts Rock crushingequipment atHOM Station andBarging Point atHung Hom FingerPier

    MTR Corporation/MainContractor/Detailed DesignConsultant

    Air PollutionControlOrdinance

    To beimplemented asper constructionprogramme

    S.6.7.1.5&S.6.9.2.2

    Tarpaulin covers would be provided on wiremesh covered steel cages to prevent dustemission during open blasting at HOMStation;

    To minimise dust impacts Open blasting areaat HOM Station

    MTR Corporation/MainContractor/Detailed DesignConsultant

    EIArecommendation

    To beimplemented asper constructionprogramme

    S.6.9.2.4 Dust suppression measures stipulated in theAir Pollution Control (Construction Dust)Regulation and good site practices: Use of regular watering, to reduce dust

    emissions from exposed site surfacesand unpaved roads, particularly duringdry weather.

    Use of frequent watering for particularlydusty construction areas and areas closeto ASRs.

    Side enclosure and covering of anyaggregate or dusty material storage pilesto reduce emissions. Where this is not

    To minimise dust impacts All works sites MTRCorporation/MainContractor/Detailed DesignConsultant

    Air PollutionControlOrdinance

    Implemented

  • Kwun Tong Line ExtensionConsultancy Agreement No. NEX/2207Environmental Impact Assessment (EIA) Study for KTEEM&A Manual

    June 2012 Page 6

    ImplementationStages

    EIAReference

    EM&AManualReference

    Environmental Protection Measures Objectives of Measuresand Main Concern toAddress

    Location ImplementationAgent

    RelevantStandard orRequirement D C O

    MaintenanceAgent Implementation

    status

    practicable owing to frequent usage,watering should be applied to aggregatefines.

    Open temporary stockpiles should beavoided or covered. Prevent placingdusty material storage piles near ASRs.

    Tarpaulin covering of all dusty vehicleloads transported to, from and betweensite locations.

    Establishment and use of vehicle wheeland body washing facilities at the exitpoints of the site.

    Imposition of speed controls forvehicles on unpaved site roads. 8kmper hour is the recommended limit.

    Routing of vehicles and positioning ofconstruction plant should be at themaximum possible distance from ASRs.

    Every stock of more than 20 bags ofcement or dry pulverised fuel ash (PFA)should be covered entirely byimpervious sheeting or placed in an areasheltered on the top and the 3 sides.

    Loading, unloading, transfer, handlingor storage of large amount of cement ordry PFA should be carried out in atotally enclosed system or facility, andany vent or exhaust should be fitted withan effective fabric filter or equivalent airpollution control system.

    Covering or enclosing any conveyor beltsystems will generally be fully enclosed,depending on the design, materialschosen, and dimension of the conveyorsystem.

    Air-borne NoiseS.7.9.2.6 The following good site practices should be

    implemented: Only well-maintained plant should be

    operated on-site and plants should beserviced regularly during theconstruction period;

    Mobile plant, if any, should be sited as

    To minimise air-bornenoise impacts

    All works sites MTR Corporation/Main Contractor

    Noise ControlOrdinance

    Implemented

  • Kwun Tong Line ExtensionConsultancy Agreement No. NEX/2207Environmental Impact Assessment (EIA) Study for KTEEM&A Manual

    June 2012 Page 7

    ImplementationStages

    EIAReference

    EM&AManualReference

    Environmental Protection Measures Objectives of Measuresand Main Concern toAddress

    Location ImplementationAgent

    RelevantStandard orRequirement D C O

    MaintenanceAgent Implementation

    status

    far from NSRs as possible; Plant known to emit noise strongly in

    one direction should, wherever possible,be properly orientated so that the noiseis directed away from the nearby NSRs;

    Use of site hoarding as a noise barrier toscreen noise at low level NSRs;

    Machines and plant that may be inintermittent use should be shut downbetween works periods or should bethrottled down to a minimum; and

    Any material stockpiles and otherstructures should be effectively utilised,wherever practicable, to screen the noisefrom on-site construction activities.

    S.7.9.2.1 The following quiet PME should be used: Air compressor Asphalt Paver Breaker Bulldozer Concrete lorry mixer Concrete Pump / Grout Pump Crane Cutter, circular, steel (electric) Dump Truck Backhoe Generator Vibrating Poker, hand-held (electric) Rock Drill Roller, vibratory Scraper Water pump (electric)

    To minimise air-bornenoise impacts

    All relevant workssites

    MTR Corporation/Main Contractor

    Noise ControlOrdinance

    Implemented

  • Kwun Tong Line ExtensionConsultancy Agreement No. NEX/2207Environmental Impact Assessment (EIA) Study for KTEEM&A Manual

    June 2012 Page 8

    ImplementationStages

    EIAReference

    EM&AManualReference

    Environmental Protection Measures Objectives of Measuresand Main Concern toAddress

    Location ImplementationAgent

    RelevantStandard orRequirement D C O

    MaintenanceAgent Implementation

    status

    S.7.9.2.4 Movable or fixed noise barrier should be usedfor the following PME where practicable: Wheeled Excavator/Loader Crane Hydraulic Breaker Scraper Breaker, hand-held Compactor, vibratory Drill, percussive, hand-held (electric) Concrete pump Circular Saw, bench mounted Truck Bar bender and cutter (electric) Conveyor belt Generator, Super Silenced Grout Pump Saw, wire Water Pump, Submersible (Electric) Hydraulic Jack with Pump

    To minimise air-bornenoise impacts

    All relevant workssites

    MTR Corporation/Main Contractor

    Noise ControlOrdinance

    Implemented

    S.7.9.2.4 Acoustic fabric should be used for thefollowing PME where practicable: Compressor and Pneumatic Drilling Rig Piling, vibrating hammer Rock Drill Silent Piling System

    To minimise air-bornenoise impacts

    All relevant workssites

    MTR Corporation/Main Contractor

    Noise ControlOrdinance

    Implemented

    S.7.9.2.4 Noise enclosure/acoustic shed should beused for the following PME wherepracticable and will generally be fullyenclosed depending on the design, materialschosen, and dimension of the PME: Air Compressor Rock Crushing Equipment

    To minimise air-bornenoise impacts

    All relevant workssites

    MTR Corporation/Main Contractor

    Noise ControlOrdinance

    Implemented

    S.7.9.2.4 Silencer should be used for the ventilationfans.

    To minimise air-bornenoise impacts

    All relevant workssites

    MTR Corporation/Main Contractor

    Noise ControlOrdinance

    Implemented

    S.7.9.2.6 Use of temporary hoardings along the worksboundary.

    To minimise air-bornenoise impacts

    All relevant workssites

    MTR Corporation/Main Contractor

    Noise ControlOrdinance

    Implemented

  • Kwun Tong Line ExtensionConsultancy Agreement No. NEX/2207Environmental Impact Assessment (EIA) Study for KTEEM&A Manual

    June 2012 Page 9

    ImplementationStages

    EIAReference

    EM&AManualReference

    Environmental Protection Measures Objectives of Measuresand Main Concern toAddress

    Location ImplementationAgent

    RelevantStandard orRequirement D C O

    MaintenanceAgent Implementation

    status

    S.7.9.2.2 Noise enclosures should be installed for themuckout points in WS1 (Gascoigne RoadRest Garden), WS7a1 (WAB at Club deRecreio) and WS26a (Fat Kwong StreetPlayground)

    To comply with thecriteria of Noise ControlOrdinance.

    All muckoutpoints at WS1,WS7a1 andWS26a

    MTR Corporation/Main Contractor

    Noise ControlOrdinance

    Implemented

    S.7.9.2.3 Noise enclosures should be installed for allrock crushing equipment.

    To comply with thecriteria of Noise ControlOrdinance.

    All rock crushingequipment

    MTR Corporation/Main Contractor

    Noise ControlOrdinance

    To beimplemented asper constructionprogramme

    S.7.10.1.2 The maximum permissible sound powerlevels (max SWLs) for the fixed plant shouldbe complied with during the selection ofequipment and mitigation measures.

    To comply with thecriteria of Noise ControlOrdinance.

    All relevantlocation of fixedplant

    MTR Corporation/Detailed DesignConsultant

    Noise ControlOrdinance

    To beimplemented asper constructionprogramme

    S.7.10.2.1 The detailed design for all fixed plant shouldincorporate the following good practicewhere practicable:

    Louvers should be orientated away fromadjacent NSRs whenever practicable;

    Adequate direct noise mitigationmeasures including silencers, acousticlouvers or acoustic enclosures should beadopted where necessary; and

    Quieter plant should be chosen as far aspractical.

    To comply with thecriteria of Noise ControlOrdinance.

    At outlets of fixedplant includingventilationbuilding,ventilation shafts,plant room forchiller plant andcooling towers,etc

    MTR Corporation/Detailed DesignConsultant

    Noise ControlOrdinance

    To beimplemented asper constructionprogramme

    Ground-borne NoiseS.8.7.1.2 MTR will further review the proposed

    mitigation measures for operationalground-borne noise during the constructionstage after the tunnel boring.

    To comply with thecriteria of Noise ControlOrdinance.

    At suitablelocation

    MTR Corporation/Main Contractor

    - To beimplemented asper constructionprogramme

    S.8.7.1.3 Commissioning test is recommended toensure compliance of the operationalground-borne noise levels

    To comply with thecriteria of Noise ControlOrdinance.

    Designatedlocations

    MTR Corporation/Main Contractor

    Noise ControlOrdinance

    To beimplemented asper constructionprogramme

    Water QualityS.9.7.6 Construction site run-off and general

    construction activities: The mitigation measures as outlined in

    the ProPECC PN 1/94 Construction SiteDrainage should be adopted where

    To control water qualityimpact from constructionsite runoff and generalconstruction activities

    All works sites MTR Corporation/Main Contractor

    EIAO-TM,Water PollutionControlOrdinance,TM-DSS

    Implemented

  • Kwun Tong Line ExtensionConsultancy Agreement No. NEX/2207Environmental Impact Assessment (EIA) Study for KTEEM&A Manual

    June 2012 Page 10

    ImplementationStages

    EIAReference

    EM&AManualReference

    Environmental Protection Measures Objectives of Measuresand Main Concern toAddress

    Location ImplementationAgent

    RelevantStandard orRequirement D C O

    MaintenanceAgent Implementation

    status

    applicable.S.9.7.6 In case seepage of uncontaminated

    groundwater occurs, groundwater should bepumped out from the works areas anddischarged into the storm system via siltremoval facilities. Uncontaminatedgroundwater from dewatering process shouldalso be discharged into the storm system viasilt traps.

    To control water qualityimpact from groundwater

    All works sites MTR Corporation/Main Contractor

    EIAO-TM,Water PollutionControlOrdinance

    To beimplemented asper constructionprogramme

    S.9.7.6 At the barging point, mitigation measures forcontrol of water quality impact from surfacerun-off should be applied and the followinggood site practices should also be adopted: All vessels should be sized so that

    adequate clearance is maintainedbetween vessels and the seabed in alltide conditions, to ensure that undueturbidity is not generated by turbulencefrom vessel movement or propellerwash.

    All hopper barges should be fitted withtight fitting seals to their bottomopenings to prevent leakage of material.

    Construction activities should not causefoam, oil, grease, scum, litter or otherobjectionable matter to be present on thewater within the site.

    Loading of barges and hoppers shouldbe controlled to prevent splashing ofmaterial into the surrounding water.Barges or hoppers should not be filled toa level that will cause the overflow ofmaterials or polluted water duringloading or transportation.

    To control water qualityimpact from barging point

    Barging point MTR Corporation/Main Contractor

    EIAO-TM,Water PollutionControlOrdinance

    To beimplemented asper constructionprogramme

    S.9.7.6 For effluent discharge, there is a need toapply to EPD for a discharge licence fordischarge of effluent from the constructionsite under the WPCO. The discharge qualityshould meet the requirements specified inthe discharge licence. Minimum distances of100m should be maintained between thedischarge points of construction site effluentand the existing seawater intakes. If

    To control water qualityimpact from effluentdischarge fromconstruction site

    All works sites MTR Corporation/Main Contractor

    EIAO-TM,Water PollutionControlOrdinance

    Implemented

  • Kwun Tong Line ExtensionConsultancy Agreement No. NEX/2207Environmental Impact Assessment (EIA) Study for KTEEM&A Manual

    June 2012 Page 11

    ImplementationStages

    EIAReference

    EM&AManualReference

    Environmental Protection Measures Objectives of Measuresand Main Concern toAddress

    Location ImplementationAgent

    RelevantStandard orRequirement D C O

    MaintenanceAgent Implementation

    status

    monitoring of the treated effluent qualityfrom the works areas is required during theconstruction phase of the Project, themonitoring should be carried out inaccordance with the WPCO license which isunder the ambit of Regional Office of theEPD.

    S.9.7.6 To prevent the accidental spillage ofchemicals, the Contractor should register asa chemical waste producer if chemicalwastes would be produced from theconstruction activities. The Waste DisposalOrdinance (Cap 354) and its subsidiaryregulations in particular the Waste Disposal(Chemical Waste) (General) Regulationshould be observed and complied with forcontrol of chemical wastes.

    To control water qualityimpact from accidentalchemical spillage

    All works sites MTR Corporation/Main Contractor

    EIAO-TM,Water PollutionControlOrdinance,Waste DisposalOrdinance

    Implemented

    S.9.7.6 Any service shop and maintenance facilitiesshould be located on hard standings within abunded area, and sumps and oil interceptorsshould be provided. Maintenance of vehiclesand equipment involving activities withpotential for leakage and spillage shouldonly be undertaken within the areasappropriately equipped to control thesedischarges.

    To control water qualityimpact from accidentalchemical spillage

    All works sites MTR Corporation/Main Contractor

    EIAO-TM,Water PollutionControlOrdinance,Waste DisposalOrdinance

    Implemented

    S.9.7.6 Disposal of chemical wastes should becarried out in compliance with the WasteDisposal Ordinance. The Code of Practiceon the Packaging, Labelling and Storage ofChemical Wastes published under the WasteDisposal Ordinance details the requirementsto deal with chemical wastes. Generalrequirements are given as follows: Suitable containers should be used to

    hold the chemical wastes to avoidleakage or spillage during storage,handling and transport.

    Chemical waste containers should besuitably labelled, to notify and warn thepersonnel who are handling the wastes,to avoid accidents.

    Storage area should be selected at a safe

    To control water qualityimpact from accidentalchemical spillage

    All works sites MTR Corporation/Main Contractor

    EIAO-TM,Water PollutionControlOrdinance,Waste DisposalOrdinance

    Implemented

  • Kwun Tong Line ExtensionConsultancy Agreement No. NEX/2207Environmental Impact Assessment (EIA) Study for KTEEM&A Manual

    June 2012 Page 12

    ImplementationStages

    EIAReference

    EM&AManualReference

    Environmental Protection Measures Objectives of Measuresand Main Concern toAddress

    Location ImplementationAgent

    RelevantStandard orRequirement D C O

    MaintenanceAgent Implementation

    status

    location on site and adequate spaceshould be allocated to the storage area.

    S.9.7.6 Regarding the hydrogeological impacts inthe construction of cut-and-cover tunnelsand associated excavations for the WAB /ventilation building, the following measuresshould be in place in order to mitigate anydrawdown effects to the groundwater tableduring the operation of the temporarydewatering works: Toe grouting should be applied beneath

    the toe level of the temporary/permanentcofferdam walls as necessary tolengthen the effective flow path ofgroundwater from outside and thuscontrol the amount of water inflow tothe excavation.

    Recharge wells should be installed asnecessary outside the excavation areas.Water pumped from the excavationareas should be recharged back into theground.

    To control groundwaterhydrogeological impactand groundwaterdrawdown

    All works sites MTR Corporation/Main Contractor

    EIAO-TM,Water PollutionControlOrdinance

    To beimplemented asper constructionprogramme

    S.9.8.6 Measures for the tunnel run-off and drainageinclude: Track drainage channels discharge

    should pass through oil/gritinterceptors/chambers to remove oil,grease and sediment before beingpumped to the foul sewer/holding tankfor further disposal.

    The silt traps and oil interceptors shouldbe cleaned and maintained regularly.

    Oily contents of the oil interceptorsshould be transferred to an appropriatedisposal facility, or to be collected forreuse, if possible.

    To control runoff from railtrack

    Tunnels and railtracks

    MTR Corporation/Detailed DesignConsultant

    Water PollutionControlOrdinance

    To beimplemented asper constructionprogramme

    S.9.8.6 Measures for the control of sewage effluentsinclude: Connection of domestic sewage

    generated from the KTE project shouldbe diverted to the foul sewer whereverpossible. If public sewer system is not

    To control water qualityimpact from sewageeffluent discharge from theventilation building andStations

    Ventilationbuilding andStations

    MTR Corporation/Detailed DesignConsultant

    EIAO-TM,Water PollutionControlOrdinance,TM-DSS,ProPECC PN

    To beimplemented asper constructionprogramme

  • Kwun Tong Line ExtensionConsultancy Agreement No. NEX/2207Environmental Impact Assessment (EIA) Study for KTEEM&A Manual

    June 2012 Page 13

    ImplementationStages

    EIAReference

    EM&AManualReference

    Environmental Protection Measures Objectives of Measuresand Main Concern toAddress

    Location ImplementationAgent

    RelevantStandard orRequirement D C O

    MaintenanceAgent Implementation

    status

    available, sewage tankering awayservices or on-site sewage treatmentfacilities should be provided to preventdirect discharge of sewage to the nearbystorm system and all the dischargeshould comply with the requirementsstipulated in the TM-DSS.

    For handling, treatment and disposal ofother operation stage effluent, thepractices outlined in ProPECC PN 5/93should be adopted where applicable.

    5/93

    Waste Management ImplicationsS.10.5.6.1 Recommendations for good site practices:

    Prepare a Waste Management Planapproved by the Engineer/SupervisingOfficer of the Project based on currentpractices on construction sites.

    Training of site personnel in, sitecleanliness, proper waste managementand chemical handling procedures.

    Provision of sufficient waste disposalpoints and regular collection of waste.

    Appropriate measures to minimisewindblown litter and dust duringtransportation of waste by eithercovering trucks or by transportingwastes in enclosed containers.

    Regular cleaning and maintenanceprogramme for drainage systems, sumpsand oil interceptors.

    Separation of chemical wastes forspecial handling and appropriatetreatment.

    To implement good sitepractice for handling,sorting reuse and recyclingof C&D materials

    All works sites Main Contractor Waste DisposalOrdinance,Land(MiscellaneousProvisions)Ordinance,ETWB TC(W)No 31/2004

    Implemented

    S.10.5.6.1 Recommendations for waste reductionmeasures: Sorting of demolition debris and

    excavated materials from demolitionworks to recover reusable/ recyclableportions (i.e. soil, broken concrete,metal etc.).

    Segregation and storage of differenttypes of waste in different containers,skips or stockpiles to enhance reuse or

    To implement on-sitesorting facilitating reuseand recycling of materialsas well as proper disposalof waste

    All works sites Main Contractor Waste DisposalOrdinance,Land(MiscellaneousProvisions)Ordinance

    Implemented

  • Kwun Tong Line ExtensionConsultancy Agreement No. NEX/2207Environmental Impact Assessment (EIA) Study for KTEEM&A Manual

    June 2012 Page 14

    ImplementationStages

    EIAReference

    EM&AManualReference

    Environmental Protection Measures Objectives of Measuresand Main Concern toAddress

    Location ImplementationAgent

    RelevantStandard orRequirement D C O

    MaintenanceAgent Implementation

    status

    recycling of materials and their properdisposal.

    Encourage collection of aluminium cansby providing separate labelled bins toenable this waste to be segregated fromother general refuse generated by theworkforce.

    Proper storage and site practices tominimize the potential for damage orcontamination of construction materials.

    Plan and stock construction materialscarefully to minimize amount of wastegenerated and avoid unnecessarygeneration of waste.

    Training should be provided to workersabout the concepts of site cleanlinessand appropriate waste managementprocedures, including waste reduction,reuse and recycle.

    S.10.5.6.1 The Contractor should prepare andimplement a Waste Management Plan as apart of the Environmental Management Planin accordance with ETWB TCW No 19/2005which describes the arrangements foravoidance, reuse, recovery, recycling,storage, collection, treatment and disposal ofdifferent categories of waste to be generatedfrom the construction activities.

    To keep trace of thegeneration, minimization,reuse and disposal of C&Dmaterials in the Project

    All works sites Main Contractor ETWB TCWNo 19/2005

    Implemented

    S.10.5.6.1 Storage of materials on-site may induceadverse environmental impacts if notproperly managed, recommendations tominimise the impacts include: Waste, such as soil, should be handled

    and stored well to ensure securecontainment, thus minimising thepotential of pollution.

    Maintain and clean storage areasroutinely.

    Stockpiling area should be providedwith covers and water spraying systemto prevent materials from wind-blown orbeing washed away.

    Different locations should be designated

    To minimise potentialimpacts of waste storageand enhance reusablevolume

    All works sites Main Contractor - Implemented

  • Kwun Tong Line ExtensionConsultancy Agreement No. NEX/2207Environmental Impact Assessment (EIA) Study for KTEEM&A Manual

    June 2012 Page 15

    ImplementationStages

    EIAReference

    EM&AManualReference

    Environmental Protection Measures Objectives of Measuresand Main Concern toAddress

    Location ImplementationAgent

    RelevantStandard orRequirement D C O

    MaintenanceAgent Implementation

    status

    to stockpile each material to enhancereuse.

    S.10.5.6.1 Waste hauliers must hold a valid permit forthe collection of waste as stipulated in theirpermits. Removal of waste should be done ina timely manner.

    To collect and removewaste generated

    All works sites Main Contractor - Implemented

    S.10.5.6.1 Implementation of trip-ticket system tomonitor waste disposal and controlfly-tipping. Set up warning signs at vehicular access

    points reminding drivers of designateddisposal sites and penalties of anoffence.

    Installation of close-circuited televisionat access points of vehicles to monitorand prevent illegal dumping.

    To monitor disposal ofwaste and controlfly-tipping

    All works sites Main Contractor ETWB TC(W)No 31/2004

    Implemented

    S.10.5.6.1 Wheel washing facilities should be providedbefore the trucks leave the works area.

    To minimise dust impact All works sites Main Contractor - Implemented

    S.10.5.6.1 The Contractor should ensure the on-siteseparation from inert portion. The wastedelivered to landfill should not contain anyfree water or have water content more than70% by weight. The haulier must ensuresuitable amount of waste would be loaded ondifferent types of trucks used. A one-weeknotice should be given to EPD withinformation on Contractor’s name andrespective contact details.

    To meet the requirementfor disposal at landfill

    All works sites Main Contractor - Implemented

    S.10.5.6.1 If chemical wastes are produced at theconstruction site, the Contractor would berequired to register with the EPD as achemical waste producer and to follow theguidelines stated in the Code of Practice onthe Packaging, Labelling and Storage ofChemical Wastes. Containers used forstorage of chemical waste should : Be compatible with the chemical wastes

    being stored, maintained in goodcondition and securely sealed.

    Have a capacity of less than 450 litresunless the specifications have beenapproved by EPD; and

    To properly store thechemical waste withinworks sites and worksareas

    All works sites Main Contractor Code ofPractice on thePackaging,Labelling andStorage ofChemicalWastes

    Implemented

  • Kwun Tong Line ExtensionConsultancy Agreement No. NEX/2207Environmental Impact Assessment (EIA) Study for KTEEM&A Manual

    June 2012 Page 16

    ImplementationStages

    EIAReference

    EM&AManualReference

    Environmental Protection Measures Objectives of Measuresand Main Concern toAddress

    Location ImplementationAgent

    RelevantStandard orRequirement D C O

    MaintenanceAgent Implementation

    status

    Display a label in English and Chinesein accordance with instructionsprescribed in Schedule 2 of the WasteDisposal (Chemical Waste) (General)Regulation.

    S.10.5.6.1 The chemical storage areas should: Be clearly labelled to indicate

    corresponding chemical characteristicsof the chemical waste and used forstorage of chemical waste only.

    Be enclosed on at least 3 sides. Have an impermeable floor and

    bunding, of capacity to accommodate110% of the volume of the largestcontainer or 20% by volume of thechemical waste stored in that area,whichever is the greatest.

    Have adequate ventilation. Be covered to prevent rainfall from

    entering. Be properly arranged so that

    incompatible materials are adequatelyseparated.

    To prepare appropriatestorage areas for chemicalwaste at works areas

    All works sites Main Contractor Code ofPractice on thePackaging,Labelling andStorage ofChemicalWastes

    Implemented

    S.10.5.6.1 Lubricants, waste oils and other chemicalwastes would be generated during themaintenance of vehicles and mechanicalequipments. Used lubricants should becollected and stored in individual containerswhich are fully labelled in English andChinese and stored in a designated secureplace.

    To clearly label thechemical waste at worksareas

    All works sites Main Contractor Code ofPractice on thePackaging,Labelling andStorage ofChemicalWastes

    Implemented

    S.10.5.6.1 A trip-ticket system should be operated inaccordance with the Waste Disposal(Chemical Waste) (General) Regulation tomonitor all movements of chemical waste.The Contractor should employ a licensedcollector to transport and dispose of thechemical wastes, to either the approvedCWTC at Tsing Yi, or another licensedfacility, in accordance with the WasteDisposal (Chemical Waste) (General)Regulation.

    To monitor the generation,reuse and disposal ofchemical waste

    All works sites Main Contractor Waste Disposal(ChemicalWaste)(General)Regulation

    Implemented

  • Kwun Tong Line ExtensionConsultancy Agreement No. NEX/2207Environmental Impact Assessment (EIA) Study for KTEEM&A Manual

    June 2012 Page 17

    ImplementationStages

    EIAReference

    EM&AManualReference

    Environmental Protection Measures Objectives of Measuresand Main Concern toAddress

    Location ImplementationAgent

    RelevantStandard orRequirement D C O

    MaintenanceAgent Implementation

    status

    S.10.5.6.1 General refuse should be stored in enclosedbins or compaction units separate from C&Dmaterials and chemical waste. A reputablewaste collector should be employed by thecontractor to remove general refuse from thesite, separately from C&D materials andchemical wastes.

    To properly store andseparate from other C&Dmaterials for subsequentcollection and disposal

    All works sites Main Contractor - Implemented

    S.10.5.6.1 The recyclable component of general refuse,such as aluminium cans, paper and cleansedplastic containers should be separated fromother waste. Provision and collection ofrecycling bins for different types ofrecyclable waste should be set up by theContractor. The Contractor should also beresponsible for arranging recyclingcompanies to collect these materials.

    To facilitate recycling ofrecyclable portions ofrefuse

    All works sites Main Contractor - Implemented

    S.10.5.6.1 The Contractor should carry out a trainingprogramme for workers in avoiding,reducing, reusing and recycling of materialsgeneration. Posters and leaflets advising onthe use of the bins should also be provided inthe sites as reminders.

    To raise workers’awareness on recyclingissue

    All works sites Main Contractor - Implemented

    S.10.6.4 Chemical waste during the operation of theKTE project: The requirements stipulated in the Code

    of Practice on the Packaging, Labellingand Storage of Chemical Wastes shouldbe followed in handling of chemicalwaste as in construction phase.

    A trip-ticket system should be operatedin accordance with the Waste Disposal(Chemical Waste) (General) Regulationto monitor all movements of chemicalwastes which would be collected by alicensed collector to a licensed facilityfor final treatment and disposal.

    The recommendations proposed for themitigation of impacts from chemicalwaste in construction phase should alsobe followed.

    To avoid environmentalimpacts in handling,storage and disposal ofchemical waste

    Ventilationbuilding andStations

    MTR Corporation Code ofPractice on thePackaging,Labelling andStorage ofChemicalWastes,Waste Disposal(ChemicalWaste)(General)Regulation

    Implemented

    S.10.6.4 General refuse during the operation of the To separate the generalrefuse from other waste

    Ventilationbuilding and

    MTR Corporation - Implemented

  • Kwun Tong Line ExtensionConsultancy Agreement No. NEX/2207Environmental Impact Assessment (EIA) Study for KTEEM&A Manual

    June 2012 Page 18

    ImplementationStages

    EIAReference

    EM&AManualReference

    Environmental Protection Measures Objectives of Measuresand Main Concern toAddress

    Location ImplementationAgent

    RelevantStandard orRequirement D C O

    MaintenanceAgent Implementation

    status

    KTE project: Provide recycling bins at designated

    areas for proper recycling of papers,aluminium cans and plastics bottles.

    Separation from other waste types andcollected by licensed collectors at dailybasis to minimize the potential impactsfrom odour and vermin.

    types and proper disposalof the refuse

    Stations

    S.10.6.4 Industrial waste during the operation of theKTE project: Separation of reusable components like

    steel before collection by licensedcollector

    To recycle useful materialsfrom industrial waste andproper disposal

    Ventilationbuilding andStations

    MTR Corporation - Implemented

    Hazard to LifeS.12.12.1, S12.12.6

    Section12.10.2.1,Section12.10.2.4

    Improved truck design to reduce the amountof combustibles in, front exhaust sparkarrester, 1 x 9 kg water based and 1 x 9 kgdry chemical powder fire extinguishers. Thisshould be combined with monthly vehicleinspec